Joint Work Session Packet - Hopkins & Minnetonka City Councils and Planning CommissionsJoint Work Session
Hopkins & Minnetonka City Councils
September 21, 2015
6 pm -Light dinner provided
6:30 pm -Meeting starts
Meeting Location –Minnetonka Community Center
14600 Minnetonka Blvd, Minnetonka MN
Dinner & Meeting—Community Room
Call to order–Mayor Maxwell
1.
Introductions/Purpose of Meeting –Mayor Schneider
2.
Shady Oak Road Update –Nate and Will
3.
Update regarding the SWLRT project –Mayor Schneider
4.
Recap of Shady Oak Station Study –Meg and Elise
5.
Vision, Development Strategy and Zoning overview –Consultant
6.
Q & A
7.
Small Group Discussion
8.
Report Back –Consultant
9.
Plaza update –Consultant
10.
Next Steps –Kersten and Julie
11.
•Zoning Code
•Phasing
•Future schedule
•Estimated completion
Hopkins & Minnetonka Study Session
Meeting of September 21, 2015
Brief Description:
Shady Oak Road and Shady Oak LRT Station Area update
Background
The city councilsof Minnetonka and Hopkins last met on January 27, 2015, for an
update on the Shady Oak Road project and to begin formulation of a development
strategyfor Shady Oak Station on the SouthwestLRT line.Minutes from this meeting
can be found on pages A1-A5.This study session is a follow up to that discussion
providing updates on both projects.
Shady Oak Road update
Construction is still underway along the entirety of the Shady Oak Road project corridor.
The contractor has been granted an extension from the original project deadline by
Hennepin County and the project is currently scheduledto be completed this fallwith
the exception of landscaping.
Excelsior Boulevard to Mainstreet
Work along the northbound lanes and adjacent boulevard between Excelsior Boulevard
to south of Mainstreet has been substantially completed. Utility work across the
roadway was completed earlier this summer and the contractor is currently working on
reconstructing the southbound lanes along this stretch of roadway.
Mainstreet to Lake Street
Sewer and water main work hasbeen completed between Mainstreet and Lake Street.
Concrete curb and base course paving hasbeen completed along the northbound and
southbound lanes;however,the median curbing has not yet been completed. The
multiuse trail on the east side of Shady Oak Roadhas been installed and the slope
along the “Duck Pond”has been stabilized. The contractor has tentatively scheduled
concrete sidewalk installation to begin on the east side of Shady Oak Roadin
September.Construction along Oak Drive Lane North and Oak Drive Lane South has
been substantially completed.
Lake Street to Trunk Highway (TH) 7
Concrete curb and gutter and base course paving along the new alignment of Shady
Oak Road from Lake Street to TH 7 has been completed. Construction along Lake
Meeting of September 21, 2015Page 2
Subject: Shady Oak LRT station area
Street and the new cul-de-sacto the northwill begin after traffic is shifted to the new
alignment of Shady Oak Road. This work is tentatively scheduled to begin in October.
The contractor has scheduled construction of the retaining wall along the west side of
the Wyndam Hills neighborhood to be completed in the upcoming weeks.
North of Trunk Highway 7
Installation of the new traffic signals and power feeds have begun at TH 7 and work
continues along the north shoulder. The contractor has tentatively scheduled paving of
the right turn lane and shoulder to be completed in September. Work in the center
median is scheduled to proceed after the turn lane and shoulder are completed to allow
for traffic shifts as necessaryon TH 7.
Construction activity north of TH 7 along Shady Oak Road continues. The contractor
has tentatively scheduled installation ofthe remaining concrete retaining wall along the
new alignment of the North Service Drive to begin in early September. It is anticipated
the remaining retaining wall construction will take 6 to 8 weeks to complete. Once the
retaining wall is completed, restoration of the roadway will proceed.The county has
indicated Shady Oak Road will reopen in October.
Utility Burial
Private utility work continues throughout the corridor. Removal of overhead utility lines is
tentatively scheduled to begin in late September. Prior to removal of the poles all utility
lines must be buried and activated.
Hennepin County Community Works
The Hennepin County Community Works project to reconstruct the Hopkins VFW
parking lot and construct a new parking lot for Syndicate Saleswas bid earlier this
summer; however,the bids received were rejected due to the extremely high prices for
the work. The city of Hopkins is currently working on rebidding the Syndicate Sales
parking lot portion this fall. The VFW parking work will be rebid later this year and is
scheduled to be completed in the summer of 2016.
Landscaping
The cities of Minnetonka and Hopkins will partner to complete a landscaping project
along Shady Oak Road after final completion of construction. Plans for the landscaping
project will be developed and bid this winter.A neighborhood meeting will be held this
fall/winter to take feedback from area residents on the proposed plan prior to bidding.
Meeting of September 21, 2015Page 3
Subject: Shady Oak LRT station area
Shady Oak Station Area Development Strategy
Background
The citiesof Hopkins and
Minnetonka are working
together on a joint development
strategy for the Shady Oak
Station area(as shown to the
right). The station area
development strategy builds
upon previous planning efforts
and formulatesan articulated
station area vision, zoning to
support the vision, and an
implementation strategy that can
be approved by both cities.
The development strategy
includesa master plan for the station area, and review of both city’sexisting zoning and
entitlement processes with a goal ofremoving barriers to the redevelopment process.
The main objectiveof the work has beento develop a master plan and zoning district
that is buildable, station-specific, shared by the two communities, transit-oriented and
supports sustainable development. Part of the development strategy work also studied
remnant parcels remaining afterthe light rail project construction and provides
recommendations for how to best take advantage of the opportunity the remnant
parcels create.The firm Crandall Arambulaof Portland, Oregon, was hired to lead the
cities through this process.Crandall Arambula is an urban design, planning and
architecture firm that has completed over 50 station area/Transit Oriented Development
(TOD) studies throughout the country.
Development Strategy Update
Crandall Arambulafirst began byanalyzingthe station area and the design plans that
had been completed through previous studies and the SouthwestProject Office.They
shared their initial recommendations at a public open houseon May 6, 2015, and
through a one on one opportunity for city council and planning commission members
the following day(their presentation can be found hereand comments from the open
house can be found here).
Since this time, city staff and consultants from Crandall Arambula have been working to
help establish a cohesive vision for the Shady Oak Station and recommend zoning to
support it.Key pieces of the vision include:
Meeting of September 21, 2015Page 4
Subject: Shady Oak LRT station area
th
Redesignedthe 17Avenue extension. As a result, the round-a-bouts were
eliminated and a protected bikeway was added. The idea is that this will
become the signature street of the area drawing redevelopment, the public to a
plaza area, and providing safe opportunities for pedestrians and bikers.
Key development sites were identified that will provide a hub of activity and eyes
on the station, which is critical for future redevelopment and safety at the station
area.
A series of secondary streets throughout the station area were created. The
location of these streets allows redevelopment to occur over time and without
having to take out buildings as they are located along property lines.
The Shady Oak Station area will be envisioned to become an office and innovation
area. The majority of the land uses envisioned are for office spaces. There is some
residential near the station itself as well as a very small amount of retail.
Status of Southwest LRT at the Shady Oak Station
From late Aprilto early Julythe entire Southwest LRT project went through a significant
cost-reduction process. Changes that were made to the Shady Oak Station as a part of
this process wereinformed by the work of Crandall Arambula. The changes made to
the station as a result are as follows:
The platform and alignment were modified to bring the platform out from behind
storage units, making it more visible. This change resulted in a cost savings of
approximately $1.5million.
The park and ride was enlarged from 400 spaces to 700 spaces to make up for
reduced parking at other stations. A portion of these are temporary.
The remnant parcels were reconfigured to accommodate additional parking while
still meeting the goal of an active station area.
Changes in design occurred at most of the station areas along the line, resulting in the
need for municipal consent. Municipal consent hearings and approval actions were
scheduled to take place in Minnetonka on September 14, 2015and in Hopkins on
September 15, 2015.
Crandall Arambula Presentation
Representatives from Crandall Arambula will be at the joint meeting to present their
work to date including:
Land use framework that allows for transition to a Transit Oriented District
Meeting of September 21, 2015Page 5
Subject: Shady Oak LRT station area
Concept for a phased street grid
Circulation recommendations
Opportunities for development
Zoning sub districts
Entitlement process
A draft of thevision portion reportcan be found on pages A6-A66.This will be the basis
for the consultant’s presentation on September 21.The zoning section will be finalized
upon discussion from this meeting.
Next Steps
A public open house is scheduled for October 7, 2015, at the Hopkins Fire Station. It is
anticipated that once the final report is complete, adoption of a sharedvision andzoning
code will be brought forward in late 2015 or early 2016.
Additionally, Crandall Arambula has be retained to develop a concept for the plaza area
located at the station area. This work will be completed by the end of the year.
Discussion Questions
Do the city councils and planning commissionsgenerallyagree on the land use
and vision that has been developed for the Shady Oak Station area?
Do the city councils and planning commissions wish to provide feedback on the
proposed zoning?
Is there any additional direction the city councils and planning commissions want
to provide staff and the consultants prior to the final report and open house
(example: roadways, entitlement process, development opportunities)?
Submitted through:
Geralyn Barone,Minnetonka City Manager
Michael Mornson, Hopkins City Manager
Originated by:
Nate Stanley, PE, Hopkins City Engineer
Will Manchester, PE, Minnetonka Director of Engineering
Kersten Elverum, Hopkins Director of Economic Development & Planning
Julie Wischnack, AICP, Minnetonka Community Development Director
Meg Beekman, AICP, Hopkins Community Development Coordinator
Elise Durbin, AICP, Minnetonka Community Development Supervisor
CITY OF HOPKINS AND CITY OF MINNETONKA
SPECIAL JOINT CITY COUNCIL WORK SESSION
TUESDAY, JANUARY 27, 2015
Hopkins Council Present:
Molly Cummings, Jason Gadd, Kristi Halverson,
Aaron Kuznia, and Mayor Gene Maxwell
Minnetonka Council Present:
Patty Acomb, Tim Bergstedt, Bob Ellingson, Tony
Wagner, Brad Wiersum, and Mayor Terry Schneider.
Dick Allendorfwasexcused
Hopkins Staff:
City Manager Mike Mornson, Director of Economic
Development and Planning Kersten Elverum,
CommunityDevelopment Coordinator Meg Beekman,
Public Works Director Steve Stadler, City Engineer
Nate Stanley
Minnetonka Staff:
City Manager Geralyn Barone, Asst. City Manager
Perry Vetter, Director of Engineering Lee Gustafson,
Community DevelopmentCoordinatorElise Durbin,
City Attorney Corrine Heine
Southwest LRT Project Office:
Sarah Ghandour, Kathryn Hansen, Kim Koempel,
Michael Krantz, Ryan Kronzer, Craig Lamothe, Dan
Pfeiffer, Tats Tanaka
Mayor Maxwell called the meeting to order at 6:30p.m. at the Hopkins Fire Department.
