Loading...
CR 2003-093 Acept Feasibility Study And Order Preparation Of Plans,Shady Oak Pond j, ,/ CITY Or: '1 I June 12,2003 .~l . HOPKINS Council Report 2003-093 Accept Feasibility Study and Order Preparation of Plans, Shady Oak Pond Proposed Action Staff recommends approval of the following motion: Accept Feasibilty Study, Shady Oak Pond and direct staff to prepare plans to install temporary outlet to basin 514 City Proiect 02-06. Overview Shady Oak Pond currently does not have an outlet and as a result the surrounding street and residential properties flood if the pond is not pumped out \;Vhen it gets near flood levels. In the 1997 Hopkins Flood Response Action Plan adopted by the Hopkins City Council, the Shady Oak Pond area was identified as Area No.1 and is the last remaining project area in the action plan. The first step in proceeding with the Shady Oak Pond Storm Sewer Improvement Project is ordering a feasibility report. The Council authorized preparation of the feasibility study in May of 2002 to look at the various options associated with alleviating the flooding problem. At that time it was anticipated that this work would ultimately be constructed at approximately the same time as the Shady Oak Road reconstruction project and other planned area roadway reconstructions. Because the schedule for reconstruction of Shady Oak Road has been pushed back by Hennepin County the outlet work may need to be implemented in phases. Primary Issues To Consider . Project Background . Conclusions detailed in Feasibility Study . Schedule for County Road 61 reconstruction . Temporary or permanent outlet to basin 514 Supportine Documents . Feasibility Report, May 2003 Recommendation . Accept Feasibility Study . Prepare plans for a temporary outlet to basin 514 ~--~ Jo derson Assistant City Engineer Financial Impact: $ 20,000 Budgeted: Y/N Related Documents (ClP, ERP, etc.): Notes: Source: Storm Sewer Fund City Council Report 2003-093, June 12, 2003 - Page 2 . Primary Issues To Consider . Project Back2round The lack of an outlet to Shady Oak Pond has resulted in many problems for Hopkins residents over the years. The pond has been and continues to necessitate high maintenance costs in order to keep the pond somewhat functional without an outlet. The problems associated with this area are vast and include areas such as the intersection of 18th Avenue North and 1st Street South, which floods upstream of the pond during heavy rains because the water has no downstream outlet after it reaches the pond. In addition to looking at the outlet options, the potential for gaining additional storage capacity through dredging will be looked at as an option. One problem that exists with many of the potential solutions to the flooding problems this area faces is the fact that the existing pond contains purple lustrife which is an undesirable species of plant that the DNR does not want spread to potential downstream ponds. Coordination of the proposed outlet has been ongoing with the DNR, Hennepin County, the City of Minnetonka, and Nine Mile Creek Watershed District during the feasibility preparation. . . Conclusions detailed in Feasibility Study The Feasibility Report recommends a phased approach to providing the outlet for Shady Oak Pond. The first phase includes construction of an outlet from Shady oak Pond crossing shady oak road to the wetland basin number 514. Basin 514 is located on west side of Shady Oak Road and south of Oak Drive Lane. This basin is located in the City of Minnetonka and currently does not have an outlet. Minnetonka's Water Resource Management Plan (MWRMP) includes a future outlet for this basin in conjunction with Shady Oak Road reconstruction. With no outlet for basin 514 in place currently, Hopkins Shady Oak Pond outlet is required to be limited to 6 inches in diameter in order to restrict the flow. The first phase of this work as suggested in the feasibility report would be to construct a 21-inch concrete pipe connecting the two basins but limit the outlet capacity to a 6-inch orifice until the outlet is installed for basin 514. This connection would provide additional infiltration area for the storm water collected in Shady Oak pond to enter the ground water. This would help maintain a lower level in shady Oak pond but would not prevent flooding in larger rainfall events. The second phase recommended in the Feasibility Report includes construction of an outlet that ties into the storm sewer system constructed with Shady Oak Road. This phase is obviously very dependent on the schedule for the reconstruction of Shady Oak Road. At this point staff anticipates construction of Shady Oak Road in 2006. After completion of the first two phases Shady Oak Pond would have a 6 inch outlet to basin 514 and an 18 inch outlet to the Shady Oak Road system. City Council Report 2003-093, June 12, 2003 - Page 3 The third phase involves removing the 6 inch orifice and allowing the full 21 inch outlet to discharge to basin 514. This phase would be implemented after Minnetonka has installed their outlet for basin 514 which would most likely be in conjunction with the Shady Oak Road project. The outlet for basin 514 in MWRMP is shown to flow to basin 512 in Minnetonka and not directly to the Shady Oak Road system and therefore would not necessarily be included in the Shady Oak Road project. . Schedule for Shady Oak Road Reconstruction Hennepin County currently shows reconstruction of Shady Oak Road in their Capital Improvement Plan to occur in 2005. City Staff has been in contact with Hennepin County staff and based on those conversations we expect construction not would begin until 2006 at the earliest. As this project will require Planning, public involvement, and right of way acquisition it is likely that construction may be even further out that 2006. . Temporary or permanent outlet to Basin 514 Until the reconstruction of Shady Oak Road takes place the largest outlet operating will be limited to 6 inches in diameter and that outlet will flow to a land locked basin, staff has considered a variation to the phasing suggested in the feasibility study. The alternate phasing would be as follows: . Phase 1 Phase 2 Installation of a temporary 6 inch pipe to outlet Shady Oak Pond to basin 514 construction of 21-inch outlet to basin 514 with 6 inch orifice Removal of temporary 6 inch outlet Construction of 18 inch outlet to new Shady Oak Road storm sewer system removal of 6 inch orifice when outlet of basin 514 is constructed Phase 3 This approach would provide a number of benefits. The initial cost of installing the 6 inch temporary pipe would be much less than installing a permanent 21 inch pipe. A temporary pipe would allow for more flexibility as the construction plans develop for Shady Oak Road. The cost of designing, bidding and installing the permanent pipe would be much less if it is part of the shady oak road project rather than contracted as a separate project. The down side of the temporary pipe is the cost of installation and removal. Recomendations Based on our review of the report and consideration of the alternatives staffs recommendation is as follows: . City council move to accept the Feasibility Report . Direct Staff to prepare plans for the installation of a temporary 6 inch outlet . Direct staff to continue working with Hennepin County in the development-of reconstruction plans for Shady Oak Road . . - =.