Loading...
VII.4. Approve Engineering Services Proposal for Blake Road Improvement Project, City Project 2013-06; May 17, 2016 Council Report 2016-053 APPROVE ENGINEERING SERVICES PROPOSAL BLAKE ROAD IMPROVEMENT PROJECT CITY PROJECT 2013-06 Proposed Action Staff recommends the following motion: adopt Resolution 2016-043, Resolution Approving Proposal for Engineering Services, Blake Road Improvement Project, City Project 2013-06. Overview Last year, a corridor study for Blake Road was completed and accepted by the City Council. The recommendations in the study will serve as the basis for final design of Blake Road. WSB & Associates is the consultant that administered the study, staff has been negotiating with WSB to complete final design, right-of way acquisition, and construction administration for the Blake Road Improvement Project. Primary Issues to Consider Background Consultant Selection, Scope and Fee Project Schedule Supporting Information Engineering Services Proposal Resolutions 2016-043 _________________________________ Nate Stanley, P.E., City Engineer Financial Impact: $579,170 Budgeted: Y/N _Y_ Source: _PIR, SA, Water, Sanitary, Storm Related Documents (CIP, ERP, etc.): CIP _ Notes: _________________________________________ Council Report 2016-053 Page 2 ANALYSIS OF ISSUES Background A corridor study was completed last year to serve as a basis for guiding reconstruction of the corridor. Several different factors and goals served as both the basis for development of recommendations in the corridor study. Considerations for traffic operations, safety, pedestrian and bicycle comfort, access, construction impacts, economic development potential, environmental impacts, cost, and long term maintenance all played a role. Between Interlachen Boulevard and Excelsior Boulevard the road section is recommended to remain a two-lane section with on-road bike lanes. A sidewalk is recommended to be added on the west side of the roadway from Maloney Avenue to Excelsior Boulevard. Between Excelsior Boulevard and Trunk Highway 7 (TH 7) the recommended cross-section for the road is a four-lane divided roadway with a multi-use trail on both sides of Blake Road. Additional turn lanes are proposed at key locations. Signalized intersection control is recommended to remain where it currently exists. Traffic lanes through the corridor are recommended to be narrowed to create boulevard space for landscape and hardscape treatments. Marked pedestrian crossings with flashing beacons away from fully controlled intersections are proposed at high pedestrian traffic locations. North of TH 7 the recommended cross-section is a four-lane divided roadway with a multi-use trail on both sides of Aquila Avenue. The southbound Aquila Avenue to westbound TH 7 ramp is recommended for removal, which would require traffic to make a right at the controlled intersection of Aquila Avenue and TH 7. Multiple public open houses were held over the course of the study process. Comments on the preliminary layout and recommendations were generally positive. The project team also participated in other public events to engage residents and property owners, and worked with civic groups who have an interest in the corridor. Consultant Selection, Scope, and Fee The agreement between Hennepin County and the City of Hopkins specifies that this will be a city led project, so City staff solicited a “turn-key” proposal for engineering services from WSB & Associates. This firm has provided excellent service on several past city projects, including the Blake Road Corridor Study. WSB also has extensive experience on past Hennepin County road projects in all phases of project development and construction. Staff believes the value of a quality consultant with a proven track record is important to a successful project, and has selected WSB & Associates for those reasons. During development of the scope and fee staff directed WSB to reach out to the cities of St. Louis Park and Edina, to see if they were at a point where they would like the corridor improvements within their boundaries incorporated into the plans. Both cities declined to participate in the project at this time; this will not affect the project within Hopkins. Council Report 2016-053 Page 3 The project scope includes all elements of final design including final construction plan development, project management, public outreach and involvement, permitting, coordination with other agencies, surveying, geotechnical evaluation, private utility coordination, environmental review and documentation, and landscape/streetscape design. Right-of-way acquisition services and construction services including, inspection, testing, management, and communication with the public are also included in this scope. The proposed fee for the services totals to $2,447,570. A breakdown of how the design services will be funded is provided below. The percentages used to calculate the cost distribution is specified in the interagency agreement between Hennepin County and the City. Task Hennepin County City of Hopkins Total Task Cost Final Design Services $1,038,000 $114,570 $1,152,570 Right-of-Way Acquisition 145,000 145,000 Construction Services 830,400 319,600 1,150,000 Total $1,868,400 $579,170 $2,447,570 The percentage of what the City is responsible for paying for design and construction services for this project is comparable to past county road projects. In this case the costs are distributed in a slightly different way, but the overall total is in line with City expectations. Funding for the Blake Road Improvement Project has been identified in the current CIP and is budgeted. Project Schedule Final Design, Plan Development, and Permitting May 2016 – November 2017 Advertise for Bids December 2017 Award Construction Contract January/February 2018 Begin Construction April 2018 Complete Construction November 2019 Staff Recommendation Staff recommends approving the proposal for engineering services for Blake Road with adoption of resolution 2016-043. Building a legacy – your legacy. 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 Equal Opportunity Employer wsbeng.com C:\Users\theppelmann\Documents\Blake Proposal Transmittal Letter.docx May 12, 2016 Mr. Nathan Stanley, PE City Engineer 101 1st St S Hopkins, MN 55343 Re: Blake Road Proposal Dear Mr. Stanley WSB is pleased to submit the attached proposal for engineering services for the Final Design and Construction of Blake Road from the south City limits to TH 7. WSB understands the City of Hopkins is looking for a turnkey approach that will take the project from the current preliminary layout through final plans, right-of-way acquisition, and construction administration. We also understand that this is a high profile project within the City of Hopkins and that it is important to involve all stakeholders in a fully transparent design process that will result in a project the entire community can be proud of. Our proposal includes completion of the final design and preparation of construction plans, right-of-way acquisition, and construction services. We have included significant public information and involvement in all phases of the project in order to involve residents and businesses in the design process and to keep them informed during the construction process. WSB commits to the City of Hopkins our top staff who have worked on previous phases of this project and who have completed many other similar projects in the Twin Cities Metro Area. WSB is committed to delivering a high quality project on time and within budget. Sincerely, WSB & Associates, Inc. Anthony Heppelmann, PE Vice President Blake Road Proposal 1 May 10, 2016 Proposal for Engineering Services for Blake Road from South City Limits to TH 7 This proposal is to provide engineering services for the final design and construction of Blake Road from just south of Excelsior Boulevard to the intersection with TH 7 in the City of Hopkins. Project Scope This proposal is based on the Final Preferred Layout for Blake Road dated April 9, 2015 and the cost estimate dated April 24, 2015. The project includes reconstruction of Blake Road from approximately the Blake School entrance south of Excelsior Boulevard to just south of the intersection with TH 7 and the construction of sidewalk on the west side of Blake Road to the southern City limits. It is assumed that the project will end at the TH 7 intersection on the north and will not involve any major work on TH 7. The project includes total reconstruction of Blake Road. The road will be converted from the existing five lane section to a four lane divided roadway with 10 foot wide multi-purpose trails on both sides of Blake Road. It is assumed that the existing bridge over Minnehaha Creek will be retained. It is assumed that retaining walls