Mayor Maxwell welcomed the City of Minnetonka staff and Council as both communities
look at the bigger vision and work on a plan for both communities.
Mr. Mornson and Ms. Barone gave an overview of the Joint Work Sessionagenda. The
two cities have met periodically to discuss matters affecting both communities. The
purpose of the Joint Work Session is to provide updates to Council Members
regarding Shady Oak Road construction and Southwest Light Rail Transit planning.
Shady Oak Road Update
a.Road Project
Mr. Gustafson and Mr. Stadlerdiscussed the Shady Oak Road construction project.
The project schedule has experienced delays due to weather but Hennepin County
has commented that they believe thatsubstantial progress can be made to complete
most of the project by this fall except for landscaping. Landscape planning is
scheduled for late this year with completion next spring.
Council MemberAcomb discussed a concern that the “No Blocking Intersection”
signage at the Frontage Roadhas been removed causing traffic congestion. Mr.
Gustafson will investigate reinstalling the signage. Mr. Gustafson commented that
the Frontage Road will be closed permanently next spring.
1
A1Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
CITY OF HOPKINS AND CITY OF MINNETONKA
SPECIAL JOINT CITY COUNCIL WORK SESSION
TUESDAY, JANUARY 27, 2015
b.Redevelopment Activities
Ms. Elverum gave an overview of the Hennepin County Community Works Grant
and what was accomplished with the funds.Ms. Elverum explained the construction
and relocation activitiesalong Shady Oak Road. Ms. Elverum commented there
have been veryfew public calls regarding the project.
Council Member Wiersum asked about the outlook of the business owners during
the redevelopment process. Ms. Elverum commented that they are continuing to
work with the businessesand address their concerns.
Mayor Schneiderquestioned the landscaping and streetscapingdesign. Ms.
Elverum gave an overview of thedesign elements, upgrades to signage and parking
lot designs.
Mayor Maxwell commented thatmany of the businesses affected by the project
relocated into Hopkins. Mayor Maxwell also commented that staff worked hard to
ensure that Minnetonkaresidentswere buffered from the backsofbuildings.Ms.
Elverum commentedon the improvements to thebacksideof buildings and alley.
Ms. Barone gave an update on the Ring Property acquisition. The closing on the
property will be in the next 3-4 weeks. Following the closing, the city will begin a
neighborhood processto determine site redevelopment. Ms. Barone commented
that construction would not begin until approximately August, 2017.
Mayor Maxwellasked if the building willcontinue tobe leased. Ms. Barone
commented that new tenants will not be sought and the building would eventually be
vacant. Mayor Schneidercommented that the public input process should include
Hopkins residents. Mayor Maxwell asked about the adjoining Johnson property. Staff
willinvestigatethe status of the vacant lot located in Hopkins.
Update on Southwest Light Rail Transit (SW LRT)
a.Shady Oak Station area
Ms. Beekman gave an overview of the Shady Oak Station areadevelopment
strategy, a joint effortby the two cities that will be partly funded by a grant fromthe
Met Council. Ms. Beekman discussed the main components of the work including
market feasibility, vision and land use scenarios, zoning, public investment
component, entitlementreview processes for both citiesand thepublic engagement
process. Ms. Beekman explained the goalsare to balance housing, retail and job
growth, develop a model for sustainable redevelopment, andcreate astreet design
anddesign guidelines.Ms. Durbin gave an overviewof Crandall Arambula, a
nationalconsultantfirmwith local sub-consultants. Ms. Durbin reviewed the
development strategy schedule and tasks that the consultants would be addressing.
Ms. Durbin explained the next steps in the process including negotiatingthefinal
2
A2Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
CITY OF HOPKINS AND CITY OF MINNETONKA
SPECIAL JOINT CITY COUNCIL WORK SESSION
TUESDAY, JANUARY 27, 2015
contract, project kick-off, land use scenarios and public input process. Staff will keep
the Councils updated on the process.
Council Member Wagner asked about the development guidelines. Ms. Durbin
commented that both staffsare working together on the zoning code. Ms. Elverum
commented that it is important not to duplicatework that has already been doneand
to concentrate onthe right mix of usesfor the area, street grid, existing businesses
and how to transitionthe area. Mayor Schneiderasked about the parking lot. Ms.
Elverum commented that they are looking at remnant parcels. Mayor Maxwellasked
about the experience of the consultant company.Ms. Durbinand Ms. Beekman gave
anoverview of the company’s experience with station area planning and level of
experience. Ms.Baroneasked for an explanation regarding the entitlement review
process.Ms. Beekman explained that the process bybothHopkins and Minnetonka
will ensure coordination of the project area vision and zoning.
b.Station Design
Representatives fromthe Southwest Light Rail Transit (SW LRT) Project Office
gave an overview of the project and development timeline with passenger operations
scheduled for 2019. The SWLRT staff gave an overview of the public involvement
processand scheduledpublic open houses and events for 2015. The open houses
will be combined for Station and Operations & Maintenance Facility (OMF) design
and will be located in the Hopkins/Minnetonkaarea. SW LRT staff explained the
Station Design Approachthat identified 4 station types: Landscape, Neighborhood,
Town Square and Landmark. Staff gave an overview of the station structures,
materials and colors.SW LRT staff reviewed the suggested station types in Hopkins
and Minnetonka.
Opus Station: Landscape or Town Square Station
Shady Oak Station: Landmark station
Downtown Hopkins Station: Town Square Station
Blake Station: Neighborhood Station
Staff explained the next steps for the stationdesignprocess including making station
prototype adjustments based on city staff input and public open houses. Staff
explainedthe public artprocess that will be used to enhance the unique identity of
the stations as well as enhance the OMF.
Mayor Schneider commentedthat the station emphasis should be on weather
protection and comfort of the riders, a suggestion that has been strongly mentioned
at public meetings.The Project Officestaffcommentedthat there will be wind flow
analysis around the stations and will refine station designs if necessary.
Mayor Maxwellasked about the durability of the art. The Project Office staff
commented that the art materials will bedesigned for long term durability.
Council Member Cummingsasked about the number of artist proposals. The Project
Office received 10proposals.
3
A3Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
CITY OF HOPKINS AND CITY OF MINNETONKA
SPECIAL JOINT CITY COUNCIL WORK SESSION
TUESDAY, JANUARY 27, 2015
c.OMF update
The Project Office staff gave an overview of the OMF design, layout and building
materials under consideration.
Mr. Mornsonasked about property negotiations. The Project Office began meeting
last week with property owners to acquirebackground information and will begin
appraisalsthis summer.Property acquisition and therelocation process will take
place after theProject Office receives the Record of Decision.
Council Member Cummingsasked whentheacquired properties come off the tax
rolls. The Project Office staff commented when the property fee title is secured.
Council Member Gaddasked about the number of trains crossing K-TelDrive at the
OMF. The Project Office staff explained that trains leave in the morning and return in
the eveningand will be inservice all day.Drivers transfer shifts at the Shady Oak
Station.
Mayor Maxwellcommented that it is important to have an enhanced OMF design for
ongoingredevelopment of the area.
d.Funding Update
Mayor Schneider gave an overview of the funding updateand the Locally Requested
Capital Investments (LRCI).
Mr. Mornsonasked about Federal Government funding. The Project Office
commented that they are expecting to get wordsoonfrom the Federal Transit
Administrationregarding the project rating.
Council Member Wagnerasked about the formularanking for communities. The
Project Office explained that new rulesstate if communities provide 51% of a local
matchthey will bump up one ranking.
Council Member Gaddcommentedon the narrowing to 14 eligible contingencies
(LRCI) and noted cities willneed to make the final decision to fund the contingencies
completely. The Project Office commented that the decision timeto fund the LRCI’s
will bein early 2016.
Mayor Maxwellasked what citiescan do regarding the negative commentsabout the
SW LRTproject. The Project Office commentedwe need to continue to have
constructive dialog and that the Project Office iscontinuing to work with the
Minneapolis Park Board and the pending neighborhood lawsuit.
e.Other SWLRT update
Mr. Stadler gave an overview of the Locally Requested Capital Investments (LRCI)
4
A4Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
CITY OF HOPKINS AND CITY OF MINNETONKA
SPECIAL JOINT CITY COUNCIL WORK SESSION
TUESDAY, JANUARY 27, 2015
and the funding criteria. Mr. Stadler gave an overview of the LRCI’s in Hopkins and
Minnetonka that met the criteria.
Mayor Maxwellasked if the requests can be presented again. Mr. Stadler
commented thatthe deadline ispast. The Project Office commented onthe criteria
to evaluate requestswasto reduce operating costsand increase ridership.
Other:
Council Member Gadd commented that cities need to make suretheyconsistently have
a positive message how the SW LRT will benefit the areaand encourage businesses
and residentswho see the benefit to keep that message out there.
Mayor Schneidercommented that businesses need the transportationasset to continue
to draw a talented work forceand that transit is critical to long term growth.
Council Member Wagnercommented that we need to engagethe business community
andappeal to those who will benefit from the project.
Council Member Wiersumcommented that City Councils need to continue to talk to
businesses, community leaders and residents.
Mayor Maxwell thanked City of Minnetonka for working together with Hopkins on a
common ground, vision for our area and maintaining the quality of life for our residents
and businesses.
The Work Session adjourned at 8:25 p.m.
Respectfully Submitted,
Debbie Vold
5
A5Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
SHADY OAK STATION AREA
DEVELOPMENT STRATEGY
Cities of Hopkins & Minnetonka
DISCUSSION DRAFT SEPTEMBER 2015
A6Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
A7Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
TABLE OF CONTENTS
INTRODUCTION
Purpose ..........................................................................................................2
Background ....................................................................................................2
Process ...........................................................................................................5
VISION
Overview ........................................................................................................8
Fundamental Concept ................................................................................10
Build-Out ......................................................................................................12
Land Use Framework ...................................................................................16
Circulation Framework ...............................................................................26
Project Phasing ............................................................................................53
ZONING (PROVIDED UNDER SEPARATE COVER)
Shady Oak Station Zoning .........................................................................XX
Purpose ........................................................................................................XX
General Requirements ...............................................................................XX
Zoning Districts ...........................................................................................XX
Use Regulations...........................................................................................XX
Development Standards ............................................................................XX
A8Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
A9Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
INTRODUCTION
A10Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
PURPOSE
All Shady Oak Station facilities will be located within the city of Hopkins; however,
The purpose of the project is to create a development strategy for the
the half-mile station area and 10 ¬minute walk shed encompasses both Hopkins
Shady Oak LRT station area along the Southwest Light-Rail Transit (SW LRT)
and Minnetonka. The Shady Oak station is anticipated to serve local businesses
Extension, located in the cities of Hopkins and Minnetonka.
and residents to the north of Excelsior Boulevard and west of Shady Oak Road,
as well as Hopkins Westbrooke neighborhood to the southeast of the station.
