CR2002-070 Change order-final payment parking lots CITY OF ~ . ~ kOPK\NS . May 2, 2002 Council Report 2002-070 Approve Construction Change Order and Final Payment - Parking Lots 500 & 600 and 10th and 11th Avenue North Improvements Proposed ActIon. Staff recommends adoption of the followIng motIon: Move that Council approve construction chanqe order 2 in the amount of $75,483.49 pertaininq to contract work on Parkinq Lots 500 & 600 and 10th and 11th Avenues North improvements and adopt Resolution 2002-43, Resolution acceptinq work and orderinq final payment, Project 98- 12. Overview. The contractor has completed construction and acted on all punch list items to the City's satisfaction. Construction change order no. 2, in the amount of $75,483.49, was discussed at the October 30, 2001 Council Work session. City Council needs to act on change order no. 2 and the final pay request to close the project. . Primary Issues to Consider. . Change order specifics . Final Project Budget Summary Supportinq information. . Contract Change Order 2 . Application for final payment . Resolution 2002-43 Steven J. Stadler, ublic Works Director Financial Impact: $ 101 ,197.75 Budgeted: Y/N Y Source: Utilities, PIR, Related Documents (CIP, ERP, etc.): Notes: Total project costs are $ 78,000 above project budqet. . . Council Report 2002-070 Page 2 Analysis of Issues . Change order specifics The two largest change orders are the soil corrections in lot 500 ($30,674.75) and additional gravel required due to not reclaiming the asphalt from lot 500 ($23,114.00). Regarding the soil corrections, the two soil borings from lot 500 did not reveal the extent of poor soils encountered. The additional excavation and gravel prices did not exceed the bid prices. In fact, the contractor agreed to a $3,000 reduction in these costs due to the increased quantity of work. The additional cost incurred by not reclaiming the lot 500 asphalt was necessary to maintain adequate open parking areas during construction and to maintain a reasonable construction schedule. An explanation of each change order item is included with the attached change order form. . Final project budget summary OriQinal construction contract amount:... ... ... ... .., ... ... ... ... ..$472,597.00 . Engineering Fees:................. 11II .............. Ii..... I......... 11II.............. ....$113,194.40 Feasibility Report & surveying: $29,100 Design: $25,400 Construction services: $49,438 Additional expenses: $9,256.40 Change Order No.1: (approved August 7).........................$36,519.16 Engineering fee change order: (approved Feb 5,2002)........... $19,000 Construction change order #2....................................... ...$75,483.49 Total Project cost..... 1-1It...... ......... ................ ............. .., ".... .$716,794.05 (12 % above original project budget) (Total construction costs = $584,599.65 - 23.70/0 over original cont amount) ORIGINAL TOTAL PROJECT BUDGET: ......... ...... .......$638,005.95 (construction contract amount x 1.35 to cover engrg + contingencies) . Total storm sewer utility additional construction costs:....... ..$38,385.01 Proposed total engineering fees = $132,194.40 or 22.6.00/0 of construction cost . CHANGE ORDER No. 2 DA TE OF ISSUANCE 4-24-02 EFFECTIVE DA TE 4-24-02 O\VNER City of Hopkins CONTRACTOR DMJ Contract: 9812 Project: Hopkins Lots 500 & 600 OWNER's Contract No. 2000-41 1m ENGINEER's Contract No. 9812 EN GlNEER RLK KULlsisto Ltd. You are directed to make the following changes in the Contract Documents; Description: See attachment Reason for Change Order: See attachment Attachments: (List documents supporting change) CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price Original Contract Times: $ Substantial Completion:_August 31,2001_ 47?j97.00 Ready for final payment:_September 21,2001 (days or dates) . Net Increase (Decrease) from previous Change Orders No._I_to_I_: Net change from previous Change Orders No._I_to No._J_: $ ."J6,jI9.16 Substantial Completion:_2 ] Ready for final payment:_ 21 Contract Price prior to this Change Order: ( days) $ 509,1 16.16 Contract Times prior to this Change Ordec Substantial Complction:_August 31. 