V.1. Public Improvement Hearing – 2018 Street and Utility Improvements, City Project 2017-10; Stanley (CR2017-138)December 5, 2017 Council Report 2017-138 PUBLIC IMPROVEMENT HEARING 2018 STREET AND UTILITYIMPROVEMENTS CITY PROJECT 2017-10 Proposed Action Staff recommends the following motion: adopt Resolution 2017-083, Resolution Ordering Improvement after Public Improvement Hearing, 2018 Street and Utility Improvements and companion Resolution 2017- 084, stating the City’s intent to reimburse itself using bonds. This action continues an assessable project for street and utility improvements. Overview At its November 6, 2017 meeting, a feasibility report concerning street and utility improvements along Division Street, Cambridge Street, Oxford Street, Lake Street Northeast, Murphy Avenue, Texas Avenue South, and the alley south of Lake Street was presented to the City Council and a public hearing on the improvements was ordered for December 5, 2017. Hearing notices have been mailed to all affected property owners of record. In accordance with state statutes, the City Council needs to conduct a public hearing and determine authorization of the project. Following the public hearing, if the project is ordered, City Council is asked to state the City’s intent to reimburse itself using bonds. Primary Issues to Consider Scope of Improvements Public Input Assessments Project Budget and Costs Project Schedule Staff Recommendation Supporting Information Public Hearing Notice & Mailing Affidavit Proposed Pending Assessment Roll Resolution 2017-083 & 2017-084 Proposal for Design and Construction Services Feasibility Report (available upon request) _________________________________ Nate Stanley, P.E., City Engineer Financial Impact: $5,779,200 Budgeted: Y/N _Y_ Source: _PIR, SA, Water, Sanitary, Storm Related Documents (CIP, ERP, etc.): CIP _ Notes: _________________________________________ Council Report 2017-138 Page 2 ANALYSIS OF ISSUES Scope of Improvements This project includes reconstruction of the following streets: • Division Street • Cambridge Street • Oxford Street • Lake Street Northeast • Murphy Avenue • Texas Avenue South • Alley south of Lake Street Proposed street improvements include full reconstruction of streets and new curb and gutter throughout the project area; width improvements are also proposed. Water main is proposed to be replaced throughout the project area. All water services will be replaced from the main to the property line unless they are copper and less than 10 years old. Sanitary sewer improvements include the removal and replacement of the main, manholes and service lines to the property line. Several segments are also proposed to rehabilitated via trenchless means. Proposed storm sewer improvements include removal and replacement of the storm sewer main, addition of storm sewer inlets to reduce water ponding in the street and improvements to reduce sediment accumulation. Bicycle facilities include installation of “sharrows” on the Hopkins portion of Texas Avenue and “sharrows” on Lake Street Northeast. St. Louis Park has designated Texas Avenue South as a bicycle corridor, and will be installing bicycle lanes on their portion of Texas Avenue South. The bicycle improvements will provide continuity between existing bicycle lanes on Texas Avenue South and the proposed bicycle improvements on Blake Road. Additional sidewalks were considered for the neighborhood; however the vast majority of resident respondents indicated they did not want new sidewalks added. During the scoping for this project, it was determined that there was some other work that should be included in the project, due not only to proximity, but to capitalize on pricing. This additional work will be funded by separate items in the CIP and Budget and includes the following: • Storm manhole rehabilitation/replacement in the intersection of 17th Avenue South and 1st Street South • Sanitary Sewer Lining in areas across the City identified by the Public Works Department. • Citywide spot alley and sidewalk repairs The municipal boundary between Hopkins and St. Louis Park runs down the middle of Division Street and Texas Avenue south of Division Street. Both of these streets will be reconstructed in their entirety, and to govern the work a Joint Powers Agreement was executed earlier this year. Hopkins will be the project lead for all work and coordinate with St. Louis Park. Council Report 2017-138 Page 3 Metropolitan Council Environmental Services (MCES) is currently reconstructing the L27 lift station, which is currently located at 420 Blake Road. The new lift station will be located at 402 Hiawatha Avenue, approximately 600 feet west of Blake Road. As part of the project, a new force main needs to be extended from the lift station into St. Louis Park. Staff has been coordinating with MCES on the placement of the new force main along Lake Street, and plan to incorporate the work into the 2018 improvements scope. A cooperative agreement between Hopkins and MCES was established prior to construction of the lift station, and will be updated to account for the additional work. Public Input Two public informational meetings regarding the improvements were held on November 1 & 29. The meeting format consisted of a presentation of the overall project, but focused detailed discussion on assessments. Between the two meetings, a total of approximately 30 people attended the meetings. A questionnaire was sent to all properties in the project area in advance of the neighborhood meeting, Drainage concerns and a desire for improved street surface were the most notable comment in the responses. Bolton & Menk and City staff has met with individual property owners in person to discuss concerns and look at options to minimize issues; it is anticipated meetings will continue as design progresses. Assessments The proposed street assessments are based on the City’s assessment policy, whereby 