It builds upon previous planning work and formulates an articulated vision, zoning
and implementation strategy that can be approved by both cities. The main
The station platform will be built along the existing Minnesota River Bluffs LRT
components of the strategy include:
Regional Trail, which is operated by the Three Rivers Park District. The trail property
1. Development of vision and land use scenarios based upon previous
is owned by the Hennepin County Regional Rail Authority, which will continue
planning work and the emerging concept of an Innovation District
to own the property once the SW LRT line is built. The station will be located
employment emphasis
approximately one quarter mile east of Shady Oak Road along the bicycle trail.
2. D
There is currently no public access as it is today to the site beyond that provided
and supports sustainable development;
by the trail.
3.
4. Project phasing and entitlement review to ensure coordination across
city boundaries
BACKGROUND
RoyalstonStation
TargetField
VanWhiteStation
Station
The cities of Minnetonka and Hopkins, aside from sharing a municipal boundary,
394
are quite different in residential and commercial character. The city of Hopkins is a
PennStation
four-square mile city of 17,591 residents just three miles west of Minneapolis. The
21stStreetStation
ST.LOUISPARK
city was incorporated in 1893, and continues to have a vibrant Mainstreet. The city
BeltlineStation
of Minnetonka, incorporated in 1956, is located directly west of Hopkins, and has
ark
P
oho WestLakeStation
StLc
ig
H
isol
u
S
169 h
a population of 50,841. The city is fully developed, and has a strong employment
LouisianaStation
HOPKINS
base of over 47,000 people.
WooddaleStation
MINNEAPOLIS
7
There is a good working relationship between the two cities and experience
BlakeStation
ShadyOakStation
DowntownHopkinsStation
working together on projects. The cities, along with Hennepin County, have
EDINA
successfully collaborated previously on two earlier studies of the station area
including a high level visioning plan and a plan that provides infrastructure
MINNETONKA
OpusStation
recommendations for SW LRT opening day and long-term improvements.
CityWestStation
012
62
Miles
EDENPRAIRIE
The Shady Oak LRT station is one of 15 stations on the 14.5-mile SW LRT Extension,
which will connect downtown St. Paul and Minneapolis to the southwest suburbs.
LRTRoute
GoldenTriangleStation
494
Opening day of passenger service for the SW LRT Extension is anticipated in 2020.
LRTStation
SouthwestStation
Heavy construction of the line is scheduled to begin in 2017.
LRTStation(deferred)
5
OperationsandMaintenanceFacilitysite
Shady Oak Station will be located at the bend of the Southwest Light Rail (SW
EdenPrairieTownCenterStation
LRT) line where the tracks change from north- and southbound to east- and
westbound, at the border of Hopkins and Minnetonka.
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A11Shady Oak Road & LRT update
INTRODUCTION
2
September 21, 2015 Jt Study Session
STUDY AREA
Cities Boundary
Study Area Parcels
SW LRT Total Property Acquisition
SW LRT Partial Property Acquisition
SW LRT - Shady Oak Station
SW LRT Alignment
EIGHTH MILEQUARTER MILEHALF MILE
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
06601,3202,640
A12Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
3
September 21, 2015 Jt Study Session
The station area is served by good regional motor vehicle access via Shady
Oak Road and Excelsior Boulevard. The intersection of Shady Oak Road and
Excelsior Boulevard has been improved recently to deal with congestion and
16200
ExcelsiorBlvd
d
Road is a four-lane, divided roadway to the south of Excelsior Boulevard, and
ExcelsiorBlv
vd
ExcelsiorBl
is being upgraded north of Excelsior Boulevard. It runs north-south and links
m
ajor connector highways such as Highway 62 to the south, and Highway 7 and
Minnetonka Boulevard to the north. Excelsior Boulevard is a four-lane divided
roadway that runs east-west from Hopkins through Minnetonka. It connects with
Highways 169 and 100 to the east of Hopkins.
The LRT project will purchase the 15 acre Hopkins Tech Center parcel near the
platform to construct a new north-south roadway extension of 17th Avenue
tW
47thS
South to access the platform as well as to accommodate a 700 space park and
nLn
Kare
ShadyOakStation
^_
ride facility. To provide access from the south, the City of Minnetonka will fund a
3450
roadway extension of 17th Avenue South from the platform across the Minnesota
5th
StS
River Bluffs Trail to K-Tel Drive. Also purchased and designed for the station area
is the 20 acre SW LRT Extension Operation and Maintenance Facility (OMF) south
of Fifth Street South.
The station area site is currently dominated by uses that are not transit-supportive,
however because of the building age, use of the properties, and location, this
6th
StS
area has seen interest in redevelopment for Transit-Oriented Development (TOD).
Redevelopment however faces many challenges, including:
Numerous property owners, parcel sizes many without current auto access
and as a result are land locked
1200
7
Prevalent light industrial and warehouse uses; many of these are successful thS
tS
businesses and are not likely to redevelop in the next few years
Possible environmental remediation because portions of sites are likely
contaminated due to their history of industrial use
Aging strip commercial development and other low-density retail uses are
prevalent along arterials; these areas are pedestrian unfriendly and are auto-
oriented, with substantial building setbacks and large surface parking lots
While the properties directly surrounding the future station site are commercial
and industrial, most of the surrounding neighborhoods are residential.
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A13Shady Oak Road & LRT update
INTRODUCTION
4
September 21, 2015 Jt Study Session
PROCESS
The cities engaged a consultant team with national Transit Oriented Development
(TOD) expertise and local knowledge to complete the area development strategy
and zoning for the Shady Oak station area. The project was initiated on March
1, 2015 and completed on September 30, 2015. Key components of the work
scope included:
Re
view of previously completed work
including development of
Creation of Vision/Land Use Scenarios
alternatives and selection of a publicly supported preferred concept that
provides a joint vision that can meet the varied needs of both communities
including input from local and national
Assessment of Market Feasibility
developers and experts, concerning the local market demand for proposed
vision, type, and location of TOD supportive land uses in the Shady Oak
station area
Development of Public Investment Analysis and Recommendations
engineering plans that were underway during this project process
the prime
Facilitation of Public Engagement and Incorporation of Feedback
including draft station oriented
Crafting of Zoning Regulations
consultant conducted two public open housesone at the beginning of the project to
permitted uses and design standards that include sustainability elements,
solicit feedback on the vision for the station area, and the other open house near the
a mix of uses, reduced parking requirements, and opportunities to foster
end of the project to present the recommendations. City staff conducted a joint study
collaborative and innovative spaces
session of the Hopkins City Council and Minnetonka City Council and received feedback
including a series of phasing
IdProject Phasing
and direction on the station area vision, land use scenario, and market feasibility
recommendations, estimated costs, and a business case for the funding of
including a summary of the work tasks, policymaker
Preparation of a Final Report
street/utility improvements that will stimulate anticipated adjacent transit
supportive development
pHopkins Planning
including a entitlement process in a
Recommendations for Entitlements
Commission, Minnetonka Planning Commission, and Minnetonka Economic Development
code form that can be integrated into the cities codes
Advisory Commission so that these commissions could make a recommendation to their
respective councils. The second presentation was a joint meeting of the Hopkins City
Council and the Minnetonka City Council. The councils adopted the report.
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A14Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
5
September 21, 2015 Jt Study Session
A15Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
VISION
A16Shady Oak Road & LRT update
September 21, 2015 Jt Study Session
OVERVIEW
INTENT
The following describes big picture themes for the station area redevelopment and are consistent with the adopted vision for future growth in the next
30 years and the implementation strategies to support that vision of both the City of Hopkins 2009 and the City of Minnetonkas 2008 Comprehensive
Plans.
TRAILHEAD
MOBILITY-ORIENTED DISTRICT
u
n
n
n
n
A
Building upon existing and planned assets such as the Minnesota River Bluffs
transportation modes, the Shady Oak station provides an opportunity to
Trail, a network of active transportationpedestrian and bicycle routes
emphasize both destination and departure functions.
A plaza will be constructed at the intersection of 17th and the park and ride
entrance; it will serve as a focus of station area activities and a threshold between
TOD and the station platform. A key plaza element will be a weather protected
bike station that includes a large amount of bicycle parking. This structure may
friendly sidewalks and protected bike lanes people will also be able to access
include ancillary uses such as a café. It should serve as an anchor and focus of
new transit supportive employment, commercial, and retail uses.
the station plaza. Additionally, the park and ride facility provides an important
receiving point into the region-wide LRT. For LRT opening day, the design and
location of the park and ride facility will accommodate surface commuter parking
while minimizing its impacts. Mid to long-range phasing envisions conversion to
a parking ramp, resulting in additional development opportunities and possible
shared parking options.
A17Shady Oak Road & LRT update
VISION
8
September 21, 2015 Jt Study Session
INNOVATION DISTRICT
AUTHENTIC CHARACTER
Establishment of unique and complementary innovation district land uses
Unlike the adjacent campus-like development character of stations to the
will differentiate this station from other employment stations in Hopkins
south, redevelopment of the Shady Oak Station is envisioned to embrace
and Minnetonka or other Southwest Corridor communities.
the station areas existing raw industrial character and build upon this asset
as a distinct, authentic development theme.
The goal of the station area redevelopment will be to create a unique market niche
that is based on emerging national trends for station area and urban development
future transit access. The district will not be a corporate campus, instead it will
give new start-ups, business incubators, and traditional employment enterprises
the opportunity to build or lease corporate, clinical, other space in proximity to
the wealth of intellectual capital and institutional knowledge of major employers
such as Cargill or United Health Care that are already present along the SW LRT
Corridor
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A18Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
9
September 21, 2015 Jt Study Session
FUNDAMENTAL CONCEPT
INTENT
The fundamental concept is a distillation of the key design ideas, physical elements and spatial relationships that have informed the development of land
use and transportation framework elements of Shady Oak Station Area Development Strategy.
An additional paved multi-use trail connection will be provided along the
LINKAGES
north curbline of 5th Street South from the station platform to 11th Avenue.
A successful Shady Oak Station will require establishment of safe, direct, and
The existing trail along 11th to the Westbrooke neighborhood should be
convenient connections. All modes will be adequately served, with an emphasis
enhanced
on pedestrian and bicycle routes within a 5 minute trip of the station. The network
17th/K-Tel will be designed as a complete street, including pedestrian
consists of an urban street grid and multi-use trails. Not all routes will be the
friendly sidewalks and a protected bikeway. The improvements will extend
same. Hierarchies of routes have been established to create a more coherent
at a minimum from Shady Oak Road to Mainstreet. North of Mainstreet, an
station area, including the following fundamental elements:
extension to the existing regional trail system will be considered.
