Loading...
2017 - 2021 CIP CAPITAL IMPROVEMENT PLAN 2017-2021 DATE: December 2016 TO: Honorable Mayor and Members of the City Council FROM: Mike Mornson, City Manager SUBJECT: 2017-2021 CAPITAL IMPROVEMENT PLAN With this letter I respectfully submit the 2017-2021 Capital Improvement Plan. This five- year planning document represents the combined efforts of city staff, advisory commissions, citizens and the City Council. The Capital Improvement Plan is a five-year forecast of project needs in the City of Hopkins. It is intended to alert the Council and citizens to the major capital needs on the horizon. The first year of the plan becomes an adopted capital budget and relates almost completely to the operating budget that is approved on a yearly basis. The remaining four year represents an estimate of project needs and funding capabilities of the city. This year’s plan does not include proposed equipment purchases. A document relating specifically to equipment replacement needs has been developed into a separate document. The Capital Improvement Plan is intended to serve as a planning tool and is therefore structured to present a meaningful, long-range perspective of the city’s capital programming needs. At the same time, sufficient projected detail is provided to enable those who review the information to make informed decisions on the programming of projects over the next several years. Please use the information provided to formulate plans, projects and questions. The Capital Improvement Plan can serve the community best by provoking thoughts and actions. This document was developed by the Finance Department with assistance of all city departments. I want to especially thank all those involved in the development of the Capital Improvement Plan and especially Steve Stadler, Public Works Director, Nate Stanley, City Engineer, Kersten Elverum, Planning and Economic Development Director, and Christine Harkess, Finance Director for their hard work and dedication. 1 Page City Manager's Message 1 Table of Contents 2 Introduction Introduction and Purpose 5 Program Descriptions Utilities Program 6 Transportation Program 7 Parks, Forestry, and Pavilion Program 9 General Public Buildings Program 10 Economic Development 12 Sources of Funding Sources of Funding 15 Funding Source Abreviations 18 Summary of Impacts on Major Funding Sources 21 Cash Flow Statements Park Capital Improvement Fund 26 Capital Improvemetn Fund 27 Communication Fund 28 Municipal State Aid Fund 29 Permanent Improvement Revolving Fund (PIR)30 Water Utility Fund 31 Sewer Utility Fund 32 Storm Sewer Utiltiy Fund 33 Pavilion - Ice Arena Fund 34 Five-Year Project Summaries Projects by Year 37 Department Summary 40 Projects by Department 41 Funding Source Summary 44 Projects by Funding Source 45 Project Descriptions & Narratives General Public Buildings 51 Parks & Recreation 95 Streets 115 Street Improvement Map 117 Utilities 129 CAPITAL IMPROVEMENT PLAN 2017-2021 TABLE OF CONTENTS 2 Introduction 3 4 INTRODUCTION AND PURPOSE The Capital Improvement Plan is a flexible plan based upon long-range physical planning and financial projections, which schedules the major public improvements that may be incurred by the City over the next five years. Flexibility of the Capital Improvement Plan is established through annual review, and revision if necessary. The annual review assures that the program will become a continuing part of the budgetary process and that it will be consistent with changing demands as well as changing patterns in cost and financial resources. Funds are appropriated only for the first year of the program, which is then included in the annual budget. The Capital Improvement Plan serves as a tool for implementing certain aspects of the City's comprehensive plan; therefore, the program describes the overall objectives of City development, the relationship between projects with respect to timing and need, and the City's fiscal capabilities. The Capital Improvement Plan can help assure: 1. A systematic approach to planning and initiating capital projects affording the opportunity to plan the location, timing, and financing of needed public improvements; 2. The development of a realistic program of capital spending within the City's projected fiscal capability to finance such projects, avoiding sharp change in the tax levy or bonded indebtedness; 3. The coordination of public and private improvement projects permitting adequate time for design and engineering to eliminate duplication of effort and expense; 4. The expenditure of public funds that is compatible with the City's adopted Comprehensive Plan; 5. That the public is kept informed of the proposed future projects and expenditures; 6. That private investors are aware of the City's long-range development program so that they may guide their development in a way that is compatible with the City's program; 7. Aid in achieving federal and/or state participation by providing the necessary planning and lead time necessary for a successful application in addition to meeting prerequisites needed for certain federal and state grants. 5 PROGRAM DESCRIPTIONS In order to effectively plan for and manage the projects contained in a Capital Improvement Plan, it is necessary to group similar activities into "Program Categories". The City of Hopkins' activities are divided into four program categories which are 1) Utilities, 2) Transportation, 3) Parks, Forestry and Pavilion, and 4) General Public Buildings. The City also includes an outline of proposed expenditures for unscheduled projects. Program categories are explained in the following sections. UTILITIES PROGRAM Program Description: The Utilities Program includes the municipal water, municipal sanitary sewer, storm sewer and refuse systems. Program Goal: Provide reliable, efficient, and safe utility service to all parts of the City with a minimum of adverse effects on the environment. Subprograms: Water, sanitary sewer, storm sewer, and refuse service. I. Municipal Water System Subprogram (WA) A. Subprogram Goal: The goal of the Municipal Water System subprogram is to provide water in sufficient quantities at sufficient pressure, with a high degree of reliability and safety to all parts of the City so as to satisfy the normal demands of the general public for water while at the same time providing sufficient reserves in case of fire emergency or power outages. B. Objectives: 1. Water quality shall meet the purity standards of the Minnesota Department of Health. 2. Any hydrant on the system shall, under maximum condition, deliver no less than 500 gallons per minute with a residual pressure of 20 pounds per square inch. 3. The system shall be looped to provide maximum reliability. 4. The supply and storage system shall be designed and maintained to have maximum reliability. 6 II. Municipal Sanitary Sewer Subprogram (SA) A. Subprogram Goal: The goal of the Municipal Sanitary Sewer subprogram is to promote a healthful environment by collecting all sewage from existing and projected development in a sanitary and economic manner. B. Objectives: 1. Provide sewer lines of adequate size and grade to collect and transmit all discharge sewage. 2. Prevent sewage from overflowing into the natural environment. 3. Prevent sewage back-ups. 4. Encourage or promote connection of all generators of sewage to the Municipal system. 5. Meet the effluent and infiltration standards of the Metropolitan Waste Control Commission. III. Storm Sewer Subprogram (SS) A. Subprogram Goal: Manage and control surface and ground waters in order to protect the man-made and natural environment in a safe and efficient manner. B. Objectives: 1. Prevent flooding. 2. Prevent damage to property due to erosion. 3. Meet water quality standards established by the controlling regulatory law or authority. TRANSPORTATION PROGRAM Program Description: This program includes streets, walkways, traffic signs and signals, vehicular parking facilities, and street lighting. Program Goal: Provide for the safe and efficient movement of people and goods throughout the city. 7 Subprograms: Streets, Walkways/Sidewalks, Signs/Signals, Parking Facilities, and Street Lights. I. Streets Subprogram (ST) A. Subprogram Goal: The goal of the Streets subprogram is to provide safe, convenient, economic public streets to best facilitate the movement of vehicular traffic. B. Objectives: 1. Streets should be constructed with permanent surfaces, concrete curb and gutter, and with ancillary storm drainage, to standards established by the City. 2. Streets should be of a size and load capacity consistent with their functional classifications. 3. Timely major repair to preserve the basic capital investment in streets. II. Walkways/Sidewalks Subprogram (WS) A. Subprogram Goal: To provide a safe and convenient pedestrian system with incidental recreational benefits. III. Signs/Signals Subprogram (SI) A. Subprogram Goal: The goal of the Signs/Signals subprogram is to provide an efficient and orderly system of street and traffic signing so as to promote safe, convenient travel throughout the City. B. Objectives: 1. Signs and signals should be installed in conformity with the Minnesota Manual on Uniform Traffic Control Devices. 2. Periodic surveys and studies should be made to document the effectiveness of City signing patterns. IV. Parking Facilities Subprogram (PA) A. Subprogram Goal: To provide such supporting facilities as will promote maximum use of public parking spaces by employers, employees, customers, and visitors. 8 B. Objectives: 1. Provide parking facilities for present and anticipated needs of the City of Hopkins. V. Street Lights Subprogram (SL) A. Subprogram Goal: To provide a system of street lighting within the City that will promote safe and convenient vehicular and pedestrian travel on City Streets. B. Objectives: 1. To provide lighting at each street intersection within the City. 2. To provide mid-block street lighting in conformance with the City's street lighting policy, in order to provide equitable, cost efficient lighting. 3. To continually update the system so as to provide energy and cost efficient lighting. PARKS, FORESTRY AND PAVILION PROGRAM Program Description: This program includes community parks, neighborhood parks, open spaces, recreational structures and facilities. Program Goal: The goal of the Park and Recreation Program is to provide facilities for safe, stimulating, and comprehensive leisure time activities of Hopkins citizens. Subprograms: Neighborhood Facilities, Community Facilities I. Neighborhood Facilities Subprogram (NF) A. Subprogram Goals: To acquire ownership or use rights of park sites located to provide convenient walking access to all Hopkins citizens and to develop such sites to provide optimum recreational serviceability consistent with the preservation and enhancement of pleasing aesthetic qualities. B. Objectives: 1. Acquire property or use rights on those neighborhoods that do not have convenient walking access to neighborhood park facilities. 2. Develop neighborhood park facilities to meet the needs of various user groups. 9 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Preserve and enhance the aesthetic qualities of neighborhood parks. II. Community Facilities Subprogram (CF) A. Subprogram Goals: The goal of the Community Facilities subprogram is to develop, or acquire ownership or use rights of sites which serve the entire City and to provide facilities that serve community-wide needs. B. Objectives: 1. Acquire sites that have valuable and unique natural characteristics to preserve irreplaceable community resources. 2. Preserve by acquisition, gift, or other arrangement properties that have valuable historic-cultural qualities. 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Construct or acquire structures and facilities necessary to meet the changing needs of the community. GENERAL PUBLIC BUILDINGS PROGRAM Program Description: The General Public Buildings Program includes all municipal buildings except those provided for in the Utility and Park Facilities Program. Program Goal: Provide buildings that are adequate and convenient for the efficient accommodation of City functions. Subprograms: Administrative Offices, Maintenance Facilities, Fire Facilities, Community Center. I. Administrative Offices Subprogram (AO) A. Subprogram Goal: The goal of the Administrative Offices subprogram is to provide facilities for the efficient and safe conduct of legislative and administrative functions of the City. 10 B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of the City services. II. Maintenance Facilities Subprogram (MF) A. Subprogram Goal: The goal of the Maintenance Facilities subprogram is to provide facilities for the efficient and safe conduct of City maintenance functions. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of City services. III. Fire Facilities Subprogram (FF) A. Subprogram Goal: To provide a fire station, or stations, for storage of Fire Department equipment and for the training and meetings of volunteer fire fighters to provide prompt and efficient protection to life and property. B. Objectives: 1. Provide a maximum four-minute daytime and three-minute nighttime response to all points within the City. 2. Meet objective 1 through the use of volunteers. IV. Community Center Subprogram (CC) A. Subprogram Goal: To provide a community facility, or facilities, which meet the social, recreational, and cultural needs of all citizens, particularly senior citizens. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repairs. 11 2. Construct or acquire structures and facilities necessary to meet the changing needs of the City. 3. Upgrade facilities as necessary to provide for efficient, safe, and effective provision of City services. ECONOMIC DEVELOPMENT PROGRAM Program Description: This program includes redevelopment projects that have been identified through adopted plans and goals of the City of Hopkins. Program Goal: To facilitate the redevelopment of key sites in order to achieve the state objectives of the project. Objectives: 1. Elimination of blight or blighting conditions 2. Creation of jobs 3. Increase property value(s) 4. Catalyst of additional redevelopment 5. Environmental clean-up 6. Increase transit-oriented development around LRT stations 12 Sources of Funding 13 14 SOURCES OF FUNDING In order to fund the anticipated Capital Improvements, the City must draw upon a variety of sources. Many of these sources have a specific or "dedicated" purpose (i.e., the water utility fund will finance water main installation but not a street overlay). Therefore, it is important to identify the uses and limitations of the various revenue sources. CURRENT REVENUES - GENERAL FUND (CR) This represents funding from current year revenue collections in the General Fund that support operations and capital outlay expenditures. Revenue sources include property tax levies, state aid payments, and various permit and license fees. This source of funding is generally used only for operations and small capital purchases. GENERAL FUND RESERVES (GR) Reserves of the general fund are the funds remaining after subtracting cash flow and emergency amounts from the City's cash balance, sometimes referred to as "fund balance". The use of General Fund Reserves is not recommended for Capital Improvements without significant staff and Council review. COMMUNICATION (formerly Cable TV) FUND (CT) This funding source consists of franchise fees received from the local Cable TV company, in excess of the amounts earmarked for the access programming and commission budgets. Expenditures are limited to cable-related facilities, or must have a cable related purpose. ECONOMIC DEVELOPMENT FUND (ED) This funding source was established by the Housing and Redevelopment Authority (HRA) and the City of Hopkins, to provide funding for the purpose of promoting development and redevelopment within the City. The Economic Development fund is a revolving fund administered by the HRA, intended to provide an ongoing funding source used to reduce or extend the long term debt involved with development and redevelopment activities. The HRA reviews all proposed uses of this fund on an individual basis. GRANT-IN-AID (GA) This is aid received from either the Federal or State government. In many cases, grants are made on matching basis, which means the City shares a portion of the costs of the project being funded. 