VI.1. Public Improvement Hearing – 2019 Street and Utility Improvements, City Project 2018-10; Klingbeil November 20, 2018 Council Report 2018-120
PUBLIC IMPROVEMENT HEARING
2019 STREET AND UTILITY IMPROVEMENTS
CITY PROJECT 2018-10
Proposed Action
Staff recommends the following motion: adopt Resolution 2018-085, Resolution Ordering Improvement
after Public Improvement Hearing, 2019 Street and Utility Improvements and companion Resolution 2018-
086, stating the City’s intent to reimburse itself using bonds.
This action continues an assessable project for street and utility improvements.
Overview
At its October 16, 2018 meeting, a feasibility report concerning street and utility improvements along
Cambridge Street west of Blake Road, Lake Street NE west of Blake Road, Van Buren Avenue N from
Cambridge Street to Lake Street NE, Tyler Avenue N from 2nd Street NE to Lake Street NE, Hiawatha
Avenue, and Oak Park Lane was presented to the City Council and a public hearing on the improvements
was ordered for November 20th, 2018.
In accordance with state statutes, the City Council needs to conduct a public hearing and determine
authorization of the project. Hearing notices have been mailed to all affected property owners of record.
Following the public hearing, if the project is ordered, City Council is asked to state the City’s intent to
reimburse itself using bonds.
Primary Issues to Consider
Scope of Improvements
Public Input
Assessments
Project Budget and Costs
Project Schedule
Staff Recommendation
Council Report 2018-120
Page 2
Supporting Information
Resolution 2018-085 & 2018-086
Public Hearing Notice & Mailing Affidavit
Proposed Pending Assessment Roll
Neighborhood Meeting Invitation
Proposal for Design and Construction Services
Feasibility Report (available upon request)
_________________________________
Eric Klingbeil, P.E., Assistant City Engineer
Financial Impact: $5,575,000 Budgeted: Y/N _Y_ Source: _PIR, SA, Water, Sanitary, Storm
Related Documents (CIP, ERP, etc.): CIP _ Notes: _________________________________________
Council Report 2018-120
Page 3
ANALYSIS OF ISSUES
Scope of Improvements
This project includes reconstruction of the following streets:
• Cambridge Street
• Lake Street NE
• Cambridge Street
• Van Buren Avenue N
• Tyler Avenue N
• Hiawatha Avenue
• Oak Park Lane
The pavement condition index for most of the project area is below 40, which indicates failed pavement
and warrants reconstruction. In recent years there has also been significant development work completed
in the area, resulting in several street impacts which are accelerating pavement deterioration in the area.
Proposed street improvements include full reconstruction of streets and new curb and gutter throughout
the project area. Street width improvements were also considered with this project.
Water main is proposed to be replaced throughout the project area. Most of the existing main is in excess
of 60 years old and made from cast iron. New main will be ductile iron, which has better reliability and
when properly installed a longer lifecycle than cast iron. All water services will be replaced from the
main to the property line unless they are copper and less than 10 years old.
Sanitary sewer improvements include the removal and replacement of the main, manholes and service
lines to the property line.
Proposed storm sewer improvements include addition of curb and gutter, removal and replacement of the
storm sewer main, addition of storm sewer inlets to reduce water ponding in the street and improvements
to reduce sediment accumulation.
Pedestrian facilities include installation of new sidewalk along Lake Street NE, Van Buren Avenue, and
Cambridge Street. This new sidewalk will provide continuous off-street pedestrian facilities between
Tyler Avenue and Blake Road. Additional sidewalks were considered for Hiawatha Avenue and Oak
Park Lane, however there is limited right-of-way and a lack of neighborhood support.
During the scoping for this project, it was determined that there was some other work that should be
included in the project, due not only to proximity, but to capitalize on pricing. This additional work will
be funded by separate items in the CIP and Budget and includes the following:
• Sanitary Sewer Lining in areas across the City identified by the Public Works Department.
• Citywide spot alley and sidewalk repairs
Metropolitan Council Environmental Services (MCES) is currently reconstructing the L27 lift station,
which is currently located at 420 Blake Road. The new lift station will be located at 402 Hiawatha
Avenue, approximately 600 feet west of Blake Road. As part of the project, existing sanitary piping in
Lake Street NE must be rerouted to the new lift station. MCES will be reconstructing portions of Lake
Street NE to accommodate this work.
Council Report 2018-120
Page 4
Public Input
Two public informational meetings regarding the improvements were held on September 19th and
November 14th. The meeting format consisted of a presentation of the overall project, with detailed
discussion on assessments. Between the two meetings, a total of approximately 12 people attended the
meetings.
A questionnaire was sent to all properties in the project area in advance of the neighborhood meeting,
Drainage concerns and a desire for improved street surface and additional sidewalks were the most
notable comments in the responses.
Bolton & Menk and City staff has met with individual property owners in person to discuss concerns and
look at options to minimize issues; it is anticipated meetings will continue as design progresses.
Assessments
The proposed street assessments are based on the City’s assessment policy, whereby 70% of the street
reconstruction cost and 50% of the water and sewer service replacement are assessed to benefiting
properties. The policy also allows for assessments to be capped should assessments exceed previous year
assessments by 20%; the costs for this project will trigger the assessment cap. A preliminary assessment
roll has been calculated and can be found in the appendix of the attached Feasibility Report.
The assessment cap for residential properties is $91.56 per front foot based on adding 3% to the 2018
cap. Without the cap assessments could be double the capped rate.
Project Budget and Costs
The estimate for this project, which includes contingency, and costs for legal, administrative, and
engineering costs for all the work totals to $5,575,000.
Project costs and funding sources are as follows:
Funding Source CIP Budget
PI-PIR/General Obligation Bonds $1,945,000
Assessments 1,280,000
Storm Sewer Fund 500,000
Sanitary Sewer Fund 600,000
Water Fund 1,250,000
Total 5,575,000
Preliminary cost estimates show the project tracking within the CIP budget. It is anticipated the costs
may come down as design progresses due to reduced contingency and efficiencies in design.
Council Report 2018-120
Page 5
Project Schedule
Accept feasibility report/order public hearing October 16, 2018
Public Informational Neighborhood Meeting November 14, 2018
Public hearing/order final design November 20, 2018
Approve final plans/order bids February 5, 2019
Order Assessment Hearing March 19, 2019
Public Informational Neighborhood Meeting Early April 2019
Conduct Public Assessment Hearing April 16, 2019
Adopt Assessment Roll/Award Contract April 16, 2019
Begin Construction May, 2019
Complete Construction November, 2019
Staff Recommendation
Staff recommends ordering the above detailed improvement with adoption of resolution 2018-085 and
adopting companion resolution 2018-086.
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2018-085
RESOLUTION ORDERING PUBLIC IMPROVEMENT
2019 STREET AND UTILITY IMPROVEMENTS, PROJECT NO. 2018-10
WHEREAS, a resolution of the City Council adopted the 20th day of November, 2018
fixed a date for a Council Hearing on the improvements on Cambridge Street, Lake Street
Northeast, Van Buren Avenue N, Tyler Avenue N, Hiawatha Avenue, and Oak Park
Lane, including pavement, curbing, sidewalk, signage, drainage, water and sanitary sewer
improvements and all necessary appurtenances, and
WHEREAS, the City Council deems it appropriate and expedient to make such
improvements, and
WHEREAS, ten days mailed notice and two weeks published notice of the hearing was
given, and the hearing was held thereon on the 20th day of November, 2018 at which all
persons desiring to be heard were given an opportunity to be heard thereon.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Hopkins, Minnesota:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the
feasibility report and the recommendations are hereby accepted.
2. Such improvement is hereby ordered as proposed in the Council Resolution
adopted the 20th day of November, 2018. The total estimated project cost is
$5,575,000 of which $1,280,000 is estimated to be assessed.
3. Bolton & Menk, Inc. is hereby designated as the engineer for this improvement
and shall prepare plans and specifications for the making of such improvement.
The Mayor and City Manager are hereby authorized to enter into a contract for
engineering and construction services for this improvement.
4. The City Attorney and City Engineer are hereby authorized to acquire necessary
easements by negotiation or condemnation.
Adopted by the City Council of the City of Hopkins this 20th day of November, 2018.
______________________
Molly Cu mmings, Mayor
ATTEST:
_______________________________
Amy Domeier, City Clerk
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2018-086
DECLARING THE OFFICIAL INTENT OF THE CITY OF HOPKINS
TO REIMBURSE CERTAIN EXPENDITURES FROM
GENERAL OBLIGATION IMPROVEMENT BOND PROCEEDS
TO BE ISSUED BY THE CITY OF HOPKINS
WHEREAS, the Internal Revenue Service has issued Treas. Reg. #1.150-2 providing that
proceeds of tax-exempt bonds used to reimburse prior expenditures shall not be deemed
spent unless certain requirements are met; and
WHEREAS, the City expects to incur certain expenditures, which may be financed
temporarily from sources other than bonds, and reimbursed from the bond proceeds;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Hopkins,
Minnesota:
1. The City intends to incur expenditures for the project described in Council Report
2018-120, for City Project 2018-10 (the “Project”), and intends to reimburse itself
for such expenditures from the bond proceeds to be issued by the City in the
maximum principal amount described in the “project”.
2. The City Manager is authorized to designate additions to Project 2018-10 in
circumstances where time is of the essence, and any such designation shall be
reported to the Council at the earliest practicable date and shall be filed with the
official books and records of the City.
3. This resolution is intended to constitute a declaration of official intent for the
purpose of Treas. Reg. #1.150-2 and any successor law, regulation, ruling or
amendment pertaining thereto.
Adopted by the City Council of the City of Hopkins, Minnesota, this 20th day of
November, 2018.
By_______________________________
Molly Cummings, Mayor
ATTEST:
_______________________________
Amy Domeier, City Clerk
CITY OF HOPKINS
Hennepin County, Minnesota
NOTICE OF PUBLIC HEARING ON IMPROVEMENT
2019 STREET IMPROVEMENTS
CITY PROJECT NO. 2018-10
«PID»
«Owner_Name»
«Taxpayer_1»
«Taxpayer_2»
«Taxpayer_3»
RE: PID #«PID» - «House_No» «Street», HOPKINS, MN
TO WHOM IT MAY CONCERN:
Notice is hereby given that the City Council will hold the Public Hearing in the City Council
Chambers of the Hopkins City Hall at 7:00 p.m. on Tuesday, November 20th, 2018, to consider the
making of improvement on:
• Lake Street NE from Van Buren Avenue N to Blake Road N;
• Tyler Avenue N from 2nd Street NE to Lake Street NE;
• Van Buren Avenue N from Lake Street NE to Cambridge Street;
• Cambridge Street from Van Buren Avenue to Blake Road N;
• Hiawatha Avenue from Cambridge Street to Blake Road N; and
• Oak Park Lane from Tyler Avenue N to its westerly limit
Generally, the project involves the addition/replacement of storm sewer; water main replacement; water
service replacement; sanitary sewer replacement and rehabilitation; sanitary sewer service replacement;
concrete curb & gutter replacement; bituminous street removal and reconstruction; and turf restoration;
pursuant to Minn. Statutes, Section 429.011 to 429.111. The area proposed to be assessed for such
improvement includes all properties located along the above described roadways and as shown below.
