2015 Mainstreet Improvement UpdateMemorandum Public Works Department
To: Honorable Mayor and Members of the City Council
From: Nate Stanley, City Engineer
Copy: Mike Mornson, City Manager
Date: June 5, 2014
Subiect: 2015 Mainstreet Improvement Update
In the summer of 2015 a rehabilitation project is scheduled for Mainstreet. Initially, the project scope
included only mill and overlay of the street, curb repair, and pedestrian improvements. The scope has
expanded as the project has developed, and now includes utility and drainage repairs, lighting
improvements, replacement of streetscape amenities, and aesthetic corridor elements. It is
anticipated that due to the expanded scope the complete reconstruction of some blocks will be
necessary, however full reconstruction along the entire length of Mainstreet is not proposed. This
project is intended to essentially provide a facelift, while maintaining the corridor's classic character.
A public informational meeting was held on May 6. Property owners, building occupants, and
residents along Mainstreet were invited, eleven people attended the meeting. Those in attendance
were generally supportive of the project.
At the public meeting, a presentation of the proposed improvements was given, schedule was
discussed, questions were answered, and comments were solicited. There were several items
presented at the meeting as options. Staff specifically sought input regarding these options for use in
refining project scope and details. A project questionnaire was mailed out to Mainstreet stakeholders
with the meeting invitation. The questionnaire is designed to collect input which will be useful to
project scoping, to date I have received eight completed questionnaires.
Since the meeting, Bolton & Menk have focused the project scope and begun preliminary plans
based on public input and City staff direction. At the work session, City and Bolton & Menk staff will
present an update on the proposed improvements, estimated cost, schedule, and next steps.
City of Hopkins 2015 Mainstreet
Improvements
2015 Mainstreet Improvements
City Council Project Update
June 10, 2014 Work Session
BOLTON & MHIV K, IIVG
2015 Mainstreet Improvements
44;V
ue•. +'` `�Y+ �."4�, 1�R.> f — •Y► - tk`�i :mac
x t tea- �'" ��%1 {+ °' 'w t, \.• ,� . �• �� r i' �S: .7 iy(�`
-tea �"" t.`!*''•' a.�{ : a- I Elu,a •(' �, _`_ .Vr
-iiia! lry,'�n,f - o• '� r ._, I•"r+ � 7- _ �' � i
4MBOLTON & Ni E=— N K, INC
May 6, 2014 Open House
6/5/2014
City of Hopkins 2015 Mainstreet
Improvements
Watermain & Service Replacements
■ 10" Main from 201h Ave to 11th Ave (1991)
■ 8" Main from 5th Ave to 11th Ave (19xx)
—To be replaced with 10" Main
— Services present and to be replaced 8th Ave to 111h Ave
— Special assessments for cost of water service
replacement (429 process for this portion of work)
BOLTON 8. MEIV K, INC
Street Construction
■ Scope of street construction tied to watermain
and service replacement scope
BO LTOfV CNK, INC
Cnnsc'
6/5/2014
May 6, 2014 Open House 2
City of Hopkins 2015 Mainstreet
Improvements
6/5/2014
201H AVE. TO 11TH AVE. PAVEMENT IMPROVEMENTS 0:
-r.��•:s.cuw.cm�as ivvuxw:=sm
um�s+cxcarz�sas� � var a.�.m.�rnv�o«:..
PROPOSED TYRCAL SECTION - MAINSTREET
MTN AVENUE TO 11TH AVENUE
STA 3-W TO 33+32
E�OI_T%71V 8. ME=NK, iNC
11TH AVE. TO 8TH AVE. PAVEMENT IMPROVEMENTS
PROPOSED TYPICAL SECTION - MAINSTREET
11TH AVENUE TO 8TH AVENUE
STA 33+36 TO STA 62w5
ENOL-OTV 8- NAE—=r-,JK , INC
May 6, 2014 Open House 3
City of Hopkins 2015 Mainstreet
Improvements
8TH AVE. TO 5TH AVE. PAVEMENT IMPROVEMENTS
i.�tvttsw�.xm•.tncxv lvwuax:llzxul'
t x toot lnsxl �
z 'ro[vzzsxoww[eei xs[Ivmrtt:oel lzxol
ax i ss 1
z rlF mlzs NOx x�r urt5[
1--1 (-1
L.5 ° WMMOt xR[ txltbx
0
Ms uu L WFt [otm.��
�� wutEc mxnu[txKM
12.5 wExutW COMIF IsrwFxzxoc�liwol t �'1
Fxunw xccls...,rt se�lfssn xxx�cut*F0.