70% of the street reconstruction cost and 50% of the water and sewer service replacement are assessed to benefiting properties. The policy also allows for assessments to be capped should assessments exceed previous year assessments by 20%; the costs for this project will trigger the assessment cap. A preliminary assessment roll has been calculated and can be found in the appendix of the attached Feasibility Report. The assessment cap for residential properties is $88.89 per front foot based on adding 3% to the 2017 cap. Without the cap assessments could be double the capped rate. Project Budget and Costs The estimate for this project, which includes 10% contingency and 21% for legal, administrative, and engineering costs for all the work totals to $5,779,200. Project costs and funding sources are as follows: Council Report 2017-138 Page 4 Funding Source CIP Budget Hopkins Costs Costs by Others PI-PIR/General Obligation Bonds $1,000,000 $1,085,600 Assessments 900,000 1,073,600 Storm Sewer Fund 350,000 194,200 Sanitary Sewer Fund 500,000 960,700 Water Fund 700,000 1,145,500 Metropolitan Council 818,600 City of St. Louis Park 501,000 Total 3,450,000 $4,459,600 $1,319,600 It should be noted that the current estimate exceeds the CIP budgeted amount for some items. The significant factors contributing to the overage at this time are the percentages applied for contingencies and design costs, these costs will be reduced as the project progresses. Costs for utilities have been increased due to further in-depth analysis of other factors that can affect construction costs, such as poor soil conditions, depth, and capacity upgrades. Public Works staff will be working with the Finance Director to assure the project as proposed can be funded. Staff will return to council with an update on costs prior to contract award. Project Schedule Accept feasibility report/order public hearing November 6, 2017 Public Informational Neighborhood Meetings November 1 & 29, 2017 Public hearing/order final design December 5, 2017 Approve final plans/order bids March 6, 2018 Order Assessment Hearing April 17, 2018 Public Informational Neighborhood Meeting #4 Early May 2018 Conduct Public Assessment Hearing May 15, 2018 Adopt Assessment Roll/Award Contract May 15, 2018 Begin Construction June, 2018 Complete Construction November, 2018 Staff Recommendation Staff recommends ordering the above detailed improvement with adoption of resolution 2017-083 and adopting companion resolution 2017-084. CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION NO. 2017-083 RESOLUTION ORDERING PUBLIC IMPROVEMENT 2018 STREET AND UTILITY IMPROVEMENTS, PROJECT NO. 2017-10 th WHEREAS, a resolution of the City Council adopted the 5day of December, 2017 fixed a date for a Council Hearing on the improvements on Division Street, Cambridge Street, Oxford Street, Lake Street Northeast, Murphy Avenue, Texas Avenue South, and the alley south of Lake Street, including pavement, curbing, sidewalk, signage, drainage, water and sanitary sewer improvements and all necessary appurtenances, and WHEREAS, the City Council deems it appropriate and expedient to make such improvements, and WHEREAS, ten days mailed notice and two weeks published notice of the hearing was th given, and the hearing was held thereon on the 5day of December, 2017 at which all persons desiring to be heard were given an opportunity to be heard thereon. NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Hopkins, Minnesota: 1. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility report and the recommendations are hereby accepted. 2. Such improvement is hereby ordered as proposed in the Council Resolution th adopted the 5day of December, 2017. The total estimated project cost is $5,779,200, of which $1,073,630 is estimated to be assessed. 3. Bolton & Menk, Inc. is hereby designated as the engineer for this improvement and shall prepare plans and specifications for the making of such improvement. The Mayor and City Manager are hereby authorized to enter into a contract for engineering and construction services for this improvement. 4. The City Attorney and City Engineer are hereby authorized to acquire necessary easements by negotiation or condemnation. th Adopted by the City Council of the City of Hopkins this 5day of December, 2017. Molly Cummings, Mayor ATTEST: Amy Domeier, City Clerk CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION NO. 2017-084 DECLARING THE OFFICIAL INTENT OF THE CITY OF HOPKINS TO REIMBURSE CERTAIN EXPENDITURES FROM GENERAL OBLIGATION IMPROVEMENT BOND PROCEEDS TO BE ISSUED BY THE CITY OF HOPKINS WHEREAS, the Internal Revenue Service has issued Treas. Reg. #1.150-2 providing that proceeds of tax-exempt bonds used to reimburse prior expenditures shall not be deemed spent unless certain requirements are met; and WHEREAS, the City expects to incur certain expenditures, which may be financed temporarily from sources other than bonds, and reimbursed from the bond proceeds; NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Hopkins, Minnesota: 1. The City intends to incur expenditures for the project described in Council Report 2017-138, for City Project 2017-10 (the “Project”), and intends to reimburse itself for such expenditures from the bond proceeds to be issued by the City in the maximum principal amount described in the “project”. 