will be required to minimize the land use impacts of the project particularly in the area of the Cold Storage site and between Cambridge Street and TH 7. Also included in this work is the replacement of sewer and water lines as appropriate. The project must coordinate with improvements constructed as part of the SWLRT project at the HCRRA corridor. The goal of this work is to complete final design and construction plans for the project, assist the City in the acquisition of the necessary right-of-way for the project and provide construction administration, construction observation, construction staking and materials testing during construction. The Final Preferred Layout provides the overall direction for the final design and construction plans but there are still numerous issues to be resolved in the final design process including; consistency with the design for the Blake Road Station, coordination with the Three Rivers Park trail underpass, coordination with the planning for development on the Cold Storage site, consistency with the design for Cottageville Park, coordination with Edina and St. Louis Park, coordination with MnDOT on the design for the TH 7 intersection, and development of an overall landscape and aesthetic design concept for the corridor. The first step in the design process will be to refine the Final Preferred Layout based on discussions with the affected stakeholders and adjacent property owners and to develop an overall concept plan for the landscaping and aesthetic design treatments in the corridor. Final construction plans will be developed based on this revised plan. The specific work tasks that will be completed include the following. Final Design and Construction Plans Project Management Administration—This task includes monitoring and updating of the project budget and schedule, preparation of monthly invoices and progress reports, and ensuring the availability of the required Blake Road Proposal 2 May 10, 2016 project staff and resources. WSB will prepare a Project Management Plan that will provide direction on the reports and project documentation that will be provided to the City to keep the City informed regarding the project progress and issues. Also included in this task is preparation of subconsultant contracts or amendments as needed for the project. Coordination – This task involves coordination with the City staff and WSB’s team. It also includes internal coordination between team members. WSB will hold regular meetings with City staff or Project Manager to discuss project progress, potential issues and strategy. Quality Reviews—WSB will prepare a Quality Assurance and Quality Control Plan for the project that will identify the specific quality control procedures that will be followed on the project to ensure project quality. WSB will assign a Quality Assurance Manager to verify that the identified procedures are being followed and identify appropriate changes if the project is not in compliance with the identified procedures. Attached to this proposal is a brief description of WSB’s Quality Review process. Public/Agency Involvement WSB will prepare a Public/Agency Involvement Plan that will identify the affected stakeholders and the techniques and schedule for coordinating with the stakeholders during the project development and design. It is anticipated that the following activities will be part of the Public/Agency Involvement Plan Citizen Advisory Committee- WSB will work with the City of Hopkins to establish a Citizen Advisory Committee to provide input and direction on the streetscape elements for Blake road. The committee would be established based on a solicitation at the first open house and through discussions with staff and neighborhood groups. The CAC’s role would be to provide direction on areas of focus within the corridor, potential themes for the corridor and areas of focus, and the potential for public art in the corridor. It is expected that the CAC will meet approximately 8 times over the course of the study. City Council—We have assumed 4 updates to the City Council over the course of the project. We expect that two of the meetings would occur during the final design and right-of-way acquisition and that two would occur during construction. These updates are assumed to be independent of specific items associated with right-of-way acquisition that would require specific council approval. Open House—We have assumed 4 open houses. We would anticipate that the one of the open houses would be to get final input on major design details and another would be held around the construction bidding to get input on construction schedule and staging. The other two open houses would be scheduled as appropriate. Website—WSB will create and maintain a website that links to the City’s website. WSB will post project information on the website as appropriate to keep the public current during the design and construction of the project. Notices/Newsletters—WSB will prepare and mail all notices for public meetings. WSB will also prepare and mail 4 newsletters during the design phase of the project to keep the public informed of the project progress. WSB will work with the City to obtain mailing addresses. Blake Road Proposal 3 May 10, 2016 Property Owner Meetings – WSB has budgeted for 20 property owner meetings during the design phase of the project. This is independent of the right-of-way acquisition process. The property owner meetings would be to discuss the design with affected property owners individually in order to minimize impacts and to discuss streetscape elements and their needs and desires for street-scaping elements along the corridor. Agency Coordination Meetings—The purpose of the agency coordination meetings is to ensure that the design meets the requirements for agency permitting and approvals. Included in these meetings are meetings necessary for the following: • SWLRT Design Coordination • Coordination with Three Rivers Park design for Cedar Lake Trail underpass • Coordination with Minnehaha Creek Watershed on design by Cold Storage Site and Cottageville Park • Metro Council Environmental Services L27 lift station project Design Surveys WSB will collect existing information on right-of-way boundaries and parcel boundaries for the corridor. The information to be collected includes: • Geographical Information System (G.I.S.) Parcel Mapping • Existing right-of-way plats • Existing subdivision plats • Existing street and utility easements of record • Section corner ties and section calculation sheets • Geodetic control datum • County half-section maps • Ownership and Encumbrance Reports on adjoining parcels. WSB will conduct a field survey of critical right-of-way information and topographic information that can be used for design purposes. Survey control will be established and utilized to prepare a complete topographical survey of the project site. The field survey will include spot elevations, cross-sections, centerline profiles, all existing features and underground/overhead utilities. The survey data will be collected electronically in the field and downloaded directly to the project CAD file in the office. Geotechnical Services Subsurface exploration and testing, laboratory testing and engineering review will be completed for the purpose of providing Foundation Reports for retaining walls, and a Design Recommendations Report for pavements and embankments. This work will comply with accepted practices under Mn/DOTs Drilling Specifications. This will include the use of calibrated test hammers, appropriate test frequencies and meeting lab test requirements. Blake Road Proposal 4 May 10, 2016 Drainage Studies The drainage study must resolve drainage issues for Blake Road and determine what drainage improvements are required to meet state and local requirements for rate control, volume control, and storm water treatment. WSB will work with the Minnehaha Creek Watershed District staff in developing the drainage plan for the corridor. We will also coordinate with the SWLRT project office to ensure that the plan is consistent with plans that have been developed for the SWLRT. The tasks that will be completed to accomplish this include: Data Collection. This part of the work effort consists of gathering relevant water resource-related information for the drainage areas tributary to the project limits. • Water resource related agreements • As-built drawings of the existing trunk storm water conveyance system • Water resource related ordinances such as shoreland, floodplain, erosion control, storm water, and/or wetland ordinances • Existing storm water policies for the City of Hopkins, Edina and St. Louis Park as well as the Minnehaha Creek Watershed. • Available topographic maps • Existing hydraulic/hydrologic models WSB has collected