The most important new street of this network will be
Signature Street
DESTINATIONS
the new 17th/K-Tel roadway which will link the areas north and south of
. This signature street will:
the Minnesota River Bluffs Trail
Within the station area, there are land use assets that generate frequent
daily or weekly trips. By serving existing assets by transit, auto usage can be
Provide direct, safe and convenient access to light rail transit from the north
minimized and duplication of successful uses can be avoided. The following
and the south
are fundamental destinations:
Establish a new front door and focus for TOD within the station area
The high density, mixed use development is envisioned
Station Hub
creating development interest for current backwater sites
for parcels in close proximity (± 1/8th mile) of the Shady Oak station.
Provide an alternative cut-through commuting route. With additional Uses will create an animated 18-hour environment of activity surrounding
development, more auto trips will be generated. This roadway will minimize the station platform. As result of having these eyes on the station, the transit
platform will be safer at all times throughout the day. Hub uses will include:
Boulevard arterial streets and intersections
Station serving commercial and retail uses. The uses will provide transit
Provide an attractive setting for adjacent development. The street will
patrons an opportunity to chain trips offering goods and services such as
include special landscaping, lighting, and other streetscape elements
a café, dry cleaner, or child day care facilityuses that they can use as they
that will signal that this street is special and importanta place worthy of
either arrive or depart the transit platform
investment
Include residential uses. Apartments and condominiums are envisioned for
a full range of resident incomes
To maximize transit use, pedestrian and
Neighborhood Connections
A loop
A wealth of retail shops, restaurants and
Hopkins Mainstreet
of active transportation improvements is envisioned that knits the Shady Oak
entertainment venues exist within approximately a half mile trip north of
station to the Downtown Hopkins Station, Mainstreet, and other attractions
the station platform.
and destinations. The connections include:
Rather than duplicate this function in the station area, linkages will be
The existing Minnesota River Bluffs LRT Regional Trail connection that will be
provided
preserved and strengthened. Improvements to the trail will include asphalt
Transit riders offer a potential new clientele for existing Mainstreet
paving between the Shady Oak Station and the Downtown Hopkins Station
businesses, if well connected
at a minimum. Lighting at intersections and the station platform will be
provided to improve safety.
A19Shady Oak Road & LRT update
VISION FUNDAMENTAL CONCEPT
10
September 21, 2015 Jt Study Session
both recreation facilities exist
Shady Oak Lakes/Beach and Central Park
:
within approximately a half mile trip of the station platform. The parks
Provide an essential open space amenity for station area high density
NEIGHBORHOOD
CONNECTIONS
residential and employment uses
Will need less parking. Transit access to the parks will serve as an auto
alternative for those using the facilities from outside the station area,
especially during high demand periods
TOD EMPLOYMENT
SIGNATURE STREET
CORRIDOR
TOD EMPLOYMENT CORRIDOR
Transit-oriented employment development will be oriented toward the 17th
Avenue /K-Tel Drive signature street. The corridor will extend from Shady Oak
Road to Excelsior Boulevard.
Adaptive reuse of existing buildings or redevelopment will be fostered
Employment intensity that will support the regions investment in light rail.
Transit supportive residential, commercial and residential uses will also be
fostered within the corridor
STATION HUB
Development is envisioned to be incremental rather than wholesale
Existing uses will be allowed to remain, expand, or redevelop at the
discretion of the owner in perpetuity
Redevelopment will discourage auto-orientation
Additional roadways and amenities, including a new public open space will
be provided
SHADY OAK STATION AREA FUNDAMENTAL CONCEPT
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A20Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
11
September 21, 2015 Jt Study Session
BUILD-OUT
INTENT
The build-out concept provides a future 5-10 year snap shot of station area redevelopment for the INorth and Station Hub subareas
north of the Minnesota River Bluffs Trail and 5th Street, including a partial redevelopment scheme for the LRT park and ride facility.
The long term redevelopment vision for the character, type, arrangement and intensity of land uses for other areas within the ½ mile station planning area would share
many of these characteristics.
the plan and perspective illustrate a scheme that is at a the plan and perspective can be used to:
Viable Depiction Graphic Tool
development intensity that is realistic and economically feasible. It is based on
Market the communitys vision for station area development to potential
investors
Minnetonka and Hopkins Comprehensive Plans policy for the
redevelopment of the Shady Oak area
public investment in street and open space improvements necessary to
SW Corridor Light Rail preliminary engineering design of the light rail stimulate desirable private investment
platform, park and ride, and operations and maintenance facility
Fundamental requirements necessary to attract investors such as road
BUILD-OUT DEVELOPMENT SUMMARY TABLE
infrastructure, public amenities, and parking ramps
630,000 Square Feet*
Fundamental TOD requirements for compact, mixed use station area design
Essential active transportation elements that will ensure safe, direct and
Industrial 107,000 Square Feet*
convenient neighborhood access to the station
Sustainable design concepts such as solar collectors, wind turbines, and Commercial/Services 195,000 Square Feet*
stormwater detention basins
Retail 15,000 Square Feet *
Development that includes a mix of repurposed, adaptive re-use of existing
structures and new construction
Residential 1,250 Units
Parking 3,635 Spaces
Park and Ride 380 Spaces
Station Plaza 1 Acre
Innovation Open Space 2 Acres
Streets 8,600 Linear Feet
A21Shady Oak Road & LRT update
VISION BUILD-OUT
12
September 21, 2015 Jt Study Session
INNOVATION OPEN SPACE
APARTMENTSRETAIL
EXISTING INDUSTRIAL EMPLOYMENT
APARTMENTS
OFFICE EMPLOYMENT
INNOVATION EMPLOYMENT
SIGNATURE STREETCONDOMINIUMS
ADAPTIVE REUSE
(17th Avenue)
EMPLOYMENT
MINNESOTA RIVER BLUFFS
REGIONAL TRAIL
LRT OPERATIONS and
MAINTENCE FACILITY
SHADY OAK STATION
and PLAZA
PARK and RIDE
INNOVATION OFFICE NORTH AND STATION HUB SUBAREAS BUILD-OUT (2020-2025)
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A22Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
13
September 21, 2015 Jt Study Session
SHADY OAK
STATION
SHADY OAKINNOVATION OFFICE NORTH AND STATION HUB SUBAREAS(2015)
EXISTING DEVELOPMENT SUMMARY TABLE
EXISTING INFRASTRUCTURE/OPEN SPACE SUMMARY TABLE
Land UseArea Area Building Area ResidentialParking
Area
Infrastructure/Open SpaceArea
(Acre)(Square Feet)(Square Feet)(Units)
(Square Feet)
(Acre/Linear Feet)
INDUSTRIAL 48 2,100,000 720,000 ---- 490
STREETS 1/71545,000
COMMERCIAL SERVICES 22 960,000 255,000 ---- 570
NINE MILE CREEK 140,000
RESIDENTIAL 0 0 0 0 0
EXISTING TOTAL 285,000
INFRASTRUTCURE/OPEN SPACE 2 85,000 --- --- ---
EXISTING TOTAL723,135,000 975,000 0 1,060
A23Shady Oak Road & LRT update
VISION BUILD-OUT
14
September 21, 2015 Jt Study Session
EXCELSIOR BOULEVARD
Sunshine
Citizens
Car Wash
Bank
INNOVATION
PARK
Scherer Bros.
Lumber
AAMCO
McDonalds
T
T
RD
3
.
..
..
Sierra
Corp.
T
T
47T
..
..
..
SHADY OAK
STATION
5TH STREET
Station Hub (Retail and Residential)
SHADY OAK INNOVATION OFFICE NORTH AND STATION HUB SUBAREAS (2025)
BUILD-OUT INFRASTRUCTURE/OPEN SPACE SUMMARY TABLE
BUILD-OUT DEVELOPMENT SUMMARY TABLE
AreaParking
Land UseArea Area Building Area Residential Parking
Infrastructure & Open Space
Area
(Square Feet)
(Acre/Linear Feet)(Spaces)
(Acre)(Square Feet)(Square Feet)(Units)(Spaces)
EXISTING STREETS 1/715 45,000
NEW OFFICE 17.5 765,500 630,000 --- 1,575
EXST. INDUSTRIAL 8.25 360,000 107,000--- 135
NEW STREETS 11/7885 476,500
EXST. COMMERCIAL SERVICES 12 525,000 195,000 --- 585
NEW STATION PLAZA 1 43,500
NEW RETAIL .75 32,500 15,000 --- 90
EXISTING NINE MILE CREEK 1 40,000
NEW RESIDENTIAL 12.5 545,000 1,400,000 1,250 1,250
NEW INNOVATION OPEN SPACE 2 87,000
INFRASTRUCTURE/OPEN SPACE21 910,000 --- --- 380
NEW PARK AND RIDE 5 218,000380
BUILD-OUT TOTAL 723,138,0002,347,000 1,2504,015 380
BUILD-OUT TOTAL 21 910,000
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A24Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
15
September 21, 2015 Jt Study Session
LAND USE FRAMEWORK
OVERVIEW
The Land Use Framework primarily describes the future development of the Shady Oak station area. It has an emphasis, in terms of focus and detail, on land
located within a half mile radius of the Shady Oak Station that extends east into Hopkins and west into Minnetonka.
The proposed development district subareas will inform anticipated revisions to both Citiess zoning ordinances.
SUBAREAS
While in the past, some of the most innovative
Innovation District Concept
regions have largely been suburban corridors of spatially-isolated corporate
The land use framework diagram illustrates the new development patterns
campuses (e.g., Silicon Valley), a new form of innovation has emerged based
on an integration of anchor institutions, key companies, start-ups, business
On many parcels, a mix of vertical uses is suggested. Where parcels contain a
incubators, and accelerators.
vertical mix of uses, the most likely predominant land use is indicated. Predominant
Districts tend to be physically compact, transit-accessible, and offer a mix
uses have been sited and categorized into subareas to:
Maximize development potential based upon existing use adjacencies and
an early trend. They are based on economic, social and physical networks
site attributes
which foster a creative, risk-taking culture that facilitates ideas and accelerates
commercialization.
Maximize utilization of existing and planned improvements such as
stormwater lines or other utilities
the best model for Shady Oak may be a mash-
Innovation District Examples
Address existing development agreements between the Cities, SW Light
up of two emerging innovation redevelopment themes:
Rail, or others
For areas north of the Minnesota River Bluffs Trail, a theme that is described
Respond to a conceptual short term and long term phasing strategy
as - industrial or warehouse districts that are
Reimagined Urban Areas
undergoing physical and economic transformations. These changes are
some instances, multiple uses are appropriate
being powered by transit access, historic building stock, and proximity to
Address policy decisions for development outside the planning area. In
downtowns and anchor companies. Examples include areas such as Denvers
particular, the desire to complement, preserve, and strengthen the historic
River North (RiNo) District, Portlands Central Eastside, Seattles South Lake
Downtown Hopkins Mainstreet
Union area, or St. Louiss Cortex District.