2. The City Manager is authorized to designate additions to Project 2017-10 in circumstances where time is of the essence, and any such designation shall be reported to the Council at the earliest practicable date and shall be filed with the official books and records of the City. 3. This resolution is intended to constitute a declaration of official intent for the purpose of Treas. Reg. #1.150-2 and any successor law, regulation, ruling or amendment pertaining thereto. Adopted by the City Council of the City of Hopkins, Minnesota, this 5thth day of December, 2017. By_______________________________ Molly Cummings, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 1 of 9 AGREEMENT FOR PROFESSIONAL SERVICES FINAL DESIGN & CONSTRUCTION SERVICES 2018 STREET & UTILITY IMPROVEMENTS CITY OF HOPKINS, MINNESOTA This Agreement, made this 5th day of December, 2017, by and between CITY OF HOPKINS, 1010 1st Street South, Hopkins, MN 55343, hereinafter referred to as CLIENT, and BOLTON & MENK, INC., 12224 Nicollet Avenue, Burnsville, MN 55337, hereinafter referred to as CONSULTANT. WITNESS, whereas the CLIENT requires professional services in conjunction with the 2018 STREET & UTILITY IMPROVEMENTS and whereas the CONSULTANT agrees to furnish the various professional services required by the CLIENT. NOW, THEREFORE, in consideration of the mutual covenants and promises between the parties hereto, it is agreed: SECTION I - CONSULTANT'S SERVICES A. The CONSULTANT agrees to perform the various Basic Services in connection with the proposed project as described in Exhibit I. B. Upon mutual agreement of the parties hereto, Additional Services may be authorized as described in Exhibit I or as described in Paragraph IV.B. SECTION II - THE CLIENT'S RESPONSIBILITIES A. The CLIENT shall promptly compensate the CONSULTANT in accordance with Section III of this Agreement. B. The CLIENT shall place any and all information related to the project in its custody at the disposal of the CONSULTANT for its use. Such information shall include but shall not be limited boundary surveys, topographic surveys, preliminary sketch plan layouts, building plans, soil surveys, abstracts, deed descriptions, tile maps and layouts, aerial photos, utility agreements, environmental reviews, and zoning limitations. The CONSULTANT may rely upon the accuracy and sufficiency of all such information in performing services unless otherwise instructed, in writing, by CLIENT. This obligation shall not include information that is classified as private or confidential under the Minnesota Government Data Practices Act (MGDPA), unless access to such information is essential to the CONSULTANT’s scope of services, in which case the CLIENT shall establish in writing, and CONSULTANT shall comply with, any conditions governing access to and use of such private or confidential information. C. The CLIENT will guarantee access to and make all provisions for entry upon both public and private portions of the project and pertinent adjoining properties. D. The CLIENT will give prompt notice to the CONSULTANT whenever the CLIENT observes or otherwise becomes aware of any defect in the proposed project. City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 2 of 9 E. The CLIENT shall designate a liaison person to act as the CLIENT'S representative with respect to services to be rendered under this Agreement. Said representative shall have the authority to transmit instructions, receive instructions, receive information, interpret and define the CLIENT'S policies with respect to the project and CONSULTANT'S services. F. The CLIENT shall provide such legal, accounting, independent cost estimating and insurance counseling services as may be required for completion of the consultant services described in this agreement. G. The CLIENT will obtain any and all regulatory permits required for the proper and legal execution of the project. H. The CLIENT will hire, when requested by the CONSULTANT, an independent test company to perform laboratory and material testing services, and soil investigation that can be justified for the proper design and construction of the project. The CONSULTANT shall assist the CLIENT in selecting a testing company. Payment for testing services shall be made directly to the testing company by the CLIENT and is not part of this Agreement. City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 3 of 9 SECTION III - COMPENSATION FOR SERVICES A. FEES. 1. The CLIENT will compensate the CONSULTANT in accordance with the following schedule of fees for the time spent in performance of Agreement services. Schedule of Fees Classification Hourly Rates Sr. Project Manager – Sr. Principal Engineer/Surveyor $140-198/Hour Sr. Project Manager – Principal Engineer/Surveyor $118-166/Hour Project Manager $100-150/Hour Project/Design Engineer /Planner $64-144/Hour Licensed Surveyor $76-140/Hour Project Surveyor $60-110/Hour Specialist (Nat. Resources; GIS; Traffic; Other) $70-130/Hour Senior Technician (Inc. Survey1) $70-145/Hour Technician (Inc. Survey1) $54-102/Hour Administrative Support & Clerical $35-84/Hour GPS/Robotic Survey Equipment No Charge CAD/Computer Usage No Charge Routine Photo Copying/Reproduction No Charge Routine Office Supplies No Charge Field Supplies/Survey Stakes & Equipment No Charge Mileage No Charge 1No separate charges will be made for GPS or robotic total stations on Bolton & Menk, Inc. survey assignments; the cost of this equipment is included in the rates for Survey Technicians. 2. Total cost for the services itemized under Exhibit I, Section A (Basic Services) shall not exceed $639,422. Itemization of this cost is as shown in the attached DETAILED WORK PLAN and PROJECT FEES tables, attached hereto as Exhibit II. 3. In addition to the foregoing, CONSULTANT shall be reimbursed at cost plus an overhead fee (not-to-exceed 10%) for the following Direct Expenses when incurred in the performance of the work. a. CLIENT approved outside (facilities not owned by CONSULTANT) computer services. b. CLIENT approved outside professional and technical services. c. Outside reproduction and reprographic charges. d. Expendable field supplies and special field equipment rental. e. Other costs for such additional items and services that the CLIENT may require the CONSULTANT to provide to fulfill the terms of this Agreement. 4. Additional services as outlined in Section I.B will vary depending upon project conditions and will be billed on an hourly basis at the rate described in Section III.A.1. 