Plat Name Sec Twp Rng Q/Q Suffix
Auburn North 19 117 21 21 0009
Auburn South 19 117 21 24 0115-0150
Condo No 0669 Oak Park Estate A Condo 19 117 21 24 0197-0203
Minnehaha Oaks 19 117 21 12 0004-0014
Parkside 2nd Addition 19 117 21 13 0021-0081
Ramsgate 19 117 21 21 0008
Reg. Land Survey No. 0362 19 117 21 12 0015-0016
Reg. Land Survey No. 0561 19 117 21 12 0018
Reg. Land Survey No. 0825 19 117 21 12 0019-0020
Reg. Land Survey No. 1241 19 117 21 12 0022-0023
Reg. Land Survey No. 1250 19 117 21 12 0027-0028
Reg. Land Survey No. 1263 19 117 21 12 0030
Reg. Land Survey No. 1651 19 117 21 21 0010
Regency 19 117 21 24 0254-0276
Rubel & Goldman Addition 19 117 21 12 0034-0040
Stevens Oakwood Park 19 117 21 24 0025-0207
Unplatted 19 117 21 19 117 21 21 0006
Unplatted 19 117 21 19 117 21 12 0003
The estimated cost of the improvement is $5,464,000. A reasonable estimate of the impact of the
assessment will be available at the hearing. Such persons as desire to be heard with reference to the
proposed improvement will be heard at this meeting.
/s/Amy Domeier, City Clerk
Dated: November 1, 2018
Published in Hopkins Sun Sailor on November 8, 2018 & November 15, 2018
YOUR ESTIMATED PENDING ASSESSMENT IS: «Amount»
TO WHOM IT MAY CONCERN:
Notice is hereby given that the City Council will hold the Public Hearing in the City Council
Chambers of the Hopkins City Hall at 7:00 p.m. on Tuesday, November 20th, 2018, to consider
the making of improvement on:
Lake Street NE from Van Buren Avenue N to Blake Road N; Tyler Avenue N from 2nd Street
NE to Lake Street NE; Van Buren Avenue N from Lake Street NE to Cambridge Street;
Cambridge Street from Van Buren Avenue to Blake Road N; Hiawatha Avenue from
Cambridge Street to Blake Road N; and Oak Park Lane from Tyler Avenue N to its westerly
limit
Generally, the project involves the addition/replacement of storm sewer; water main replacement;
water service replacement; sanitary sewer replacement and rehabilitation; sanitary sewer service
replacement; concrete curb & gutter replacement; bituminous street removal and reconstruction;
and turf restoration; pursuant to Minn. Statutes, Section 429.011 to 429.111. The area proposed
to be assessed for such improvement includes all properties located along the above described
roadways and as shown below.
Plat Name Sec Twp Rng Q/Q Suffix
Auburn North 19 117 21 21 0009
Auburn South 19 117 21 24 0115-0150
Condo No 0669 Oak Park Estate A Condo 19 117 21 24 0197-0203
Minnehaha Oaks 19 117 21 12 0004-0014
Parkside 2nd Addition 19 117 21 13 0021-0081
Ramsgate 19 117 21 21 0008
Reg. Land Survey No. 0362 19 117 21 12 0015-0016
Reg. Land Survey No. 0561 19 117 21 12 0018
Reg. Land Survey No. 0825 19 117 21 12 0019-0020
Reg. Land Survey No. 1241 19 117 21 12 0022-0023
Reg. Land Survey No. 1250 19 117 21 12 0027-0028
Reg. Land Survey No. 1263 19 117 21 12 0030
Reg. Land Survey No. 1651 19 117 21 21 0010
Regency 19 117 21 24 0254-0276
Rubel & Goldman Addition 19 117 21 12 0034-0040
Stevens Oakwood Park 19 117 21 24 0025-0207
Unplatted 19 117 21 19 117 21 21 0006
Unplatted 19 117 21 19 117 21 12 0003
The estimated cost of the improvement is $5,464,000. A reasonable estimate of the impact of the
assessment will be available at the hearing. Such persons as desire to be heard with reference to
the proposed improvement will be heard at this meeting.
Amy Domeier, City Clerk
952-548-6304
Published in the Sun Sailor on November 8 & November 15, 2018.
AFFIDAVIT OF M AILIN G PUBLI C HEARIN G NOTICE
ST A TE OF M INN ESOTA )
) ss.
COUNCIL OF HOPKINS )
Cathryn DeBaker, being first duly sworn, deposed and says:
I am a United States citizen, over 21 years of age. On November 2, 2018, acting on behalf of
the City of Hopkins, I caused to be deposited in the United States Post Office at the City of
Burnsville, Minnesota, copies of the attached Notice of Public Hearing for the 2019 Street
Improvements, City of Hopkins, MN Project No. 2018-10, enclosed in sealed envelopes, with
postage thereon fully prepaid, addressed to the following persons at the addresses appearing on
the attached copy of the mailing list.
There is delivery service by United States mail between the place of mailing and the places so
addressed.
Signature
Subscribed and sworn to before me this 2° day of November, 2018.
ye'-"shh@ff! .JACQUELINE A CAPLE
! NOTARY PUBLIC ~ MINNESOTA
-<,_omission Expires Jan.st, 2021
Notary Public
Source: H:\HOPK\T19116650\2_Preliminary\A_Calculations\116650_Eng Est_Prelim
TAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)
1 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
2 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
3 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
4 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
5 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
6 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
7 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
8 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
9 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
10 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
11 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
12 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
13 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
14 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
15 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
16 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
17 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
18 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
19 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
20 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
21 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
22 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
23 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
24 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
25 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAZATA 15210 WAYZATA BLVD WAYZATA MN 55391
26 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
27 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
28 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
29 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
30 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
31 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
32 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAZATA 15210 WAYZATA BLVD WAYZATA MN 55391
33 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
34 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
35 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
36 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
37 AUBURN LIMITED PARTNERSHIP PARK AVENUE OF WAYZATA 15210 WAYZATA BLVD WAYZATA MN 55391
38 MANOJ T MATHEW AND SUDHANSHU ANAND 5060 HOLLY LN N #4 PLYMOUTH MN 55446
39 THOMAS L BUEHNER 612 OAK PARK LA HOPKINS MN 55343
40 MEGAN RODGERS 614 OAK PARK LA HOPKINS MN 55343
41 SUSAN NOKLEBY 616 OAK PARK LA HOPKINS MN 55343
42 NICHOLAS JON MILLER 618 OAK PARK LA HOPKINS MN 55343
43 RICHARD HOGLUND 620 OAK PARK LA HOPKINS MN 55343
44 SANDRA KAY HAHN P O BOX 189 HOPKINS MN 55343
45 SUSAN E WOLFE 517 HIAWATHA AVE HOPKINS MN 55343
46 KYLE T PITTS & KATY K PITTS 505 HIAWATHA AVE HOPKINS MN 55343
47 KERI FICKAU 511 HIAWATHA AVE HOPKINS MN 55343
48 RONALD A & BONNIE M GILBERT 406 HIAWATHA AVE HOPKINS MN 55343
49 JEFFREY M JORDAN AND TRINA E MUNNINGS 410 HIAWATHA AVE HOPKINS MN 55343
50 JOHN THOLE 418 HIAWATHA AVE HOPKINS MN 55343
51 DIANA GLASGOW 426 HIAWATHA AVE HOPKINS MN 55343
52 VERNON L ISAAK 434 HIAWATHA AVE HOPKINS MN 55343
53 NAPOLEON & MARIBEL TENERIFE 801 KASSIE CT HOPKINS MN 55343
54 TOM BOMBERG & JORDYN BOMBERG 805 KASSIE CT HOPKINS MN 55343
55 JUDE D RAJAN & LEENA PHILIP 4753 HAMILTON RD MINNETONKA MN 55345
56 NICK BROWN 813 KASSIE CT HOPKINS MN 55343
57 GEORGE PARRINO 901 PARKSIDE BLVD HOPKINS MN 55343
58 ZACHARY W ZIMNIEWICZ 905 PARKSIDE BLVD HOPKINS MN 55343
59 SARA WITT 909 PARKSIDE BLVD HOPKINS MN 55343
60 PHUONG NGUYEN & KIET NGO 913 PARKSIDE BLVD HOPKINS MN 55343
61 JILEEN S ARENDT 917 PARKSIDE BLVD HOPKINS MN 55343
62 ADAM C DRISCOLL QUINN A DRISCOLL 921 PARKSIDE BLVD HOPKINS MN 55343
63 RAHUL R SINGH 925 PARKSIDE BLVD HOPKINS MN 55343
64 STEVEN G BENTLEY DIANA DOMINICA DARDEN 929 PARKSIDE BLVD HOPKINS MN 55343
65 STEVEN YETTER & STACY HELM 933 PARKSIDE BLVD HOPKINS MN 55343
66 NGUYEN HOANG 937 PARKSIDE BLVD HOPKINS MN 55343
67 LARRY & BONNARY KETOLA 900 PARKSIDE BLVD HOPKINS MN 55343
Source: H:\HOPK\T19116650\2_Preliminary\A_Calculations\116650_Eng Est_Prelim
68 TAKAYUKI NEGISHI 912 PARKSIDE BLVD HOPKINS MN 55343
69 CHONGBIN WU 1165 MOERS DR CHASKA MN 55318
70 KELSEY C GUZMAN 920 PARKSIDE BLVD HOPKINS MN 55343
71 CALYNE QUYNH 9748 77TH ST S COTTAGE GROVE MN 55016
72 LAWRENCE J MANDILE NORA J MANDILE 928 PARKSIDE BLVD HOPKINS MN 55343
73 RAMESH GANESAN/VIJAYA RAMESH 932 PARKSIDE BLVD HOPKINS MN 55343
74 PATRICK ALAN QUIGLEY 929 ABBIE LA HOPKINS MN 55343
75 NATALYA MOROZ 925 ABBIE LA HOPKINS MN 55343