200 J ~ Net increase (decrease) ofthis Change Order: Ready for tirJa] payment:_ September 21, 200 I (days or oates) $ 75.483.49 Net increase {decrease) this Change Order: Contract Price with all approved Change Orders: Substantial Completion: Ready for tinal payment: .$ 584.599.65 (days) Contract Times with all approved Change Orders: Substantial CompJetion:_ September 21, 2001 Ready for final payment;~ October J 2, 200 I (days or dates) RECO APPROVED: By: By: By: ~ ENGINEER (A thorizld Signature) OWNER (Authorized Signature) CO RACTOR (Authorized Signature) Date: 'i /z,-j6 "- Date: Date:~ 0 L . . CHANGE ORDER No. 2 DA TE OF ISSUANCE 4-24.02 EFFECTIVE DATE 4-24-02 OWNER City of Hopkins CONTRACTOR DMJ Contract: 9812 Project: Hopkins Lots 500 & 600 O\VNER's Contract No. 2000-41 1m ENGINEER's Contract No. 98J2 ENGINEER RLK Kuusisto Ltd. Description: Additional Cost Required for Soil Corrections in Lot 500 & 600, Cost Associated to Abandoned Oil Tank in Lot 500, Additional Costs Required for Stonn Sewer Installation, Reduction in Mobilization Due to Constructing Lot 600 in One Phase, Additional Gravel Required Due to Removing Pavement Instead of Reclaiming (Due to Scheduling Issues), Additional Excavation Due to Moving Storm Sewer Location North of Alley and Changing Grade of Parking Lot, High Early Concrete Additive to Provide Access for Driskill's, Mulch Piaced in Tree Boxes and Around Two Large Trees West of Lot 600, Compensation for Grading 10th Ave., Business Access Signs, Grate Replacement in Pedramp Located on 11th Ave., Reduction in Payment for Damage to Kurt Rolf's Garage Floor, Traffic Control Conduit Replacement, Cutting Tree Grates, Sidewalk Removal in front of Center Drug, and Additional Electrical Improvements. . Reasons for Change Order: The Additional Cost Required for Soil Corrections in Lot 500 & 600: During excavation efforts in Lot 500 & 600 unsuitable" soil containing organic material was discovered. In order to insure a solid subbase the undesirable soil was excavated and replaced with gravel. The result of the soil corrections is a more solid, longer lasting parking lot surface. Cost Associated to Abandoned Oil Tank in Lot 500: During the excavation of Lot 500 an abandoned oil tank containing service drain oil was discovered. The tanl<. was considered a hazardous material and was removed according to Minnesota State regulations. Mimlesota Petrolewn Services removed the hazardous materials and the tank. Additional Costs Required for Storm Sewer Installation: The storm sewer system was modified during the course of the project. The changes resulted in an overrun in the original pipe lengths and storm structures quantities. The changes resulted in a better more efficient storm sewer system. . . Reduction in Mobilization Due to Constructing Lot 600 in One Phase: The phasing schedule for Lot 600 changed during the course of construction. Originally Lot 600 was going to be constructed in two phased in order to increase parking in the area during the project. After discussing the phasing schedule with local businesses and considering the additional time required to reconstruct the lot in two phases a decision was made to construct the lot in one phase. This decision saved DMJ (contractor) time and money, which resulted in a reduction in mobilization costs. Additional Gravel Required Due to Removing Pavement Instead of Reclaiming (Due to Scheduling Issues): The scope of the proj ect changed during the course of construction increasing the required gravel quantity. Originally Lots 500 & 600 were going to be reclaimed, meaning that the existing asphalt would be reused as gravel. During the course of the project the decision was made to remove the asphalt in both parking lots and use gravel from an outside source. The reason for this decision was based on the thickness of the asphalt in the parking lot, scheduling issues, and quality of finished product. The asphalt in the