2015-2019 Capital Improvement Plan (CIP)CITY OF HOPKINS FINANCE DEPARTMENT MEMORANDUM Date: June 10, 2014 To: Mayor & City Council From: Christine Harkess, Finance Director Subject: 2015-20109 Capital Improvement Plan (C.I.P.) Attached is a proposed CIP which has undergone several staff revisions. At the work session we will review the 2015-2019 documents and incorporate any changes from the work session discussion. Included in this packet are the following — 1. Summary of changes in the 2015-2019 CIP 2. The cash flow statements by fund 3. Projects summarized by year for the years 2015-2019 Individual project sheets providing a description of the project, justification, and funding source are not included but can be provided if you are interested in reviewing them. Please let me know if you'd like to review the individual project sheets and I will email them to you. There are a total of 79 individual project sheets. All of the funds with the exception of the Capital Improvement Fund are balanced. Since there were a number of new items added in 2015 and 2016 I am coordinating with Ehlers who did our Financial Management Plan to see what our options are for bringing this fund back into balance. The presentation on Tuesday will be put up on the SMART board for ease of discussion. There are a lot of components and this will ensure we are all at the same point for the discussion and will allow staff to highlight items of interest easier. 2015-2019 CIP SUMMARY OF CHANGES Park Dedication Fund 1. Skate park commitment of $7,000 ends in 2014. Ongoing commitment of $7,000 is budgeted. 2. Park dedication fees are not projected at the current time. 3. Franchise fees for park projects were added effective 2014 at $85,300 per year. In addition, pursuant to the FMP the 2012 increase previously earmarked for streets is moved into the Park Dedication Fund. There will be a transfer in 2014 to move excess street franchise fees collected in 2012 and 2013 to this fund. 4. Parks projects for 2014 were revised as shown on the cash flow statement. The largest items added relate to Cottageville Park. 5. In 2015 the Depot Recreation Center was added at a participation amount of $50,000. A Hennepin County grant will be applied for and there is a local match required. 6. In 2016 Cottageville Park phase 2 improvements were added. 7. Other park projects were rescheduled between years. Capital Improvement Fund 1. Tax levy has been adjusted per the Financial Management Plan reducing the levy which is now causing challenges. 2. In 2015 projects totaling $145,500 were added and the Arts Center Theater seats were moved up from 2017 at a cost of $138,500. 3. In 2016 projects totaling $70,000 were added. 4. In 2017 projects totaling $15,000 were added and the Arts Center Theater seats were moved up to 2015. Communications Fund 1. No changes from prior CIP. MSA Fund I . The amount owing from the State on the Shady Oak Road advance is shown on the cash flow statement. 2. The amount currently owing to Hennepin County for our share of ROW acquisition costs is shown in 2013 and again as a reduction of project costs in 2014. We have not been formally billed and those costs are included in the project sheet as part of Hopkins share of total project costs. 3. In 2015 Mainstreet Rehabilitation projects with MSA funding are shown along with the related bond issue. PIR Fund 1. Bonds are projected to be sold each year we have a street project. 2. Residential street improvements a. 2015 - $3,565,000 i. PIR - $3,255,000 — increase of $1,730,000 1. Eliminated residential street projects of $500,000 2. Increased Co Rd 61 (Shady Oak Rd) from $200,000 to $700,000 3. Increased parking lot project from $800,000 to $930,000. 4. Added Railroad quiet zone plan, design and implementation at $25,000 5. Added Mainstreet Rehabilitation project at a cost of $1,400,000 6. Added street overlay project at a cost of $175,000 ii. SA - $$310,000— decrease of $140,000 1 Eliminated residential street projects of $200,000 2. Added Mainstreet Rehabilitation project at $60,000 b. 2016 - $2,600,000 i. PIR - $1,540,000 — no change ii. SA - $1,060,000 — no change c. 2017 - $3,855,000 i. PIR - $2,791,000 increase of $1,250,000 1. Increased residential street projects by $1,000,000 2. Added Blake Road corridor improvements at a cost of $250,000. ii. SA - $1,064,000 — no change d. 2018 - $3,175,000 i. PIR - $2,425,000 — increase of $575,000 1. Decreased rail road quite zone by $25,000 that was pulled forward to 2015 as plan design and implementation. 2. Added Blake Road corridor improvements at a cost of $600,000 ii. SA - $750,000 — no change e. 2019 - $2,250,000 i. PIR - $1500,000 ii. SA - $750,000 Water Fund 1. Residential street improvements a. 2015 - $250,000 — increase of $50,000. Residential street improvements of $200,000 were eliminated and $250,000 for Mainstreet Rehabilitation was added. b. 2016 - $786,000 — increase of $350,000. Residential street improvements increased by $200,000 and Eight Ave LRT corridor was added at $150,000. c. 2017 - $400,000 — increase of $200,000 for residential street improvements d. 2018 - $850,000 — increase of $250,000 for Blake Road corridor improvements e. 2019 - $$268,000 Sanitary Sewer Fund 1. Residential street improvements a. 2015 - $0 — decreased by $200,000 as residential street improvement project eliminated b. 2016 - $300,000 — decrease of $5,000; Residential street improvements decreased by $55,000, Lift Station #4 of $160,000 was pushed back to 2019, Blake Road corridor improvements added at $100,000 c. 2017 - $240,000 — increase of $120,000 for residential street improvements d. 2018 — $475,000 — increase of $150,000 for Blake Road corridor improvements. e. 2019 - $298,000 Storm Sewer Fund 1. Residential street improvements a. 2015 - $470,000 — increased by $150,000. Residential street projects of $100,000 eliminated, $230,000 storm water management projects pushed back from 2014 and $20,000 added to the parking lots and HCRAA alley project. b. 2016 - $396,000 — increase of $240,000. Residential street improvements increased $90,000 and $150,000 was added for Blake Road corridor improvements. c. 2017 - $241,000 —increase of $110,000 for residential street improvements d. 2018 - $321,000 — no change e. 2019 - $190,000 Pavilion Fund 1. 