5. The payment to the CONSULTANT will be made by the CLIENT upon billing at intervals not more often than monthly at the herein rates. Itemized invoices identifying all work completed shall be submitted to the CLIENT by CONSULTANT and paid in the same manner as other claims made to the CLIENT. City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 4 of 9 SECTION IV - GENERAL A. STANDARD OF CARE Professional services provided under this Agreement will be conducted in a manner consistent with that level of care and skill ordinarily exercised by members of the Consultant's profession currently practicing under similar conditions. No warranty, express or implied, is made. B. CHANGE IN PROJECT SCOPE In the event the CLIENT changes or is required to change the scope of the project from that described in Section I and/or the applicable addendum, and such changes require Additional Services by the CONSULTANT, the CONSULTANT shall be entitled to additional compensation at the applicable hourly rates. The CONSULTANT shall give notice to the CLIENT of any Additional Services, prior to furnishing such additional services and the CLIENT must approve an Additional Services in writing. The CLIENT may request an estimate of additional cost from the CONSULTANT, and upon receipt of the request, the CONSULTANT shall furnish such, prior to authorization of the changed scope of work. C. INDEPENDENT CONTRACTOR The CONSULTANT shall at times be deemed an independent contractor. The CONSULTANT is not to be deemed an employee or agent of the CLIENT and has no authority to make any binding commitments or obligations on behalf of the CLIENT except to the extent expressly provided herein. All services provided by the CONSUTANT pursuant to this agreement shall be provide on an independent contractor basis not as an employee of the CLIENT for any purpose including, but not limited to, income tax withholding, workers’ compensation, unemployment compensation, FICA taxes, liability for torts, and eligibility for employee benefits. D. LIMITATION OF LIABILITY CONSULTANT shall indemnify, defend, and hold harmless CLIENT and its officials, agents and employees from any loss, claim, liability, and expense (including reasonable attorneys’ fees and expenses of litigation) arising from, or based in the whole, or in any part, on any negligent act or omission by CONSULTANT’S employees, agents, or subconsultants. In no event shall CLIENT be liable to CONSULTANT for consequential, incidental, indirect, special, or punitive damages. CLIENT shall indemnify, defend, and hold harmless CONSULTANT and its employees from any loss, claim, liability, and expense (including reasonable attorneys’ fees and expenses of litigation) arising from, or based in the whole, or in any part, on any negligent act or omission by CLIENT’S employees, agents, or consultants. In no event shall CONSULTANT be liable to CLIENT for consequential, incidental, indirect, special, or punitive damages. Nothing contained in this Agreement shall be construed as a limitation on or waiver of any immunities or limitations on liability otherwise available to the CLIENT. Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in favor of a third party against either the CLIENT or the CONSULTANT. The CONSULTANT'S services under this Agreement are being performed solely for the CLIENT'S benefit, and no other entity shall have any claim against the CONSULTANT because of this Agreement or the performance or nonperformance of services provided hereunder. The CLIENT agrees to include a provision in all City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 5 of 9 contracts with contractors and other entities involved in this project to carry out the intent of the paragraph. E. INSURANCE 1. The CONSULTANT agrees to maintain, at CONSULTANT’S expense a commercial general liability and excess umbrella general liability insurance policy or policies insuring CONSULTANT against claims for bodily injury, death or property damage arising out of CONSULTANT’S general business activities. The general liability coverage shall provide limits of not less than $2,000,000 per occurrence and not less than $2,000,000 general aggregate. Coverage shall include Premises and Operations Bodily Injury and Property Damage; Personal and Advertising Injury; Blanket Contractual Liability; Products and Completed Operations Liability. 2. The CONSULTANT also agrees to maintain, at CONSULTANT’S expense, a single limit or combined limit automobile liability insurance and excess umbrella liability policy or policies insuring owned, non-owned and hired vehicles used by CONSULTANT under this Agreement. The automobile liability coverages shall provide limits of not less than $1,000,000 per accident for property damage, $2,000,000 for bodily injuries, death and damages to any one person and $2,000,000 for total bodily injury, death and damage claims arising from one accident. 3. CLIENT shall be named Additional Insured for the above liability policies. 4. The CONSULTANT agrees to maintain, at the CONSULTANT'S expense, statutory worker's compensation coverage together with Coverage B, Employer’s Liability limits of not less than $500,000 for Bodily Injury by Disease per employee, $500,000.00 for Bodily Injury by Disease aggregate and $500,000 for Bodily Injury by Accident. 5. During the period of design and construction of the project, the CONSULTANT also agrees to maintain, at CONSULTANT’S expense, Professional Liability Insurance coverage insuring CONSULTANT against damages for legal liability arising from an error, omission or negligent act in the performance of professional services required by this agreement. The professional liability insurance coverage shall provide limits of not less than $2,000,000 per claim and an annual aggregate of not less than $2,000,000 on a claims-made basis. 