most of this information during previous studies. We will confirm we have the latest information from the following agencies: Hennepin County, City of Hopkins, Minnehaha Creek Watershed, Minnesota Department of Transportation, and City of St. Louis Park. Develop Preliminary Drainage Study. The water resources data collected as part of the previous tasks and studies will be used to develop the Preliminary Drainage Study. The Preliminary Drainage Study will build on the work previously completed for this area and will include the following: • Determination of impacts of the proposed construction, including an increase in runoff rate and pollutant loading, it any. • Preliminary layout of proposed storm water conveyance system. • Preliminary discussion of possible storm water treatment systems. Present Preliminary Drainage Study. The Preliminary Drainage Study will be discussed with the affected stakeholders to get input on the proposed plan. Develop Final Drainage Study. With the input received from stakeholders a Final Drainage Plan will be developed that will meet the permitting agency requirements. Environmental Documentation The project involves the reconstruction of an existing roadway. The proposed improvements will not add additional travel lanes and will not add a new interchange. At the present time the project does not have federal funding. As a result the project does not require the preparation of any state or federal Blake Road Proposal 5 May 10, 2016 environmental document. Permits will be required for storm water drainage and potentially for modifications to water or sanitary sewer. WSB will prepare a list of permit requirements that should be addressed in final design. Our estimate assumes that no additional environmental documentation will be required. We will complete an environmental scan to identify the permits needed and any potential impacts on the project costs. Approved Project Layout/Construction Limits WSB will prepare a final layout for approval by the City of Hopkins and Hennepin County based on the final preferred layout dated April 9th, 2015. It is assumed that the general cross-section and plan on the final preferred layout are set but that minor changes in alignment and grade can be made to minimize cost and right-of-way needs. The layout will meet Hennepin County requirements and will include horizontal and vertical alignments, cross-sections and construction limits. WSB will work with the City of Hopkins and Hennepin County to adjust alignment and profile in order to minimize the project right-of- way needs. The layout will be developed in coordination with adjacent property owners in order to create a plan that works well for both the roadway and the adjacent properties. Locations for retaining walls and storm water treatment will be identified. WSB will meet with the SWLRT project office, Minnehaha Creek Watershed District and other key property owners in developing the final layout. The final layout will be presented to the Hopkins City Council for approval. Streetscape Design Develop / refine streetscape concepts: In coordination with Hopkins staff, WSB will establish, facilitate and coordinate a Citizen’s Advisory Committee (CAC) to provide input on and inform the streetscape elements. A public meeting will be planned to collect ideas and input on streetscape elements and explore tradeoffs. Public art and theming will be topics of discussion. This meeting may also be used to solicit interest in participation in the CAC. Following the public meeting WSB will identify potential areas of focus within the corridor and develop up to five (5) themes for review by the CAC. WSB will prepare sections, plan enlargements, and up to 10 renderings to aid in review of design approach, themes and potential areas of focus, the options will then be presented to the CAC. After selection of the corridor theme and areas of focus, WSB will work with City Staff to identify thematic elements along the corridor and determine which elements would be available for use as a vessel for public art or customization. Once elements have been identified and approved by City Staff, the options will be presented to the CAC. WSB will also coordinate with City staff to develop a formal Artist RFP to actively engage in the streetscape planning and design process. Approval of design concepts will lead to preparation of construction documents. Construction Documents: Once the design options are fully explored and selected through the services listed above, WSB will prepare final Construction Documents for the streetscape improvements as approved by the OWNER for inclusion in this project. These documents shall include plans, details, and specifications in sufficient detail for the OWNER to pursue competitive bids for the construction of the proposed pedestrian improvements. Specific scope of work for this task will include: Construction Plans including: Blake Road Proposal 6 May 10, 2016 • Site Layout Plans • Landscape and Restoration Plans • Pavement Designs and Typical Details • Miscellaneous Site Construction Details • Prepare Related Technical Specifications • Prepare Related Final Cost Estimate Right-of-way Plans WSB will develop a final right-of-way plan based on the Final Approved Layout. The right of way plan will follow County format and meet State-Aid standards for review and approval. The plan will include the proposed plan and profile, estimated construction limits, proposed right of way and temporary and permanent easements. The right of way plan will have ownership tabulations, and show trees and other topographic information. WSB will also prepare a right of way layout with this information. The preparation of individual parcel drawings and written descriptions of the right of way and easements is included in the right-of-way and surveying tasks. We have assumed that Hennepin County will provide existing parcel and right of way information. The layout will be developed using County Right of Way Division Standards. It is anticipated that WSB will meet with the City and make revisions as necessary to finalize the right-of-way plan. Private Utility Coordination WSB will coordinate with private utility owners in the corridor to identify affected utilities and develop a utility relocation plan. WSB will make a Gopher-State One-Call for a utility locate. Information on existing utilities will be placed on the plans and a copy will be provided to each utility to have them verify or correct the information. Potential utility impacts will be identified and a meeting will be held with each affected utility to discuss utility relocation plans. The proposed relocations will be shown on the plan and sent to each affected utility. Two meetings will be held with all utilities present; the first meeting during 60% plan preparation and the second meeting after 95% complete plans is submitted. Meeting minutes will be provided for all utility meetings by WSB within two weeks. City Utilities WSB will identify the city utilities that will be affected by the project. This would include water main and sanitary sewer. WSB will meet with City staff to understand what water main or sanitary sewer may be impacted by the project as well as any potential upgrades the City may want to undertake with the project. WSB will prepare utility construction plans for relocating existing city utilities as necessary for the project. Signal Justification Reports Signal Justification Reports (SJR) will be prepared for four intersections in the project corridor for submission to Hennepin County and MnDOT State Aid for approval. The four intersections include: 1. Blake Road and Excelsior Boulevard 2. Blake Road and 2nd Street Blake Road Proposal 7 May 10, 2016 3. Blake Road and Cambridge Street 4. Blake Road and TH 7 The SJR for 2nd Street will also include an evaluation of the interconnect with the railroad crossing to the south of the intersection. It is assumed that additional traffic information will be collected in order to prepare the SJR reports. The current traffic data will be nearly 4 years old and new data should be collected. Final Design and Construction Plans WSB will complete the final design and prepare construction plans based on the final approved layout. These plans will include the following: Roadway— The roadway plans will include developing the title sheet, general layout, soils construction notes and standard plates, typical sections, miscellaneous details, standard plans, construction plans, profile, cross-sections, sidewalks and trails, and removals. Also included are alignment plans and tabulations, quantity tabulations, super elevation diagrams, and intersection details. Drainage— The drainage plans will include the basins and structures for storm water rate control and treatment, tabulation