2015 — Gas fired rooftop furnace was purchased in 2014 with excess bond funds and eliminated from 2015. 2. 2016 — Roof replacement at a cost of $140,000 was added 3. 2017 — no change 4. 2018 — Increased by $20,000 for painting the arena ceiling and bar joist. Original project was $20,000. Projects added for 2019 include: a. HHS Team room rooftop unit replacement — $9,500 06/05/2014 132-020-013 132-350-001 (3) Project MUNICIPAL STATE AID FUND (302) Paid Balance State Aid Funds due City Total From State Actual Projected Projected Projected Projected Projected Projected Minnetonka Mills Rd 2013 2014 2015 2016 2017 2018 2019 Working Capital Beginning Bal 2,064,148 467,787 2,307,436 1,318,973 1,325,568 1,332,195 238,856 Revenues: 62.05 State MSA Funds, projects 446,662 0 0 0 0 0 400,000 State MSA Advance 2,087,310 Interest Earnings (5,873) 2,339 11,537 6,595 6,628 6,661 1,194 Hennepin County Hennepin County - Land Reimb 2,271,909 Land Sale proceeds 3,698 Bond issue 1,630,000 Total Revenues 2,716,396 2,089,649 1,641,537 6,595 6,628 6,661 401,194 Transfer Out for Projects CIP State Aid Projects 190,697 County Rd 61 - Shady Oak Rd 2,050,000 1,000,000 Mainstreet Rehabilitation 1,630,000 County Road 3 - EB 700,000 Sixth St S (11th - 12th Ave) 400,000 Shady Oak Rd ROW Purchase (1) 1,814,674 (1,800,000) Misc Expenses 31,779 Shady Oak Rd Land Acqusition 2,275,607 Total Expenditures 4,312,757 250,000 2,630,000 0 0 1,100,000 0 Working Capital Ending Balance 467,787 2,307,436 1,318,973 1,325,568 1,332,195 238,856 640,051 includes cash. interest rcvbl. & A/P Cash Balance 12/31120XX 1,216,125 ESTIMATED Cash Balance 12/31/20XX 3,055,774 2,067,311 2,073,906 2,080,534 987,195 1,388,389 Amount owed Hennepin County as of 12-31-13 (1,814,674) (1) Hopkins share of expenditures paid by Hennepin County and not yet billed. Project expenses budgeted for 2014 total $2,050,000, however we are recognizing a liability for amounts already expended on Hopkins behalf by Hennepin County so show that as a deduct of the 2014 budget. 132-020-013 132-350-001 (3) Project Total Due Paid Balance State Aid Funds due City Total From State To Date Due 5/31/14 Excelsior Blvd CSAH 3/61 5,629,235.87 4,086,619.00 3,293,290.51 793,328.49 Minnetonka Mills Rd 1,231,889.51 894,019.71 100,882.69 793,137.02 5th Street South 1,165,881.73 - Total 8,027,007.11 4,980,638.71 3,394,173.20 1,586,465.51 62.05 Cash Flow Analysis P.I.R. FUND (501) 06/0512014 Working Capital Beginning Year Revenues: Special Assessment Revenues - from levy Special Assessment Revenues - Prepaid Interest Bond Proceeds Transfer In - matured bonds (excess) Total Revenues Expenditures: C.I.P. Projects C.I.P. Projects - Special Assm Transfers for SA Debt collected thru Assm Debt Service Transfers - 2007B Debt Service Transfers - 2010A - Impry Debt Service Transfers - 2010B - Rfdg Debt Service Transfers (prepaids to DS funds) Total Expenditures Working Capital Year End Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 2,389,701 2,341,089 1,792,273 1,038,798 959,745 858,227 657,265 305,687 25,000 20,000 0 0 0 0 24,000 62,000 212,000 212,800 150,000 150,000 (562) 10,535 8,065 4,675 4,319 3,862 2,958 1,906,296 1,940,000 2,800,000 2,388,000 3,642,200 3,025,000 2,100,000 18,483 2,229,904 1,999,535 2,890,065 2,604,675 3,859,319 3,178,862 2,252,958 2,074,511 2,355,000 3,255,000 1,540,000 2,791,000 2,425,000 1,500,000 120,000 310,000 1,060,000 1,064,000 750,000 750,000 15,384 14,815 17,182 19,548 38,835 0 62,203 58,536 61,358 64,180 67,002 69,824 80,794 0 126,418 2,278,516 2,341,089 2,548,351 3,643,540 2,683,728 3,960,837 3,379,824 2,465,794 1,792,273 1,038,798 959,745 858,227 657,265 444,429 Total Projects Scheduled (CIP & SA) 2,074,511 2,475,000 3,565,000 2,600,000 3,855,000 3,175,000 2,250,000 WATER FUND - WORKING CAPITAL PROJECTION 06/05/2014 Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 Working Capital Beginning Year 76,872 597,731 873,064 838,711 1,019,606 1,104,705 1,219,632 Revenues: Operating Revenues 1,468,956 1,541,669 1,377,850 1,416,550 1,461,500 1,506,450 1,551,550 Other 14,327 152,149 158,533 165,235 172,272 179,661 187,418 Interest 139 0 0 0 0 0 0 Gain on Sale of Asset 21,855 Bond Issuance 860,000 195,000 200,000 780,000 400,000 850,000 268,000 Total Revenues 2,365,277 1,888,818 1,736,383 2,361,785 2,033,772 2,536,111 2,006,968 Expenditures: Operation Expense 1,069,741 1,037,781 1,073,846 1,111,244 1,150,027 1,190,249 1,231,969 Other Exp - bond issuance -fiscal fee Other Exp - int on current bonds 64,620 0 0 0 Other Exp - int on refunded bonds 7,587 2,700 Other Exp - int on 2009 bonds 24,225 22,850 21,350 19,725 17,887 15,963 Other Exp - int on 2012 bonds 14,179 13,379 12,529 11,629 10,729 9,829 Other Exp - int on 2013 bonds 22,713 17,431 16,431 15,431 14,381 13,281 Other Exp -est interest on Future Bonds 5,730 17,035 21,861 33,037 34,635 Equipment Replacement Items 0 6,800 0 61,700 Capital Improvements 462,660 197,000 250,000 786,000 400,000 850,000 268,000 Principal Bond payment 260,000 Principal Bond payment - refunded 175,000 180,000 Principal Bond pymnt - 2009 debt 50,000 50,000 50,000 50,000 55,000 55,000 Principal Bond pymnt - 2012 debt 40,000 40,000 45,000 45,000 45,000 45,000 Principal Bond pymnt - 2013 debt 50,000 50,000 50,000 55,000 55,000 Principal Bond pymnt - Future Debt 13,000 26,300 78,300 104,900 161,500 Capital Lease (PW Facility) (1) 0 45,000 45,000 45,000 45,000 45,000 45,000 Total Expenditures 1,857,021 1,613,485 1,770,736 2,180,890 1,948,673 2,421,184 1,953,177 Change in available funds 508,256 275,334 (34,353) 180,895 85,099 114,927 53,791 Inventory change 52 Bond Premium/Discount Exp 12,551 Working Capital Ending Year 597,731 873,064 838,711 1,019,606 1,104,705 1,219,632 1,273,424 (1) Capital Lease moved to Storm Sewer - back to water fund in 2014 Rate History (water/sprinkler) 2014 - 2018 financial data was taken from the Utility Master Plan done by City Engineer 1984 $0.85 1993 $1.05 Notes - 1997 $1.10 Income - 2008 and forward used utility master plan rates (fixture/no surcharge option) 2000 $1.20 2005 $1.40 Equipment Per Utility Master Plan (10/07) 2015 - phone system 2008 $1.65 2017 - 1/2 ton truck and 3/4 ton utility truck 2009 $1.86 2010 $1.90 2011 $1.94/2.40 - not incr, left at $1.90 2012 $1.96/2.40 2013 $2.02/2.40 2014 $2.10/2.50 2015 $2.18/2.60 2016 $2.25/2.70 projected rate 