2021-2025 Equipment Replacement Plan
EQUIPMENT REPLACEMENT PLAN
2021-2025
DATE: November 17, 2020
TO: Honorable Mayor and Members of the City Council
FROM: Mike Mornson, City Manager
SUBJECT: 2021-2025 EQUIPMENT REPLACEMENT PLAN
With this letter, I respectfully submit the 2021-2025 Equipment Replacement Plan. This
five-year planning document represents the combined efforts of city staff and the City
Council.
The Equipment Replacement Plan is a five-year forecast of equipment replacement needs
in the City of Hopkins. It is intended to alert the Council and residents of equipment
replacement needs that are needed to maintain the efficiency of city services and the
safety of city staff. The first year of the plan becomes the adopted budget, however the
equipment is again re-evaluated before final approval is given for the purchase. The
remaining four years represents estimated replacement needs and the related funding.
The Equipment Replacement Plan does not include proposed capital projects. A
document relating specifically to capital project needs has been developed into a separate
document.
The Equipment Replacement Plan is intended to serve as a planning tool and is therefore
structured to present a meaningful, long-range perspective of the city’s equipment needs
over the next 20 years. At the same time sufficient details on individual pieces of
equipment scheduled for replacement is provided to enable those who review the
information to make informed decisions of the city’s equipment needs over the next several
years.
Please use the information provided to assist in the understanding of the city’s equipment
needs as they relate to the delivery of service to the residents of Hopkins.
This document was developed by the Finance Department with the assistance of all city
departments. I wish to especially thank all those involved in the development of the
Equipment Replacement Plan, and especially Steve Stadler, Public Works Director, Brent
Johnson, Police Chief, Dale Specken, Fire Chief, Ari Lenz, Assistant City Manager, and
Nick Bishop, Finance Director for their hard work and dedication.
1
2
Page
City Manager's Message 1
Table of Contents 3
Introduction
Background and Summary of Changes from 2017 Plan 6
Cash Flow Statements
Equipment Replacement Fund 10
Five-Year Project Summaries
Projects by Year 12
Department Summary 15
Projects by Department 16
Funding Source Summary 18
Projects by Funding Source 19
Equipment Requests
Individual Equipment Request Details
Activity Center 22
Arts Center 25
Community Services - IT 28
Fire 41
HRA 50
Pavilion 52
Police 53
Public Works 64
Refuse 74
Water/Sewer 75
Twenty Year Replacement Schedule
Twenty Year Replacement Schedule by Department 78
Equipment Inventory 82
EQUIPMENT REPLACEMENT PLAN
2021-2025
TABLE OF CONTENTS
3
4
INTRODUCTION
5
EQUIPMENT REPLACEMENT PLAN 2021-2025
BACKGROUND AND SUMMARY OF CHANGES FROM 2020 PLAN
Background
The Equipment Replacement Plan is a twenty-year forecast and a five-year plan of equipment needs in
the City of Hopkins. It is intended to inform the Council and residents of the major equipment needs on
the horizon. The first year of the plan becomes an adopted equipment budget and relates to the
operating budget of the equipment replacement fund, which is approved on an annual basis. The
remaining nineteen years represent an estimate of equipment needs and funding capabilities of the City.
Funding requirements vary from year to year. In order to maintain a fairly consistent levy each year, the
twenty-year schedule is projected with a 3% inflation factor for operating expenses.
The cash flow requirements to fund equipment needs in the equipment replacement fund will experience
a roller coaster effect over the next 20 years given the projected equipment needs and 3% inflation rate.
The intragovernmental charges were increased in 2021 by 9% and will be increased by 6% in 2022
through 2025. The majority of items purchased with ERP funds are used by departments within the
General Fund which accounts for the most of the operations of the city. The fund will continue to rely
on a tax levy in 2021. The levy being proposed for 2020 is $200,000. It is planned to be $250,000 for
2022-2025.
There have been many changes in technology and the way we operate and as a result there is more
equipment in the plan; however the rate has not increased to accommodate the increase in equipment.
Equipment that was purchased with grants such as digital squad cameras, laptop computers in squad cars
and fire vehicles, and infrared cameras are included in the ERP but the rates have not kept up with the
addition of all these items. In addition society is dictating some of the equipment under consideration.
One of the items that was added in recent years was police body cameras, which are currently included
in this plan.
The long term viability of the fund remains questionable and will result in difficult decisions regarding
equipment and operations. These issues were addressed as part of the Financial Management Plan
(FMP) first completed in 2014. The FMP establishes funding mechanisms to get the fund to a constant
balance of $750,000. Items that will be considered and/or implemented are rate increases, a tax levy and
issuing equipment certificates.
Equipment Certificates were sold for $590,000 in 2018. This will allow us to replace aging equipment
and spread the payments over 10 years. The required Equipment Certificate payment will be part of the
debt levy in the applicable year. Equipment certificates will be considered as a funding source in 2022.
Each year staff re-evaluates the equipment needs and adjusts the schedule accordingly. Changes to the
plan are reflected in the document. Refurbishments, extended life expectancy and closer cost estimates
of replacements have been incorporated into the plan. The equipment replacement charges in the
general fund represent approximately 3% of total general fund expenditures.
6
The Equipment Replacement Plan’s basic premise is scheduled replacement of present equipment. A
new item must, in the year proposed, be presented in the annual operating budget with a stipulation that
replacement will be necessary in the future. Flexibility of the Equipment Replacement Plan is
established through annual review and revision, if necessary.
Summary of Changes from 2020-2024 Plan
Highlights of changes from last year’s equipment replacement plan for the years 2021-2024:
CS - Activity Center: No changes
CS - Arts Center: No changes
CS - IT: Financial Software Upgrade was cancelled in 2021 for $307,468.
Community Services: No changes
Fire: Hose replacement project removed in 2023 for $38,000.
Quick Attack Pumper/Rescue in 2022 estimated costs increased from
$525,000 to $725,000.
Extrication Tool in 2022 was removed for $30,000.
Emergency Operations Center Updated advanced from 2024 to 2022 for
$16,000.
Fire Helmets advanced from 2023 to 2022 for $12,000.
Thermal Imaging Cameras delayed from 2023 to 2025 for $16,180.
Radios delayed from 2023 to 2025 for $386,000.
HRA No changes.
Police: Building Video Server costs increased by $5,000 in 2023.
Taser Replacement costs increased by $10,000 in 2023.
Squad Car Camera System/Body Worn Cameras cost increased by $55,000 in
2024.
.
Public Works: Building/Equipment Services
No Changes
Engineering
Van was removed from 2024 for $28,900.
7
Parks/Forestry
Riding Mowers advanced from 2022 to 2021 for $50,000
Log Truck delayed from 2022 to 2023 for $163,600.
Trailer Flatbed
Streets/Traffic
Single Axle Dump Truck was delayed from 2021 to 2022 for $225,000.
Front End Loader delayed from 2023 to 2024 for $268,600.
4x4 ¾ Ton Truck with Plow was removed from 2024 for $38,500.
Asphalt Hot Mix Heating Box was removed from 2024 for $22,100.
Refuse
No changes
Sewer
Televising Camera and Van added to 2022 for $180,000.
4x4 ¾ Ton Truck was removed from 2024 for $40,300.
Water
No Changes
8
CASH FLOW STATEMENT
9
City of Hopkins
Equipment Replacement Fund (602)
Rate Change 9%9%9%6%6%6%6%
ACTUAL PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET
2019 2020 2021 2022 2023 2024 2025
Working Capital Begin Year (114,895) 250,501 293,175 559,915 570,152 383,141 468,829
Revenues from charges 529,264 579,674 631,845 669,755 709,941 752,537 797,689
Tax Levy 227,680 110,000 200,000 250,000 250,000 250,000 196,947
Interest earnings - - 293 359 2,851 3,000 3,000
Other revenues (sale of assets)3,254 - 15,000 35,000 35,000 35,000 40,000
Equipment Certificates (Bonds)- 255,539 - - 850,000 - 425,000
Total Revenues 760,198 945,213 847,138 955,114 1,847,791 1,040,537 1,462,636
Expenditures (excludes Leases & Depr.) 6,333 6,333 34,899 35,248 36,305 37,395 38,516
Capital Outlay - Equipment 388,469 896,206 545,499 909,629 1,998,497 917,454 1,428,329
Total Expenses 394,802 902,539 580,398 944,877 2,034,802 954,849 1,466,845
Working Capital Ending Balance 250,501 293,175 559,915 570,152 383,141 468,829 464,620
(Unrestricted Net Position)
10
FIVE-YEAR
PROJECT SUMMARIES
11
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP
PROJECTS BY YEAR
2021 2025thru
Project Name Department Project #Priority Project Cost
2021
01-ERP-0037Activity Center Security System Upgrade 1 20,000Comm Svcs - Activity Center
01-ERP-0041Activity Center A/V Replacement & Upgrade 3 62,624Comm Svcs - Activity Center
01-ERP-0003CH - Network Server n/a 22,000Comm Svcs - IT
01-ERP-0006Computers n/a 33,075Comm Svcs - IT
01-ERP-0017IT - Office 365 n/a 33,000Comm Svcs - IT
01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT
01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 21,000Comm Svcs - IT
01-ERP-0211PD - Network Server n/a 22,000Comm Svcs - IT
01-ERP-0200Marked Patrol Vehicles (7)n/a 161,100Police
01-ERP-0201Sergeant's Vehicle n/a 57,000Police
01-ERP-0202PSO / Parking Enforcement Vehicle n/a 53,700Police
01-ERP-0808Riding Mowers (2)1 50,000Public Works: Parks/Forestry
01-ERP-0900Refuse Truck (RAP-R) (2)n/a 270,300Refuse
815,799Total for 2021
2022
01-ERP-0038Activity Center Kitchen Storage 5 17,000Comm Svcs - Activity Center
01-ERP-1105Art Center Jaycee Studio Audio Visual n/a 13,500Comm Svcs - Arts Center
01-ERP-0003CH - Network Server n/a 25,000Comm Svcs - IT
01-ERP-0006Computers n/a 34,729Comm Svcs - IT
01-ERP-0009Network Infrastructure Upgrade n/a 23,400Comm Svcs - IT
01-ERP-0017IT - Office 365 n/a 44,000Comm Svcs - IT
01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT
01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 42,000Comm Svcs - IT
01-ERP-0211PD - Network Server n/a 25,000Comm Svcs - IT
01-ERP-0126Fire - Fire Helmets n/a 16,000Fire
01-ERP-0129Fire - EOC Upgrade n/a 12,000Fire
01-ERP-0401HRA Copier n/a 16,500HRA
01-ERP-0200Marked Patrol Vehicles (7)n/a 110,000Police
01-ERP-0203PSO - Utility 4x4 n/a 72,100Police
01-ERP-0221Records Management System n/a 150,000Police
01-ERP-03031 Ton Dump Truck (2)n/a 53,400Public Works: Streets/Traffic
01-ERP-0305Single Axle Dump Truck (2)n/a 225,000Public Works: Streets/Traffic
01-ERP-0309Skid Loader (2)n/a 50,000Public Works: Streets/Traffic
01-ERP-0555Generator (2)n/a 43,000Sewer
01-ERP-0560Sewer Televising Camera and Van n/a 180,000Sewer
1,162,629Total for 2022
2023
01-ERP-0038Activity Center Kitchen Storage 5 12,000Comm Svcs - Activity Center
01-ERP-0003CH - Network Server n/a 26,250Comm Svcs - IT
01-ERP-0004Telephone System n/a 89,600Comm Svcs - IT
01-ERP-0006Computers n/a 36,465Comm Svcs - IT
Wednesday, November 11, 2020
12
Project Name Department Project #Priority Project Cost
01-ERP-0015Backup Server n/a 72,120Comm Svcs - IT
01-ERP-0017IT - Office 365 n/a 44,000Comm Svcs - IT
01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT
01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 42,000Comm Svcs - IT
01-ERP-0211PD - Network Server n/a 26,250Comm Svcs - IT
01-ERP-0105Quick Attack Pumper/Rescue (Rescue 8)n/a 725,000Fire
01-ERP-0109Extrication Tool (1)n/a 32,000Fire
01-ERP-0127Fire - Lucus Device n/a 18,000Fire
01-ERP-04004x4 3/4 Ton Truck n/a 41,100HRA
01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police
01-ERP-0214Tactical Ballistic Vests / Helmets - SWAT 3 76,512Police
01-ERP-0215Police - Portable Radios n/a 290,000Police
01-ERP-0217Taser Replacement n/a 90,000Police
01-ERP-0218Building Video Server n/a 22,000Police
01-ERP-08001/2 Ton Pickup Truck n/a 35,400Public Works: Parks/Forestry
01-ERP-0804Log Truck n/a 163,600Public Works: Parks/Forestry