76 ESTHER J WILLIAMS 921 ABBIE LA HOPKINS MN 55343
77 RHONDA M BROWN 917 ABBIE LA HOPKINS MN 55343
78 MICHAEL A BLACKMON JR MAGGIE W BLACKMON 913 ABBIE LA HOPKINS MN 55343
79 GERALDINE D PIRA P O BOX 894602 MILANI HI 96789
80 GREGORY J GENGLER 905 ABBIE LA HOPKINS MN 55343
81 KELLY J MARX 1 WEBSTER PL HOPKINS MN 55305
82 REBECCA NUNN 20860 ST ALBANS GREEN EXCELSIOR MN 55331
83 APARNA PHILKANA 808 KASSIE CT HOPKINS MN 55343
84 JOHN BARNES 812 KASSIE CT HOPKINS MN 55343
85 MOLLIE C LARSON 813 CAMERON CT HOPKINS MN 55343
86 ANDREW M GULAN SHANNA L GULAN 809 CAMERON CT HOPKINS MN 55343
87 JULIE M GREENBERG JAMIE W REINBOLD 805 CAMERON CT HOPKINS MN 55343
88 MATTHEW E & MARA COREY 801 CAMERON CT HOPKINS MN 55343
89 BRIAN P DAHLBERG 800 CAMERON CT HOPKINS MN 55343
90 MEGAN HINRICHSEN 804 CAMERON CT HOPKINS MN 55343
91 JEAN A SORENSON 808 CAMERON CT HOPKINS MN 55343
92 RAKESH & PRERNA VERMA 812 CAMERON CT HOPKINS MN 55343
93 VENKATA N U BHASKA MARELLA 9692 TREE FARM RD EDEN PRAIRIE MN 55347
94 IVAN MADJOS 809 LINDSEY LA HOPKINS MN 55343
95 SOUMYA JANDHYALA VENKATA M GOWTHAM AKULA 805 LINDSEY LA HOPKINS MN 55343
96 SARATHCHANDRA KARUNANAYAKE 801 LINDSEY LA HOPKINS MN 55343
97 PATRICE PETERSEN 900 ABBIE LA HOPKINS MN 55343
98 CEDAR GLEN DEVELOPMENT LLC 7271 KURVERS POINT RD CHANHASSEN MN 55317
99 JAMES C BARRINGER TRUSTEE GLORIA A BARRINGER TRUSTEE 414 WEST PALMER CIRCLE ABERDEEN SD 57401
100 SHARAD GOYAL 912 ABBIE LA HOPKINS MN 55343
101 JOE CAVANAUGH 3650 YUMA LANE N PLYMOUTH MN 55446
102 SAMIH KADADAH SOUZAN AL-SHAWA 924 ABBIE LA HOPKINS MN 55343
103 CHEDITA D & ROSENDO T MIGUEL 928 ABBIE LA HOPKINS MN 55343
104 IVAN & MARITES SENDRIJAS 925 LINDSEY LA HOPKINS MN 55343
105 PRAFULL VERMA ET AL 422 GOLDEN HARVEST LOOP CARRY NC 27519-9495
106 MARGARET REYNOLDS 917 LINDSEY LA HOPKINS MN 55343
107 MELISSA DVORAK 913 LINDSEY LA HOPKINS MN 55343
108 LYNN RONNING & MYRA SIMENSON 909 LINDSEY LA HOPKINS MN 55343
109 DAVID A BERDASS 905 LINDSEY LA HOPKINS MN 55343
110 RAVIKUMAR JASTHI 901 LINDSEY LA HOPKINS MN 55343
111 PARKSIDE HOMEOWNERS ASSOC C/O URGANWOOD REAL ESTATE P O BOX 19497 MINNEAPOLIS MN 55419
112 PARKSIDE HOMEOWNERS ASSOC C/O URBANWOOD REAL ESTATE P O BOX 19497 MINNEAPOLIS MN 55419
113 PARKSIDE HOMEOWNERS ASSOC C/O URBANWOOD REAL ESTATE P O BOX 19497 MINNEAPOLIS MN 55419
114 RAMSGATE APARTMENTS LLC 5290 VILLA WAY EDINA MN 55436
115 JODY LYNN DE ST HUBERT 425 HIAWATHA AVE HOPKINS MN 55343
116 ERIC M P & CARRIE S KENNEDY 435 HIAWATHA AVE HOPKINS MN 55343
117 CREEK POINT APARTMENTS 1045 HIAWATHA AVE HOPKINS MN 55343
118 RICHARD P HURLEY 409 HIAWATHA AVE HOPKINS MN 55343
119 ELLEN HANSEN & ERIC LARSON 413 HIAWATHA AVE HOPKINS MN 55343
120 HOLIDAY STATIONSTORES INC ATTN TAX DEPARTMENT 4567 AMERICAN BLVD W MINNEAPOLIS MN 55437
121 WHITE CASTLE SYSTEM INC 555 WEST GOODALE ST COLUMBUS OH 43215-1158
122 MD LAND LLC 5425 BOONE AVE N NEW HOPE MN 55428
123 MARVIN DEVELOPMENT IV LLC 5425 BOONE AVE N NEW HOPE MN 55428
124 PAM CASH 5475 BUTTERNUT CIR MINNETONKA MN 55343
125 RAMSGATE APARTMENTS LLC 5290 VILLA WAY EDINA MN 55436
126 WEILIN ONG MARKFORT EDWARD MARKFORT 710 REGENCY LA E HOPKINS MN 55343
127 THOMAS L ROBERTSON 714 REGENCY LA E HOPKINS MN 55343
128 JULIA RUTH CLARK 718 REGENCY LA E HOPKINS MN 55343
129 JUNKO KUMAMOTO HIROSHI KUMAMOTO 722 REGENCY LA E HOPKINS MN 55343
130 MIKALAI ZAIKO 726 REGENCY LA E HOPKINS MN 55343
131 HUNTER MOEN 730 REGENCY LA E HOPKINS MN 55343
132 SUZANNE K KALAN 738 REGENCY LA E HOPKINS MN 55343
133 IGOR KORABEL 742 REGENCY LA E HOPKINS MN 55343
134 LINDA M SLOAN 746 REGENCY LA E HOPKINS MN 55343
135 STEVEN T & ELIZABETH A WAHL 620 S 7TH AVE #347 PO BOX 1908 FRISCO CO 80443
136 JEANETTE WOOD 754 REGENCY LA E HOPKINS MN 55343
137 KENNETH & RENAE JACOBSON 755 2ND ST N E HOPKINS MN 55343
Source: H:\HOPK\T19116650\2_Preliminary\A_Calculations\116650_Eng Est_Prelim
138 CNBI LLC C/O MIDWEST REALTY SERV 12800 INDUSTL PK BLVD #150A PLYMOUTH MN 55441
139 MICHELE EDDIE 1631 N 127TH ST KANSAS CITY KS 66109
140 IVAN MCMULLEN/JOYCE MCMULLEN 743 2ND ST N E HOPKINS MN 55343
141 SHADOW INVESTMENTS LLC 2063 AUSTRIAN PINE MINNETONKA MN 55305
142 JAMES A SODERBERG 245 SKI HILL RD MINNEAPOLIS MN 55422
143 JESUS A VENERO ROMAN 727 2ND ST N E HOPKINS MN 55343
144 STEVEN KNUTSON KRISTIN J JOHNSON 432 SUMMERFIELD DR CHANHASSEN MN 55317
145 ALTHEA JENKINS 719 2ND ST N E HOPKINS MN 55343
146 URI SPECTOR & TANIA SPECTOR 715 2ND ST N E HOPKINS MN 55343
147 TERRI L KRUGER 711 2ND ST N E HOPKINS MN 55343
148 REGENCY MASTER ASSN 4672 SLATER RD EAGAN MN 55122
149 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS MN 55404
150 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS MN 55404
151 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS MN 55404
152 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS MN 55404
153 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS MN 55404
154 CADY MANAGEMENT 2200 BLAISDELL AVE S MINNEAPOLIS, MN 55404
155 DALE T & LINDA H NOVY 218 TYLER AVE N HOPKINS MN 55343
156 JASON DUSCHER 226 TYLER AVE N HOPKINS MN 55343
157 NATHAN BROWN 236 TYLER AVE N HOPKINS MN 55343
158 GLORIA A CAMPBELL 304 TYLER AVE N HOPKINS MN 55343
159 DAVID J HANSEN 306 TYLER AVE N HOPKINS MN 55343
160 DANIEL R SANDBERG 312 TYLER AVE N HOPKINS MN 55343
161 RICKY D HUYNH & CAT-ANH PHAM 318 TYLER AVE N HOPKINS MN 55343
162 GAROLD B & JUDITH A S HEALY 700 OAK PARK LN HOPKINS MN 55343
163 CRYSTAL M CAIN 228 TYLER AVE N HOPKINS MN 55343
164 JESSICA DALMAN 232 TYLER AVE N HOPKINS MN 55343
165 THE PLANATION CARRGE HSE LLC C/O ERWIN R STOBBE 500 CAMBRIDGE ST HOPKINS MN 55343
166 CREEK POINT APARTMENTS 1045 HIAWATHA AVE HOPKINS MN 55343
167 MARVIN DEVELOPMENT IV LLC 5425 BOONE AVE N NEW HOPE MN 55428
PRELIMINARY ASSESSMENT ROLL2019 STREET & UTILITY IMPROVEMENTSCITY OF HOPKINS, MNBMI PROJECT NO. T19.1166501911721120004517HIAWATHA AVESUSAN E WOLFE517 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120020409HIAWATHA AVERICHARD P HURLEY409 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120019413HIAWATHA AVEELLEN HANSEN & ERIC LARSON413 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120016425HIAWATHA AVEJODY LYNN DE ST HUBERT425 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120015435HIAWATHA AVEERIC M P & CARRIE S KENNEDY435 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120006505HIAWATHA AVEKYLE T PITTS & KATY K PITTS505 HIAWATHA AVEHOPKINS MN 55343 9,156.00$ 1,275.00$ 1,350.00$ 11,781.00$ 1911721120005511HIAWATHA AVEKERI FICKAU511 HIAWATHA AVEHOPKINS MN 55343 9,156.00$ 1,275.00$ 1,350.00$ 11,781.00$ 1911721120011406HIAWATHA AVERONALD A & BONNIE M GILBERT406 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120008410HIAWATHA AVEJEFFREY M JORDAN ANDTRINA E MUNNINGS410 HIAWATHA AVEHOPKINS MN 553438,258.71$ 1,275.00$ 1,350.00$ 10,883.71$ 1911721120012418HIAWATHA AVEJOHN THOLE418 HIAWATHA AVEHOPKINS MN 55343 7,952.90$ 1,275.00$ 1,350.00$ 10,577.90$ 1911721120013426HIAWATHA AVEDIANA GLASGOW426 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721120014434HIAWATHA AVEVERNON L ISAAK434 HIAWATHA AVEHOPKINS MN 55343 11,445.00$ 1,275.00$ 1,350.00$ 14,070.00$ 1911721240025218TYLER AVE NDALE T & LINDA H NOVY218 TYLER AVE NHOPKINS MN 55343 9,888.48$ 1,275.00$ 1,350.00$ 12,513.48$ 1911721240026226TYLER AVE NJASON DUSCHER226 TYLER AVE NHOPKINS MN 55343 7,324.80$ 1,275.00$ 1,350.00$ 9,949.80$ 1911721240104228TYLER AVE NCRYSTAL M CAIN228 TYLER AVE NHOPKINS MN 55343 6,918.27$ 1,275.00$ 1,350.00$ 9,543.27$ 1911721240103232TYLER AVE NJESSICA DALMAN232 TYLER AVE NHOPKINS MN 55343 5,493.60$ 1,275.00$ 1,350.00$ 8,118.60$ 1911721240028236TYLER AVE NNATHAN BROWN236 TYLER AVE NHOPKINS MN 55343 9,888.48$ 1,275.00$ 1,350.00$ 12,513.48$ 1911721240029304TYLER AVE NGLORIA A CAMPBELL304 TYLER AVE NHOPKINS MN 55343 9,888.48$ 1,275.00$ 1,350.00$ 12,513.48$ 1911721240195306TYLER AVE NDAVID J HANSEN306 TYLER AVE NHOPKINS MN 55343 4,944.24$ 1,275.00$ 1,350.00$ 7,569.24$ 1911721240032312TYLER AVE NDANIEL R SANDBERG312 TYLER AVE NHOPKINS MN 55343 4,944.24$ 1,275.00$ 1,350.00$ 7,569.24$ 1911721240207318TYLER AVE NRICKY D HUYNH & CAT-ANH PHAM318 TYLER AVE NHOPKINS MN 55343 9,888.48$ 1,275.00$ 1,350.00$ 12,513.48$ 1911721240138336TYLER AVE NAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAZATA15210 WAYZATA BLVDWAYZATA MN 553915,310.48$ 5,310.48$ 1911721240139338TYLER AVE NAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 553914,120.20$ 4,120.20$ 1911721240140342TYLER AVE NAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 553914,120.20$ 4,120.20$ 1911721240141344TYLER AVE NAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 553914,578.00$ 4,578.00$ 1911721240197610OAK PARK LAMANOJ T MATHEW ANDSUDHANSHU ANAND5060 HOLLY LN N #4PLYMOUTH MN 55446185.86$ 185.86$ 1911721240198612OAK PARK LATHOMAS L BUEHNER612 OAK PARK LAHOPKINS MN 55343 185.86$ 185.86$ 1911721240199614OAK PARK LAMEGAN RODGERS614 OAK PARK LAHOPKINS MN 55343 185.86$ 185.86$ 1911721240200616OAK PARK LASUSAN NOKLEBY616 OAK PARK LAHOPKINS MN 55343 185.86$ 185.86$ 1911721240201618OAK PARK LANICHOLAS JON MILLER618 OAK PARK LAHOPKINS MN 55343 185.86$ 185.86$ 1911721240202620OAK PARK LARICHARD HOGLUND620 OAK PARK LAHOPKINS MN 55343 185.86$ 185.86$ 1911721240203622OAK PARK LASANDRA KAY HAHNP O BOX 189HOPKINS MN 55343 185.86$ 185.86$ 1911721240206700OAK PARK LAGAROLD B & JUDITH A S HEALY700 OAK PARK LNHOPKINS MN 55343 6,255.00$ 6,255.00$ 1911721210009420STATE HWY NO 7AUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391158,700.00$ 13,125.00$ 171,825.00$ 191172124014930ADDRESS UNASSIGNEDAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 553919,786.09$ 9,786.09$ 191172124015030ADDRESS UNASSIGNEDAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391722.84$ 722.84$ 1911721240115701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240116701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ PIDSTREET NUMBERSTREET NAMETOTAL PROPOSED ASSESSMENTTAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)PROPOSED STREET ASSESSMENTPROPOSED SEWER SERVICE ASSESSMENTPROPOSED WATER SERVICE ASSESSMENT