- ----: - - . " ' --~~ -~~~ffi - ,~ I L \ " \ \ \ ~ \ \ \ II \ \ \ \ \ \ I \ :\ \ \; FEASIBiliTY REPORT Shady Oak Pond Outlet Hopkins, Minnesota SEH No. A-HOPKN0202.00 -May, 2003 ~s~tJ SHORT ELLIOTT HENDRICKSON INC Mu Itid isciplined. Single Source. . ,. . ~S~t~ 3535 Vadnais Center Drive, St. Paul, MN 55110-5196 651.490.2000 651.490.2150 FAX environmental transportation architecture engineering May 21, 2003 RE: City of Hopkins Shady Oak Pond Feasibility Report SEH No. A-HOPKN0202.00 14.,00 Mr. Steve Stadler, PE Public Works Director/City Engineer I City of Hopkins 1010 First Street South , Hopkins, MN. 55343 Dear Mr. Stadler: On behalf of Short Elliott Hendrickson Inc. we are 'pleased to submit the final Feasibility Report .for Shady Oak Pond. The report covers possible outlet options for the pond and a solution for the flooding at the intersection of 18th Avenue N. and 1st Street N. ' The recommended outlet option is a phasep. solution due to the tentative schedule of the full implementation of the Min1?-etonka Water Resource Management Plan (MWRMP) and the reconstruction of Shady Oak Road. A. Phase I - Install 21-inch culvert crossing under Shady Oak Road to Minnetonka, with 6-inch orifice restriction. This provides a 25-year/24-hour level of protection. B. ~ Phase II - Install outlet along Shady Oak Road in conjunction with Shady Oak Road improvements. This provides a 75-year/24-hour level of protection. C. Remove orifice at full MWRMP implementation. This provides a 100-year/24-hour " level of protection. The wetland on the west side of Shady Oak Road, where the proposed culvert discharges to Minnetonka subwatershed 514, does not currently have an outlet. According to the MWRMP an 18-inch culvert is proposed to outlet the wetland. There is an overflow berm that is higher than Shady Oak Road that will drain the wetland to the south towards - Excelsior Boulevard. 'Until Minnetonka fully implements their Water Resource Management Plan and constructs the specified outlets, there is still the potential for Shady_Oak Pond and Shady Oak Road to flood. To alleviate the flooding at the intersection of 18th A venue N. and 1 st ~treet N., the existing storm sewer system between 18th Avenue N. and Shady Oak Pond should be replaced with a 36-inch RC~ or equivalent storm s~wer pipe. Also, the inlet capacities of the storm sewer at 18th Avenue N. and 1st Street N. should be upgraded to increase the intake of overland flow at the intersection. This~ will provide a 25-year/24-hour level of p~otection for the intersection. Short Elliott Hendrickson Inc. Your Trusted Resource Equal Opportunity Employer Mr. Steve Stadler May 21. 2003May 12,2003 Page 2 . Please feel free to contact us if you have any further questions. It was our pleasure to complete this project for you. Sincerel y, SHORT ELLIOTT HENDRICKSON INC. ~- David C.Halter, PE Project Manager ~'1~ Beth Peterson, PE Project Engineer bcp c: John Anderson, PE, City of Hopkins Paul Hegre, PE, SEH x:\tj\hopk.n\020200\word\report translTllttalltr.doc . . . . . Feasibility Report Shady Oak Pong Outlet City of Hopkins SEH NO: A-HOPKN0202.00 May 2003 I hereby certify that this report was prepared by me ~r under my direct supervision, and that I am a duly Licensed Professional Engineer under the laws of the State of Minnesota. fJ~ /) }/~(f0 t}. Date: s-- cJol- Os Lic. No.: ReVieweW--O C ~(~ Short Elliott Hendrickson Inc. 3535 Vadnais Center Drive , St. Paul, MN 55110-5196 651.490.2000 YJ3JJ, ,. ~"2Z-6 3 Date . .- I i Table of Contents ! Cover Letter Certification Page Table of Contents 1.0 CONCLUSIONS AND RECOMMENDATIONS ................................................................1 1.1 CONCLUSIONS..................... ..:.................................................................................. ................ 1 1.2 RECOMMENDATIONS.......... ...1................................................................................................. 2 I I 2.0 -" INTR 0 D U CTI ON ...... ............~............ ..... ............ .................... ....~.......................................... 3 i 2.1 - AUTIiORIZA TION ............ .......'.. .................:....................... ............. ........... ...... ~....... ................ 3 2.2 BACKGROUND....... ......... ..... ..:. ..................................... ................................... ....... ................. 3 I 3.0 EX IS TINGe 0 ND ITI 0 NS....i....... ............ .............................................................................. 4 3.1 DRAmAGE AREA DESCRIPTION................................................................................. .............4 3.2 SHADY OAK POND DESCRIPTiON ................................................... ................. ......... ..............4 3.3 STORM SEWER SYSTEM DESCRIPTION ................... ..... .................. ......... ..... ............ ................5 , 4.0 D ESI G N ME TH 0 DO LOGy;:......................... .................................................................... !'~' 5 4.1 HyDROLOGy................. ..... ...:............................................................................ .'.................... 5 4.2 HYDRAULICS ...................... ..!......................................................................... ........................5 I 5.0 CRITERIA FOR INVESTIGA TION ....................................................................................5 5 .1 MUNICIPAL CRITERIA....... ....J......:........................................... ............................ ...................5 I 5.2 OTHER AGENCY CRITERIA ...~..... .................................... ........................................................6 i 6.0 PR 0 POSED IMPROVEMENTS..................... ................... .............................................. ..... 6 6.1 OUTLET OPTIONS CONSIDERED.. .......... ................ ............ ......... .......... ........... ......... ............... 6 6.1.1 Option I-Storm Sewer' along Shady Oak Road (Figure 6).......................................... 7 6.1.2 Option II - Storm Sewer along 18th Ave to 1st St S (Figure 7) ......................................8 6.1.3 Option III - Entire Dis~harge through Culvert Crossing to Minnetonka (Figure 8) . 10 6.1.4 Option IV - Lift Station with gravity system from 1st St N to 1st St S (Figure 9).........10 6.2 18TH AVE N AND 1 ST ST N FLOOD MITIGATION OPTIONS CONSIDERED ........:.......................12 6.2.1 Replace Existing Systetft and Inlets................ ............. ...................... ........... .......:....... 12 6.2.2 Split Flow into Propos~d Pond Outlet ........................................................................13 i 7. 0 FINAN CIN G.................... ......1................... ............................... ...................... ...... ................. 13 I I 7.1 OpmION OF PROBABLE COSTS ......... ........ ................ .............. .......................... ....... ....;........ 13 7.2 PROPOSED Fm ANCmG.... ......1....................................................................... ........................ 13 8.0 PRO JE CT S CHED ULE .......~.......................... ..... .......... ......... ..... .............................. .......... 14 8 .1 TENTATIVE SCHEDULE FOR RBLA TED PROJECTS: ........ ...................... ................ .................... 14 I ' 8.2 SCHEDULE FOR POND OUTLET AND FLOOD MITIGATION .....................................................14 8.2.1 Option I ....................... ~............................................................................................... 14 9.0 PR OJECT CO NT A CTS .......f............................................................................................... 14 Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page i . . Table 1 Table 2 Appendix A Appendix B Appendix C List of Tables Peak Flows.............................................................................. 12 Opinion of Probable Cost ........................................................13 List of Appendices Figures 1-10 Table of Results Drainage Map Calculations Estimates References Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 . Page ii May 20, 2003 . Feasibility Report Shady Oak Pond Outlet Prepared for the City of Hopkins . 1.0 Conclusions and Recommendations 1.1 Conclusions As a result of oui study and investigation we can conclude that: 1. The watershed boundary for Shady Oak Pond is currently labeled CE in the City of Hopkins Water Resources Management Plan (HWRMP). Property development and storm sewer modifications within the watershed boundary have decreased the boundary area from 114 to 82 acres. . 2. The City of ,Minnetonka's Water Resources Management Plan (MWRMP) indicates. drainage north of Highway 7 will be routed through Shady Oak Pond in the future. The MWRMP includes a future 21-inch culvert from Shady Oak Pond crossing Shady Oak Road discharging into Minnetonka's drainage system. The hydrologic model data included in the MWRMP indicate a peak flow of 11 cfs for the 100 year storm discharging from Shady Oak Pond into Minnetonka's jurisdiction (Appendix C). 3. With the Shady Oak Pond Outlet constructed, 2nd St N immediately north of Shady Oak Pond will have to be raised approximately 1 foot to provide protection against overtopping from the 100-yrI24-hr storm. 4. Dredging the islands will not provid~ eIJough additional storage to prevent Shady Oak Pond from overtopping Shady Oak Road for the 100-yr/24-hr storm. An outlet would still need to be constructed. . 5. It is incumbent upon the City of Hopkins to justify to the Minnesota Department of Natural Resources (DNR) the reason for A-HOPN0202.00 Page 1 . dredging the islands which contain Purple Loosestrife. The DNR requires either same-site disposal or existing-site disposal of spoil material containing Purple Loosestrife. The DNR requires a permanent outlet structure be constructed as opposed to a flared end section outlet, and the Ordinary High Water (OHW) to remain at or near the established elevation. 6. The Nine ,Mile Creek Watershed District requires a mInimUm manhole dimension of 60-inches for outlet structures. The watershed district also requires design criteria regarding runoff rate as established by the following guideline: Minnesota Pollution Control Agency, 1989, "Protecting Water Quality in Urban Areas." 7. Hennepin County has future plans for the reconstruction of Shady Oak Road between Excelsior Boulevard and Highway 7. The county has a standard cost share program based on contributing watershed area for sponsors that wish to be included in the project scope. A formal request to Hennepin County is the first step of the cost share program. 8. The storm sewer system along Shady Oak Road south of Excelsior Boulevard is sized to accommodate the lOO-yrI24-hr > storm for MWRMP's proposed improvements. ,. 9. The existing storm sewer system along Excelsior Boulevard between 18th Ave S and Nine Mile Creek surcharges at 17th Ave S from the 1O-yr/24-hr storm. 10. To alleviate flooding at the intersection of 18th Ave N and 1st St N, the existing 18 and 24-inch storm sewer system between 18th Ave Nand S,hady Oak Pond should be replaced with a 36-inch RCP storm sewer pipe. Also, the inlet capacities at 18th Ave Nand 1st St N should be upgraded to increase the intake of overland flow at the intersection. 11. Option I for the Shady Oak Pond outlet should be constructed to provide protection against the pond overtopping Shady Oak Road during a lOO-yrI24-hr storril. This option includes 'installing a 21- inch culvert crossing Shady Oak Road to Minnetonka's jurisdiction and routing an 18-inch storm sewer along Shady Oak Road to Excelsior Boulevard. Option I includes 3 phases of constructibn. See section 6.1.1 for details on phases. 12. The improvements are necessary, cost-effective, and feasible. 1.2 Recommendations It is recommended that: . 1. This report be reviewed by the City Council, staff, and financial advisors. , Shady Oak Pond Feasibility Report Hopkins. Minnesota A-HOPKN0202.00 Page 2 ' . . 2. The City Council accepts this report and proceeds with implementation of Option I for the Shady Oak Pond outlet. The opinion of probable project cost (Appendix C) for Option I IS $876,500. The City proceeds with replacing the storm sewer inlet system along 1st St N from 18th Ave N to Shady Oak Pond. The opinion of probable project cost is $436,100. The City investigates the cost of raising 2nd 5t N to protect it from inundation during large storms. The City should implement these improvements for the following reasons: a. They address the immediate needs. b. They can be integrated into future construction projects. c. They implement an item of the capital improvement plan. 3. The pond outlet and 1st 5t N storm sewer improvement should be constructed as proposed in this report. 2.0 Introduction 2.1 Authorization This feasibility report has been - prepared and is submitted in accordance with an agreement between the City of Hopkins and Short Elliott Hendrickson Inc. (SEH). The report, authorized by the City of Hopkins on June 26, 2002, is a result of city resolution 97-104. The resolution outlines an Action Plan to alleviate flooding problems within the city. This report addresses Problem Areas 1 and, 3 described in the Action Plan (Appendix C). \- 2.2 Background Shady Oak Pond and the intersection of 18th Ave Nand 1 st St N are defined as Problem Area 1 and 3, respectively, in the "Action Plan". The areas are shown in Figure 1 (Appendix A). A feasibility study titled Storm Water Flooding Analysis was performed for the city in 1998 that, in part, addressed the flooding problems of Problem Area 3. The 1998 study recommended a 3-phase solution to the flooding problems. Phase 1 a. Increase the inlet capacity in the alley between 18th Ave Nand 17th Ave N. b. Reconstruct the entrance apron of the alley. c. Bulkhead the 12-inch storm sewer connection between the alley and 18th Ave N. Phase 2 Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 3 . a. Increase the stor:r:p sewer size from the alley to 17th Ave N. b. Lower the intersection of 18th Ave N and 1st St N. c. Increase the storm sewer size from 18th Ave N to Shady Oak Pond. . Phase 3 a. Construct an outlet for Shady Oak Pond. To date, all items of Phase 1 have been constructed. Item a of Phase 2 has not been constructed. Items band c of Phase 2 and i tern a of Phase 3 are addressed in this report. 3.0 Existing Conditions 3.1 Drainage Area Description The drainage area boundary for Shady Oak Pond produced from this study is shown in Figure 2 (Appendix A). The boundary covers 82 acres. The HWRMP identifies this area as watershed CE and lists it at 114 acres. The 32 acre difference is primarily a result of two changes; property development north of the pond that routes runoff to the north eliminating 11 acres and runoff collection that stays west of Shady Oak Road eliminating 21 acres of watershed from the HWRMP boundary. The area is predominantly single family residential homes roughly bordered by Highway 7 to the north, Mainstreet to the south, Shady Oak Road to the west, and 17th Ave N to the east. The natural overland overflow of the drainage area is across Shady Oak Road into Minnetonka. Once across Shady Oak Road drainage generally flows south to Shady Oak Lake. . . . 3.2 Shady Oak Pond Description The DNR lists Shady Oak Pond as protected water number 27-777P and established the Ordinary High Water level (OHW) at 921.0 feet. The pond is bounded by 2nd St N to the north, 1st St N to the south, Shady Oak Road to' the west, and residential property to the east. Presently, there is not a functioning manmade outlet from the pond. There is an existing 18-inch corrugated metal pipe (CMP) crossing Shady Oak' Road at the south end of the pond. Field. survey information from April of 1988 indicates the west end of this pipe is buried in the shoulder of the road and is not functioning. There is an 18-inch eMP crossing Shady Oak Road at the north end of the pond that discharges runoff into the pond from approximately 5 acres of residential property on the west side of Shady Oak Road. Total area of the pond at OHW level is approximately 6 acres. The pond has 2 islands that have a total surface area of 1.92 acres shown in Figure 3 (Appendix A). The islands are infested with a perennial Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 4 . . noxious weed called Purple Loosestrife. Biological control methods have been implemented over the past few years in an effort to control the weed. Based on the numerical model, the pond overtops Shady Oak Road at approximately the 25-yr/24-hr storm. The pond frequently overtops 20 St N causing extended street closures that block traffic' on West Park Road and 2nd St N. 3.3 Storm Sewer System Description Shady Oak Pond's storm sewer system consists of lateral 12-inch Reinforced Concrete Pipes (RCP) discharging to a trunkline located on 1 st St N. The existing storm sewer system is shown in Figure 4 (Appendix A). The trunkline ultimately discharges into the southeast corner of Shady Oak Pond. The storm sewer system collects runoff from approximately 55 of the pond's 82 acre drainage area. System modifications constructed in recent years have added catchbasin inlets to the system on 2nd St N. There are 4 catchbasin inlets and 1 manhole grate at the intersection of 18th Ave N and 1st St N. The trunkline from 18th Ave N to 19th Ave N is I8-inch RCP, and from 19th Ave N to Shady Oak Pond it is 24-inch RCP. The 18th Ave Nand 1 st 5t N intersection floods during large storms. 4.0 Design Methodology 4.1 Hydrology HydroCAD version 6.0 was used to develop the storm water runoff models for the options explored. The 100-yr/24-hr storm (5.9 inches) was input as the design storm for all options. The SCS TR-20 method. was used to generate flows from the watersheds. Simultaneous pond routing which allows for dynamic tail water elevations was used for . routing hydro graphs through the ponds. 4.2 Hydraulics Eagle Point 2002 design software was used to develop the storm sewer hydraulic models of the existing and proposed storm sewer systems. The Rational Method was used to develop the peak flows and the Standard Step Method to develop the hydraulic grade lines of the storm sewer systems. 5.0 Criteria for Investigation 5.1 Municipal Criteria The Water Resources Management. Plans from Hopkins and Minnetonka were used as a basis for analysis and preliminary design of the pond outlet. . Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 5 . Both plans were referenced because various options allow flow to enter both jurisdictions. The plans include guidelines and data to help meet municipal requirements. 5.2 Other Agency Criteria This drainage system is within the Nine Mile Creek Watershed District. It is anticipated that compliance with municipal requirements for the design of the drainage system will comply with the requirements of the Watershed District. - Because Shady Oak Pond is a designated DNR protected water, agency permits will be required before construction of an outlet begins. . 6.0 Proposed Improvements 6.1 Outlet Options Considered Four main options were considered for the proposed outlet. A schematic of each option is shown in Appendix A. Each option was analyzed with and without dredging the existing islands. Three of the four options were analyzed with and without the culvert crossing to Minnetonka's jurisdiction with the remaining option being the culvert crossing as the only outlet. A summary 'of the results is tabulated in Appendix B. Dredging the islands would provide additional storage for runoff during large storms.'. However, because the islands are infested with' Purple Loosestrife the spoil material must be disposed of in one of two ways. Either the spoil material stays on site or is hauled to a site where Purple Loosestrife already exists. Considering .the project location, keeping the material on site IS not a feasible option. Hauling the spoil increases the cost associated with dredging the islands. The opinion of probable cost for dredging the islands is $400,000. Dredging the islands will not provide enough additional storage to prevent Shady Oak Pond from overtopping Shady Oak Road for the 100-yr/24-hr storm. Therefore, an outlet must be constructed. The culvert crossing to Minnetonka's jurisdiction is part of the . MWRMP. The MWRMP states that high flows will enter their jurisdiction from Shady Oak Pond. The MWRMP designates Subcatchment 514 as the point of entry. In accordance with the MWRMP, the maximum flow rate allowed intoSubcatchment 514 for the 100-yrI24-hr storm is 11 cfs. All options considered were designed , to accommodate MWRMP's stated flow rate (+/- 1 cfs). To comply with DNR requirements, the crossing is designed with an outlet structure as opposed to a precast open flared end section. The invert elevation exiting the outlet structure is 921.0 feet. Full design implementation of any option using the crossing as an integral element Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 6 . of the solution is based on when Minnetonka implements their MWRMP. Construction of Option I or III would include installing a 6-inch orifice on the crossing to restrict flow into Minnetonka pending full implementation of the MWRMP. The opinion of probable cost for installation of the crossing is $75,000. Under all options 2nd St N bordering the north side of Shady Oak Pond must be raised to prevent flooding fr9m larger storms. The low point on 2nd St N is approximately 922.2 feet. Inundation of 2nd St N from larger storms after full implementation of recommended. option I or III is shown in Figure 5. ,The critical elevation used in analyzing the outlet options was the low point of Shady Oak Road at 923.5 feet using NGVD 1929 as the datum. Circumstances surrounding the pond such as available pipe cover for larger outlets, agency restrictions for maximum flow entering Minnetonka, and minimum elevation maintaining OHW preclude the option of lowering the pond's flood elevation to protect 2nd St N from inundation at the street's present elevation. The City should consider including the cost of raising 2nd St N in this project or include it in the Capital Improvement Plan (CIP) for street improvements. It is listed in section 8.0 as a future phase for construction. A preliminary investigation of existing utilities was done to ensure the proposed alignments considered were constructible. . The criterion for recommendation is based on protecting Shady Oak Road from the 100-yr/24-hr storm. 6.1.1 Option I - Storm Sewer along Shady Oak Road (Figure 6) This option includes a proposed outlet structure that sets Shady Oak Pond's NWL at 920.5 feet. . The outlet discharges to a proposed storm sewer system that' flows south 1970 feet to Excelsior, Boulevard. At Excelsior Boulevard the system connects to an existing 30-inch storm sewer system that ultimately discharges to Shady Oak Lake. The existing storm sewer system south of Excelsior Boulevard is designed for the 100-yrI24-hr storm., l:Iennepin County has future plans to reconstruct Shady Oak Road from Excelsior Boulevard. to Highway 7. Therefore, this option would be best constructed under a cost sharing agreement with Hennepin County. The county has a standard cost share program based on contributing watershed area with interested sponsors. Coordination with the City of Minnetonka will be required as portions of Shady Oak Road either border or are within Minnetonka's jurisdiction. Because of the tentative schedule for reconstruction of Shady Oak Road and full implementation of the MWRMP, the construction . process would follow a 3 phase scenario: Shady Oak Pond Feasibility Report A-HOPKN0202.00 Hopkins. Minnesota Page 7 . Phase I - Install 21-inch Minnetonka culvert crossing with orifice restriction. This provides a 25-yr/24-hr level of protection. Phase II ...: Install outlet along Shady Oak Road in conjunction with Shady Oak Road improvements. This provides a 75- yr/24-hr level of protection. Phase III - Remove orifice at full MWRMP jmplementation. This provides a 100-yr/24-hr level of protection. ' Some of the variations described below do not correlate with the 3 phase construction scenario because cost precludes them from being a feasible option. The values stated for each variation below assume full design implementation. 6,1.1.1 Shady Oak Road Outlet Considering the proposed outlet as the only outlet, the system size is a 24-inch RCP. Peak discharge for the outlet is approximately 17 cfs. Peak elevation of Shady Oak Pond is 923.36 feet. . 6.1.1.2 Shady Oak Road Outlet and Island Dredging Considering the proposed outlet as the only outlet and dredging the islands, the system size is an IS-inch RCP. Peak discharge for the system is approximately 9 cfs. Peak elevation of Shady Oak Pond is 923.31 feet. 6.1.1.3 Shady Oak Road Outlet and Minnetonka Culvert Crossing Considering the proposed outlet and a 21-inch RCP culvert crossing to Minnetonka's jurisdiction the proposed storm sewer system size is an IS-inch RCP. Peak discharge for the proposed outlet and crossing is 9 cfs and 12 cfs, respectively. Peak elevation of Shady Oak Pond is 923.34 feet. . 6.1.1.4 Shady Oak Road Outlet, Minnetonka Crossing, and Island Dredging Considering the proposed outlet, a 21-inch RCP culvert crossing to Minnetonka's jurisdiction, and dredging the islands, the proposed storm sewer system size is a 12-inch RCP. Peak discharge for the proposed outlet and crossing is 3 cfs and 10 cfs, respectively. Peak elevation of Shady Oak Pond is 923.15 feet. 6.1.2 Option II - Storm Sewer along 18th Ave to 1st St S (Figure 7) This option includes a proposed outlet structure that sets Shady Oak Pond's NWL at 920.5 feet. The outlet discharges to a proposed storm sewer system that flows east 900 feet along 1 st St N to ISth Ave, then south 1690 feet along lSth Ave to 1st St S, then east 330 feet to 17th Ave S. At 17th Ave S the storm sewer system connects to an existing 27-inch storm sewer system that ultimately discharges to Nine Mile Shady Oak Pond Feasibility Report HopkinS, Minnesota A-HOPKN0202.00 Page 8 . Creek at Excelsior Boulevard and 13th Ave S. The existing 27-inch system is designed for the 1O-yrI24-hr storm that surcharges during larger storms. This option will add surcharge to the existing storm sewer system possibly causing nuisance flooding in streets during larger storms. However, this option will alleviate flooding at Shady Oak Pond. Because the existing storm sewer system surcharges during larger storms, this option cannot ensure a 100-yr/24-hr level of protection. Variations of this option were considered including replacing the existing 27-inch storm sewer system on 17th Ave S from 1st StS to Excelsior Boulevard with a 36-inch storm sewer system, to improve the capacity of the system. However, the magnitude of improvement isn't large enough, as the existing storm sewer system would still surcharge at larger storms even with the improved capacity. ' Another variation considered was routing the proposed storm sewer system south on 18th Ave across Excelsior Boulevard then east to Nine Mile Creek. However, the additional construction cost for this variation would preclude Option II froni being feasible. Hopkins has future plans to reconstruct 18th Ave N. Therefore, the street reconstruction could be constructed in conjunction with this option. The average depth of the outlet along 18th Ave is 15 feet. Therefore, when developing the opinion of probable cost for this option, removal and replacement of the street from curb to curb was included in the construc~ion quantities. Option II has construction scheduling advantages over other options. The entire outlet is within Hopkins jurisdiction allowing the City to control when construction and full implementation of the Pond outlet takes place. Also, coordinating County projects and cost sharing agreements is not required with Option II. However, because a 100- yr/24-hr level of protection cannot be ensured, it is not the recommended option. The values stated for each variation below aSSUme full design implementation. 6.1.2.1 18th Ave Outlet Considering the proposed outlet as the only outlet, the system size is a 24-inch RCP. Peak discharge for the outlet is approximately 17 cfs. Peak elevation of Shady Oak Pond is 923.38 feet. 6.1.2.2 18th Ave Outlet and Island Dredging Considering the proposed outlet as the only outlet and dredging the islands, the system size is an 18-inch RCP. Peak discharge for the system is approximately 8 cfs. Peak elevation of Shady Oak Pond is 923.35 feet. Shady Oak Pond Feasibility Report A-HOPKN0202.00 Hopkins, Minnesota Page 9 . 6.1.2.3 18th Ave Outlet and Minnetonka Culvert Crossing Considering the proposed outlet and a 21-inch RCP culvert crossing to Minnetonka's jurisdiction the proposed system size is an 18-inch RCP. Peak discharge for the proposed outlet and crossing is 8 cfs and 12 cfs respectively. Peak elevation of Shady Oak Pond is 923.34 feet. 6.1.2.4 18th Ave Outlet, Minnetonka Culvert Crossing, and Island Dredging Considering the proposed outlet, a 21-inch RCP culvert crossing to Minnetonka's jurisdiction, and dredging the islands, the proposed system size is a 12-inch RCP. Peak discharge for the proposed outlet and crossing is 3 cfs and 10 cfs, respectively. Peak elevation of Shady Oak Pond is 923.15 feet. 6.1.3 Option III - Entire Discharge through Culvert Crossing to Minnetonka (Figure 8) The description and details of the culvert crossing can be read in Section 6.1. To achieve the flow restriction of 11 cfs to Minnetonka's jurisdiction, the islands must be dredged. This option is wholly dependent on the implementation of theMWRMP. As stated in Section 6.1 a6-inch orifice would be installed on the culvert crossing. pending full implementation of the MWRNlP. The construction process would follow a 3 phase scenario: Phase I - Install culvert crossing with orifice restriction. This . provides a 25-yrI24-hr level of protection. Phase II - Dredge Shady Oak Pond islands. This provides a 50- yrl24-hr level of protection. Phase III - Remove orifice at full MWRMP implementation. This provides a 100-yr/24-hr level of protection. Because of the complications related to the presence of purple loosestrife on the islands (permitting and disposal), this is not the recommended option. The values below assume full design implementation. 6.1.3.1 Miimetonka Culvert Crossing and Island Dredging Considering the proposed culvert as the only outlet and dredging the islands, the culvert size is a 21-inch RCP. Peak discharge for the system is approximately 11 cfs.Peak elevation of Shady Oak Pond is 923.21 feet. 6.1.4 Option IV - Lift Station with gravity system from 1st St N to 1st St S (Figure 9) This option includes a proposed outlet structure that sets Shady Oak Pond's NWL at 920.5 feet. The outlet discharges to a lift station that pumps water through 1000 feet of forcemain along 1st St N to a gravity Shady Oak Pond Feasibility Report A-HOPKN0202.00 Hopkins, Minnesota Page 10 . . 6.1.4.1 6.1.4.2 storm sewer system at 18th Ave N. From there the gravity storm sewer system flows south 1690 feet to 15t St S, then east 330 feet to 1 ih Ave S. At 17th Ave S the storm sewer system connects to an existing 27- inch system that ultimately discharges to Nine Mile Creek at Excelsior Boulevard and 13th Ave S. The existing storm sewer system is designed for the lOyr/24hr storm that surcharges during larger storms. This option will add surcharge to the existing storm sewer system possibly causing nuisance flooding in streets during larger storms. However, this. option will alleviate flooding at Shady Oak Pond. Because the existing storm sewer system surcharges during larger , storms, this option cannot be considered a true 100-yr/24-hr outlet. Land acquisition and annual maintenance are additional costs associated only with this option. The lift station construction costs, along with utility costs are also exclusive to this option. However, due to the lift station and force main, a shallower gravity system can be constructed on 18th Ave. The average depth of the gravity system is 8 feet. This allows one side of the street to remain in-place during construction. Savings in street construction offset the increased construction cost of the lift station. However, because future street improvements are planned for 18th Ave, the advantage of cost savings due to street replacement cannot be fully realized. Because of this, and operation and maintenance costs, this is not the recommended option. The values stated for each variation below assume full design implementation. Lift Station Outlet Considering the proposed lift station as the only outlet, the pump size is 5000 gpm, the force main size is an 18-inch DIP, and the gravity system size is an 18-inch RCP. Peak discharge for the outlet is approximately 11 cfs. Peak elevation of Shady Oak Pond is 923.45 feet. Lift Station Outlet and Island Dredging Considering the proposed lift station as the only~outlet and dredging the islands, the pump size is 3000 gpm, the force main size is an 18- inch DIP, and the gravity system size is an 18-inch RCP. Peak discharge for the outlet is approximately 7 cfs. Peak elevation of Shady Oak Pond is 923.40 feet. 6.1.4.3 Lift Station Outlet and Minnetonka Culvert Crossing Considering the proposed lift station and a 21-inch RCP culvert crossing to Minnetonka's jurisdiction, the pump size is 2000 gpm, the force main size is a 16-inch DIP, and the gravity system size is an 15- inch RCP. Peak discharge for the proposed lift station and crossing is 5 cfs and 12 cfs respectively. Peak elevation of Shady Oak Pond is 923.42 feet. ' Shady Oak Pond Feasibility Report Hopkins. Minnesota c A-HOPKN0202.00 Page 11 . . . 6.1.4.4 Lift Station, Minnetonka Culvert Crossing, and Island Dredging , Considering the proposed lift station, a 21-inch RCP culvert crossing to Minnetonka's jurisdiction, and dredging the islands, the pump size is 1200 gpm, the force main size is a 16-inch DIP, and the gravity system size is an 15-inch RCP. Peak discharge for the proposed lift station and crossing is 3 cfs and 10 cfs, respectively. Peak elevation of Shady Oak Pond is 923.08 feet. 6.2 18th Ave Nand 15t St N Flood Mitigation Options Considered 6.2.1 Replace Existing System and Inlets The intersection of 18th Ave Nand 1st St N floods during large storms due to inadequate capacity of the existing storm sewer system. The capacity of the existing storm sewer system is limited by an I8-inch RCP that allows 14 cfs to flow west towards Shady Oak Pond. The total inlet capacity of the inlets at the intersection is approximately 8 cfs. The intersection collects runoff from approximately 35 acres... The boundary is shown in Figure 10 (Appendix A). The peak runoff for the 35-acre catchment area is summarized in Table 1. Table 1 Peak Flows Event Peak Flow (cfs) 2-yr/24-hr 28 5-yrI24-hr 37 10- yr/24-hr 42 Upstream of .the intersection the total inlet capacity is approximately 20 cfs. To alleviate flooding the inlet capacity at the intersection and the storm sewer system capacity to Shady Oak Pond must be improved. Replacing the existing storm sewer system from the intersection to the pond with a 36-inch RCP at 0.45 % will increase the capacity to 45 cfs. Replacing existing inlets with more efficient grates will approximately double the inlet capacity. With the proposed . improvements in-place the intersection will be protected from flooding during a 1O-yr/24-hr storm. The average depth of the proposed storm sewer system is 10 feet. Because of the depth of the proposed storm sewer system, 1st St N would need to be reconstructed from curb to curb. The City of Hopkins' Capital Improvement Plan (CIP) indicates street improvements for 1st St N are scheduled for 2004. Constructing this storm sewer improvement in conjunction with the CIP street Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 12 . improvements would reduce the construction costs of replacing the storm sewer. The cost breakdown between street replacement and storm sewer replacement is in Appendix C. 6.2.2 Split Flow into Proposed Pond Outlet This option considered splitting flow from the intersection into the proposed pond outlet (option II or IV) flowing south on 18th Ave. However, because the proposed outlet connects to an existing storm sewer system that surcharges from large storms, flood mitigation at the intersection would be minimal. 7.0 7.1 Financing Opinion of Probable Costs Detailed opinions of probable costs were developed for all options and improvements discussed in this report. They can be found in Appendix C. The totals in Table 2 show the opinion of probable cost assuming all improvements recommended in this report are constructed under the same contract. . Option I will benefit from a cost sharing program with Hennepin County based on contributing drainage area of the shared storm sewer. Table 2 Opinion of Probable Cost Improvements Option I Pond Outlet $ 876,500* 1 st St N Storm Sewer $ 268,500 1 st St N Street $ 167,600 Total $ 1,312,600* * Figure does not reflect County cost sharing benefit 7.2 Proposed Financing The 1 st St N storm sewer improvements to mitigate flooding at the intersection of 18th Ave Nand 1 st St N would be funded through the City's storm sewer utility fund. ,The Shady Oak Pond outlet would be funded through the City's storm sewer utility fund. The cost of street reconstruction for 1st St N from Shady Oak Pond to 18th Ave N would be funded through the City's Capital Improvement Plan for street improvements. Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 13 . If Option I for the Shady Oak Pond outlet is implemented, it is possible that the City would enter into a cost sharing program with Hennepin County to defray a portion of the cost to the County. 8.0 Project Schedule This project would benefit if combined with other projects by taking _ advantage of lower unit prices on larger projects. Coordinating construction with Hennepin County and the City's CIP plan is important in reducing the cost of this project. 8.1 Tentative schedule for related projects: Shady Oak Road Reconstruction (County) 1st St N/lSlh Ave N CIP Improvements (City) 2004-2005 ,2004 8.2 Schedule for Pond Outlet and Flood Mitigation 8.2.1 Option I Culvert Crossing (with orifice restriction) 2003 1st St N/1Slh Ave N Flood Mitigation Shady Oak Pond Outlet 2004 2005 2005- ? Remove restriction from culvert crossing Raise 2nd St N Future Phase 9.0 Project Contacts Steve Stadler, PE Public Works Director City of Hopkins 1010 ISIStS Hopkins, MN 55343 Beth Peterson, PE Project Engineer Short Elliott Hendrickson 3535 Vadnais Center Drive 200 SEH Center St. Paul, MN 55110 (651) 765-2901 . Shady Oak Pond Feasibility Report Hopkins, Minnesota A-HOPKN0202.00 Page 14 . Appendix A Figures 1-10 . . ~:;I -< Ii 0' . ...jr[ roo: - 0, I- . r -< hi . < :r:_! ' I (f) ~ . if l '~~)r_. . , - - v; ~ ..._p.......r- . ~SfH <( ~(f) Zz 0- tJl~ ZIO z' Ll:r: I I ./"''1 /~ r' ~, :'-', )r _ ---,- - <- L'/ -1./.-/ J , Jr' ~.-/ /~// ,], I ( , . - "1 .' j I I i' ,', , Il I ' ; J[ I ' ; I j i 1 I , II : i PROPOSED OUTLET STUDY LOCATIONS HOPKINS, MN -, f e' r-;::;.-.:::::::;-', FILE NO. AHOPKN0202.00 DATE: 10/15/02 co .- , ~J', :' ' ~ l.JJ l.JJ oc <.) ~ .....l, ~ " -" /w ' . ./ Z ~ Z u ri---'\ -. .. ,.u-~,_ __ \ D , X /' ~ / FIGURE NO. 1 11 (~~:-:::::""""""',,"':m,d ",,- ~~_~~M ') ~~~ I ..~~ . ~.,,,='=,,"' J; C-==; ~~.:' -~Nlr:-=; , ' I I I : '. J j : , I ' . Ii" -, ~ - ~- dl F-";;" '1 P:"'l r -" I r I ; ,,1" -SOO' ; { ! l t ~ I 'I!. ;. II ,Jill ,,)1 ' " ",':. ~i L' I' __.. .--! L. ~,,:.:...:..... J ~'---. 1_.... 'I '-' .-' 1 ("'-- . -., r "-1 r- . I ; , I i I II (---",,:, 'jl I. ' 'I , : I . , 1 I I J ' II j j i J I '> I i I /' i ' ; , dl , I~ II II .! ]. I \ I . . ) ; f ,i 1 I: I 1~12_.t.C~~.~..~_ L_:~J l__~~t __. _ j l : 1 r -""1 (~...- 1 ("-....-.11 '---1--11~" ", j} 1/ ii' I J'I )! _I II ,I I( If f , Ii! ( 1 I ), i '/ J i I! II' I! I J { j i J i I J I I ; I II I II II J! i ! I I \ If' , I J." I, 1 I Ii , ,.,E!.J _1 SIJlS:LJ':iORJ8-.. ,- L. - ...-..J l__,__J I_.d, ;,,, .1; r" --: -.../ r~'-' -""1 r --' - r' r - -..../ -"'] r 'II Ij! II 1 I U II J I I I I' I I Ji i i (i I II i I (, I I i i i II " 'I 'I I I II i [", If J i 1 r--- - .."j'. J' i .{ . . ; (I rL ~ " c.>.. I II ' " I II J ; .,. l I l II !' , >:........................,..& n,d n WP ....J L......... ......... _~ vi "~..,J .,~~aJ.. .,-""'"~^~ <"...-..> ~ L ~ "'" ""'- .... .. .-"- ''..~r-''~''''' '')1.1 -.' ="' "? i~' "~) ,"0- ,- .. 'J 'j I , J / '" ) I " J t , J'I" l { ~~ , I : '. i I I I I !. "/ ! /1;' ,S .',:' I " . , .1 I t II _ i ' II ."pEX~tL,SIOB' 13_Ql,JLEVARQ__ . . I I CORPORATE ~ LIMITS ~ I . ~5fH o <(, O. 0:::; ~ :~ <(, i I 0" >- 0" <(' :C' (f) I . FILE NO. AHOPKN0202.00 DATE: 10/15/02 ..' i{ II II J! , PROPOSED OUTLET POND CATCHMENT AREA HOPKINS, MN FIGURE NO.2 . . N ~ '50 100 i2,~-a~~~="~',,~~ 'SCALe ~N ;:"((T ~5eH , "- \~ 150 -- , - ~ {' I~~-b-- 'i , @: 1K.,:::>~:j \ / I : I"',", \ , . il~; ~ T----;--.," --1 i FILE NO. AHOPKN0202.00 DATE: 10/15/02 PROPOSED OUTLET POND ISLANDS HOPKINS, MN FI GU R E NO.3 ~ I ' ( I t \ ( 1 ~ I r ! ' j \ I I ; looN 1 ; I ! I I 0 ~1, \ i ~ I 1 ;' : I ~ ) G .. 1 l ; ! J t ~ I' ' _ ~ " 1 . ) ! : I ! I : 1" - i zqO' J' J' ~ I ! '0 ! 1 ~ I M ~ I I J 'i ~' , " ,1 I ' : . " ~ " ' ,,0 u I" , ' 0 I I 7 l fNP ~#S_T ...NOfiTt:V l~.,,_ -1~~'"R6p- ~ L ~. - ~H - _. -,.) ,-,-, ,I r - -------(,- - --,~~ - fL___r.- -I (- ,l I ! i I I i ,/ J i ' \ I I ! I ) i ! r ,I I I I J \ ' I ~~ I 1 ,t' i ~II ' > :: i' I i J ~ ~ ,l 'i I 1 ~ I I ( I' f, ) I i I I " I : ~ , ~ ; .. I I 1 a. ~'" I · I .f J :. f I ~:il"i I ! I' i I I .- i I i i ,I ~ ' j , ' I 3 j I I ~ " , " ! , f ,i I l k I I I I l ' " I " ~ ',' ~, ,~ ( i t 1 ,1 1 ,I ','V' iv" ' Ii r i I I I J'~' 11 ' I , _._ _'_ =_ _ ......~_) t,~~.24~ -RCe.., _ ,_ j \" _ ,'_'_ ""''- ,_,..",,".J1 t._ -ItSTw"ST .NOHvH~ --"" _, _ __ ,'" _<:<<_. . _ _ ,->.,<,_ ,_ _ "'~ ._ _ "_'~ ~ -.:::''::''. - - - -- --. --'\ r- - . /: .'