01-ERP-03004x4 1/2 Ton Pickup with Plow n/a 28,900Public Works: Streets/Traffic
01-ERP-03041 Ton Traffic Boom Truck n/a 136,400Public Works: Streets/Traffic
2,134,997Total for 2023
2024
01-ERP-1107Art Center Theater Projection Screen 2 6,700Comm Svcs - Arts Center
01-ERP-0003CH - Network Server n/a 27,037Comm Svcs - IT
01-ERP-0006Computers n/a 37,559Comm Svcs - IT
01-ERP-0012Core Network Switch n/a 20,000Comm Svcs - IT
01-ERP-0017IT - Office 365 n/a 45,320Comm Svcs - IT
01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT
01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 63,000Comm Svcs - IT
01-ERP-0211PD - Network Server n/a 27,038Comm Svcs - IT
01-ERP-1003Pavilion - Floor Scrubber n/a 11,600Pavilion
01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police
01-ERP-0212Squad Car Camera Systems/ Body Worn Camera n/a 160,000Police
01-ERP-0220Squad Computers n/a 90,000Police
01-ERP-0814Trailer Flatbed n/a 10,000Public Works: Parks/Forestry
01-ERP-03031 Ton Dump Truck (2)n/a 49,500Public Works: Streets/Traffic
01-ERP-0308Front End Loaders (2)n/a 268,600Public Works: Streets/Traffic
943,754Total for 2024
2025
01-ERP-1109Art Center Floor Scrubber n/a 10,800Comm Svcs - Arts Center
01-ERP-0003CH - Network Server n/a 27,849Comm Svcs - IT
01-ERP-0005Financial Software - Various Depts.n/a 315,000Comm Svcs - IT
01-ERP-0006Computers n/a 38,686Comm Svcs - IT
01-ERP-0014Distribution Network Switches n/a 57,000Comm Svcs - IT
01-ERP-0017IT - Office 365 n/a 46,680Comm Svcs - IT
01-ERP-0020IT - Patching Automation Software 1 10,300Comm Svcs - IT
01-ERP-0211PD - Network Server n/a 27,849Comm Svcs - IT
01-ERP-0052Electronic Inspections Processing 2 16,231Community Services
01-ERP-0108Self Contained Breathing Apparatus (SCBA) (45)n/a 250,000Fire
01-ERP-0112Thermal Imaging Camera (2)n/a 16,180Fire
01-ERP-0125Fire Radios - Portable and Mobile Devices n/a 386,000Fire
01-ERP-0131Fire - Station Alerting System n/a 55,000Fire
01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police
01-ERP-0201Sergeant's Vehicle n/a 64,154Police
01-ERP-0900Refuse Truck (RAP-R) (2)n/a 275,200Refuse
Wednesday, November 11, 2020
13
Project Name Department Project #Priority Project Cost
1,714,329Total for 2025
GRAND TOTAL 6,771,508
Wednesday, November 11, 2020
14
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP
DEPARTMENT SUMMARY
2021 2025thru
Total2021 2022 2023 2024 2025Department
Comm Svcs - Activity Center 111,62482,624 17,000 12,000
Comm Svcs - Arts Center 31,00013,500 6,700 10,800
Comm Svcs - IT 1,445,207141,075 204,129 346,685 229,954 523,364
Community Services 16,23116,231
Fire 1,510,18028,000 775,000 707,180
HRA 57,60016,500 41,100
Pavilion 11,60011,600
Police 1,748,766271,800 332,100 595,912 367,400 181,554
Public Works: Parks/Forestry 259,00050,000 199,000 10,000
Public Works: Streets/Traffic 811,800328,400 165,300 318,100
Refuse 545,500270,300 275,200
Sewer 223,000223,000
815,799 1,162,629 2,134,997 943,754 1,714,329 6,771,508TOTAL
Wednesday, November 11, 202015
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP
PROJECTS BY DEPARTMENT
2021 2025thru
Total2021 2022 2023 2024 2025Department Project # Priority
Comm Svcs - Activity Center
01-ERP-0037 20,00020,000Activity Center Security System Upgrade 1
01-ERP-0038 29,00017,000 12,000Activity Center Kitchen Storage 5
01-ERP-0041 62,62462,624Activity Center A/V Replacement & Upgrade 3
111,62482,624 17,000 12,000Comm Svcs - Activity Center Total
Comm Svcs - Arts Center
01-ERP-1105 13,50013,500Art Center Jaycee Studio Audio Visual n/a
01-ERP-1107 6,7006,700Art Center Theater Projection Screen 2
01-ERP-1109 10,80010,800Art Center Floor Scrubber n/a
31,00013,500 6,700 10,800Comm Svcs - Arts Center Total
Comm Svcs - IT
01-ERP-0003 128,13622,000 25,000 26,250 27,037 27,849CH - Network Server n/a
01-ERP-0004 89,60089,600Telephone System n/a
01-ERP-0005 315,000315,000Financial Software - Various Depts.n/a
01-ERP-0006 180,51433,075 34,729 36,465 37,559 38,686Computersn/a
01-ERP-0009 23,40023,400Network Infrastructure Upgrade n/a
01-ERP-0012 20,00020,000Core Network Switch n/a
01-ERP-0014 57,00057,000Distribution Network Switches n/a
01-ERP-0015 72,12072,120Backup Server n/a
01-ERP-0017 213,00033,000 44,000 44,000 45,320 46,680IT - Office 365 n/a
01-ERP-0020 50,30010,000 10,000 10,000 10,000 10,300IT - Patching Automation Software 1
01-ERP-0022 168,00021,000 42,000 42,000 63,000IT - Windows 10 Enterprise Upgrade n/a
01-ERP-0211 128,13722,000 25,000 26,250 27,038 27,849PD - Network Server n/a
1,445,207141,075 204,129 346,685 229,954 523,364Comm Svcs - IT Total
Community Services
01-ERP-0052 16,23116,231Electronic Inspections Processing 2
16,23116,231Community Services Total
Fire
01-ERP-0105 725,000725,000Quick Attack Pumper/Rescue (Rescue 8) n/a
01-ERP-0108 250,000250,000Self Contained Breathing Apparatus (SCBA) (45)n/a
01-ERP-0109 32,00032,000Extrication Tool (1)n/a
01-ERP-0112 16,18016,180Thermal Imaging Camera (2)n/a
01-ERP-0125 386,000386,000Fire Radios - Portable and Mobile Devices n/a
01-ERP-0126 16,00016,000Fire - Fire Helmets n/a
01-ERP-0127 18,00018,000Fire - Lucus Device n/a
01-ERP-0129 12,00012,000Fire - EOC Upgrade n/a
01-ERP-0131 55,00055,000Fire - Station Alerting System n/a
1,510,18028,000 775,000 707,180Fire Total
Wednesday, November 11, 202016
Total2021 2022 2023 2024 2025Department Project # Priority
HRA
01-ERP-0400 41,10041,1004x4 3/4 Ton Truck n/a
01-ERP-0401 16,50016,500HRA Copier n/a
57,60016,500 41,100HRA Total
Pavilion
01-ERP-1003 11,60011,600Pavilion - Floor Scrubber n/a
11,60011,600Pavilion Total
Police
01-ERP-0200 623,300161,100 110,000 117,400 117,400 117,400Marked Patrol Vehicles (7) n/a
01-ERP-0201 121,15457,000 64,154Sergeant's Vehicle n/a
01-ERP-0202 53,70053,700PSO / Parking Enforcement Vehicle n/a
01-ERP-0203 72,10072,100PSO - Utility 4x4 n/a
01-ERP-0212 160,000160,000Squad Car Camera Systems/ Body Worn Camera n/a
01-ERP-0214 76,51276,512Tactical Ballistic Vests / Helmets - SWAT 3
01-ERP-0215 290,000290,000Police - Portable Radios n/a
01-ERP-0217 90,00090,000Taser Replacement n/a
01-ERP-0218 22,00022,000Building Video Server n/a
01-ERP-0220 90,00090,000Squad Computers n/a
01-ERP-0221 150,000150,000Records Management System n/a
1,748,766271,800 332,100 595,912 367,400 181,554Police Total
Public Works: Parks/Forestry
01-ERP-0800 35,40035,4001/2 Ton Pickup Truck n/a
01-ERP-0804 163,600163,600Log Truck n/a
01-ERP-0808 50,00050,000Riding Mowers (2)1
01-ERP-0814 10,00010,000Trailer Flatbed n/a
259,00050,000 199,000 10,000Public Works: Parks/Forestry Total
Public Works: Streets/Traffic
01-ERP-0300 28,90028,9004x4 1/2 Ton Pickup with Plow n/a
01-ERP-0303 102,90053,400 49,5001 Ton Dump Truck (2)n/a
01-ERP-0304 136,400136,4001 Ton Traffic Boom Truck n/a
01-ERP-0305 225,000225,000Single Axle Dump Truck (2)n/a
01-ERP-0308 268,600268,600Front End Loaders (2)n/a
01-ERP-0309 50,00050,000Skid Loader (2)n/a
811,800328,400 165,300 318,100Public Works: Streets/Traffic Total
Refuse
01-ERP-0900 545,500270,300 275,200Refuse Truck (RAP-R) (2) n/a
545,500270,300 275,200Refuse Total
Sewer
01-ERP-0555 43,00043,000Generator (2) n/a
01-ERP-0560 180,000180,000Sewer Televising Camera and Van n/a
223,000223,000Sewer Total
GRAND TOTAL 6,771,508815,799 1,162,629 2,134,997 943,754 1,714,329
Wednesday, November 11, 202017
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP
FUNDING SOURCE SUMMARY
2021 thru 2025
TotalSource2021 2022 2023 2024 2025
AC - Arts Center Fund 31,00013,500 6,700 10,800
Equipment Replacement Fund 5,799,408545,499 909,629 1,998,497 917,454 1,428,329
HRA - Housing and Redevelopment Authority 57,60016,500 41,100
PA - Pavilion Fund 11,60011,600
PKG - Parking Fund 8,0008,000
RF - Refuse Fund 627,300270,300 81,800 275,200
SF - Sanitary Sewer Fund 229,800223,000 6,800
WF - Water Fund 6,8006,800
815,799 1,162,629 2,134,997 943,754 1,714,329 6,771,508GRAND TOTAL
Wednesday, November 11, 2020
18
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP
PROJECTS BY FUNDING SOURCE
2021 2025thru
TotalSource Project # Priority 2021 2022 2023 2024 2025
AC - Arts Center Fund
01-ERP-1105 13,50013,500Art Center Jaycee Studio Audio Visual n/a
01-ERP-1107 6,7006,700Art Center Theater Projection Screen 2
01-ERP-1109 10,80010,800Art Center Floor Scrubber n/a
31,00013,500 6,700 10,800AC - Arts Center Fund Total
Equipment Replacement Fund
01-ERP-0003 128,13622,000 25,000 26,250 27,037 27,849CH - Network Server n/a
01-ERP-0004 76,00076,000Telephone System n/a
01-ERP-0005 315,000315,000Financial Software - Various Depts.n/a
01-ERP-0006 180,51433,075 34,729 36,465 37,559 38,686Computersn/a
01-ERP-0009 23,40023,400Network Infrastructure Upgrade n/a
01-ERP-0012 20,00020,000Core Network Switch n/a
01-ERP-0014 57,00057,000Distribution Network Switches n/a
01-ERP-0015 72,12072,120Backup Server n/a
01-ERP-0017 213,00033,000 44,000 44,000 45,320 46,680IT - Office 365 n/a
01-ERP-0020 50,30010,000 10,000 10,000 10,000 10,300IT - Patching Automation Software 1
01-ERP-0022 168,00021,000 42,000 42,000 63,000IT - Windows 10 Enterprise Upgrade n/a
01-ERP-0037 20,00020,000Activity Center Security System Upgrade 1
01-ERP-0038 29,00017,000 12,000Activity Center Kitchen Storage 5
01-ERP-0041 62,62462,624Activity Center A/V Replacement & Upgrade 3
01-ERP-0052 16,23116,231Electronic Inspections Processing 2
01-ERP-0105 725,000725,000Quick Attack Pumper/Rescue (Rescue 8)n/a
01-ERP-0108 250,000250,000Self Contained Breathing Apparatus (SCBA) (45)n/a
01-ERP-0109 32,00032,000Extrication Tool (1)n/a
01-ERP-0112 16,18016,180Thermal Imaging Camera (2)n/a
01-ERP-0125 386,000386,000Fire Radios - Portable and Mobile Devices n/a
01-ERP-0126 16,00016,000Fire - Fire Helmets n/a
01-ERP-0127 18,00018,000Fire - Lucus Device n/a
01-ERP-0129 12,00012,000Fire - EOC Upgrade n/a
01-ERP-0131 55,00055,000Fire - Station Alerting System n/a
01-ERP-0200 623,300161,100 110,000 117,400 117,400 117,400Marked Patrol Vehicles (7)n/a
01-ERP-0201 121,15457,000 64,154Sergeant's Vehicle n/a
01-ERP-0202 53,70053,700PSO / Parking Enforcement Vehicle n/a
01-ERP-0203 72,10072,100PSO - Utility 4x4 n/a
01-ERP-0211 128,13722,000 25,000 26,250 27,038 27,849PD - Network Server n/a
01-ERP-0212 152,000152,000Squad Car Camera Systems/ Body Worn Camera n/a
01-ERP-0214 76,51276,512Tactical Ballistic Vests / Helmets - SWAT 3
01-ERP-0215 290,000290,000Police - Portable Radios n/a
01-ERP-0217 90,00090,000Taser Replacement n/a
01-ERP-0218 22,00022,000Building Video Server n/a
01-ERP-0220 90,00090,000Squad Computers n/a
01-ERP-0221 150,000150,000Records Management System n/a
01-ERP-0300 28,90028,9004x4 1/2 Ton Pickup with Plow n/a
Wednesday, November 11, 2020
19
TotalSource Project # Priority 2021 2022 2023 2024 2025
01-ERP-0303 102,90053,400 49,5001 Ton Dump Truck (2) n/a
01-ERP-0304 136,400136,4001 Ton Traffic Boom Truck n/a
01-ERP-0305 225,000225,000Single Axle Dump Truck (2)n/a
01-ERP-0308 268,600268,600Front End Loaders (2)n/a
01-ERP-0309 50,00050,000Skid Loader (2)n/a
01-ERP-0800 35,40035,4001/2 Ton Pickup Truck n/a
01-ERP-0804 81,80081,800Log Truck n/a
01-ERP-0808 50,00050,000Riding Mowers (2)1
01-ERP-0814 10,00010,000Trailer Flatbed n/a
5,799,408545,499 909,629 1,998,497 917,454 1,428,329Equipment Replacement Fund Total
HRA - Housing and Redevelopment A
01-ERP-0400 41,10041,1004x4 3/4 Ton Truck n/a
01-ERP-0401 16,50016,500HRA Copier n/a
57,60016,500 41,100HRA - Housing and Redevelopment
Authority Total
PA - Pavilion Fund
01-ERP-1003 11,60011,600Pavilion - Floor Scrubber n/a
11,60011,600PA - Pavilion Fund Total
PKG - Parking Fund
01-ERP-0212 8,0008,000Squad Car Camera Systems/ Body Worn Camera n/a
8,0008,000PKG - Parking Fund Total
RF - Refuse Fund
01-ERP-0804 81,80081,800Log Truck n/a
01-ERP-0900 545,500270,300 275,200Refuse Truck (RAP-R) (2)n/a
627,300270,300 81,800 275,200RF - Refuse Fund Total
SF - Sanitary Sewer Fund
01-ERP-0004 6,8006,800Telephone System n/a
01-ERP-0555 43,00043,000Generator (2)n/a
01-ERP-0560 180,000180,000Sewer Televising Camera and Van n/a
229,800223,000 6,800SF - Sanitary Sewer Fund Total
WF - Water Fund
01-ERP-0004 6,8006,800Telephone System n/a
6,8006,800WF - Water Fund Total
6,771,508815,799 1,162,629 2,134,997 943,754 1,714,329GRAND TOTAL
Wednesday, November 11, 2020
20
EQUIPMENT REQUESTS
21
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Activity Ctr Director
2021 2025
thru Department Comm Svcs - Activity Center
Description
Upgrade the present security system, which was installed in 2008.