2017 $2.35/2.85 increases 2018 $2.45/3.00 these are the correct rates per the UMP SEWER FUND - WORKING CAPITAL PROJECTION 06/05/2014 Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 Working Capital Beginning Year 394,411 229,722 370,127 505,976 615,059 713,615 823,069 Revenues: Operating Revenues 1,981,580 2,308,500 2,399,700 2,496,600 2,593,500 2,696,100 2,804,400 Other 17,903 20,000 20,000 20,000 20,000 20,000 20,000 Interest 33 574 925 1,265 1,538 1,784 2,058 Bond Issuance 490,000 150,000 0 300,000 240,000 475,000 298,000 Total Revenues 2,489,516 2,479,074 2,420,625 2,817,865 2,855,038 3,192,884 3,124,458 Expenditures: Operation Expense 551,763 551,833 570,253 589,319 609,053 629,484 650,634 MWCC Charges (3% inflation) 1,222,893 1,436,144 1,504,307 1,575,771 1,650,698 1,729,256 1,811,624 Other - Bond Issuance -fiscal fees Interest Expense 45,015 30,100 28,450 26,575 24,463 22,187 19,825 Interest Expense - 2012 Debt 3,149 2,949 2,749 2,549 2,349 2,149 Interest Expense - 2013 Debt 12,943 9,918 9,318 8,719 8,119 7,519 Interest Expense - Future Debt 2,100 6,450 9,600 16,035 19,341 Equipment Replacement Items 0 6,800 33,600 26,400 Capital Improvements 773,923 154,500 0 300,000 240,000 475,000 298,000 Principal Bond payment (2009) 70,000 60,000 60,000 65,000 65,000 65,000 70,000 Principal Bond payment (2012) 10,000 10,000 10,000 10,000 10,000 10,000 Principal Bond payment (2013) 30,000 30,000 30,000 30,000 30,000 30,000 Principal Bond payments Future Debt 10,000 10,000 30,000 46,000 77,600 Capital Lease (PW Facility) (1) 0 50,000 50,000 50,000 50,000 50,000 50,000 Total Expenditures 2,663,594 2,338,669 2,284,777 2,708,782 2,756,482 3,083,430 3,064,691 Change in available funds (174,078) 140,406 135,849 109,083 98,556 109,454 59,766 Inventory change 90 Bond Premium/Discount Exp 9,299 Working Capital Ending Year 229,722 370,127 505,976 615,059 713,615 823,069 882,835 (1) Capital Lease moved to Storm Sewer - back in fund in 2014 Rate History 2014 - 2018 financial data was taken from the Utility Master Plan done by City Engineer 1983 $1.50 1989 $1.75 1991 $2.00 1993 $2.50 Notes - 1999 $2.25 Rate DECREASE Income - 2008 and forward used utility master plan rates (no fixture option) 2006 $2.50 rate increase Per Utility Master Plan (10/07) Equipment 2008$2.70 2015 - phone system 2009$3.10 2016 - 3/4 ton utility truck 2010$3.40 2017 - generator 2011 $3.70 - act 3.60 2012$3.75 2013$3.90 2014$4.10 2015$4.30 2016$4.55 2017 $4.80 Projected rate increases 2018$5.10 these are the correct rates per the UMP STORM SEWER FUND - WORKING CAPITAL PROJECTION 06/05/2014 Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 Working Capital Beginning Year 744,314 883,002 116,885 184,295 584,429 949,815 1,294,855 Revenues: Operating Revenues 794,630 794,630 794,630 794,630 794,630 794,630 794,630 Other 4,973 5,000 5,000 5,000 5,000 5,000 5,000 Interest (1,717) 2,208 292 461 1,461 2,375 3,237 Bond Issuance 380,000 300,000 240,000 395,000 240,000 320,000 190,000 Total Revenues 1,177,886 1,101,838 1,039,922 1,195,091 1,041,091 1,122,005 992,867 Expenditures: Operation Expense 177,656 181,209 184,833 188,530 192,301 196,147 200,070 Other - Bond Issuance -fiscal fees Bond Interest - existing 35,437 Bond Interest - 2009 refunded bonds 5,312 1,875 Bond Interest -2010 bonds 15,348 14,585 13,623 12,485 11,173 9,629 Bond Interest - 2012 bonds 6,031 5,681 5,281 4,881 4,481 4,081 Bond Interest - 2013 bonds 10,054 7,738 7,338 6,888 6,388 5,888 Interest Expense - Future Debt 7,800 13,185 15,850 19,476 20,832 Capital Outlay (per ERP) 0 0 0 0 0 0 0 Cottageville Property purchase 400,000 Cottageville Park Storm Water Mgmt 1,000,000 Capital Improvements 506,675 20,000 470,000 396,000 241,000 321,000 190,000 Capital Improvements - PW Bldg 18,000 2009 Principal Bond payment 120,000 125,000 125,000 2010 Principal Bond payment 70,000 65,000 70,000 70,000 70,000 70,000 75,000 2012 Principal Bond payment 15,000 15,000 20,000 20,000 20,000 20,000 20,000 2013 Principal Bond payment 20,000 20,000 25,000 25,000 25,000 Principal Bond payments Future Debt 20,000 36,000 62,300 78,300 99,601 Capital Lease - PW Facility (1) 120,000 25,000 25,000 25,000 25,000 25,000 25,000 Total Expenditures 1,044,768 1,867,955 972,512 794,957 675,705 776,965 693,100 Change in available funds 133,118 (766,117) 67,410 400,134 365,386 345,040 299,767 Inventory change 372 Bond Premium/Discount Exp (net) 5,198 Working Capital Ending Year 883,002 116,885 184,295 584,429 949,815 1,294,855 1,594,622 (1) In 2012 this includes Water, Sewer & Storm Sewer transfers; in 2014 transfer returned to normal level Rate History (per month) 1989 $4.75 per quarter 1991 $6.00 per quarter 1992 $2.50 1993 $3.00 1998 $3.20 1999 $4.00 2006 $4.50 2009 $5.00 Working Capital Beginning Year Revenues: Taxes (from matured Park Bonds) Interest Dedication fees Joint Rec refunds Franchise Fees (gas/elec) 2014 incr Franchise Fees (gas/elec) 2012 incr Transfer in Franchise Fees' Hennepin County Grant Met Council - easememt/grant Grants - Private Foundations Donations - general Donations - benches Total Revenues Expenditures: C.I.P. Projects Cottageville Property Acquisition Skate Park commitment Total Expenditures Working Capital Year End ' Transfer in of Franchise Fees collected in 2012 -2013 not needed for debt service on street projects. Going forward the 2012 franchise fee increase has been proposed to be used for park projects rather than street projects. PARK CAPITAL IMPROVEMENTS FUND (301) 06104/2014 Revised Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 82,902 139,566 48,262 138,044 66,486 182,780 22,564 62 311 1,396 483 4,141 1,995 5,483 677 0 0 0 0 0 0 6,267 6,000 6,000 6,000 6,000 6,000 6,000 85,300 85,300 85,300 85,300 85,300 85,300 210,000 210,000 210,000 210,000 210,000 210,000 200,000 150,000 20,182 1,000 176,822 503,696 301,783 305,441 303,295 306,783 301,977 113,158 588,000 205,000 370,000 180,000 460,000 130,000 0 7,000 7,000 7,000 7,000 7,000 7,000 7,000 120,158 595,000 212,000 377,000 187,000 467,000 137,000 139,566 48,262 138,044 66,486 182,780 22,564 187,541 outdoor lighting - Play equipment - Drinking fountain - lighting Park play equipment Park general improvements improvements - Yr 3 of 3 yr agreement 2019 Proiects 50,000 Burnes Park - Lighting 30,000 Harley Hopkins Park - Warming House 50,000 Harley