VII.2. Award of Contract: VFW and Syndicate Sales Parking Lot Project, City Project 2016-07; Stanley (CR2016-043) (2)BID TABULATION SUMMARY
PROJECT:
VFW and Syndicate Sales Parking Lot Improvements
OWNER:
City of Hopkins, MN
WSB PROJECT NO.:
1502-540
Bids Opened: Tuesday, April 5, 2016 10:00 am
ContractorBid Security (5%)Schedule ASchedule BGrand Total Bid
1Northwest Asphalt, Inc.X$314,913.10$110,343.35$425,256.45
2Park Construction CompanyX$327,371.10$108,740.75$436,111.85
3Sunram ConstructionX$335,752.80$104,874.00$440,626.80
4Omann Brothers, Inc.X$349,510.00$117,434.00$466,944.00
5New Look Contracting, Inc.X$347,058.00$121,647.00$468,705.00
Engineer's Opinion of Cost$426,516.50$141,339.50$567,856.00
I hereby certify that this is a true and correct tabulation of the bids as received on April 5, 2016
Nicholas Hentges, PE Project Manager
Denotes corrected figure
K:\\01502-540\\Admin\\Construction Admin\\1502-54 Bid Tab Summary 040516
4/6/2016
WSB
Project Bid Abstract
Project Name:
Project No.: 01502-54
Client: City of Minnetonka
Bid Opening: Owner: Minneapoli
s
Park Construction
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Northwest Asphalt, Inc. Sunram Construction
Company - Mpls
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
SCHEDULE A
1 2021.501 MOBILIZATION LS 1$20,000.00$20,000.00$31,144.00$31,144.00$11,300.00$11,300.00$11,500.20$11,500.20
2 2101.511 CLEARING & GRUBBING LS 1$3,000.00$3,000.00$8,250.00$8,250.00$7,650.00$7,650.00$8,000.00$8,000.00
3 2104.501 REMOVE WOOD FENCE L F 40$15.00$600.00$10.00$400.00$10.20$408.00$12.00$480.00
4 2104.505 REMOVE BITUMINOUS PAVEMENT S Y 1630$5.00$8,150.00$2.50$4,075.00$3.20$5,216.00$3.50$5,705.00
5 2104.503 REMOVE CONCRETE WALK S F 535$4.00$2,140.00$1.00$535.00$2.10$1,123.50$1.90$1,016.50
$1,016.50
6 2104.503 REMOVE CONCRETE SLAB S F 80$14.00$1,120.00$2.50$200.00$3.90$312.00$3.90$312.00
7 2104.523 SALVAGE CASTING EACH 1$300.00$300.00$50.00$50.00$204.00$204.00$500.00$500.00
8 2104.525 ABANDON & SEAL WELL SHAFT EACH 1$5,000.00$5,000.00$2,000.00$2,000.00$765.00$765.00$2,500.00$2,500.00
9 2104.601 REMOVE CONCRETE RAMP & STAIRS LS 1$5,000.00$5,000.00$1,500.00$1,500.00$619.00$619.00$4,050.00$4,050.00
10 2104.601 REMOVE MISCELLANEOUS STRUCTURES LS 1$7,500.00$7,500.00$1,000.00$1,000.00$966.00$966.00$8,000.00$8,000.00
11 2105.501 COMMON EXCAVATION (P) C Y 1040$26.00$27,040.00$18.75$19,500.00$19.60$20,384.00$23.80$24,752.00