of in place drainage, and tabulations for proposed drainage. WSB will design and prepare storm water plans to meet agency permitting requirements. This effort will include the design of storm water rate control and treatment basins meeting NPDES Phase II criteria. This includes providing for special manhole treatment structures. WSB will determine the size of proposed drainage system components using an accepted hydrologic method. This will include the drainage areas for each drainage structure and the size of the structure. State Aid eligibility and cost splits will also be determined. We will show centerline profiles of proposed culverts and storm sewers, show the culvert or pipe size, length, grade, aprons, and inlet/outlet elevation along with all known existing and proposed utility locations and elevations. All utilities will be labeled. The inplace drainage tabulations will list type, size and location of in-place drainage structures within the project limits shown on the existing topography and utility plans. Proposed construction impacts (remove, leave as is, etc.) will also be tabulated. The proposed drainage tabulations will list the location, type, size, length, inlet and outlet elevations, grade, class, erosion control, excavation and bedding for larger culverts. Staging/Traffic Control -- Detailed plans will be prepared demonstrating a stage-by-stage process by which the new roadways can be constructed. It is assumed that the project will remain open to traffic during construction and that access to in-place businesses is to be maintained at all times. Detour plans will be provided if necessary. WSB will prepare color coded general layout depicting staging sequence for use at meetings. Detailed plans and notes will be prepared showing the locations of signs, barriers and striping necessary to accommodate the construction staging within the project area in a manner consistent with the MNMUTCD Manual, Field Manual for Temporary Traffic Control Zone Layouts, City of Hopkins, Hennepin County, and MnDOT Metro Division practices. The signing will be included on the staging plan. A Blake Road Proposal 8 May 10, 2016 tabulation showing the description and estimated quantities of traffic control devices by stage will also be prepared. Plans will be developed for temporary traffic signals. It is assumed that temporary traffic signals may be needed at all four signalized intersections. It is anticipated that the existing controller and signal faces can be utilized during construction and that video detection would be provided. This includes minor modifications to the existing permanent signal at accommodate staging. Traffic Signals – It is assumed that new or modified traffic signal systems will be required on Blake Road at Excelsior Boulevard, 2nd Street, Cambridge Street and TH 7. Signing/Striping -- Prepare permanent signing plans showing the location of proposed signs and containing all details necessary for the fabrication and installation of the signs in accordance with MnDOT specifications. Assemble plans and prepare tabulations in accordance with Hennepin County and MnDOT Sign Plan Standards. Field check and record existing signs. It is assumed that all new signs will be used on the project. Signing required by the city such as trail signs will also be incorporated. Prepare permanent striping plans showing the location, type, size, and color of striping necessary for the permanent striping of this project, including standard plans. Lighting -- It is assumed that lights will be provided at the signal intersections as part of the traffic signal. If additional street lights are required WSB would develop appropriate plans for construction. Pedestrian level lighting is included in the Landscaping and Aesthetic Design task. It is assumed that the city and county would provide input on the light style. Retaining Walls -- Prepare detailed plans of structured retaining walls with parapet showing proposed architectural treatment. These retaining walls will be designed consistent with MnDOT standard retaining wall plans. Standard designs of architectural treatments for walls (i.e. standard form liners), railings, and fence are included in this task. Utilities – WSB will prepare plans for modifications to the watermain and sanitary sewer system. Plan Review WSB will submit plans to the City of Hopkins and Hennepin County for review and approval. An electronic file of the plans, and bid proposal will be provided to the City once the project is bid and awarded. WSB will submit plans and supplemental specifications for review and approval at four stages of development: Stage 1 – Preliminary Design (30 Percent Complete): WSB will develop the plans to 30 percent completion. The plans for Stage 1 will meet State Aid Standards and at a minimum will include existing topography and utility plans, vertical and horizontal alignment plans, intersection layouts, drainage plans, typical cross-sections, and preliminary utility relocations. Upon receipt of City and County review comments the plans will be revised accordingly. Blake Road Proposal 9 May 10, 2016 Stage 2 – Final Design (60 Percent Complete): After receiving approval of Stage 1, WSB will complete the existing topography and utility plans, the vertical and horizontal alignment plans, intersection layouts, traffic signal design plans, drainage plans, typical cross-sections and utility relocation plans. Preliminary cross-sections will also be completed. The 60% plan set will be a complete set of plans for the project that addresses all design elements. Upon receipt of City and County review comments the plans will be revised accordingly. Stage 3 - Final Design (95 Percent Complete): After receiving approval of Stage 2, WSB will complete all areas of design and all sheets in the plan and submit eight (8) sets of plans and supplemental specifications. Three (3) sets of design computations (including drainage) and quantity calculations will also be submitted. One (1) copy of the engineer’s opinion of probable construction costs will be submitted. Upon receipt of City and County review comments the plans will be revised accordingly. Stage 4 - Final Design (100 Percent Complete): After receiving approval of Stage 3, WSB will incorporate the comments and will submit one (1) complete set of signed originals on bond paper with eight (8) copies. In addition, one (1) complete set of design computations, basis of quantity, and quantity calculations, and one (1) copy of the engineer’s opinion of probable construction costs will be submitted. Cost Estimating WSB will prepare a Statement of Estimated Quantities and a cost estimate at five key points during the design process; completion of the Staff Approved Layout and Construction Limits, 30%, 60%, 95%, and 100% plans. Permitting WSB will identify the permits needed for the project and complete the necessary permit applications to obtain the permits. The permits that are anticipated for the project include the NPDES permit, Minnesota Department of Health permit, Watershed District permit, a Corp of Engineers 404 permit, and potentially permits from the Mn/DNR for protected waters and possibly dewatering. We will also obtain necessary City and MnDOT approvals for the project. Bid Documents and Advertising WSB will prepare the necessary documentation and information for the bidding of the project. This will include preparing the bid proposal and contract documents for electronic bidding of the project. We will respond to contractor questions and issue appropriate addendums during the bidding phase and we will tabulate the bids and recommend award for the project. Right-of-Way Acquisition WSB will assist the City in the acquisition of all new rights-of-way, permanent easements, and temporary easements required for the construction of the Project. The assistance will include the performance of tasks and duties necessary and legally required to obtain the right to use the subject properties for the reconstruction of Blake Road as shown in the approved concept plan. This would include document Blake Road Proposal 10 May 10, 2016 searches, title opinions and updates, appraisals and appraisal services, negotiations, relocation, closing documents, and recording. To assist in appraisals and negotiations we will prepare parcel sketches and provide field stakes for viewing. This scope does not include participation in condemnation. The specific assumptions on the number of parcels where right-of-way is required and the number of assumed relocations is identified in the estimated cost. Construction Engineering We have assumed in our proposal all of the work required to properly administer and document the construction of this turnback and state aid funded project. Our scope of services assumes that the