For areas south of the trail, a second theme described as an
Urbanized
The station area includes the following areas:
- commonly found in suburban and exurban areas where
Science Park
1) I
traditionally isolated and sprawling business park areas of innovation are
2) Urban Industrial
urbanizing through increased density and infusion of new uses may be more
applicable. North Carolinas Research Triangle, for example, has recognized
3) Station Hub
that its isolated car-dependent environment has not been successful in
attracting young talent. A recently completed master plan calls for the
creation of a central district, the addition of up to 1,400 multi-family housing
units, retail, and potential light rail transit.
While innovation districts take a number of different forms, the key tenants
include transit accessibility and mix of uses. These tenets, in and of
themselves, do not guarantee success. The fundamental goal of the Land
Use Framework is to identify marketable uses combined with the creation of
a physical environment conducive to innovation.
A25Shady Oak Road & LRT update
VISION LAND USE FRAMEWORK
16
September 21, 2015 Jt Study Session
LAND USE SUBAREAS
Urban Industrial Subarea
Station Hub Subarea
Innovation Park
Station Plaza
PLAZA
Existing Park/Open Space
SUBAREAS DEVELOPMENT SUMMARY TABLE
I 2,000,000 Square Feet*
I
Park
395,000 Square Feet*
and
Commercial/Services
Ride
Urban Industrial445,000 Square Feet*
Station Hub Retail 15,000 Square Feet*
Station Hub Residential 1,250 Units
Parking 8,285 Spaces
SW LRT OMF150,000 Square Feet*
Park and Ride380 Spaces
Station Plaza1 Acre
Innovation Park2 Acres
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A26Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
17
September 21, 2015 Jt Study Session
INNOVATION OFFICE SUBAREA NORTH
The subarea is substantial in size: it extends from the Minnesota River Bluffs Trail at the south, to Excelsior Boulevard on the north, and between Shady Oak
Road on the west and 11th Avenue on the east. The subarea includes parcels in both cities of Minnetonka and Hopkins
T
development.
The subarea has the following essential real estate site criteria for innovation with the presence of light rail, parking will be limited to
EfParking
development concepts:
1000 square feet); for commercial/retail (2.5 spaces per 1000); and residential (1
fronting major arterials, the blocks are close to the Hopkins Mainstreet
Proximity
space per unit). Fewer spaces or shared parking will be fostered. Parking ramps
and have direct access to other anchor institutions such as the Cargill campus by
are likely required to serve the anticipated intensity of development. They should
either light rail or auto commute
be sited to conveniently serve multiple buildings while providing direct access to
the sites are located adjacent to the busy major arterial roadway.
Good visibility
Today, Excelsior Boulevard provides over 16,000 daily drive-by trips and over
Where parking lots are built, parking will be required to be located behind or to
11,000 daily drive-by trips on Shady Oak Road
the side of buildings. Design techniques that minimize parked car visual impacts
the sites can be easily accessed from existing intersections at 17th and
Access
.................................................................................
For all development projects bicycle parking will be maximized. Minimum bike
47th Street. Additional right-in right out (minimum) access points are anticipated
parking standards will be in excess of current City of Minnetonka and Hopkins
as part of a local street grid for intersections at 19th, 15th and 14th Avenues, and
possibly 3rd Street or 20th Avenue
required for all new development or major renovation projects
Prominent Address
adaptive reuse, renovation, expansion and repurposing of
Sustainability
multiple front door addresses along the existing Excelsior Boulevard and Shady
existing structures should be encouraged. Maximizing the imbued energy and
Oak Road and the future 17th Avenue signature street
materials of these buildings is a key component of sustainability objectives
a green space, located within the street grid provides a window into
Amenity
of the project. Other sustainable practices such as the incorporation of solar
panels, wind turbines, and use of green roofs or bioswale green street practices
development, and gathering place for employees, residents and visitors
promoted
GENERAL DEVELOPMENT CHARACTER
For redevelopment proposals, prohibited
Permitted and Conditional Uses
Development will front the new street grid creating a more urban
Orientation
uses will generally include those that are auto-oriented. Warehousing, storage,
oHub transit
Primary building access will be from the street, green spaces or pedestrian
serving retail will be prohibited. Manufacturing or assembly uses will be permitted,
corridors not from parking lots, sky bridges, or parking ramps
but limitations on uses that may create adverse impactsnoise, air quality, etc.
Buildings should be urban, covering a majority of
Form and Massing
Open space general function, location, size and use of open spaces will be
Generally buildings should range from one story to six stories in height for the prescribed. Public parks will be required of adequate size and design to serve
a more urban condition discouraged, instead facilities that promote areas for lunch a break, or other
employee activities should be fostered
A27Shady Oak Road & LRT update
VISION LAND USE FRAMEWORK
18
September 21, 2015 Jt Study Session
INNOVATION OFFICE SUBAREANORTH
Innovation Park
Station Plaza
PLAZA
Existing Park/Open Space
SUBAREAS DEVELOPMENT SUMMARY TABLE
Industrial 905,000 Square Feet*
Commercial/Services 395,000 Square Feet*
Park
and
Ride
Parking 3,250 Spaces
Innovation Park 2 Acres
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A28Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
19
September 21, 2015 Jt Study Session
INNOVATION OFFICE SUBAREA SOUTH
The subarea is substantial in size: it extends from the Minnesota River Bluffs Trail at the north to the Canadian PBass Lake Spur freight rail line on the
south, and between Shady Oak Road on the west and future light rail trackway on the east. The subarea includes parcels in the city of Minnetonka only.
T
incubators, and accelerators and a limited amount of complementary retail and service development while maintain existing industrial, warehousing and
manufacturing functions.
Currently the subarea does not have the characteristics that would engender innovative uses, however in the long term after light rail has been built and
development has largely been achieved in the Innovation North Subarea, this subarea will become ripe for new investment.
Within 5-10 years the subarea will possess the following essential real estate site criteria for innovation development concepts:
redevelopment sites have direct access to the Imris corporate
ProximityBuildings should be urban, covering a majority of
Form and Massing
headquarters
(FAR) will be prescribed. Generally buildings should range from one story to six
as noted previously, the new signature
Good visibility and Prominent Address
stories in height for the majority of the sub area
that demand greater exposure. With this increased exposure, development sites
with the presence of light rail, parking will be limited to
EfParking
will have greater investor interest
of 3 spaces per 1000 square feet); for commercial/retail (2.5 spaces per 1000); and
the sites can be easily accessed from the west at an existing signalized
Access
..................................................................................
intersection at Shady Oak Road and from 5th Street to the east
Where parking lots are built, parking will be required to be located behind or to
the side of buildings. Design techniques that minimize parked car visual impacts
the proximity to the Shady Oak Beach may attract residential
Amenity
from streets and the disruption of the pedestrian environment will be required. For
increase in residential development, a public park, possibly associated with one
accessible, long term bike parking rooms will be required for all new development
of the existing ponds should be built to serve this population
or major renovation projects
GENERAL DEVELOPMENT CHARACTER
adaptive reuse, renovation, expansion and repurposing of
Sustainability
Due the relatively new age and quality of existing industrial structures, considerable
existing structures should be encouraged. Maximizing the imbued energy and
more renovation, adaptive reuse, and repurposing of existing buildings rather
materials of these buildings is a key component of sustainability objectives
than new development may occur within this subarea.
of the project. Other sustainable practices such as the incorporation of solar
panels, wind turbines, and use of green roofs or bioswale green street practices
are developed at a very low density. The large parking lots and underutilized
promoted
For redevelopment proposals, uses that are
Permitted and Conditional Uses
characteristics will be required:
auto-oriented will be discouraged. Development or expansion of new warehousing
Development will front the existing streets to create a more urban
Orientation
and storage uses will be discouraged. Manufacturing or assembly uses will be
street edge that creates a more pedestrian friendly public realm. Primary building
permitted, but limitations on uses that may create adverse impactsnoise, air
access will be from the street rather than directly from internal parking lots, sky
bridges, or parking ramps
A29Shady Oak Road & LRT update
VISION LAND USE FRAMEWORK
20
September 21, 2015 Jt Study Session
INNOVATION OFFICE SUBAREASOUTH
Station Plaza
PLAZA
Existing Park/Open Space
SUBAREAS DEVELOPMENT SUMMARY TABLE
Industrial 1,095,000 Square Feet*
Parking 2,740 Spaces
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A30Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
21
September 21, 2015 Jt Study Session
URBAN INDUSTRIAL SUBAREA
The subarea is substantial in size: it is generally located below 5th Street and east of 11th Avenue. The subarea extends to the Canadian PBass Lake
Spur freight rail line on the south, to the future light rail trackway on the west, and 11th Avenue on the on the east. The subarea includes parcels only in
the City of Hopkins.
A
incubators, and accelerators and a limited amount of complementary retail and service development. However, industrial, warehousing and manufacturing
functions are envisioned to largely remain within most of the subarea.
adaptive reuse, renovation, expansion and repurposing of
GENERAL DEVELOPMENT CHARACTER Sustainability
existing structures should be encouraged. Maximizing the imbued energy and
Due the nature of industrial development a greater auto and truck orientation
materials of these buildings is a key component of sustainability objectives
will occur in this subarea. Nevertheless, site improvements that enhance the
of the project. Other sustainable practices such as the incorporation of solar
pedestrian environment and foster safe and direct access to light rail will required
panels, wind turbines, and use of green roofs or bioswale green street practices
for any new or major renovation project.
promoted
required:
For redevelopment proposals, uses that are
Permitted and Conditional Uses
Development will front the existing streets to create a more urban
Orientation
auto-oriented will be permitted. Development or expansion of new warehousing
street edge that creates a more pedestrian friendly public realm. Primary building
and storage uses will be permitted. Manufacturing or assembly uses will be
access will require at least one entrance directly accessible the street rather than
permitted, but limitations on uses that may create adverse impactsnoise, air
directly from internal parking lots
with the presence of light rail, parking will be limited to
Ef
Parking
of 3 spaces per 1000 square feet); for commercial/retail (2.5 spaces per 1000); and
..................................................................................
Where parking lots are built, parking will be required to be located behind or
to side of buildings. Design techniques that minimize parked car visual impacts
.................................................................................
For all development projects bicycle parking will be maximized. Minimum bike
parking standards will be in excess of current City of Hopkins standards. Ground
development or major renovation projects
A31Shady Oak Road & LRT update
VISION LAND USE FRAMEWORK
22
September 21, 2015 Jt Study Session
URBAN INDUSTRIAL SUBAREA
Urban Industrial Subarea
Station Plaza
PLAZA
Existing Park/Open Space
SUBAREAS DEVELOPMENT SUMMARY TABLE
Industrial 445,000 Square Feet*
Parking 1000 Spaces
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A32Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
23
September 21, 2015 Jt Study Session
STATION HUB SUBAREA
The subarea is the most compact in size of all the subareas: It generally surrounds the future light rail station north of the Minnesota River Bluffs Trail with
the exception of additional parcels south of the trail along 5th Street, generally west of 15th Avenue.
