IV.4. Minutes of the November 13, 2017 City Council Work Session Proceedings
HOPKINS CITY COUNCIL
WORK SESSION PROCEEDINGS
NOVEMBER 13, 2017
CALL TO ORDER
Pursuant to due call and notice thereof a regular work session of the Hopkins City
Council was held on Monday, November 13, 2017 at 6:30 pm. in the Raspberry Room
at City Hall, 1010 First Street South, Hopkins.
Mayor Cummings called the meeting to order with Council Member Campbell, Gadd,
Halverson and Kuznia attending. Staff present included City Manager Mornson, Art
Center Executive Director Anderson, Finance Director Bishop, City Clerk Domeier,
Assistant City Manager Lenz and Public Works Director Stadler.
CITY HALL FACILITY ASSESSMENT
In addition to City staff, representatives from Wold Architects and Engineers present for
the item were Jonathan Loose, Melissa Stein and John McNamara. Assistant City
Manager Lenz introduced the Facility Assessment Study, a plan for long-term City Hall
facility needs and improvements.
Wold Architects and Engineers is a national firm specializing in the public sector. Wold
representatives met with City Hall staff to discuss existing and anticipated space needs.
Mr. Loose discussed the factors, guiding principles and project goals that were
considered when creating the long-term plan for City Hall.
There was Council discussion regarding space for future growth and common work
areas. Ms. Stein explained that the work space was laid out in response to a staff
survey and that flexible work spaces could accommodate growth and collaboration
between departments. Mr. McNamara discussed the flexible work environment concept.
Mr. Loose discussed the preliminary budget and construction costs and commented that
the costs are based on a database of past project bids and inflated to 2019 costs. The
projections are also based on cost if the phases were treated as individual projects.
There was discussion about the project timeframe. Mr. Loose explained that to
complete the entire facility improvement project would be approximately 4-6 months for
design and 6-8 months for construction. Current municipalities that Wold Architects are
working for include the cities of Carver, Cottage Grove, Brooklyn Park, Richfield, Eagan,
New Hope and Crystal. There was discussion about the best timeframe for City Hall
construction, phasing the construction and the impact on customers. Ms. Lenz
explained that an odd year would work best for a construction project so not to impact
elections. A temporary entrance could be used for customers and that a winter
construction timeframe would work for an interior project. Council discussed the
importance to anticipate future staffing needs, department collaboration and the impacts
of a phased vs. one larger construction project. Council commented that one larger
construction project would have less disruption to the staff and public and that they
preferred that option.
HOPKINS CITY COUNCIL
WORK SESSION PROCEEDINGS
NOVEMBER 13, 2017
2018-2022 CAPITAL IMPROVEMENT PLAN (CIP) AND 2018-2022 EQUIPMENT
REPLACEMENT PLAN (ERP)
Finance Director Bishop discussed the CIP and City Hall improvements. The $260,000
budgeted in the CIP for City Hall improvements has been forwarded to the year 2019.
Mr. Bishop would look at how the additional costs for a larger improvement project
would impact the Financial Management Plan (FMP). Mr. Bishop commented that he
would work with Ehlers, Inc. to update the FMP but he figured that it would add
approximately $20 for the average homeowner above what is already budgeted.
Finance Director Bishop gave an overview of the CIP. Mr. Bishop discussed the
revenues and expenditures of the different funds. Park Dedication fees continue to fund
the projects. Mr. Bishop discussed the Water Fund 2018 rate increase and explained
that staff and Council could re-examine the rates in the future to assure they are
supporting the fund. The balance in the Sewer Fund continues to increase and the
Storm Sewer fund remains healthy. Mr. Bishop discussed the Pavilion Fund and
explained that the working capital would balance once the bonds are issued and that
staff would continue to work on ways to pay for the debt.
Mr. Bishop discussed the ERP balances for 2018 and commented that the fund is
supported for now but staff would need to revaluate the ERP each year. The CIP and
ERP would be on the December City Council agenda.
2018 SPECIAL REVENUE AND ENTERPRISE FUND BUDGETS
Finance Director Bishop gave an overview of the 2018 Special Revenue and Enterprise
Funds.
There was discussion of the Arts Center revenues, expenditures, budget needs to
sustain the Center and efforts to eliminate the Arts Center deficit. Staff is making
decisions on future programming and concerts. Arts Center Executive Director
Anderson discussed concert sales and costs, commenting that ticket sales are up
overall and that the holiday concert is well attended. Ms. Anderson commented that the
Arts Center staff has only been together for 1-1/2 years, staff continues to adjust
programming and would like the City to commit to the 2019-20 season. Concerts are
high profile and elimination of concerts would impact the Arts Center ability to get
grants, donations and membership. Staff is exploring programming alternatives and
event center options that have more predictable costs than concerts. There was
discussion regarding the positive impact and amenity that the Arts Center is to Hopkins
and the economic boost concert attendees bring to area businesses.
The Chemical Assessment Fund grant revenues cover the expenditures. The Economic
Development Fund is budgeted for the maximum levy and the fund has had additional
expenditures due to The Artery project. The Parking Fund expenditures will include a
6% rate increase for 2018 and no capital expenditures. Staff is reviewing the electric car
permits. The Communications Fund revenues remain the same in 2018. The Depot
Coffee House Fund continues to be supported by the City, Three Rivers Park District
HOPKINS CITY COUNCIL
WORK SESSION PROCEEDINGS
NOVEMBER 13, 2017
and the Joint Recreation Department. The Class and Comp Study salary increases are
affecting the budget as well as future impacts of road closures and construction. Staff
will review the fund and look at negotiating partnership fund increases. The Water Fund
and Sewer Fund rate increases are needed to sustain the ongoing capital needs. There
are no changes to the Refuse and Storm Sewer Funds. The Pavilion Fund revenues
increased due to the lease with the Hopkins School District. The revenue increases may
be offset due to no dry floor rental during the construction.
City Manager Mornson commented that Finance Director would provide Council with a
FMP update in 2018.
UPDATES
Council Member Kuznia discussed a resident concern about plastic shopping bags
in the recycle bins. Staff will discuss issue with the Solid Waste Coordinator.
Council Member Gadd discussed vehicles parked overnight and for extended
periods of time in Maetzold Field parking lot.
Mayor Cummings read a thank you note from ResourceWest.
Mayor Cummings discussed a Hopkins High School student’s mission to empower
young women. A proclamation would be on the City Council February 5, 2018
agenda.
Mayor Cummings and Council Member Halverson attended the PPL ribbon cutting
event.
City Manager Mornson gave the following updates:
City Council tour of PPL is on Tuesday, November 21, 5 pm
Update on the Goal Setting meeting on January 12, 2018.
ADJOURNMENT
There being no further business to come before the City Council and upon a motion by
Campbell, second by Kuznia, the meeting was unanimously adjourned at 8:48 p.m.
Respectfully Submitted,
Debbie Vold
ATTEST:
___________________________ ____________________________
Molly Cummings, Mayor Amy Domeier, City Clerk