project will be constructed in 2018 and 2019 with final paving, clean up and maintenance completed in summer 2019 and final closeout payment to the contractor in April 2020. Project Management and Contract Administration WSB & Associates, Inc. will provide the overall project management of the project and will be responsible for all construction administration activities. After the contract has been awarded, WSB will hold a pre-construction meeting. WSB will assign a Project Manager who will work and coordinate with the City Engineer and run weekly construction meetings. The assigned Project Manager will be responsible for preparing and certifying all monthly pay vouchers, change orders, supplemental agreements, and authorizations to proceed with contract changes, prior to forwarding them on to the City for processing. The Project Manager will also be responsible for providing coordination with the contractor, the utility companies, property owners, and project personnel. It is anticipated that the Project Manager will be on site part-time throughout the duration of the project to address project needs. All shop drawings, material and suppliers will be reviewed for compliance with the plans and specifications. Construction Inspection Services WSB will assign a lead full-time resident inspector to administer the field construction activities to assure that the project is constructed in conformity with the plans, specifications and contract provisions. The full time resident inspector will manage a team of inspector’s, surveyors and material testers. In 2018 it is assumed two full time inspectors will be onsite with a third part time inspector as needed (half time). In 2019, two full time inspectors will be on site with a third inspector as needed. WSB’s inspectors will work with City personnel to coordinate construction inspection responsibilities on the project. It is assumed the construction start date will be May 1, 2018 with winter shutdown November 25, 2015, providing 29 weeks of construction in 2018. In 2019, we have assumed a start date of May 2, 2019 with completion September 29, 2019, providing 21 weeks of construction. We have assumed 60 hours per week in 2018 and 60 hours per week in 2019. The construction inspection team’s responsibilities on the project would include the following:  Monitor Contractor for Compliance with Plans and Specifications Blake Road Proposal 11 May 10, 2016  Track Quantities and material certifications  Review Equal Employment Opportunity and Labor Compliance requirements  Coordinate Surveying and Staking  Coordinate with Met Council regarding the progress of their improvements  Coordinate with utilities and the Contractor for utility relocations  Coordinate Material Sampling and Testing to ensure compliance to the Schedule of Material Controls.  Coordinate Shop Drawing submittals and Design Issues with Engineer  Monitor conformance with all applicable permit requirements  Ensure compliance to County and City construction practices and design standards.  Coordinate with City personnel on construction activities.  Inspect Traffic Control and Public Safety.  Complete project documentation  Coordinate with Property and Business Owners on Construction Activities The project documentation that will be completed as part of these services will include but not be limited to:  Change in Construction Status  Authorizations to Proceed with Contract Changes  Change orders  Supplemental Agreements  Daily and Weekly Diaries  Preliminary and Final Grading and Base Reports  Partial and Final Payment Vouchers  Material Certification Forms  Item Record Accounts  Field monitoring of labor compliance WSB will assign a Quality Assurance Manager for the project. The QA Manager will work with all WSB construction inspection personnel to ensure the project will be administered to conform to applicable laws and regulations and procedures established by MnDOT for State Aid projects. Construction Staking WSB will provide a survey crew to do all construction staking for the project, including construction limits, grading alignment and grades for all utility and street facilities and appurtenances, signage locations, and any other survey needs for this project. Preconstruction Documentation WSB will provide a photographic record of the existing conditions along the corridor. The photographic record will display the existing conditions of all portions of properties directly adjacent to and possibly affected by the project. Specific information that will be documented photographically will include but not be limited to the existing condition of; walls, decks, patios, building structures, walks, and landscaping. WSB will provide this record to the City. Blake Road Proposal 12 May 10, 2016 Materials WSB will undertake material sampling and testing with either our own staff or with an independent testing company. We have assumed MnDOT will be providing the plant inspection. MnDOT does charge for these services and WSB will coordinate the payment of these costs. All field tests will be done in conformance with current MnDOT (SALT) schedule of material controls and project specifications or as modified by the contract special provisions. WSB (or selected consultant) will provide the necessary testing personnel and certified testing equipment and will provide logs and records consistent with MnDOT policies. Necessary concrete, bituminous, grading and base reports will be prepared. WSB will obtain and manage all testing documentation. Record Drawings WSB will provide a set of record drawings of the project to the City on bond paper and electronic format as part of the contract. Prior to submitting record drawings, a black line copy of the record drawings will be submitted to the County and City for review and comments. Environmental Services WSB will assign a lead environmental specialist to manage the environmental services for this project. All environmental investigation and oversight work will be approved by and under the direction of the City. This will include at a minimum; guidance for project scope and directives, review of regulatory submittals and reports, and routine project communications for work schedules and task completion. WSB will conduct subsurface investigation in construction areas with a high potential to encounter contamination. The Limited Phase II Investigation will be conducted in winter conditions and will include soil screening, soil sampling and analysis, and final reporting. The intent of the investigation is identify the extent (i.e. vertical and horizontal) of known or suspected contamination that may be located in the construction zone and/or project Right of Way (ROW). WSB will prepare a project Construction Contingency Plan (CCP) for the identification, classification, handling, on-site management and disposal of hazardous waste, contaminated soil and groundwater, solid waste and other regulated materials that may be encountered during construction activities. The CCP outlines procedures for response actions and management of regulated waste/contamination, identify key project personnel contact information, and outline regulatory reporting requirements. The CCP is included in the contract documents. WSB will complete environmental oversight and documentation during excavation activities in areas with known or suspected regulated waste/contamination. We will also conduct investigation of materials/contaminants encountered at the site that were not previously identified. Soils will be visually examined for evidence of contamination (i.e. odor, staining, sheen, etc.) and screened on regular intervals with a photoionization detector (PID) per Minnesota Pollution Control Agencies (MPCA) recommendations. Blake Road Proposal 13 May 10, 2016 WSB will prepare a final report at the conclusion of the project. The report will include at a minimum: PID screening results, soil and groundwater analytical results, waste manifests and weight tickets for contaminated soils/waste disposal, a photo log of site activities and figures identifying sample locations, areas of removed soil contamination and remaining impacts (if necessary). All Laboratory samples will be analyzed with a standard 10-day turnaround time. Public Information Coordination WSB will provide public information coordination services for this contract. WSB will coordinate with the City to provide specific project information to the public, as well as respond to the daily needs and concerns of the public. WSB will assist the City in creating an effective public relations campaign as well as preparing a project specific Public Information Plan. The Public Information Plan shall include strategies for distribution of project updates, identification of target audiences, development of procedures for