Project #01-ERP-0037
Priority 1 Urgent
Justification
We monitor the Activity Center to insure the safety of our participants and staff. Staff works numerous hours while alone within the building. We
rely on security cameras to deter harm to participants or staff, or damage to the building itself. Cameras can help identify the perpetrator if
something should happen. Recommendation to complete security upgrades after capital improvements in the facility.
Budget Impact/Other
Useful Life 15-18 yearsProject Name Activity Center Security System Upgrade Category Equipment
Type Equipment
Future
Total Project Cost:$51,160
Total2021 2022 2023 2024 2025Expenditures
20,00020,000Equipment
20,000 20,000Total
Total2021 2022 2023 2024 2025Funding Sources
20,00020,000Equipment Replacement Fund
20,000 20,000Total
Wednesday, November 11, 2020
22
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Activity Ctr Director
2021 2025
thru Department Comm Svcs - Activity Center
Description
Purchase of stainless steel enclosed cabinets for the kitchen over a 2-year span.
Project #01-ERP-0038
Priority 5 Future Consideration
Justification
The Activity Center kitchen presently has open type shelving cages, purchased in 1991. Shelving should be replaced with shelving conducive to
water as some shelves are used for storing silverware and coffee cups directly from the dishwasher. The present shelving is rusting. Enclosed units
are needed to secure items we use for our own kitchen operation from facility use renters, as well as proper storage of equipment from the dirt,
dust, and grim associated with everyday use of the kitchen.
Budget Impact/Other
Useful Life 30 yearsProject Name Activity Center Kitchen Storage Category Equipment
Type Equipment
Future
Total Project Cost:$29,000
Total2021 2022 2023 2024 2025Expenditures
29,00017,000 12,000Equipment
17,000 12,000 29,000Total
Total2021 2022 2023 2024 2025Funding Sources
29,00017,000 12,000Equipment Replacement Fund
17,000 12,000 29,000Total
Wednesday, November 11, 2020
23
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Activity Ctr Director
2021 2025
thru Department Comm Svcs - Activity Center
Description
Continue this replacement project that began in 2016 to replace and upgrade the audio and visual system within the Hopkins Activity Center, area
by area, throughout the next 4 years. Note: The gym has already been replaced and upgraded.
Project #01-ERP-0041
Priority 3 Important
Justification
The present sound system in this facility was installed in 1980. It was primarily used as a paging system. This replacement and upgrading project
began in 2016. We continue to replace and upgrade the audio/visual system to allow better hearing for our participants as well amplification
devices for speakers, presenters, leaders, and instructors. We add equipment to use the technology now available for visual enhancements using
our present televisions in various areas that are used in presentations, classroom instruction, and recreational activities. We are recommending
delaying the project to corelate with the potential improvements at the Activity Center. We would like to complete upgrades at once time to ensure
all equipment is compatible. We have upgraded sound and visual in the gymnasium and it has made significant difference in our participant’s
ability to hear and see in the programs they participate in. In addition, those who have rented from us and have used our upgraded equipment say
how much it has enhanced their events.
Budget Impact/Other
Useful Life 15-20 yearsProject Name Activity Center A/V Replacement & Upgrade Category Equipment
Type Improvement
Future
Total Project Cost:$160,192
Total2021 2022 2023 2024 2025Expenditures
62,62462,624Equipment
62,624 62,624Total
Total2021 2022 2023 2024 2025Funding Sources
62,62462,624Equipment Replacement Fund
62,624 62,624Total
Wednesday, November 11, 2020
24
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Arts Center Director
2021 2025
thru Department Comm Svcs - Arts Center
Description
Install a projector in a ceiling mount. Wire speakers into the ceiling. Wire input for computer on front wall. Add two microphones. Mount
supporting hardware in rack that fits into closet.
Originally scheduled for the Community Room this project was moved to the Jaycee Studio as they found a greater need for this equipment in that
room.
Project #01-ERP-1105
Priority n/a
Justification
An increasing number of users of this room require media support. Current means of providing this include the use of an oversized A/V cart, cords
stretch across the floor and a large speaker on a stick. We can streamline the appearance and functionality by making these appropriate changes.
These changes also address safety concerns. They will help attract safety concerns. They will help attract and retain rental customers as well as
appropriately support our own activities.
Budget Impact/Other
Move this item from 2014 to 2015.
Useful Life 7 yearsProject Name Art Center Jaycee Studio Audio Visual Category Equipment
Type Equipment
Future
Total Project Cost:$61,515
Total2021 2022 2023 2024 2025Expenditures
13,50013,500Equipment
13,500 13,500Total
Total2021 2022 2023 2024 2025Funding Sources
13,50013,500AC - Arts Center Fund
13,500 13,500Total
Wednesday, November 11, 2020
25
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Arts Center Director
2021 2025
thru Department Comm Svcs - Arts Center
Description
Replace original retractable projection screen in the theater with wider format screen to mesh with current technology.
Project #01-ERP-1107
Priority 2 Very Important
Justification
This is an item being requested more frequently from renters as they find the dimensions of the current screen do not match up with the
presentations they bring in.
Budget Impact/Other
Variance from 20-year plan: New item
Useful Life 10 yearsProject Name Art Center Theater Projection Screen Category Equipment
Type Equipment
Future
Total Project Cost:$32,794
Total2021 2022 2023 2024 2025Expenditures
6,7006,700Equipment
6,700 6,700Total
Total2021 2022 2023 2024 2025Funding Sources
6,7006,700AC - Arts Center Fund
6,700 6,700Total
Wednesday, November 11, 2020
26
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Arts Center Co-Director
2021 2025
thru Department Comm Svcs - Arts Center
Description
26-inch auto scrubber
Project #01-ERP-1109
Priority n/a
Justification
Current scrubber has reached its lifetime and no longer spins fast enough to be effective.
Budget Impact/Other
Variance from 20 year plan - New item
Estimate salvage/resale value on replaced item: $-0-
Useful Life 10 yearsProject Name Art Center Floor Scrubber Category Equipment
Type Equipment
Future
Total Project Cost:$33,316
Total2021 2022 2023 2024 2025Expenditures
10,80010,800Equipment
10,800 10,800Total
Total2021 2022 2023 2024 2025Funding Sources
10,80010,800AC - Arts Center Fund
10,800 10,800Total
Wednesday, November 11, 2020
27
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
The network server is the hub of the network. New computers are faster and more reliable.
Project #01-ERP-0003
Priority n/a
Justification
Networking allows user to share information that is stored in a single location, the network server. This is more efficient because the information
does not have to be stored on many different computers. It also makes for better accuracy because as the information changes or is updated, every
user is working with the same data.
Budget Impact/Other
Changes reflect anticipated need for increased storage.
Useful Life 1 yearProject Name CH - Network Server Category Equipment
Type Equipment
Future
Total Project Cost:$1,113,900
Total2021 2022 2023 2024 2025Expenditures
128,13622,000 25,000 26,250 27,037 27,849Equipment
22,000 25,000 26,250 27,037 27,849 128,136Total
Total2021 2022 2023 2024 2025Funding Sources
128,13622,000 25,000 26,250 27,037 27,849Equipment Replacement Fund
22,000 25,000 26,250 27,037 27,849 128,136Total
Wednesday, November 11, 2020
28
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Includes the PBX, the voice mail systems, and all telephone instruments. Currently there are over 200 extensions served by this system. Also
includes software for the PBX and voice mail systems.
Project #01-ERP-0004
Priority n/a
Justification
Making, receiving and routing telephone calls, storing voice mail messages, and providing telephone based information services (snow line, etc.)
Budget Impact/Other
Variance from 20 year plan - Upgrade to controller in 2009 delays complete replacement to 2015.
Estimate salvage/resale value on replaced item: $
Useful Life 8 yearsProject Name Telephone System Category Equipment
Type Equipment
Future
Total Project Cost:$490,131
Total2021 2022 2023 2024 2025Expenditures
89,60089,600Equipment
89,600 89,600Total
Total2021 2022 2023 2024 2025Funding Sources
76,00076,000Equipment Replacement Fund
6,8006,800SF - Sanitary Sewer Fund
6,8006,800WF - Water Fund
89,600 89,600Total
Wednesday, November 11, 2020
29
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Finance Director
2021 2025
thru Department Comm Svcs - IT
Description
Finance software upgrade. Software currently used by Finance, City Clerk, Inspections and Public Works. This includes software for all finance
applications including general ledger, payroll, accounts payable, accounts receivable, fixed assets, utility billing; Business Licenses, Building
Permits, GIS Mapping, Purchasing, etc.
Project #01-ERP-0005
Priority n/a
Justification
Current software vendor is unable to keep up with technology and internet security standards. Staff is often frustrated with how the software
works and are often unable to get reports they need from the system.
Budget Impact/Other
Variance from 20 year plan - replacement needed in 2014
Estimate salvage/resale value on replaced item: $-0-
Useful Life 7 yearsProject Name Financial Software - Various Depts.Category Equipment
Type Equipment
Future
Total Project Cost:$1,573,219
Total2021 2022 2023 2024 2025Expenditures
315,000315,000Equipment
315,000 315,000Total
Total2021 2022 2023 2024 2025Funding Sources
315,000315,000Equipment Replacement Fund
315,000 315,000Total
Wednesday, November 11, 2020
30
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Finance Director/IT
2021 2025
thru Department Comm Svcs - IT
Description
Personal computer purchases and upgrades for the entire City staff. Coordinating personal computer purchases from individual departments to one
fund.
Project #01-ERP-0006
Priority n/a
Justification
Tools enabling staff to perform job responsibilities efficiently and effectively.
Budget Impact/Other
Increase in expenditure a result of supporting more computers than when the original allotment was put in place.
Useful Life 3-5 yearsProject Name Computers Category Equipment
Type Equipment
Future
Total Project Cost:$1,852,679
Total2021 2022 2023 2024 2025Expenditures
180,51433,075 34,729 36,465 37,559 38,686Equipment
33,075 34,729 36,465 37,559 38,686 180,514Total
Total2021 2022 2023 2024 2025Funding Sources
180,51433,075 34,729 36,465 37,559 38,686Equipment Replacement Fund
33,075 34,729 36,465 37,559 38,686 180,514Total
Wednesday, November 11, 2020
31
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Finance Director/IT
2021 2025
thru Department Comm Svcs - IT
Description
Install new and additional network wiring and equipment.
Project #01-ERP-0009
Priority n/a
Justification
Improve capacity, coverage and reliability. Installation will coincide with office space update.