PRELIMINARY ASSESSMENT ROLL2019 STREET & UTILITY IMPROVEMENTSCITY OF HOPKINS, MNBMI PROJECT NO. T19.116650PIDSTREET NUMBERSTREET NAMETOTAL PROPOSED ASSESSMENTTAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)PROPOSED STREET ASSESSMENTPROPOSED SEWER SERVICE ASSESSMENTPROPOSED WATER SERVICE ASSESSMENT1911721240117701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240118701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240119701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240120701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240121701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240122701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240123701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240124701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240125701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240126701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240127701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240128701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240129701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240130701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240131701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240132701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240133701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240134701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240135701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240136701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240137701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240142701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240143701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240144701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240145701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240146701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240147701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721240148701OAK PARK LAAUBURN LIMITED PARTNERSHIPPARK AVENUE OF WAYZATA15210 WAYZATA BLVDWAYZATA MN 55391331.76$ 331.76$ 1911721130021801KASSIE CTNAPOLEON & MARIBEL TENERIFE801 KASSIE CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130022805KASSIE CTTOM BOMBERG & JORDYN BOMBERG805 KASSIE CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130023809KASSIE CTJUDE D RAJAN & LEENA PHILIP4753 HAMILTON RDMINNETONKA MN 55345 654.94$ 654.94$ 1911721130024813KASSIE CTNICK BROWN813 KASSIE CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130025901PARKSIDE BLVDGEORGE PARRINO901 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130026905PARKSIDE BLVDZACHARY W ZIMNIEWICZ905 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130027909PARKSIDE BLVDSARA WITT909 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130028913PARKSIDE BLVDPHUONG NGUYEN & KIET NGO913 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130029917PARKSIDE BLVDJILEEN S ARENDT917 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130030921PARKSIDE BLVDADAM C DRISCOLLQUINN A DRISCOLL921 PARKSIDE BLVDHOPKINS MN 55343654.94$ 654.94$
PRELIMINARY ASSESSMENT ROLL2019 STREET & UTILITY IMPROVEMENTSCITY OF HOPKINS, MNBMI PROJECT NO. T19.116650PIDSTREET NUMBERSTREET NAMETOTAL PROPOSED ASSESSMENTTAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)PROPOSED STREET ASSESSMENTPROPOSED SEWER SERVICE ASSESSMENTPROPOSED WATER SERVICE ASSESSMENT1911721130031925PARKSIDE BLVDRAHUL R SINGH925 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130032929PARKSIDE BLVDSTEVEN G BENTLEYDIANA DOMINICA DARDEN929 PARKSIDE BLVDHOPKINS MN 55343654.94$ 654.94$ 1911721130033933PARKSIDE BLVDSTEVEN YETTER & STACY HELM933 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130034937PARKSIDE BLVDNGUYEN HOANG937 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130035900PARKSIDE BLVDLARRY & BONNARY KETOLA900 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130036912PARKSIDE BLVDTAKAYUKI NEGISHI912 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130037916PARKSIDE BLVDCHONGBIN WU1165 MOERS DRCHASKA MN 55318 654.94$ 654.94$ 1911721130038920PARKSIDE BLVDKELSEY C GUZMAN920 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130039924PARKSIDE BLVDCALYNE QUYNH9748 77TH ST SCOTTAGE GROVE MN 55016 654.94$ 654.94$ 1911721130040928PARKSIDE BLVDLAWRENCE J MANDILENORA J MANDILE928 PARKSIDE BLVDHOPKINS MN 55343654.94$ 654.94$ 1911721130041932PARKSIDE BLVDRAMESH GANESAN/VIJAYA RAMESH932 PARKSIDE BLVDHOPKINS MN 55343 654.94$ 654.94$ 1911721130042929ABBIE LAPATRICK ALAN QUIGLEY929 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130043925ABBIE LANATALYA MOROZ925 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130044921ABBIE LAESTHER J WILLIAMS921 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130045917ABBIE LARHONDA M BROWN917 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130046913ABBIE LAMICHAEL A BLACKMON JRMAGGIE W BLACKMON913 ABBIE LAHOPKINS MN 55343654.94$ 654.94$ 1911721130047909ABBIE LAGERALDINE D PIRAP O BOX 894602MILANI HI 96789 654.94$ 654.94$ 1911721130048905ABBIE LAGREGORY J GENGLER905 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130049800KASSIE CTKELLY J MARX1 WEBSTER PLHOPKINS MN 55305 654.94$ 654.94$ 1911721130050804KASSIE CTREBECCA NUNN20860 ST ALBANS GREENEXCELSIOR MN 55331 654.94$ 654.94$ 1911721130051808KASSIE CTAPARNA PHILKANA808 KASSIE CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130052812KASSIE CTJOHN BARNES812 KASSIE CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130053813CAMERON CTMOLLIE C LARSON813 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130054809CAMERON CTANDREW M GULANSHANNA L GULAN809 CAMERON CTHOPKINS MN 55343654.94$ 654.94$ 1911721130055805CAMERON CTJULIE M GREENBERGJAMIE W REINBOLD805 CAMERON CTHOPKINS MN 55343654.94$ 654.94$ 1911721130056801CAMERON CTMATTHEW E & MARA COREY801 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130057800CAMERON CTBRIAN P DAHLBERG800 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130058804CAMERON CTMEGAN HINRICHSEN804 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130059808CAMERON CTJEAN A SORENSON808 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130060812CAMERON CTRAKESH & PRERNA VERMA812 CAMERON CTHOPKINS MN 55343 654.94$ 654.94$ 1911721130061813LINDSEY LAVENKATA N U BHASKA MARELLA9692 TREE FARM RDEDEN PRAIRIE MN 55347 654.94$ 654.94$ 1911721130062809LINDSEY LAIVAN MADJOS809 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130063805LINDSEY LASOUMYA JANDHYALAVENKATA M GOWTHAM AKULA805 LINDSEY LAHOPKINS MN 55343654.94$ 654.94$ 1911721130064801LINDSEY LASARATHCHANDRA KARUNANAYAKE801 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130065900ABBIE LAPATRICE PETERSEN900 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130066904ABBIE LACEDAR GLEN DEVELOPMENT LLC7271 KURVERS POINT RDCHANHASSEN MN 55317 654.94$ 654.94$ 1911721130067908ABBIE LAJAMES C BARRINGER TRUSTEEGLORIA A BARRINGER TRUSTEE414 WEST PALMER CIRCLEABERDEEN SD 57401654.94$ 654.94$ 1911721130068912ABBIE LASHARAD GOYAL912 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$