parking lots was very thin in several places making it unfeasible to reclaim. The scheduling for the reclaiming would have held up the project. Replacing the gravel versus using reclaim provides a better-finished product. Additional Excavation Due to Moving Storm Sewer Location North of Alley and Changing Grade of Parking Lot: The location of the storm sewer in lot 500 was moved from the curb along the south end of lot 500 to 30 feet north of the curb. The change in . sewer location resulted in a grade change in lot 500 that increased the amount of required common excavation. The result of this decision eliminated the risk of \vater pooling in front of the buildings facing Lot 500 on the south side during a heavy rainfall. High Early Concrete Additive Required to Provide Access fo.' Driskill's: The use of high early additive reduced the required curing time of the concrete poured for Driskill's truck access apron from 7 to 3 days. Driskill's food receives deliveries on a daily basis and could not wait 7 days between shipments. I J\1ulch Placed in Tree Boxes and Around two Large Trees \Vest of Lot 600: The scope of the landscape plan changed due to the hvo tree boxes placed on 11 th Ave and the removal of tree grates around the hvo Imge trees west of Lot 600. Additional mulch was required along "vith compensation for the additional work. Compensation for Grading 10th Ave: During the construction of 10th Ave a decision was made to keep the existing gravel in place versus excavating the street to sub grade and hauling in new gravel. This decision was made after consulting a geotechnical engineer in an eff0l1 to reduce the cost of the project. The overhead expense for grading the street was included in the price of the gravel. Additional compensation was required for grading 1 otll Ave due to the reduction in gravel required to reconstruct lOth Ave. . . Business Access Signs: At the start of the project many business owners in the area where concerned of the impacts to their business due to the construction. A major concern was that people would not Imow how to access their businesses. In order to reduce confusion and increase business, signs were made that directed traffic to the street that provided access during each phase of the project. Grate Replacement in Pedramp Located on 11111 Ave: TIle grate located in the pedramp located on 11 th Ave. was replaced at the request of the city in order to provide better drainage and reduce maintenance. Reduction in Payment for Damage to Kurt Rolf's Garage Floor: The drive apron in front of Km1 Rolf s garage was replaced as part of the project. Dming the process of removing the existing drive apron and pouring new concrete several new cracks were formed in the garage floor slab. DMJ and their concrete sub-contractor both refused to look into the mater leaving the city responsible for repairing the damage caused during the construction efforts. A decision was made after access tbe damage to retain moneys in order to have an outside contractor repair the cracks. Traffic Control Conduit Replacement: During tbe asphalt removal of 10111 Ave the conduit for the traffic control was damaged resulting in the traffic signal to be inoperable for approximately thTee weeks. The conduit was replaced according to the requests of the . city. A decision was made to pay half of the price of replacing the conduit under the bid prices set by the contract. The compromise in price was made because the existing conduit was working and did not need to be replaced, but the new conduit system is installed to code while the existing conduit system was not. Cutting Tree Grates: The new tree grates installed around two existing trees in Lot 600 had to be cut in order to fit around tile trees. DMJ requested additional payment to compensate for their time spent cutting the tree grates. Sidewalk Removal in front of Center Drug: TIle existing sidewalk in front of Center Drug was 13 inches thick and required additional work in order to be removed. Additional payment \vas made to compensate for the