2015 Mainstreet Improvement UpdateMemorandum Public Works Department To: Honorable Mayor and Members of the City Council From: Nate Stanley, City Engineer Copy: Mike Mornson, City Manager Date: June 5, 2014 Subiect: 2015 Mainstreet Improvement Update In the summer of 2015 a rehabilitation project is scheduled for Mainstreet. Initially, the project scope included only mill and overlay of the street, curb repair, and pedestrian improvements. The scope has expanded as the project has developed, and now includes utility and drainage repairs, lighting improvements, replacement of streetscape amenities, and aesthetic corridor elements. It is anticipated that due to the expanded scope the complete reconstruction of some blocks will be necessary, however full reconstruction along the entire length of Mainstreet is not proposed. This project is intended to essentially provide a facelift, while maintaining the corridor's classic character. A public informational meeting was held on May 6. Property owners, building occupants, and residents along Mainstreet were invited, eleven people attended the meeting. Those in attendance were generally supportive of the project. At the public meeting, a presentation of the proposed improvements was given, schedule was discussed, questions were answered, and comments were solicited. There were several items presented at the meeting as options. Staff specifically sought input regarding these options for use in refining project scope and details. A project questionnaire was mailed out to Mainstreet stakeholders with the meeting invitation. The questionnaire is designed to collect input which will be useful to project scoping, to date I have received eight completed questionnaires. Since the meeting, Bolton & Menk have focused the project scope and begun preliminary plans based on public input and City staff direction. At the work session, City and Bolton & Menk staff will present an update on the proposed improvements, estimated cost, schedule, and next steps. City of Hopkins 2015 Mainstreet Improvements 2015 Mainstreet Improvements City Council Project Update June 10, 2014 Work Session BOLTON & MHIV K, IIVG 2015 Mainstreet Improvements 44;V ue•. +'` `�Y+ �."4�, 1�R.> f — •Y► - tk`�i :mac x t tea- �'" ��%1 {+ °' 'w t, \.• ,� . �• �� r i' �S: .7 iy(�` -tea �"" t.`!*''•' a.�{ : a- I Elu,a •(' �, _`_ .Vr -iiia! lry,'�n,f - o• '� r ._, I•"r+ � 7- _ �' � i 4MBOLTON & Ni E=— N K, INC May 6, 2014 Open House 6/5/2014 City of Hopkins 2015 Mainstreet Improvements Watermain & Service Replacements ■ 10" Main from 201h Ave to 11th Ave (1991) ■ 8" Main from 5th Ave to 11th Ave (19xx) —To be replaced with 10" Main — Services present and to be replaced 8th Ave to 111h Ave — Special assessments for cost of water service replacement (429 process for this portion of work) BOLTON 8. MEIV K, INC Street Construction ■ Scope of street construction tied to watermain and service replacement scope BO LTOfV CNK, INC Cnnsc' 6/5/2014 May 6, 2014 Open House 2 City of Hopkins 2015 Mainstreet Improvements 6/5/2014 201H AVE. TO 11TH AVE. PAVEMENT IMPROVEMENTS 0: -r.��•:s.cuw.cm�as ivvuxw:=sm um�s+cxcarz�sas� � var a.�.m.�rnv�o«:.. PROPOSED TYRCAL SECTION - MAINSTREET MTN AVENUE TO 11TH AVENUE STA 3-W TO 33+32 E�OI_T%71V 8. ME=NK, iNC 11TH AVE. TO 8TH AVE. PAVEMENT IMPROVEMENTS PROPOSED TYPICAL SECTION - MAINSTREET 11TH AVENUE TO 8TH AVENUE STA 33+36 TO STA 62w5 ENOL-OTV 8- NAE—=r-,JK , INC May 6, 2014 Open House 3 City of Hopkins 2015 Mainstreet Improvements 8TH AVE. TO 5TH AVE. PAVEMENT IMPROVEMENTS i.�tvttsw�.xm•.tncxv lvwuax:llzxul' t x toot lnsxl � z 'ro[vzzsxoww[eei xs[Ivmrtt:oel lzxol ax i ss 1 z rlF mlzs NOx x�r urt5[ 1--1 (-1 L.5 ° WMMOt xR[ txltbx 0 Ms uu L WFt [otm.�� �� wutEc mxnu[txKM 12.5 wExutW COMIF IsrwFxzxoc�liwol t �'1 Fxunw xccls...,rt se�lfssn xxx�cut*F0. PROPOSED TYPICAL SECTION - MAINSTREET 8TH AVENUE TO 5TH AVENUE STA 42+95 70 STA 53+70 I BOLTON Sx MEN LNG ..I.Inp �npineers & Survaymt 2015 MAINSTREET PAVEMENT IMPROVEMENTS 4M IAILL 8 OVERLAY (RESURFACING OF UPPER 2.51 • FULL DEPTH RECONSTRUCTION FOR INATERMAIN IMPROVEMENTS EE30 L_TON 8. M E_= N I< , I N C 6/5/2014 May 6, 2014 Open House 4 City of Hopkins 2015 Mainstreet Improvements Drainage Improvements 0: ■ Add storm sewer 1311 to 1511 ■ Replace 25 defective catch basins ■ Add catch basins & replace curb where needed EEx::> L--rC>--4 & %4 r= rV K , Irv` -- Treer-- �-- Tree Inventory & Assessment 7- 13TH AVE TO 9TH AVE i -A , E To 5TH AVE MAINSTREET TREE ASSESSMENT EB(DL--r-CDf1J S. MENK, INC 6/5/2014 r--.jC- 6/5/2014 May 6, 2014 Open House 5 City of Hopkins 2015 Mainstreet Improvements 6/5/2014 LED vs. HPS Lighting 4M Mainstreet Estimated Cost Analysis (HPS vs LED) HPS (Existing) LED 20 Year Energy Cost: $79,843 $33,555 Replace HPS Fixtures with LED Fixtures: $0 $112,500 20 Year Maintenance Costs: $69,400 $0 Xcel Energy Rebate $400 kW over 20 years)$0 $0 $9 058 Total 20 Year Analysis Cost: $149,243 $136,997 Estimated Savings Over 20 Years with LED Retrofit: $12,246 ■ Savings due to decreased energy and maintenance costs ■ Return on investment estimated in year 18 BOLTON a MP=IV K IIVG onsni'.iey'noweis A Sire" May 6, 2014 Open House 6 City of Hopkins 2015 Mainstreet Improvements LED vs. HPS Lighting AM ■ Other benefits of LED lighting include: — "Green" technology — Better visibility at same light intensity — LED lights provide more consistent lighting — Consistency with Shady Oak Road project HOL_TOfV & MEfV K INC I Traffic Signal Upgrades Push buttons, countdown timers, & audible messages rvC- 6/5/2014 May 6, 2014 Open House 7 City of Hopkins 2015 Mainstreet Improvements 6/5/2014 Paver Replacements 4M ■ Proposed at corners with new pavers ■ Proposed at doorways with concrete sidewalk • -1 y C Paver Replacements :Y T' -ON CEPT A CONCEPT B CONCEPT C r CONCEPT CI CONCEPT DI INTERSECTION PAVING BOLTON &MINK, INC Lon May 6, 2014 Open House 8 City of Hopkins 2015 Mainstreet Improvements Streetscape Amenities //I • r SITE AMENITIES BOLTOfV Rn/I BIV K, INC Signage Improvements i r��16-10 \A/evrimnimr. rsir.mAnr BOLTON 8. n/1 Et,1 4G. Jr--- � May n; - May 6, 2014 Open House 6/5/2014 A City of Hopkins 2015 Mainstreet Improvements Signage Improvements f; I 4M POLE MOUNTED PARKING SIGN • POLE MOUNTED WAYFINDING SIGN INFORMATIONALKIOSK ELECTRONIC MESSAGE BOARD BIKE RACK SIGNAGE LOCATION MAP BOLTON 8. MEIV K, IIVC Estimated Costs & Funding ■ Estimated Project Cost = $4,000,000 — $660,000 Federal HSIP Grant 90% of signal and pedestrian ramp improvements — $1,630,000 Municipal State Aid Construction — $1,400,000 GO Bonds — $250,000 Water Fund — Special Assessments from Water Services May 6, 2014 Open House BO LTOI-,I P— ME=1V K, INC cels D i� :=sora 6/5/2014 10 City of Hopkins 2015 Mainstreet Improvements Project Schedule 4M ■ June, 2014 — Coordination with private utility owners — Preliminary plans & Project Memorandum — Initiate feasibility report for water services — Neighborhood meeting on water service assessments • July, 2014 — Submit plans for State Aid Review — City Council work Session to discuss plans & phasing — Present feasibility report to Council — 2nd BOI_T�" & MEN K , INC Public Open House Consulrn :, Pn:.; Project Schedule 4M ■ August — September, 2014 — Receive approvals from State Aid Office — City Council approval of final plans — Initiate bidding phase ■ October —December, 2014 — Open Bids, submit for State/Federal Approvals — Final Assessment Hearing —Award Contract ■ July — October, 2015: Construction BOLTON 8, NI EIV K , I IVC Consulting 6/5/2014 May 6, 2014 Open House 11