12 2105.521 GRANULAR BORROW (CV) (P) C Y 19$28.00$532.00$35.00$665.00$34.70$659.30$58.00$1,102.00
13 2105.522 SELECT GRANULAR BORROW (CV) (P) C Y 691$30.00$20,730.00$28.55$19,728.05$27.40$18,933.40$34.25$23,666.75
14 2105.522 SELECT GRANULAR BORROW MOD 10% (CV) (P) C Y 383$36.00$13,788.00$25.75$9,862.25$32.50$12,447.50$24.00$9,192.00
15 2211.503 AGGREGATE BASE (CV) CLASS 5 C Y 368$44.00$16,192.00$30.95$11,389.60$32.40$11,923.20$44.20$16,265.60
16 2360.501 TYPE SP 12.5 WEARING COURSE MIX (2,C) TON 560$90.00$50,400.00$77.10$43,176.00$78.50$43,960.00$78.75$44,100.00
17 2402.583 ORNAMENTAL METAL RAILING L F 150$180.00$27,000.00$187.00$28,050.00$334.00$50,100.00$180.00$27,000.00
18 2402.585 PIPE RAILING L F 55$130.00$7,150.00$135.00$7,425.00$122.00$6,710.00$135.00$7,425.00
19 2411.507 CONCRETE STAIRWAY EACH 2$9,000.00$18,000.00$5,040.00$10,080.00$5,880.00$11,760.00$6,000.00$12,000.00
20 2411.507 CONCRETE STAIRWAY EACH 1$5,000.00$5,000.00$3,465.00$3,465.00$3,580.00$3,580.00$4,000.00$4,000.00
21 2411.511 STRUCTURE EXCAVATION CLASS U C Y 281$40.00$11,240.00$25.00$7,025.00$22.90$6,434.90$24.15$6,786.15
22 2411.604 MODULAR BLOCK RETAINING WALL SPECIAL S Y 175$525.00$91,875.00$315.00$55,125.00$305.00$53,375.00$306.00$53,550.00
23 2411.618 MODULAR BLOCK RETAINING WALL S F 256$34.00$8,704.00$25.20$6,451.20$24.50$6,272.00$28.60$7,321.60
1
24 2411.618 ANTI-GRAFFITI COATING S F 1575$6.00$9,450.00$1.35$2,126.25$1.30$2,047.50$2.10$3,307.50
Park Construction
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Northwest Asphalt, Inc. Sunram Construction
Company - Mpls
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
25 2411.618 ARCH SURFACE FINISH (MULTI COLOR) S F 1575$7.00$11,025.00$3.95$6,221.25$3.85$6,063.75$4.75$7,481.25
26 2503.541 15" RC PIPE SEWER DES 3006 CL V L F 51$75.00$3,825.00$38.00$1,938.00$66.30$3,381.30$56.25$2,868.75
27 2503.602 CONNECT TO EXISTING STORM SEWER EACH 1$1,200.00$1,200.00$1,000.00$1,000.00$714.00$714.00$800.00$800.00
28 2506.502 CONST DRAINAGE STRUCTURE DESIGN SPECIAL EACH 1$2,500.00$2,500.00$1,500.00$1,500.00$4,600.00$4,600.00$3,100.00$3,100.00
29 2506.503 RECONSTRUCT DRAINAGE STRUCTURE L F 7$500.00$3,500.00$350.00$2,450.00$255.00$1,785.00$440.00$3,080.00
30 2506.516 CASTING ASSEMBLY EACH 1$800.00$800.00$550.00$550.00$459.00$459.00$800.00$800.00
31 2506.521 INSTALL CASTING EACH 1$450.00$450.00$100.00$100.00$255.00$255.00$350.00$350.00
32 2506.522 ADJUST FRAME & RING CASTING EACH 1$700.00$700.00$500.00$500.00$765.00$765.00$350.00$350.00