Budget Impact/Other
Variance from 20 year plan - new item to replace substandard network wiring.
Estimate salvage/resale value on replaced item: $
Useful Life 15 yearsProject Name Network Infrastructure Upgrade Category Equipment
Type Equipment
Future
Total Project Cost:$74,856
Total2021 2022 2023 2024 2025Expenditures
23,40023,400Equipment
23,400 23,400Total
Total2021 2022 2023 2024 2025Funding Sources
23,40023,400Equipment Replacement Fund
23,400 23,400Total
Wednesday, November 11, 2020
32
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Finance Director/IT
2021 2025
thru Department Comm Svcs - IT
Description
Provides layer 3 IP presence for the network, core switching connectivity, backbone on which all network communication is built and facilitates
fiber optic network connection to fire department.
2 - Cisco 3560E-24PD managed switch - $3,000 each
2 - Cisco X2-10GB-LR fiber optic transceiver - $1200 each
cost listed is for equipment only and does not include tax, shipping and other related costs
Project #01-ERP-0012
Priority n/a
Justification
Current two switches are obsolete, end of life and no longer supported by manufacturer. Past lost of service resulted in significant network outage
that was immediately noticed by many employees.
Budget Impact/Other
Variance from 20 year plan - Not currently in ERP but critical to network communication infrastructure. This is outside the budget for city hall
server network budget as the "Lisa" service is scheduled for replacement due to end of life, out of PCI compliance and obsolete.
2015 - change amount from $12,000 to $17,000 - more expensive than originally thought based on 2015 replacement.
Estimate salvage/resale value on replace item: - $-0-
Useful Life 6 yearsProject Name Core Network Switch Category Equipment
Type Equipment
Future
Total Project Cost:$133,878
Total2021 2022 2023 2024 2025Expenditures
20,00020,000Equipment
20,000 20,000Total
Total2021 2022 2023 2024 2025Funding Sources
20,00020,000Equipment Replacement Fund
20,000 20,000Total
Wednesday, November 11, 2020
33
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
We have 25 distribution network switches in our enterprise environment along with fiber optic transceivers and direct attach sfp cables to connect
them. Distribution switches connect to the core switches and bring the data to the actual endpoints such as desktops, servers, telephones, and
copiers.
Project #01-ERP-0014
Priority n/a
Justification
Replacement of these switches with current technology is vital to the function of the network as well as the safety of the data being passed through
the switch.
Budget Impact/Other
2016 - New item in ERP
Useful Life 5 yearsProject Name Distribution Network Switches Category Equipment
Type Equipment
Future
Total Project Cost:$338,486
Total2021 2022 2023 2024 2025Expenditures
57,00057,000Equipment
57,000 57,000Total
Total2021 2022 2023 2024 2025Funding Sources
57,00057,000Equipment Replacement Fund
57,000 57,000Total
Wednesday, November 11, 2020
34
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Group of Dell servers to run Dell Rapid Recovery software to backup city computers and servers, along with Windows and VMWare licsensing
required to run the servers.
Project #01-ERP-0015
Priority n/a
Justification
Backup servers are essential to keep the electronic data for the city safe. We have overgrown our current system and are not able to backup
everything that needs to be backed up in a timely manor. Additinally restores on the curent system take hours to days. If we needed to restore a
critical server from backup, we would be looking at an unacceptable amount of downtime.
Budget Impact/Other
Useful Life 3 yearsProject Name Backup Server Category Equipment
Type Equipment
Future
Total Project Cost:$801,110
Total2021 2022 2023 2024 2025Expenditures
72,12072,120Equipment
72,120 72,120Total
Total2021 2022 2023 2024 2025Funding Sources
72,12072,120Equipment Replacement Fund
72,120 72,120Total
Wednesday, November 11, 2020
35
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Transition from the legacy model of Microsoft Office to Office 365. This project would transition 25 percent of our users and devices per year.
Project #01-ERP-0017
Priority n/a
Justification
As we become a more mobile workforce embracing new mobile and remote technology we need to move away from the traditonal office that can
only be installed on a Windows computer and transition to the version of Office that can be used in the cloud and as a mobile app. Unfortunately,
as is becoming common with most enterprise softwre, you can no longer just purchase it out right, you must rent it from the software author. The
cost for Office 365 will now be a yearly ongoing cost. Office 365 is common at other cities, corporations, and educational environments.
Budget Impact/Other
Useful Life 1 yearProject Name IT - Office 365 Category Equipment
Type Equipment
Future
Total Project Cost:$2,420,118
Total2021 2022 2023 2024 2025Expenditures
213,00033,000 44,000 44,000 45,320 46,680Equipment
33,000 44,000 44,000 45,320 46,680 213,000Total
Total2021 2022 2023 2024 2025Funding Sources
213,00033,000 44,000 44,000 45,320 46,680Equipment Replacement Fund
33,000 44,000 44,000 45,320 46,680 213,000Total
Wednesday, November 11, 2020
36
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Software to automate the delivery of critical and maintenance patches to our enterprise endpoints and yearly maintenance of the software going
forward.
Project #01-ERP-0020
Priority 1 Urgent
Justification
Microsoft software has to be patched the second Tuesday of every month. Adobe software has to be patched every time a critical vulnerability is
discovered, which can be twice in a week in a bad week. Other applications have to be patched as new releases are produced from vendors.
Currently our staff must touch every endpoint for the majority of the software installs. We are using up an inordinate amount of staff time to patch
all of our endpoints only to have to restart the cycle 3 weeks later. Automation of this process would free up staff time to work on other projects
and problems for the city. Approx. two full weeks of 1FTE per month or 960 hours per year saved.
Budget Impact/Other
Useful Life 1 yearProject Name IT - Patching Automation Software Category Equipment
Type Equipment
Future
Total Project Cost:$287,617
Total2021 2022 2023 2024 2025Expenditures
50,30010,000 10,000 10,000 10,000 10,300Equipment
10,000 10,000 10,000 10,000 10,300 50,300Total
Total2021 2022 2023 2024 2025Funding Sources
50,30010,000 10,000 10,000 10,000 10,300Equipment Replacement Fund
10,000 10,000 10,000 10,000 10,300 50,300Total
Wednesday, November 11, 2020
37
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Upgrade Windows 10 Pro software to Windows 10 Enterprise. Required to renew every 3 years. This plan would bring the PD into compliance in
2020 then upgrade 60 city computers a year until all city computers are upgraded. Each batch of 60 computers needs to be renewed every 3 years.
It is estimated that it will take 3 years to fully upgrade the city to Windows 10 Enterprise.
Project #01-ERP-0022
Priority n/a
Justification
The BCA has mandated that we move to Enterprise edition for our Windows computers in the PD. Microsoft is changing the way they deliver
Windows. It is becoming like Office, where you will no longer own Windows outright, you will have to rent it from them. We have to switch to
Enterprise in the PD for compliance reasons, but it is strongly suggested that we plan on switching to Enterprise for all city computers as well.
There may come a time where we are forced to switch to Enterprise edition for the city. It would be ideal to plan ahead and budget money for a
gradual upgrade for the city so it doesn't come as a surprise.
Budget Impact/Other
Useful Life 1 yearProject Name IT - Windows 10 Enterprise Upgrade Category Unassigned
Type Equipment
Future
Total Project Cost:$189,000
Total2021 2022 2023 2024 2025Expenditures
168,00021,000 42,000 42,000 63,000Equipment
21,000 42,000 42,000 63,000 168,000Total
Total2021 2022 2023 2024 2025Funding Sources
168,00021,000 42,000 42,000 63,000Equipment Replacement Fund
21,000 42,000 42,000 63,000 168,000Total
Wednesday, November 11, 2020
38
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact IT Director
2021 2025
thru Department Comm Svcs - IT
Description
Computer servers store information and system programs for Police Department.
Project #01-ERP-0211
Priority n/a
Justification
Annual replacement cycle allows development of system storage program. Use of newer servers for heavy use programs while older servers
usedfor data storage
Budget Impact/Other
Useful Life 1 yearProject Name PD - Network Server Category Equipment
Type Equipment
Future
Total Project Cost:$1,118,901
Total2021 2022 2023 2024 2025Expenditures
128,13722,000 25,000 26,250 27,038 27,849Equipment
22,000 25,000 26,250 27,038 27,849 128,137Total
Total2021 2022 2023 2024 2025Funding Sources
128,13722,000 25,000 26,250 27,038 27,849Equipment Replacement Fund
22,000 25,000 26,250 27,038 27,849 128,137Total
Wednesday, November 11, 2020
39
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Asst City Manager
2021 2025
thru Department Community Services
Description
Included in this request are equipment needed to move to an electronic plan review and inspections process.
Revu -Bluebeam electronic plan review software - 2020 - $1,100 (useful life 8-10 years)
Ipads - 2020 - $5,400 (useful life 5-6 years)
Rental Inspection software - 2020 - $7,500 (useful life 7-10 years)
Project #01-ERP-0052
Priority 2 Very Important
Justification
As more and more contractors and architects ask to submit plan electronically, Blubeam software will enable inspectors to perform electronic plan
reviews which will make the plan review process more efficient and enhance customer service. As the inspection and construction industry
becomes more paperless, iPads will enable inspectors to use mobile technology to keep up with the requests of engineers, architect, contractors,
landlords and residents. Ipads are a key piece that will enable staff to view electronic plans in the field. Going paperless will eventually eliminate
our need for paper plan scanning and sorting which is very time consuming and costs $1,500 - $2,000 per year.
The software company currently used by Rental Inspectors has recently gone out of business and support for the software is going to be on a very
limited basis after 2020. Because rental inspections effect such a large part of the city and the department, I believe getting a new software in place
before the existing software stops functioning is essential to the rental inspection program.
Budget Impact/Other
Useful Life 5-7 yearsProject Name Electronic Inspections Processing Category Equipment
Type Equipment
Future
Total Project Cost:$96,150
Total2021 2022 2023 2024 2025Expenditures
16,23116,231Equipment
16,231 16,231Total
Total2021 2022 2023 2024 2025Funding Sources
16,23116,231Equipment Replacement Fund
16,231 16,231Total
Wednesday, November 11, 2020
40
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Quick attack pumper/rescue.
Current vehicle: 2012 Rescue (#104)
Project #01-ERP-0105
Priority n/a
Justification
This truck is used for day to day operation. We would move to a bigger vehicle due to the use of the vehicle for response. The current vehicle is
undersized for the type of truck it is on. We are spending $20,000.00 per maintanance cost per year.
Would replace Rescue 8 (lite rescue) and use as a utility vehicle. This truck could be used for daytime and nighttime medicals and small fires.
This will reduce having all personnel respond to small fires. It will also let us drop one engine in 2022 but still keep ISO rating.
Budget Impact/Other
Variance from 20 year plan - Useful life change to 10 years.
Reoccurs every 10 years.
Useful Life 10 yearsProject Name Quick Attack Pumper/Rescue (Rescue 8)Category Vehicles
Type Equipment
Future
Total Project Cost:$1,653,063
Total2021 2022 2023 2024 2025Expenditures
725,000725,000Equipment
725,000 725,000Total
Total2021 2022 2023 2024 2025Funding Sources
725,000725,000Equipment Replacement Fund
725,000 725,000Total
Wednesday, November 11, 2020
41
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Breathing apparatus for interior firefighting for firefighters.
Project #01-ERP-0108
Priority n/a
Justification
The breathing apparatus was taken out of the ERP in 2006 because we thought we were getting a grant. Grant was not successful. The SCBA's
(45) need to be replaced because they are at the end of their life and cannot be hydro tested any longer.
Budget Impact/Other
Variance from 20 year plan - Move back to 2025. Purchased SCBA's in 2015 with grant funds.
Estimate salvage/resale value on replaced item: $
Useful Life 10 yearsProject Name Self Contained Breathing Apparatus (SCBA) (45)Category Equipment
Type Equipment
Future
Total Project Cost:$752,000
Total2021 2022 2023 2024 2025Expenditures
250,000250,000Equipment
250,000 250,000Total
Total2021 2022 2023 2024 2025Funding Sources
250,000250,000Equipment Replacement Fund
250,000 250,000Total
Wednesday, November 11, 2020
42
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Hydraulic rescue and extrication tool with spreader, cutters and hydraulic ram.
Project #01-ERP-0109
Priority n/a
Justification
All vehicle and industrial rescue situations which will require patient disentanglement or entrapment. This tool will be added to the purchase of the
quick attack pumper. The tool will be scaled down to a smaller tool, possibly reducing cost.
Budget Impact/Other
Estimate salvage/resale value on replaced item: $1,000
Purchased: 2007
Useful Life 10 yearsProject Name Extrication Tool (1)Category Equipment
Type Equipment
Future
Total Project Cost:$180,800
Total2021 2022 2023 2024 2025Expenditures
32,00032,000Equipment
32,000 32,000Total
Total2021 2022 2023 2024 2025Funding Sources
32,00032,000Equipment Replacement Fund
32,000 32,000Total
Wednesday, November 11, 2020
43
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Used by our fire companies to locate victims trapped in a smoke filled building. It helps us determine where fire and heat may be hidden allowing
for faster extinguishment.