Hopkins Park - Lighting 130,000 2014 Projects Adjusted Original Actual 40,000 40,000 Valley Park 130,000 100,000 Oakes Park 10,000 10,000 Oakes Park - 20,000 Oakes Park 200,000 Cottageville 208,000 Cottageville 7,000 7,000 Skate Park 595,000 177,000 0 2015 Proiects 60,000 Burnes Park - warming house 30,000 Oakes Park - picnic shelter 40,000 Oakes Park - Lighting 25,000 Valley Park - construct storage building 50,000 Depot Recreation Area 205,000 2016 Proiects 50,000 Burnes Park - play equipment 250,000 Cottageville Park - phase II improvements 70,000 Rehab Downtown Park 370,000 2017 Proiects 80,000 Valley Park - play equipment 100,000 Hilltop Park - play equipment 180,000 2018 Proiects 60,000 Park Valley - play equpment 20,000 Burnes Park - resurface tennis courts 20,000 Oakes Park - tennis courts 60,000 Valley Park - warming house 300,000 Burns Park - splash pad 460,000 outdoor lighting - Play equipment - Drinking fountain - lighting Park play equipment Park general improvements improvements - Yr 3 of 3 yr agreement 2019 Proiects 50,000 Burnes Park - Lighting 30,000 Harley Hopkins Park - Warming House 50,000 Harley Hopkins Park - Lighting 130,000 FACILITIES & BUILDINGS CAPITAL IMPROVEMENTS FUND (305) 06/05/2014 Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 Working Capital Beginning Year 135,687 194,214 253,885 (12,956) (544,946) (812,671) (693,734) Revenues: Interest (646) 971 1,269 (65) (2,725) (4,063) (3,469) Transfers from General Fund Tax Levy (red per FMP) 123,687 125,000 53,000 35,000 150,000 175,000 125,000 Total Revenues 123,041 125,971 54,269 34,935 147,275 170,937 121,531 Expenditures: C.I.P. Projects 64,514 45,000 304,010 561,000 415,000 52,000 133,000 C.I.P. Projects - Arts Center 21,300 17,100 5,925 Transfer to General Fund Total Expenditures 64,514 66,300 321,110 566,925 415,000 52,000 133,000 Working Capital Year End 194,214 253,885 (12,956) (544,946) (812,671) (693,734) (705,203) 2014 Proiects 36,000 Activity Center - Raspberry room carpet 9,000 Arts Center - Restroom Improvements 45,000 2015 Proiects formerly in for 2017 138,510 Arts Center - Theater Seats 20,000 Public Works Garage Upgrade - engineering 13,000 Activity Center - Fencing/Landscaping New addition 67,000 Activity Center - Multi-purpose Gym Improvements New addition 15,000 Arts Center - paint theater New addition 23,000 PW - Wash Bay Roof Replacement New addition 15,000 PW - Wash Bay Air Handler Replacement New addition 12,500 PW - Fuel Management System Upgrade New addition $145,500 in new items added 304,010 2016 Proiects 105,000 Activity Ctr - replace gymnasium roof 80,000 Activity Center - Raspberry Room roof replacement 56,000 Fire Dept - Repl carpet & apparatus floor finish 40,000 Police Dept - replace carpet 110,000 City Hall Lobby Upgrade 100,000 Public Works Garage Upgrade (total project = $200,000 - $100K from Ent Funds) 20,000 Activity Center- computer/library room ehnancements New addition 50,000 Arts Center - Remodel administrative offices New addition $70,000 in new items added 561,000 2017 Proiects 80,000 Activity Center - lower roof repl 320,000 Art Center - Replace HVAC units 15,000 Activity Center - dishwasher one item (138,510) moved to 2015 415,000 2018 Proiects 52,000 Art Center - lobby carpet 2019 Proiects 18,000 PW - overhead door repl 115,000 City Hall - roof repl 133,000 Working Capital Beginning Year Revenues: Operating Revenues Leases current lease expires in 2013 Levy per FMP Other Interest Total Revenues Expenditures: Operation Expense Capital Outlay - ERP Capital Improvements Payment on Equip Certific P&I Payment on Interfund Loan Total Expenditures Change in available funds Bond Premium/Discount Exp (net) Working Capital Ending Year PAVILION - ICE ARENA - WORKING CAPITAL PROJECTIONS 06/05/2014 Actual Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 117,122 141,036 145,981 162,394 (39,123) 5,086 17,218 359,961 377,959 396,857 416,700 437,535 459,412 482,382 38,000 287,000 380,779 383,014 455,444 693,217 468,326 522,279 24,215 65,000 65,000 65,000 65,000 65,000 7,224 10,000 10,000 10,000 10,000 10,000 10,000 (191) 162,394 (39,123) 5,086 17,218 Paint Pavilion Exterior CIP 404,994 387,959 471,857 491,700 512,535 534,412 557,382 351,064 361,596 372,444 383,617 395,126 406,979 7,833 - - 12,000 - - - - 60,000 275,000 51,000 93,500 3,130 18,350 23,000 22,600 22,200 21,800 18,752 3,068 - - 287,000 380,779 383,014 455,444 693,217 468,326 522,279 24,215 4,945 16,413 (201,517) 44,209 12,132 (301) CIP 2018 24,500 Mezzanine Rooftop Unit Replacement CIP 141,036 145,981 162,394 (39,123) 5,086 17,218 93,500 CIP 2019 9,500 1 HHS Team Room Rooftop Unit Replacement 419,189 9,500 21,400 450,089 107,293 124,512 Pavilion Pro'ects CIP 2014 Roof Replacement - moved to 2016 CIP 2015 60,000 Evaporator Condenser Replacement CIP 2016 40,000 Overhead Door Replacement CIP 2016 95,000 Indoor Turf Replacement CIP 2016 140,000 Roof Replacement ERP 2016 12,000 Arena Scoreboard 287,000 CIP 2017 6,000 Desiccant Repl of Dehumidification System CIP 2017 45,000 Skate Tile Lobby Improvement 51,000 CIP 2018 24,500 Mezzanine Rooftop Unit Replacement CIP 2018 7,000 Pavilion Entry & Lobby Door Replacement CIP 2018 22,000 Paint Pavilion Exterior CIP 2018 40,000 Painting the Arena Ceiling and Bar Joist 93,500 CIP 2019 9,500 1 HHS Team Room Rooftop Unit Replacement 419,189 9,500 21,400 450,089 107,293 124,512 Working Capital Beginning Year Revenues: Franchise Fees Franchise Fees - PEG Fees Interest Total Revenues Expenditures: Expense Transfer Out Capital Outlay Total Expenditures Change in available funds Working Capital Ending Year 06/04/2014 COMMUNICATIONS (Cable TV) - WORKING CAPITAL PROJECTIONS Projected Projected Projected Projected Projected Projected Projected 2013 2014 2015 2016 2017 2018 2019 381,181 418,657 417,712 387,326 375,265 348,480 325,286 224,130 210,000 210,000 210,000 210,000 210,000 210,000 28,577 15,000 15,000 15,000 15,000 15,000 15,000 (931) 1,675 1,671 1,549 1,501 1,394 1,301 251,776 226,675 226,671 226,549 226,501 226,394 226,301 127,379 131,200 135,136 139,190 143,366 147,667 152,097 86,920 86,920 86,920 86,920 86,920 86,920 86,920 - 9,500 35,000 12,500 23,000 15,000 - 214,299 227,620 257,056 238,610 253,286 249,587 239,017 37,477 (946) (30,386) (12,061) (26,785) (23,193) (12,716) 418,657 417,712 387,326 375,265 348,480 325,286 312,570 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2015 thru 2019 PROJECTS BY YEAR Project Name Department Project # Priority Project Cost 2015 Activity Center - Fencing/Landscaping Activity Center 14-CIPACOO 1 1 13,000 Activity Center - Multi Purpose/Gym Improvements Activity Center 14-CIPAC002 2 67,000 Arts Center- Replace theatre seats and backs Arts Center 12-CIPAR002 1 138,510 Arts Center - Replace Information Desk and Kiosk Arts Center 12-CIPAR005 1 5,000 Arts Center - Re -landscape E & W faces of building Arts Center 13-CIPAR001 2 3,600 Arts Center - Storage in Art Classroom Arts Center 14-CIPAROOI 1 3,500 Arts Center - Kitchen Handwashing Sink Arts Center 14-CIPAR002 1 5,000 Arts Center - Paint Theatre Arts Center 14-CIPAR003 2 15,000 Technology Improvement - Council Chambers & Studio Communications 13 CIP-CM001 n/a 35,000 Redevelopment, East Excelsior Boulevard Development 01-CIP-D4010 n/a 2,000,000 Block 64 Redevelopment Project Development 06-CIP-D404 n/a 4,500,000 Blake Corridor Redevelopment Development 09-CIP-D406 n/a 5,000,000 Pavilion Evaporator Condenser Replacement Pavilion 09-CIP-PO36 n/a 60,000 Public Works Garage Upgrade Public Works: Bldg/Equip Sery 13-CIP-BOI f 1 20,000 Wash Bay Roof Replacement Public Works: Bldg/Equip Sery 14-CIP-BOO1 4 23,000 Wash Bay Air Handler Replacement Public Works: Bldg/Equip Sery 14-CIP-B002 3 15,000 Fuel Management System Upgrade Public Works: Bldg/Equip Sery 14-CIP-B003 4 12,500 Skate Park Public Works: Parks 08-CIP-P003 n/a 7,000 Burnes Park - Warming House Public Works: Parks 13-CIP-PO40 n/a 60,000 Oakes Park - Replace Picnic Shelter Public Works: Parks 13-CIP-PO41 n/a 30,000 Valley Park - Construct Storage Building Public Works: Parks 13-CIP-PO42 n/a 25,000 Oakes Park - Lighting Public Works: Parks 13-CIP-PO72 n/a 40,000 County Road 61 (Shady Oak Road) Public Works: Streets/Traffic 01-CIP-S106 n/a 18,800,000 Parking Lots and HCRRA Alley Improvements Public Works: Streets/Traffic 06-CIP-S 118 n/a 1,150,000 Plan, Design and Implement Railroad Quiet Zone Public Works: Streets/Traffic 11-CIP-S 120 n/a 25,000 Mainstreet Rehabilitation Public Works: Streets/Traffic 11-CIP-S 121 3 4,000,000 Pedestrian & Bicycle Access Improvements Public Works: Streets/Traffic 13-CIP-SO40 n/a 25,000 2015 Street Overlay Project Public Works: Streets/Traffic 15-CIP-SO39 n/a 175,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-CIP-0002 n/a 20,000 Storm Water Management Projects Public Works: Utilities 01-CIP-0003 n/a 230,000 Depot Recreation Area Recreation 10-CIP-RO02 2 225,000 Total for 2015 36,728,110 2016 Activity Center - Replace Gynmasium Roof Activity Center 08-CIP-AC018 n/a 105,000 Activity Center - Raspberry Room Roof Replacement Activity Center 08-CIPACO24 n/a 80,000 Activity Center Computer/Library Room Enhancements Activity Center 14-CIPAC003 4 20,000 Arts Center - Storage & Hanging, Display Systems Arts Center 13-CIPAR004 1 3,125 Arts Center- Remodel Administrative Offices Arts Center 14-CIPAR004 2 50,000 Arts Center - Entryway Planters Arts Center 14-CIPAR005 3 2,800 City Hall Lobby Upgrade City Hall Administration 09-CIP-CH030 n/a 110,000 Technology Improvement - Council Chambers & Studio Communications 13 CIP-CM001 n/a 12,500 8th Ave Streetscape and parking facility Development 12-CIP-0408 n/a 4,000,000 Replace Carpet and Apparatus Floor Finish - FD Fire 08-CIP-FDO 19 n/a 56,000 Thursday, June 05, 2014 Project Name Department Project # Priority Project Cost Pavilion Overhead Door Improvement Pavilion 07-C/P-P314 n/a 40,000 Pavilion Roof Replacement Pavilion 09-C/P-PO26 1 140,000 Pavilion Indoor Turf Replacement Pavilion 10-C/P-P319 n/a 95,000 Replace Carpet - Police Station Police 08-C/P-PDO16 n/a 40,000 Public Works Garage Upgrade Public Works: Bldg/Equip Sery 13-C/P-BO 11 1 200,000 Skate Park Public Works: Parks 08-C/P-P003 n/a 7,000 Burnes Park - Play Equipment Public Works: Parks 13-C/P-PO43 n/a 50,000 Cottageville Park - Phase II Improvements Public Works: Parks 13-C/P-PO54 n/a 250,000 Rehab Downtown Park Public Works: Parks 14-C/P-POOI n/a 70,000 Residential Street Improvements and Utilities Public Works: Streets/Traffic 01 -CF -S101 n/a 3,275,000 Citywide Concrete Alleys Public Works: Streets/Traffic 01-C/P-S103 n/a 75,000 Pedestrian & Bicycle Access Improvements Public Works: Streets/Traffic 13-C/P-SO40 n/a 25,000 Eighth Avenue LRT Corridor Public Works: Transportation 01-C/P-S503 n/a 3,700,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 21,000 St. Louis Park Emergency Connection Public Works: Utilities 08-C/P-UOIO n/a 211,000 Total for 2016 12,638,425 r 20r Activity Center - Lower Roof Replacement Activity Center 09-CIPAC031 n/a 80,000 Activity Center - Dishwasher Activity Center 14-CIPAC004 5 15,000 Arts Center - Replace Rooftop HVAC Units Arts Center 08-CIPAR013 n/a 320,000 Technology Improvement - Council Chambers & Studio Communications 13 C/P-CM001 n/a 23,000 Pavilion skate Tile Replacement/Lobby Improvement Pavilion 07-C/P-P313 n/a 45,000 Pavilion - Desiccant Repl of Dehumidification Syst Pavilion 10-C/P-P320 n/a 6,000 Skate Park Public Works: Parks 08-C/P-P003 n/a 7,000 Hilltop Park - Play Equipment Public Works: Parks 08-C/P-PO14 n/a 100,000 Valley Park - Play Equipment Public Works: Parks 08-C/P-P015 n/a 80,000 Residential Street Improvements and Utilities Public Works: Streets/Traffic 01-C/P-S101 n/a 4,360,000 Citywide Concrete Alleys Public Works: Streets/Traffic 01-C/P-5103 n/a 80,000 Pedestrian & Bicycle Access Improvements Public Works: Streets/Traffic 13-C/P-SO40 n/a 25,000 Blake Road Corridor Improvements Public Works: Streets/Traffic 15-C/P-SOOI n/a 1,000,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 21,000 Total for 2017 6,162,000 2018 nowwwwwwwom Art Center - Replace Lobby Carpet Arts Center 09-CIPAR027 n/a 52,000 Technology Improvement - Council Chambers & Studio Communications 13 C/P-CM001 n/a 15,000 Pavilion Mezzanine Rooftop Unit Replacement Pavilion 13-C/P-P321 1 24,500 Pavilion Entry and Lobby Door Replacement Pavilion 13-C/P-P324 3 7,000 Pavilion - Paint Exterior Building Pavilion 13-C/P-P325 1 22,000 Pavilion Painting the Arena Ceiling and Bar Joist Pavilion 14-C/P-PO10 1 40,000 Skate Park Public Works: Parks 08-C/P-P003 n/a 7,000 Park Valley - Play Equipment Public Works: Parks 08-C/P-POLO n/a 60,000 Burnes Park - Resurface Tennis Courts Public Works: Parks 08-C/P-POI f n/a 20,000 Oakes Park - Tennis Courts Public Works: Parks 13-C/P-PO44 n/a 20,000 Valley Park - Warming House Public Works: Parks 13-C/P-PO45 n/a 60,000 Burnes Park Splash Pad Public Works: Parks 14-C/P-P002 n/a 300,000 Residential Street Improvements and Utilities Public Works: Streets/Traffic Of-C/P-S 101 n/a 3,475,000 County Road 3 Public Works: Streets/Traffic 01-C/P-S104 n/a 2,300,000 Sixth Street South (11th to 12th Avenue South) Public Works: Streets/Traffic 01-C/P-S504 n/a 500,000 Plan, Design and Implement Railroad Quiet Zone Public Works: Streets/Traffic 11-C/P-S 120 n/a 200,000 Pedestrian & Bicycle Access Improvements Public Works: Streets/Traffic 13-C/P-SO40 n/a 25,000 Blake Road Corridor Improvements Public Works: Streets/Traffic 15-C/P-SOOI n/a 9,000,000 Light Rail Transit Stations (3) Public Works: Transportation 01-C/P-5502 n/a 500,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 21,000 Thursday, June 05, 2014 Project Name Department Project # Priority Project Cost 2019 1 City Hall Roof Replacement Pavilion HHS Team Room Rooftop Unit Repl Public Works - Replace Overhead Doors Skate Park Burnes Park - Lighting Harley Hopkins Park - Warming House Harley Hopkins Park - Lighting Residential Street Improvements and Utilities Storm Drainage System Maintenance - Alley Repairs Lift Station # 4 Total for 2018 16,648,500 City Hall Administration 09-C/P-CH029 n/a 115,000 Pavilion 13-C/P-P322 1 9,500 Public Works: Bldg/Equip Sery 08-C/P-BO23 n/a 90,000 Public Works: Parks 08-C/P-P003 n/a 7,000 Public Works: Parks 13-C/P-PO46 n/a 50,000 Public Works: Parks 13-C/P-PO56 n/a 30,000 Public Works: Parks 13-C/P-PO57 n/a 50,000 Public Works: Streets/Traftic 01-C/P-S101 n/a 2,770,000 Public Works: Utilities 01-C/P-0002 n/a 22,000 Public Works: Utilities 08-C/P-0001 n/a 160,000 Total for 2019 3,303,500 GRAND TOTAL 75,480,535 Thursday, June 05, 2014 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2015 thru 2019 PROJECTS BY DEPARTMENT Department Project# Priority 2015 2016 2017 2018 2019 Total Activity Center Activity Center - Replace Gynmasium Roof 08-C/P-AC018 n/a 105,000 105,000 Activity Center - Raspberry Room Roof Replacement 08-C/P-ACO24 n/a 80,000 80,000 Activity Center- Lower Roof Replacement 09-C/P-AC031 n/a 80,000 80,000 Activity Center - Fencing/Landscaping 14-CIP-AC001 1 13,000 13,000 Activity Center - Multi Purpose/Gym Improvements 14-C/P-AC002 2 67,000 67,000 Activity Center Computer/Library Room Enhancements 14-CIP-AC003 4 20,000 20,000 Activity Center - Dishwasher 14-CIP-AC004 5 15,000 15,000 Activity Center Total 80,000 205,000 95,000 380,000 lrts Center Arts Center - Replace Rooftop HVAC Units 08-C/P-AR013 n/a 320,000 320,000 Art Center - Replace Lobby Carpet 09-C/P-AR027 n/a 52,000 52,000 Arts Center - Replace theatre seats and backs 12-C/P-AR002 1 138,510 138,510 Arts Center - Replace Information Desk and Kiosk 12-C/P-AR005 1 5,000 5,000 Arts Center - Re -landscape E & W faces of building 13-CIPAR001 2 3,600 3,600 Arts Center - Storage & Hanging, Display Systems 13-C/P-AR004 1 3,125 3,125 Arts Center - Storage in Art Classroom 14-C/P-AR001 1 3,500 3,500 Arts Center - Kitchen Handwashing Sink 14-CIPAR002 1 5,000 5,000 Arts Center - Paint Theatre 14-CIP-AR003 2 15,000 15,000 Arts Center - Remodel Administrative Offices 14-CIPAR004 2 50,000 50,000 Arts Center - Entryway Planters 14-C/P-AR005 3 2,800 2,800 Arts Center Total 170,610 55,925 320,000 52,000 598,535 (City Hall Administration City Hall Roof Replacement 09-C/P-CH029 n/a 115,000 115,000 City Hall Lobby Upgrade 09-C/P-CH030 n/a 110,000 110,000 City Hall Administration Total 110,000 115,000 225,000 (Communications Technology Improvement - Council Chambers & Studio 13 C/P-CM001 n/a 35,000 12,500 23,000 15,000 85,500 Communications Total 35,000 12,500 23,000 15,000 85,500 Development - Redevelopment, East Excelsior Boulevard 01-C/P-D4010 n/a 2,000,000 2,000,000 Block 64 Redevelopment Project 06-C/P-0404 n/a 4,500,000 4,500,000 Blake Corridor Redevelopment 09-C/P-0406 n/a 5,000,000 5,000,000 8th Ave Streetscape and parking facility 12-C/P-0408 n/a 4,000,000 4,000,000 Development Total 11,500,000 4,000,000 15,500,000 (Fire Replace Carpet and Apparatus Floor Finish - FD 08-C/P-FDO19 n/a 56,000 56,000 71hursday, June 05, 2014 Department Project# Priority 2015 2016 2017 2018 2019 Total Fire Total 45,000 7,000 7,000 45,000 35,000 Pavilion Pavilion skate Tile Replacement/Lobby Improvement 07-C/P-P313 n/a Pavilion Overhead Door Improvement 07-C/P-P314 n/a Pavilion Roof Replacement 09-C/P-PO26 1 Pavilion Evaporator Condenser Replacement 09-C/P-PO36 n/a Pavilion Indoor Turf Replacement 10-C/P-P319 n/a Pavilion - Desiccant Repl of Dehumidification Syst 10-C/P-P320 n/a Pavilion Mezzanine Rooftop Unit Replacement 13-C/P-P321 1 Pavilion HHS Team Room Rooftop Unit Rept 13-C/P-P322 1 Pavilion Entry and Lobby Door Replacement 13-C/P-P324 3 Pavilion - Paint Exterior Building 13-C/P-P325 1 Pavilion Painting the Arena Ceiling and Bar Joist 14-C/P-P010 1 Pavilion Total 30,000 7,000 7,000 Police Replace Carpet - Police Station 08-C/P-PDO16 n/a Police Total 40,000 (Public Works: Bldg/Equip Sery 40,000 60,000 Public Works - Replace Overhead Doors 08-C/P-8023 n/a Public Works Garage Upgrade 13-C/P-BOIL 1 Wash Bay Roof Replacement 14-C/P-BOOL 4 Wash Bay Air Handler Replacement 14-C1P-B002 3 Fuel Management System Upgrade 14-C/P-B003 4 Public Works: Bldg/Equip Sery Total 90,000 90,000 20,000 200,000 Public Works: Parks Skate Park 08-CIP--P003 n/a Park Valley - Play Equipment 08-C/P-POIO n/a Burnes Park - Resurface Tennis Courts 08-CIP--PO11 n/a Hilltop Park - Play Equipment 08-C/P-P014 n/a Valley Park - Play Equipment 08-C/P-P015 n/a Burnes Park - Warming House 13-CIP--PO40 n/a Oakes Park - Replace Picnic Shelter 13-C/P-PO41 n/a Valley Park - Construct Storage Building 13-C/P-PO42 n/a Burnes Park - Play Equipment 13-C/P-PO43 n/a Oakes Park - Tennis Courts 13-CIP--PO44 n/a Valley Park - Warming House 13-C/P-PO45 n/a Burnes Park - Lighting 13-CIP-PO46 n/a Cottageville Park - Phase II Improvements 13-CIP-PO54 n/a Harley Hopkins Park- Warming House 13-C/P-PO56 n/a Harley Hopkins Park - Lighting 13-C/P-PO57 n/a Oakes Park - Lighting 13-CIP-PO72 n/a Rehab Downtown Park 14-CIP-POOI n/a Burnes Park Splash Pad 14-C/P-P002 n/a Public Works: Parks Total Public Works: Streets/Traffic Residential Street Improvements and Utilities 01-C/P-S101 n/a Citywide Concrete Alleys 01-C/P-S103 n/a 56,000 56,000 7,000 45,000 7,000 7,000 45,000 35,000 40,000 40,000 140,000 140,000 60,000 20,000 60,000 100,000 95,000 100,000 95,000 6,000 6,000 60,000 24,500 24,500 60,000 30,000 9,500 9,500 30,000 7,000 7,000 22,000 22,000 40,000 50,000 40,000 60,000 275,000 51,000 93,500 9,500 489,000 40,000 60,000 40,000 60,000 40,000 40,000 50,000 50,000 90,000 90,000 20,000 200,000 250,000 220,000 23,000 30,000 30,000 23,000 15,000 50,000 15,000 12,500 12,500 70,500 200,000 70,000 90,000 360,500 7,000 7,000 7,000 7,000 7,000 35,000 60,000 60,000 20,000 20,000 100,000 100,000 80,000 80,000 60,000 60,000 30,000 30,000 25,000 25,000 50,000 50,000 20,000 20,000 60,000 60,000 50,000 50,000 250,000 250,000 30,000 30,000 50,000 50,000 40,000 40,000 70,000 70,000 300,000 300,000 162,000 377,000 187,000 467,000 137,000 1,330,000 3,275,000 4,360,000 3,475,000 2,770,000 13,880,000 75,000 80,000 155,000 Tharsdav, Jure 05, 2014 Department Project# Priority 2015 2016 2017 2018 2019 Total County Road 3 01-C1P-S104 n/a 2,300,000 2,300,000 County Road 61 (Shady Oak Road) 01-CIP-S106 n/a 18,800,000 18,800,000 Sixth Street South (11th to 12th Avenue South) 01-C1P-5504 n/a 500,000 500,000 Parking Lots and HCRRA Alley Improvements 06-CIP-S 118 n/a 1,150,000 1,150,000 Plan, Design and Implement Railroad Quiet Zone 11-C/P-S120 n/a 25,000 200,000 225,000 Mainstreet Rehabilitation 11-C/P-S 121 3 4,000,000 4,000,000 Pedestrian & Bicycle Access Improvements 13-C/P-SO40 n/a 25,000 25,000 25,000 25,000 100,000 Blake Road Corridor Improvements 15-C/P-S001 n/a 1,000,000 9,000,000 10,000,000 2015 Street Overlay Project 15-C/P-SO39 n/a 175,000 175,000 Public Works: Streets/Traffic Total 24,175,000 3,375,000 5,465,000 15,500,000 2,770,000 51,285,000 Public Works: Transportation Light Rail Transit Stations (3) 01-C/P-S502 n/a 500,000 500,000 Eighth Avenue LRT Corridor 01-CIP-S503 n/a 3,700,000 3,700,000 Public Works: Transportation Total 3,700,000 500,000 4,200,000 [Public Works: Utilities Storm Drainage System Maintenance - Alley Repairs 01-C/P-0002 n/a 20,000 21,000 21,000 21,000 22,000 105,000 Storm Water Management Projects 01-CIP-0003 n/a 230,000 230,000 Lift Station # 4 08-CIP--0001 n/a 160,000 160,000 St. Louis Park Emergency Connection 08-CIP--U0f0 n/a 211,000 211,000 Public Works: Utilities Total 250,000 232,000 21,000 21,000 182,000 706,000 Recreation i Depot Recreation Area 10-CIP-RO02 2 225,000 225,000 Recreation Total 225,000 225,000 GRAND TOTAL 36,728,110 12,638,425 6,162,000 16,648,500 3,303,500 75480,535 Thursday. June 05, 2014 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2015 thru 2019 PROJECTS BY FUNDING SOURCE Source Project# Priority 2015 2016 2017 2018 2019 Total IAC - Arts Center Fund 304,010 561,000 415,000 52,000 133,000 1,465,010 Arts Center - Replace Information Desk and Kiosk 12-C/P-AR005 1 5,000 Arts Center - Re -landscape E & W faces of building 13-C/P-AR001 2 3,600 Arts Center- Storage & Hanging, Display Systems 13-CIPAR004 1 3,125 Arts Center - Storage in Art Classroom 14-C/P-AROOI 1 3,500 Arts Center - Kitchen Handwashing Sink 14-CIP-AR002 1 5,000 Arts Center - Entryway Planters 14-C/P-AR005 3 2,800 AC - Arts Center Fund Total 17,100 5,925 ICI - Capital Improvement Fund Activity Center - Replace Gynmasium Roof 08-C/P-AC018 n/a 105,000 Activity Center - Raspberry Room Roof Replacement 08-CIP-ACO24 n/a 80,000 Arts Center - Replace Rooftop HVAC Units 08-CIP-AR013 n/a Public Works - Replace Overhead Doors 08-CIP-BO23 n/a Replace Carpet and Apparatus Floor Finish - FD 08-CIP-FD019 n/a 56,000 Replace Carpet - Police Station 08-CIP-PDO16 n/a 40,000 Activity Center - Lower Roof Replacement 09-CIP-AC031 n/a Art Center - Replace Lobby Carpet 09-CIPAR027 n/a City Hall Roof Replacement 09-CIP-CH029 n/a City Hall Lobby Upgrade 09-CIP-CH030 n/a 110,000 Arts Center - Replace theatre seats and backs 12-CIP-AR002 1 138,510 Public Works Garage Upgrade 13-CIP-BOI f 1 20,000 100,000 Activity Center - Fencing/Landscaping 14-CIPACOOI 1 13,000 Activity Center - Multi Purpose/Gym Improvements 14-CIP-AC002 2 67,000 Activity Center Computer/Library Room Enhancements 14-CIP-AC003 4 20,000 Activity Center - Dishwasher 14-CIP-AC004 5 Arts Center - Paint Theatre 14-CIPAR003 2 15,000 Arts Center - Remodel Administrative Offices 14-CIP-AR004 2 50,000 Wash Bay Roof Replacement 14-CIP-BOOI 4 23,000 Wash Bay Air Handler Replacement 14-CIP-B002 3 15,000 Fuel Management System Upgrade 14-CIP-B003 4 12,500 320,000 18,000 80,000 52,000 115,000 15,000 5,000 3,600 3,125 3,500 5,000 2,800 23,025 105,000 80,000 320,000 18,000 56,000 40,000 80,000 52,000 115,000 110,000 138,510 120,000 13,000 67,000 20,000 15,000 15,000 50,000 23,000 15,000 12,500 Cl - Capital Improvement Fund Total 304,010 561,000 415,000 52,000 133,000 1,465,010 ICT - Cable Franchise Fees Technology Improvement - Council Chambers & Studio 13 CIP-CM001 n/a 35,000 12,500 23,000 15,000 85,500 CT - Cable Franchise Fees Total 35,000 12,500 23,000 15,000 855010 ED - Economic Development Fund Block 64 Redevelopment Project 06-CIP-D404 n/a 1,000,000 11000,000 8th Ave Streetscape and parking facility 12-CIP-D408 n/a 4,000,000 4,000,000 Thursday, June 05, 2014 Source Project# Priority 2015 2016 2017 2018 2019 Total ED - Economic Development Fund Total 1,000,000 4,000,000 5,000,0100 GU - Other Governmental Units County Road 3 01-CIP-S104 n/a 45,000 1,600,000 1,600,000 County Road 61 (Shady Oak Road) 01-CIP-S106 n/a 16,850,000 16,850,000 Eighth Avenue LRT Corridor 01-CIP-S503 n/a 2,300,000 n/a 2,300,000 Depot Recreation Area 10-CIP-RO02 2 125,000 08-CIP-P014 125,000 Mainstreet Rehabilitation 11-CIP-S121 3 660,000 Valley Park - Play Equipment 660,000 Blake Road Corridor Improvements 15-CIP-SOOI n/a 6,000 750,000 8,000,000 8,750,000 GU - Other Governmental Units Total 13-CIP-P321 1 17,635,000 2,300,000 750,000 9,600,000 30,285,000 MS - Municipal State Aid Streets 13-CIP-P322 1 60,000 9,500 9,500 County Road 3 01-CIP-5104 n/a n/a 700,000 700,000 County Road 61 (Shady Oak Road) 01-CIP-S106 n/a 1,000,000 22,000 11000,000 Sixth Street South (11th to 12th Avenue South) 01-CIP-S504 n/a Burnes Park - Play Equipment 400,000 400,000 Mainstreet Rehabilitation 