additional time required to remove the sidevvalk. Additional Electrical Improvements: During the course of the construction project additional electrical work \vas warranted to improve the street light electrical wiring. . -~- . City of Hopkins Lots SOD & 600, 10th and 11 th Avenues City Project Number 9B-12 Additional Cost Required for Soil Corrections in Lot 500 & lot 600 Item Description Quantity Unit Unit Price Sub Total Common Excavation Soii Corrections Lot 600 21 CY $ 11.25 $ 236.25 Common Excavation Soil Corrections Lot 500 778 CY $ 11.25 $ 8,752.50 Aggregate CL 5 Fill Material 1522 TN $ 14.00 $ 21,308.00 Fabric Geotech Fabric placed in lot 500 378 SY $ 1.00 $ 378.00 Grand Total $ 30,674.75 Costs Associated to Abandoned all Tank in Lot 500 Item Description Quantity Unit Unit Price Sub Total Exploratory Dig Excavation of oil tank 1 HR $ 250.00 S 250.00 La bar Tank Removal (MPS)" 11.5 HR $ 60.00 $ 690.00 Monitoring Equipment Tank Removal (MPS)' 1 LS $ 85.00 $ 85.00 Materials-Dry Ice Tank Removal (MPS)" 1 EA $ 37.50 $ 37.50 Vac truck Tank Removal (MPS)" 4 HR $ 97.75 $ 391.00 Vac truck Tank Removal (MPS)" 0.5 HR(OT) $ 146.62 $ 73.31 Waste Service Charge Tank Removal (MPS)" 1 LS $ 17.25 $ 17.25 Tank Disposal Tank Removal (MPS)* 1 LS $ 230.00 $ 230.00 Sludge Disposal Tank Removal (MPS)' 50 GAL $ 8.50 $ 425.00 Oil Disposal Tank Removal (MPS)* 167 GAL $ 2.00 $ 334.00 . Soil Sampling Tank Removal (MPS}* 1 LS $ 1,019.00 $ 1,019.00 Soil Testing Tank Remo'Jal (MPS)* 2 EA $ 54.00 $ 108.00 General Contractor 5% Tank Removal (MPS)* 1 LS $ 165.10 S 170.50 Grand Total $ 3,830.56 . Minnesota Petroleum Service Additional Costs Required for Storm Sewer Installation Item Description Quantity Unit Unit Price Sub Total Connect Storm Drain Fernco Connect to existing drain 1 EA $ 250.00 $ 250 00 Watermain Parts and Material 1 LS $ 1,142.71 $ 1,142.71 Watermain Labor, Building and Installing Section 4.5 HR $ 350.00 $ 1,575.00 General Contractor 5% Watermain Drop 1 LS $ 127.14 $ 127.14 Install 12" RCP Storm Sewer 79 LF $ 25.00 $ 1,975.00 Install 15" RCP Storm Sewer 10 LF $ 28.00 $ 280.00 Install 10" PVC Storm Sewer 124 LF $ 17.00 $ 2,10B.00 Install R3D65 Casting Storm Sewer 1 EA $ 320.00 $ 32000 Install 2x3 CB Storm Sewer 1 EA $ 1,260.00 $ 1.260.00 R1733 MH Casting CB-11 A and Access to PVC 2 EA $ 320.00 $ 640.00 Traffic Control Additional Compensation for Traffic Control 1 LS $ 900.00 $ 900.00 Grand Total S 10,57785 . . City of Hopkins Lots 500 & 600, 10th and 11 th Avenues City Project Number 98-12 Reduction in MObilization Due to Constructing Lot 600 in One Phase Item Description Quantity Unit Unit Price Sub Total Mobilization I Costs Required to Move Equipment I 1 1 LS 1$ (6,000.00)1 $ (6.000.00) Grand Total $ (6,000.00) Additional Gravel Required Due to Removing Pavement Instead of Reclaiming (Due to Scheduling Issues) Item Description Quantity Unit Unit Price Sub Total Aggregate CL 5 I Base Material I 1651 I TN 1$ 14.00 I S 23,114.00 Grand Total S 23,114.00 Additional Excavation Due to Moving Storm Sewer Location North of Alley and Changing Grade of Parking Lot !tem Description Quantity Unit Unit Price Sub Total Common Excava1ion I Grade Change in Lot 500 I 393.6 I Cy 1$ 11.25 1$ 4.428.00 . Grand Total $ 4,428.00 High Early Concrete Additive Required to Provide Access For Driskill's Item Description Quantity Unit Unit Price Sub Totat High Early I Concrete Accelerator I 1 I LS \$ 200.00 I $ 200.00 Grand Total $ 200.00 Mulch Placed in Tree Boxes and Around two Large Trees West of Lot 600 Item Descri ptio n Quantity Unit Unit Price Sub Total Mulch I Landscape Ground Cover I 11 I SY 1$ 5.00 I $ 55.00 Grand Total $ 55.00 Compensation for Grading 10th Ave. Item Description Ouantity Unit Unit Price Sub Total Gradi n 9 I Grading Gravel Prior to Paving I 1 I LS 1$ 2,665.00 I $ 2,665.00 Grand Total $ 2,665.00 . . Crty of Hopkins Lots 500 & 600, 10th and 11th Avenues City Project Number 98-12 Business ACCess Signs Item Description Quantity Unil Unit Price Sub Tolai Signs I Business Access Available... I 2 I EA 1$ 52.18 I $ 104.36 General Contractor 5% I Compensation for Overhead Expense I 1 I LS 1$ 5.22 I $ 5.22 Grand Tolal $ 109.58 Grate Replacement in Pedramp Located on 11 th AVe. Item Description Quantity Unit UlHt Price Swb Total Grate I Grate with Larger Holes I 1 I EA 1$ 165.00 I $ 165 CO Genersl Contractor 5% I Compensation for Overhead Expense I 1 I LS 1$ 8.25 I $ 8.25 Grand Total $ 173.25 Reduction In Payment lor Damage to Kurt Rolfs Garage Floor Item Description Quantity Unit Unit Price Sub Total S aw-n-S eal I Repair to Cracks Cause by Construction I 1 I LS I $ (500.00)/ $ (500.00) Grand Total $ (500.00) . Traffic Control Conduit Repl<lcernent ilem Description Sub Total TraffiC Control ReplaCement and upgr<lding of Conduit $ 1,620.50 Grand Total S 1,620.50 Cutting Tree Grates Item Descriplion Quantity Unit Unit Price Sub Total Cutting Tree Grates 1 Compensation for Cutting Tree Grates I 1 I LS I $ 500.00 I $ 500,00 Grand T alai $ 500.00 Sidewalk Removal In frant of Center Drug Ilem DeSCription Quantity Unit Unil Price Sub Total Sidewalk Removal I Additional Compensation for sidewalk removal I 1 I LS I $ 735.00 I $ 735 00 Grand Total $ 735.00 Additional Electricallmpravements Item Descriplion Quantity Unrt Unit Price Sub Total #4 Wire I install #4 Wire I 2750 , IF 1$ 1.20' $ 3,300,00 Grand Total $ 3,300.00 . Net Change in Conlract Price $ 75,483.49 - -- - . APPLICATION FOR PAYMENT NO. S (Final) To: City of Hopkins (OWNER) From: DMJ Corporation (CONTRACTOR) Contract/Project: Lots 500 & 600, 10th and 1 rh A venues Owner's Contract No.98-12 ENGrNEER's Project No.2000-4]]M For Work accomplished through the date of: 4-24-02 1. Original Contract Price: $472,597.00 2. Net change by Change Orders and Written Amendments (+ or -) $] 12,002.65 3. Current Contract Price (] plus 2): $584,599.65 4. Total completed to date: $584,599.65 5. Retainage (per Agreement): ~% of completed Work: $0.00 Total Retainage: $0.00 6. Total completed to date less retainage (4 minus 5) $584,599.65 7. Less previous Application for Payments: $483.401.90 1L DUE THIS APPLICA nON (6 MINUS 7): $1 0 1.197.75 Accompanying Documentation: CONTRACTOR's Certification: . The undersigned CONTRACTOR certifies that (l) all previous progress payments received from OWNER on aCCOUnt of Work done under the Contract referred to above have been applied on account to discharge CONTRACTOR's legitimate obligations incurred in connection with Work covered by prior Applications for Payment numbered 1 through-Linclusive; (2) title of all Work, materials and equipment incorporated in said Work or otherwise listed in or covered by this application for Payment will pass to O\VNER st the time of psyment free and clear of all Liens, security interests and encumbrances except such as are covered by a Bond acceptable to OWNER indemnifying OWNER against any such Lien, security interest or encumbrance); and (3) ALL Work covered by this application for Payment is in accordance with the Contract Documents and not defective. DatedM 02- DMJ Corporation (~ ~CTOR By. ~ -:3- Payment of$lOL197.75 DUE THIS APPLICATION is recommended. Dated j,1/z 5;/07- RLK - Kuusisto, Ltd. ENGINEER BY:~ ~ {~<~ . , . CITY OF HOPKINS HENNEPIN COUNTY MINNESOTA RESOLUTION NO. 2002-43 RESOLUTION ACCEPTING WORK AND ORDERING FINAL PAYMENT PARKfNG LOT 500, 600 AND 10TH /lITH AVE. NORTH IMPROVEMENTS PROJECT 98-12 WHEREAS, pursuant to a written contract signed with the City on May 15, 2001, DMJ Corporation, has satisfactorily completed construction of Park Lots 500, 600 and 101h/11 th A venues North, City Project 98-12, in accordance with such contract, NOW, THEREFORE, BE IT RESOLVED BY THE CITY OF HOPKlNS, MINNESOTA: 1. The work completed under said contract is hereby declared accepted and approved. 2. Order for final payment on such contract is hereby ordered, taking the contractor's receipt in full. . 3. A one-year warranty on contract work shall commence as of this resolution. Adopted by the City Council of Hopkins, Milll1esota this 7th day of May, 2002. By Eugene J. Maxwell, Mayor ATTEST: Terry Obermaier, City Clerk .