Note: purchased 2013 & 2017
Project #01-ERP-0112
Priority n/a
Justification
Current camera is ten years old and has been through many hot fires and needs to be replaced. Current camera was purchased with donation
money.
Budget Impact/Other
Variance from 20 year plan - department owns 2 cameras.
Reoccuring expenditure.
Estimate salvage/resale value on replaced item: $-0-
Useful Life 10 yearsProject Name Thermal Imaging Camera (2)Category Equipment
Type Equipment
Future
Total Project Cost:$144,885
Total2021 2022 2023 2024 2025Expenditures
16,18016,180Equipment
16,180 16,180Total
Total2021 2022 2023 2024 2025Funding Sources
16,18016,180Equipment Replacement Fund
16,180 16,180Total
Wednesday, November 11, 2020
44
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Portable and mobile radios used by the police departments to allow the department to communicate on one frequency.
Fire has 50 portable and 13 mobile radios along with 50 pagers.
Cost in ERP includes portable radios (30), portable radio's encrypted (20), mobile radio's (13), pagers (50), chargers single (60), charger base (3)
plus other needed equipment. Details of all items are on file with Fire and Finance Depts.
Project #01-ERP-0125
Priority n/a
Justification
Provides radios so that the police, fire and public works can communicate on a common radio frequency during an emergency and multiple county
interoperability.
Budget Impact/Other
In 2016 the Fire radios were separated from Police for better accountability. Project was adjusted for current pricing.
2025 - 356,500 FD
2025 - 29,500 PW
Useful Life 5-7 yearsProject Name Fire Radios - Portable and Mobile Devices Category Equipment
Type Equipment
Future
Total Project Cost:$2,335,328
Total2021 2022 2023 2024 2025Expenditures
386,000386,000Equipment
386,000 386,000Total
Total2021 2022 2023 2024 2025Funding Sources
386,000386,000Equipment Replacement Fund
386,000 386,000Total
Wednesday, November 11, 2020
45
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Fire Helmets for firefighters. Helmets are used for safety of personnel at Fire and other Emergency incidents. In 2017, the NFPA and OSHA
Standard changed to recommending helmet change every 10 years.
Project #01-ERP-0126
Priority n/a
Justification
Safety of Firefighters. Current helmets useful life will be up in 2022.
Budget Impact/Other
Reoccuring every 10 years.
Useful Life 10 yearsProject Name Fire - Fire Helmets Category Equipment
Type Equipment
Future
Total Project Cost:$58,191
Total2021 2022 2023 2024 2025Expenditures
16,00016,000Equipment
16,000 16,000Total
Total2021 2022 2023 2024 2025Funding Sources
16,00016,000Equipment Replacement Fund
16,000 16,000Total
Wednesday, November 11, 2020
46
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Lucus device is used to assist CPR during full arrest. The current device was purchased in 2016 and with changed in technology, it is
recommended to update every 5 years.
Project #01-ERP-0127
Priority n/a
Justification
To continue to serve citizens of Hopkins during medical incidents.
Budget Impact/Other
Reoccurs every 5 years.
Useful Life 5 yearsProject Name Fire - Lucus Device Category Equipment
Type Equipment
Future
Total Project Cost:$98,686
Total2021 2022 2023 2024 2025Expenditures
18,00018,000Equipment
18,000 18,000Total
Total2021 2022 2023 2024 2025Funding Sources
18,00018,000Equipment Replacement Fund
18,000 18,000Total
Wednesday, November 11, 2020
47
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
Upgrade EOC
Project #01-ERP-0129
Priority n/a
Justification
The EOC has not been upgraded since the station opened in 2004. The upgrade would consist of upgrading Technology IE: TV and Video
conferencing.
Budget Impact/Other
Useful Life 20 yearsProject Name Fire - EOC Upgrade Category Equipment
Type Equipment
Future
Total Project Cost:$12,000
Total2021 2022 2023 2024 2025Expenditures
12,00012,000Equipment
12,000 12,000Total
Total2021 2022 2023 2024 2025Funding Sources
12,00012,000Equipment Replacement Fund
12,000 12,000Total
Wednesday, November 11, 2020
48
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Fire Chief
2021 2025
thru Department Fire
Description
This sytem would alert members thogh out the station when there is a call. This system will integrate with the new paging system that Hennepin
County is adopting.
Project #01-ERP-0131
Priority n/a
Justification
Help with quicker response to in coming calls. Will prepare the staion for future 24 hour shifts.
Budget Impact/Other
Useful LifeProject Name Fire - Station Alerting System Category Buildings: Fire Facilities
Type Equipment
Future
Total Project Cost:$55,000
Total2021 2022 2023 2024 2025Expenditures
55,00055,000Equipment
55,000 55,000Total
Total2021 2022 2023 2024 2025Funding Sources
55,00055,000Equipment Replacement Fund
55,000 55,000Total
Wednesday, November 11, 2020
49
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Unassigned
2021 2025
thru Department HRA
Description
4 wheel drive 3/4 ton truck to be used by Public Housing maintenance staff. Includes snow plow.
Current vehicle: 2015 Chevrolet Pickup
Project #01-ERP-0400
Priority n/a
Justification
Transportation for Public Housing Superintendent and snow plowing at various HRA properties around the city.
Budget Impact/Other
Variance from 20 year plan - none
Estimate salvage/resale value on replaced item: $1,800
Useful Life 8 yearsProject Name 4x4 3/4 Ton Truck Category Vehicles
Type Equipment
Future
Total Project Cost:$214,398
Total2021 2022 2023 2024 2025Expenditures
41,10041,100Vehicles
41,100 41,100Total
Total2021 2022 2023 2024 2025Funding Sources
41,10041,100HRA - Housing and
Redevelopment Authority
41,100 41,100Total
Wednesday, November 11, 2020
50
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Finance Director
2021 2025
thru Department HRA
Description
Color copy machine to service the needs of the HRA. High volume product copier to do a variety of copying tasks.
Current equipment: Imagistics ZB35
Project #01-ERP-0401
Priority n/a
Justification
Daily use to make copies of correspondence, forms and rental documents. Periodically produce documents such as resident newsletters and
marketing. Machine will duplex, sort, collate and staple copies.
Budget Impact/Other
Variance from 20 year plan - New item.
Estimate salvage/resale value on replace item: $ - 0 -
Useful Life 8 yearsProject Name HRA Copier Category Equipment
Type Equipment
Future
Total Project Cost:$76,876
Total2021 2022 2023 2024 2025Expenditures
16,50016,500Equipment
16,500 16,500Total
Total2021 2022 2023 2024 2025Funding Sources
16,50016,500HRA - Housing and
Redevelopment Authority
16,500 16,500Total
Wednesday, November 11, 2020
51
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Pavilion Manager
2021 2025
thru Department Pavilion
Description
26" to 28" battery operated walk behind floor scrubber. Floor scrubber is used to clean the arenas concrete floor and tiled surfaces throughout the
building.
2014 cost = $8,651.94
Asset ID #5172
Project #01-ERP-1003
Priority n/a
Justification
Replace the existing floor scrubber with new model. Current floor scrubber was purchased in 2014 and is scheduled to be replaced in 2024.
Budget Impact/Other
Variance from 20 year plan - New item
Estimate salvage/resale value on replaced item: $
Useful Life 10 yearsProject Name Pavilion - Floor Scrubber Category Equipment
Type Equipment
Future
Total Project Cost:$48,167
Total2021 2022 2023 2024 2025Expenditures
11,60011,600Equipment
11,600 11,600Total
Total2021 2022 2023 2024 2025Funding Sources
11,60011,600PA - Pavilion Fund
11,600 11,600Total
Wednesday, November 11, 2020
52
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Marked patrol vehicles used by patrol officers to respond to calls, enforce traffic laws and perform general patrol duties.
Fleet consists of 7 marked patrol vehicles
Project #01-ERP-0200
Priority n/a
Justification
Set up and marking of police vehicles must conform to Minnesota law and POST standards. Vehicles contain secure data and radio equipment for
routine and emergency operations. Vehicles contain secure seating for prisoner transport.
Budget Impact/Other
In 2019, no vehicles were purchased. Planned reallocation to body camera project.
Useful Life 3 yearsProject Name Marked Patrol Vehicles (7)Category Vehicles
Type Equipment
Future
Total Project Cost:$3,287,200
Total2021 2022 2023 2024 2025Expenditures
623,300161,100 110,000 117,400 117,400 117,400Vehicles
161,100 110,000 117,400 117,400 117,400 623,300Total
Total2021 2022 2023 2024 2025Funding Sources
623,300161,100 110,000 117,400 117,400 117,400Equipment Replacement Fund
161,100 110,000 117,400 117,400 117,400 623,300Total
Wednesday, November 11, 2020
53
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Marked patrol vehicle used by patrol officers to respond to calls, enforce traffic laws and perform general patrol duties.
4 year rotation.
Current vehicle: Ford Utility
Project #01-ERP-0201
Priority n/a
Justification
Set up and marking of police vehicles must conform to Minnesota law and POST standards. Vehicles contain secure data and radio equipment for
routine and emergency operations. Vehicles contain secure seating for prisoner transport.
Budget Impact/Other
Useful Life 4 yearsProject Name Sergeant's Vehicle Category Vehicles
Type Equipment
Future
Total Project Cost:$596,642
Total2021 2022 2023 2024 2025Expenditures
121,15457,000 64,154Vehicles
57,000 64,154 121,154Total
Total2021 2022 2023 2024 2025Funding Sources
121,15457,000 64,154Equipment Replacement Fund
57,000 64,154 121,154Total
Wednesday, November 11, 2020
54
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Marked patrol vehicle used by Parking Enforcement Officer to respond to calls for service, enforce parking laws, and perfom duties as assigned.
Current Vehicle: (1) 2016 Ford Utility
Project #01-ERP-0202
Priority n/a
Justification
Use by parking enforcement officers in the course of their duties enforcing parking regulations in the downtown area.
Set up and marking of police vehicles must conform to Minnesota law and POST standards. Vehicles contain secure data and radio equipment for
routine and emergency operations. Vehicles contain secure seating for prisoner transport.
Budget Impact/Other
2016 - Change in replacement schedule due to full time use of vehicle and change of position responsibilities. Next replacement scheduled for
2021 from 2026
Useful Life 5 yearsProject Name PSO / Parking Enforcement Vehicle Category Vehicles
Type Equipment
Future
Total Project Cost:$412,572
Total2021 2022 2023 2024 2025Expenditures
53,70053,700Vehicles
53,700 53,700Total
Total2021 2022 2023 2024 2025Funding Sources
53,70053,700Equipment Replacement Fund
53,700 53,700Total
Wednesday, November 11, 2020
55
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Four wheel drive marked patrol vehicle used by PSOs to respond to calls for service, handle animal complaints, and perform other duties
associated with department operations.
Current vehicle: 2018 Ford F150 (#212)
Project #01-ERP-0203
Priority n/a
Justification
Vehicle is normally used by public service officers for a wide variety of uses such as transporting animals, prisoners and equipment. The 4 wheel
drive vehicle is also used at times as a patrol vehicle, particularly in the winter in extreme snow conditions.
Budget Impact/Other
2016 - Variance from 20 year plan - Change in replacement schedule due to full time use of vehicle. Changing useful life from 6 years to 4 years
Useful Life 4 yearsProject Name PSO - Utility 4x4 Category Vehicles
Type Equipment
Future
Total Project Cost:$795,189
Total2021 2022 2023 2024 2025Expenditures
72,10072,100Vehicles
72,100 72,100Total
Total2021 2022 2023 2024 2025Funding Sources
72,10072,100Equipment Replacement Fund
72,100 72,100Total
Wednesday, November 11, 2020
56
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Squad car camera systems are used to document events inside and outside of the patrol vehicles. The cameras utilize a forward facing camera and a
prisoner transport area camaera.
Body cameras capture interactions between the officers and the public for transparency. Body cameras also capture evidence used in future court
proceedings.
Project #01-ERP-0212
Priority n/a
Justification
The police vehicle cameras are a necessary component of the patrol vehicles. Evidentiary information is collected from the cameras and often used
in court. Cameras also provide a snapshot of an officers interaction with the public so we are able to maintain transparency and public trust with
our operations.
Budget Impact/Other
Integrated camera system - 11 Squad car cameras and 24 body cameras
Squad cameras 6,000/each. Body cameras 1,200/each.
Annual costs/maintenance = $17,325 (Body Cameras 3 year warranty, Squad Cameras 5 year warranty)
Useful Life 5 yearsProject Name Squad Car Camera Systems/ Body Worn Camera Category Equipment
Type Equipment
Future
Total Project Cost:$866,921
Total2021 2022 2023 2024 2025Expenditures
160,000160,000Equipment
160,000 160,000Total
Total2021 2022 2023 2024 2025Funding Sources
152,000152,000Equipment Replacement Fund
8,0008,000PKG - Parking Fund
160,000 160,000Total
Wednesday, November 11, 2020
57
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
12 Tactical Ballistical Vests worn by members of the Hopkins Police Department SWAT (Special Weapons and Tactics) team. These vests offer a
higher level of protection for officers involved in high risk situations; this protection offers a higher level of ballistic protection compared to
regular duty vests. SWAT team members also require ballistic helmets on the same rotational cycle. Equipment breakdown: 12 vests @ $4,215 =
$50,580. 12 ballistic helmets @ $642 = $7,716. 2 New protective shields @ $2,864 = $5,729. 12 Radio headsets @ $1,042 = $12,500.