33 2521.501 4" CONCRETE WALK S F 1187$8.50$10,089.50$5.50$6,528.50$6.30$7,478.10$5.00$5,935.00
34 2531.501 CONCRETE CURB & GUTTER DESIGN B612 L F 280$35.00$9,800.00$20.00$5,600.00$20.20$5,656.00$20.00$5,600.00
35 2531.502 CONCRETE CURB DESIGN V10 (MODIFIED) L F 62$50.00$3,100.00$76.50$4,743.00$101.00$6,262.00$76.50$4,743.00
36 2557.603 WOODEN FENCE L F 20$60.00$1,200.00$50.00$1,000.00$51.00$1,020.00$75.00$1,500.00
37 2563.601 TRAFFIC CONTROL LS 1$2,500.00$2,500.00$1,000.00$1,000.00$1,020.00$1,020.00$5,000.00$5,000.00
38 2564.531 SIGN PANELS TYPE C S F 7$100.00$700.00$50.00$350.00$45.90$321.30$50.00$350.00
39 2573.502 SILT FENCE, TYPE MS L F 385$5.00$1,925.00$3.00$1,155.00$2.55$981.75$3.50$1,347.50
40 2573.530 STORM DRAIN INLET PROTECTION EACH 5$275.00$1,375.00$150.00$750.00$204.00$1,020.00$125.00$625.00
41 2573.535 STABILIZED CONSTRUCTION EXIT LS 1$1,500.00$1,500.00$500.00$500.00$954.00$954.00$800.00$800.00
42 2574.525 LOAM TOPSOIL BORROW C Y 38$52.00$1,976.00$35.00$1,330.00$54.20$2,059.60$90.00$3,420.00
43 2575.505 SODDING TYPE SALT TOLERANT S Y 130$18.00$2,340.00$11.50$1,495.00$11.70$1,521.00$15.00$1,950.00
44 2582.501 PAVT MSSG (HANDICAPPED SYMBOL) EPOXY EACH 4$175.00$700.00$115.00$460.00$151.00$604.00$120.00$480.00
45 2582.502 4" SOLID LINE WHITE-EPOXY L F 1200$4.50$5,400.00$2.10$2,520.00$2.75$3,300.00$2.20$2,640.00
Total SCHEDULE A: $426,516.50 $314,913.10 $327,371.10 $335,752.80
$314,913.10 $335,752.80
Schedule B
46 2021.501 MOBILIZATION LS 1$5,000.00$5,000.00$14,283.00$14,283.00$4,780.00$4,780.00$6,000.05$6,000.05
47 2104.501 REMOVE RETAINING WALL L F 10$15.00$150.00$20.00$200.00$21.50$215.00$50.00$500.00
48 2105.501 COMMON EXCAVATION (P) C Y 150$28.00$4,200.00$30.00$4,500.00$21.60$3,240.00$23.80$3,570.00
49 2105.522 SELECT GRANULAR BORROW (CV) (P) C Y 150$32.00$4,800.00$28.55$4,282.50$27.10$4,065.00$34.25$5,137.50
50 2105.522 SELECT GRANULAR BORROW MOD 10% (CV) (P) C Y 350$36.00$12,600.00$25.75$9,012.50$27.10$9,485.00$24.00$8,400.00
51 2105.523 COMMON BORROW (CV) C Y 200$38.00$7,600.00$20.00$4,000.00$17.00$3,400.00$24.00$4,800.00
52 2211.503 AGGREGATE BASE (CV) CLASS 5 C Y 78$48.00$3,744.00$30.00$2,340.00$37.30$2,909.40$44.20$3,447.60
53 2360.501 TYPE SP 12.5 WEARING COURSE MIX (2,C) TON 95$95.00$9,025.00$86.80$8,246.00$87.10$8,274.50$100.00$9,500.00
54 2402.583 ORNAMENTAL METAL RAILING L F 58$180.00$10,440.00$187.00$10,846.00$334.00$19,372.00$180.00$10,440.00