PRELIMINARY ASSESSMENT ROLL2019 STREET & UTILITY IMPROVEMENTSCITY OF HOPKINS, MNBMI PROJECT NO. T19.116650PIDSTREET NUMBERSTREET NAMETOTAL PROPOSED ASSESSMENTTAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)PROPOSED STREET ASSESSMENTPROPOSED SEWER SERVICE ASSESSMENTPROPOSED WATER SERVICE ASSESSMENT1911721130069916ABBIE LAJOE CAVANAUGH3650 YUMA LANE NPLYMOUTH MN 55446 654.94$ 654.94$ 1911721130070924ABBIE LASAMIH KADADAHSOUZAN AL-SHAWA924 ABBIE LAHOPKINS MN 55343654.94$ 654.94$ 1911721130071928ABBIE LACHEDITA D & ROSENDO T MIGUEL928 ABBIE LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130072925LINDSEY LAIVAN & MARITES SENDRIJAS925 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130073921LINDSEY LAPRAFULL VERMA ET AL422 GOLDEN HARVEST LOOPCARRY NC 27519-9495 654.94$ 654.94$ 1911721130074917LINDSEY LAMARGARET REYNOLDS917 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130075913LINDSEY LAMELISSA DVORAK913 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130076909LINDSEY LALYNN RONNING & MYRA SIMENSON909 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130077905LINDSEY LADAVID A BERDASS905 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 1911721130078901LINDSEY LARAVIKUMAR JASTHI901 LINDSEY LAHOPKINS MN 55343 654.94$ 654.94$ 191172113007930ADDRESS UNASSIGNEDPARKSIDE HOMEOWNERS ASSOCC/O URGANWOOD REAL ESTATEP O BOX 19497MINNEAPOLIS MN 5541921,439.75$ 21,439.75$ 191172113008030ADDRESS UNASSIGNEDPARKSIDE HOMEOWNERS ASSOCC/O URBANWOOD REAL ESTATEP O BOX 19497MINNEAPOLIS MN 5541914,283.61$ 14,283.61$ 191172113008130ADDRESS UNASSIGNEDPARKSIDE HOMEOWNERS ASSOCC/O URBANWOOD REAL ESTATEP O BOX 19497MINNEAPOLIS MN 554194,385.31$ 4,385.31$ 1911721240254710REGENCY LA EWEILIN ONG MARKFORTEDWARD MARKFORT710 REGENCY LA EHOPKINS MN 55343437.81$ 437.81$ 1911721240255714REGENCY LA ETHOMAS L ROBERTSON714 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240256718REGENCY LA EJULIA RUTH CLARK718 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240257722REGENCY LA EJUNKO KUMAMOTOHIROSHI KUMAMOTO722 REGENCY LA EHOPKINS MN 55343437.81$ 437.81$ 1911721240258726REGENCY LA EMIKALAI ZAIKO726 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240259730REGENCY LA EHUNTER MOEN730 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240260738REGENCY LA ESUZANNE K KALAN738 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240261742REGENCY LA EIGOR KORABEL742 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240262746REGENCY LA ELINDA M SLOAN746 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 1911721240263750REGENCY LA ESTEVEN T & ELIZABETH A WAHL620 S 7TH AVE #347PO BOX 1908FRISCO CO 80443437.81$ 437.81$ 1911721240264754REGENCY LA EJEANETTE WOOD754 REGENCY LA EHOPKINS MN 55343 437.81$ 437.81$ 19117212402657552ND ST N EKENNETH & RENAE JACOBSON755 2ND ST N EHOPKINS MN 55343 437.81$ 437.81$ 19117212402667512ND ST N ECNBI LLCC/O MIDWEST REALTY SERV12800 INDUSTL PK BLVD #150APLYMOUTH MN 55441437.81$ 437.81$ 19117212402677472ND ST N EMICHELE EDDIE1631 N 127TH STKANSAS CITY KS 66109 437.81$ 437.81$ 19117212402687432ND ST N EIVAN MCMULLEN/JOYCE MCMULLEN743 2ND ST N EHOPKINS MN 55343 437.81$ 437.81$ 19117212402697392ND ST N ESHADOW INVESTMENTS LLC2063 AUSTRIAN PINEMINNETONKA MN 55305 437.81$ 437.81$ 19117212402707312ND ST N EJAMES A SODERBERG245 SKI HILL RDMINNEAPOLIS MN 55422 437.81$ 437.81$ 19117212402717272ND ST N EJESUS A VENERO ROMAN727 2ND ST N EHOPKINS MN 55343 437.81$ 437.81$ 19117212402727232ND ST N ESTEVEN KNUTSONKRISTIN J JOHNSON432 SUMMERFIELD DRCHANHASSEN MN 55317437.81$ 437.81$ 19117212402737192ND ST N EALTHEA JENKINS719 2ND ST N EHOPKINS MN 55343 437.81$ 437.81$ 19117212402747152ND ST N EURI SPECTOR & TANIA SPECTOR715 2ND ST N EHOPKINS MN 55343 437.81$ 437.81$ 19117212402757112ND ST N ETERRI L KRUGER711 2ND ST N EHOPKINS MN 55343437.81$ 437.81$ 191172124027630ADDRESS UNASSIGNEDREGENCY MASTER ASSN4672 SLATER RDEAGAN MN 55122 10,169.89$ 10,169.89$ 1911721210008700CAMBRIDGE STRAMSGATE APARTMENTS LLC5290 VILLA WAYEDINA MN 55436 278,300.00$ 4,442.00$ 282,742.00$ 191172121001030ADDRESS UNASSIGNEDRAMSGATE APARTMENTS LLC5290 VILLA WAYEDINA MN 55436 6,300.75$ 158.00$ 6,458.75$
PRELIMINARY ASSESSMENT ROLL2019 STREET & UTILITY IMPROVEMENTSCITY OF HOPKINS, MNBMI PROJECT NO. T19.116650PIDSTREET NUMBERSTREET NAMETOTAL PROPOSED ASSESSMENTTAXPAYER NAME TAXPAYER ADDRESS (LINE1)TAXPAYER ADDRESS (LINE2)TAXPAYER ADDRESS (LINE3)PROPOSED STREET ASSESSMENTPROPOSED SEWER SERVICE ASSESSMENTPROPOSED WATER SERVICE ASSESSMENT1911721210006500CAMBRIDGE STTHE PLANATION CARRGE HSE LLCC/O ERWIN R STOBBE500 CAMBRIDGE STHOPKINS MN 5534373,817.08$ 4,600.00$ 78,417.08$ 19117211200031045HIAWATHA AVECREEK POINT APARTMENTS1045 HIAWATHA AVEHOPKINS MN 55343 28,828.25$ 2,004.00$ 5,000.00$ 35,832.25$ 19117211200181050HIAWATHA AVECREEK POINT APARTMENTS1045 HIAWATHA AVEHOPKINS MN 55343 10,300.00$ 1,716.00$ 3,300.00$ 15,316.00$ 1911721120023530BLAKE RD NHOLIDAY STATIONSTORES INCATTN TAX DEPARTMENT4567 AMERICAN BLVD WMINNEAPOLIS MN 5543734,300.00$ 2,484.00$ 36,784.00$ 19117211200221111CAMBRIDGE STWHITE CASTLE SYSTEM INC555 WEST GOODALE STCOLUMBUS OH 43215-1158 21,200.00$ 784.00$ 21,984.00$ 1911721120028819CAMBRIDGE STMD LAND LLC5425 BOONE AVE NNEW HOPE MN 55428 26,800.00$ 27,100.00$ 53,900.00$ 1911721120027919CAMBRIDGE STMARVIN DEVELOPMENT IV LLC5425 BOONE AVE NNEW HOPE MN 55428 33,956.84$ 27,100.00$ 61,056.84$ 191172112002930ADDRESS UNASSIGNEDMARVIN DEVELOPMENT IV LLC5425 BOONE AVE NNEW HOPE MN 55428 7,900.00$ 7,900.00$ 1911721120030520BLAKE RD NPAM CASH5475 BUTTERNUT CIRMINNETONKA MN 55343 21,600.00$ 2,484.00$ 24,084.00$ 19117211200341105HIAWATHA AVECADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS MN 55404 7,967.08$ 2,004.00$ 5,000.00$ 14,971.08$ 19117211200351115HIAWATHA AVECADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS MN 55404 7,967.08$ 2,004.00$ 5,000.00$ 14,971.08$ 19117211200361125HIAWATHA AVECADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS MN 55404 13,800.00$ 2,004.00$ 5,000.00$ 20,804.00$ 19117211200371110HIAWATHA AVECADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS MN 55404 10,692.66$ 2,004.00$ 5,000.00$ 17,696.66$ 19117211200381120HIAWATHA AVECADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS MN 55404 11,139.24$ 2,004.00$ 5,000.00$ 18,143.24$ 191172112004030ADDRESS UNASSIGNEDCADY MANAGEMENT2200 BLAISDELL AVE SMINNEAPOLIS, MN 55404 3,326.37$ 3,326.37$ 1,280,643.56$ PRELIMINARY TOTAL AMOUNT TO BE ASSESSED
PUBLIC OPEN HOUSE
2019 Street & Utility Improvements
Wednesday, November 14 at 5:00 p.m.
Hopkins City Hall Council Chambers
1010 1st St S, Hopkins MN
During the summer of 2019, the City of Hopkins will be making improvements to the streets and utilities in your neighborhood. An
open house will be conducted to provide information on the proposed improvements, special assessments, and funding for the project.
The meeting has been scheduled for Wednesday, November 14 in the Council Chambers at Hopkins City Hall. The open house will
begin at 5:00 p.m. with an informational presentation to occur at 5:30 p.m. Members of the project team will be present to answer
questions and take comments over the course of the event.
There will be additional meetings held over the next several months as the project design progresses and construction nears.
This open house is not the only opportunity to provide feedback. Residents who are unable to attend can contact either of the
individuals below with any questions, concerns, or comments.
Eric Klingbeil, P.E. Mike Waltman, P.E.
Assistant City Engineer Project Manager
952-548-6357 612-221-6946
eklingbeil@hopkinsmn.com mikewa@bolton-menk.com
PUBLIC OPEN HOUSE
2018 Street & Utility Improvements
Cottageville Area Neighborhood
Wednesday, November 14 at 5:00 p.m.
Hopkins City Hall Council Chambers
1010 1st St S, Hopkins MN
During the summer of 2019, the City of Hopkins will be making improvements to the streets and utilities in your neighborhood. An
open house will be conducted to provide information on the proposed improvements, special assessments, and funding for the project.
The meeting has been scheduled for Wednesday, November 14 in the Council Chambers at Hopkins City Hall. The open house will
begin at 5:00 p.m. with an informational presentation to occur at 5:30 p.m. Members of the project team will be present to answer
questions and take comments over the course of the event.
There will be additional meetings held over the next several months as the project design progresses and construction nears.
This open house is not the only opportunity to provide feedback. Residents who are unable to attend can contact either of the
individuals below with any questions, concerns, or comments.
Eric Klingbeil, P.E. Mike Waltman, P.E.
Assistant City Engineer Project Manager
952-548-6357 612-221-6946
eklingbeil@hopkinsmn.com mikewa@bolton-menk.com
Bolton & Menk, Inc.
12224 Nicollet Avenue
Burnsville, MN 55337
Bolton & Menk, Inc.
12224 Nicollet Avenue
Burnsville, MN 55337
C:\Users\mikewa\Desktop\Hopkins 2019 Improvements\Final Design Construction\Klingbeil 111418.docx
November 14, 2018
Mr. Eric Klingbeil, P.E., Asst. City Engineer
City of Hopkins
1010 1st Street South
Hopkins, MN 55343
Re: Proposal for Professional Engineering and Surveying Services
2019 Street and Utility Improvements – Final Design & Construction Services
City of Hopkins, Minnesota
Dear Mr. Klingbeil:
We are pleased to offer you our proposal for professional engineering and surveying services for the final design
and construction phases of the City of Hopkins’ 2019 Street and Utility Improvements. This proposal is based on
the preliminary engineering report prepared as part of the feasibility phase of the project and has been prepared in
the form of our standard agreement consistent with past projects. The enclosed Detailed Work Plan and Estimate
of Project Fees further detail our proposed level of effort.
