Memo-Shady Oak Road UpdatePublic Works Department
~'~
Memorandum
To: Honorable Mayor and Members of the City Council
Copy: Steven C. Mielke, City Manager ~~
From: Steven J. Stadler, Public Works Director
Date: February 13, 2004
Subject: Shady Oak Road Update
Shady Oak Road Reconstruction Update
\• The County Board approved a contract for WSB Engineers to provide consulting
engineering services to the County Transportation Dept. Based on County furnished
traffic projections, WSB will develop concept-level road alignment/layout options on an
aerial map. The layouts are scheduled for completion by April '04. City staffs and City
Councils will then review proposed plans to discuss proposed road width,
redevelopment options and a public input process. Hennepin County Community
Works may assist the redevelopment effort with a grant for planning level consultant
services. The project schedule is to complete preliminary design/redevelopment plans
in 2004/2005, final design and property acquisition in 2005/2006 and road
reconstruction in 2007/2008.