55 2411.511 STRUCTURE EXCAVATION CLASS U C Y 40$40.00$1,600.00$30.00$1,200.00$39.70$1,588.00$24.15$966.00
56 2411.604 MODULAR BLOCK RETAINING WALL SPECIAL S Y 91$525.00$47,775.00$315.00$28,665.00$305.00$27,755.00$306.00$27,846.00
57 2411.618 ANTI-GRAFFITI COATING S F 819$6.00$4,914.00$1.35$1,105.65$1.30$1,064.70$2.10$1,719.90
2
Park Construction
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Northwest Asphalt, Inc. Sunram Construction
Company - Mpls
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
58 2411.618 ARCH SURFACE FINISH (MULTI COLOR) S F 819$7.00$5,733.00$3.95$3,235.05$3.85$3,153.15$4.75$3,890.25
59 2504.602 ADJUST GATE VALVE & BOX EACH 1$550.00$550.00$350.00$350.00$255.00$255.00$500.00$500.00
60 2521.501 4" CONCRETE WALK S F 853$9.50$8,103.50$5.55$4,734.15$6.30$5,373.90$5.00$4,265.00
61 2531.501 CONCRETE CURB & GUTTER DESIGN B612 L F 195$35.00$6,825.00$22.50$4,387.50$20.50$3,997.50$22.50$4,387.50
62 2531.502 CONCRETE CURB DESIGN V10 L F 63$50.00$3,150.00$73.00$4,599.00$86.70$5,462.10$73.00$4,599.00
63 2531.618 TRUNCATED DOMES S F 10$70.00$700.00$147.00$1,470.00$56.10$561.00$147.00$1,470.00
64 2564.531 SIGN PANELS TYPE C S F 2$100.00$200.00$75.00$150.00$66.30$132.60$100.00$200.00
65 2573.502 SILT FENCE, TYPE MS L F 150$5.00$750.00$4.50$675.00$4.10$615.00$3.50$525.00
66 2573.530 STORM DRAIN INLET PROTECTION EACH 1$275.00$275.00$150.00$150.00$204.00$204.00$125.00$125.00
67 2573.535 STABILIZED CONSTRUCTION EXIT LS 1$1,500.00$1,500.00$500.00$500.00$954.00$954.00$800.00$800.00
68 2574.525 LOAM TOPSOIL BORROW C Y 9$52.00$468.00$35.00$315.00$72.10$648.90$90.00$810.00
69 2575.505 SODDING TYPE SALT TOLERANT S Y 30$18.00$540.00$25.00$750.00$25.50$765.00$20.00$600.00
70 2582.501 PAVT MSSG (HANDICAPPED SYMBOL) EPOXY EACH 1$175.00$175.00$115.00$115.00$151.00$151.00$120.00$120.00
71 2582.502 4" SOLID LINE WHITE-EPOXY L F 116$4.50$522.00$2.00$232.00$2.75$319.00$2.20$255.20
Total Schedule B: $141,339.50 $110,343.35 $108,740.75 $104,874.00
Total SCHEDULE A: $426,516.50 $314,913.10 $327,371.10 $335,752.80
$314,913.10
Total Schedule B: $141,339.50 $110,343.35 $108,740.75 $104,874.00
$108,740.75
Totals for Project 01502-54 $567,856.00 $425,256.45 $436,111.85 $440,626.80
$425,256.45 $436,111.85 $440,626.80
% of Estimate for Project 01502-54 -25.11% -23.20% -22.41%
3
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Omann Brothers, Inc. New Look Contracting, Inc.