PROPOSED TYPICAL SECTION - MAINSTREET
8TH AVENUE TO 5TH AVENUE
STA 42+95 70 STA 53+70
I
BOLTON Sx MEN LNG
..I.Inp �npineers & Survaymt
2015 MAINSTREET PAVEMENT IMPROVEMENTS 4M
IAILL 8 OVERLAY (RESURFACING OF UPPER 2.51
• FULL DEPTH RECONSTRUCTION FOR INATERMAIN IMPROVEMENTS
EE30 L_TON 8. M E_= N I< , I N C
6/5/2014
May 6, 2014 Open House 4
City of Hopkins 2015 Mainstreet
Improvements
Drainage Improvements 0:
■ Add storm sewer 1311 to 1511
■ Replace 25 defective catch basins
■ Add catch basins & replace curb where needed
EEx::> L--rC>--4 & %4 r= rV K , Irv` --
Treer-- �--
Tree Inventory & Assessment
7-
13TH AVE TO 9TH AVE i -A
, E To 5TH AVE
MAINSTREET TREE ASSESSMENT
EB(DL--r-CDf1J S. MENK, INC
6/5/2014 r--.jC-
6/5/2014
May 6, 2014 Open House 5
City of Hopkins 2015 Mainstreet
Improvements
6/5/2014
LED vs. HPS Lighting
4M
Mainstreet Estimated Cost Analysis (HPS vs LED)
HPS (Existing)
LED
20 Year Energy Cost:
$79,843
$33,555
Replace HPS Fixtures with LED Fixtures:
$0
$112,500
20 Year Maintenance Costs:
$69,400
$0
Xcel Energy Rebate $400 kW over 20 years)$0
$0
$9 058
Total 20 Year Analysis Cost:
$149,243
$136,997
Estimated Savings Over 20 Years with LED Retrofit:
$12,246
■ Savings due to decreased energy and
maintenance costs
■ Return on investment estimated in year 18
BOLTON a MP=IV K IIVG
onsni'.iey'noweis A Sire"
May 6, 2014 Open House 6
City of Hopkins 2015 Mainstreet
Improvements
LED vs. HPS Lighting AM
■ Other benefits of LED lighting include:
— "Green" technology
— Better visibility at same light intensity
— LED lights provide more consistent lighting
— Consistency with Shady Oak Road project
HOL_TOfV & MEfV K INC I
Traffic Signal Upgrades
Push buttons, countdown timers, &
audible messages
rvC-
6/5/2014
May 6, 2014 Open House 7
City of Hopkins 2015 Mainstreet
Improvements
6/5/2014
Paver Replacements 4M
■ Proposed at corners with new pavers
■ Proposed at doorways with concrete sidewalk
• -1
y C
Paver Replacements
:Y T'
-ON CEPT A CONCEPT B CONCEPT C
r
CONCEPT CI CONCEPT DI
INTERSECTION PAVING
BOLTON &MINK, INC
Lon
May 6, 2014 Open House 8
City of Hopkins 2015 Mainstreet
Improvements
Streetscape Amenities
//I
• r
SITE AMENITIES
BOLTOfV Rn/I BIV K, INC
Signage Improvements
i
r��16-10
\A/evrimnimr. rsir.mAnr
BOLTON 8. n/1 Et,1 4G. Jr--- �
May
n; -
May 6, 2014 Open House
6/5/2014
A
City of Hopkins 2015 Mainstreet
Improvements
Signage Improvements
f;
I
4M
POLE MOUNTED PARKING SIGN
• POLE MOUNTED WAYFINDING SIGN
INFORMATIONALKIOSK
ELECTRONIC MESSAGE BOARD
BIKE RACK
SIGNAGE LOCATION MAP
BOLTON 8. MEIV K, IIVC
Estimated Costs & Funding
■ Estimated Project Cost = $4,000,000
— $660,000 Federal HSIP Grant
90% of signal and pedestrian ramp improvements
— $1,630,000 Municipal State Aid Construction
— $1,400,000 GO Bonds
— $250,000 Water Fund
— Special Assessments from Water Services
May 6, 2014 Open House
BO LTOI-,I P— ME=1V K, INC
cels D i� :=sora
6/5/2014
10
City of Hopkins 2015 Mainstreet
Improvements
Project Schedule 4M
■ June, 2014
— Coordination with private utility owners
— Preliminary plans & Project Memorandum
— Initiate feasibility report for water services
— Neighborhood meeting on water service assessments
• July, 2014
— Submit plans for State Aid Review
— City Council work Session to discuss plans & phasing
— Present feasibility report to Council
— 2nd BOI_T�" & MEN K , INC
Public Open House Consulrn :, Pn:.;
Project Schedule 4M
■ August — September, 2014
— Receive approvals from State Aid Office
— City Council approval of final plans
— Initiate bidding phase
■ October —December, 2014
— Open Bids, submit for State/Federal Approvals
— Final Assessment Hearing
—Award Contract
■ July — October, 2015: Construction