11-CIP-5121 3 1,630,000 93,500 9,500 1,630,000 MS - Municipal State Aid Streets Total 20,000 2,630,000 1,100,000 3,730,000 PA - Pavilion Fluid Pavilion skate Tile Replacement/Lobby Improvement 07-CIP-P313 n/a 45,000 7,000 45,000 Pavilion Overhead Door Improvement 07-CIP-P314 n/a 40,000 40,000 Pavilion Roof Replacement 09-CIP-PO26 1 140,000 n/a 140,000 Pavilion Evaporator Condenser Replacement 09-CIP-PO36 n/a 60,000 08-CIP-P014 60,000 Pavilion Indoor Turf Replacement 10-CIP-P319 n/a 95,000 Valley Park - Play Equipment 95,000 Pavilion - Desiccant Repl of Dehumidification Syst 10-CIP-P320 n/a 6,000 80,000 6,000 Pavilion Mezzanine Rooftop Unit Replacement 13-CIP-P321 1 24,500 24,500 Pavilion HHS Team Room Rooftop Unit Repl 13-CIP-P322 1 60,000 9,500 9,500 Pavilion Entry and Lobby Door Replacement 13-CIP-P324 3 n/a 7,000 7,000 Pavilion - Paint Exterior Building 13-CIP-P325 1 13-CIP-PO42 22,000 22,000 Pavilion Painting the Arena Ceiling and Bar Joist 14-CIP-POIO 1 Burnes Park - Play Equipment 40,000 40,000 PA - Pavilion Fund Total 60,000 275,000 51,000 93,500 9,500 489,000 PDF- Park Dedication Fund Skate Park 08-CIP-P003 n/a 7,000 7,000 7,000 7,000 7,000 35,000 Park Valley - Play Equipment 08-CIP-POIO n/a 60,000 60,000 Burnes Park - Resurface Tennis Courts 08-CIP-POII n/a 20,000 20,000 Hilltop Park - Play Equipment 08-CIP-P014 n/a 100,000 100,000 Valley Park - Play Equipment 08-CIP-P015 n/a 80,000 80,000 Depot Recreation Area 10-CIP-RO02 2 50,000 50,000 Burnes Park - Warming House 13-CIP-PO40 n/a 60,000 60,000 Oakes Park - Replace Picnic Shelter 13-CIP-PO41 n/a 30,000 30,000 Valley Park - Construct Storage Building 13-CIP-PO42 n/a 25,000 25,000 Burnes Park - Play Equipment 13-CIP-PO43 n/a 50,000 50,000 Oakes Park - Tennis Courts 13-CIP-PO44 n/a 20,000 20,000 Valley Park - Warming House 13-CIP-PO45 n/a 60,000 60,000 Burnes Park - Lighting 13-CIP-PO46 n/a 50,000 50,000 Cottageville Park - Phase II Improvements 13-CIP-PO54 n/a 250,000 250,000 Harley Hopkins Park - Warming House 13-CIP-PO56 n/a 30,000 30,000 Harley Hopkins Park - Lighting 13-CIP-PO57 n/a 50,000 50,000 Thursdav, June 05, 2014 Source Protect# Priority 2015 2016 2017 2018 2019 Total Oakes Park - Lighting 13-CIP-PO72 n/a 40,000 40,000 Rehab Downtown Park 14-CIP-POOI n/a 70,000 70,000 Burnes Park Splash Pad 14-C/P-P002 n/a 300,000 300,000 PDF- Park Dedication Fund Total 212,000 377,000 187,000 467,000 137,000 1,380,000 IPF - Private Sector Funds Depot Recreation Area 10-CIP--RO02 2 50,000 50,000 PF - Private Sector Funds Total 50,000 50,000 IPI - PIR/General Obligation Bonds Residential Street Improvements and Utilities 01-C/P-S101 n/a 1,500,000 2,500,000 1,500,000 1,500,000 7,000,000 Citywide Concrete Alleys 01-C/P-S103 n/a 15,000 16,000 31,000 County Road 61 (Shady Oak Road) 01-CIP-S106 n/a 700,000 700,000 Sixth Street South (11th to 12th Avenue South) 01-C1P-S504 n/a 100,000 100,000 Parking Lots and HCRRA Alley Improvements 06-C/P-S118 n/a 930,000 930,000 Plan, Design and Implement Railroad Quiet Zone 11-C/P-S120 n/a 25,000 200,000 225,000 Mainstreet Rehabilitation 11-C/P-S121 3 1,400,000 1,400,000 Pedestrian & Bicycle Access Improvements 13-C/P-SO40 n/a 25,000 25,000 25,000 25,000 100,000 Blake Road Corridor Improvements 15-C/P-SOOI n/a 250,000 600;000 850,000 2015 Street Overlay Project 15-C/P-SO39 n/a 175,000 175,000 PI - PIR/General Obligation Bonds Total 3,255,000 1,540,000 2,791,000 2,425,000 1,500,000 11,511,000 IRF - Refuse Fund Public Works - Replace Overhead Doors 08-C/P-BO23 n/a 18,000 18,000 Public Works Garage Upgrade 13-C/P-BOII 1 25,000 25,000 RF - Refuse Fund Total 25,000 18,000 43,000 ISA - Special Assessment Residential Street Improvements and Utilities 01-C/P-S101 n/a 1,000,000 1,000,000 750,000 750,000 3,500,000 Citywide Concrete Alleys 01-C/P-S103 n/a 60,000 64,000 124,000 County Road 61 (Shady Oak Road) 01-CIP-5106 n/a 250,000 250,000 Mainstreet Rehabilitation 11-CIP-S121 3 60,000 60,000 SA - Special Assessment Total 310,000 1,060,000 1,064,000 750,000 750,000 3,934,000 ISF - Sanitary Sewer Fund Residential Street Improvements and Utilities 01-C/P-S101 nla 175,000 240,000 325,000 120,000 860,000 Eighth Avenue LRT Corridor 01-CIP--S503 n/a 100,000 100,000 Public Works - Replace Overhead Doors 08-C/P-BO23 n/a 18,000 18,000 Lift Station # 4 08-CIP-0001 n/a 160,000 160,000 Public Works Garage Upgrade 13-C/P-BOII 1 25,000 25,000 Blake Road Corridor Improvements 15-C/P-5001 n/a 150,000 150,000 SF - Sanitary Sewer Fund Total 300,000 240,000 475,000 298,000 1,313,000 SU - Storm Sewer Fund Residential Street Improvements and Utilities 01-C/P-5101 n/a 200,000 220,000 300,000 150,000 870,000 Eighth Avenue LRT Corridor 01-CIP-S503 n/a 150,000 150,000 Thursdur, June 05. 2014 Source Project# Priority 2015 2016 2017 2018 2019 Total Storm Drainage System Maintenance - Alley Repairs 01-C/P-0002 n/a 20,000 21,000 21,000 21,000 22,000 105,000 Storm Water Management Projects 01-CIP-0003 n/a 230,000 230,000 Parking Lots and HCRRA Alley Improvements 06-C/P-5118 n/a 220,000 220,000 Public Works - Replace Overhead Doors 08-C/P-8023 n/a 18,000 18,000 Public Works Garage Upgrade 13-C/P-BOI1 1 25,000 25,000 SU - Storm Sewer Fund Total 470,000 396,000 241,000 321,000 190,000 1,618,000 ITF - Tax Increment Financing [I Redevelopment, East Excelsior Boulevard 01-C/P-D4010 n/a 2,000,000 2,000,000 Light Rail Transit Stations (3) 01-C/P-S502 n/a 500,000 500,000 Eighth Avenue LRT Corridor 01-CIP-S503 n/a 1,000,000 11000,000 Block 64 Redevelopment Project 06-C/P-D404 n/a 3,500,000 3,500,000 Blake Corridor Redevelopment 09-C/P-D406 n/a 5,000,000 5,000,000 TF - Tax Increment Financing Total 10,500,000 1,000,000 500,000 12,000,000 N - Water Fund Residential Street Improvements and Utilities 01-C/P-5101 n/a 400,000 400,000 600,000 250,000 1,650,000 Eighth Avenue LRT Corridor 01-CIP-S503 n/a 150,000 150,000 Public Works - Replace Overhead Doors 08-C/P-BO23 n/a 18,000 18,000 St. Louis Park Emergency Connection 08-CIP-UOIO n/a 211,000 211,000 Mainstreet Rehabilitation 11-C/P-S121 3 250,000 150,000 Public Works Garage Upgrade 13-C/P-BOII 1 25,000 25,000 Blake Road Corridor Improvements 15-C/P-SOOI n/a 250,000 250,000 WF - Water Fund Total 250,000 786,000 400,000 850,000 268,000 2,554,000 GRAND TOTAL 36,728,110 12,638,425 6,162,000 16,648,500 3,303,500 75,480,535 Thu sdm. June 05, 2014