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
SCHEDULE A
1 2021.501 MOBILIZATION LS 1$20,000.00$20,000.00$15,000.00$15,000.00$12,000.00$12,000.00
2 2101.511 CLEARING & GRUBBING LS 1$3,000.00$3,000.00$10,500.00$10,500.00$12,000.00$12,000.00
3 2104.501 REMOVE WOOD FENCE L F 40$15.00$600.00$12.50$500.00$14.00$560.00
4 2104.505 REMOVE BITUMINOUS PAVEMENT S Y 1630$5.00$8,150.00$8.70$14,181.00$6.00$9,780.00
5 2104.503 REMOVE CONCRETE WALK S F 535$4.00$2,140.00$3.00$1,605.00$2.00$1,070.00
6 2104.503 REMOVE CONCRETE SLAB S F 80$14.00$1,120.00$3.00$240.00$18.00$1,440.00
7 2104.523 SALVAGE CASTING EACH 1$300.00$300.00$100.00$100.00$100.00$100.00
8 2104.525 ABANDON & SEAL WELL SHAFT EACH 1$5,000.00$5,000.00$6,000.00$6,000.00$2,450.00$2,450.00
9 2104.601 REMOVE CONCRETE RAMP & STAIRS LS 1$5,000.00$5,000.00$1,500.00$1,500.00$2,500.00$2,500.00
10 2104.601 REMOVE MISCELLANEOUS STRUCTURES LS 1$7,500.00$7,500.00$2,500.00$2,500.00$5,550.00$5,550.00
11 2105.501 COMMON EXCAVATION (P) C Y 1040$26.00$27,040.00$25.00$26,000.00$20.00$20,800.00
12 2105.521 GRANULAR BORROW (CV) (P) C Y 19$28.00$532.00$65.00$1,235.00$65.00$1,235.00
13 2105.522 SELECT GRANULAR BORROW (CV) (P) C Y 691$30.00$20,730.00$38.35$26,499.85$25.00$17,275.00
14 2105.522 SELECT GRANULAR BORROW MOD 10% (CV) (P) C Y 383$36.00$13,788.00$48.00$18,384.00$25.00$9,575.00
15 2211.503 AGGREGATE BASE (CV) CLASS 5 C Y 368$44.00$16,192.00$54.30$19,982.40$42.00$15,456.00
16 2360.501 TYPE SP 12.5 WEARING COURSE MIX (2,C) TON 560$90.00$50,400.00$77.50$43,400.00$98.00$54,880.00
17 2402.583 ORNAMENTAL METAL RAILING L F 150$180.00$27,000.00$175.00$26,250.00$215.00$32,250.00
18 2402.585 PIPE RAILING L F 55$130.00$7,150.00$125.00$6,875.00$155.00$8,525.00
19 2411.507 CONCRETE STAIRWAY EACH 2$9,000.00$18,000.00$3,300.00$6,600.00$2,250.00$4,500.00
20 2411.507 CONCRETE STAIRWAY EACH 1$5,000.00$5,000.00$2,800.00$2,800.00$2,250.00$2,250.00
21 2411.511 STRUCTURE EXCAVATION CLASS U C Y 281$40.00$11,240.00$25.00$7,025.00$22.00$6,182.00
22 2411.604 MODULAR BLOCK RETAINING WALL SPECIAL S Y 175$525.00$91,875.00$310.00$54,250.00$362.00$63,350.00
23 2411.618 MODULAR BLOCK RETAINING WALL S F 256$34.00$8,704.00$25.25$6,464.00$29.00$7,424.00
24 2411.618 ANTI-GRAFFITI COATING S F 1575$6.00$9,450.00$1.30$2,047.50$1.00$1,575.00
25 2411.618 ARCH SURFACE FINISH (MULTI COLOR) S F 1575$7.00$11,025.00$3.95$6,221.25$4.00$6,300.00
26 2503.541 15" RC PIPE SEWER DES 3006 CL V L F 51$75.00$3,825.00$65.00$3,315.00$50.00$2,550.00
27 2503.602 CONNECT TO EXISTING STORM SEWER EACH 1$1,200.00$1,200.00$1,500.00$1,500.00$550.00$550.00
28 2506.502 CONST DRAINAGE STRUCTURE DESIGN SPECIAL EACH 1$2,500.00$2,500.00$1,250.00$1,250.00$1,250.00$1,250.00
29 2506.503 RECONSTRUCT DRAINAGE STRUCTURE L F 7$500.00$3,500.00$1,000.00$7,000.00$825.00$5,775.00
30 2506.516 CASTING ASSEMBLY EACH 1$800.00$800.00$400.00$400.00$750.00$750.00
31 2506.521 INSTALL CASTING EACH 1$450.00$450.00$200.00$200.00$600.00$600.00
32 2506.522 ADJUST FRAME & RING CASTING EACH 1$700.00$700.00$150.00$150.00$600.00$600.00
33 2521.501 4" CONCRETE WALK S F 1187$8.50$10,089.50$4.75$5,638.25$6.00$7,122.00
34 2531.501 CONCRETE CURB & GUTTER DESIGN B612 L F 280$35.00$9,800.00$26.25$7,350.00$32.00$8,960.00
4
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Omann Brothers, Inc. New Look Contracting, Inc.