6. Prior to commencement of this Agreement, the CONSULTANT will provide the CLIENT with certificates of insurance, showing evidence of required coverages. All policies of insurance shall contain a provision or endorsement that the coverage afforded will not be canceled or reduced in limits by endorsement for any reason except non-payment of premium, until at least 30 days’ prior written notice has been given to the CLIENT, and at least 10 days’ prior written notice in the case of non-payment of premium. F. OPINIONS OR ESTIMATES OF CONSTRUCTION COST Where provided by the CONSULTANT as part of Exhibit I or otherwise, opinions or estimates of construction cost will generally be based upon public construction cost information. Since the CONSULTANT has no control over the cost of labor, materials, competitive bidding process, weather conditions and other factors affecting the cost of construction, all cost estimates are opinions for general information of the CLIENT and the CONSULTANT does not warrant or guarantee the accuracy of construction cost opinions or estimates. The CLIENT acknowledges that City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 6 of 9 costs for project financing should be based upon contracted construction costs with appropriate contingencies. G. CONSTRUCTION SERVICES It is agreed that the CONSULTANT and its representatives shall not be responsible for the means, methods, techniques, schedules or procedures of construction selected by the contractor or the safety precautions or programs incident to the work of the contractor. H. USE OF ELECTRONIC/DIGITAL DATA Because of the potential instability of electronic/digital data and susceptibility to unauthorized changes, copies of documents that may be relied upon by CLIENT are limited to the printed copies (also known as hard copies) that are signed or sealed by CONSULTANT. Except for electronic/digital data which is specifically identified as a project deliverable by this AGREEMENT or except as otherwise explicitly provided in this AGREEMENT, all electronic/digital data developed by the CONSULTANT as part of the PROJECT is acknowledged to be an internal working document for the CONSULTANT’S purposes solely and any such information provided to the CLIENT shall be on an “AS IS” basis strictly for the convenience of the CLIENT without any warranties of any kind. As such, the CLIENT is advised and acknowledges that use of such information may require substantial modification and independent verification by the CLIENT (or its designees). Provision of electronic/digital data, whether required by this Agreement or provided as a convenience to the Client, does not include any license of software or other systems necessary to read, use or reproduce the information. It is the responsibility of the CLIENT to verify compatibility with its system and long-term stability of media. CLIENT shall indemnify and hold harmless CONSULTANT and its Subconsultants from all claims, damages, losses, and expenses, including attorneys' fees arising out of or resulting from third party use or any adaptation or distribution of electronic/digital data provided under this AGREEMENT, unless such third party use and adaptation or distribution is explicitly authorized by this AGREEMENT. I. DATA PRACTICES All data collected, created, received, maintained, or disseminated, or used for any purposes in the course of the CONSULTANT’S performance of the Agreement is governed by the Minnesota Government Data Practices Act, Minnesota Statutes Section 13.01, et seq. or any other applicable state statutes and state rules adopted to implement the Act, as well as state statutes and federal regulations on data privacy. The Consultant agrees to abide by these statutes, rules and regulations and as they may be amended. In the event the CONSULTANT receives a request to release data, it shall notify CLIENT as soon as practical. The CLIENT will give instructions concerning release of data to requesting party and CONSULTANT will be reimbursed as Additional Services by CLIENT for its reasonable expenses in complying with the request. J. PERIOD OF AGREEMENT City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 7 of 9 This Agreement will remain in effect for the longer of a period of two years or such other explicitly identified completion period, after which time the Agreement may be extended upon mutual agreement of both parties. K PAYMENTS If CLIENT fails to make any payment due CONSULTANT for services and expenses within 60 days after date of the CONSULTANT'S itemized invoice, a service charge of one and one-half percent (1.5%) per month or the maximum rate permitted by law, whichever is less, will be charged on any unpaid balance. In addition after giving seven days' written notice to CLIENT, CONSULTANT may, without waiving any claim or right against the CLIENT and without incurring liability whatsoever to the CLIENT, suspend services and withhold project deliverables due under this Agreement until CONSULTANT has been paid in full all amounts due for services, expenses and charges. L. TERMINATION This Agreement may be terminated by the CLIENT for any reason or for convenience by the CLIENT upon seven (7) days written notice. The CONSULTANT may only terminate for non- payment by CLIENT upon CLIENT’s failure to cure upon 30 days written notice. M. CONTINGENT FEE The CONSULTANT warrants that it has not employed or retained any company or person, other than a bona fide employee working solely for the CONSULTANT to solicit or secure this Contract, and that it has not paid or agreed to pay any company or person, other than a bona fide employee, any fee, commission, percentage, brokerage fee, gift or any other consideration, contingent upon or resulting from award or making of this Agreement. N. NON-DISCRIMINATION The provisions of any applicable law or ordinance relating to civil rights and discrimination shall be considered part of this Agreement as if fully set forth herein. The CONSULTANT is an Equal Opportunity Employer and it is the policy of the CONSULTANT that all employees, persons seeking employment, subcontractors, subconsultants and vendors are treated without regard to their race, religion, sex, color, national origin, disability, age, sexual orientation, marital status, public assistance status or any other characteristic protected by federal, state or local law. O. CONTROLLING LAW This Agreement is to be governed by the law of the State of Minnesota. P. DISPUTE RESOLUTION City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 8 of 9 CLIENT and CONSULTANT agree to negotiate all disputes between them in good faith for a period of 30 days from the date of notice of dispute prior to proceeding to formal dispute resolution or exercising their rights under law. Q. SURVIVAL All obligations, representations and provisions made in or given in Section IV of this Agreement will survive the completion of all services of the CONSULTANT under this Agreement or the termination of this Agreement for any reason. R. SEVERABILITY Any provision or part of the Agreement held to be void or unenforceable under any law or regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon CLIENT and CONSULTANT, who agree that the Agreement shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. S. AUDIT DISCLOSURE The CONSULTANT must allow the CLIENT, or its duly authorized agents, and the state auditor or legislative auditor reasonable access to the CONSULTANT’s books, records, documents, and accounting procedures and practices that are pertinent to all services provided under this Agreement for a minimum of six years from the termination of this Agreement. [remainder of the page intentionally blank] City of Hopkins 2018 Agreement (Modified from 2004 Standard Form) VER. 12/05/2017 Page 9 of 9 SECTION V - SIGNATURES THIS INSTRUMENT embodies the whole agreement of the parties, there being no promises, terms, conditions or obligation referring to the subject matter other than contained herein. This Agreement may only be amended, supplemented, modified or canceled by a duly executed written instrument signed by both parties. IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in their behalf. CLIENT: City of Hopkins, Minnesota CONSULTANT: Bolton & Menk, Inc. Mike Waltman, P.E., Principal Engineer Marcus A. Thomas, P.E., BMI Office Manager Date Date City of Hopkins December 5, 2017 1 EXHIBIT I FINAL DESIGN, CONSTRUCTION OBSERVATION, ADMINISTRATION & STAKING 2018 STREET AND UTILITY IMPROVEMENTS CITY OF HOPKINS, MINNESOTA A. BASIC SERVICES In accordance with the City of Hopkins’ Preliminary Engineering Report, Bolton & Menk, Inc. has been requested to complete final design, bidding assistance, construction staking, construction observation and construction administration services for the City’s 2018 Street and Utility Improvements. The project area includes the following corridors:  Lake St NE, Blake Rd N to Texas Ave S (surface improvements from Blake Rd to the bridge is part of a separate project)  Texas Ave, 150 feet south of Lake St NE to Division St (Shared with St. Louis Park)  Alley south of Lake St NE, Murphy Ave to Texas Ave S  Texas Ave S, Division St to TH 7 (St. Louis Park)  Division St, Texas Ave S to the western dead end (Shared with St. Louis Park)  Cambridge St, Texas Ave S to Blake Rd N  Oxford St, Texas Ave S to Blake Rd N  Murphy Ave, Oxford St to Lake St NE  17th Ave & 1st St S, Storm Sewer and Pavement Replacement  CIPP Lining throughout the City  Spot Concrete Sidewalk and Alley Repairs Building from tasks 1 and 2 of our preliminary design scope of services, detailed tasks associated with the work are itemized in the attached Detailed Work Plan and are described below. Task 3: Final Design & Bidding Services Final Design Final design for the 2018 Street and Utility Improvements will be completed based on the Preliminary Engineering Report completed by Bolton & Menk, Inc. in November, 2017. Final plans and specifications will be completed in compliance with the City of Hopkins’ Engineering Guidelines. Detailed construction plans will be prepared in Civil3D design software. The plans and specifications will include:  Plan and profile views of the street reconstruction and utility improvements at 25 scale.  Cross sections will be shown for reconstructed streets at approximately 25' spacing and at each driveway.  Required construction details.  Special provisions for elements of work not addressed in the MnDOT 2016 Standard Construction Specifications. City of Hopkins December 5, 2017 2  Construction phasing/staging plans to coordinate construction with Blake Rd, Metropolitan Council, and MnDOT’s work at TH 7 and Texas Ave.  Temporary traffic control plans for necessary detours or temporary access routes to businesses.  Metropolitan Council specific construction details, specifications, and CAD work prepared by others but integrated into Bolton & Menk’s plan set. Final plans will be submitted for review and comment by private utility owners. Permit applications as noted in the Preliminary Engineering Report will be completed and submitted to the permitting agency. Upon completion of construction plans and specifications, a final estimate of construction cost will be prepared and submitted to the client. The project will be advertised, bids will be taken, and recommendation will be made to accept or reject bids. Meetings included during final design include three (3) City Staff meetings for design review and two (2) City Council meetings for final plan presentation and conducting the Public Assessment Hearing. Bolton & Menk will coordinate efforts with the Blake Rd Improvements project, Metropolitan Council, St. Louis Park, and Mn/DOT to assure the plans coincide with one another. Impacts to some trees and privately owned landscaping are anticipated. Coordination efforts will be undertaken with homeowners regarding tree removals and landscaping impacts prior to construction. Letters will be sent to each affected property to inform the owner of the known or potential tree and/or landscaping impacts to their property. The Construction Observer and/or Project Engineer will respond to questions of the owner(s) and will coordinate on-site meetings as necessary to coordinate any impacts prior to construction. Supplemental Topographic Survey Completion of the Feasibility Study for this project has revealed the need for some additional topographic survey, necessary to complete the final design of the proposed improvements. This includes Oxford St where construction was recently finished for the new Oxford Village apartments. Topographic survey will be completed in these areas to the same standard as done during the preliminary design phase. Special Assessments Assistance For this project, the City of Hopkins intends to assess this project prior to awarding the contract, based on the bid of the lowest responsible bidder. Bolton & Menk will prepare a final assessment roll after bids have been opened and will attend the public assessment hearing to assist City Staff. Bolton & Menk will assist City Staff with the assessment process and associated statutory requirements, as well as aid in responding to property owner inquiries throughout the process. Bolton & Menk will attend and facilitate two neighborhood meetings prior to the final assessment hearing to provide additional information on assessment amounts, payment options, and any remaining questions on the proposed improvements. City of Hopkins December 5, 2017 3 Task 4: Construction Services Construction Staking Construction staking indicating cuts to the line and grade of the proposed utilities will typically be performed at intervals of 50 feet. These utilities include sanitary sewer pipe and manholes; watermain pipe, hydrants, and bends; storm sewer pipe, manholes, and catch basins; Metropolitan Council Forcemain. Curb stakes will be provided along the reconstructed roadways at intervals of 25 feet. Construction Observation and Administration This project is proposed to be constructed during the 2018 construction season and is anticipated to occur multiple phases of construction between late May and early November. The projected fee estimate is therefore based upon a 26-week construction season. Full time construction observation is proposed for this project. The contractor’s use of several construction crews across the multi-phased project will be necessary for timely completion. Duties of the Construction Observer will include attendance at the pre-construction meeting and all construction-related meetings, service as a liaison between the City and the contractor, review of the completed work to determine if the project is in general conformance with the plans and specifications, review and scheduling of all materials testing, maintenance of construction documentation, tracking quantities, project closeout including checking in on punch list items, and communication with affected property owners, as necessary, to address their construction-related concerns and issues. Communication will include door-to-door notices as often as daily, phone calls, text messages, emails, and in-person meetings. Administration duties include a pre-construction meeting, weekly project meetings including minutes, review of shop drawings, sending out weekly email updates to resident subscribers, preparing and mailing out monthly newsletters to residents, updating and maintaining a project website, and preparation of pay estimates. Observation and administration services will be completed on an hourly basis. Estimated weekly time spent for key staff during the construction process (tasks 4.2 – 4.4) are as follows: Estimated Hours: Tasks 4.2 – 4.4 Title Hours / Week Weeks Total Hours Principal Engineer-in-Charge 3 26 78 Project Design Engineer 12 26 312 Construction Observer 60 26 1560 Survey Crew (1-man) 20 20 400 City of Hopkins December 5, 2017 4 Record Drawings & GIS Integration Record drawings detailing the completed improvements as recorded by the construction observer will be completed and furnished to the City in hard copy and electronic format. These record drawings will and also integrated with the City’s GIS web application in PDF. Utilities, signs, curb stops, and structures will located (horizontally) after construction using a handheld GPS unit and will also be incorporated in the GIS schematic layout as GIS entities. The following is a preliminary schedule for the 2018 Street & Utility Improvements: Preparation of Final Plans & Specifications .......................... December 6 – March 6, 2018 Approve Final Plans & Specifications / Set Bid Date / Set Assessment Hearing Authorize Advertisement for Bids ................................................ March 6, 2018 Bid Opening ........................................................................................... April 10 - 12, 2018 Council Sets Public Assessment Hearing Date ........................................ April 17, 2018 Neighborhood Meeting 3 ........................................................................... May 1 - 10, 2018 Council Accepts Bids / Conduct Public Assessment Hearing / Adopt Assessment Roll / Award Bid .............................................. May 15, 2018 Construction ...................................................................Late May – Early November 2018 B. ADDITIONAL SERVICES Consulting services performed other than those authorized under Section I.A. shall be considered not part of the Contract Services and may be authorized by the CLIENT as additional services. Additional Services consist of those services which are not generally considered to be Contract Services; or exceed the requirements of the Contract Services; or are not definable prior to the commencement of the project; or vary depending on the technique, procedures or schedule of the project contractor. Additional services may consist of the following: 1. Cost of postage for mass mailing (those with greater than 100 recipients). 