Project #01-ERP-0214
Priority 3 Important
Justification
Variance - Change in vendor equipment pricing and SWAT team staffing levels. Current price is reflective of a twelve person (fully staffed)
SWAT team with current vendor pricing.
Budget Impact/Other
5 year replacement schedule
Useful Life 5 yearsProject Name Tactical Ballistic Vests / Helmets - SWAT Category Equipment
Type Equipment
Future
Total Project Cost:$623,626
Total2021 2022 2023 2024 2025Expenditures
76,51276,512Equipment
76,512 76,512Total
Total2021 2022 2023 2024 2025Funding Sources
76,51276,512Equipment Replacement Fund
76,512 76,512Total
Wednesday, November 11, 2020
58
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief
2021 2025
thru Department Police
Description
Portable radios used by the police departments to allow the department to communicate on one frequency.
Estimated Replacement Cost
Portable - $4,500 x 50 = $225,000
Plus chargers, shoulder mic's and batteries - $11,300
TOTAL = $236,300
In 2016 we will need to replace the portables as the current model will no longer be supported by Hennepin County.
Project #01-ERP-0215
Priority n/a
Justification
Provides radios so that the police, fire and public works can communicate on a common radio frequency during an emergency and multiple county
interoperability.
Budget Impact/Other
Radio's have a 7-10 year life expectancy. Portables need replacement due to manufacturer issues and county requirements. Increase in cost from
$3,800 to $4,500 per radior. Mobile radios were removed and now will be included with the vehicles as they are replaced.
Estimate salvage/resale value on replaced item: $0
Useful Life 5-7 yearsProject Name Police - Portable Radios Category Equipment
Type Equipment
Future
Total Project Cost:$1,906,203
Total2021 2022 2023 2024 2025Expenditures
290,000290,000Equipment
290,000 290,000Total
Total2021 2022 2023 2024 2025Funding Sources
290,000290,000Equipment Replacement Fund
290,000 290,000Total
Wednesday, November 11, 2020
59
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Captain
2021 2025
thru Department Police
Description
Tasers can prevent officers and the public from injuries.Taser technology continues to develop and are worn/ carried 24/7. Tasers have a useful life
expectancy of approximately 5 years.
Project #01-ERP-0217
Priority n/a
Justification
Tasers are a crtical tool for Law Enforcement for control purposes during use of force encounters.
Budget Impact/Other
35- X2 Tasers, each officer has their own taser.
Total overall cost of Tasers in 2020 was $81,130 ($2,1318 x 35)
Useful Life 4 yearsProject Name Taser Replacement Category Equipment
Type Equipment
Future
Total Project Cost:$721,905
Total2021 2022 2023 2024 2025Expenditures
90,00090,000Equipment
90,000 90,000Total
Total2021 2022 2023 2024 2025Funding Sources
90,00090,000Equipment Replacement Fund
90,000 90,000Total
Wednesday, November 11, 2020
60
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief/IT
2021 2025
thru Department Police
Description
Building Video Server hardware and associated software is used to store video recorded by the cameras in and around the police department
including interview rooms as well as booking. We record approximately 6 TB of video every 2-3 weeks. Large amounts of storage are required
for 30 days of archival storage on the server itself.
Project #01-ERP-0218
Priority n/a
Justification
Maintenance agreement with software vendor needs to be renewed every three years. Computer hardware should be refreshed around the same
time to minimize drive failure and take advantage of new storage technology.
Budget Impact/Other
Variance from 20 year plan - Change in replacement schedule and estimated cost. Current equipment was purchased with DTF funding. Beginning
in 2020 it will be funded with ERP funds.
Estimate salvage/resale value on replaced item: $-0-
Useful Life 4 yearsProject Name Building Video Server Category Equipment
Type Equipment
Future
Total Project Cost:$93,000
Total2021 2022 2023 2024 2025Expenditures
22,00022,000Equipment
22,000 22,000Total
Total2021 2022 2023 2024 2025Funding Sources
22,00022,000Equipment Replacement Fund
22,000 22,000Total
Wednesday, November 11, 2020
61
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief/IT
2021 2025
thru Department Police
Description
Mobile Data Computers are used in the squad cars to receive calls for service from dispatch, query information from criminal justice databases, and
facilitate communication between squad cars.
Replacement in 2019 for 12 computers. To be replaced in 2024.
Project #01-ERP-0220
Priority n/a
Justification
Mobile Data Computers have a limited life expectancy. The computers facilitate the basic response to emergency calls for service to which police
officers respond. Vital information is forwarded to officers via the mobile data computers. Officers complete investigative reports, issue traffic
related warnings and citations, and process arrest incidents from the mobile data computers.
As technology evolves the officers must be able to access information using up to date computers that can process the large amount of data and
applications. Mobile data computers are currently used to host the squad car video camera system and have the potential to be integrated with a
possible body worn camera.
Budget Impact/Other
Change in replacement year to accurately reflect life expectancy in relation to when the computers were purchased.
Useful Life 5 yearsProject Name Squad Computers Category Equipment
Type Equipment
Future
Total Project Cost:$561,242
Total2021 2022 2023 2024 2025Expenditures
90,00090,000Equipment
90,000 90,000Total
Total2021 2022 2023 2024 2025Funding Sources
90,00090,000Equipment Replacement Fund
90,000 90,000Total
Wednesday, November 11, 2020
62
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Police Chief/IT
2021 2025
thru Department Police
Description
LETG - Records Management System was purchased at the end of 2012. This maintains all police records and reports.
Project #01-ERP-0221
Priority n/a
Justification
A new RMS system may be needed by 2022.
Budget Impact/Other
Current cost to maintain system is $29,368 anually.
Useful LifeProject Name Records Management System Category Equipment
Type Equipment
Future
Total Project Cost:$150,000
Total2021 2022 2023 2024 2025Expenditures
150,000150,000Equipment
150,000 150,000Total
Total2021 2022 2023 2024 2025Funding Sources
150,000150,000Equipment Replacement Fund
150,000 150,000Total
Wednesday, November 11, 2020
63
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Parks/Forestry
Description
Pickup used by Park Division of Public Works.
Project #01-ERP-0800
Priority n/a
Justification
Budget Impact/Other
Estimate salvage/resale value on replaced item: $
Useful Life 10 yearsProject Name 1/2 Ton Pickup Truck Category Vehicles
Type Equipment
Future
Total Project Cost:$173,369
Total2021 2022 2023 2024 2025Expenditures
35,40035,400Vehicles
35,400 35,400Total
Total2021 2022 2023 2024 2025Funding Sources
35,40035,400Equipment Replacement Fund
35,400 35,400Total
Wednesday, November 11, 2020
64
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Parks/Forestry
Description
Truck is used for hauling brush and logs in the Forestry department.
Current vehicle: 2007 International LP4600 Log Truck (#811)
Project #01-ERP-0804
Priority n/a
Justification
Budget Impact/Other
Variance from 20 year plan - 50% Equipment Replacement/50% Refuse - increase amount to $105,000 to reflect actual cost.
Estimated useful life reduced from 20 to 15 years.
Useful Life 15 yearsProject Name Log Truck Category Vehicles
Type Equipment
Future
Total Project Cost:$523,484
Total2021 2022 2023 2024 2025Expenditures
163,600163,600Vehicles
163,600 163,600Total
Total2021 2022 2023 2024 2025Funding Sources
81,80081,800Equipment Replacement Fund
81,80081,800RF - Refuse Fund
163,600 163,600Total
Wednesday, November 11, 2020
65
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Parks/Forestry
Description
Riding mowers used by Parks Division of Public Works.
Current equipment: 2004 Toro Zero Turn (#826), 2006 Jacobson Rotary Mower (#823)
Project #01-ERP-0808
Priority 1 Urgent
Justification
Mowing city parks and right of ways.
Move replacement of #826 to 2021 - Ran 10 years past useful life
Move replacement of #823 to 2021
Both replacements of current vehicles were held off in 2020 due to the COVID-19 Pandemic.
Budget Impact/Other
2021 - Replace 2004 Zero Turn #826 at $15,000
2021 - Replace 2006 Jacobson #823 at $35,000
The Jacobson will be replaced with 7500-D Zmaster Toro Zero Turn
Useful Life 6 yearsProject Name Riding Mowers (2)Category Equipment
Type Equipment
Future
Total Project Cost:$323,930
Total2021 2022 2023 2024 2025Expenditures
50,00050,000Equipment
50,000 50,000Total
Total2021 2022 2023 2024 2025Funding Sources
50,00050,000Equipment Replacement Fund
50,000 50,000Total
Wednesday, November 11, 2020
66
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Parks/Forestry
Description
Used to haul multiple riding mowers
Current trailor: Unit #845, 1997 Remackle Trailer, overhauled/refurbished in 2016
Project #01-ERP-0814
Priority n/a
Justification
Allows one truck to pull two riding mowers to parks
Budget Impact/Other
Variance from 20 year plan - extend life 4 years due to overhaul/refurbishment.
Estimate salvage/resale value on replaced item: $
2016-Increased estimated replacement cost from $2,200 to $10,000
Useful Life 15 yearsProject Name Trailer Flatbed Category Equipment
Type Equipment
Future
Total Project Cost:$26,980
Total2021 2022 2023 2024 2025Expenditures
10,00010,000Equipment
10,000 10,000Total
Total2021 2022 2023 2024 2025Funding Sources
10,00010,000Equipment Replacement Fund
10,000 10,000Total
Wednesday, November 11, 2020
67
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Pickup used by various divisions of Public Works.
Current vehicle: 2013 Ford F-150 (#301)
Project #01-ERP-0300
Priority n/a
Justification
Light hauling and transportation for supervisors. Maintenance garage service vehicle.
Budget Impact/Other
Variance from 20 year plan - Move up from 2015 to 2013. Replace with 1/2 ton 4x4 pickup. Reduce amount from 33,600 to 21,500..
Estimate salvage/resale value on replaced item: $1,500
Useful Life 10 yearsProject Name 4x4 1/2 Ton Pickup with Plow Category Vehicles
Type Equipment
Future
Total Project Cost:$114,200
Total2021 2022 2023 2024 2025Expenditures
28,90028,900Vehicles
28,900 28,900Total
Total2021 2022 2023 2024 2025Funding Sources
28,90028,900Equipment Replacement Fund
28,900 28,900Total
Wednesday, November 11, 2020
68
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Truck is used in the Street Division of Public Works.
Current vehicles: 2000 Ford F450 (#805) & 2011 Ford F350 (#308)
Project #01-ERP-0303
Priority n/a
Justification
Vehicle used by various departments for street and park maintenance and light hauling.
Budget Impact/Other
Variance from 20 year plan - move back from 2009 to 2010.
Estimated useful life reduced from 12 to 8 years.
Estimate salvage/resale value on replaced item: $3,500
Useful Life 10 yearsProject Name 1 Ton Dump Truck (2)Category Vehicles
Type Equipment
Future
Total Project Cost:$281,600
Total2021 2022 2023 2024 2025Expenditures
102,90053,400 49,500Vehicles
53,400 49,500 102,900Total
Total2021 2022 2023 2024 2025Funding Sources
102,90053,400 49,500Equipment Replacement Fund
53,400 49,500 102,900Total
Wednesday, November 11, 2020
69
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Boom truck used in Street and Traffic Divisions of Public Works.
Current vehicle: 2012 Ford F450 (#309)
Project #01-ERP-0304
Priority n/a
Justification
Vehicle used by Traffic Department for signal and light pole maintenance.
Budget Impact/Other
Variance from 20 year plan - Increase amount to reflect actual.
Estimate salvage/resale value on replaced item: $8,000
Useful life moved from 17 years to 12 years.
Useful Life 12 yearsProject Name 1 Ton Traffic Boom Truck Category Vehicles
Type Equipment
Future
Total Project Cost:$218,900
Total2021 2022 2023 2024 2025Expenditures
136,400136,400Vehicles
136,400 136,400Total
Total2021 2022 2023 2024 2025Funding Sources
136,400136,400Equipment Replacement Fund
136,400 136,400Total
Wednesday, November 11, 2020
70
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Single axle dump truck used by various division of Public Works.
Current vehicles: 2005 Freightliner M2 106 (#312) and 2011 Freightliner MZ-1068 (#311)
Project #01-ERP-0305
Priority n/a
Justification
Vehicle used for heavy hauling, snow plowing and sanding.
Moved single axel dump truck due in 2018 to a tandem axel dump truck in 2018. Done to increase snow hauling and other material hauling
capacity.
Budget Impact/Other
Variance from 20 year plan - Move 1 truck from single axle to tandem axel to increase hauling capacity for snow and road materials.
Estimate salvage/resale value on replaced item: $4,500 each
We will then have 2 single axel (change from 3) dump trucks and 2 (change from 1) tandem axel dump trucks.
Estimated useful life reduced from 17 to 15 years.