TA limited amount of transit
Recent SW LRT corridor housing market analysis indicates that residential development is the most viable development segment in the short term for the
entire Twin Cities market area. To capitalize upon this burgeoning market segment, development should be targeted to occur before or concurrently with
light rail construction. Additionally, because a number of sites will be initially controlled by Metro Transit, public private development opportunities may
be greater within this subarea.
The subarea has the following essential real estate site criteria for innovation
Buildings should be urban, covering a majority of
Form and Massing
development concepts:
development parcelswhen a site is redeveloped, a minimum density of 60
dwelling units per acre or a 0.5 FAR for commercial/retail development will be
fronting light rail and in proximity to employment uses, this subarea
Proximity
prescribed. Generally buildings should range from two to six stories in height
will be one the SW LRTs best residential development opportunities.
for the majority of the sub area
the sites are located adjacent to the future signature street
Good visibility
with the presence of light rail, parking will be limited to
Ef
Parking
the proximity to the station retail, Central Park, Shady Oak Beach, and
Amenity
of 3 spaces per 1000 square feet); for commercial/retail (2.5 spaces per 1000);
the station plaza will attract residential development interest. Over time, should
and residential (1 space per unit). Fewer spaces or shared parking will be
fostered. Where parking lots are built, parking will be required to be located
additional public park, possibly associated with one of the existing ponds should
behind buildings. Design techniques that minimize parked car visual impacts
be built to serve the residents. Incorporation of active recreation features such
.................................................................................
For all development projects bicycle parking will be maximized. Minimum bike
p
arking standards will be in excess of current City of Hopkins standards. Ground
GENERAL DEVELOPMENT CHARACTER
New development will occur within this sub area. Located at the trailhead to
development or major renovation projects
and from light rail, the subarea will set the bar for the entire station area. The
Sustainable practices such as the incorporation of solar panels,
Sustainability
wind turbines, and use of green roofs or bioswale green street practices should
constructed here. To provide a positive experience and image, the development
be encouraged. LEED certification should not be required but should be
must be welcoming, pedestrian-friendly, and compatible with surrounding
promoted
subarea context
prohibited uses will generally include those
Permitted and Conditional Uses
The following characteristics will be required:
that are auto-oriented. For the subarea, a maximum of 50,000 square feet of retail
Development will front the existing and new streets to create an
Orientation
will required to avoid competing with Hopkins Mainstreet
urban street edge that creates a more pedestrian friendly public realm. Primary
building access will be from the street rather than directly from internal parking
lots or parking ramps
A33Shady Oak Road & LRT update
VISION LAND USE FRAMEWORK
24
September 21, 2015 Jt Study Session
STATION HUB SUBAREA
Station Hub (Residential & Retail)
Subarea
Station Plaza
PLAZA
Existing Park/Open Space
SUBAREAS DEVELOPMENT SUMMARY TABLE
Retail 15,000 Square Feet*
Residential 1,250 Units
Parking 1,295 Spaces
Park and Ride 380 Spaces
Park
Station Plaza .75 Acre
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A34Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
25
September 21, 2015 Jt Study Session
CIRCULATION FRAMEWORK
OVERVIEW
The Transportation FIt has an emphasis, in
terms of focus and detail, on complete street multimodal connections located within a half mile radius of the Shady Oak station.
Recommendations on the location and configuration of automobile, bus,
BICYCLE
PEDESTRIAN
includes:
the circulation diagram prescribes a street network of
Roadway hierarchy
or design, these Secondary Streets are not optional, they must be provided
as part of future development proposals to improve station access and
establish a framework for transit oriented development
pedestrian and bicycle
An emphasis on active transportation
parking impacts; maximize light rail transit investment, and foster health
TRANSITAUTO
because the station is locate outside a comfortable
A bus shuttle route
walking distance (1/4 mile) from the majority of existing residential areas,
schools, and the Hopkins Mainstreet, a bus shuttle route and stop locations
frequent and dependable service to key destinations within a reasonable
timeframe. The shuttle will be invaluable for those who are physically
challenged or those who would prefer not to walk or cycle in inclement
weather or at night
COMPLETE STREETS
A35Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
26
September 21, 2015 Jt Study Session
CIRCULATION FRAMEWORK DIAGRAM
Signature Street
Primary Streets
Secondary Streets
Neighborhood Connections
(Active Transportation)
SW LRT Alignment
Proposed Shuttle Route and Stops
Bike Signal
Future Pedestrian Activated Signal
(HAWK)
Park
and
Existing Stop Sign
Ride
Future Stop Sign
Bike Station
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A36Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
27
September 21, 2015 Jt Study Session
CURRENT AND FUTURE TRAFFIC CONDITIONS
The assessment includes data for existing and future roadway conditions for key streets and intersections, and existing parking conditions near the proposed
station area. Shady Oak Road, Excelsior Boulevard, 11th Avenue, 5th Street and K-Tel Drive are the major roadways serving the study area.
PROPOSED NEW DEVELOPMENT TRIP GENERATION
CURRENT AND FUTURE TRAFFIC FORECASTING
An estimate of the number of vehicle trips generated by the proposed new station
Level of Service (LOS) was calculated at key intersections using _. Turning
movement counts from the _ anticipated future development of the Shady Oak
station area were used in the LOS analysis. The current and estimated future
development.
development. development. development. development.
xxxxx
The new developments trips were assigned to the surrounding roadways based
The new developments trips were assigned to the surrounding roadways based The new developments trips were assigned to the surrounding roadways based
yyyyy
upon the proximity of site roadways to the regional roadway connections. The
upon the proximity of site roadways to the regional roadway connections. The upon the proximity of site roadways to the regional roadway connections. The
trip distribution was weighted _______. Approximately ___ percent or less of the
zzzzz
trip distribution was weighted _______. Approximately ___ percent or less of the trip distribution was weighted _______. Approximately ___ percent or less of the
proposed new development was assigned to the other streets. The assumed trip
distribution is consistent with _____.
new development is____ vehicle trips per day (vpd). ________, _______, ______
A37Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
28
September 21, 2015 Jt Study Session
SUMMARY OF FINDINGS AND RECOMMENDATIONS
Numerous proposed vehicular access points will intersect existing major
to the impact of the proposed new development will require the following
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A38Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
29
September 21, 2015 Jt Study Session
NEIGHBORHOOD ACTIVE TRANSPORTATION CONNECTIONS
F
it is essential that well designed safe and direct active transportation routes be established. T
auto congestion, enabling a reduction of parking requirements for future development, and an increase in transit boardings at the Shady Oak Station.
The Active Transportation Concept prescribes:
surfaces) or enhancements are provided for:
Routes that are intended to build upon existing multi-use Minnesota River
Bluffs, Shady Oak and 11th Avenue trails.
Along the north and south side of Excelsior Boulevard the existing sidewalks
will be expanded to 12 when adjacent to a landscaped buffer (14 when
Future routes that will also provide linkages to adjacent neighborhoods and
located adjacent to the curbline) from 5th Avenue to 17th Avenue. From 17th
incorporate planning concepts for future facilities such as the future 8th
Avenue to Shady Oak Road the existing sidewalk will expand on the south
Street Artery enhancements
side of Excelsior Boulevard only
Coupled with bicycle facilities, enhanced pedestrian sidewalks and
Along the west side of Nine Mile Creek from 5th Street to existing trails
crosswalks to foster walking within a quarter mile of the station and for those
within Central Park at 13th Avenue; a new at-grade crossing at Excelsior
willing to travel further distances.
Boulevard will include a HAWK (High-intensity Activated Walk) beacon
BICYCLE AND PEDESTRIAN ENHANCEMENTS
Along the west side of K-Tel Drive from Fifth Street to Shady Oak Road.
North of 5th, the trail would transition into a protected bike lane
The Station area is designed to include premium active transportation
pedestrian and bicycle transportation facilities.
Along the north side of Fifth Street from K-Tel Drive to 11th Avenue
serve primarily a commuting function. They are physically
Along 11th, the existing trail will be extended south to Smetana Road;
Protected bike lanes
separated by a combination of parked cars, landscaping, bollards, raised curbs, or
connections will be made to the Nine Mile Creek Trail at Westbrooke Way
Along the Minnesota River Bluffs Trail safe crossings will be provided. At 11th
Between the Downtown Hopkins Station and Shady Oak Station, the
ridership within the station area. Protected bike lanes are proposed:
Minnesota River Bluffs Trail existing surfaces will be upgraded to asphalt
Along the west side of the 17th Avenue/K-Tel Drive signature street from
South along the west side of the future light rail trackway connecting to
5th Street to Excelsior Boulevard. A 10 wide bi-directional facility will be
Smetana Road and further south to the future Opus Station
provided; south of 5th Avenue, the protected bike lane would transition to a
Along the north side of Smetana Road between 11th Avenue and Shady Oak
multi-use trail
Road
North of Excelsior, an 11 wide bi-directional facility with a 1 extruded curb
(adjacent to the southbound travel lane) will continue on the west side of the
facilities are provided for as part of the station plaza design. The
Bike Station
roadway. A bicycle signal phase will be added to provide a safe crossing at
Bike Station:
this busy intersection. The protected bike lane should continue north along
Will offer secure indoor long term bike parking, possibly showers/restrooms,
17th Avenue past Mainstreet and connect to the regional multi-use trail
lockers and ancillary uses such as repair services or a café
crossing between Third and Fourth Street
A private or public vendor may operate the facility. Daily fees or month/
annual membership fees may be required to access part or all of the facility
serve both a recreation and commuting function. Where
Multi-use Trails
sidewalks do not exist, they will also provide access to businesses and residences.
Short-term use bike racks will be provided at the station and throughout the
A number of combined pedestrian and bicycle routes currently exists; expansion
station area as part of street improvements.
of these routes is planned to create a network. When adjacent to arterial roadways,
On-street bike corral multi-rack facilities that replace curbside parking will
new trails will be physically separated from the travel lanes by a landscape buffer
be permitted on a case by case basis, initiated by adjacent property owners
desiring such facilities
A39Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
30
September 21, 2015 Jt Study Session
ACTIVE TRANSPORTATION DIAGRAM
Existing/Planned Protected Bike Lane
Proposed Protected Bike Lane
Existing Multi-Use Trail
Proposed Multi-Use Trail
SW LRT Alignment
Bike Signal
HAWK Signal
Bike Station
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A40Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
31
September 21, 2015 Jt Study Session
NEIGHBORHOOD TRANSIT CONNECTIONS
Currently the station area is served by four Metro Transit bus routes (Routes 12, 615,670, and 664). Next year, a sector study of existing bus routes will be
developed to better incorporate the light rail transit service and eliminate redundant routes.