obtaining public comments as well as how to respond to complaints, and implementation of social media outlets for specific project updates or information. The Public Information Plan shall identify the level of involvement of the City personnel. WSB will coordinate with City personnel to determine the most effective process to deliver that information to the public. In addition to the tasks listed above, WSB will engage local groups and/or residents for the purposes of coordinating meetings to provide specific project information. WSB will work with the Contractor to provide credible, timely information to establish an effective working partnership with the project’s customer groups. The WSB construction inspection team will assist the City in coordinating maintenance of traffic, special business signing and visibility strategies, discussing construction impacts, and communicating the vision, progress, and coping strategies of the project. WSB will coordinate with City personnel to provide project updates such as milestones, road closures, and other relevant topics using the project website, email, social media, newsletters, press releases, or other project communication documents. These updates will be initiated by the public information team and forwarded to City personnel for comment prior to release. WSB will prepare and mail all notices and newsletters. The City will provide mailing addresses. WSB will make at least one member available for all project open houses, business group meetings, project kickoff meetings, and other related public outreach meetings. A member of the team will attend public involvement meetings, as requested by the City, and be prepared to answer detailed project questions. Cost Estimate Our estimated cost to complete the above Scope of Work is shown in Table 1 on the following page. The labor costs are based on WSB’s billing rate schedule shown in Table 2. Since a final project design has not been completed and staging of the project construction has not been defined it is difficult to estimate the construction engineering services. The costs included in Table 1 reflect our typical cost percentages for this type of project. It is similar to the scope and cost recently provided to Hennepin County for a county road reconstruction in Minnetonka where we provide similar services. Blake Road Proposal 14 May 10, 2016 Schedule A proposed schedule follows the cost estimate. This schedule is based on a two year construction project beginning in 2018. There is currently about 3 to 5 months of float in the schedule. However, this float can be quickly eaten up if issues come up or decisions are delayed on the project. The coordination with adjacent property owners and their plans is the biggest concern relative to the proposed schedule. Table 1 Blake Road Reconstruction Blake School Entrance to TH 7 Estimated Engineering Costs--Design, Right-of-way Acquisition, Construction Principal/ Project Manager Sr. Project Engineer Planner/ Engineer Engineering Technician Sr. Landscape Architect Landscape Architect Designer Survey Clerical/ Office Tech Total Hours Sub-Task Cost Task Cost Final Design and Construction Plans Project Management $87,548.00 Administration 200 24 24 24 272 $39,424.00 Coordination 120 40 40 24 224 $30,736.00 Quality Assurance and Quality Control 10 64 64 138 $17,388.00 Public Involvement $109,880.00 Citizen Advisory Committee (8 meetings)64 64 24 152 $20,840.00 City Council Meetings (4 Meetings)32 32 64 $9,472.00 Open House (4 Meetings)32 32 64 $9,472.00 Website Maintenance/Articles/Newsletters/Notices 96 96 24 216 $30,312.00 Individual Property Owner Meetings (20 Meetings)80 80 12 172 $24,628.00 Agency Coordination Meetings (12 meetings)48 48 12 108 $15,156.00 Design Surveys 24 120 144 $22,992.00 $22,992.00 Geotechnical Services $150,000.00 $150,000.00 Drainage Studies 80 80 80 240 $28,720.00 $28,720.00 Environmental Studies 4 16 16 16 52 $6,376.00 $6,376.00 Approved Project Layout Construction Limits 8 80 80 80 248 $29,984.00 $29,984.00 Streetscape Design Development 90 200 290 $27,610.00 $27,610.00 Right-of-way Plans 2 64 48 80 194 $23,340.00 $23,340.00 Private Utility Coordination 2 48 16 16 82 $10,476.00 $10,476.00 City Utilities 2 24 40 24 90 $10,676.00 $10,676.00 Signal Justification Reports 2 32 80 32 146 $17,036.00 $17,036.00 Final Design and Construction Plans 30% Design $109,892.00 Roadway and Trails 4 80 120 120 324 $38,192.00 Drainage 4 24 40 80 148 $17,264.00 Staging/Traffic Control 4 24 40 40 108 $12,784.00 Traffic Signals 2 8 24 24 58 $6,724.00 Signing/Striping 2 8 24 24 58 $6,724.00 Lighting 2 4 8 8 22 $2,636.00 Retaining Walls 4 24 40 40 108 $12,784.00 Utilities 4 24 40 40 108 $12,784.00 60% Design $167,720.00 Address 30% Comments 8 24 40 16 88 $10,728.00 Roadway and Trails 4 80 160 160 404 $47,032.00 Drainage 4 40 80 80 204 $23,832.00 Staging/Traffic Control 4 24 40 40 108 $12,784.00 Traffic Signals 2 24 40 40 106 $12,468.00 Signing/Striping 2 24 40 40 106 $12,468.00 Lighting 2 8 16 16 42 $4,956.00 Retaining Walls 4 40 80 80 204 $23,832.00 Streetscape Design 2 40 64 106 $10,372.00 Utilities 4 24 24 24 76 $9,248.00 95% Complete $192,104.00 Address 60% Comments 8 24 40 16 88 $10,728.00 Roadway and Trails 4 80 160 160 404 $47,032.00 Drainage 4 40 80 80 204 $23,832.00 Staging/Traffic Control 4 24 40 40 108 $12,784.00 Traffic Signals 2 24 40 40 106 $12,468.00 Signing/Striping 2 24 40 40 106 $12,468.00 Lighting 2 8 16 16 42 $4,956.00 Retaining Walls 4 40 80 80 204 $23,832.00 Streetscape Design 2 120 240 362 $34,756.00 Utilities 4 24 24 24 76 $9,248.00 100% Complete 0 $106,648.00 Address 95% Comments 8 16 20 16 60 $7,444.00 Roadway and Trails 4 80 80 80 244 $29,352.00 Drainage 4 40 40 40 124 $14,992.00 Staging/Traffic Control 4 20 20 20 64 $7,812.00 Traffic Signals 2 20 20 20 62 $7,496.00 Signing/Striping 2 20 20 20 62 $7,496.00 Lighting 2 8 8 8 26 $3,188.00 Retaining Walls 4 40 40 40 124 $14,992.00 Streetscape Design 2 40 64 106 $10,372.00 Utilities 4 8 8 8 28 $3,504.00 Cost Estimating 8 80 80 24 192 $23,712.00 $23,712.00 Permitting 4 40 80 24 148 $17,560.00 $17,560.00 Bid Documents and Advertising 8 40 24 8 80 $10,296.00 $10,296.00 Total Hours 856 2032 2304 2004 290 568 120 120 8294 $1,152,570.00 $1,152,570.00 Hourly Rates $158.00 $138.00 $109.00 $112.00 $109.00 $89.00 $164.00 $79.00 Total Labor Design and Construction Plans $135,248.00 $280,416.00 $251,136.00 $224,448.00 $31,610.00 $50,552.00 $19,680.00 $9,480.00 Right-of-way Acquisition (See Attached)145,000.00$ Construction Services Administration and Inspection --8% of Construction Cost 800,000.00$ Material Sampling and Testing -- 1.5% of Construction Cost 150,000.00$ Construction Staking --2%200,000.00$ Total Engineering Services $2,447,570.00 Note: Construction Services is based on estimated $10,000,000 construction cost. 1 Project Management $210 $4,620 1.1 2 Acquisition Services $3,010 $66,220 2.1 2.2 2.3 Minimum Compensation Report 2.4 Acquisition Services - Sub-Total $3,220 $70,840 3 Relocation Services $6,000 $6,000 3.1 Relocation Study 3.2 Relocation TOTAL - WSB & Associates Acquisition Costs $76,840 Per Parcel Total $400 $10,800 $45,000 $13,350 Sub-Consultant Costs $69,150 TOTAL $145,990 Optional Costs (Not included above): Right of Way Certificate # 1 (if Federal Funds are part of the project)$2,500 6. Testimony is not included in this estimate for the appraiser or staff of WSB. 5. Sub-Consultant services coordination will be conducted by WSB staff. The invoices will be submitted to WSB staff for review and passed to the City to pay those bills directly to the sub-consultants. Assumptions: City of Hopkins Acquisition/Relocation Estimate for: Blake Road Project 1. This estimate assumes 27 parcels for the title work and 22 parcels for the acquisition, appraisal and review work. Appraisals - Kelly Lindstrom - based on 22 appraisals - 16 commercial and 6 residential General Project Management , Reports, Coordination of title commitments, appraisals and appraisal reviews General Information Letter, Doncuments, Mortgage Releases Field Title Report Offer and Negotiations Title Committments- 1st American Title -based on 27 parcels 4. No relocation has been included for any billboards or signage that will need to be relocated as part of the project. Sub-Consultant Services- to be paid directly by the City of Hopkins 2. Acquisition services are estimated through the title and possession date. Any services required beyond that date would be paid at the hourly rates. Task Description 3. Relocation services are assuming one residential owner/occupant relocation. If there is a landlord/tenant, an amendment would be made to the contract for the additional relocation. Appraisal Reviews - Turnkey Appraisals, LLC- based on 22 appraisal reviews - 16 commercial and 6 residential March 24, 