2. All other services not specifically identified in Section A. DETAILED WORK PLAN ESTIMATED PERSON-HOURS 2018 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES CITY OF HOPKINS, MINNESOTA 11/28/2017 CLIENT:CITY OF HOPKINS, MINNESOTA PROJECT: CONSULTANT: 2018 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES BOLTON & MENK, INC. Task No.Work Task Description 3.0 FINAL DESIGN & BIDDING 3.1 Utility Engineering and Design 40 60 100 220 420 3.2 Roadway Engineering and Design 40 100 400 540 3.3 Plan Set Production 100 180 500 780 3.4 Supplemental Topographic Survey 8 16 20 44 3.5 Private Utility, Met Council, & MnDOT Coordination 16 80 40 136 3.6 Construction Quantities and Cost Estimates 6 30 40 12 88 3.7 Construction Specifications 30 30 40 100 3.8 Permit Applications 2 8 16 16 4 46 3.9 Bidding Assistance, Addenda, Award Recommendation 12 12 20 20 64 3.10 Final Assessment Roll Preparation 4 20 24 3.11 QA / QC 32 12 44 3.12 Project Meetings (City Staff - 3), Public Communication 24 80 80 40 16 240 3.13 City Council Meeting (2 meetings)10 10 20 SUBTOTAL HOURS: TASK 3 216 68 478 796 324 500 40 8 16 20 80 2546 4.0 CONSTRUCTION SERVICES 4.1 Construction Phase Startup (Precon, Resident Coordination, Construction Staking Preparation, etc.)24 24 80 12 40 180 4.2 Construction Administration (26 weeks @ Waltman 3 hrs/week, Amatuccio 12 hrs/week)78 312 64 60 514 4.3 Construction Observation (26 weeks @ 60 hrs/week)1560 1560 4.4 Construction Staking 28 60 400 488 4.5 Record Drawings 4 8 40 52 4.6 Project Closeout, Punch List 20 40 100 160 4.7 GIS Integration 4 16 8 40 68 SUBTOTAL HOURS: TASK 4 130 0 400 0 1788 40 64 40 100 400 60 3022 TOTAL HOURS 346 68 878 796 2112 540 104 48 116 420 140 5568 Surveying Technician Survey Crew (1-man)ClericalEngineering Specialist Construction Observer ESTIMATED PERSON-HOURS TotalsPrincipal Engineer Project Engineer Project Design Engineer Design Engineer Web Specialist Survey Manager / L.S. ESTIMATE OF PROJECT FEES 2018 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES CITY OF HOPKINS, MINNESOTA 11/28/2017 CLIENT:CITY OF HOPKINS, MINNESOTA PROJECT: CONSULTANT: 2018 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES BOLTON & MENK, INC. TASK AVERAGE RATE:$161.00 $153.00 $124.00 $110.00 $115.00 $70.00 $95.00 $145.00 $100.00 $135.00 $79.00 3.0 FINAL DESIGN & BIDDING 3.1 Utility Engineering and Design $6,440.00 $9,180.00 $12,400.00 $24,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $52,220.00 3.2 Roadway Engineering and Design $6,440.00 $0.00 $12,400.00 $44,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $62,840.00 3.3 Plan Set Production $0.00 $0.00 $0.00 $11,000.00 $20,700.00 $35,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $66,700.00 3.4 Supplemental Topographic Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1,160.00 $1,600.00 $2,700.00 $0.00 $5,460.00 3.5 Private Utility, Met Council, & MnDOT Coordination $2,576.00 $0.00 $9,920.00 $0.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $17,096.00 3.6 Construction Quantities and Cost Estimates $966.00 $0.00 $3,720.00 $4,400.00 $1,380.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $10,466.00 3.7 Construction Specifications $4,830.00 $0.00 $3,720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,160.00 $11,710.00 3.8 Permit Applications $322.00 $1,224.00 $1,984.00 $1,760.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $316.00 $5,606.00 3.9 Bidding Assistance, Addenda, Award Recommendation $1,932.00 $0.00 $1,488.00 $2,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1,580.00 $7,200.00 3.10 Final Assessment Roll Preparation $644.00 $0.00 $2,480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,124.00 3.11 QA / QC $5,152.00 $0.00 $0.00 $0.00 $1,380.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,532.00 3.12 Project Meetings (City Staff - 3), Public Communication $3,864.00 $0.00 $9,920.00 $0.00 $9,200.00 $0.00 $3,800.00 $0.00 $0.00 $0.00 $1,264.00 $28,048.00 3.13 City Council Meeting (2 meetings)$1,610.00 $0.00 $1,240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,850.00 SUBTOTAL FEES: TASK 3 $34,776.00 $10,404.00 $59,272.00 $87,560.00 $37,260.00 $35,000.00 $3,800.00 $1,160.00 $1,600.00 $2,700.00 $6,320.00 $279,852.00 4.0 CONSTRUCTION SERVICES 4.1 Construction Phase Startup (Precon, Resident Coordination, Construction Staking Preparation, etc.)$3,864.00 $0.00 $2,976.00 $0.00 $9,200.00 $0.00 $0.00 $1,740.00 $4,000.00 $0.00 $0.00 $21,780.00 4.2 Construction Administration (26 weeks @ Waltman 3 hrs/week, Amatuccio 12 hrs/week)$12,558.00 $0.00 $38,688.00 $0.00 $0.00 $0.00 $6,080.00 $0.00 $0.00 $0.00 $4,740.00 $62,066.00 4.3 Construction Observation (26 weeks @ 60 hrs/week)$0.00 $0.00 $0.00 $0.00 $179,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $179,400.00 4.4 Construction Staking $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $4,060.00 $6,000.00 $54,000.00 $0.00 $64,060.00 4.5 Record Drawings $644.00 $0.00 $992.00 $0.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,236.00 4.6 Project Closeout, Punch List $3,220.00 $0.00 $4,960.00 $0.00 $11,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $19,680.00 4.7 GIS Integration $644.00 $0.00 $1,984.00 $0.00 $920.00 $2,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,348.00 SUBTOTAL FEES: TASK 4 $20,930.00 $0.00 $49,600.00 $0.00 $205,620.00 $2,800.00 $6,080.00 $5,800.00 $10,000.00 $54,000.00 $4,740.00 $359,570.00 TOTAL FEES $55,706.00 $10,404.00 $108,872.00 $87,560.00 $242,880.00 $37,800.00 $9,880.00 $6,960.00 $11,600.00 $56,700.00 $11,060.00 $639,422.00 Design Engineer PROJECT FEES Principal Engineer Project Engineer Project Design Engineer Survey Crew (1-man)Clerical TotalsSurvey Manager / L.S. Construction Observer Surveying Technician Engineering Specialist Web Specialist