LOCAL CIRCULATOR SHUTTLE BUS
Because the station is located outside a comfortable walking distance (1/4
mile) from the majority of existing residential areas, schools, and the Hopkins
additional means to providing necessary frequent and dependable service to
key destinations within a reasonable timeframe. The shuttle will be invaluable
for those who are physically challenged or those who would prefer not to walk or
cycle in inclement weather or at night.
examine, at a minimum:
Additional analysis of potential routes for a shuttle service linking the
neighborhoods and centers
Phasing strategies that ensure services could be adequately provided for at
opening day of LRT while not precluding opportunities for serving additional
transit destinations
Vehicles types and operational requirements
Future stop location, design, and any other necessary shuttle infrastructure
Funding strategies
A41Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
32
September 21, 2015 Jt Study Session
BUS TRANSIT DIAGRAM
METRO Bus Routes
SW LRT Alignment
Proposed Shuttle Route and Stops
Existing METRO Bus Routes
Bus 12 - Local Bus Route
(Uptown Minneapolis - Excelsior Blvd - Hopkins - Opus)
Bus 615 - Local Bus Route
(Ridgedale- Co Rd 73- St Louis Park)
Bus 670 - Express Bus Route
(Excelsior- Downtown Minneapolis)
Bus 664 - Express Bus Route
Park
(Co Rd 3 - Excelsior Blvd - Downtown Minneapolis)
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A42Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
33
September 21, 2015 Jt Study Session
REGIONAL TRANSIT CONNECTIONS
Many of the anticipated Park & Ride users will come from areas north, south, and west of the station area. A
Minnetonka in order to get to the station and the associated Park and Ride facility. The siting and design of the park
and ride ensures that the facility is commuter friendly while not compromising City of Hopkins and Minnetonka Station Area policy or impacting long term
TOD potential.
revised on July 8, 2015 by the Metropolitan Outlined is an area adjacent to the station where 270
Opening Day Improvements Long Term Facilities
Council, park-and-ride numbers for the SW LRT corridor indicate that the Shady permanent spaces are most appropriate. The remaining 430 stalls would be
Oak Station is slated to accommodate 700 parking spaces. Approximately subject to potential redevelopment.
270 of the 700 stalls will be designed and constructed as permanent surface
Park and ride facilities commonly have a higher incidence of criminal activity.
stalls. The balance will be temporary, meaning they will be built with thinner
Providing eyes on the station discourages criminal activity at the station. The
bituminous surfacing and bituminous curbing, anticipated to last around 5 years.
permanent stalls have been sited with consideration of maximizing station
It is anticipated that the temporary parking will be removed and replaced when
platform safety. The location of the park and ride ensures that considerable
a redevelopment proposal comes to the table in that time. The replacement of
temporary stalls would need to be replaced at a 1:1 or possibly lesser ratio (the
station, thereby creating a safer environment for transit patrons, residents and
process for redevelopment and replacement ratio has yet to be determined).
commercial clientele, as well.
Because of high costs, parking replacement requirements at any ratio (1:1 or even
Moreover, the parking has been located to create a critical mass of a collection of
redevelopment partnerships are likely needed for redevelopment
TOD parcels on the site along 17th Avenue. By providing this development area,
a linkage of development sites can be created that spills over to potential TOD
on adjacent sites west of the Hopkins Tech Center site. With this development
in place, it will be more viable that the temporary parking spaces will be
redeveloped.
Overtime it is anticipated that the area including the 270 permanent spaces would
redevelop as multi-family development over a parking ramp. The parking ramp
would be required to provide 270 permanent park and ride spaces as well as,=
parking for multi-family residents.
A43Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
34
September 21, 2015 Jt Study Session
RECOMMENDED LOCATION FOR PERMANENT PARK AND RIDE SPACES
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A44Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
35
September 21, 2015 Jt Study Session
ROADWAY HIERARCHY
The roadway hierarchy diagram, illustrates the minimum street types and locations required to provide adequate station platform and development parcel
access. Moreover, it establishes a development contextscale and massing limitations for future land uses and a setting for placemaking. These design
elements will contribute to the creation of a distinct and attractive innovation district.
The framework establishes holistic complete streets where minimum facilities for all modesauto, truck, transit, pedestrian, and bicycle are adequately
provided. These complete streets include essential auto and truck infrastructureright-sized roadway travel lanes and in most instances, curbside parking
and loading zones. Moreover, winter design issues have been addressed.
Within the street grid, a hierarchy of streets has been established to address both
mobility and adjacent land use needs. Categories are as follows:
A. Signature Street
B. Primary Streets
C. Secondary Streets
A45Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
36
September 21, 2015 Jt Study Session
ROADWAY HIERARCHY DIAGRAM
Signature Street
Primary Streets
Secondary Streets
SW LRT Alignment
Bike Signal
BH
Future Pedestrian Activated Signal
(HAWK)
Existing Stop Sign
Future Stop Sign
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A46Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
37
September 21, 2015 Jt Study Session
SIGNATURE STREET
The Signature Street serves as the primary station connection between major arterial roadways and the Shady Oak Station. The street scale and street
elements have been crafted to foster a pedestrian friendly, urban, vertical mixed use development environment. The street will not be a seam; rather it will
knit the station areas of Hopkins and M
The Signature Street consists of two segments
a) Segment 1 new 17th Avenue street construction would occur from Excelsior
Boulevard to 47th Street, providing access to the station platform and park and
ride facility to be built by Metro Transit as part of the SW LRT project.
b) Segment 2 This segment will merge and realign the existing K-Tel Drive
with the17th Avenue extension south of 47th Street to 5th Street. Fifth Street will
be realigned to T into K-Tel Drive /17th Avenue as part of the SW LRT project.
From approximately 47th Street south to 5th Street, the street construction will
be funded by the city of Minnetonka.
A47Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
38
September 21, 2015 Jt Study Session
SIGNATURE STREET DIAGRAM
Signature Street
SW LRT Alignment
Bike Signal
Future Stop Sign
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A48Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
39
September 21, 2015 Jt Study Session
17TH AVENUE (SIGNATURE STREET - SEGMENT 1)
The 17th Avenue - Segment 1 can be described as a
the street should include the following elements:
Placemaking Character
Detail
street that is complete and functions effectively in all seasons; more importantly
A public right-of way dimension of 88
however, it will be distinctive and memorable. The street will:
Two 12-6 travel lanes
RHopkins and Minnetonka. It will be
Two 8 curbside parking lanes
beautifula place where people will want to linger.
West Side: A 10 bi-directional protected bike lane, 3 door zone sidewalk,
It will be sustainable. In particular it will include elements such as bioswales
and 17 sidewalk (with landscaping/hardscaping) adjacent to the west
and other green features such as water conserving irrigation systems,
curbline
East Side: A 17 wide sidewalk (with landscaping/hardscaping) adjacent to
Evoke an innovation theme yet not appear to feel foreign or incompatible
the east curbline
with the surrounding neighborhoods
A 6 building setback from the right-of-way for adjacent development to
Demonstrate to those who are traveling through to the light rail station that
incorporate landscaping/hardscaping
the Shady Oak station area is worthy of investment.
Stormwater detention/landscaped curb extensions
A49Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
40
September 21, 2015 Jt Study Session
17TH AVENUE SECTION - 88 RIGHT-OF-WAY
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A50Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
41
September 21, 2015 Jt Study Session
K-TEL DRIVE (SIGNATURE STREET - SEGMENT 2)
the street should include the following elements:
Placemaking Character
Detail
volume roadways that together provides access to existing light industrial
A public right-of way dimension of 66
Two 17 travel lanes
consists of two travel lanes and no sidewalks.
West Side: A 12 multi-use trail (with 5 landscaping buffer) adjacent to the
In the future, the street is envisioned to be a focus of development for
west curbline.
East Side: A 6 wide sidewalk located (with 5 landscaping buffer) adjacent to
park and ride. Additionally, it is envisioned as a street that provides a vital
the east curbline property line and additional 4 landscaping between the
pedestrian and bicycle connection through the heart of the Shady Oak Station
sidewalk and adjacent development parcels.
area, and linkage between the Shady Oak Beach and the Hopkins Mainstreet
.
This segment of the Signature Street will include fewer improvements.
Improvements will primarily include a new multi-use trail along the west right-
of-way line. Additional enhancements envisioned include additional street
trees, landscaping and pedestrian scaled lighting. A new 6 sidewalk may be
constructed on the east side of the roadway.
A51Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
42
September 21, 2015 Jt Study Session
Side-
walk
K-TEL DRIVE SECTION - 66 RIGHT-OF-WAY
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A52Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
43
September 21, 2015 Jt Study Session
PRIMARY STREETS
The Primary Streets establish a complete street grid through portions of the station area. MPrimary Streets
as public rights-of-way is an essential action necessary to stimulate early TOD in the Innovation North and Station Hub subareas.
These streets also provide essential access to a number of land locked parcels that currently have no direct public right-of-way frontage. Barring parcel
consolidation with adjacent parcels that have access, it is unlikely that these land locked parcels will redevelop as envisioned. To lessen and share development
impacts equally, new street center lines are generally aligned along existing property lines.
Park and ride access will be improved by proving an additional access
Primary Streets include:
point from the west via 47th Street. Especially at peak hours, this road will
3rd Street
serve as an additional dispersion route, lessening congestion at 17th/ K-Tel
47th Street
intersections.
5th Street
5th Street is an essential LRT station access way for residents in the
Westbrooke neighborhood. Many of these residents are dependent on
19th Avenue
transit as a primary means of transportation. Providing active transportation
15th Avenue
improvements along the street is imperative to ensure so that they have safe
and comfortable access to transit.
A53Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
44
September 21, 2015 Jt Study Session
PRIMARY STREETS DIAGRAM
Primary Streets
SW LRT Alignment
Future Stop Sign
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A54Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
45
September 21, 2015 Jt Study Session
3RD STREET, 47TH STREET, 19TH AVENUE AND 15TH AVENUE
these streets can be described as providing a front
Placemaking Character
Hub
subareas. The street scale and street elements have been crafted to foster a
pedestrian friendly, urban, vertical mixed use development environment.
the street should include the following elements:
Detail
A public right-of way dimension of 66
Two 12 travel lanes
Two 8 curbside parking lanes
Two 13 wide sidewalks (with landscaping/hardscaping) adjacent to the
property lines .
TYPICAL PRIMARY STREET SECTION - 66 RIGHT-OFWAY
A55Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
46
September 21, 2015 Jt Study Session
5TH STREET
the street is envisioned to be a focus of
Placemaking Character
development for urban industrial uses and access for commuters to the light
rail station and park and ride. Additionally, it is envisioned as a street that
provides a vital pedestrian and bicycle connection and linkage between the
Shady Oak Station and the Westbrooke neighborhood to the south
.
construction of a realignment of a portion of 5th Street (along the planned
Operations and Management Facility frontage) to K-Tel Drive into a t-
Side-
track crossing, new crosswalks, a sidewalk on the south side of the street and
walk
a multi-use trail on the north side of the street. East of the realignment, a new
multi-use trail along the north right-of-way line should be constructed to 11th
Avenue. Additional enhancements envisioned include additional street trees,
landscaping and pedestrian scaled lighting.
the street should include the following elements:
Detail
A public right-of way dimension of 66
TYPICAL 5TH SECTION- 66 RIGHT-OF-WAY
Two 17 travel lanes
North Side: A 12 multi-use trail (with 5 landscaping buffer) adjacent to the
west curbline.
South Side: A 6 wide sidewalk located (with 5 landscaping buffer) adjacent
to the east curbline property line and additional 4 landscaping between the
sidewalk and adjacent development parcels.
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A56Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
47
September 21, 2015 Jt Study Session
SECONDARY STREETS
The Secondary Streets provide necessary access within the
station area and should be developed as public rights-of-way. In many instances they provide a functional role a place for access to parking, service bays
or other necessary uses. I
Their character and function will be determined by their location and adjacent land uses. Prior to future site plan approvals, the placemaking character and
Secondary Streets include:
20th Avenue
3rd Street
14th Avenue
16th Avenue
A57Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
48
September 21, 2015 Jt Study Session
SECONDARY STREETS DIAGRAM
Secondary Streets
SW LRT Alignment
H
Park
and
Ride
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A58Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
49
September 21, 2015 Jt Study Session
20TH AVENUE AND 3RD STREET
these streets provide a setting for front door
Placemaking Character
the street should include the following elements:
Detail
A public right-of way dimension of 66
Two 12 travel lanes
Two 8 curbside parking lanes
Two 13 wide sidewalks (with landscaping/hardscaping) adjacent to the
property lines
TYPICAL STREET SECTION- 66 RIGHT-OF-WAY
A59Shady Oak Road & LRT update
VISION CIRCULATION FRAMEWORK
50
September 21, 2015 Jt Study Session
14TH AVENUE AND 16TH AVENUE
these streets provide a functional role for accessing
Placemaking Character
parking, service bays or other necessary uses and do not include development
on both sides of the street.
the street should include the following elements:
Detail
A public right-of way dimension of 58
Two 12 travel lanes
One 8 curbside parking lanes adjacent to development
Two 13 wide sidewalks (with landscaping/hardscaping) adjacent to the
property lines
TYPICAL STREET SECTION- 58 RIGHT-OF-WAY
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A60Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
51
September 21, 2015 Jt Study Session
This Page Intentionally Left Blank
A61Shady Oak Road & LRT update
VISION PROJECT PHASING
52
September 21, 2015 Jt Study Session
PROJECT PHASING
INTENT
The Project Phasing includes near-term strategies for creating a viable station area. Included are both smaller tactical projects that address access needs and
larger more complex projects that will be necessary to stimulate TOD.
project will need to be addressed. Moreover, the role, responsibilities and coordination between the Cities, Metro Transit, and the private sector will need to be
ESTABLISH EARLY MOMENTUM
SPUR GAME CHANGING INVESTMENT
These projects will:
These projects will:
Establish a sense of positive change within the station area and signal to
Signal to the development community that the Cities of Minnetonka and
the greater community that Minnetonka and Hopkins are serious about
Hopkins are committed to implementing TOD in the station area
implementing the station area vision
Animate the station with residents and retail activity when light rail begins
service in 2020
result in new safe, direct and convenient access routes between existing
Attract private investment in properties that have seen little or no recent
neighborhoods, destinations such as Mainstreet, and the future light rail
development interest
station
Improve the value of existing businesses and properties
Require more time to implement than early momentum projects, as a result
dependant and reside beyond an easy ¼ mile walking distance of the station
projects can be initiated, but may not be constructed prior to construction of
platform
the Southwest LRT project
Generally occur within existing public right-of-ways and will require no or
little property acquisition or easements. As a result, they will be relatively
easy to implement compared to game changing projects.
Be implemented before the Southwest LRT project has been constructed
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A62Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
53
September 21, 2015 Jt Study Session
PROJECTS
EARLY MOMENTUM PROJECTS
City acquisition of properties, then preparation of a developer request for
proposals (RFP) to solicit interest from a private sector developer(s) who will
that provide safe pedestrian
Neighborhood-LRT Access Improvements
and bike access to the light rail station, include:
the developer offering
Multi use trails: 1) located along the north side of 5th Street between 11th
that provides necessary roadway access and utility
Street Grid Initiation
Avenue and the realigned 17th Avenue/K-Tel Drive, 2) located along the
north side of K-Tel Drive between the realigned 17th Avenue/K-Tel Drive
grid in the northwest quadrant of the station area.
and Shady Oak Road, and 3) located along Nine Mile Creek linking Central
Park and the Minnesota River Bluffs Regional Trail. Additional design and
Alignment and features: Beginning at Excelsior Boulevard, 19th Street will
be centered along existing property lines and continue south through the
Midblock crossings: a high-intensity activated crosswalk (HAWK) beacon at
western edge of the Hopkins Tech Center parcel, then continue along the
the intersection of Excelsior Boulevard at Central Park/13th Avenue and a
western edge of the parcel currently owned by the Roth Corporation, to
signalized intersection at the Minnesota River Bluffs Regional Trail and 11th
connect with 47th Street where a cul-de-sac currently exists. A dedicated left
be required
Bi-directional protected bikeway and new sidewalk: on the west side of 17th
Implementation of the project will require:
New sidewalks: on both sides of 47th Street from the 47th Street extension to
Acquisition or easement of a 66 right-of-way for roadway and utility service
construction
GAME CHANGING PROJECTS
will provide necessary parking access and
Station Access Improvements
front door drive-by visibility for the Initial TOD Site projects
that catalyze development of adjacent parcels and serve as
Initial TOD Sites
Alignment and features: An extension of 47th Street to the future 17th
examples of quality, mixed use high density residential development that establish
Avenue and the construction of the 17th Avenue extension from Excelsior
the character envisioned throughout the station area.
Boulevard to K-Tel Drive will provide access across the Minnesota River Bluffs
Site Area: three parcels comprise an approximately 5.75 acre development
Trail that does not currently exist
area. The sites are located adjacent to the Shady Oak Station platform along
Implementation of the improvements will require:
the west side of 17th Avenue from 3rd Street to the Minnesota River Bluffs
Regional Trail. The sites will be bisected by a future extension of 47th Street.
They will be developed either as multiple separate projects respecting
Acquisition or easement of a 66 right-of-way for the 47th Street roadway and
current property boundaries or possibly as a single site
utility service construction
Market Demand: The projects are time sensitivecurrently, in the Twin
Cities region, demand for multifamily development is high and these sites
Fast tracking construction of the 17th Avenue extension from Excelsior
will likely draw considerable interest from developers, with or without light
Boulevard to K-Tel Drive
rail service in place
Coordination of subsequent Southwest LRT project elements with Metro
To implement the projects, pre-development activities will be required soon,
Transit
including either of the following two options:
Preparation of a public/private partnership development agreement
between the Cities, Metro Transit, and property owners, or;
A63Shady Oak Road & LRT update
VISION PROJECT PHASING
54
September 21, 2015 Jt Study Session
STATION AREA PROJECTS
Neighborhood - LRT Access Improvements
1
Initial TOD Sites
2
(Mixed Use Residential Development)
Street Grid Initiation
1
3
(19th Avenue Roadway)
Station Access Improvements
4
(17th Avenue Segment/Station Plaza &
47th Street Extension)
1
Southwest LRT Project Area
1
3
2
4
1
2
1
EIGHTH MILEQUARTER MILEHALF MILE
06601,3202,640
A64Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
55
September 21, 2015 Jt Study Session
SCHEDULE
Action on all projects will be initiated and substantially completed within 10 years.
TIMELINE
YEAR 1YEAR 2YEAR 3YEAR 4YEAR 5YEAR 6YEAR 7YEAR 8YEAR 9YEAR 10
PROJECTS
Neighborhood - LRT Access
1
COMPLETED WITHIN 5 YEARS
Improvements
Initial TOD Sites
2
(Mixed Use Residential
INITIATED IMMEDIATELY & COMPLETED WITHIN 5 TO 7 YEARS
Development)
Street Grid Initiation
3
INITIATED IMMEDIATELY & COMPLETED WITHIN 5 TO 10 YEARS
(19th Avenue Roadway)
Station Access Improvements
4
(17th Avenue Segment/Station Plaza
INITIATED IMMEDIATELY & COMPLETED WITHIN 5 YEARS
& 47th Street Extension)
2020
Opening Day
Southwest LRT
A65Shady Oak Road & LRT update
VISION PROJECT PHASING
56
September 21, 2015 Jt Study Session
INVESTMENT - STATION AREA PROJECTS
Id
Early Momentum Public Investment SummaryGame-Changing Public Investment Summary
These are the essential public investments required to ensure safe and direct
investment within the northwest quadrant of the station area.
access to light rail.
The Game Changing Costs to Value tables and diagram below illustrates the
amount of public investment ($5,175,000) that if spent, is anticipated to stimulate
substantial private investment ($200,000,000)
ProjectProjected Cost
Game-Changing
Early Momentum ProjectProjected Cost
Initial TOD Sites (Land Assembly)$3,250,000*
2
Neighborhood-LRT Access Improvements
1
Street Grid Initiation (19th Ave)$1,350,000*
Multi-Use Trails (5th St, K-Tel Dr, & Nine Mile Crk)$767,500 3
4 Station Access Improvements (47th St Ext. Only)*$575,000*
Mid-Block Crossings (11th Ave & Excelsior Blvd)$300,000
Public Investment Total:
17th Ave Protected Bikeway (Excelsior to Mainstreet)$20,000
$5,175,000
* Costs include typical roadway improvements and wet utilities only and does not include soft costs,
Add Sidewalks (47th Street)$212,500
land costs or entitlements
Public Investment Total:
$1,300,000
Stimulated Private Investment Summary
Private Development ProjectProjected Value
350,000$89,250,000
Housing (Unit)*600$102,250,000
Commercial/Retail (SF)*30,500$8,500,000
Private Investment Total:
$200,000,000
* Includes on-site parking
$38
$1
PublicPrivate
EIGHTH MILEQUARTER MILEHALF MILE
GAME-CHANGING COSTS TO VALUE RATIO
06601,3202,640
A66Shady Oak Road & LRT update
DISCUSSION DRAFT 09/15/15
SHADY OAK STATION AREA DEVELOPMENT STRATEGY
57
September 21, 2015 Jt Study Session