2016 Costs Costs associated with word processing, vehicle mileage, cell phones, reproductions of common correspondence and mailing are included in the hourly rates. Note: Average Hourly Fees (include overhead and profit) Per Parcel Blake Road Reconstruction Blake School Entrance to TH 7 Schedule--Design, Right-of-way Acquisition, Construction 2016 2017 2018 May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar April Project Management Public Involvement Design Surveys Geotechnical Services Drainage Studies Environmental Studies Approved Project Layout Construction Limits Landscaping and Aesthetic Design Concept Right-of-way Plans Private Utility Coordination City Utilities Signal Justification Reports Final Design and Construction Plans 30% Design 60% Design 95% Complete 100% Complete Cost Estimating Permitting Bid Documents and Advertising Right-of-Way Acquisition Construction 22001166 RRaattee SScchheedduullee 2 0 1 6 R A T E S C H E D U L E Billing Rate/Hour Principal $158 Associate / Senior Project Manager $137$147$158 Project Manager $121$127$133 Project Engineer $104$112$121$127$133 Graduate Engineer $80$85$92$98 Sr Landscape Architect / Sr Planner / Sr GIS Specialist $109$118$125$133$138 Landscape Architect / Planner / GIS Specialist $66$74$81$89$99$104 Engineering Specialist / Senior Environmental Scientist $90$98$105$112$121$130 Engineering Technician / Environmental Scientist $52$60$67$74$79$85 Construction Observer $87$94$99$105$110 Coring Crew One-Person Crew $162 Two-Person Crew $238 Survey Crew One-Person Crew $132 Two-Person Crew $164 Three-Person Crew $184 Underwater Inspection Dive Team $460 Office Technician $42$65$75$85 Costs associated with word processing, cell phones, reproduction of common correspondence and mailing are included in the above hourly rates. Vehicle mileage is normally included in our billing rates, but can be charged separately if specifically outlined by contract. Reimbursable expenses include costs associated with plan, specification and report reproduction, permit fee, delivery cost, etc. Rate Schedule is adjusted annually. Multiple rates illustrate the varying levels of experience within each category. Engineering  Planning  Environmental  Construction wsbeng.com QUALITY MANAGEMENT PLAN 1. Quality Management Overview Quality is the result of a partnership between the providers of project development services (plan development, technical reports and environmental documentation) and those responsible for quality assurance. Those providing project development services must implement quality control to ensure that products and services meet or exceed expectations of quality. Those responsible for quality assurance must review or audit these products and services to make certain that the quality control efforts are achieving desired results. The overall outcome of these efforts is continuous improvement in the ongoing quest for the highest quality engineering products and technical reports with the most efficient use of resources. A Quality Management Plan (QMP) will be specifically written for the Blake Road project. The QMP is based on WSB’s Corporate Quality Management Plan (CQMP) which defines the core quality principles to which all projects at WSB must adhere. 1.1. Intent & Philosophy of the QMP The intent of this QMP is to provide a mechanism by which all documents produced by the project can be subject to a systematic and consistent review needed to deliver a high quality product, on time, and within budget. This plan is intended to be a living document which will be reviewed and updated periodically to ensure compliance with changes to document preparation requirements, processes and organizational structure. Quality control is based on the philosophy that:  Quality control should ensure that the work is done correctly the first time.  Quality is achieved by focusing on preventing problems or errors rather than reacting to them.  Quality is achieved by qualified individuals performing all work functions.  Quality is achieved by providing proper training of personnel and ensuring that all personnel remain current on the knowledge and skills needed for their position.  Quality is verified through the checking, reviewing, and monitoring of work activities, with documentation by experienced, qualified individuals who are not directly responsible for performing the work.  Quality is continual improvement of the quality system. 1.2. Quality Organization and Authority The Project Manager (PM) is responsible for the planning, coordination and execution of the project from inception to completion and meeting the project goals within schedule and budget. The PM has ultimate authority for implementing the QMP and is responsible for creating a clear level of accountability throughout the organizational structure so that all members understand their role, expectations, and responsibilities. The PM is responsible for ensuring that both the QC and QA activities have been completed. The QA/QC Manager (QM) is responsible for administering the QMP and will ensure the quality control processes outlined in this QMP are adhered to by utilizing an ongoing audit process. The QM will conduct QA audits of the documents generated by the project prior to submittal to verify the quality control procedures were completed in their entirety. The QM will provide a detailed report of the quality activities completed on a monthly basis to the PM. Task Managers are responsible for accuracy and completeness of the designs and documents prepared for the project. The task leader is responsible for the quality of work of each person involved in the efforts to bring individual task to completion. The task leader is responsible for the use of the standardized QC procedures and is responsible for completing and submitting to the PM and QM all checks, checklists, review reports, computations, and other project documentation. 2. Quality Plan Implementation and Training 2.1. Implementation The PM is responsible for completing and distributing the Project Implementation Plan (PIP) along with the QMP to all members of the team. These governing documents will be issued prior to the initiation of any work. 2.2. Training The QM will conduct project specific QMP training prior to initiation of work. All members of the team, including sub-consultants, are required to attend the training and sign a certificate of attendance. The QM will maintain the official training list and provide additional training sessions as needed throughout the project for new staff. 3. List of Requirements This QMP requires the designers to utilize the current State and Local design standards that apply to each of the deliverables as defined by scope of services. At minimum, the following deliverables will follow the formal review process defined in Section 4: 4. Overview of Technical Document Review Process At the core of this QMP is the technical document review process. The following sections detail the procedures that are required to be completed on this project. In general, the process is broken into two parts: quality control reviews/checks and quality assurance verification. The quality control reviews/checks are the procedures utilized to review the technical adequacy and accuracy of the documents and their conformance with design inputs. Quality assurance verification documents the QC processes and their conformance with the QMP through an auditing process. All deliverables transmitted to the City or any outside agency including the design memorandum and the utility coordination letters not listed in the table above shall be subject to the document review process. 4.1. Quality Control Flowchart 4.2. Quality Control Checking Procedures Quality control checking consists of a systematic review of project inputs and outputs including, but not limited to, the following:  Computer software inputs and outputs.  Calculations.  Plans, drawings, and layouts.  Reports, studies and modeling.  Formal project correspondence & meeting minutes. These reviews shall include, at minimum, the following activities:  Compliance with project requirements.  Technical accuracy and adequacy.  Compatibility with other associated project documents.  