Loading...
VI.2. Pavilion Project Contract Awards; Stadler (Memo)er��.oran um To: Copy: From: D ate : Subject: Overview Public �Uorks De artment p Honorable Mayor and Members of the City Council Mike Mornson, City Manager Steven J. Stadler, Public Works Director January 11, 2018 Pavilion Project Contract Awards/Assignment to RJM Construction �id opening vva� held on 1"ue�day, Jan 9 at 2 pr�. aNe had very cornpetitive bidding in virtually all 15 bid categories. We opened over 90 separate bids. The construction manager, RJM Construction, is reviewing all the apparent low bids and will be providing their recommendation as soon as possible. A City Council report will be provided as soon as the CM completes their bids analysis and provides their award recommendations, likely late Friday or Monday morning. The anticipated City Council actions will be to adopt a resolution awarding 15 contracts and then a motion to approve an agreement assigning these contracts to the City's Construction Manager, RJM Construction. � _ _ Project Costs/Budget Update When we consider the construction low bids and quotes, and all other project costs, our total project cost is at $5,839,888 — see attached report. Our project budget is $5,700,000. Having said that, there are a few factors to point out: 1) the cost includes a construction contingency of only $135,207, but there are also unassigned allowances built into many of the bids to be used at the CM's discretion, these total $130,000; 2) there are two bids received by one contractor (categories: select demolition and site earthwork/utilities) wherein all four addendums were not acknowledged with their bids and their combined bids are $126,240 below the second low bidders — the above project cost assumes we'll have to award to the second low bidder; 3) unanticipated poor load bearing capacity soils resulted in having to specify specialized foundation methods, increasing the cost by $94,000. There are two bid alternates not included in the above project cost that staff are considering: an outdoor assist refrigeration upgrade and folding glass partition walls. The costs for these bid alternates are $41, 800 and $18, 985, respectively. The City Council report will include a recommendation on these alternates. ESTIMATE DATE: January 9, 2017 PROJECT: Hopkins Pavilion ARCHITECT: 292 Design DRAWING DATE: December 20, 2017 Apparent Low Previous Bid $/sf Difference DESCRIPTION Sub Contractors Estimate Amount 10,024 , , Can�truct�on Cfls�s � �� � � � � � �� ;. . � . � 1A - Survey Westwood $8,034 $6,138 $0.61 ($1,896) 1B - Final Cleaning Petersen $21,576 $11,828 $1.18 ($9,748) 2A - Demolition �Excludes site Demolition) Kellington $220,753 $149,270 $14.89 ($71,483) 3A - Concrete Systems Steenberg 3A & 4A $157,141 $510,000 $50.88 $352,859 3B - Precast Structural Concrete Plank Molin $54,918 $66,033 $6.59 $11,115 4A - Masonry Systems Steenberg 3A & 4A $308,489 $0 $0.00 ($308,489) 7A - Waterproofing Kremer Davis $0 $5,680 $0.57 $5,680 SA - Steel Material Briese $72,120 $48,500 $4.84 ($23,620) 5B - Steel Labor Bald Eagle $38,500 $34,300 $3.42 ($4,200) 6A - Carpentry and Specialties George F Cook $195,809 $220,600 $22.01 $24,791 7B - Roofing B & B $263,054 $266,700 $26.61 $3,646 7C - Metal Wall Panels Flynn Midwest $134,295 $151,542 $15.12 $17,247 8A - Aluminum Entrances/Storefronts Brin Contract Glazing $147,538 $171,500 $17.11 $23,962 8C - Sectiona) Doors Crawford $23,000 $15,860 $1.58 ($7,140) 9A - Gypsum Board Systems RTL $124,962 $81,100 $8.09 �$43,862) 9E - Painting Decor Tec $169,054 $219,890 $21.94 $50,836 9B - Tiling Twin City T& M $21,820 $21,600 $2.15 ($220) 9C - Acoustical Ceilings Kirk $15,030 $9,960 $0.99 ($5,070) 9D - Flooring Henricksen- $23,945 $5,242 $0.52 ($18,703) 13 - Ice Rink Systems Cimco $1,377,200 $1,258,900 $125.59 ($118,300� 10A - Signage Spectrum $10,000 $20,125 $2.01 $10,125 12A - Roller Shades American Drapery Systems $0 $2,393 $0.24 $2,393 31B - Rammed Aggregate Piles Foundation Service Corp $95,000 $94,000 $9.38 ($1,000) 21A - Fire Sprinkler Lifesaver $41,550 $24,982 $2.49 ($16,568) 22A - Plumbing and Piping Systems Modern Piping $185,473 $274,000 $27.33 $88,527 23A - HVAC and Contro) Systems General Sheet Metal $247,950 $313,223 $31.25 $65,273 26A - Electrica) Manor $203,850 $260,350 $25.97 $56,500 31A - Earthwork/Utilities Rachel $205,569 $179,470 $17.90 �$26,099) 32B - Concrete Curb and Gutter North Country $22,915 $20,290 $2.02 ($2,625) 32D - Seeding and Plants Urban Companies $50,000 $72,000 $7.18 $22,000 Genera) Requirements $51,306 $51,306 $5.12 $0 General Conditions $166,531 $166,531 $16.61 $0 General Liability Insurance $38,114 $45,174 $4.51 $7,060 Builders Risk Insurance $0 $0 $0.00 $0 Building Permit $2,378 $2,538 $0.25 $160 Bond $33,792 $47,810 $4.77 $14,018 Subt�tt�1 Cvristruction �'osts ' $�,733,6b'6 $�,828,835 ; „��51:73 ;$97�,169 Escalation $0 $0 $0.00 $0 Design/Estimating Contingency $121,951 $0 $0.00 ($121,951) Contingency $125,374 $135,207 $13.49 $9,833 Contractors Fee $103,561 $111,691 $11.14 $8,130 : 5 �'�`2 7 , 'Tr�tal Cons#�ruct�on ��st ; `:` ; DS2 S f�75 33 =: S06 3� 6�38 , ; . ' � 1 l � 1 1 � ... , °' ��, 1. � CLARIFICATIONS