15 MUNICIPAL STATE AID STREETS (MS) This funding source represents funds received from the State of Minnesota to support construction and maintenance of State Aid classified municipal streets. State law defines the types and limits of State Aid Streets expenditures. PERMANENT IMPROVEMENT REVOLVING/GENERAL OBLIGATION BONDS (PI) Improvements with a life of several years may be financed from the proceeds of a General Obligation Bond Issue. Law limits the total debt that can be incurred under this method of financing. With some exception, General Obligation Bonds are generally subject to a referendum process. Examples of projects, which may not require a referendum, are those financed through the use of special assessments where at least 20 percent of the project cost is assessed to the benefiting property owners. The remaining portion not assessed can be financed through general obligation bonds repaid by a tax levy. PRIVATE SECTOR FUNDING (PF) This funding source consists primarily of payments made by developers for the purchase of land, the installation of water, sewer, or streets or other related expenditures. It can also refer to donations made to the City by individuals or groups. OTHER GOVERNMENTAL UNITS (GU) These are funds received from Hennepin County, adjacent communities, etc. for projects that also benefit a jurisdiction other than the City of Hopkins. REVENUE BONDS (RB) These are bonds issued for improvements made for specific revenue producing facility or operation. The debt incurred is repaid from the revenue generated by the facility. If the revenue generated is insufficient, then the difference becomes an annual obligation of the taxpayers and becomes an additional tax levy. These are generally not subject to referendum. REAL ESTATE SALES FUND (RE) This funding source consists primarily of funds built up from the sale of City owned property. To date, the fund has been used for building improvements. Because the sale of both general City property and park/recreation property are accumulated into this fund, earmarking a portion for recreational purposes may be justified. 16 SPECIAL ASSESSMENT (SA) A number of projects may be realistically financed using Special Assessment to pay the ultimate cost. Almost any project can potentially be financed using the assessment process. In each case it is necessary to make a determination that the assessed property will benefit by the amount of the assessment. The cost of street reconstruction is shared by the property owner and the City. Special assessments to individual properties are capped per city policy. Concurrent improvement costs to the utility systems are assumed by the respective utility funds. TAX INCREMENT FINANCING (TF) This funding source results from the tax value of new development that is "incrementally" greater than the existing tax value. Typically, bonds are sold based on the assumption that the higher tax receipts will retire the bonds. However, the use of TIF funds through a "pay as you go" method has become more common. This type of funding can be used for public improvements within a redevelopment district to support the goals of redevelopment, specifically the elimination of blighted conditions. Approval of the Hopkins HRA should be anticipated prior to the commitment of these funds. State law strictly regulates the use of these funds. WATER FUNDS (WF) Water funds consist of revenue generated from the sale of water. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. SANITARY SEWER FUNDS (SF) Sanitary sewer funds consist of revenue generated from charges made for sewage disposal. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. STORM SEWER UTILITY REVENUES (SU) Storm sewer funds consist of revenue generated by charging storm water drainage fee to parcels of land for the availability and use of municipal storm sewer facilities. Expenditures from this funding source are related to drainage facilities. PAVILION FUND (PA) Pavilion Funds consist of revenues generated from rental fees collected from users of the Pavilion. These funds are utilized to pay for operating, and capital expenditures. 17 Funding Sources Communication (formerly Cable TV) Fund CT Current Revenues – General Fund CR General Fund Reserves GR Economic Development Fund ED Grant-In-Aid GA Housing and Redevelopment Authority HRA Municipal State-Aid Streets MS Other Government Units GU Park Dedication Fund PDF Pavilion Fund PA Permanent Improvement Revolving/General Obligation Bonds PI Private Sector Funds PF Real Estate Sales Fund RE Revenue Bonds RB Sanitary Sewer Fund SF Special Assessment SA Storm Sewer Fund SU Tax Increment Financing TF Water Fund WF 18 Summary of Impacts on Major Funding Sources 19 20 SUMMARY OF PROJECT IMPACTS ON MAJOR FUNDING SOURCES CURRENT REVENUES/GENERAL FUND RESERVES Expenditures for 2016 are budgeted at an increase of 4.66% over the 2015 budget. The 2016 budget was compiled with an average 2% salary increase. The 2016 budget has no levy limits and the City will receive approximately $413,900 in LGA. The tax levy is the major source of revenues (82%) for the General Fund and therefore presents a challenge when levy limits are in place. Unassigned fund balance in the General Fund totals $5,439,799 at the end of 2015 and is projected to remain at that level for 2016 or increase slightly. The State Auditor’s Office recommends no less than five month of operating expenditures in reserves. For 2016 five months of expenditures would total $4,948,221 or 41.6%. At January 1, 2016 the unassigned fund balance was at 45.8% of budgeted expenditures. PERMANENT IMPROVEMENT REVOLVING FUND, (P.I.R.) - G.O. DEBT Funding from bonds is used to reimburse the P.I.R. fund for public improvement projects, which have been previously expended. The debt is funded by special assessment collections and city tax levies over a ten to fifteen year period. Bonds totaling $3,800,000 were sold in 2016 to fund the 2016 street improvement projects. The next bond sale is scheduled for 2017 and will be for the Park Valley and Peacefully Valley neighborhood street projects. These bonds are expected to total approximately $7,700,000. The P.I.R. fund has completed substantial projects over the last three and this pace is expected to continue with scheduled projects for 2017 totaling $7,742,8000 and future projects in the years 2018-2021 totaling over $17 million. Projects scheduled for 2017 include the Park Valley, Peaceful Valley street reconstruction projects, Eight Avenue Artery project, pedestrian and bicycle access improvements, Blake Road corridor improvements along with street overlay and street sign management programs. The funding is provided for these projects by special assessments and PIR/Bonding. In the years 2017-2021 as mentioned above, the city has an aggressive residential street improvement schedule planned, all of which will require bonding. MUNICIPAL STATE AID FUND Funding for municipal state aid road projects comes from state MSA funding and is drawn down as projects are done. State funding is not sufficient for current planned projects as the City has been aggressive in doing MSA projects. In the queue for reimbursement is a request for is the Shady Oak project. In late 2014 we received an advance on the Shady Oak project which essentially cleared up our receivable backlog for Excelsior Blvd and Minnetonka Mills Road. This leaves Shady Oak Road as the only project in the funding queue. Currently the only MSA project scheduled is lighting, landscaping and street improvements on County Road 3 from Shady Oak Road to Meadowbrook Road. This is programed for 2021. 21 CAPITAL IMPROVEMENT FUND Funding for these improvements comes from a general tax levy that was implemented in 2005. Upon approval of the Financial Management Plan the levy was scaled back in 2015 to allow for other needs to take precedence. The levy is restored in 2016 and increased in 2017. Projects scheduled in 2017 total $76,500 and include upgrades to the public works lunchroom, planning for the city hall lobby upgrade, and Activity Center gym enhancements. Beginning in 2018 projects exceeds available funding, and therefore an interfund loan will be considered with a 4- year payback. The projects currently are placed in the CIP but will not be done if funding is not secured. PARK IMPROVEMENT FUND The source of funding for this fund is development fees charged to developers for park development, in addition to franchise fees from gas and electric services. The franchise fees are expected to supply approximately $295,000 to the fund for much needed park projects. Developer payments are uncertain as they are dependent on future development and redevelopment in the city, however there are two projects in the works that will result in developer fees over the next few years. Projects scheduled for 2017 total $1,586,5000 and include improvements for Burnes, Hilltop, Maetzold, and Interlachen Parks along with improvements to Shady Oak Beach. WATER FUND Implementing the rates as proposed in the Utility Master Plan (UMP) in 2017 along with a bond sale in 2017 provide the funding needed for projects scheduled for 2017. Bonds will need to be sold each year thereafter in which there are water projects associated with the residential street improvement program. Projects planned for 2017 include $1,500,000 in water main improvements done in conjunction with street improvements, and water improvements along the Eight Avenue Artery. The public works facility improvement project annual transfer of $45,000 was reinstated in 2014 and goes until 2023. The City along with their financial advisor prepared a comprehensive rate study which will be implemented on January 1, 2017. The city is implementing a tiered rate structure that is a significant change from past practice. Tiered rates will allow the city to comply with MN Department of Natural Resource requirements for conservation pricing of rates and provide funds for operations, debt service and capital outlay. SANITARY SEWER FUND Implementing the rates as proposed in the Utility Master Plan (UMP) in 2017 along with a bond sale in 2017 provide the funding needed for projects scheduled for 2017. Bonds will need to be sold each year thereafter in which there are water projects associated with the residential street improvement program. 22 Projects planned for 2017 include $1,300,000 in sewer main improvements done in conjunction with street improvements and along the Eight Avenue Artery along with reconstruction of Lift Station No. 7.. In addition to the scheduled capital expenditures, the Metropolitan Waste Control Commission is projecting annual increases in its disposal charges to local governments. The public works facility improvement project annual transfer of $50,000 was reinstated in 2014 and goes until 2023. The City along with their financial advisor prepared a comprehensive rate study which will be implemented on January 1, 2017. Rates will be increasing from $4.30 to $5.81 per $1,000 gallons of water used. This rate increase will provide funds for operations, debt service and capital outlay. STORM SEWER FUND Bonds will be sold in 2015 for the 2015 storm water management project. These bonds issues along with current revenues should provide the needed funding for scheduled projects. Bonds will need to be sold in 2016 and each year thereafter in which there are water projects associated with the residential street improvement program. Projects planned for 2017 include $600,000 in sewer main improvements done in conjunction with street improvements, Westbrook Way/Smetana Road drainage improvements and alley repairs for storm water management. The public works facility improvement project will cost the storm sewer enterprise $25,000 a year for twenty years (2004–2023). The most recent rate increase pursuant to the 2007 Utility Master Plan was done in 2009. This rate increase is expected to support the storm sewer system well into the future and currently no additional rates increases are proposed. PAVILION FUND This facility built in 1990 is starting to need repairs and replacement to areas that are heavily used; capital projects scheduled for 2017 include $140,000 for the Pavilion roof replacement and $200,000 in engineering fees to prepare plans and specs for the refrigeration system replacement which is scheduled for 2018. In 2018-2021 facility projects totaling $2,717,000 will be needed. A major project coming up is the replacement of the refrigeration system 2018 at a cost of $2.4 million. A Financial Management Plan was developed in 2014 to address the growing capital needs of the Pavilion along with other funds. A levy was put in place for 2015 and 2016 to address the growing capital needs and may be continued in the future depending on the various funds levy needs. 23 Cash Flow Statements 24 25 PARK CAPITAL IMPROVEMENTS FUND (301)11/16/2016 Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 141,306 258,547 1,595,722 1,566,394 1,337,686 770,616 728,035 Revenues: Taxes (from matured Park Bonds) Interest 8,743 4,266 47,872 46,992 40,131 23,118 21,841 Dedication fees 0 0 0 0 Moline Apts 180,000 Village Apts 120,000 Cold Storage Site Redevelopment 300,000 Joint Rec refunds 6,000 6,000 6,000 6,000 6,000 6,000 Franchise Fees (gas/elec) 2014 incr 87,148 85,300 85,300 85,300 85,300 85,300 85,300 Franchise Fees (gas/elec) 2012 incr 206,227 210,000 210,000 210,000 210,000 210,000 210,000 Transfer in Franchise Fees 316,970 Bond Proceeds 1,504,382 1,150,000 1,200,000 Hennepin County Grant Cottageville Park Donations 34,689 BWSR Grant 425,250 CDBG Funds 180,000 PIR Funding (Transfer In)225,000 Water Funding (Transfer In)37,500 Sewer Funding (Transfer In)37,500 Storm Sewer Funding (Transfer In)265,000 Donations - general 989 Donations - benches Total Revenues 2,372,489 2,592,475 1,669,172 648,292 341,431 324,418 323,141 Expenditures: C.I.P. Projects 101,269 858,300 1,586,500 210,000 691,500 150,000 40,000 Cottageville Property Acquisition Cottageville Park Playground 338,835 Cottageville Park House Demo 12,107 Cottageville Park Improvements 1,796,036 450,000 Cottageville Park Pavilion 380,000 Bond Payment Contribution (2015 Bonds)10,000 10,000 10,000 10,000 10,000 10,000 Bond Payment Contribution (2016 Bonds)95,000 100,000 100,000 100,000 100,000 Bond Payment Contribution (2017 Bonds)100,000 100,000 100,000 100,000 Skate Park commitment 7,000 7,000 7,000 7,000 7,000 7,000 7,000 Total Expenditures 2,255,248 1,255,300 1,698,500 877,000 908,500 367,000 257,000 Working Capital Year End 258,547 1,595,722 1,566,394 1,337,686 770,616 728,035 794,176 26 FACILITIES & BUILDINGS 11/16/2016 CAPITAL IMPROVEMENTS FUND (305) Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 255,974 67,621 (265,588) 67,912 60,252 12,553 4,616 Revenues: Interest 1,991 338 0 340 301 63 23 Transfers from General Fund 125,000 100,000 100,000 100,000 100,000 100,000 Transfers from Enterprise Funds 400,000 Transfer from Real Estate Fund 128,697 Interfund Loan 350,000 Tax Levy (red per FMP)52,311 125,000 310,000 100,000 100,000 100,000 100,000 Total Revenues 182,999 650,338 410,000 550,340 200,301 200,063 200,023 Expenditures: C.I.P. Projects 371,352 983,547 76,500 558,000 223,000 118,000 45,000 Repay Interfund Loan 25,000 90,000 150,000 Transfer to General Fund Total Expenditures 371,352 983,547 76,500 558,000 248,000 208,000 195,000 W orking Capital Year End 67,621 (265,588) 67,912 60,252 12,553 4,616 9,639 27 COMMUNICATIONS (Cable TV) - WORKING CAPITAL PROJECTIONS Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 490,071 532,952 542,372 533,381 496,272 504,295 507,488 Revenues: Franchise Fees 232,667 225,000 225,000 225,000 225,000 225,000 225,000 Franchise Fees - PEG Fees 35,059 30,000 30,000 30,000 30,000 30,000 30,000 Interest 6,047 2,132 2,169 2,134 1,985 2,017 2,030 Total Revenues 273,773 257,132 257,169 257,134 256,985 257,017 257,030 Expenditures: Expense 143,972 148,292 152,740 157,323 162,042 166,903 171,911 Transfer Out 86,920 86,920 86,920 86,920 86,920 86,920 86,920 Capital Outlay - 12,500 26,500 50,000 - - - Total Expenditures 230,892 247,712 266,160 294,243 248,962 253,823 258,831 Change in available funds 42,881 9,420 (8,991) (37,109) 8,023 3,194 (1,801) Working Capital Ending Year 532,952 542,372 533,381 496,272 504,295 507,488 505,688 11/16/2016 28 11/16/2016 MUNICIPAL STATE AID FUND (302) Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Bal 513,074 422,235 424,346 426,467 428,600 830,743 1,234,897 Revenues: State MSA Funds, projects 600,766 0 0 0 400,000 400,000 400,000 State MSA Advance Interest Earnings 18,630 2,111 2,122 2,132 2,143 4,154 6,174 Hennepin County -SOR Land Reimb Shady Oak Rd - Land Sale proceeds Bond issue Total Revenues 619,396 2,111 2,122 2,132 402,143 404,154 406,174 Transfer Out for Projects CIP State Aid Projects Highway 7 & 5th Ave Traffic Signal Shady Oak Rd - Co Rd 61 542,662 Shady Oak Rd ROW Purchase Shady Oak Rd Land Acqusition Mainstreet Rehabilitation 109,935 ARTery - 8th Ave S County Road 3 - EB 700,000 Sixth St S (11th - 12th Ave) Landscape - Excelsior Blvd Median 25,424 Misc Expenses 32,214 Total Expenditures 710,235 0 0000700,000 Working Capital Ending Balance 422,235 424,346 426,467 428,600 830,743 1,234,897 941,071 includes cash, interest rcvbl, & A/P 29 Cash Flow Analysis P.I.R. FUND (501)11/16/2016 Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 2,785,317 442,413 422,657 364,757 246,274 91,289 18,654 Revenues: Property Taxes 1,260 Special Assessment Revenues - from levy 53,803 55,000 50,000 50,000 50,000 50,000 55,000 Special Assessment Revenues - Prepaid County Grant 122,929 State Gas Tax 120,554 Interest 43,183 4,424 1,902 1,641 1,108 411 84 Bond Proceeds 5,361,851 3,800,000 7,700,000 4,300,000 4,800,000 4,200,000 4,300,000 Total Revenues 5,703,580 3,859,424 7,751,902 4,351,641 4,851,108 4,250,411 4,355,084 Expenditures: C.I.P. Projects 6,338,523 2,505,000 5,678,800 3,365,300 3,290,300 2,220,000 2,245,000 C.I.P. Projects - Special Assm 1,310,000 2,064,000 900,000 1,500,000 1,885,000 1,885,000 Transfers for SA Debt collected thru