In addition to the enclosed standard agreement, Exhibit I details our proposed process and scope of work to be
performed. The schedule presented in Exhibit I illustrates a streamlined schedule, for council meetings, consistent
with the approach followed in years past for assessment projects. The proposed project schedule is intended to meet
the City’s desire to have a bid opening in March and contract award in April. Upon authorization by the Council on
the 20th, we will proceed with final design of the improvements immediately to meet all required deadlines.
As always, thank you for allowing Bolton & Menk, Inc. to submit this proposal for your consideration. Upon your
review and approval of this agreement, please sign each copy of the agreement, and return them both to our office.
I will return a fully executed copy to you. If you have any questions regarding this proposal or would like to discuss
any of its details, please do not hesitate to call me. We truly appreciate and value our continued working relationship
with the City of Hopkins.
Sincerely,
Bolton & Menk, Inc.
Michael J. Waltman, P.E.
Principal Engineer
cc: Nate Stanley, P.E., City Engineer
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 1 of 9
AGREEMENT FOR PROFESSIONAL SERVICES
FINAL DESIGN & CONSTRUCTION SERVICES
2019 STREET & UTILITY IMPROVEMENTS
CITY OF HOPKINS, MINNESOTA
This Agreement, made this 20th day of November, 2018, by and between CITY OF HOPKINS, 1010 1st
Street South, Hopkins, MN 55343, hereinafter referred to as CLIENT, and BOLTON & MENK, INC.,
12224 Nicollet Avenue, Burnsville, MN 55337, hereinafter referred to as CONSULTANT.
WITNESS, whereas the CLIENT requires professional services in conjunction with the 2019 STREET &
UTILITY IMPROVEMENTS and whereas the CONSULTANT agrees to furnish the various professional
services required by the CLIENT.
NOW, THEREFORE, in consideration of the mutual covenants and promises between the parties hereto,
it is agreed:
SECTION I - CONSULTANT'S SERVICES
A. The CONSULTANT agrees to perform the various Basic Services in connection with the proposed
project as described in Exhibit I.
B. Upon mutual agreement of the parties hereto, Additional Services may be authorized as described
in Exhibit I or as described in Paragraph IV.B.
SECTION II - THE CLIENT'S RESPONSIBILITIES
A. The CLIENT shall promptly compensate the CONSULTANT in accordance with Section III of this
Agreement.
B. The CLIENT shall place any and all information related to the project in its custody at the disposal
of the CONSULTANT for its use. Such information shall include but shall not be limited boundary
surveys, topographic surveys, preliminary sketch plan layouts, building plans, soil surveys,
abstracts, deed descriptions, tile maps and layouts, aerial photos, utility agreements, environmental
reviews, and zoning limitations. The CONSULTANT may rely upon the accuracy and sufficiency
of all such information in performing services unless otherwise instructed, in writing, by CLIENT.
This obligation shall not include information that is classified as private or confidential under the
Minnesota Government Data Practices Act (MGDPA), unless access to such information is
essential to the CONSULTANT’s scope of services, in which case the CLIENT shall establish in
writing, and CONSULTANT shall comply with, any conditions governing access to and use of
such private or confidential information.
C. The CLIENT will guarantee access to and make all provisions for entry upon both public and
private portions of the project and pertinent adjoining properties.
D. The CLIENT will give prompt notice to the CONSULTANT whenever the CLIENT observes or
otherwise becomes aware of any defect in the proposed project.
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 2 of 9
E. The CLIENT shall designate a liaison person to act as the CLIENT'S representative with respect to
services to be rendered under this Agreement. Said representative shall have the authority to
transmit instructions, receive instructions, receive information, interpret and define the CLIENT'S
policies with respect to the project and CONSULTANT'S services.
F. The CLIENT shall provide such legal, accounting, independent cost estimating and insurance
counseling services as may be required for completion of the consultant services described in this
agreement.
G. The CLIENT will obtain any and all regulatory permits required for the proper and legal execution
of the project.
H. The CLIENT will hire, when requested by the CONSULTANT, an independent test company to
perform laboratory and material testing services, and soil investigation that can be justified for the
proper design and construction of the project. The CONSULTANT shall assist the CLIENT in
selecting a testing company. Payment for testing services shall be made directly to the testing
company by the CLIENT and is not part of this Agreement.
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 3 of 9
SECTION III - COMPENSATION FOR SERVICES
A. FEES.
1. The CLIENT will compensate the CONSULTANT in accordance with the following schedule
of fees for the time spent in performance of Agreement services.
Schedule of Fees
Classification Hourly Rates
Sr. Project Manager – Sr. Principal Engineer/Surveyor $150-220/Hour
Sr. Project Manager – Principal Engineer/Surveyor $140-200/Hour
Project Manager $125-175/Hour
Project/Design Engineer /Planner $110-160/Hour
Licensed Surveyor $120-160/Hour
Project Surveyor $105-150/Hour
Specialist (Nat. Resources; GIS; Traffic; Other) $85-140/Hour
Senior Technician (Inc. Survey1) $105-155/Hour
Technician (Inc. Survey1) $95-125/Hour
Administrative Support & Clerical $85/Hour
GPS/Robotic Survey Equipment No Charge
CAD/Computer Usage No Charge
Routine Photo Copying/Reproduction No Charge
Routine Office Supplies No Charge
Field Supplies/Survey Stakes & Equipment No Charge
Mileage No Charge
1No separate charges will be made for GPS or robotic total stations on Bolton & Menk, Inc. survey assignments; the
cost of this equipment is included in the rates for Survey Technicians.
2. Total cost for the services itemized under Exhibit I, Section A (Basic Services) shall not exceed
$625,352. Itemization of this cost is as shown in the attached DETAILED WORK PLAN and
PROJECT FEES tables, attached hereto as Exhibit II.
3. In addition to the foregoing, CONSULTANT shall be reimbursed at cost plus an overhead fee
(not-to-exceed 10%) for the following Direct Expenses when incurred in the performance of the
work.
a. CLIENT approved outside (facilities not owned by CONSULTANT) computer services.
b. CLIENT approved outside professional and technical services.
c. Outside reproduction and reprographic charges.
d. Expendable field supplies and special field equipment rental.
e. Other costs for such additional items and services that the CLIENT may require the
CONSULTANT to provide to fulfill the terms of this Agreement.
4. Additional services as outlined in Section I.B will vary depending upon project conditions and
will be billed on an hourly basis at the rate described in Section III.A.1.
5. The payment to the CONSULTANT will be made by the CLIENT upon billing at intervals not
more often than monthly at the herein rates. Itemized invoices identifying all work completed
shall be submitted to the CLIENT by CONSULTANT and paid in the same manner as other
claims made to the CLIENT.
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 4 of 9
SECTION IV - GENERAL
A. STANDARD OF CARE
Professional services provided under this Agreement will be conducted in a manner consistent with
that level of care and skill ordinarily exercised by members of the Consultant's profession currently
practicing under similar conditions. No warranty, express or implied, is made.
B. CHANGE IN PROJECT SCOPE
In the event the CLIENT changes or is required to change the scope of the project from that
described in Section I and/or the applicable addendum, and such changes require Additional
Services by the CONSULTANT, the CONSULTANT shall be entitled to additional compensation
at the applicable hourly rates. The CONSULTANT shall give notice to the CLIENT of any
Additional Services, prior to furnishing such additional services and the CLIENT must approve an
Additional Services in writing. The CLIENT may request an estimate of additional cost from the
CONSULTANT, and upon receipt of the request, the CONSULTANT shall furnish such, prior to
authorization of the changed scope of work.
C. INDEPENDENT CONTRACTOR
The CONSULTANT shall at times be deemed an independent contractor. The CONSULTANT is
not to be deemed an employee or agent of the CLIENT and has no authority to make any binding
commitments or obligations on behalf of the CLIENT except to the extent expressly provided
herein. All services provided by the CONSUTANT pursuant to this agreement shall be provide on
an independent contractor basis not as an employee of the CLIENT for any purpose including, but
not limited to, income tax withholding, workers’ compensation, unemployment compensation,
FICA taxes, liability for torts, and eligibility for employee benefits.
D. LIMITATION OF LIABILITY
CONSULTANT shall indemnify, defend, and hold harmless CLIENT and its officials, agents and
employees from any loss, claim, liability, and expense (including reasonable attorneys’ fees and
expenses of litigation) arising from, or based in the whole, or in any part, on any negligent act or
omission by CONSULTANT’S employees, agents, or subconsultants. In no event shall CLIENT
be liable to CONSULTANT for consequential, incidental, indirect, special, or punitive damages.
CLIENT shall indemnify, defend, and hold harmless CONSULTANT and its employees from any
loss, claim, liability, and expense (including reasonable attorneys’ fees and expenses of litigation)
arising from, or based in the whole, or in any part, on any negligent act or omission by CLIENT’S
employees, agents, or consultants. In no event shall CONSULTANT be liable to CLIENT for
consequential, incidental, indirect, special, or punitive damages.
Nothing contained in this Agreement shall be construed as a limitation on or waiver of any
immunities or limitations on liability otherwise available to the CLIENT. Nothing contained in this
Agreement shall create a contractual relationship with or a cause of action in favor of a third party
against either the CLIENT or the CONSULTANT. The CONSULTANT'S services under this
Agreement are being performed solely for the CLIENT'S benefit, and no other entity shall have any
claim against the CONSULTANT because of this Agreement or the performance or
nonperformance of services provided hereunder. The CLIENT agrees to include a provision in all
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 5 of 9
contracts with contractors and other entities involved in this project to carry out the intent of the
paragraph.
E. INSURANCE
1. The CONSULTANT agrees to maintain, at CONSULTANT’S expense a commercial general
liability and excess umbrella general liability insurance policy or policies insuring CONSULTANT
against claims for bodily injury, death or property damage arising out of CONSULTANT’S general
business activities. The general liability coverage shall provide limits of not less than $2,000,000
per occurrence and not less than $2,000,000 general aggregate. Coverage shall include Premises
and Operations Bodily Injury and Property Damage; Personal and Advertising Injury; Blanket
Contractual Liability; Products and Completed Operations Liability.
2. The CONSULTANT also agrees to maintain, at CONSULTANT’S expense, a single limit or
combined limit automobile liability insurance and excess umbrella liability policy or policies
insuring owned, non-owned and hired vehicles used by CONSULTANT under this Agreement.
The automobile liability coverages shall provide limits of not less than $1,000,000 per accident for
property damage, $2,000,000 for bodily injuries, death and damages to any one person and
$2,000,000 for total bodily injury, death and damage claims arising from one accident.
3. CLIENT shall be named Additional Insured for the above liability policies.
4. The CONSULTANT agrees to maintain, at the CONSULTANT'S expense, statutory worker's
compensation coverage together with Coverage B, Employer’s Liability limits of not less than
$500,000 for Bodily Injury by Disease per employee, $500,000.00 for Bodily Injury by Disease
aggregate and $500,000 for Bodily Injury by Accident.
5. During the period of design and construction of the project, the CONSULTANT also agrees to
maintain, at CONSULTANT’S expense, Professional Liability Insurance coverage insuring
CONSULTANT against damages for legal liability arising from an error, omission or negligent act
in the performance of professional services required by this agreement. The professional liability
insurance coverage shall provide limits of not less than $2,000,000 per claim and an annual
aggregate of not less than $2,000,000 on a claims-made basis.
6. Prior to commencement of this Agreement, the CONSULTANT will provide the CLIENT with
certificates of insurance, showing evidence of required coverages. All policies of insurance shall
contain a provision or endorsement that the coverage afforded will not be canceled or reduced in
limits by endorsement for any reason except non-payment of premium, until at least 30 days’ prior
written notice has been given to the CLIENT, and at least 10 days’ prior written notice in the case
of non-payment of premium.
F. OPINIONS OR ESTIMATES OF CONSTRUCTION COST
Where provided by the CONSULTANT as part of Exhibit I or otherwise, opinions or estimates of
construction cost will generally be based upon public construction cost information. Since the
CONSULTANT has no control over the cost of labor, materials, competitive bidding process,
weather conditions and other factors affecting the cost of construction, all cost estimates are
opinions for general information of the CLIENT and the CONSULTANT does not warrant or
guarantee the accuracy of construction cost opinions or estimates. The CLIENT acknowledges that
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 6 of 9
costs for project financing should be based upon contracted construction costs with appropriate
contingencies.
G. CONSTRUCTION SERVICES
It is agreed that the CONSULTANT and its representatives shall not be responsible for the means,
methods, techniques, schedules or procedures of construction selected by the contractor or the
safety precautions or programs incident to the work of the contractor.
H. USE OF ELECTRONIC/DIGITAL DATA
Because of the potential instability of electronic/digital data and susceptibility to unauthorized
changes, copies of documents that may be relied upon by CLIENT are limited to the printed copies
(also known as hard copies) that are signed or sealed by CONSULTANT. Except for
electronic/digital data which is specifically identified as a project deliverable by this
AGREEMENT or except as otherwise explicitly provided in this AGREEMENT, all
electronic/digital data developed by the CONSULTANT as part of the PROJECT is acknowledged
to be an internal working document for the CONSULTANT’S purposes solely and any such
information provided to the CLIENT shall be on an “AS IS” basis strictly for the convenience of
the CLIENT without any warranties of any kind. As such, the CLIENT is advised and
acknowledges that use of such information may require substantial modification and independent
verification by the CLIENT (or its designees). Provision of electronic/digital data, whether
required by this Agreement or provided as a convenience to the Client, does not include any license
of software or other systems necessary to read, use or reproduce the information. It is the
responsibility of the CLIENT to verify compatibility with its system and long-term stability of
media. CLIENT shall indemnify and hold harmless CONSULTANT and its Subconsultants from
all claims, damages, losses, and expenses, including attorneys' fees arising out of or resulting from
third party use or any adaptation or distribution of electronic/digital data provided under this
AGREEMENT, unless such third party use and adaptation or distribution is explicitly authorized by
this AGREEMENT.
I. DATA PRACTICES
All data collected, created, received, maintained, or disseminated, or used for any purposes in the
course of the CONSULTANT’S performance of the Agreement is governed by the Minnesota
Government Data Practices Act, Minnesota Statutes Section 13.01, et seq. or any other applicable
state statutes and state rules adopted to implement the Act, as well as state statutes and federal
regulations on data privacy. The Consultant agrees to abide by these statutes, rules and regulations
and as they may be amended. In the event the CONSULTANT receives a request to release data, it
shall notify CLIENT as soon as practical. The CLIENT will give instructions concerning release of
data to requesting party and CONSULTANT will be reimbursed as Additional Services by CLIENT
for its reasonable expenses in complying with the request.
J. PERIOD OF AGREEMENT
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 7 of 9
This Agreement will remain in effect for the longer of a period of two years or such other explicitly
identified completion period, after which time the Agreement may be extended upon mutual
agreement of both parties.
K PAYMENTS
If CLIENT fails to make any payment due CONSULTANT for services and expenses within 60
days after date of the CONSULTANT'S itemized invoice, a service charge of one and one-half
percent (1.5%) per month or the maximum rate permitted by law, whichever is less, will be charged
on any unpaid balance. In addition after giving seven days' written notice to CLIENT,
CONSULTANT may, without waiving any claim or right against the CLIENT and without
incurring liability whatsoever to the CLIENT, suspend services and withhold project deliverables
due under this Agreement until CONSULTANT has been paid in full all amounts due for services,
expenses and charges.
L. TERMINATION
This Agreement may be terminated by the CLIENT for any reason or for convenience by the
CLIENT upon seven (7) days written notice. The CONSULTANT may only terminate for non-
payment by CLIENT upon CLIENT’s failure to cure upon 30 days written notice.
M. CONTINGENT FEE
The CONSULTANT warrants that it has not employed or retained any company or person, other
than a bona fide employee working solely for the CONSULTANT to solicit or secure this Contract,
and that it has not paid or agreed to pay any company or person, other than a bona fide employee,
any fee, commission, percentage, brokerage fee, gift or any other consideration, contingent upon or
resulting from award or making of this Agreement.
N. NON-DISCRIMINATION
The provisions of any applicable law or ordinance relating to civil rights and discrimination shall be
considered part of this Agreement as if fully set forth herein.
The CONSULTANT is an Equal Opportunity Employer and it is the policy of the
CONSULTANT that all employees, persons seeking employment, subcontractors, subconsultants
and vendors are treated without regard to their race, religion, sex, color, national origin, disability,
age, sexual orientation, marital status, public assistance status or any other characteristic protected
by federal, state or local law.
O. CONTROLLING LAW
This Agreement is to be governed by the law of the State of Minnesota.
P. DISPUTE RESOLUTION
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 8 of 9
CLIENT and CONSULTANT agree to negotiate all disputes between them in good faith for a
period of 30 days from the date of notice of dispute prior to proceeding to formal dispute resolution
or exercising their rights under law.
Q. SURVIVAL
All obligations, representations and provisions made in or given in Section IV of this Agreement
will survive the completion of all services of the CONSULTANT under this Agreement or the
termination of this Agreement for any reason.
R. SEVERABILITY
Any provision or part of the Agreement held to be void or unenforceable under any law or
regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and
binding upon CLIENT and CONSULTANT, who agree that the Agreement shall be reformed to
replace such stricken provision or part thereof with a valid and enforceable provision that comes as
close as possible to expressing the intention of the stricken provision.
S. AUDIT DISCLOSURE
The CONSULTANT must allow the CLIENT, or its duly authorized agents, and the state auditor or
legislative auditor reasonable access to the CONSULTANT’s books, records, documents, and
accounting procedures and practices that are pertinent to all services provided under this Agreement
for a minimum of six years from the termination of this Agreement.
[remainder of the page intentionally blank]
City of Hopkins 2019 Agreement (Modified from 2004 Standard Form) VER. 11/14/18
Page 9 of 9
SECTION V - SIGNATURES
THIS INSTRUMENT embodies the whole agreement of the parties, there being no promises, terms,
conditions or obligation referring to the subject matter other than contained herein. This Agreement may
only be amended, supplemented, modified or canceled by a duly executed written instrument signed by
both parties.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in their behalf.
CLIENT: City of Hopkins, Minnesota CONSULTANT: Bolton & Menk, Inc.
Mike Waltman, P.E., Principal Engineer
Marcus A. Thomas, P.E., BMI Office Manager
Date
Date
City of Hopkins November 20, 2018
1
EXHIBIT I
FINAL DESIGN, CONSTRUCTION OBSERVATION, ADMINISTRATION & STAKING
2019 STREET AND UTILITY IMPROVEMENTS
CITY OF HOPKINS, MINNESOTA
A. BASIC SERVICES
In accordance with the City of Hopkins’ Preliminary Engineering Report, Bolton &
Menk, Inc. has been requested to complete final design, bidding assistance, construction
staking, construction observation and construction administration services for the City’s
2019 Street and Utility Improvements. The project area includes the following corridors:
Cambridge St, Blake Rd N to Van Buren Ave N
Van Buren Ave N, Cambridge St to Lake St NE
Lake St NE, Van Buren Ave N to mid-block between Tyler Ave N & Blake Rd N
Hiawatha Ave, Cambridge St to Blake Rd N
Tyler Ave N, Lake St NE to 2nd St NE
Oak Park Ln, Tyler Ave N to Public Street Limits
CIPP Lining throughout the City
Spot Concrete Sidewalk and Alley Repairs
Building from tasks 1 and 2 of our preliminary design scope of services, detailed tasks
associated with the work are itemized in the attached Detailed Work Plan and are
described below.
Task 3: Final Design & Bidding Services
Final Design
Final design for the 2019 Street and Utility Improvements will be completed based on the
Preliminary Engineering Report completed by Bolton & Menk, Inc. in October, 2018.
Final plans and specifications will be completed in compliance with the City of Hopkins’
Engineering Guidelines. Detailed construction plans will be prepared in Civil3D design
software. The plans and specifications will include:
• Plan and profile views of the street reconstruction and utility improvements at 25
scale.
• Cross sections will be shown for reconstructed streets at approximately 25'
spacing and at each driveway.
• Required construction details.
• Special provisions for elements of work not addressed in the MnDOT 2018
Standard Construction Specifications.
• Construction phasing/staging plans to coordinate construction with the Blake
Road reconstruction improvements and Met Council construction along Lake
Street.
City of Hopkins November 20, 2018
2
• Applicable plans for improvements to the Cambridge St bridge, prepared by a
licensed structural engineer with experience in bridge design in Minnesota, as
scoped in the preliminary engineering report.
• Temporary traffic control plans for necessary detours or temporary access routes
to businesses. Coordination with Met Transit will occur regarding busing
operations to serve the neighborhood during construction.
Final plans will be submitted for review and comment by private utility owners. Permit
applications as noted in the Preliminary Engineering Report will be completed and
submitted to the permitting agency. Upon completion of construction plans and
specifications, a final estimate of construction cost will be prepared and submitted to the
client. The project will be advertised, bids will be taken, and recommendation will be
made to accept or reject bids. Meetings included during final design include three (3)
City Staff meetings for design review and two (2) City Council meetings for final plan
presentation and conducting the Public Assessment Hearing.
Impacts to some trees and privately owned landscaping are anticipated. Coordination
efforts will be undertaken with homeowners regarding tree removals and landscaping
impacts prior to construction. Letters will be sent to each affected property to inform the
owner of the known or potential tree and/or landscaping impacts to their property. The
Construction Observer and/or Project Engineer will respond to questions of the owner(s)
and will coordinate on-site meetings as necessary to coordinate any impacts prior to
construction.
Special Assessments Assistance
For this project, the City of Hopkins intends to assess this project prior to awarding the
contract, based on the bid of the lowest responsible bidder. Bolton & Menk will prepare a
final assessment roll after bids have been opened and will attend the public assessment
hearing to assist City Staff. Bolton & Menk will assist City Staff with the assessment
process and associated statutory requirements, as well as aid in responding to property
owner inquiries throughout the process. Bolton & Menk will attend and facilitate two
neighborhood meetings prior to the final assessment hearing to provide additional
information on assessment amounts, payment options, and any remaining questions on
the proposed improvements.
Task 4: Construction Services
Construction Staking
Construction staking indicating cuts to the line and grade of the proposed utilities will
typically be performed at intervals of 50 feet. These utilities include sanitary sewer pipe
and manholes; watermain pipe, hydrants, and bends; storm sewer pipe, manholes, and
catch basins. Curb stakes will be provided along the reconstructed roadways at intervals
of 25 feet.
City of Hopkins November 20, 2018
3
Construction Observation and Administration
This project is proposed to be constructed during the 2019 construction season and is
anticipated to occur multiple phases of construction from May through October. The
projected fee estimate is based upon a 25-week construction season. Full time
construction observation is proposed for this project. The contractor’s use of several
construction crews across the multi-phased project will be necessary for timely
completion.
Duties of the Construction Observer will include attendance at the pre-construction
meeting and all construction-related meetings, service as a liaison between the City and
the contractor, review of the completed work to determine if the project is in general
conformance with the plans and specifications, review and scheduling of all materials
testing, maintenance of construction documentation, tracking quantities, project closeout
including checking in on punch list items, and communication with affected property
owners, as necessary, to address their construction-related concerns and issues.
Communication will include door-to-door notices as often as daily, phone calls, text
messages, emails, and in-person meetings.
The observer provided for the Cambridge St bridge work will be certified by MnDOT for
inspection of bridges.
Administration duties include a pre-construction meeting, weekly project meetings
including minutes, review of shop drawings, sending out weekly email updates to
resident subscribers, preparing and mailing out monthly newsletters to residents, updating
and maintaining a project website, and preparation of pay estimates. Observation and
administration services will be completed on an hourly basis. Estimated weekly time
spent for key staff during the construction process (tasks 4.2 – 4.4) are as follows:
Estimated Hours: Tasks 4.2 – 4.4
Title
Hours
/
Week
Weeks Total
Hours
Principal Engineer-in-Charge 3 25 75
Project Design Engineer 12 25 300
Construction Observer 60 25 1500
Survey Crew (1-man) 15 25 375
Record Drawings & GIS Integration
Record drawings detailing the completed improvements as recorded by the construction
observer will be completed and furnished to the City in hard copy and electronic format.
These record drawings will and also integrated with the City’s GIS web application in
PDF. Utilities, signs, curb stops, and structures will located (horizontally) after
construction using a handheld GPS unit and will also be incorporated in the GIS
schematic layout as GIS entities.
City of Hopkins November 20, 2018
4
The following is the anticipated schedule for the 2019 Street & Utility
Improvements:
Preparation of Final Plans & Specifications ......... November 21, 2018 – February 5, 2019
Approve Final Plans & Specifications / Set Bid Date / Set Assessment Hearing
Authorize Advertisement for Bids ........................................... February 5, 2019
Bid Opening .................................................................................................. March 8, 2019
Council Sets Public Assessment Hearing Date ...................................... March 19, 2019
Neighborhood Meeting 3 .......................................................................... April 1 - 10, 2019
Council Accepts Bids / Conduct Public Assessment Hearing /
Adopt Assessment Roll / Award Bid ............................................ April 16, 2019
Construction ........................................................................................ May – October 2019
B. ADDITIONAL SERVICES
Consulting services performed other than those authorized under Section I.A. shall be
considered not part of the Contract Services and may be authorized by the CLIENT as
additional services. Additional Services consist of those services which are not generally
considered to be Contract Services; or exceed the requirements of the Contract Services;
or are not definable prior to the commencement of the project; or vary depending on the
technique, procedures or schedule of the project contractor. Additional services may
consist of the following:
1. Cost of postage for mass mailing (those with greater than 100 recipients).
2. Cost of subconsultants desired by the Client, including benefit appraisals for use in
developing the final assessment roll and soils and material testing by a geotechnical
engineering firm.
3. All other services not specifically identified in Section A.
DETAILED WORK PLANESTIMATED PERSON-HOURS2019 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICESCITY OF HOPKINS, MINNESOTA11/14/2018CLIENT: CITY OF HOPKINS, MINNESOTAPROJECT:CONSULTANT:2019 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICESBOLTON & MENK, INC.Task No.Work Task Description3.0 FINAL DESIGN & BIDDING3.1 Utility Engineering and Design40 40 100 100 1604403.2 Roadway Engineering and Design40 100 200 60 1005003.3 Plan Set Production1001002003.4 Private Utility Coordination16 4040 2 4 8 1103.5 Construction Quantities and Cost Estimates6 30 30 4 12823.6 Construction Specifications40 40 840 1283.7 Permit Applications8 16 12 244 643.8 Bidding Assistance, Addenda, Award Recommendation12 12 12 420 603.9 Final Assessment Roll Preparation4 20 20443.10 QA / QC40 40 8883.11 Project Meetings (City Staff - 3), 1 Neighborhood Meeting, Public Communication 24 80 4 80 4016 2443.12 City Council Meeting (2 meetings)10 1020SUBTOTAL HOURS: TASK 3240 428 462 100 124 492 40 2 4 8 80 19804.0 CONSTRUCTION SERVICES4.1 Construction Phase Startup (Precon, Resident Coordination, Construction Staking Preparation, etc.) 24 24 4 80 12 241684.2 Construction Administration (25 weeks @ Waltman 3 hrs/week, Amatuccio 12 hrs/week) 75 300 125060 4974.3 Construction Observation (25 weeks @ 60 hrs/week)150015004.4 Construction Staking24 50 375 4494.5 Record Drawings4 840524.6 Project Closeout, Punch List20 40 12 801524.7 GIS Integration4 16828SUBTOTAL HOURS: TASK 4127 388 0 28 0 1708 50 36 74 375 60 2846TOTAL HOURS367 816 462 128 124 2200 90 38 78 383 140 4826ClericalConstruction ObserverSenior Structural EngineerESTIMATED PERSON-HOURSTotalsPrincipal EngineerProject Engineer Design EngineerWater Resources EngineerWeb SpecialistSurvey Manager / L.S.Surveying TechnicianSurvey Crew (1-man)
ESTIMATE OF PROJECT FEES2019 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICESCITY OF HOPKINS, MINNESOTA11/14/2018CLIENT: CITY OF HOPKINS, MINNESOTAPROJECT:CONSULTANT:2019 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICESBOLTON & MENK, INC.TASKAVERAGE RATE: $168.00 $135.00 $112.00 $160.00 $145.00 $125.00 $100.00 $150.00 $104.00 $140.00 $85.003.0FINAL DESIGN & BIDDING3.1Utility Engineering and Design$6,720.00 $5,400.00 $11,200.00 $0.00 $14,500.00 $20,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $57,820.003.2Roadway Engineering and Design$6,720.00 $13,500.00 $22,400.00 $9,600.00 $0.00 $12,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $64,720.003.3Plan Set Production$0.00 $0.00 $11,200.00 $0.00 $0.00 $12,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $23,700.003.4Private Utility Coordination$2,688.00 $5,400.00 $0.00 $0.00 $0.00 $5,000.00 $0.00 $300.00 $416.00 $1,120.00 $0.00 $14,924.003.5Construction Quantities and Cost Estimates$1,008.00 $4,050.00 $3,360.00 $640.00 $0.00 $1,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $10,558.003.6Construction Specifications$6,720.00 $5,400.00 $0.00 $1,280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,400.00 $16,800.003.7Permit Applications$1,344.00 $2,160.00 $0.00 $1,920.00 $3,480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $340.00 $9,244.003.8Bidding Assistance, Addenda, Award Recommendation$2,016.00 $1,620.00 $1,344.00 $640.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1,700.00 $7,320.003.9Final Assessment Roll Preparation$672.00 $2,700.00 $2,240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5,612.003.10QA / QC$6,720.00 $5,400.00 $0.00 $1,280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $13,400.003.11Project Meetings (City Staff - 3), 1 Neighborhood Meeting, Public Communication $4,032.00 $10,800.00 $0.00 $640.00 $0.00$10,000.00 $4,000.00 $0.00 $0.00 $0.00 $1,360.00 $30,832.003.12City Council Meeting (2 meetings)$1,680.00 $1,350.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,030.00SUBTOTAL FEES: TASK 3$40,320.00 $57,780.00 $51,744.00 $16,000.00 $17,980.00 $61,500.00 $4,000.00 $300.00 $416.00 $1,120.00 $6,800.00 $257,960.004.0CONSTRUCTION SERVICES4.1Construction Phase Startup (Precon, Resident Coordination, Construction Staking Preparation, etc.) $4,032.00 $3,240.00 $0.00 $640.00 $0.00 $10,000.00 $0.00 $1,800.00 $2,496.00 $0.00 $0.00 $22,208.004.2Construction Administration (25 weeks @ Waltman 3 hrs/week, Amatuccio 12 hrs/week) $12,600.00 $40,500.00$0.00 $1,920.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 $0.00 $5,100.00 $65,120.004.3Construction Observation (25 weeks @ 60 hrs/week)$0.00 $0.00 $0.00 $0.00 $0.00 $187,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $187,500.004.4Construction Staking$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,600.00 $5,200.00 $52,500.00 $0.00 $61,300.004.5Record Drawings$672.00 $1,080.00 $0.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $6,752.004.6Project Closeout, Punch List$3,360.00 $5,400.00 $0.00 $1,920.00 $0.00 $10,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $20,680.004.7GIS Integration$672.00 $2,160.00 $0.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,832.00SUBTOTAL FEES: TASK 4$21,336.00 $52,380.00 $0.00 $4,480.00 $0.00 $213,500.00 $5,000.00 $5,400.00 $7,696.00 $52,500.00 $5,100.00 $367,392.00TOTAL FEES$61,656.00$110,160.00$51,744.00$20,480.00$17,980.00$275,000.00$9,000.00$5,700.00$8,112.00$53,620.00$11,900.00$625,352.00Survey Manager / L.S.Construction ObserverSenior Structural EngineerSurveying TechnicianWeb SpecialistWater Resources EngineerPROJECT FEESPrincipal EngineerProject Engineer Design EngineerSurvey Crew (1-man)Clerical Totals