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
35 2531.502 CONCRETE CURB DESIGN V10 (MODIFIED) L F 62$50.00$3,100.00$42.00$2,604.00$43.00$2,666.00
36 2557.603 WOODEN FENCE L F 20$60.00$1,200.00$55.00$1,100.00$100.00$2,000.00
37 2563.601 TRAFFIC CONTROL LS 1$2,500.00$2,500.00$500.00$500.00$1,500.00$1,500.00
38 2564.531 SIGN PANELS TYPE C S F 7$100.00$700.00$210.00$1,470.00$125.00$875.00
39 2573.502 SILT FENCE, TYPE MS L F 385$5.00$1,925.00$3.15$1,212.75$3.00$1,155.00
40 2573.530 STORM DRAIN INLET PROTECTION EACH 5$275.00$1,375.00$125.00$625.00$350.00$1,750.00
41 2573.535 STABILIZED CONSTRUCTION EXIT LS 1$1,500.00$1,500.00$2,000.00$2,000.00$1,500.00$1,500.00
42 2574.525 LOAM TOPSOIL BORROW C Y 38$52.00$1,976.00$65.00$2,470.00$36.00$1,368.00
43 2575.505 SODDING TYPE SALT TOLERANT S Y 130$18.00$2,340.00$10.50$1,365.00$22.00$2,860.00
44 2582.501 PAVT MSSG (HANDICAPPED SYMBOL) EPOXY EACH 4$175.00$700.00$125.00$500.00$150.00$600.00
45 2582.502 4" SOLID LINE WHITE-EPOXY L F 1200$4.50$5,400.00$2.25$2,700.00$3.00$3,600.00
Total SCHEDULE A: $426,516.50 $349,510.00 $347,058.00
Schedule B
46 2021.501 MOBILIZATION LS 1$5,000.00$5,000.00$5,000.00$5,000.00$7,500.00$7,500.00
47 2104.501 REMOVE RETAINING WALL L F 10$15.00$150.00$50.00$500.00$38.00$380.00
48 2105.501 COMMON EXCAVATION (P) C Y 150$28.00$4,200.00$25.00$3,750.00$30.00$4,500.00
49 2105.522 SELECT GRANULAR BORROW (CV) (P) C Y 150$32.00$4,800.00$50.00$7,500.00$32.00$4,800.00
50 2105.522 SELECT GRANULAR BORROW MOD 10% (CV) (P) C Y 350$36.00$12,600.00$48.00$16,800.00$32.00$11,200.00
51 2105.523 COMMON BORROW (CV) C Y 200$38.00$7,600.00$30.00$6,000.00$32.00$6,400.00
52 2211.503 AGGREGATE BASE (CV) CLASS 5 C Y 78$48.00$3,744.00$75.00$5,850.00$53.00$4,134.00
53 2360.501 TYPE SP 12.5 WEARING COURSE MIX (2,C) TON 95$95.00$9,025.00$105.50$10,022.50$110.00$10,450.00
54 2402.583 ORNAMENTAL METAL RAILING L F 58$180.00$10,440.00$175.00$10,150.00$215.00$12,470.00
55 2411.511 STRUCTURE EXCAVATION CLASS U C Y 40$40.00$1,600.00$50.00$2,000.00$36.00$1,440.00
56 2411.604 MODULAR BLOCK RETAINING WALL SPECIAL S Y 91$525.00$47,775.00$310.00$28,210.00$365.00$33,215.00
57 2411.618 ANTI-GRAFFITI COATING S F 819$6.00$4,914.00$1.30$1,064.70$2.00$1,638.00
58 2411.618 ARCH SURFACE FINISH (MULTI COLOR) S F 819$7.00$5,733.00$3.95$3,235.05$5.00$4,095.00
59 2504.602 ADJUST GATE VALVE & BOX EACH 1$550.00$550.00$250.00$250.00$600.00$600.00
60 2521.501 4" CONCRETE WALK S F 853$9.50$8,103.50$4.50$3,838.50$6.00$5,118.00
61 2531.501 CONCRETE CURB & GUTTER DESIGN B612 L F 195$35.00$6,825.00$26.25$5,118.75$33.00$6,435.00
62 2531.502 CONCRETE CURB DESIGN V10 L F 63$50.00$3,150.00$42.00$2,646.00$40.00$2,520.00
63 2531.618 TRUNCATED DOMES S F 10$70.00$700.00$55.00$550.00$72.00$720.00
64 2564.531 SIGN PANELS TYPE C S F 2$100.00$200.00$275.00$550.00$125.00$250.00
65 2573.502 SILT FENCE, TYPE MS L F 150$5.00$750.00$3.25$487.50$3.00$450.00
66 2573.530 STORM DRAIN INLET PROTECTION EACH 1$275.00$275.00$125.00$125.00$350.00$350.00
67 2573.535 STABILIZED CONSTRUCTION EXIT LS 1$1,500.00$1,500.00$2,500.00$2,500.00$1,500.00$1,500.00
5
Project: 01502-54 - MTKA - Downtown Business Lots Engineers Estimate Omann Brothers, Inc. New Look Contracting, Inc.
Line No. Item Units QuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
68 2574.525 LOAM TOPSOIL BORROW C Y 9$52.00$468.00$65.00$585.00$36.00$324.00
69 2575.505 SODDING TYPE SALT TOLERANT S Y 30$18.00$540.00$10.50$315.00$22.00$660.00
70 2582.501 PAVT MSSG (HANDICAPPED SYMBOL) EPOXY EACH 1$175.00$175.00$125.00$125.00$150.00$150.00
71 2582.502 4" SOLID LINE WHITE-EPOXY L F 116$4.50$522.00$2.25$261.00$3.00$348.00
Total Schedule B: $141,339.50 $117,434.00 $121,647.00
Total SCHEDULE A: $426,516.50 $349,510.00 $347,058.00
Total Schedule B: $141,339.50 $117,434.00 $121,647.00
Totals for Project 01502-54 $567,856.00 $466,944.00 $468,705.00
% of Estimate for Project 01502-54 -17.77% -17.46%
I hereby certify that this is an exact reproduction of bids received.
Certified By: License No.
Date:
6
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2016-037
RESOLUTION FOR AWARD OF CONTRACT
VFW AND SYNDICATE SALES PARKING LOT PROJECT
CITY PROJECT 2016-07
BE IT RESOLVED BY THE CITY COUNCIL OF HOPKINS, MINNESOTA
, that
the lowest bid of Northwest Asphalt, Inc. in the amount of $425,256.45 is the lowest responsible
bid for the VFW and Syndicate Sales Parking Lot Project, City Project 2016-07, and the Mayor
and City Manager are hereby authorized and directed to enter into a contract with said bidder for
and on behalf of the City.
th
Adopted by the City Council of the City of Hopkins, Minnesota, this 19 day of April, 2016.
By___________________________________
Molly Cummings, Mayor
ATTEST:
_____________________________________
Amy Domeier, City Clerk
C:\\Users\\adomeier\\AppData\\Local\\Microsoft\\Windows\\Temporary Internet Files\\Content.Outlook\\3394JZ13\\R2016-037 Award
Contract VFW Parking Lot Project (2).docx