Useful Life 15 yearsProject Name Single Axle Dump Truck (2)Category Vehicles
Type Equipment
Future
Total Project Cost:$643,000
Total2021 2022 2023 2024 2025Expenditures
225,000225,000Vehicles
225,000 225,000Total
Total2021 2022 2023 2024 2025Funding Sources
225,000225,000Equipment Replacement Fund
225,000 225,000Total
Wednesday, November 11, 2020
71
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Current equipment: 2005 Caterpillar 938G (#322)
Project #01-ERP-0308
Priority n/a
Justification
Budget Impact/Other
Variance from 20 year plan - None
Estimate salvage/resale value on replaced item: $
Useful Life 15-18 yearsProject Name Front End Loaders (2)Category Equipment
Type Equipment
Future
Total Project Cost:$848,600
Total2021 2022 2023 2024 2025Expenditures
268,600268,600Equipment
268,600 268,600Total
Total2021 2022 2023 2024 2025Funding Sources
268,600268,600Equipment Replacement Fund
268,600 268,600Total
Wednesday, November 11, 2020
72
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Public Works: Streets/Traffic
Description
Loading trucks, landscape work, snow removal, material handling.
Current equipment: 2011 Bobcat S650 Skid-Steer Loader (#325)
Project #01-ERP-0309
Priority n/a
Justification
Budget Impact/Other
Estimate salvage/resale value on replaced item: $
Useful Life 10 yearsProject Name Skid Loader (2)Category Equipment
Type Equipment
Future
Total Project Cost:$258,900
Total2021 2022 2023 2024 2025Expenditures
50,00050,000Equipment
50,000 50,000Total
Total2021 2022 2023 2024 2025Funding Sources
50,00050,000Equipment Replacement Fund
50,000 50,000Total
Wednesday, November 11, 2020
73
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Refuse
Description
Refuse truck used by Refuse Utility Division of Public Works.
Current vehicle: 2011 Freightliner Rapid Rail (#900)
Project #01-ERP-0900
Priority n/a
Justification
Residential waste pick up.
Budget Impact/Other
Variance from 20 year plan - increase cost to reflect actual
Estimate salvage/resale value on replaced item: $18,000
Useful Life 8 yearsProject Name Refuse Truck (RAP-R) (2)Category Vehicles
Type Equipment
Future
Total Project Cost:$1,462,600
Total2021 2022 2023 2024 2025Expenditures
545,500270,300 275,200Vehicles
270,300 275,200 545,500Total
Total2021 2022 2023 2024 2025Funding Sources
545,500270,300 275,200RF - Refuse Fund
270,300 275,200 545,500Total
Wednesday, November 11, 2020
74
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Sewer
Description
Portable generator used by Water/Sewer Divisions of Public Works.
Current equipment: 2022 Generator (#535), "PW Generator " 2010 Caterpillar C15 (#537)
Project #01-ERP-0555
Priority n/a
Justification
Emergency back up generator for lift stations and pumps, off site power for lights and welding.
Budget Impact/Other
Estimated useful life reduced from 25 to 20 years.
Estimate salvage/resale value on replaced item: $2,500
Useful Life 20 yearsProject Name Generator (2)Category Equipment
Type Equipment
Future
Total Project Cost:$79,000
Total2021 2022 2023 2024 2025Expenditures
43,00043,000Equipment
43,000 43,000Total
Total2021 2022 2023 2024 2025Funding Sources
43,00043,000SF - Sanitary Sewer Fund
43,000 43,000Total
Wednesday, November 11, 2020
75
EQUIPMENT REPLACEMENT PLAN
City of Hopkins, MN - ERP Contact Public Works Director
2021 2025
thru Department Sewer
Description
Sewer inspection Crawler (Televising Camera) with Ford Transit Van used by Utility crews to televise sanitary and storm sewers annually.
Project #01-ERP-0560
Priority n/a
Justification
Better effectiviness, efficiency and cost. Currently the televising for our sanitary lines go out for bids, RFP's for 2020's work averaged over
$33,000. The payback would be 6 years and with the camera's useful life as 12-15 years, we would benefit 6-9 years of induring no costs other than
maintenance before needing to replace. We're at the mercy of the contractor for a timley completion of televising, the best scenario is to televise
immediately after jetting to make sure the sanitary lines are clean of debris or damage. With this we can react immediately to resolve any issues we
may find.
Budget Impact/Other
Estimate salvage/resale value at the end of useful life is $30,000.
Useful Life 12 yearsProject Name Sewer Televising Camera and Van Category Utilities: Municipal Sanitary Se
Type Equipment
Future
Total Project Cost:$180,000
Total2021 2022 2023 2024 2025Expenditures
180,000180,000Equipment
180,000 180,000Total
Total2021 2022 2023 2024 2025Funding Sources
180,000180,000SF - Sanitary Sewer Fund
180,000 180,000Total
Wednesday, November 11, 2020
76
TWENTY-YEAR
REPLACEMENT SCHEDULE
77
11/17/2020 EQUIPMENT REPLACEMENT SCHEDULE
Net General Fund 20 Year Average:1,400,100$
INFLATION FACTOR 3.0%
REPL
EQUIPMENT /VEHICLES YRS 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
ACTIVITY CENTER
ERP-0032 Sound System 15 13,700
ERP-0035 Floor Scrubber 10 6,700 9,000
ERP-0037 Security System Upgrade 15-18 20,000 32,000
ERP-0038 Kitchen Storage 30 17,000 12,000
ERP-0039 Dishwasher 30
ERP-0041 A/V Replacement & Upgrade 20 62,624
SUBTOTAL 82,624 17,000 12,000 6,700 13,700 9,000 32,000
ARTS CENTER
ERP-1101 Carpet Extractor 10 7,000
ERP-1102 Kitchen Catering Equipment 12 7,100
ERP-1105 Community Room A/V 7 13,500 16,600 20,400
ERP-1107 Theater Projection Screen 10 6,700 9,000
ERP-1109 Floor Scrubber 10 10,800 14,500
ERP-1112 Surveillance System 5 6,000 8,000 10,000
13,500 6,700 10,800 7,100 6,000 16,600 15,000 9,000 14,500 20,400 10,000
COMMUNITY SERVICES
ERP-0010 Election Booths 20 6,500
ERP-0051 Exterior Security Camera System 15 65,000
ERP-0052 Electronic Inspections Processing 5-7 16,231 21,800 29,200
EQUIPMENT SUBTOTAL 16,231 6,500 21,800 65,000 29,200
FIRE
ERP-0100 Tele-Squirt E-2 10 1,000,000 1,350,000
ERP-0101 Fire Pumper E-3 20 722,400
ERP-0105 Quick Attack Pumper/Rescue R-8 10 725,000 974,000
ERP-0106 Aerial Truck 20 1,572,000
VEHICLES SUBTOTAL 725,000 722,400 1,000,000 1,572,000 974,000 1,350,000
ERP-0107 Air Compressor 15 54,400
ERP-0108 Breathing Apparatus (45) (SCBA)10 250,000 336,000
ERP-0109 Extrication Tool (2)10 32,000 36,900 40,300
ERP-0112 Thermal Imaging Camera (2)10 16,180 20,700
ERP-0113 Emergency Preparedness Siren 20 38,500
ERP-0114 Floor Scrubber 12 20,300 28,900
ERP-0125 Radios-Portable & Mobile 5-7 386,000 431,498 514,700
ERP-0126 Helmets 10 16,000 22,000
ERP-0127 Lucus Device 5 18,000 20,000 24,000 30,000
ERP-0128 Hose Replacement 20 70,000
ERP-0129 EOC Upgrade 20 12,000
ERP-0131 Station Alerting System 55,000
EQUIPMENT SUBTOTAL 28,000 50,000 707,180 38,500 20,300 20,000 36,900 485,898 62,300 24,000 356,700 514,700 30,000 28,900 70,000
IT
ERP-0003 City Hall - Network Upgrade 1 22,000 25,000 26,250 27,038 27,849 28,684 29,545 30,431 31,344 32,285 33,253 34,251 35,278 36,337 37,427 38,550 39,706 40,897 42,124 43,388
ERP-0004 Phone System 8 89,600 110,700 140,000
ERP-0005 Financial Software 7 315,000
ERP-0006 Computers 3-5 33,075 34,729 36,465 37,559 38,686 40,620 42,651 44,784 47,023 49,374 51,843 54,435 57,157 60,015 63,015 66,166 69,474 72,948 76,596 80,425
ERP-0009 Network Infrastructure Upgrade 15 23,400
ERP-0012 Core Network Switch 6 20,000 24,000 27,000
ERP-0014 Distribution Network Switches 5 57,000 65,000 75,000
ERP-0015 Backup Server 3 72,120 74,000 78,000 82,000 87,000
ERP-0017 Office 365 1 33,000 44,000 44,000 45,320 46,680 49,000 51,000 54,000 57,000 60,000 63,000 66,000 69,000 72,000 75,000 78,000 80,000 85,000 88,000 90,000
ERP-0018 RSA/Netmotion VPN 5 24,000 27,000 31,500
ERP-0019 Email Threat Protection 5 26,500 30,000
ERP-0020 Patching Automation Software 5 10,000 10,000 10,000 10,000 10,300 10,000 10,000 10,000 50,000 10,000 10,000 10,000 10,000 60,000 10,000 10,000 10,000 10,000 10,000 10,000
ERP-0022 Windows 10 Enterprise Upgrade 1 21,000 42,000 42,000 63,000
ERP-0211 Police - Network Server (3)3 22,000 25,000 26,250 27,038 27,849 28,684 29,545 30,431 31,344 32,285 33,253 34,251 35,278 36,337 37,427 38,550 39,706 40,897 42,124 43,388
EQUIPMENT SUBTOTAL 141,075 204,129 346,685 229,954 523,364 230,989 162,741 169,647 345,212 272,943 302,049 198,937 288,713 321,688 297,869 345,265 238,887 249,743 430,344 267,201
POLICE
ERP-0200 Squad 3 161,100 110,000 117,400 117,400 117,400 128,000 128,000 128,000 140,000 140,000 140,000 153,200 153,200 153,000 157,000 160,000 165,000 170,000 175,000 180,000
ERP-0201 Sergeant Vehicle #209 4 57,000 64,154 72,200 81,300 91,500
ERP-0202 Parking Vehicle #211 10 53,700 60,000 65,000
ERP-0203 PSO Utility 4x4 #212 6 72,100 86,100 90,000 92,000 107,000
ERP-0205 SWAT Vehicle #240 15 77,900
VEHICLES SUBTOTAL 271,800 182,100 117,400 117,400 181,554 274,100 128,000 128,000 212,200 230,000 217,900 153,200 234,500 245,000 157,000 225,000 256,500 170,000 282,000 180,000
ERP-0208 Computer System 20 200,000
ERP-0212 Mobile Data Computers/Digital Cameras 7 160,000 196,800 242,000
ERP-0214 Tactical Ballistic Vests (9)5 76,512 45,000 50,000 58,000
ERP-0215 Radios-Portable & Mobile 5-7 290,000 310,000 325,000
ERP-0217 Taser Replacement 4 90,000 101,300 114,000 128,300 144,400
ERP-0218 Building Video Server 4 22,000 24,800 27,900 31,400 35,300
ERP-0220 Squad Cams 5 90,000 104,335 120,952 140,217
ERP-0222 Body Worn Camera 5 150,000 165,000 175,000 185,000 214,500
EQUIPMENT SUBTOTAL 150,000 478,512 250,000 291,100 45,000 414,335 338,700 175,000 250,000 120,952 484,700 185,000 300,000 319,917 214,500
78
REPL
EQUIPMENT /VEHICLES YRS 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
P.W. BLDG./EQUIPMENT SVCS
ERP-0710 1/2 Ton Truck 10 42,100 47,000
ERP-0711 Vehicle Washer 12 8,300
ERP-0712 4x4 3/4 Ton Pick-up Truck 15 52,000
ERP-0715 PW - Forklift 15 28,000
42,100 8,300 28,000 52,000 47,000
P.W. ENGINEERING
ERP-0700 Engineering Van 10 28,900 38,800
28,900
P.W. PARKS & FORESTRY
ERP-0800 1/2 Ton Truck 10 35,400 47,600
ERP-0801 4x4 3/4 Ton Truck 8 108,000 115,000
ERP-0802 3/4 Ton Utility Truck 10 48,700 65,400
ERP-0804 Log Truck (50% w/Refuse)20 81,800 128,000
ERP-0805 Aerial Lift 20 228,900
ERP-0806 Tractor 30 52,000
ERP-0807 Truckster 15 17,140 53,200
ERP-0808 Riding Mower (6 50,000 59,700 71,300 85,100
ERP-0810 Large Turf Mower (#825)10 130,000 175,000
ERP-0812 Stump Cutter 20 45,000
ERP-0813 Brush Clipper 20 43,700
ERP-0814 Trailer Flatbed 15 10,000 12,500
ERP-0815 Skid Loader 12 45,600 50,000
ERP-0816 Toolcat 8 80,200 101,600
ERP-0817 Grass Seed Applicator 20 17,900
VEHICLES SUBTOTAL 50,000 117,200 10,000 80,200 76,840 108,000 175,600 295,500 162,600 206,800 127,500 173,000 50,000 260,100 65,400
P.W. STREETS/TRAFFIC
ERP-0300 4x4 3/4 Ton Truck/Plow 10 28,900 38,800
ERP-0301 4x4 3/4 Ton Truck/Plow 8 38,500 48,800
ERP-0302 4x2 1 Ton Dump Truck 12 77,800
ERP-0303 1 Ton Dump Truck 12 53,400 49,500 76,100
ERP-0304 1 Ton Boom Truck 17 136,400
ERP-0305 Single Axle Dump Truck 17 225,000 210,600 372,000
ERP-0306 Tandem Dump Truck 17 286,000 294,000
ERP-0307 Water Truck 22 201,000
ERP-0308 Front End Loader 15 268,600 415,000
ERP-0309 Skid Loader 12 50,000 59,700 71,300
ERP-0311 Sweeper 20
ERP-0312 Roller 20 82,000
ERP-0313 Striper 12 16,000
ERP-0314 Paver 20 120,000
ERP-0315 Snow Blower 20 117,000
ERP-0316 Trailer 20 4,900
ERP-0317 Sign Machine 10 18,100 24,000
ERP-0319 Regenerative Air Sweeper 20 210,000
ERP-0320 Planer 20 18,600
ERP-321 Wheel Loader 20 308,000
VEHICLES SUBTOTAL 328,400 165,300 318,100 56,600 269,700 226,600 82,700 219,600 120,000 38,800 599,200 294,000 24,000 82,000 1,095,000
HRA
ERP-0400 4x4 3/4 Ton Truck 8 41,100 52,100 66,000
ERP-0401 Copier 8 16,500 20,900
SUBTOTAL 16,500 41,100 20,900 52,100 66,000
PAVILION
ERP-1000 Ice Resurfacer 12 165,000 235,200
ERP-1001 Electric Ice Edger 12 8,900 12,700
ERP-1002 Arena Scoreboard 20 12,000
ERP-1003 Floor Scrubber 10 11,600 15,600
ERP-1004 Scissor Lift 15 16,200
SUBTOTAL 11,600 185,900 16,200 15,600 247,900
REFUSE
ERP-0900 Refuse Truck (RAP-R)10 270,300 275,200 363,200 369,800
ERP-0901 Refuse Truck (Rear-L)10 136,500
ERP-0803 Swap Loader 20 171,000
ERP-0804 Log Truck (50% w/Forestry)20 81,800
SUBTOTAL 270,300 81,800 275,200 363,200 136,500 171,000 369,800
WATER
ERP-0500 1./2 Ton Truck 10 36,000 54,000
ERP-0501 3/4 Ton Utility Truck 10 46,900 63,000
ERP-0502 Backhoe 20 153,700
SUBTOTAL 46,900 36,000 153,700 63,000 54,000
79
REPL
EQUIPMENT /VEHICLES YRS 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
SEWER
ERP-0550 4x4 3/4 Ton Truck 10 40,300 54,200
ERP-0551 3/4 Ton Utility Truck 10 45,200 54,000
ERP-0552 Jet Vactor 20
ERP-0555 Generator 25 43,000
ERP-0560 Televising Camera and Van 12 180,000 256,600
SUBTOTAL 223,000 85,500 256,600 108,200
TOTALS 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
GENERAL FUND-VEHICLES/EQUIP 321,800 510,500 1,124,900 445,500 181,554 1,204,300 1,204,840 2,077,700 614,400 608,200 437,500 273,200 1,409,900 1,103,000 451,000 462,300 1,861,500 220,000 1,637,100 245,400
GENERAL FUND-OTHER EQUIP 223,699 399,129 887,197 479,954 1,246,775 276,189 474,141 234,647 804,746 293,143 1,148,447 436,237 590,713 442,640 1,204,269 539,265 814,787 579,743 779,161 551,701
HRA - 16,500 41,100 20,900 52,100 66,000
ARTS CENTER - 13,500 6,700 10,800 7,100 6,000 16,600 15,000 9,000 14,500 20,400 10,000
REFUSE 270,300 - 81,800 275,200 363,200 136,500 171,000 369,800
PAVILION - - 11,600 185,900 16,200 15,600 247,900
WATER - - 46,900 36,000 153,700 63,000 54,000
SEWER - 223,000 85,500 256,600 108,200
GENERAL FUND TOTAL 545,499 909,629 2,012,097 925,454 1,428,329 1,480,489 1,678,981 2,312,347 1,419,146 901,343 1,585,947 709,437 2,000,613 1,545,640 1,655,269 1,001,565 2,676,287 799,743 2,416,261 797,101
HRA TOTAL - 16,500 41,100 20,900 52,100 66,000
ARTS CENTER FUND TOTAL - 13,500 6,700 10,800 7,100 6,000 16,600 15,000 9,000 14,500 20,400 10,000
ENTERPRISE FUNDS TOTAL 270,300 223,000 81,800 11,600 275,200 318,300 36,000 16,200 363,200 290,200 171,000 272,200 432,800 162,200 247,900
TOTAL ALL FUNDS 815,799 1,162,629 2,134,997 943,754 1,714,329 1,805,889 1,720,981 2,312,347 1,451,946 922,243 2,001,247 1,014,637 2,171,613 1,826,840 2,102,569 1,184,165 2,686,287 1,047,643 2,482,261 797,101
GENERAL FUND SALVAGE 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000 40,000
NET GENERAL FUND 505,499 869,629 1,972,097 885,454 1,388,329 1,440,489 1,638,981 2,272,347 1,379,146 861,343 1,545,947 669,437 1,960,613 1,505,640 1,615,269 961,565 2,636,287 759,743 2,376,261 757,101
20 YEAR AVERAGES:Total Average
ACTIVITY CENTER ADMINISTRATION 173,024 8,700
IT 5,567,435 278,400
COMMUNITY SERVICES 138,731 6,900
FIRE EQUIPMENT 6,343,400 317,200
FIRE ADMINISTRATION 2,473,378 123,700
POLICE EQUIPMENT 3,963,654 198,200
POLICE ADMINISTRATION 4,017,716 200,900
PUBLIC WORKS ADMINISTRATION
BLDG./EQUIPMENT SERVICES EQUIPMENT 177,400 8,900
ENGINEERING EQUIPMENT 67,700 3,400
PARKS/FORESTRY EQUIPMENT 1,958,740 97,900
STREET EQUIPMENT 3,920,000 196,000
GENERAL FUND VEHICLE/EQUIPMENT 16,430,894 821,500
GENERAL FUND OTHER EQUIPMENT 12,370,284 618,500
GENERAL FUND TOTAL 28,801,178 1,440,100
HRA FUND 196,600 9,800
ARTS CENTER FUND 129,600 6,500
REFUSE FUND 1,667,800 83,400
PAVILION FUND 477,200 23,900
WATER FUND 353,600 17,700
SEWER FUND 673,300 33,700
UTILITY VEHICLES/EQUIPMENT 3,498,100 174,900
32,299,278
80
EQUIPMENT INVENTORY
81
CITY OF HOPKINS
VEHICLE/EQUIPMENT INVENTORY
FALL, 2020
UNIT #YEAR MAKE MODEL VALUE
FIRE DEPARTMENT
100 2017 PIERCE IMPEL 900,000$
103 2006 PETERBILT 357 420,000
104 2012 FORD F550 248,500
105 2016 FORD F150 25,000
106 2019 FORD EXPLORER 55,000
107 2019 FORD EXPLORER 55,000
108 2019 FORD F150 33,000
109 2008 PIERCE AREO XT 874,000
110 2017 FORD EXPLORER 47,500
115 1952 MACK NONE 4,000
POLICE DEPARTMENT
200 2018 FORD UTILITY 49,000$
201 2018 FORD UTILITY 49,000
202 2018 FORD UTILITY 49,000
205 2020 FORD UTILITY 54,000
206 2020 FORD UTILITY 54,000
207 2017 FORD UTILITY 49,000
208 2017 FORD UTILITY 49,000
209 2018 FORD UTILITY 49,000
211 2016 FORD UTILITY 34,000
212 2018 FORD F150 55,000
213 2020 CHEVROLET BLAZER 54,000
214 2018 FORD EXPLORER 49,000
216 2011 FORD TAURUS 30,000
218 2013 FORD UTILITY BLUE 40,000
219 2013 FORD TAURUS 24,000
220 2017 FORD EXPLORER 50,000
221 2019 FORD EXPLORER 55,000
240 2017 FORD TRANSIT-350 67,000
299 2018 FORD F150 55,000
DWI.2015 FORD UTILITY 41,000
82
CITY OF HOPKINS
VEHICLE/EQUIPMENT INVENTORY
FALL, 2020
UNIT #YEAR MAKE MODEL VALUE
STREET/TRAFFIC DIVISION
301 2013 FORD F-150 19,500$
302 2018 FORD F350 DRW 54,600
303 2016 FORD F-250 26,500
307 2006 FORD F-350 27,400
308 2011 FORD F-350 20,300
309 2012 FORD F-450 30,300
311 2011 FREIGHTLINER M2-106V 79,400
312 2004 FREIGHTLINER M2-106 98,000
315 2017 FREIGHTLINER 114SD 221,700
317 2016 FREIGHTLINER M2-106 69,400
318 2019 FREIGHTLINER 114SD 235,000
320 2020 CATERPILLAR 926M 232,000
321 2012 CATERPILLAR 924K 177,500
322 2005 CATERPILLAR 938G 157,800
325 2011 BOBCAT S-650 35,100
327 2019 ELGIN PELICAN 230,000
328 2013 ISUZU 435 REGEN SWEEP 145,300
329 2017 BOMAG BW120 SL5 ROLLE 45,900
331 2016 BOBCAT S-650 35,100
337 1994 CATERPILLAR AP200B 17,000
344 1996 SNO-GO WK800 58,000
346 2017 SNO- GO SG WK-800 160,000
348 2014 SPARKS T6202 TRAILER 5,300
350 1993 TOWMASTER T14 TRAILER 4,000
351 2004 TENNANT SWEEPER 3640 10,000
352 2017 FALCON PATCH TRAILER 15,000
ENGINEERING DIVISION
706 2015 FORD TRANSIT 250 24,000$
BUILDING MAINTENANCE & EQUIPMENT SERVICES
700 2015 FORD UTILITY 35,000$
702 2004 FORD F350 18,000
705 2018 FORD F350 30,000
707 2020 FORD F250 35,000
708 2016 FORD TRANSIT 350 29,700
712 2015 FORD UTILITY 35,000
713 2014 FORD UTILITY 30,000
750 2018 CLARK GTS25-FORKLIFT 25,000
83
CITY OF HOPKINS
VEHICLE/EQUIPMENT INVENTORY
FALL, 2020
UNIT #YEAR MAKE MODEL VALUE
PARKS/FORESTRY DIVISION
800 2013 FORD F-150 23,700$
801 2012 FORD F-350 24,100
804 1995 CHEVROLET CC31403 45,000
806 2016 FORD TRANSIT 350 29,700
807 2006 FORD F250 18,000
811 2006 INTERNATIONAL LOG TRUCK 45,000
812 2010 FREIGHTLINER AERIAL LIFT 130,000
813 2019 FREIGHTLINER M2-106 235,000
814 2020 FORD F350 43,000
815 2020 FORD F350 43,000
816 2014 BOBCAT 5610 50,900
817 2018 BOBCAT 5600 63,300
818 2017 TORO WORKMAN HDX 13,000
820 2004 TORO WORKMAN 3200 15,000
822 2014 TORO MDE 18,000
823 2006 JACOBSON TURFCAT 600 10,000
824 2020 TORO GM4000 68,000
825 2010 TORO 4100-D 56,500
826 2004 TORO Z587L 8,900
828 2001 DEWEZE ATM-72 21,000
829 2016 TORO 3280-D 10,000
831 2016 RAYCO RG45X 3,400
834 2013 VERMEER BRUSH CHIPPER 29,800
835 2016 BOBCAT S70 55,000
843 2007 CARR TRAILER 2,500
844 2010 FELLING FT-6T 6,000
845 1997 REMACKEL DT-D7-E 3,500
846 2001 DRESSEN 8110 2,000
848 2017 LOAD TRAIL TILT DECK 5,400
84
CITY OF HOPKINS
VEHICLE/EQUIPMENT INVENTORY
FALL, 2020
UNIT #YEAR MAKE MODEL VALUE
HRA
411 2007 CHEVROLET 2500 17,500$
WATER/SEWER
502 2017 FORD F-150 SUPERCAB 28,000
503 2015 FORD F-350 24,000
508 2016 FORD TRANSIT CONNECT 25,000
509 2016 FORD F-350 65,000
510 2016 FORD F-350 30,000
531 2017 FREIGHTLINER 114SD 425,400
533 2012 CATERPILLAR 420-EH2 87,700
535 1992 KOHLER GEN/TRL 10,000
537 2010 CATERPILLAR C15 144,300
PAVILION
802 2012 FORD F-350 20,000$
808 2014 ZAMBONI 552 126,000
809 2002 OLYMPIA MILLINEUM 87,800
REFUSE
900 2011 FREIGHTLINER M2-106 201,109$
902 2015 FREIGHTLINER M2-106 232,500
903 2015 PETERBILT REAR LOADER 155,000
85