RESOLUTION NO: 02-67
RESOLUTION MAKING FINDINGS OF FACT AND
APPROVING A CONDITIONAL USE PERMIT TO CONSTRUCT A BUILDING.
WHEREAS, an application for Conditional Use Permit CUP02-5 has been made by
Metro Water Conditioning, Inc;
WHEREAS, the procedural history of the application is as follows:
1. That an application for a conditional use permit was made by Metro Water
Conditioning on April 23, 2002;
2. That the Hopkins Zoning and Planning Commission, pursuant to mailed
and published notice, held a public hearing on the application and
reviewed such application on May 28, 2002, and June 26th: all persons
present were given an opportunity to be heard;
3. That the written comments and analysis of City staff were considered; and
4. A legal description ofthe subject property is as follows:
Lot 1 Block 1 Downey Addition
NOVl, THEREFORE, BE IT RESOLVED that the application for Conditional Use
Permit CUP02-5 is hereby approved based on the following Findings of Fact:
1. That the proposed use meets the requirements for a conditional use permit.
BE IT FURTHER RESOLVED that application for Conditional Use Permit CUP02-5 is
hereby approved subject to the following conditions:
1. A temporary right of entry or construction easement will be needed from the
property owners to the south of this site in order to install the curb described in
curb detail A-A.
2. The concrete gutter of the concrete driveway apron must be installed to drain. hl
order to accomplish this, a high point may need to be installed in the gutter.
3. Nine Mile Creek Watershed District approval and permitting is required for this
project.
4. That the plat is approved and filed.
5. That a revised landscaped plan is submitted and approved by staff.
6. The developer shall install a stOlIDceptor on the end of the storm sewer pipe at the
end of the 6th Street South right of way, just east of 12th Avenue South before it
outlets into Nine Mile Creek. The stormceptor shall be designed to treat the flow
for the entire drainage area. All costs associated with furnishing and installing the
stormceptor to City standards shall be the responsibility of the developer.
Following City approval and acceptance of the stormceptor installation, the City
will take over the responsibility, ownership, and maintenance of the stormceptor.
This overall treatment of the entire drainage area will be allowed by the City
instead of an individual storm sewer plpmg and treatment system on the
individual development site.
7. Prior to the issuance of the building permit, the developer shall provide an
accurate survey and staking of the property, which is found acceptable to the City
Attorney and Building OfficiaL
8. That the access to the site from 12th Avenue is increased 25-30 feet to the north.
9. That the applicant's truck does not back into the alley from Seventh Street South.
Adopted this 16th day of July 2002.
/~
Eu ene J. Maxwell, Mayor