Assm Debt Service Transfers - 2010A - Imprv 61,358 64,180 67,002 69,824 80,794 83,045 69,238 Debt Service Transfers (prepaids to DS funds) Debt Fund - Zion Special Assessments 22,482 Transfer Out - Bond Proceeds to Enterprise Funds 1,399,121 Transfer for Cottageville Park 225,000 Total Expenditures 8,046,484 3,879,180 7,809,802 4,470,124 5,006,094 4,323,045 4,334,238 Working Capital Year End 442,413 422,657 364,757 246,274 91,289 18,654 39,500 Total Projects Scheduled (CIP & SA) 6,338,523 3,815,000 7,742,800 4,265,300 4,790,300 4,105,000 4,130,000 30 WATER FUND - WORKING CAPITAL PROJECTION 11/16/2016 Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 73,581 (176,360) (100,308) 283,577 830,552 1,351,182 1,839,135 Revenues: Operating Revenues 1,347,992 1,401,911 2,035,905 2,147,880 2,266,014 2,390,644 2,522,130 Other 166,245 165,235 172,272 179,661 187,418 195,564 204,116 Interest 2,555 0 0 0 0 0 0 Grants/Other Govt Funding Gain on Sale of Asset Trsansfer In - Bond Proceeds 496,275 Bond Issuance 2,200,000 1,700,000 1,550,000 1,760,000 1,500,000 1,500,000 Total Revenues 2,013,066 3,767,146 3,908,177 3,877,541 4,213,432 4,086,208 4,226,246 Expenditures: Operation Expense 1,396,476 1,111,244 1,150,027 1,190,249 1,231,969 1,275,245 1,320,140 Other Exp - bond issuance-fiscal fee Other Exp - int on current bonds 50,003 0 0 0 Other Exp - int on refunded bonds Other Exp - int on 2009 bonds 21,350 19,725 17,887 15,963 13,900 11,600 Other Exp - int on 2012 bonds 12,529 11,629 10,729 9,829 8,929 7,979 Other Exp - int on 2013 bonds 16,431 15,431 14,381 13,281 12,181 11,081 Other Exp -est interest on Future Bonds 13,000 153,000 258,000 328,000 438,000 Equipment Replacement Items 35,000 222,000 0 0 Capital Improvements 376,710 2,270,000 1,700,000 1,550,000 1,768,000 1,510,000 1,500,000 Principal Bond payment Principal Bond payment - refunded 180,000 Principal Bond pymnt - 2009 debt 50,000 50,000 50,000 55,000 55,000 55,000 60,000 Principal Bond pymnt - 2012 debt 40,000 45,000 45,000 45,000 45,000 45,000 50,000 Principal Bond pymnt - 2013 debt 50,000 50,000 50,000 55,000 55,000 55,000 55,000 Transfer for 2014A Debt Payment 17,800 17,800 17,800 17,800 17,800 17,800 17,800 Principal Bond pymnt - Future Debt 3,740 44,680 71,520 89,960 112,200 Transfer Out - Cottageville Park 37,500 Capital Lease (PW Facility) (1)45,000 45,000 45,000 45,000 45,000 45,000 45,000 Total Expenditures 2,243,489 3,691,094 3,524,292 3,330,566 3,692,802 3,598,255 3,078,600 Change in available funds (230,423)76,052 383,885 546,975 520,630 487,953 1,147,646 Inventory change (16,182) Bond Premium/Discount Exp (3,335) Working Capital Ending Year (176,360)(100,308) 283,577 830,552 1,351,182 1,839,135 2,986,781 (1) Capital Lease moved to Storm Sewer - back to water fund in 2014 Rate History (water/sprinkler) 1984 $0.85 1993 $1.05 1997 $1.10 2000 $1.20 2005 $1.40 Per Utility Master Plan (10/07) 2008 $1.65 2009 $1.86 2010 $1.90 2011 $1.94/2.40 - not incr, left at $1.90 2012 $1.96 / 2.40 2013 $2.02 / 2.40 2014 $2.10 / 2.50 2015 $2.18 / 2.60 2017 Tiered Rate Structure Implemented 31 SEWER FUND - WORKING CAPITAL PROJECTION 11/16/2016 Actual Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 116,280 385,285 575,986 664,282 1,247,100 1,797,676 2,444,650 Revenues: Operating Revenues 2,172,278 2,496,600 2,917,804 3,078,283 3,247,589 3,426,206 3,614,648 Grants/Other Govt Funding Other 150 20,000 20,000 20,000 20,000 20,000 0 Interest 2,270 963 1,440 1,661 3,118 4,494 6,112 Transfer In - Bond Proceeds 297,004 Bond Issuance 0 650,000 1,300,000 1,000,000 1,000,000 760,000 750,000 Total Revenues 2,471,701 3,167,563 4,239,244 4,099,944 4,270,707 4,210,700 4,370,760 Expenditures: Operation Expense 519,685 589,319 609,053 629,484 650,634 672,533 695,207 MWCC Charges (3% inflation) 1,321,360 1,361,001 1,401,831 1,443,886 1,487,203 1,531,819 1,577,774 Other - Bond Issuance-fiscal fees Interest Expense 39,084 26,575 24,463 22,187 19,825 17,200 14,300 Interest Expense - 2012 Debt 2,749 2,549 2,349 2,149 1,949 1,749 Interest Expense - 2013 Debt 9,318 8,719 8,119 7,519 6,919 6,319 Interest Expense - Future Debt 19,500 57,200 83,300 107,402 122,306 Equipment Replacement Items 33,600 531,000 0 Capital Improvements 106,249 762,000 1,300,000 1,025,000 1,053,000 760,000 750,000 Principal Bond payment (2009)60,000 65,000 65,000 65,000 70,000 70,000 75,000 Principal Bond payment (2012)10,000 10,000 10,000 10,000 10,000 10,000 10,000 Principal Bond payment (2013)30,000 30,000 30,000 30,000 30,000 30,000 30,000 Transfer for 2014A Debt Payment 17,800 17,800 17,800 17,800 17,800 17,800 17,800 Principal Bond payments Future Deb 0 0 43,333 130,000 196,600 263,200 Transfer Out - Cottageville Park 37,500 Capital Lease (PW Facility) (1)50,000 50,000 50,000 50,000 50,000 50,000 50,000 Total Expenditures 2,191,680 2,976,862 4,150,948 3,517,125 3,720,131 3,563,726 3,228,148 Change in available funds 280,021 190,701 88,296 582,819 550,575 646,974 1,142,611 Inventory change (9,424) Bond Premium/Discount Exp (1,592) Working Capital Ending Year 385,285 575,986 664,282 1,247,100 1,797,676 2,444,650 3,587,261 (1) Capital Lease moved to Storm Sewer - back in fund in 2014 Rate History 1983 $1.50 1989 $1.75 1991 $2.00 1993 $2.50 1999 $2.25 Rate DECREASE 2006 $2.50 rate increase Per Utility Master Plan (10/07) 2008 $2.70 2009 $3.10 2010 $3.40 2011 $3.70 - act 3.60 2012 $3.75 2013 $3.90 2014 $4.10 2015 $4.30 Rates per 2016 Utility FMP 2017 $5.81 2018 $6.12 2019 $6.46 2020 $6.82 32 STORM SEWER FUND - WORKING CAPITAL PROJECTION Projected Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year 508,676 755,174 1,171,790 1,459,343 1,684,310 898,580 1,137,846 Revenues: Operating Revenues 799,306 799,306 799,306 799,306 799,306 799,306 799,306 Other 6,236 5,000 5,000 5,000 5,000 5,000 5,000 Interest 8,149 1,888 2,929 3,648 4,211 2,246 2,845 Transfer In - PY Cottageville Park Exp 282,119 Transfer In - Bond Proceeds 605,843 Bond Issuance 500,000 900,000 350,000 500,000 700,000 700,000 Total Revenues 1,701,653 1,306,194 1,707,235 1,157,954 1,308,517 1,506,552 1,507,151 Expenditures: Operation Expense 135,296 138,002 140,762 143,577 146,449 149,378 152,365 Other - Bond Issuance-fiscal fees Bond Interest - existing 27,901 Bond Interest - 2009 refunded bonds Bond Interest - 2010 bonds 13,623 12,485 11,173 9,629 7,805 5,765 Bond Interest - 2012 bonds 5,281 4,881 4,481 4,081 3,681 3,281 Bond Interest - 2013 bonds 7,338 6,888 6,388 5,888 5,388 4,888 Interest Expense - Future Debt 15,000 41,000 48,700 60,200 76,700 Capital Outlay (per ERP) 000000 Cottageville Property purchase Cottageville Park Storm Water Mgmt Capital Improvements 752,892 561,000 1,026,000 471,000 1,592,000 710,000 700,000 2009 Principal Bond payment 125,000 2010 Principal Bond payment 70,000 70,000 70,000 70,000 75,000 80,000 80,000 2012 Principal Bond payment 20,000 20,000 20,000 20,000 20,000 20,000 20,000 2013 Principal Bond payment 20,000 20,000 25,000 25,000 25,000 25,000 25,000 Transfer for 2014A Debt Payment 14,334 14,334 14,334 14,334 14,334 14,334 14,334 Principal Bond payments Future Debt 0 0 33,333 93,333 116,667 150,001 Transfer Out - Cottageville Park 265,000 Capital Lease - PW Facility (1)25,000 25,000 25,000 25,000 25,000 25,000 25,000 Total Expenditures 1,455,424 889,578 1,419,683 932,986 2,094,247 1,267,287 1,030,633 Change in available funds 246,229 416,616 287,552 224,968 (785,731) 239,266 476,517 Inventory change 413 Bond Premium/Discount Exp (net)(144) Working Capital Ending Year 755,174 1,171,790 1,459,343 1,684,310 898,580 1,137,846 1,614,363 Rate History (per month) 1989 $4.75 per quarter 1991 $6.00 per quarter 1992 $2.50 1993 $3.00 1998 $3.20 1999 $4.00 2006 $4.50 2009 $5.00 11/16/2016 33 PAVILION - ICE ARENA - WORKING CAPITAL PROJECTIONS 11/16/2016 Projected Projected Projected Projected Projected Projected Projected 2015 2016 2017 2018 2019 2020 2021 Working Capital Beginning Year (45,591) 20,731 (54,646) (327,645) 440,042 258,406 131,101 Revenues: Operating Revenues 392,306 356,000 460,449 483,471 507,645 533,027 559,679 Leases Levy per FMP 64,160 65,000 - 65,000 65,000 65,000 65,000 Other 5,925 31,100 20,000 20,000 20,000 20,000 10,000 Interest Bond Proceeds 3,300,000 Transfer In Total Revenues 462,391 452,100 480,449 3,868,471 592,645 618,027 634,679 Expenditures: Operation Expense 373,218 379,852 391,248 402,985 415,075 427,527 440,353 Capital Outlay - ERP - - - - - - - Capital Improvements - 125,000 340,000 2,676,000 41,000 - - Equip Certif - principal 20,000 20,000 20,000 20,000 20,000 20,000 20,000 Equip Certif - interest 2,550 2,625 2,200 1,800 1,400 1,000 600 Payment on Interfund Loan - - Bond Repayment 296,806 296,806 296,806 Total Expenditures 395,768 527,477 753,448 3,100,785 774,281 745,333 757,759 Change in available funds 66,623 (75,377) (272,999) 767,686 (181,636) (127,305) (123,080) Bond Premium/Discount Exp (net) (301) Working Capital Ending Year 20,731 (54,646) (327,645) 440,042 258,406 131,101 8,021 34 Five Year Project Summaries 35 36 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN PROJECTS BY YEAR 2017 2021thru Project Name Department Project # Priority Project Cost 2017 09-CIP-CH030City Hall Lobby Upgrade n/a 15,000City Hall Administration 14-CIP-AC004Activity Center - Dishwasher 4 15,000Comm Svcs - Activity Center 17-CIP-AC037Activity Center - Room/Gym Enhancements 1 25,000Comm Svcs - Activity Center 08-CIP-AR013Arts Center - Replace Rooftop HVAC Units n/a 320,000Comm Svcs - Arts Center 14-CIP-AR003Arts Center - Paint Theatre 2 15,000Comm Svcs - Arts Center 16-CIP-AR002Arts Center - Jaycee Studio Curtain System 2 30,000Comm Svcs - Arts Center 17-CIP-AR003Arts Center - Lighting Improvements 2 12,200Comm Svcs - Arts Center 17-CIP-AR006Arts Center - Door Handles and Locks 1 10,000Comm Svcs - Arts Center 13 CIP-CM001Technology Improvement - Council Chambers & Studio n/a 23,000Comm Svcs - Communications 09-CIP-PV026Pavilion Roof Replacement 1 140,000Pavilion 16-CIP-PV327Pavilion - Refrigeration System - Engineering Fees n/a 200,000Pavilion 16-CIP-B006PW - Public Works Lunchroom 1 25,000Public Works: Bldg/Equip Serv 08-CIP-P014Hilltop Park - Play Equipment n/a 120,000Public Works: Parks 13-CIP-P043Burnes Park - 2-5 Play Equipment n/a 100,000Public Works: Parks 13-CIP-P062Maetzold Field - Play Equipment n/a 100,000Public Works: Parks 14-CIP-P002Burnes Park Warming House & Splash Pad n/a 1,200,000Public Works: Parks 16-CIP-P003Interlachen Park - Portable Hockey Boards n/a 50,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 6,600,000Public Works: Streets/Traffic 01-CIP-S103Citywide Concrete Alleys n/a 80,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 15-CIP-S001Blake Road Corridor Improvements n/a 2,648,800Public Works: Streets/Traffic 16-CIP-S041Street Overlay Improvements n/a 275,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 01-CIP-S503Eighth Avenue Artery Project n/a 5,313,000Public Works: Transportation 16-CIP-S045Westbrook Way/Smetana Rd Drainage Improvements n/a 100,000Public Works: Transportation 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 21,000Public Works: Utilities 16-CIP-U015Reconstruct Lift Station No. 7 n/a 700,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 50,000Recreation 18,233,000Total for 2017 2018 09-CIP-CH030City Hall Lobby Upgrade n/a 260,000City Hall Administration 08-CIP-AC018Activity Center - Replace Gymnasium Roof n/a 105,000Comm Svcs - Activity Center 08-CIP-AC024Activity Center - Raspberry Room Roof Replacement n/a 80,000Comm Svcs - Activity Center 09-CIP-AC031Activity Center - Lower Roof Replacement n/a 80,000Comm Svcs - Activity Center 09-CIP-AR027Arts Center - Replace Lobby Carpet n/a 52,000Comm Svcs - Arts Center 14-CIP-AR004Arts Center - Remodel Administrative Offices 2 50,000Comm Svcs - Arts Center 13 CIP-CM001Technology Improvement - Council Chambers & Studio n/a 15,000Comm Svcs - Communications 08-CIP-FD019Fire - Replace Carpet and Apparatus Floor Finish n/a 28,000Fire 07-CIP-PV313Pavilion Restroom/Lobby Floor Improvement n/a 35,000Pavilion 07-CIP-PV314Pavilion Overhead Door Improvement n/a 65,000Pavilion 10-CIP-PV317Pavilion - Skate Tile Replacement n/a 75,000Pavilion 10-CIP-PV318Pavilion - Refrigeration Equip & Arena Floor Repl n/a 2,400,000Pavilion 13-CIP-PV324Pavilion Entry and Lobby Door Replacement 3 25,000Pavilion Thursday, November 17, 2016 37 Project Name Department Project # Priority Project Cost 13-CIP-PV325Pavilion - Paint Exterior Building 1 28,000Pavilion 14-CIP-PV010Pavilion Painting the Arena Ceiling and Bar Joist 1 48,000Pavilion 08-CIP-PD016Replace Carpet - Police Station n/a 40,000Police 08-CIP-P010Park Valley - Play Equipment n/a 120,000Public Works: Parks 08-CIP-P011Burnes Park - Resurface Tennis Courts n/a 20,000Public Works: Parks 13-CIP-P044Oakes Park - Tennis Courts n/a 20,000Public Works: Parks 13-CIP-P055Elmo Park - 2-5 Play Equipment n/a 50,000Public Works: Parks 16-CIP-P002Cottageville Park - Phase III Improvements n/a 450,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 3,450,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 15-CIP-S001Blake Road Corridor Improvements n/a 7,949,900Public Works: Streets/Traffic 16-CIP-S041Street Overlay Improvements n/a 300,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 01-CIP-S502Light Rail Transit Stations (3)n/a 1,500,000Public Works: Transportation 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 21,000Public Works: Utilities 17,311,900Total for 2018 2019 09-CIP-CH029City Hall Roof Replacement n/a 115,000City Hall Administration 16-CIP-AC035Activity Center - Former Historical Society Area 1 50,000Comm Svcs - Activity Center 17-CIP-AC039Activity Center - Bathroom Improvements 1 15,000Comm Svcs - Activity Center 17-CIP-AC041Activity Center - Raspberry Room Enhancements 4 25,000Comm Svcs - Activity Center 17-CIP-AR004Arts Center - Theater Curtains 3 80,000Comm Svcs - Arts Center 13-CIP-PV321Pavilion Mezzanine Rooftop Unit Replacement 1 30,000Pavilion 13-CIP-PV322Pavilion HHS Team Room Rooftop Unit Repl 1 11,000Pavilion 08-CIP-B023Public Works - Replace Overhead Doors n/a 90,000Public Works: Bldg/Equip Serv 13-CIP-P050Pavilion Addion/Warming House n/a 600,000Public Works: Parks 13-CIP-P056Harley Hopkins Park - Warming House n/a 30,000Public Works: Parks 13-CIP-P057Harley Hopkins Park - Lighting n/a 50,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 5,575,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 15-CIP-S001Blake Road Corridor Improvements n/a 7,449,900Public Works: Streets/Traffic 16-CIP-S041Street Overlay Improvements n/a 325,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 01-CIP-S502Light Rail Transit Stations (3)n/a 3,181,000Public Works: Transportation 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 22,000Public Works: Utilities 08-CIP-U001Lift Station # 4 n/a 160,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 35,000Recreation 17,888,900Total for 2019 2020 08-CIP-CH010City Hall - Replace Carpeting n/a 58,000City Hall Administration 09-CIP-AR028Art Center - Various Rooms and Hallway (Carpet) n/a 21,500Comm Svcs - Arts Center 16-CIP-AR006Arts Center - Seal Floors in Restroom & Kitchen 1 15,000Comm Svcs - Arts Center 08-CIP-B021Public Works - Replace Wash Bay Roof n/a 50,000Public Works: Bldg/Equip Serv 09-CIP-B034Public Works Garage Roof Replacement n/a 50,000Public Works: Bldg/Equip Serv 05-CIP-P202Central Park Tennis Courts n/a 20,000Public Works: Parks 13-CIP-P059Interlachen Park - Lighting n/a 50,000Public Works: Parks 13-CIP-P063Maetzold Field - Pavilion n/a 80,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 6,660,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Overlay Improvements n/a 350,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 7,399,500Total for 2020 Thursday, November 17, 2016 38 Project Name Department Project # Priority Project Cost 2021 08-CIP-AR006Arts Center-Replace Office Carpet - Stages Theatre n/a 20,225Comm Svcs - Arts Center 08-CIP-B123Fire Station - Replace Boilers n/a 45,000Fire 13-CIP-P058Hilltop - Picnic Shelter n/a 40,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 6,660,000Public Works: Streets/Traffic 01-CIP-S104County Road 3 n/a 2,300,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Overlay Improvements n/a 375,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 9,485,225Total for 2021 GRAND TOTAL 70,318,525 Thursday, November 17, 2016 39 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN DEPARTMENT SUMMARY 2017 2021thru Total2017 2018 2019 2020 2021Department City Hall Administration 448,00015,000 260,000 115,000 58,000 Comm Svcs - Activity Center 395,00040,000 265,000 90,000 Comm Svcs - Arts Center 625,925387,200 102,000 80,000 36,500 20,225 Comm Svcs - Communications 38,00023,000 15,000 Fire 73,00028,000 45,000 Pavilion 3,057,000340,000 2,676,000 41,000 Police 40,00040,000 Public Works: Bldg/Equip Serv 215,00025,000 90,000 100,000 Public Works: Parks 3,100,0001,570,000 660,000 680,000 150,000 40,000 Public Works: Streets/Traffic 51,223,6009,648,800 11,744,900 13,394,900 7,055,000 9,380,000 Public Works: Transportation 10,094,0005,413,000 1,500,000 3,181,000 Public Works: Utilities 924,000721,000 21,000 182,000 Recreation 85,00050,000 35,000 18,233,000 17,311,900 17,888,900 7,399,500 9,485,225 70,318,525TOTAL Thursday, November 17, 201640 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN PROJECTS BY DEPARTMENT 2017 2021thru Total2017 2018 2019 2020 2021Department Project# Priority City Hall Administration 08-CIP-CH010 58,00058,000City Hall - Replace Carpeting n/a 09-CIP-CH029 115,000115,000City Hall Roof Replacement n/a 09-CIP-CH030 275,00015,000 260,000City Hall Lobby Upgrade n/a 448,00015,000 260,000 115,000 58,000City Hall Administration Total Comm Svcs - Activity Center 08-CIP-AC018 105,000105,000Activity Center - Replace Gymnasium Roof n/a 08-CIP-AC024 80,00080,000Activity Center - Raspberry Room Roof Replacement n/a 09-CIP-AC031 80,00080,000Activity Center - Lower Roof Replacement n/a 14-CIP-AC004 15,00015,000Activity Center - Dishwasher 4 16-CIP-AC035 50,00050,000Activity Center - Former Historical Society Area 1 17-CIP-AC037 25,00025,000Activity Center - Room/Gym Enhancements 1 17-CIP-AC039 15,00015,000Activity Center - Bathroom Improvements 1 17-CIP-AC041 25,00025,000Activity Center - Raspberry Room Enhancements 4 395,00040,000 265,000 90,000Comm Svcs - Activity Center Total Comm Svcs - Arts Center 08-CIP-AR006 20,22520,225Arts Center-Replace Office Carpet - Stages Theatre n/a 08-CIP-AR013 320,000320,000Arts Center - Replace Rooftop HVAC Units n/a 09-CIP-AR027 52,00052,000Arts Center - Replace Lobby Carpet n/a 09-CIP-AR028 21,50021,500Art Center - Various Rooms and Hallway (Carpet)n/a 14-CIP-AR003 15,00015,000Arts Center - Paint Theatre 2 14-CIP-AR004 50,00050,000Arts Center - Remodel Administrative Offices 2 16-CIP-AR002 30,00030,000Arts Center - Jaycee Studio Curtain System 2 16-CIP-AR006 15,00015,000Arts Center - Seal Floors in Restroom & Kitchen 1 17-CIP-AR003 12,20012,200Arts Center - Lighting Improvements 2 17-CIP-AR004 80,00080,000Arts Center - Theater Curtains 3 17-CIP-AR006 10,00010,000Arts Center - Door Handles and Locks 1 625,925387,200 102,000 80,000 36,500 20,225Comm Svcs - Arts Center Total Comm Svcs - Communications 13 CIP-CM001 38,00023,000 15,000Technology Improvement - Council Chambers & Studio n/a 38,00023,000 15,000Comm Svcs - Communications Total Fire 08-CIP-B123 45,00045,000Fire Station - Replace Boilers n/a 08-CIP-FD019 28,00028,000Fire - Replace Carpet and Apparatus Floor Finish n/a 73,00028,000 45,000Fire Total Pavilion 07-CIP-PV313 35,00035,000Pavilion Restroom/Lobby Floor Improvement n/a Thursday, November 17, 201641 Total2017 2018 2019 2020 2021Department Project# Priority 07-CIP-PV314 65,00065,000Pavilion Overhead Door Improvement n/a 09-CIP-PV026 140,000140,000Pavilion Roof Replacement 1 10-CIP-PV317 75,00075,000Pavilion - Skate Tile Replacement n/a 10-CIP-PV318 2,400,0002,400,000Pavilion - Refrigeration Equip & Arena Floor Repl n/a 13-CIP-PV321 30,00030,000Pavilion Mezzanine Rooftop Unit Replacement 1 13-CIP-PV322 11,00011,000Pavilion HHS Team Room Rooftop Unit Repl 1 13-CIP-PV324 25,00025,000Pavilion Entry and Lobby Door Replacement 3 13-CIP-PV325 28,00028,000Pavilion - Paint Exterior Building 1 14-CIP-PV010 48,00048,000Pavilion Painting the Arena Ceiling and Bar Joist 1 16-CIP-PV327 200,000200,000Pavilion - Refrigeration System - Engineering Fees n/a 3,057,000340,000 2,676,000 41,000Pavilion Total Police 08-CIP-PD016 40,00040,000Replace Carpet - Police Station n/a 40,00040,000Police Total Public Works: Bldg/Equip Serv 08-CIP-B021 50,00050,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 90,00090,000Public Works - Replace Overhead Doors n/a 09-CIP-B034 50,00050,000Public Works Garage Roof Replacement n/a 16-CIP-B006 25,00025,000PW - Public Works Lunchroom 1 215,00025,000 90,000 100,000Public Works: Bldg/Equip Serv Total Public Works: Parks 05-CIP-P202 20,00020,000Central Park Tennis Courts n/a 08-CIP-P010 120,000120,000Park Valley - Play Equipment n/a 08-CIP-P011 20,00020,000Burnes Park - Resurface Tennis Courts n/a 08-CIP-P014 120,000120,000Hilltop Park - Play Equipment n/a 13-CIP-P043 100,000100,000Burnes Park - 2-5 Play Equipment n/a 13-CIP-P044 20,00020,000Oakes Park - Tennis Courts n/a 13-CIP-P050 600,000600,000Pavilion Addion/Warming House n/a 13-CIP-P055 50,00050,000Elmo Park - 2-5 Play Equipment n/a 13-CIP-P056 30,00030,000Harley Hopkins Park - Warming House n/a 13-CIP-P057 50,00050,000Harley Hopkins Park - Lighting n/a 13-CIP-P058 40,00040,000Hilltop - Picnic Shelter n/a 13-CIP-P059 50,00050,000Interlachen Park - Lighting n/a 13-CIP-P062 100,000100,000Maetzold Field - Play Equipment n/a 13-CIP-P063 80,00080,000Maetzold Field - Pavilion n/a 14-CIP-P002 1,200,0001,200,000Burnes Park Warming House & Splash Pad n/a 16-CIP-P002 450,000450,000Cottageville Park - Phase III Improvements n/a 16-CIP-P003 50,00050,000Interlachen Park - Portable Hockey Boards n/a 3,100,0001,570,000 660,000 680,000 150,000 40,000Public Works: Parks Total Public Works: Streets/Traffic 01-CIP-S101 28,945,0006,600,000 3,450,000 5,575,000 6,660,000 6,660,000Residential Street Improvements and Utilities n/a 01-CIP-S103 80,00080,000Citywide Concrete Alleys n/a 01-CIP-S104 2,300,0002,300,000County Road 3 n/a 13-CIP-S040 125,00025,000 25,000 25,000 25,000 25,000Pedestrian & Bicycle Access Improvements n/a 15-CIP-S001 18,048,6002,648,800 7,949,900 7,449,900Blake Road Corridor Improvements n/a 16-CIP-S041 1,625,000275,000 300,000 325,000 350,000 375,000Street Overlay Improvements n/a 16-CIP-S042 100,00020,000 20,000 20,000 20,000 20,000Street Sign Management n/a 51,223,6009,648,800 11,744,900 13,394,900 7,055,000 9,380,000Public Works: Streets/Traffic Total Thursday, November 17, 201642 Total2017 2018 2019 2020 2021Department Project# Priority Public Works: Transportation 01-CIP-S502 4,681,0001,500,000 3,181,000Light Rail Transit Stations (3) n/a 01-CIP-S503 5,313,0005,313,000Eighth Avenue Artery Project n/a 16-CIP-S045 100,000100,000Westbrook Way/Smetana Rd Drainage Improvements n/a 10,094,0005,413,000 1,500,000 3,181,000Public Works: Transportation Total Public Works: Utilities 01-CIP-U002 64,00021,000 21,000 22,000Storm Drainage System Maintenance - Alley Repairs n/a 08-CIP-U001 160,000160,000Lift Station # 4 n/a 16-CIP-U015 700,000700,000Reconstruct Lift Station No. 7 n/a 924,000721,000 21,000 182,000Public Works: Utilities Total Recreation 16-CIP-R003 85,00050,000 35,000Shady Oak Beach Improvements 3 85,00050,000 35,000Recreation Total GRAND TOTAL 70,318,52518,233,000 17,311,900 17,888,900 7,399,500 9,485,225 Thursday, November 17, 201643 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN FUNDING SOURCE SUMMARY 2017 thru 2021 TotalSource2017 2018 2019 2020 2021 AC - Arts Center Fund 625,925387,200 102,000 80,000 36,500 20,225 CI - Capital Improvement Fund 1,020,50076,500 558,000 223,000 118,000 45,000 CT - Cable Franchise Fees 76,50026,500 50,000 GU - Other Governmental Units 19,234,2004,047,500 5,954,600 7,632,100 1,600,000 MS - Municipal State Aid Streets 700,000700,000 PA - Pavilion Fund 3,057,000340,000 2,676,000 41,000 PDF- Park Dedication Fund 3,128,0001,586,500 660,000 691,500 150,000 40,000 PI - PIR/General Obligation Bonds 16,799,4005,678,800 3,365,300 3,290,300 2,220,000 2,245,000 RF - Refuse Fund 28,00018,000 10,000 SA - Special Assessment 8,234,0002,064,000 900,000 1,500,000 1,885,000 1,885,000 SF - Sanitary Sewer Fund 4,888,0001,300,000 1,025,000 1,053,000 760,000 750,000 SU - Storm Sewer Fund 4,499,0001,026,000 471,000 1,592,000 710,000 700,000 WF - Water Fund 8,028,0001,700,000 1,550,000 1,768,000 1,510,000 1,500,000 18,233,000 17,311,900 17,888,900 7,399,500 9,485,225 70,318,525GRAND TOTAL Thursday, November 17, 2016 44 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN PROJECTS BY FUNDING SOURCE 2017 2021thru TotalSourceProject# Priority 2017 2018 2019 2020 2021 AC - Arts Center Fund 08-CIP-AR006 20,22520,225Arts Center-Replace Office Carpet - Stages Theatre n/a 08-CIP-AR013 320,000320,000Arts Center - Replace Rooftop HVAC Units n/a 09-CIP-AR027 52,00052,000Arts Center - Replace Lobby Carpet n/a 09-CIP-AR028 21,50021,500Art Center - Various Rooms and Hallway (Carpet)n/a 14-CIP-AR003 15,00015,000Arts Center - Paint Theatre 2 14-CIP-AR004 50,00050,000Arts Center - Remodel Administrative Offices 2 16-CIP-AR002 30,00030,000Arts Center - Jaycee Studio Curtain System 2 16-CIP-AR006 15,00015,000Arts Center - Seal Floors in Restroom & Kitchen 1 17-CIP-AR003 12,20012,200Arts Center - Lighting Improvements 2 17-CIP-AR004 80,00080,000Arts Center - Theater Curtains 3 17-CIP-AR006 10,00010,000Arts Center - Door Handles and Locks 1 625,925387,200 102,000 80,000 36,500 20,225AC - Arts Center Fund Total CI - Capital Improvement Fund 08-CIP-AC018 105,000105,000Activity Center - Replace Gymnasium Roof n/a 08-CIP-AC024 80,00080,000Activity Center - Raspberry Room Roof Replacement n/a 08-CIP-B021 10,00010,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 08-CIP-B123 45,00045,000Fire Station - Replace Boilers n/a 08-CIP-CH010 58,00058,000City Hall - Replace Carpeting n/a 08-CIP-FD019 28,00028,000Fire - Replace Carpet and Apparatus Floor Finish n/a 08-CIP-PD016 40,00040,000Replace Carpet - Police Station n/a 09-CIP-AC031 80,00080,000Activity Center - Lower Roof Replacement n/a 09-CIP-B034 50,00050,000Public Works Garage Roof Replacement n/a 09-CIP-CH029 115,000115,000City Hall Roof Replacement n/a 09-CIP-CH030 236,50011,500 225,000City Hall Lobby Upgrade n/a 14-CIP-AC004 15,00015,000Activity Center - Dishwasher 4 16-CIP-AC035 50,00050,000Activity Center - Former Historical Society Area 1 16-CIP-B006 25,00025,000PW - Public Works Lunchroom 1 17-CIP-AC037 25,00025,000Activity Center - Room/Gym Enhancements 1 17-CIP-AC039 15,00015,000Activity Center - Bathroom Improvements 1 17-CIP-AC041 25,00025,000Activity Center - Raspberry Room Enhancements 4 1,020,50076,500 558,000 223,000 118,000 45,000CI - Capital Improvement Fund Total CT - Cable Franchise Fees 09-CIP-CH030 38,5003,500 35,000City Hall Lobby Upgrade n/a 13 CIP-CM001 38,00023,000 15,000Technology Improvement - Council Chambers & Studio n/a 76,50026,500 50,000CT - Cable Franchise Fees Total GU - Other Governmental Units Thursday, November 17, 2016 45 TotalSourceProject# Priority 2017 2018 2019 2020 2021 01-CIP-S104 1,600,0001,600,000County Road 3 n/a 01-CIP-S502 1,904,0001,904,000Light Rail Transit Stations (3) n/a 01-CIP-S503 2,745,0002,745,000Eighth Avenue Artery Project n/a 15-CIP-S001 12,928,2001,269,000 5,954,600 5,704,600Blake Road Corridor Improvements n/a 16-CIP-R003 57,00033,500 23,500Shady Oak Beach Improvements 3 19,234,2004,047,500 5,954,600 7,632,100 1,600,000GU - Other Governmental Units Total MS - Municipal State Aid Streets 01-CIP-S104 700,000700,000County Road 3 n/a 700,000700,000MS - Municipal State Aid Streets Total PA - Pavilion Fund 07-CIP-PV313 35,00035,000Pavilion Restroom/Lobby Floor Improvement n/a 07-CIP-PV314 65,00065,000Pavilion Overhead Door Improvement n/a 09-CIP-PV026 140,000140,000Pavilion Roof Replacement 1 10-CIP-PV317 75,00075,000Pavilion - Skate Tile Replacement n/a 10-CIP-PV318 2,400,0002,400,000Pavilion - Refrigeration Equip & Arena Floor Repl n/a 13-CIP-PV321 30,00030,000Pavilion Mezzanine Rooftop Unit Replacement 1 13-CIP-PV322 11,00011,000Pavilion HHS Team Room Rooftop Unit Repl 1 13-CIP-PV324 25,00025,000Pavilion Entry and Lobby Door Replacement 3 13-CIP-PV325 28,00028,000Pavilion - Paint Exterior Building 1 14-CIP-PV010 48,00048,000Pavilion Painting the Arena Ceiling and Bar Joist 1 16-CIP-PV327 200,000200,000Pavilion - Refrigeration System - Engineering Fees n/a 3,057,000340,000 2,676,000 41,000PA - Pavilion Fund Total PDF- Park Dedication Fund 05-CIP-P202 20,00020,000Central Park Tennis Courts n/a 08-CIP-P010 120,000120,000Park Valley - Play Equipment n/a 08-CIP-P011 20,00020,000Burnes Park - Resurface Tennis Courts n/a 08-CIP-P014 120,000120,000Hilltop Park - Play Equipment n/a 13-CIP-P043 100,000100,000Burnes Park - 2-5 Play Equipment n/a 13-CIP-P044 20,00020,000Oakes Park - Tennis Courts n/a 13-CIP-P050 600,000600,000Pavilion Addion/Warming House n/a 13-CIP-P055 50,00050,000Elmo Park - 2-5 Play Equipment n/a 13-CIP-P056 30,00030,000Harley Hopkins Park - Warming House n/a 13-CIP-P057 50,00050,000Harley Hopkins Park - Lighting n/a 13-CIP-P058 40,00040,000Hilltop - Picnic Shelter n/a 13-CIP-P059 50,00050,000Interlachen Park - Lighting n/a 13-CIP-P062 100,000100,000Maetzold Field - Play Equipment n/a 13-CIP-P063 80,00080,000Maetzold Field - Pavilion n/a 14-CIP-P002 1,200,0001,200,000Burnes Park Warming House & Splash Pad n/a 16-CIP-P002 450,000450,000Cottageville Park - Phase III Improvements n/a 16-CIP-P003 50,00050,000Interlachen Park - Portable Hockey Boards n/a 16-CIP-R003 28,00016,500 11,500Shady Oak Beach Improvements 3 3,128,0001,586,500 660,000 691,500 150,000 40,000PDF- Park Dedication Fund Total PI - PIR/General Obligation Bonds 01-CIP-S101 8,475,0002,000,000 1,000,000 1,825,000 1,825,000 1,825,000Residential Street Improvements and Utilities n/a 01-CIP-S103 16,00016,000Citywide Concrete Alleys n/a Thursday, November 17, 2016 46 TotalSourceProject# Priority 2017 2018 2019 2020 2021 01-CIP-S502 1,325,0001,000,000 325,000Light Rail Transit Stations (3) n/a 01-CIP-S503 1,963,0001,963,000Eighth Avenue Artery Project n/a 13-CIP-S040 125,00025,000 25,000 25,000 25,000 25,000Pedestrian & Bicycle Access Improvements n/a 15-CIP-S001 3,170,4001,379,800 1,020,300 770,300Blake Road Corridor Improvements n/a 16-CIP-S041 1,625,000275,000 300,000 325,000 350,000 375,000Street Overlay Improvements n/a 16-CIP-S042 100,00020,000 20,000 20,000 20,000 20,000Street Sign Management n/a 16,799,4005,678,800 3,365,300 3,290,300 2,220,000 2,245,000PI - PIR/General Obligation Bonds Total RF - Refuse Fund 08-CIP-B021 10,00010,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 28,00018,000 10,000RF - Refuse Fund Total SA - Special Assessment 01-CIP-S101 8,170,0002,000,000 900,000 1,500,000 1,885,000 1,885,000Residential Street Improvements and Utilities n/a 01-CIP-S103 64,00064,000Citywide Concrete Alleys n/a 8,234,0002,064,000 900,000 1,500,000 1,885,000 1,885,000SA - Special Assessment Total SF - Sanitary Sewer Fund 01-CIP-S101 3,000,000500,000 500,000 500,000 750,000 750,000Residential Street Improvements and Utilities n/a 01-CIP-S502 150,000150,000Light Rail Transit Stations (3)n/a 01-CIP-S503 100,000100,000Eighth Avenue Artery Project n/a 08-CIP-B021 10,00010,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 08-CIP-U001 160,000160,000Lift Station # 4 n/a 15-CIP-S001 750,000375,000 375,000Blake Road Corridor Improvements n/a 16-CIP-U015 700,000700,000Reconstruct Lift Station No. 7 n/a 4,888,0001,300,000 1,025,000 1,053,000 760,000 750,000SF - Sanitary Sewer Fund Total SU - Storm Sewer Fund 01-CIP-S101 2,850,000600,000 350,000 500,000 700,000 700,000Residential Street Improvements and Utilities n/a 01-CIP-S502 952,000952,000Light Rail Transit Stations (3) n/a 01-CIP-S503 305,000305,000Eighth Avenue Artery Project n/a 01-CIP-U002 64,00021,000 21,000 22,000Storm Drainage System Maintenance - Alley Repairs n/a 08-CIP-B021 10,00010,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 15-CIP-S001 200,000100,000 100,000Blake Road Corridor Improvements n/a 16-CIP-S045 100,000100,000Westbrook Way/Smetana Rd Drainage Improvements n/a 4,499,0001,026,000 471,000 1,592,000 710,000 700,000SU - Storm Sewer Fund Total WF - Water Fund 01-CIP-S101 6,450,0001,500,000 700,000 1,250,000 1,500,000 1,500,000Residential Street Improvements and Utilities n/a 01-CIP-S502 350,000350,000Light Rail Transit Stations (3) n/a 01-CIP-S503 200,000200,000Eighth Avenue Artery Project n/a 08-CIP-B021 10,00010,000Public Works - Replace Wash Bay Roof n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 15-CIP-S001 1,000,000500,000 500,000Blake Road Corridor Improvements n/a Thursday, November 17, 2016 47 TotalSourceProject# Priority 2017 2018 2019 2020 2021 8,028,0001,700,000 1,550,000 1,768,000 1,510,000 1,500,000WF - Water Fund Total 70,318,52518,233,000 17,311,900 17,888,900 7,399,500 9,485,225GRAND TOTAL Thursday, November 17, 2016 48 Project Descriptions And Narratives 49 50 General Public Buildings 51 52 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact City Manager 2017 2021 thru Department City Hall Administration Description Replace carpeting Project #08-CIP-CH010 Priority n/a Justification Budget Impact/Other Useful LifeProject Name City Hall - Replace Carpeting Category Bldgs: Administrative Offices Type Improvement Future Total Project Cost:$58,000 Total2017 2018 2019 2020 2021Expenditures 58,00058,000Construction/Maintenance 58,000 58,000Total Total2017 2018 2019 2020 2021Funding Sources 58,00058,000CI - Capital Improvement Fund 58,000 58,000Total Thursday, November 17, 2016 53 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department City Hall Administration Description Build up roof on City Hall and Council Chambers Project #09-CIP-CH029 Priority n/a Justification Existing roof was installed in 1994, estimated replacement due in 2019 Budget Impact/Other Useful Life 25 years Project Name City Hall Roof Replacement Category Bldg: City Hall Type Improvement Future Total Project Cost:$115,000 Total2017 2018 2019 2020 2021Expenditures 115,000115,000Construction/Maintenance 115,000 115,000Total Total2017 2018 2019 2020 2021Funding Sources 115,000115,000CI - Capital Improvement Fund 115,000 115,000Total Thursday, November 17, 2016 54 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Asst City Manager 2017 2021 thru Department City Hall Administration Description Upgrade of City Hall Lobby, Entrance and Council Chambers. Timeline 2017- Architect would complete design. 2018 - Upgrade would be completed. City Hall Lobby and Internal Entrance Upgrade Originally proposed as part of the 2007 City Hall upgrade/Carpet project by Public Works. Project would include updating the entire lobby area and basic upgrades to match in the front entrance area. City Hall Exterior Entrance Facelift for the front of City Hall, removing large concrete structure and upgrading front of building including signage. Council Chambers Upgrade Renovation of the Council Chambers including updating wall décor, carpeting, audience chairs, and dias to meet current needs. Project #09-CIP-CH030 Priority n/a Justification City Hall has not had an upgrade since 1989. Current facilities are outdated and in need of facelift. City Hall Lobby Existing lobby is dated, ceiling tiles have yellowed and wall paper has numerous stains from years of service. Existing reception area does not functionally meet the demands of the position and requires dual workstations for working. City Hall Exterior Entrance Front of the building overhang and entrance is still the original 1960's design and is due for an upgrade to better meet our goals and to set an example for the community. Council Chambers Upgrade Current chamber is dated and due for a facelift. The current dias lacks storage space for necessary items such as microphones, ADA accessibility items, remotes, keyboards and general staff documents, additionally there is not large enough to seat staff that are currently expected to attend the meeting. Budget Impact/Other Variance from 20-year plan: Move project from 2016 to 2018 and adjust cost from $110,000 to $150,000. Technology upgrades in the Council Chambers should be included in the same time. One designer for all parts of the project would help ensure a cohesive design. Upgrading at once would reduce inconvenience period for residents and staff and may have additional cost savings. Useful Life 20 years Project Name City Hall Lobby Upgrade Category Bldg: City Hall Type Improvement Future Total Project Cost:$275,000 Total2017 2018 2019 2020 2021Expenditures 275,00015,000 260,000Construction/Maintenance 15,000 260,000 275,000Total Total2017 2018 2019 2020 2021Funding Sources 236,50011,500 225,000CI - Capital Improvement Fund 38,5003,500 35,000CT - Cable Franchise Fees 15,000 260,000 275,000Total Thursday, November 17, 2016 55 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Comm Svcs - Activity Center Description Existing roof was installed in 1989 and is at the end of its projected useful life. Portion is cost share with Raspberry Ridge Condo Assn. Project #08-CIP-AC018 Priority n/a Justification Roof was installed in 1989 and is at the end of its 25 year useful life. Budget Impact/Other Roof in good condition - move project from 2014 to 2016 and re-evaluate in 2 years. Moved again from 2016 to 2018 and all roof components will be done with one contract for better bids. Useful Life 25 years Project Name Activity Center - Replace Gymnasium Roof Category Buildings: Activity Center Type Improvement Future Total Project Cost:$105,000 Total2017 2018 2019 2020 2021Expenditures 105,000105,000Construction/Maintenance 105,000 105,000Total Total2017 2018 2019 2020 2021Funding Sources 105,000105,000CI - Capital Improvement Fund 105,000 105,000Total Thursday, November 17, 2016 56 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Comm Svcs - Activity Center Description Built up asphalt roofing system covering Raspberry Rooms, Craft Room and Hallways at the Activity Center Project #08-CIP-AC024 Priority n/a Justification Existing roof was replaced in 1992, Expected life is 25 years. Budget Impact/Other Inspection, repair and upkeep of roofing systems prevent deterioration of interior building structure and damage to interior components of building. Variance from 20 year plan: Moved from 2016 to 2018 and all roof components will be done with one contract for better bids. Useful LifeProject Name Activity Center - Raspberry Room Roof Replacement Category Buildings: Activity Center Type Improvement Future Total Project Cost:$80,000 Total2017 2018 2019 2020 2021Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total2017 2018 2019 2020 2021Funding Sources 80,00080,000CI - Capital Improvement Fund 80,000 80,000Total Thursday, November 17, 2016 57 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Comm Svcs - Activity Center Description Built up Roof on Activity Center Raspberry Rooms and Hallway. Project #09-CIP-AC031 Priority n/a Justification Existing roof was installed in 1992, estimated replacement due in 2017. Budget Impact/Other Variance from 20 year plan: Moved from 2017 to 2018 and all roof components will be done with one contract for better bids. Useful Life 25 years Project Name Activity Center - Lower Roof Replacement Category Buildings: Activity Center Type Improvement Future Total Project Cost:$80,000 Total2017 2018 2019 2020 2021Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total2017 2018 2019 2020 2021Funding Sources 80,00080,000CI - Capital Improvement Fund 80,000 80,000Total Thursday, November 17, 2016 58 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Susan Newville 2017 2021 thru Department Comm Svcs - Activity Center Description Dishwasher for the kitchen needed for daily operations of the Hopkins Activity Center and rentals. Project #14-CIP-AC004 Priority 4 Less Important Justification The present dishwasher was installed in 1990 and is not running at code in its present state. Budget Impact/Other Estimate salvage/resale value on replaced pieces: $200. Useful LifeProject Name Activity Center - Dishwasher Category Equipment Type Improvement Future Total Project Cost:$15,000 Total2017 2018 2019 2020 2021Expenditures 15,00015,000Construction/Maintenance 15,000 15,000Total Total2017 2018 2019 2020 2021Funding Sources 15,00015,000CI - Capital Improvement Fund 15,000 15,000Total Thursday, November 17, 2016 59 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Activity Ctr Director 2017 2021 thru Department Comm Svcs - Activity Center Description Improve the looks and function of the former Historical Society area. Reconfigure walls, storage, sinks and cabinets, tables, chairs, audio visual, lighting, floor covering, wall covering, etc. Project #16-CIP-AC035 Priority 1 Urgent Justification Once the Historical Society moves to its new home on Mainstreet the Hopkins Activity Center will expand its program offers into this additional space. Room improvements will be made including lighting, sound system, acoustics, media, office and room configurations, wall and floor covering. Budget Impact/Other Variance from 20 year plan - New item 2016 - Historical Society not yet moved into new space, moving project from 2017 to 2019 and reduce budget from $100,000 to $50,000 Useful LifeProject Name Activity Center - Former Historical Society Area Category Buildings: Activity Center Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000CI - Capital Improvement Fund 50,000 50,000Total Thursday, November 17, 2016 60 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Activity Ctr Director 2017 2021 thru Department Comm Svcs - Activity Center Description Continuation of the enhancement project in the Multi-purpose Room/Gymnasium. 1. Place acoustical panels and lighting around the perimeter of the room 2. Sound and media system Project #17-CIP-AC037 Priority 1 Urgent Justification The room is used more and more for classes, parties, receptions and larger meetings. The physical appearance of the room has not had any improvements since 1990. Painting and tile replacement is scheduled for August 2016, but funds did not allow the acoustical panels and lighting to be done. Acoustical panels are needed to keep the sound from bouncing about the room especially during presentations, meetings, and classes making it hard to hear. The sound system has not been upgraded since the facility opened in 1981. The speakers are muffled making it more difficult for our aging population to understand speech when attending classes, speakers, and presentations. We have found that when we can clearly amplify an instructor or presenter's voice, allowing participants to hear well, that people will continue to engage in activity. People who stay engaged in activities stay healthier. People who can not hear instructors and presenters will tend to stay away and not engage in activity. We also have to make it easier for instructors and presenters to use amplifying devises, as they too are resistant to using equipment that inhibits their ability to do what they need to do. Improving the media in this room improves our ability to rent the room to outside sources. Budget Impact/Other 2016 - reduced original request from $100,000 to $25,000 as significant upgrades were done in 2016 and 2016 Useful Life 25 years Project Name Activity Center - Room/Gym Enhancements Category Buildings: Activity Center Type Improvement Future Total Project Cost:$25,000 Total2017 2018 2019 2020 2021Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total2017 2018 2019 2020 2021Funding Sources 25,00025,000CI - Capital Improvement Fund 25,000 25,000Total Thursday, November 17, 2016 61 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Activity Ctr Director 2017 2021 thru Department Comm Svcs - Activity Center Description Improve both the men's and women's bathrooms with new wallcoverings, flooring, ceiling tiles, lighting, vanities, stall enclosures, dispensers, toilets. Project #17-CIP-AC039 Priority 1 Urgent Justification The bathrooms have not had any improvements since the 1990 building improving project except for touch up painting of the walls and stall walls. The stall walls are scratched and chipped. The ceiling tiles are not within code. The dispensers need to be replaced due to their sharp edges. Toilets could be taller to accommodate the primary population we serve here. Budget Impact/Other Useful Life 20 years Project Name Activity Center - Bathroom Improvements Category Buildings: Activity Center Type Improvement Future Total Project Cost:$15,000 Total2017 2018 2019 2020 2021Expenditures 15,00015,000Construction/Maintenance 15,000 15,000Total Total2017 2018 2019 2020 2021Funding Sources 15,00015,000CI - Capital Improvement Fund 15,000 15,000Total Thursday, November 17, 2016 62 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Activity Ctr Director 2017 2021 thru Department Comm Svcs - Activity Center Description Reconfigure this room to be used as an room for our numerous dance activities, as well as yoga, Tia Chi, Qigong, meeting space, etc. We would be making a wall in this room which will make a hallway and therefore have a legal exit for gym participants in case of an emergency. Project #17-CIP-AC041 Priority 4 Less Important Justification Right now anyone exiting the east side of the gym is exiting into a classroom and not a hallway. Therefore the number of people we can accommodate in the Multi-purpose/Gym is lower because we do not have the proper exits to accommodate bigger numbers of people using the gym. Making these changes will reconfigure the room to accommodate existing and new programing. Budget Impact/Other Useful LifeProject Name Activity Center - Raspberry Room Enhancements Category Buildings: Activity Center Type Improvement Future Total Project Cost:$25,000 Total2017 2018 2019 2020 2021Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total2017 2018 2019 2020 2021Funding Sources 25,00025,000CI - Capital Improvement Fund 25,000 25,000Total Thursday, November 17, 2016 63 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Remove and replace carpet and carpet base in Stages Theatre offices, ticket office and Facility Manager's office, and coat room and Arts Director office. 260 sq. yards x $48/yard = $12,480 Project #08-CIP-AR006 Priority n/a Justification Carpet is 13 years old as of 2010. Carpet will have exceeded its useful life. Carpet has separated from backing which has caused it to wrinkle and it can no longer be cleaned in these areas. Added Arts Director office (Susan's) guests do come in. It is visible to public - same vintage as facility office. Budget Impact/Other Note: Repeat project in 2021 at $20,225 Useful Life 10 years Project Name Arts Center-Replace Office Carpet - Stages Theatre Category Buildings: Arts Center Type Improvement Future Total Project Cost:$37,225 Total2017 2018 2019 2020 2021Expenditures 20,22520,225Construction/Maintenance 20,225 20,225Total Total2017 2018 2019 2020 2021Funding Sources 20,22520,225AC - Arts Center Fund 20,225 20,225Total Thursday, November 17, 2016 64 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Comm Svcs - Arts Center Description Replace rooftop heating and AC units that were installing in 1997. Useful life is 20 years. There are 15 total units from 25 tons to 5 tons Project #08-CIP-AR013 Priority n/a Justification Planned replacement at 20 years estimated useful life. Budget Impact/Other Useful LifeProject Name Arts Center - Replace Rooftop HVAC Units Category Buildings: Arts Center Type Improvement Future Total Project Cost:$320,000 Total2017 2018 2019 2020 2021Expenditures 320,000320,000Construction/Maintenance 320,000 320,000Total Total2017 2018 2019 2020 2021Funding Sources 320,000320,000AC - Arts Center Fund 320,000 320,000Total Thursday, November 17, 2016 65 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Replace the lobby carpet including staircases, second floor, elevator floor, coat room and dance studio dressing room. ESTIMATED PROJECT SHCEDULE: Future 2018 Project #09-CIP-AR027 Priority n/a Justification The Lobby carpet will be at the end of it's useful life in a high traffic area like the lobby. Budget Impact/Other Useful Life 10 years Project Name Arts Center - Replace Lobby Carpet Category Buildings: Arts Center Type Improvement Future Total Project Cost:$52,000 Total2017 2018 2019 2020 2021Expenditures 52,00052,000Construction/Maintenance 52,000 52,000Total Total2017 2018 2019 2020 2021Funding Sources 52,00052,000AC - Arts Center Fund 52,000 52,000Total Thursday, November 17, 2016 66 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Remove and replace carpet and carpet base in the Community Room, Green Room, West Main Floor Hallway, Conference Room and Dance Studio Dressing Rooms of the Art Center. 330 Sq. Yards x $48/yard = $15,840. ESTIMATED PROJECT SCHEDULE: Future - Repeat project in 2020 @ $21,500 Project #09-CIP-AR028 Priority n/a Justification Most of this project was approved for 2008, but scheduling constraints pushed the project to 2009. The carpet to be replaced is the original carpet - 13 years old -= and there are "runs" down to the carpet backing in the Community Room, Green Room and Hallway. The Community Room carpet loos especially poor, which as a result reflect poorly on the room when shown to perspective customers. Budget Impact/Other Useful LifeProject Name Art Center - Various Rooms and Hallway (Carpet)Category Buildings: Arts Center Type Improvement Future Total Project Cost:$37,500 Total2017 2018 2019 2020 2021Expenditures 21,50021,500Construction/Maintenance 21,500 21,500Total Total2017 2018 2019 2020 2021Funding Sources 21,50021,500AC - Arts Center Fund 21,500 21,500Total Thursday, November 17, 2016 67 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Co-Director 2017 2021 thru Department Comm Svcs - Arts Center Description Paint house of theatre which hasn't been done since 1997. This will require professional painters and estimated 65 gallons of paint to cover the house walls. Project #14-CIP-AR003 Priority 2 Very Important Justification It is time to spruce up the paint. With the addition of new carpeting in 2013 and new seating in 2015, it is perfect timing to paint the walls so that they are not only clean and fresh, but coordinate in color with the rest of the theater house décor. Budget Impact/Other Did not complete in 2015, moving project forward Useful Life 15 years Project Name Arts Center - Paint Theatre Category Buildings: Arts Center Type Improvement Future Total Project Cost:$15,000 Total2017 2018 2019 2020 2021Expenditures 15,00015,000Construction/Maintenance 15,000 15,000Total Total2017 2018 2019 2020 2021Funding Sources 15,00015,000AC - Arts Center Fund 15,000 15,000Total Thursday, November 17, 2016 68 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Co-Director 2017 2021 thru Department Comm Svcs - Arts Center Description Remodel administrative offices on second floor, moving the conference room to room 206 and combing room 204 and 205 into one office area. Adding one work station. Project #14-CIP-AR004 Priority 2 Very Important Justification While this does not significantly increase office square footage, it does create a more flexible space that will accommodate the addition on one more work station. This in in anticipation for the need for an additional office worker, whether paid or volunteer, within two years. Budget Impact/Other Variance in 20 year plan - move project from 2016 to 2018. Useful LifeProject Name Arts Center - Remodel Administrative Offices Category Buildings: Arts Center Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000AC - Arts Center Fund 50,000 50,000Total Thursday, November 17, 2016 69 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Co-Director 2017 2021 thru Department Comm Svcs - Arts Center Description Add retractable curtain system to Jacyee Studio walls Project #16-CIP-AR002 Priority 2 Very Important Justification This will aid in increasing the flexibility and decdreasing turn-around time between events in this multi-purpose room. /the curtains can be drawn to cover walls during performances but be retractable to the room corners for receptions/meetings, etc. This means the walls can be painted a lighter color, making the room more attractive for rentals. Budget Impact/Other 2016 - adjusting from 2016 to 2017 due to unexpected repairs Useful Life 15 years Project Name Arts Center - Jaycee Studio Curtain System Category Buildings: Arts Center Type Improvement Future Total Project Cost:$30,000 Total2017 2018 2019 2020 2021Expenditures 30,00030,000Construction/Maintenance 30,000 30,000Total Total2017 2018 2019 2020 2021Funding Sources 30,00030,000AC - Arts Center Fund 30,000 30,000Total Thursday, November 17, 2016 70 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Co-Director 2017 2021 thru Department Comm Svcs - Arts Center Description Sani Glaze restrooms off lobby and in Green Room (floors and walls). Sani Glaze floor in the catering kitchen. Maintenance of floors each year Project #16-CIP-AR006 Priority 1 Urgent Justification Process makes it easier to keep these areas clean and attractive. Budget Impact/Other Originallin in 2012 CIP and then cancelled. Re-worked for 2016. Completed 2016 Useful LifeProject Name Arts Center - Seal Floors in Restroom & Kitchen Category Buildings: Arts Center Type Improvement Future Total Project Cost:$25,000 Total2017 2018 2019 2020 2021Expenditures 15,00015,000Construction/Maintenance 15,000 15,000Total Total2017 2018 2019 2020 2021Funding Sources 15,00015,000AC - Arts Center Fund 15,000 15,000Total Thursday, November 17, 2016 71 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Replace bulbs with LED lighting in gallery and lobby, add track lighting in classrooms, replace cans and bulbs in floor lighting in theater balcony for safety. Project #17-CIP-AR003 Priority 2 Very Important Justification Replacing the bulbs with LED lights will help with Utility costs. The balcony can be quite dark when performances are taking place and the steps are a safety concern - improved lighting will address that concern. Budget Impact/Other Useful Life 10 years Project Name Arts Center - Lighting Improvements Category Buildings: Arts Center Type Improvement Future Total Project Cost:$12,200 Total2017 2018 2019 2020 2021Expenditures 12,20012,200Construction/Maintenance 12,200 12,200Total Total2017 2018 2019 2020 2021Funding Sources 12,20012,200AC - Arts Center Fund 12,200 12,200Total Thursday, November 17, 2016 72 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Replace main Theater front curtains Project #17-CIP-AR004 Priority 3 Important Justification Due to age of curtains, estimating they will need to be reaplced in 2019 Budget Impact/Other Useful Life 15 years Project Name Arts Center - Theater Curtains Category Buildings: Arts Center Type Improvement Future Total Project Cost:$80,000 Total2017 2018 2019 2020 2021Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total2017 2018 2019 2020 2021Funding Sources 80,00080,000AC - Arts Center Fund 80,000 80,000Total Thursday, November 17, 2016 73 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Arts Center Director 2017 2021 thru Department Comm Svcs - Arts Center Description Replace door knobs and locks on all Art Center doors. Estimating 25 new handles will be needed. Project #17-CIP-AR006 Priority 1 Urgent Justification Many of the door handles and locks are breaking down due to age and use. Budget Impact/Other Useful Life 10 years Project Name Arts Center - Door Handles and Locks Category Buildings: Arts Center Type Improvement Future Total Project Cost:$10,000 Total2017 2018 2019 2020 2021Expenditures 10,00010,000Construction/Maintenance 10,000 10,000Total Total2017 2018 2019 2020 2021Funding Sources 10,00010,000AC - Arts Center Fund 10,000 10,000Total Thursday, November 17, 2016 74 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Asst City Manager 2017 2021 thru Department Comm Svcs - Communication Description 2014 - Installation of surge protection and uninterruptible power supplies in the studio. 2015 - Upgrade equipment in the Council Chamber presentation table 2016 - Replace current document camera with high resolution camera. 2017 - Projection system 2018 - Sound system 2019 - Council chamber cameras Project #13 CIP-CM001 Priority n/a Justification 2014 - current and future technology improvements are processor based and are sensitive to power fluctuations 2015 - The current presentation switching configuration requires the control room operator to determine what is presented to the room. Presenters do not have much control over their presentations and outside presenters need to use the City computer system. The new equipment will allow the presenter to use their own equipment which will simplify the process while protecting the City's computer network. 2016 - The existing camera is standard definition. The new camera will be high resolution 2017 - Current projectors are 10 years old and low resolution. 2018 - Current ceiling speakers are old and need to be replaced. Lobby speakers have no volume control. 2019 - Current cameras will be 15 years old by 2019 and are standard definition. Replace with high definition cameras. Budget Impact/Other Useful Life 10 years Project Name Technology Improvement - Council Chambers & Studio Category Bldg: City Hall Type Improvement Future Total Project Cost:$95,000 Total2017 2018 2019 2020 2021Expenditures 38,00023,000 15,000Communications 23,000 15,000 38,000Total Total2017 2018 2019 2020 2021Funding Sources 38,00023,000 15,000CT - Cable Franchise Fees 23,000 15,000 38,000Total Thursday, November 17, 2016 75 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Fire Chief 2017 2021 thru Department Fire Description Replace boilers Project #08-CIP-B123 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Fire Station - Replace Boilers Category Buildings: Fire Facilities Type Improvement Future Total Project Cost:$45,000 Total2017 2018 2019 2020 2021Expenditures 45,00045,000Construction/Maintenance 45,000 45,000Total Total2017 2018 2019 2020 2021Funding Sources 45,00045,000CI - Capital Improvement Fund 45,000 45,000Total Thursday, November 17, 2016 76 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Fire Chief 2017 2021 thru Department Fire Description Replace carpet and apparatus floor finish systems. Carpet to be done in 2016 at an estimated cost of $28,000 Flooring to be done in 2018 at an estimated cost of $28,000 Project #08-CIP-FD019 Priority n/a Justification Planned replacement at end of estimated 10 year useful life. Classroom and 2nd and 3rd Floor entryway and lounge replacement, due to excessive use of classroom and lounge. FD spoke with Steve Stadler and he was ok with moving it up to 10 years from 15 years. Budget Impact/Other Original plan replacement was 15 years. Due to excessive use of classroom and lounge the life was moved to 10 years. Variance from 20 year plan: move floor portion of the project from 2016 to 2018. Useful Life 10 years Project Name Fire - Replace Carpet and Apparatus Floor Finish Category Buildings: Fire Facilities Type Improvement Future Total Project Cost:$56,000 Total2017 2018 2019 2020 2021Expenditures 28,00028,000Construction/Maintenance 28,000 28,000Total Total2017 2018 2019 2020 2021Funding Sources 28,00028,000CI - Capital Improvement Fund 28,000 28,000Total Thursday, November 17, 2016 77 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Remove current epoxy floor coating from the restroom floors and install ceramic floor tile in restrooms, lobby and entry to the Pavilion Project #07-CIP-PV313 Priority n/a Justification The current restroom coating is worn and chipping out, ceramic tile would improve aesthetics and provide a more sanitary surface. Budget Impact/Other Variance from 20 year plan - this project originally rescheduled for 2017 has moved back to 2018 and costs decreased from $45,000 to $35,000 Useful Life 15 years Project Name Pavilion Restroom/Lobby Floor Improvement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$87,000 Total2017 2018 2019 2020 2021Expenditures 35,00035,000Construction/Maintenance 35,000 35,000Total Total2017 2018 2019 2020 2021Funding Sources 35,00035,000PA - Pavilion Fund 35,000 35,000Total Thursday, November 17, 2016 78 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Remove and block in four of the six overhead doors on the west side of the Pavilion's arena with a portion to windows or glass block to allow for natural light in the arena. Install automatic openers on the remaining four overhead doors in the arena. Project #07-CIP-PV314 Priority n/a Justification Currently the overhead doors are seldom utilized and the removal and installation of glass block or windows will decrease the need for arena lighting and add to the arena aesthetics. Saving repairs and maintenance of the removed doors. Pavilion user groups have asked for this project. Budget Impact/Other Variance from 20 year plan - project costs increased from $40,000 to $65,000 and moved from 2016 to 2018. Potential savings on utilities and greater satisfaction from user groups with arena aesthetics. Useful Life 30 years Project Name Pavilion Overhead Door Improvement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$65,000 Total2017 2018 2019 2020 2021Expenditures 65,00065,000Construction/Maintenance 65,000 65,000Total Total2017 2018 2019 2020 2021Funding Sources 65,00065,000PA - Pavilion Fund 65,000 65,000Total Thursday, November 17, 2016 79 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Removal and replacement of existing ballast and membrane for both the north and south roof sections. Project #09-CIP-PV026 Priority 1 Urgent Justification Repairs made in 2005 extended the life of the roof but it is now 25 years old and has surpassed manufacturers recommendation for replacements. The current roof has leaks and given the current condition of the membrane more failures are expected. Budget Impact/Other Variance from 20 Year Plan - project moved from 2016 to 2017 Roof leaks can potentially be harmful to the steel roof deck and may cause damage to equipment and interior of Pavilion, impacting operations and adding cost to roof replacement. Useful Life 25 years Project Name Pavilion Roof Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$140,000 Total2017 2018 2019 2020 2021Expenditures 140,000140,000Construction/Maintenance 140,000 140,000Total Total2017 2018 2019 2020 2021Funding Sources 140,000140,000PA - Pavilion Fund 140,000 140,000Total Thursday, November 17, 2016 80 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Replace the Pavilions 5,000 Square Feet of Skate Tile. Project #10-CIP-PV317 Priority n/a Justification The skate tile is on a 15 year replacement cycle, the tile was last replaced in 2005. Given the volume of traffic and the wear shown since installation replacement is recommended by 2020. Also if dasher board system is replaced potential cutting and patching may occur adding expense to that project. If skate replacement is schedule to coincide with dasher board replacement it has savings potential for both projects. Budget Impact/Other Variance from 20 year plan - project moved up from 2020 to 2018. Cost remains the same. Useful Life 15 Project Name Pavilion - Skate Tile Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$75,000 Total2017 2018 2019 2020 2021Expenditures 75,00075,000Construction/Maintenance 75,000 75,000Total Total2017 2018 2019 2020 2021Funding Sources 75,00075,000PA - Pavilion Fund 75,000 75,000Total Thursday, November 17, 2016 81 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Replace the current R22 direct refrigeration system with a new indirect system using a environmental friendly refrigerant at a estimated cost of $1,575,000 . Remove existing concrete arena floor and refrigeration piping and replace new piping and concrete at a estimated cost of $500,000. Remove the existing arena dasher boards and replace with a new board system at a estimated cost of $175,000. Project #10-CIP-PV318 Priority n/a Justification The existing refrigeration system, arena floor, and dasher boards were installed when the building was built in 1990. Due to a federal mandate R22 refrigerate will not be manufactured after 2020, all new refrigeration equipment must use a ozone-friendly refrigerant. Manaufactureers have started to cease production of some of the replacement parts for our current R22 system making parts expensive and difficult to find. Due to the age of the arena floors piping it will start to develop leaks leading to costly repairs and may not readily accommodate a new type of refrigerant. The dasher boards would need to be removed to allow for the arena floor replacement. Reinstallation of the current boards would be more difficult due to the damage to the anchors that would occur during removal. The boards show signs of wear and bending from years of use and are in need of replacement. Budget Impact/Other Variance from 20 year plan - cost increased from $1,225,000 to $2,400,000 and project moved from 2020 to 2018. Possible resale of the existing dasher boards may offset some of the cost of a new dasher system. Useful Life 15 years Project Name Pavilion - Refrigeration Equip & Arena Floor Repl Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$2,400,000 Total2017 2018 2019 2020 2021Expenditures 2,400,0002,400,000Construction/Maintenance 2,400,000 2,400,000Total Total2017 2018 2019 2020 2021Funding Sources 2,400,0002,400,000PA - Pavilion Fund 2,400,000 2,400,000Total Thursday, November 17, 2016 82 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Purchase and installation of (3) rooftop HVAC units that supply heating and cooling to the Pavilions Mezzanine Project #13-CIP-PV321 Priority 1 Urgent Justification The current units were installed in 2003 and are at the end of their useful life. Budget Impact/Other Variance from 20 year plan - move project from 2018 to 2018 and increase cost from $24,500 to $30,000 Useful Life 15 years Project Name Pavilion Mezzanine Rooftop Unit Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$30,000 Total2017 2018 2019 2020 2021Expenditures 30,00030,000Construction/Maintenance 30,000 30,000Total Total2017 2018 2019 2020 2021Funding Sources 30,00030,000PA - Pavilion Fund 30,000 30,000Total Thursday, November 17, 2016 83 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Purchase and installation of (1) rooftop HVAC unit that supply's heating and cooling to the High School Hockey Team Rooms. Project #13-CIP-PV322 Priority 1 Urgent Justification The current unit was installed in 2004 and is at the end of its useful life. Budget Impact/Other Varfiance from 20 year plan - increase cost from $9,500 to $11,000 Useful Life 15 years Project Name Pavilion HHS Team Room Rooftop Unit Repl Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$11,000 Total2017 2018 2019 2020 2021Expenditures 11,00011,000Construction/Maintenance 11,000 11,000Total Total2017 2018 2019 2020 2021Funding Sources 11,00011,000PA - Pavilion Fund 11,000 11,000Total Thursday, November 17, 2016 84 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Purchase and install (10) doors, closers, and push bars to replace the current doors at the entrance to the Pavilion. Project #13-CIP-PV324 Priority 3 Important Justification The current doors were installed when the facility was built in 1990 and have exceeded their useful life. Budget Impact/Other Variance from 20 year plan - cost increased from $7,000 to $25,000 Useful Life 25 years Project Name Pavilion Entry and Lobby Door Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$25,000 Total2017 2018 2019 2020 2021Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total2017 2018 2019 2020 2021Funding Sources 25,00025,000PA - Pavilion Fund 25,000 25,000Total Thursday, November 17, 2016 85 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Hire a painting contractor to pain the Pavilions exterior. Project #13-CIP-PV325 Priority 1 Urgent Justification The exterior block of the facility has not been painted since the facility was built and the current paint is faded and chipped in areas. Budget Impact/Other Variance from 20 year plan - costs increased from $22,000 to $28,000 Useful Life 25 years Project Name Pavilion - Paint Exterior Building Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$28,000 Total2017 2018 2019 2020 2021Expenditures 28,00028,000Construction/Maintenance 28,000 28,000Total Total2017 2018 2019 2020 2021Funding Sources 28,00028,000PA - Pavilion Fund 28,000 28,000Total Thursday, November 17, 2016 86 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Hire a painting contractor to clean, prep, and paint the roof deck, bar joist, and arena walls. Project #14-CIP-PV010 Priority 1 Urgent Justification The current coating was painted when the facility was built and is in need of recoating to protect roof deck and bar joist from rust. Budget Impact/Other Variance from 20 year plan - costs were increased from $40,000 to $48,000 Useful Life 25 years Project Name Pavilion Painting the Arena Ceiling and Bar Joist Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$48,000 Total2017 2018 2019 2020 2021Expenditures 48,00048,000Construction/Maintenance 48,000 48,000Total Total2017 2018 2019 2020 2021Funding Sources 48,00048,000PA - Pavilion Fund 48,000 48,000Total Thursday, November 17, 2016 87 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Pavilion Manager 2017 2021 thru Department Pavilion Description Fees and payments associated with the design, planning, and specifications documents with the Pavilion's Refrigeration System Replacement and other scheduled projects in 2018 Project #16-CIP-PV327 Priority n/a Justification Due to the expertise needed to remove, design and replace the current refrigeration system staff feels a engineering firm should be contracted to complete all the necessary documents for the project being completed at the Pavilion in 2018. Budget Impact/Other Variance from 20 year plan - New item Useful LifeProject Name Pavilion - Refrigeration System - Engineering Fees Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$200,000 Total2017 2018 2019 2020 2021Expenditures 200,000200,000Construction/Maintenance 200,000 200,000Total Total2017 2018 2019 2020 2021Funding Sources 200,000200,000PA - Pavilion Fund 200,000 200,000Total Thursday, November 17, 2016 88 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Police Chief 2017 2021 thru Department Police Description Replace Police Station Carpeting Project #08-CIP-PD016 Priority n/a Justification Planned replacement at end of estimated 10 year useful life. This is a 24hour/day work center that required the shorter carpet replacement cycle. Budget Impact/Other Variance from 20 yar plan: carpet replacement moved back to 2018. Previously in at a 7 year life - moved back to 10 year life Useful Life 7 years Project Name Replace Carpet - Police Station Category Buildings: Police Department Type Improvement Future Total Project Cost:$40,000 Total2017 2018 2019 2020 2021Expenditures 40,00040,000Construction/Maintenance 40,000 40,000Total Total2017 2018 2019 2020 2021Funding Sources 40,00040,000CI - Capital Improvement Fund 40,000 40,000Total Thursday, November 17, 2016 89 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Facilities Director 2017 2021 thru Department Public Works: Bldg/Equip Ser Description Replace Wash Bay Roof Project #08-CIP-B021 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Public Works - Replace Wash Bay Roof Category Buildings: Public Works Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 10,00010,000CI - Capital Improvement Fund 10,00010,000RF - Refuse Fund 10,00010,000SF - Sanitary Sewer Fund 10,00010,000SU - Storm Sewer Fund 10,00010,000WF - Water Fund 50,000 50,000Total Thursday, November 17, 2016 90 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Facilities Director 2017 2021 thru Department Public Works: Bldg/Equip Ser Description Replace overhead doors Project #08-CIP-B023 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Public Works - Replace Overhead Doors Category Buildings: Public Works Type Improvement Future Total Project Cost:$90,000 Total2017 2018 2019 2020 2021Expenditures 90,00090,000Construction/Maintenance 90,000 90,000Total Total2017 2018 2019 2020 2021Funding Sources 18,00018,000CI - Capital Improvement Fund 18,00018,000RF - Refuse Fund 18,00018,000SF - Sanitary Sewer Fund 18,00018,000SU - Storm Sewer Fund 18,00018,000WF - Water Fund 90,000 90,000Total Thursday, November 17, 2016 91 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Facilities Director 2017 2021 thru Department Public Works: Bldg/Equip Ser Description Built up roof on Wash Bay and Eastern third of Maintenance Shop. Project #09-CIP-B034 Priority n/a Justification Existing roof was installed in 1995, estimated replacement due in 2020. Budget Impact/Other Useful Life 25 years Project Name Public Works Garage Roof Replacement Category Buildings: Public Works Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000CI - Capital Improvement Fund 50,000 50,000Total Thursday, November 17, 2016 92 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Bldg/Equip Ser Description Upgrade the tables and chairs, reconfigure cabinets and shelving to suit todays needs, paint, and any electrical needs. Project #16-CIP-B006 Priority 1 Urgent Justification This room is used for lunch breaks, meetings, and trainings. Currently using donated tables and chairs Budget Impact/Other Useful Life 20 years Project Name PW - Public Works Lunchroom Category Buildings: Public Works Type Improvement Future Total Project Cost:$25,000 Total2017 2018 2019 2020 2021Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total2017 2018 2019 2020 2021Funding Sources 25,00025,000CI - Capital Improvement Fund 25,000 25,000Total Thursday, November 17, 2016 93 94 Parks and Recreation 95 96 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Remove and replace blacktop tennis court surfaces at Central Park. Recoat and restripe for tennis. Repairs are next scheduled for 2020 and again in 2026 Total reconstruction due in 2033 - 4 courts Project #05-CIP-P202 Priority n/a Justification Current age of courts is 28 years. Annual crack maintenance and color coating is excessive. Replacement recommended by 2008. Budget Impact/Other Design 2008, install 2008 Identified 3-21-05, High Priority Park Board Useful Life 20 years Project Name Central Park Tennis Courts Category Parks/Fores/Pav.: Neighborhoo Type Improvement Future Total Project Cost:$595,000 Total2017 2018 2019 2020 2021Expenditures 20,00020,000Construction/Maintenance 20,000 20,000Total Total2017 2018 2019 2020 2021Funding Sources 20,00020,000PDF- Park Dedication Fund 20,000 20,000Total Thursday, November 17, 2016 97 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Public Works: Parks Description Replace park play equipment Project #08-CIP-P010 Priority n/a Justification Upgrade of park play equipment after 20 - 25 years of use. Budget Impact/Other Moved from 2014 to 2018 and increased cost from $45,000 to $60,000. Useful LifeProject Name Park Valley - Play Equipment Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$120,000 Total2017 2018 2019 2020 2021Expenditures 120,000120,000Construction/Maintenance 120,000 120,000Total Total2017 2018 2019 2020 2021Funding Sources 120,000120,000PDF- Park Dedication Fund 120,000 120,000Total Thursday, November 17, 2016 98 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Facilities Director 2017 2021 thru Department Public Works: Parks Description Crack seal and apply new surface color coat to Burnes Park tennis courts. Periodic repairs needed to ensure quality safe playing surface. Project #08-CIP-P011 Priority n/a Justification Work needed to restore asphalt surface condition and extend life of tennis courts. Budget Impact/Other Work last done in 2009 - periodically needs repairs. Useful LifeProject Name Burnes Park - Resurface Tennis Courts Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$30,000 Total2017 2018 2019 2020 2021Expenditures 20,00020,000Construction/Maintenance 20,000 20,000Total Total2017 2018 2019 2020 2021Funding Sources 20,00020,000PDF- Park Dedication Fund 20,000 20,000Total Thursday, November 17, 2016 99 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Facilities Director 2017 2021 thru Department Public Works: Parks Description Replace park play equipment. Project #08-CIP-P014 Priority n/a Justification Replace park play equipment after 20-25 years - installed in 1990 and needs replacement Budget Impact/Other Project changed from $45,000 to $100,000 and moved from 2014 top 2016 Useful LifeProject Name Hilltop Park - Play Equipment Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$120,000 Total2017 2018 2019 2020 2021Expenditures 120,000120,000Construction/Maintenance 120,000 120,000Total Total2017 2018 2019 2020 2021Funding Sources 120,000120,000PDF- Park Dedication Fund 120,000 120,000Total Thursday, November 17, 2016 100 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Replace 2-5 play equipment - Install concrete play container edging Project #13-CIP-P043 Priority n/a Justification Existing equipment was installed in 1996. This large park and its play equipment are heavily used by area residents and for large picnic events. Budget Impact/Other New to CIP in 2013 Useful LifeProject Name Burnes Park - 2-5 Play Equipment Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$100,000 Total2017 2018 2019 2020 2021Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total2017 2018 2019 2020 2021Funding Sources 100,000100,000PDF- Park Dedication Fund 100,000 100,000Total Thursday, November 17, 2016 101 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Repair tennis courts - $20,000 2025 - Tennis Courts Reconstruct = $180,000 (2 courts) Project #13-CIP-P044 Priority n/a Justification Periodic repairs needed to ensure quality safe playing surface Budget Impact/Other Added to CIP in 2013 Useful LifeProject Name Oakes Park - Tennis Courts Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$200,000 Total2017 2018 2019 2020 2021Expenditures 20,00020,000Construction/Maintenance 20,000 20,000Total Total2017 2018 2019 2020 2021Funding Sources 20,00020,000PDF- Park Dedication Fund 20,000 20,000Total Thursday, November 17, 2016 102 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Pavilion addition and warming house Stie work Project #13-CIP-P050 Priority n/a Justification Replace existing 60 year old warming house Budget Impact/Other Useful LifeProject Name Pavilion Addion/Warming House Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$600,000 Total2017 2018 2019 2020 2021Expenditures 600,000600,000Construction/Maintenance 600,000 600,000Total Total2017 2018 2019 2020 2021Funding Sources 600,000600,000PDF- Park Dedication Fund 600,000 600,000Total Thursday, November 17, 2016 103 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Play equipment Project #13-CIP-P055 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Elmo Park - 2-5 Play Equipment Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000PDF- Park Dedication Fund 50,000 50,000Total Thursday, November 17, 2016 104 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Warming House Project #13-CIP-P056 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Harley Hopkins Park - Warming House Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$30,000 Total2017 2018 2019 2020 2021Expenditures 30,00030,000Construction/Maintenance 30,000 30,000Total Total2017 2018 2019 2020 2021Funding Sources 30,00030,000PDF- Park Dedication Fund 30,000 30,000Total Thursday, November 17, 2016 105 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Lighting Project #13-CIP-P057 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Harley Hopkins Park - Lighting Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000PDF- Park Dedication Fund 50,000 50,000Total Thursday, November 17, 2016 106 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Picnic Shelter Project #13-CIP-P058 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Hilltop - Picnic Shelter Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$40,000 Total2017 2018 2019 2020 2021Expenditures 40,00040,000Construction/Maintenance 40,000 40,000Total Total2017 2018 2019 2020 2021Funding Sources 40,00040,000PDF- Park Dedication Fund 40,000 40,000Total Thursday, November 17, 2016 107 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Lighting Project #13-CIP-P059 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Interlachen Park - Lighting Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000PDF- Park Dedication Fund 50,000 50,000Total Thursday, November 17, 2016 108 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Play Equipment Project #13-CIP-P062 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Maetzold Field - Play Equipment Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$100,000 Total2017 2018 2019 2020 2021Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total2017 2018 2019 2020 2021Funding Sources 100,000100,000PDF- Park Dedication Fund 100,000 100,000Total Thursday, November 17, 2016 109 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Warming House Project #13-CIP-P063 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Maetzold Field - Pavilion Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$80,000 Total2017 2018 2019 2020 2021Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total2017 2018 2019 2020 2021Funding Sources 80,00080,000PDF- Park Dedication Fund 80,000 80,000Total Thursday, November 17, 2016 110 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Public Works: Parks Description Construct Splash pad play area Replace & construct warming house Replace & constructr picnic shelter Project #14-CIP-P002 Priority n/a Justification A water play area alternative to Shady Oak Beach is needed for 2-5 year old children Budget Impact/Other Useful LifeProject Name Burnes Park Warming House & Splash Pad Category PW - Parks Type Improvement Future Total Project Cost:$1,200,000 Total2017 2018 2019 2020 2021Expenditures 1,200,0001,200,000Construction/Maintenance 1,200,000 1,200,000Total Total2017 2018 2019 2020 2021Funding Sources 1,200,0001,200,000PDF- Park Dedication Fund 1,200,000 1,200,000Total Thursday, November 17, 2016 111 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Improvements to the area around the creek bound by Blaker Road, Lake St and Minnihaha Creek Project #16-CIP-P002 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Cottageville Park - Phase III Improvements Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$450,000 Total2017 2018 2019 2020 2021Expenditures 450,000450,000Construction/Maintenance 450,000 450,000Total Total2017 2018 2019 2020 2021Funding Sources 450,000450,000PDF- Park Dedication Fund 450,000 450,000Total Thursday, November 17, 2016 112 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Parks Description Replace deteriorating portable hockey boards in Interlachen Park Project #16-CIP-P003 Priority n/a Justification Current board are old and deteriorating Budget Impact/Other Useful Life 15 Project Name Interlachen Park - Portable Hockey Boards Category PW - Parks Type Improvement Future Total Project Cost:$50,000 Total2017 2018 2019 2020 2021Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total2017 2018 2019 2020 2021Funding Sources 50,00050,000PDF- Park Dedication Fund 50,000 50,000Total Thursday, November 17, 2016 113 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Joint Recreation Dir. 2017 2021 thru Department Recreation Description The joint recreaton agreement in place between the cities of Hopkins and Minnetonka provides for the sharing of operational and maintenance expenses for Shady Oak Beach. These expenses are split 33% city of Hopkins and 67% city of Minnetonka. Shady Oak Beach is operated from June - August annually; however the park is avaialble for use year round. Project #16-CIP-R003 Priority 3 Important Justification Since last undergoing a renovation in 1998, Shady Oak Beach contiues to be a primary park destination for residents of Hopkins and Minnetonka. Scheduled items are intended to keep the park in excellent appearence, establish a gateway to the park, and to provide park users with a quality recreational experience. 2016: Improvements to existing landscaping, replacement of aging patio furniture. 2017: Construction of a monument sign that features the park entrance. 2019: Preventative interior and exterior building maintenance, interior and exterior lighting upgrades, and irrigation improvements, Budget Impact/Other Variance from 20 year plan - New item Useful Life 10-20 years Project Name Shady Oak Beach Improvements Category PW - Parks Type Improvement Future Total Project Cost:$125,000 Total2017 2018 2019 2020 2021Expenditures 85,00050,000 35,000Construction/Maintenance 50,000 35,000 85,000Total Total2017 2018 2019 2020 2021Funding Sources 57,00033,500 23,500GU - Other Governmental Units 28,00016,500 11,500PDF- Park Dedication Fund 50,000 35,000 85,000Total Thursday, November 17, 2016 114 Streets, Traffic & Transportation 115 116 117 118 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Streets/Traffic Description Locations to be determined consistent with the street reconstruction program. Program includes reconstruction of deteriorated water main, sanitary sewer and storm sewer in conjunction with street improvement projects. Utility improvements are consistent with the Storm Water Management Plan, Water and Sewer Utility Master Plan, and televised inspections. 2017: Park Valley and Peaceful Valley. Reconstruction project. 2018: Northeast Hopkins Reconstruction Project. 2019: Avenues Streets Reconstruction Project. 2020-2021: Interlachen Park Reconstruction Project Project #01-CIP-S101 Priority n/a Justification In most cases where street reconstruction takes place, storm sewer facilities either need upgrading or need to be installed new. In most cases, water main and sanitary sewer need to be rehabilitated in conjunction with street reconstruction. The costs assume the city funding 100% of major storm sewer, water main, and sanitary sewer improvements. Budget Impact/Other Public Hearing - year prior to planned construction Plans and specifications - year prior to planned construction Bid - year of planned construction Consistent with the Storm Water Management Plan, Water and Sewer Utility Master Plan, and television inspections. Consistent with the City Council adopted Roadway Improvement Policy, Street Ratings, Pavement Management Program, Storm Water Management Plan, Water and Sewer Utility Master Plan, and televised inspections. Useful Life Unassigned Project Name Residential Street Improvements and Utilities Category Trans: Streets Type Improvement Future Total Project Cost:$37,584,000 Total2017 2018 2019 2020 2021Expenditures 28,945,0006,600,000 3,450,000 5,575,000 6,660,000 6,660,000Construction/Maintenance 6,600,000 3,450,000 5,575,000 6,660,000 6,660,000 28,945,000Total Total2017 2018 2019 2020 2021Funding Sources 8,475,0002,000,000 1,000,000 1,825,000 1,825,000 1,825,000PI - PIR/General Obligation Bonds 8,170,0002,000,000 900,000 1,500,000 1,885,000 1,885,000SA - Special Assessment 3,000,000500,000 500,000 500,000 750,000 750,000SF - Sanitary Sewer Fund 2,850,000600,000 350,000 500,000 700,000 700,000SU - Storm Sewer Fund 6,450,0001,500,000 700,000 1,250,000 1,500,000 1,500,000WF - Water Fund 6,600,000 3,450,000 5,575,000 6,660,000 6,660,000 28,945,000Total Thursday, November 17, 2016 119 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Streets/Traffic Description 2017: Alley south of 6th Street South and North of Nine Mile Creek, between 11th Avenue South and 10th Avenue South. Program to construct concrete alleys in areas designated as poor on the Alley Condition Survey. Project #01-CIP-S103 Priority n/a Justification The city has had a policy of constructing concrete alleys for a number of years. This policy has proved to be sound by the concrete alleys' durability and low maintenance costs. Current policy has the city share at 20% of the cost in residential areas. The city will experience cost savings due to lower maintenance costs. Budget Impact/Other Consistent with the City Council adopted Roadway Improvement Policy and Alley ratings. Useful Life Unassigned Project Name Citywide Concrete Alleys Category Trans: Streets Type Improvement Future Total Project Cost:$1,368,000 Total2017 2018 2019 2020 2021Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total2017 2018 2019 2020 2021Funding Sources 16,00016,000PI - PIR/General Obligation Bonds 64,00064,000SA - Special Assessment 80,000 80,000Total Thursday, November 17, 2016 120 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Streets/Traffic Description County Road 3 from Shady Oak Road to Meadowbrook Road. Lighting, landscaping, street, etc. improvements along Excelsior Boulevard from the east to west city limits. GO Bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue Segment 1: Construction - 1998/1999 Segment 2: Planning - 2004; bidding and construction (median upgrades only) - 2005 Segment 3: Planning and acquisition - 1999/2001, bidding/construction - 2002/2003/2004 Segment 4: Planning and acquisition - Not in County funding plan TIF funded work includes the following: A signalized intersection will be constructed at Monroe Avenue. A second intersection will also be built at Jackson Ave/St. Louis Street. There will also be a reconfiguration of Monroe Avenue and Milwaukee south of Excelsior Boulevard. This work is being completed in conjunction with the reconstruction of Excelsior Boulevard from Highway 169 to Blake Road. The intersection is being constructed to facilitate redevelopment of the SuperValu north annex site. Project #01-CIP-S104 Priority n/a Justification Deficiencies in terms of roadway condition, traffic/pedestrian movement, safety and aesthetics appear in all four segments of County Road 3: - Segment 1 from Shady Oak Road to 11th Avenue S.; upgrade existing undivided roadway, upgrade 11th Avenue intersection to meet future needs, implement beautification program--completed in 1998 - Segment 2 from 11th Avenue S. to Hwy 169; median pavers construction - Segment 3 from Highway 169 to Blake Road; upgrade existing narrow undivided roadway, resolve safety issues at railroad crossing, improve north-south access, account for future LRT access, address redevelopment needs, add integration for full access at Jackson Avenue. - Segment 4 from Blake Road to Meadowbrook Road; upgrade roadway, implement beautification program. Budget Impact/Other GO bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue. Segment 1: Construction - 1998/1999 Segment 2: Planning - 2005; bidding and construction (median upgrades only) - 2006 Segment 3: Planning and acquisition - 1999/2000; bidding/construction - 2003/2004 Segment 4: Planning and acquisition - Not in County Funding Plan Consistent with Hennepin County CIP and City Council action. Useful Life Unassigned Project Name County Road 3 Category Trans: Streets Type Improvement Future Total Project Cost:$2,300,000 Total2017 2018 2019 2020 2021Expenditures 2,300,0002,300,000Construction/Maintenance 2,300,000 2,300,000Total Total2017 2018 2019 2020 2021Funding Sources 1,600,0001,600,000GU - Other Governmental Units 700,000700,000MS - Municipal State Aid Streets 2,300,000 2,300,000Total Thursday, November 17, 2016 121 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Public Works: Streets/Traffic Description Painting bike lanes, constructing trails and sidewalks, adding safety improvements Project #13-CIP-S040 Priority n/a Justification Council recently adopted plan to increase pedestrian and bicycle access and safety. These improvements begin to implement that plan. Budget Impact/Other Useful Life 20 years Project Name Pedestrian & Bicycle Access Improvements Category Trans: Streets Type Improvement Future Total Project Cost:$200,000 Total2017 2018 2019 2020 2021Expenditures 125,00025,000 25,000 25,000 25,000 25,000Construction/Maintenance 25,000 25,000 25,000 25,000 25,000 125,000Total Total2017 2018 2019 2020 2021Funding Sources 125,00025,000 25,000 25,000 25,000 25,000PI - PIR/General Obligation Bonds 25,000 25,000 25,000 25,000 25,000 125,000Total Thursday, November 17, 2016 122 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact PW Director 2017 2021 thru Department Public Works: Streets/Traffic Description Blake Road, just South of Excelsior blvd, will be reconstructed to enhance accommodations for pedestrians, bicycles, and buses, improve access to adjacent neighborhoods, provide the necessary infrastructure to support redevelopment and enhance economic growth along the corridor, improve and enhance traffic flow at major intersections/interchanges, and provide for access to the planned SWLRT Blake Station. Project #15-CIP-S001 Priority n/a Justification Blake road is a heavily travelled thoroughfare and currently a county road between Excelsior Boulevard and TH7. The construction of a SWLRT station at Blake road will increase traffic and present significant redevelopment opportunity along the corridor. Many traffic issues exist along Blake road including lack of pedestrian accommodations, congestion and poor access. The City of Hopkins completed a study in partnership with the cities of Edina and St. Louis Park, Hennepin County, MNDOT, the Minnehaha Creek Watershed District, Three Rivers Park District, and the SWLRT project office to develop a plan for the future transportation needs of the corridor. Final design of the project began in 2016. Budget Impact/Other Consistent with the City Council adopted roadway improvement policy. Useful LifeProject Name Blake Road Corridor Improvements Category Trans: Streets Type Improvement Future Total Project Cost:$18,398,600 Total2017 2018 2019 2020 2021Expenditures 18,048,6002,648,800 7,949,900 7,449,900Construction/Maintenance 2,648,800 7,949,900 7,449,900 18,048,600Total Total2017 2018 2019 2020 2021Funding Sources 12,928,2001,269,000 5,954,600 5,704,600GU - Other Governmental Units 3,170,4001,379,800 1,020,300 770,300PI - PIR/General Obligation Bonds 750,000375,000 375,000SF - Sanitary Sewer Fund 200,000100,000 100,000SU - Storm Sewer Fund 1,000,000500,000 500,000WF - Water Fund 2,648,800 7,949,900 7,449,900 18,048,600Total Thursday, November 17, 2016 123 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Streets/Traffic Description Location to be determined based on Pavement Management Program. Program includes mill and overlay of deteriorated pavements to extend the useful life of the street. Streets for this method of rehabilitation have usually been rehabilitated or reconstructed within the last 20 years. Project #16-CIP-S041 Priority n/a Justification Properly timed mill and overlay projects can significantly extend the life of a street and delay the need for reconstruction. Mill and overlay projects also require less disturbance and are shorter in duration than reconstruction, which results in less impact of the traveling public. Budget Impact/Other Variance from 20 year plan - New annual pavement rehabilitation category. Useful LifeProject Name Street Overlay Improvements Category Trans: Streets Type Improvement Future Total Project Cost:$1,875,000 Total2017 2018 2019 2020 2021Expenditures 1,625,000275,000 300,000 325,000 350,000 375,000Construction/Maintenance 275,000 300,000 325,000 350,000 375,000 1,625,000Total Total2017 2018 2019 2020 2021Funding Sources 1,625,000275,000 300,000 325,000 350,000 375,000PI - PIR/General Obligation Bonds 275,000 300,000 325,000 350,000 375,000 1,625,000Total Thursday, November 17, 2016 124 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Streets/Traffic Description Replacement of aged regulatory and warning signs that have lost minimum retroreflectivity and replacement of posts, when needed. Project #16-CIP-S042 Priority n/a Justification The city is required to have a sign management program which includes a sign replacement strategy to ensure regulatory and warning signs provide adequate retroreflectivity. Sign replacement cycle is 8 years. Estimated costs assume sign replacements by contract. Parking signs will be replaced as needed due to age, fading, etc. Sign inventory data base will be updated to reflect install date/sign age. Budget Impact/Other Variance from 20 year plan - New item Useful LifeProject Name Street Sign Management Category Trans: Streets Type Improvement Future Total Project Cost:$120,000 Total2017 2018 2019 2020 2021Expenditures 100,00020,000 20,000 20,000 20,000 20,000Construction/Maintenance 20,000 20,000 20,000 20,000 20,000 100,000Total Total2017 2018 2019 2020 2021Funding Sources 100,00020,000 20,000 20,000 20,000 20,000PI - PIR/General Obligation Bonds 20,000 20,000 20,000 20,000 20,000 100,000Total Thursday, November 17, 2016 125 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Transportation Description Supplemental improvements to 3 Light Rail Transit (LRT) station areas in the proposed locations, which includes burial of overhead powerlines, relocation of proposed storm water facilities, extension of municipal utilities, and other miscellaneous aesthetic items. Project #01-CIP-S502 Priority n/a Justification Three stations along the Southwest Corridor in Hopkins. The proposed expenditures would be in addition to the funds expended by the Metropolitan Council. The additional funds would be used to ensure the stations are high quality in appearance, and maximize redevelopment potential in the station areas. These improvements came out of recent transit oriented development planning recommendations. Budget Impact/Other Dependent on Metropolitan Council plans. Consistent with LRT and station plans. Useful Life Unassigned Project Name Light Rail Transit Stations (3)Category Trans: Streets Type Improvement Future Total Project Cost:$4,681,000 Total2017 2018 2019 2020 2021Expenditures 4,681,0001,500,000 3,181,000Construction/Maintenance 1,500,000 3,181,000 4,681,000Total Total2017 2018 2019 2020 2021Funding Sources 1,904,0001,904,000GU - Other Governmental Units 1,325,0001,000,000 325,000PI - PIR/General Obligation Bonds 150,000150,000SF - Sanitary Sewer Fund 952,000952,000SU - Storm Sewer Fund 350,000350,000WF - Water Fund 1,500,000 3,181,000 4,681,000Total Thursday, November 17, 2016 126 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Transportation Description Eighth Avenue from County Road 3 to Mainstreet and access modifications along 2nd Street South, cycle truck extension from MN River Bluffs Regional Trail to Lake Minnetonka Regional Trail and Municipal Lot 700 improvements Design and construction of pedestrian improvements, streetscape improvements, street reconstruction, utility improvements and drainage improvements. Project #01-CIP-S503 Priority n/a Justification The city desires to create a vibrant corridor between the proposed SWLRT station at Excelsior Boulevard and historic downtown Hopkins, that will accommodate pedestrians and bicycles as well as vehicles. Budget Impact/Other Dependent on Metropolitan Council SWLRT plans 2016 - Increased 2017 estimated expenses from $4,033,600 to $5,313,000 Useful Life Unassigned Project Name Eighth Avenue Artery Project Category Trans: Streets Type Improvement Future Total Project Cost:$5,813,000 Total2017 2018 2019 2020 2021Expenditures 5,313,0005,313,000Construction/Maintenance 5,313,000 5,313,000Total Total2017 2018 2019 2020 2021Funding Sources 2,745,0002,745,000GU - Other Governmental Units 1,963,0001,963,000PI - PIR/General Obligation Bonds 100,000100,000SF - Sanitary Sewer Fund 305,000305,000SU - Storm Sewer Fund 200,000200,000WF - Water Fund 5,313,000 5,313,000Total Thursday, November 17, 2016 127 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Transportation Description Grading and culvert improvements needed through the drainage way in the area that extends from Smetana Rd to Nine Mile Creek. Project #16-CIP-S045 Priority n/a Justification Several storm culverts discharge at this location and there is a conveyance problem. The problem is causing sedimentation in the drainage way which could potentially lead to flooding of the roadway. This is currently a maintenance issue for Public Works and needs to be resolved. Budget Impact/Other Useful LifeProject Name Westbrook Way/Smetana Rd Drainage Improvements Category Utilities: Storm Sewer Type Improvement Future Total Project Cost:$100,000 Total2017 2018 2019 2020 2021Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total2017 2018 2019 2020 2021Funding Sources 100,000100,000SU - Storm Sewer Fund 100,000 100,000Total Thursday, November 17, 2016 128 Utilities 129 130 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Utilities Description 2015-2019 Concrete alley repairs Project #01-CIP-U002 Priority n/a Justification Annual alley pavement concrete slab repairs are needed. Budget Impact/Other Consistent with the Storm Water Management Plan. Useful Life Unassigned Project Name Storm Drainage System Maintenance - Alley Repairs Category Utilities: Municipal Sanitary Se Type Improvement Future Total Project Cost:$211,000 Total2017 2018 2019 2020 2021Expenditures 64,00021,000 21,000 22,000Construction/Maintenance 21,000 21,000 22,000 64,000Total Total2017 2018 2019 2020 2021Funding Sources 64,00021,000 21,000 22,000SU - Storm Sewer Fund 21,000 21,000 22,000 64,000Total Thursday, November 17, 2016 131 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Utilities Description Rehabilitate LS No. 4 Project #08-CIP-U001 Priority n/a Justification Lift station No. 4 was identified for rehab in the 2007 comprehensive utility plan Regular major maintenance identified in the 2007 comprehensive utility plan. Budget Impact/Other Useful LifeProject Name Lift Station # 4 Category Utilities: Municipal Sanitary Se Type Improvement Future Total Project Cost:$160,000 Total2017 2018 2019 2020 2021Expenditures 160,000160,000Construction/Maintenance 160,000 160,000Total Total2017 2018 2019 2020 2021Funding Sources 160,000160,000SF - Sanitary Sewer Fund 160,000 160,000Total Thursday, November 17, 2016 132 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Contact Public Works Director 2017 2021 thru Department Public Works: Utilities Description Construction of a new submersible lift station. The new lift station would accommodate three submersible pumps. The existing control building would remain to house the controls and electrical equipment including the existing backup generator, Project #16-CIP-U015 Priority n/a Justification Lift Station No, 7 is the City's largest lift station pumping an average of 0.5 million gallons a day. The existing lift station is over 40 years old. It was partially rehabilitated in 2003, however the station design is wet well/dry well with little storage in the event of pumping failure and maintenance or repair/removal of pumps is a safety concern and extremely difficult and time consuming. The existing steel dry well is corroding quickly due to the harsh environment. Budget Impact/Other Useful Life 30 years Project Name Reconstruct Lift Station No. 7 Category Utilities: Municipal Sanitary Se Type Improvement Future Total Project Cost:$700,000 Total2017 2018 2019 2020 2021Expenditures 700,000700,000Construction 700,000 700,000Total Total2017 2018 2019 2020 2021Funding Sources 700,000700,000SF - Sanitary Sewer Fund 700,000 700,000Total Thursday, November 17, 2016 133