Compliance with previous review comments. Formal Review Process Originator: The Originator is typically the Task Manager or designer responsible for the plan, report, document or calculation to be reviewed. The Originator typically also functions as the Back Checker. The Originator is responsible for implementing the quality control check process by preparing the quality review memorandum and checklist detailing the extent of the review, identifying the reviewers, documenting the basis of the review and specifying review schedule. Copies of this memorandum and checklist will remain in the project files. The Originator will also stamp the document with the check print stamp and provide the check print to the Checker. Checker: The Checker is responsible for checking the plan, report, document or calculation independently of the Originator. The Checker must be technically competent and experienced in the subject matter of the document. The Checker will check the entire document for design intent, technical adequacy, and conformance to any applicable standards and format. The Checker will also verify conformance with standards, published design checklists and WSB’s internal design checklists. Information found to be correct will be highlighted in yellow. Information found to be incorrect will be stricken in red and comments and/or instructions will be written in red. For documents generated in word processing software, the Checker will utilize “track changes” within the software to document the comments and revisions. Once the review is complete, the Checker will sign and date the check print stamp. Back Checker: The Back Checker will review each of the Checker’s suggested corrections. If the Back Checker concurs with a correction, the Back Checker will place a check mark in green next to the correction. If the Back Checker does not concur with the Checker’s correction, the Back Checker will confer with the Checker and determine a resolution. If both agree that the Checker’s correction should not be made, the Back Checker will cross out the Checker’s correction in green. If the Back Checker and the Checker cannot achieve resolution, the PM will be consulted to resolve the differences. Once the back check is complete, the Back Checker will sign and date the check print stamp. Corrector: The Corrector will make the changes to the document and will highlight each correction in blue. Once complete, the Corrector will sign and date the check print stamp and provide a new copy of the corrected plan and the original marked-up check print to the Verifier. Verifier: The Verifier will compare the new copy of the plan or document with the check print to confirm that the corrections have been incorporated accurately. If a correction had been made properly, the Verifier will cross-highlight in yellow the Corrector’s blue highlight. If a correction has not been made or is in error, the new copy of the document will be annotated in red and returned to the Corrector. The Corrector will make the corrections and provide a new copy of the document to the Verifier. Once all the corrections have been verified, the Verifier will sign and date the check print stamp and return the entire package to the Originator. Discipline Coordination Reviews (DCRs), Constructability Review (CR), Independent Technical Review (ITR). The PM will determine in the PIP at what stage the ITR and CR reviews will be completed. The PM will assign technically competent and experienced staff to complete the reviews. ITRs are a review of any and all documents developed which require specialized expertise. The review shall be conducted by a peer who is not directly involved with the project and who is independent of the final review and/or approval by the PM and Task Manager. At a minimum, all structural designs will receive an ITR. The person assigned the conduct the ITR will review the package and provide comments on the document in red. Once completed, the reviewer will complete the bottom half of the ITR form and return the entire package back to the PM. The PM will review the comments and determine if they should be incorporated into the plan or if further discussion is needed. Once final comment resolution is determined, the PM and the reviewer will sign and date the ITR form. CRs are a review of the documents to obtain input from individuals who have construction-related expertise. For this project, the reviewer shall have at least ten years of experience in highway design and/or construction management. The process for conducting the CRs will be the same as the ITRs. 4.3. Quality Assurance / Verification Document Level QA The QM is responsible for ensuring that the quality control processes outlined in this QMP are applied to all documents generated by this project and all deliverables to the City. Upon receipt of a completed review package, the QM will initiate the QA process by completing the QA Verification Form. The QM will verify that all QC functions were completed. If all steps were completed, the QM will sign and date the QA Verification Form and return the entire package to the PM for final distribution. If steps were missed, the QM will complete the non-conformance form (in Appendix C) and return the entire package to the PM. The PM will review the non-conformance and make the necessary corrections. Once the corrections are made, the PM will sign the non-conformance form and return the entire package to the QM. Once the QM verifies that the non-conformance was corrected, the QM signs and dates the non-conformance form and the QA Verification Form. The package is then returned to the PM for final distribution. The QM will maintain a log of the packages that have been verified along with any non-conformances identified. System Level QA The QA/QC Manager will conduct periodic audits of the overall project to ensure conformance with the QMP. After each audit, a report will be provided to the PM detailing the audit findings, any non- conformances and any suggested improvements to the QMP. 4.4. Stakeholder Reviews The PM will coordinate all reviews and comment resolutions. Upon receipt of comments from stakeholders, the PM will enter the comments into the Stakeholder Comment Resolution Form. The PM, along with City’s PM will determine the need for a comment resolution meeting prior to the design team progressing with plan revisions. Each Task Manager will review the comments and provide a response and final comment disposition on the Stakeholder Comment Resolution Form. This form will then be provided to the City for review. Once all the comments from each discipline have been completed, the revised plan will go through the formal check process to ensure that the stakeholder comments have been addressed. 5. Documentation Meeting Minutes Meeting minutes shall be taken at every meeting. The PM will distribute meeting minutes for draft review to all attendees within two business days of the meeting with a deadline of one business day to return comments. The PM will incorporate any changes and distribute the final meeting minutes within eight business days after the meeting. The meetings minutes will be signed by the PM. Correspondence All correspondence including, but not limited to, letter, e-mails, faxes and telephone conversations will be documented and stored in a shared folder. File locations All the files that pertain to this project will be kept in a shared folder directory utilizing the standard WSB file structure. Note: Appendix A (Project Implementation Plan), Appendix B (Quality Control Form & Checklists), and Appendix C (Quality Assurance Forms & Checklist) are not included in proposal version. CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION NO. 2016-043 RESOLUTION APPROVING PROPOSAL FOR ENGINEERING SERVICES BLAKE ROAD IMPROVEMENT PROJECT CITY PROJECT 2013-06 WHEREAS , a corridor study was completed by the City of Hopkins (City) in 2015 in collaboration with Hennepin County (County) and other agencies which provided recommendations for improvements to Blake Road, and WHEREAS , the City Council accepted and approved the recommendations of the corridor study and deems it appropriate and expedient to make such improvements, and WHEREAS , the City and County have negotiated an agreement to bring out the reconstruction and jurisdictional transfer of Blake Road, and WHEREAS , the agreement between the City and County specifies that the City will take the lead in the design, construction, construction oversight and right-of-way acquisition to support the reconstruction of Blake Road, and WHEREAS , the City has negotiated a proposal for engineering services with WSB & Associates, Inc. for the improvement of Blake Road. NOW, THEREFORE, BE IT RESOLVED , by the City Council of the City of Hopkins, Minnesota: 1.WSB & Associates, Inc. is hereby designated as the engineer for this improvement and shall provide engineering, construction and right-of-way services for the improvement of Blake Road. The Mayor and City Manager are hereby authorized to enter into a contract for said services for the project. 2.The City Attorney and City Engineer are hereby authorized to acquire necessary easements by negotiation or condemnation. th Adopted by the City Council of the City of Hopkins this 17 day of May, 2016. ______________________ Molly Cummings, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk