IV.7. Subordinate Funding Agreement 01 – Southwest LRT; Elverum (CR2015-064)
Reference Numbers:
SWLRT Project: 61001
Metropolitan Council: 14I059A
City of Hopkins: ___________
PROJECT: SOUTHWEST LIGHT RAIL TRANSIT PROJECT
MASTER AGREEMENT: Master Funding Agreement City of Hopkins
PARTIES TO AGREEMENT:
Metropolitan Council (ncil
City of Hopkins City
SUBORDINATE FUNDING AGREEMENT
th
City of Hopkins - SFA 01 (Water & Sanitary Sewer under 17 Ave)
This Subordinate Funding Agreement with the City of Hopkins-01 is entered into by and
between the above named Parties.
WHEREAS:
1.The Parties entered into a Southwest Light Rail Transit Project (Project) Master Funding
Agreement , effective April 1, 2015.
2.The Parties provided in the MFA that certain aspects of funding for the Project or components
related to but not part of the Project would be determined in subsequent SFAs.
3.The Parties desire to enter into this SFA to transfer City funds to reimburse the cost for Council
activities for professional services to produce design plans,
complete required federal, state, and local environmental documentation, and prepare a
construction cost estimate for proposed components related to, but not part of the Project.
4.The Parties acknowledge that the planning of the Project will require numerous federal, state and
local processes, approvals and funding commitments. The environmental review and other
processes for the Project are ongoing and the Project is subject to change to address those
processes. The outcomes of those processes may affect whether the components requested in
this SFA will ultimately be constructed.
NOW, THEREFORE,
in reliance on the statements in these recitals, the Parties hereby agree as
:
follows
Maximum Amount of Authorized Funding.
1.
and administration activities authorized by this SFA shall not exceed $14,730 unless authorized
in a subsequent agreement or an amendment to this SFA. The Maximum Amount of Authorized
Funding is subject to amendment based on, but not limited to, additional environmental
documentation, as determined necessary.
SFA Budget.
2.The budget for the activities described in this SFA is provided as
Exhibit A. City funds provided for this SFA may only be
costs for activities directly incurred within the described Description of Activities and as detailed
in the MFA.
Description of Activities.
3.The activities to be performed by the Council and reimbursed by the
City include the development of design plans, completing required federal, state, and local
environmental documentation, and a construction cost estimate for installation of a water main
th
and sanitary sewer generally located under 17 Avenue starting from Excelsior Boulevard then
southward to the second roundabout, and installation of a water main from the roundabout
heading east to the limits of the Metro Transit Park and Ride site to an existing main in the City
If authorized by the City, the Utilities are anticipated to be constructed by the
Project.
The Council will incorporate the Utilities design plans as a bid alternate in the proposed Project
construction bid documents if: a) the environmental review of the Project and the components
described in this SFA allow the construction of the Utilities; and b) the Project is permitted to
proceed to construction. The Utilities construction specifications will be incorporated in the
overall specifications within the Project construction bid documents. No separate or stand alone
specifications for the Utilities design plans will be created.
After the Council selects a Project construction bid and the bid alternate is public, the City will
determine whether or not to accept the bid alternate. If the City chooses to accept the bid
alternate, the City is required to enter into a subsequent SFA authorizing the Council to construct
the bid alternate and reimburse the Council costs.
Environmental Documentation
4.. The
lead federal agency
Council is the Responsible Governmental Unit under the Minnesota Environmental Policy Act of
the Project, including the components described in this SFA proposed to be constructed as part
of the ProjectNotwithstanding any contrary language in the MFA or this SFA, the disclosure of
͵
draft environmental documents are subject to the Minnesota Government Data Practices Act,
Minn. Statutes, Chapter 13, and applicable federal law and the Council in its sole discretion shall
determine when such documents can or will be shared with the City.
Release of Design Plans.
5.If the City does not enter into an SFA with the Council to construct
the Utilities along with the construction of the Project, but requests the Council to release the
Utility design plans to the City for the purpose of current or future use of the plans, the Council
shall release the design plans provided an amendment to this SFA or subsequent agreement is
executed by the Parties to address indemnification, liability, claims, access, copyright, and
related issues as a result of the release of the Utilities design plans.
Property Acquisition.
6. If it is necessary to acquire property rights for the Utilities, subsequent
agreements must address property access, acquisition, disposition, and other real property
matters needed to construct the Utilities beyond what is required to construct the Project.
Page 2 of 4
Project Activity Periods.
7. The term of this SFA shall be effective as of April 1, 2015 and shall
terminate on the date all costs under this SFA have been reimbursed, unless terminated earlier by
the Council consistent with the terms of the MFA. Notwithstanding the terms of this SFA or the
MFA, the City agrees that it shall not terminate this SFA prior to the issuance of a Record of
After issuance of the ROD, the City may terminate this SFA as
provided in the MFA.
No Guarantee of Construction.
8.This SFA describes terms requiring the City to reimburse the
Utilities. It does not guarantee
that the Utilities will satisfy environmental review or be constructed.The City and the Council
acknowledge that nothing in this Agreement shall require the Council to take any action or make
any decision that will prejudice or compromise any review or decision-making processes
required under state and federal environmental review laws, regulations or rules. The Parties
intend this Agreement to be interpreted consistent with statutory and other legal authorities,
including but not limited to the MEPA and the NEPA. The Parties agree that this SFA does not
limit the alternatives or mitigative measures that the Council may undertake in the development
and construction of the Project. The Council retains the right to make decisions and necessary
approvals associated with Project requirements.
Incorporation.
9.The terms, conditions, and definitions of the MFA are expressly incorporated
into this SFA.
METROPOLITAN COUNCIL
CITY OF HOPKINS
By: By:
Its: Its:
Date: Date:
By:
Its:
Date:
Page 3 of 4
Exhibit A
th
SFA Budget - Water and Sanitary Sewer Under 17 Avenue
Item Cost
Professional Services
Design Cost $10,000
1
Environmental Documentation Cost 4,301
Professional Services Subtotal $14,301
Administrative Fee (3% of Professional Services) 429
$14,730
Maximum Amount of Authorized Funding
1
Additional environmental documentation (e.g., cultural resources survey, contaminated property
investigation, etc.) may be required and authorized in a subsequent agreement or amending this SFA, as
determined necessary.
Page 4 of 4