< I (,:" I ( '1' 8" R C P ,. / , ,0 ' " ~ ,I " I" I I "~ I I { Ii ^ ';/ ,I~ fi I ,I" 110\ (I J~ II I I ~ I ' 'I ( ~ i ) R , , ' I ! I I 1 I ' I I I j j , , 'WI I j ,ij j , I " 'I , I 1 1 ,D( l I l'~ ^ ,Ii ~i "f ,~ : ; : ]10\ : ~ ~j j } I il I~ ' ,iCr-'1 )~, I 1 ' I l ro1 ! r , I ( j..:.l i . ! Ii: : ! " I I i ~t Jt " \ 1 r ) 1 r 1 'I I I 1 j I ~ _ \ It, I ~ !. >.,,'~' u "_,. _ _ ,,) 1__ _" ~_ _ ~,_ _~ ,_-~) l-MAiNSTREET' '-~ - n._ -. -' -~-' "r ~-, _.' ,~-- /- - ~- -- .- -. - ,- -", - . -, -, "" -.." ('~' -..., .- --", ",'- ~" .\\ 'fl ~ ,..... -7- J r ~ :?""'" ~ -:;::::.: ~,\ t ~-') g~ "*"-'>.-.,,-- ~ I ' J ' 1 . I I .,I , '\ ! . t " [ ! ~ 1 l j q , { ! i i t , i N ~ ,~ l p' , I { ~ o SHADY OAK POND . 1 ) FILE NO. AHOPKN0202.00 DATE: 10/15/02 PROPOSED OUTLET EXISTING STORM SEWER HOPKINS, MN ~5fH FIGURE NO.4 \ \~ \ ! N / ~ \ ,) ~ r\ \ --0 .. . \~ \ it \7- \ '-;9\ \0 \ /,', '1? ) \ t 1" = 1 00' I" ~.. 100-YR/24-HR (923.3) - - - - 50-YR/24-HR (923.0). 25-YR/24-HR (922.5) . NOTE: ELEVATIONS ARE BASED ON FULL DESIGN IMPLEMENTATION. 923\.5 >~~~~"';-'; , :.:....:.;;~ NWL 920.5 " --: '^ . 15T 5T NORTH ., I I ~5ai FILE NO. AHOPKN0202.00 DATE: 10/15/02 SHADY OAK POND OPTIONS I AND III WATER LEVEL BOUNDARIES HOPKINS, MN + FIGURE NO.5 - ..."",-........ \ \~"""~,............... , I i ~ 1 . ! I I ! ,i ' , I 21 J IMINNETONKA 1 i ! CU~VERT CROSSIN~ : i i j I' I I ! i j 1 . , 1 ,I <' .~ _, _ _ ,__.",... _""J C_ ~ _ J 'u~'" _) \ -" tST -ST NORTH"'" -"" - ..;::,~ l '.... --~-,,_._',......~~- _,~~,"",,\,,",""'-J'"tr""'''"-"''''''W. ,,...,...,,_..->~.p-:< _K rA",,^,,",=:"""'-E>~- , , l ~ " , , ',' I r , ' " \~ ,j PROPOSED O'UTLET 1 ,j' I! " j 1 \ ~ I' 1 STRUCTUfRE J I J: ~ 1" = 250'; I \ ~ ; Iii \ 1 I , I I j \~ Iii; i I I ! -..}, :, I ! ' 1 l - " ; 1 \~\!U Ii :; Ui!' i 1 j .' 1 i ( , ! 1 ( I I I 1 I 1 r I ' ' I I 1 I J 1 J ! : ; ~ ' i ' '1 l ) J I , ._ MINNETON~!- .', i ! i ,: J i i : . } ~. : HOPKINS ,,' JI 'I ; ,,\)[ , ! " t \ ~' GRAVITY .J' t " I' ,: \ -- l' , I rI1'o...'-, , I l' '" ' r i' {~:~ "~- -- - TbRM-'SEWER - -,_.- MAINSTR-ET'-':_J --- ~' iB,_,_ . J r" -- ,- - - - - - - - - ~ '''...... '" ~ r -, ~ ,-", "'" ~, 1 fE, -..J< ::::::;;::;:, ~ ~ 1 f- 1 :'! I J 1 /, ' ' " I ') I /' ,! \ '. ! I -.:l. : I . I 1 : , " i '1 ' " I I ~ 1 " : / '. 'II ' , Ii' ' " ~ : I ' 2 I I ~ I I' I'll ,~),' 11 ,,'<" /" I I,~ .. '" , Il I >i5/ I 11 ' ~ I I __ II 1 i I ---___.J " \. 'I r~~--'~-j (---==--~'=~ ( " " ii', " ! "- II " , I I: / .! II II ! r II ! I : t I I ! I I f ! I II ) II' II II II I III I I i ! ! i I I I I I \ I ~ \, / ,',) \ j M . __. ~ r:..= =:-= =':.r:, \___{".~~~~,~?~~,~c~g9-U~EV~R~M ", " r ,_ _ _ _ ,_____ \ ' \. ~ SHADY OAK POND : ) I , N 1, ~ ' ~ 1 . ; ~ , , : , .. . _.../ let , . ~-'\ . 0', IVI <( V o !! 0::: '-~ I , 1 1 .; ( I ' ) I ) I I I I ... I ( I I I ( ) ( ) r ) I I , 11 : .. 1 [ ,----. ! 1 l i j , 1 , ~ <( o ''.:I "V )-,'" 0'" II' <( :( > :c (J). '1/ V jL~ 1 ' , l ~5ai FILE NO., AHOPKN0202.00 DATE: 10/15/02 PROPOSED OUTLET SHADY OAK ROAD - OPTION HOPKINS, MN FIGURE NO. 6 . J\\" I; \' /,/" ,/' _ f ) ',/ /l" " /" ,/ \ < ." -; /",,-.,/' II , ,/ ",/,,,,, /,,/' '-- // ,/' ,,,"'- ,,pI93.J/ / ...?'"' ",' ~~,., ,..- / , , 1 ~ ~ ~ , '" t; ~ 1 \ ,! I Ii! ;; i j j I ! ,i " I! N I I ", 1 ". ' 'i ',. ' , 1 j ,.' 1 l : ,< , \. ~,_ _"MW ~ '_ ~ _J ~,_ _ _,"'- .,.;,_,_-#, , _' _, _'. '~' ,_ j 1, - ~"-"-'-~ r'- 'M. ~,",,-- - -I '" -~~.,-< "-1 I ,1 ' I' j" ,I f , " Ii" ( ! I ,'1 I J r ;1 I ' , ! J I { \ I I I { 1" = 250' j j , ( I \ , j I ii' , , ' I J .' r WI ; i i ~ 1 I Oi I I j I ! i Z) I i PR~~OSED f} ~ ! J OUT~ET I I a:: I I STRl)CTURE : J iti I ,I II /1 ~\ i'~ } I " f!'" .', ' I!' ' ", ,l , ,_,_ ,/ 1 ST "STRErt NORTH < i ,I,' ;" " !.! '-""-'" -...... ,_...... ___....... ____.. \. _._"....... ,...l"-...,.......I1_ _ rt-... ___ __ _ ",.~~"~,..# l......... ..,.;r,_,~""",~ <i', 10.0........) 6.". ~'\ -;: r '-'-~~"Ii (c~-"~- -J r 7"~~'-r ---- "'11 t , ~ I I 1 : ! ',i 21" M I ETp ;KA ; ~ .i i r: ' i I CULVER\ CFRO Sj! SING ; ; ,; ~ , !) l~l .~ 8" GRAVITY",,: t ' , , Dr / ]SrORM SEWER! I I'u i i S,t \' III ~I >i .. I : I J :',1 I j :, ;~\ ,2.J \;' I .! { j I " " ~ .::z:l , } r . I ' , W/[ , H' , I J i IV ;f'., 1q \" .. ! f l ", "L,r,';'i f.'~,,~',:,'- .. !~--.....) L,~,___~<_,......J l_,,_<__,J _,,_ ,j L:;..:;:.."",_.. _ J ~__ J: ;r---- __M~t:iS_TBEq" r- --, -. -, r'-~ == ^', ,- . l .. ." ; /;; I . .... )f I ,/ ill..' : .,' j~:'; j , , I I , ,i " J I' , ,i , I ' : I , II!! Ii . f . ! I I~b !l I {-JST $r~Ui1 { II II.: PROPOSED OUTLET 18TH AVENUE - OPTION /I HOPKINS, MN SHADY OAK POND . <(I ~i Z(f) OZ 1-- w~ zo... zO -I ~ ~~~; ......... , ] r ;' ] I ' I I L f [ . FILE NO. AHOPKN0202.00 DATE: 10/15/02 FIGURE NO.7 ......----:- PROPOSED OUTLET STRUCTURE . SHADY OAK POND ",,",\-"~-"h ,,~ ~".' ",,'- ,- \ "\ \'\ . -l " " ' , ~-;'''.'''',i~t' 'ff',,'t,r N. ~ 1 ~ - 100' , '"l1';, ';1'.."'~ ;;" L ~~' , ,I ' ;;"(..~~ .. :;:). ~"~ <1:0 .!.--- [ MINNETONKA'S JURISDICTION . 2. o cc. 'i o \ \~ \ \ \ FILE NO. AHOPKN0202.00 DATE: 10/15/02 i:^~ )~,~" "I"i,~' ;";'~"1^"f;;!.~, -:...';:;::t::,:'{.;.{;<lI ~~, '~'w{""f"= -' _."~,,, : JST.,;. ~I t;JQBT~L~e, ""-,,'" 'j~ ~ : ,:; , ~l J ,; .' ~) PROPOSED OUTLET MINNETONK'A CROSSING HOPKINS, MN FIGURE NO.8 . > 1 ; I \ .j 1 i J '1 1 i ""----'-, r"-"-"~""----) ii, ! , ! . : l ' i , r " ( ,j I Ij { ! i J ( i i 1" = 2Sq'. , , [" , f ) r ! I 1 I ' {! I I lIFTSTATIO' ~I I I j ! l' I, li~ dJi II t , I " :::> I I I I : ffi I I I I ( l>,! I ," , i <( 1 1 J ) ! I I I J:!:j f J I I ;~i i ; I I ' { " t , \" " " ( I I ,,' j i J ,I" , I I " ~ ._ ,,' " J 6 __ D1E ,.FD.RG;EMAlN" _,,_ ..... l__ -' ,,,_ ... _", _ ~ _,,) i.... ",}>>r ,,""" - ~~... "-- (,::;:;>~" ""-, - .- ~1- r -- - tSI-ST~Qon+, ! I . I ,'" I ~\ ! I '" 1 j J if ]i I! ii I t \ i 1 .. i ! J . j I 1 f ) I ; I': ! , ,t; ,I ,I j , , l I ' ' 1 ! .i (I., ) l~~ , ,! / J : . . . I ' 1 , i ;i'! ii-..j; 'I il if .>~ I . ' ,f l 1 I I r I I i ( ! I" I I. , ; ! i i, , ( it '.)l 'jl" ,.,1 ( 1 r ,,, 1 r " W( , r ) , ' I ' 1" , IVI ; -;\ \ j I" 1 5" !R,l", ' i ",' , ". i l II~~" -YL I,CP:""'"jf:,, i I. t ~:"' ... '__""__m__, ~'-- -'- ,GRAV/-p.(-"--,._.,, .J' C".... v L _.' ._, "__ J L,,_ JI(" , - -. "'" - -~ -- -'- -- ,_. -"'5.Tt}R, - ,....._"' ,- .. .- "l. r-' ,MAINSJ~E.EJ:. .r-'~ . " S ' .-. ,~- '.) I )/ EWE." J i ".,. ~ ! {' . , ~ ,,: , I ) j "" I I 'If ;/, ',' !tf . ' ,/ i '[I { i ~.f I}I f! 0::::' i J , 6 1~-ST::?~~1i+1 ~-_.J l <( r --..., !-"_.,---~._~ .r i)i i. --. I \. (J. /f I II { ( I I PROPOSED OUTLET L1FTSTATION - OPTION IV HOPKINS, MN . ; . '\ \ J : \ \. . ./ \ \ . ,,/ \ /$,;' ~~ f ,,) < ",,/ /,r ! I '- \ -r'::r~/'/ 1 ~ ,..,,)/...,. I I .,/' /''' ~ - ,~/ ,i' /f/" ".,.~' /' /'''' tIS; /;; .-" .' \ '~ '-, '- \ \\\ ,';' \ \ '- i \ ,...~...",'\ \ \ \ \, \" SHADY OAK POND /--, --1 I <(I Y:t Z'(f) . OZ 1-- wY: zo.. zO -I ~ ~ ! I . j' ,I I I I I 1 I " . .' i l ,. ! ,.,...... """,,,",mf ""* '_ >>:<<0< .-J ~l,_,.w-"_......._~..,.,.,,........... ~ :',.:' ."tN..... I ___:P._......,.... ,,,,,,,,,,,,,", -"......",..",""""!t"'" """-1 .1 J .lIr5aJ FILE NO. , AHOPKN0202.00 DATE: 10/15/02 FIGURE NO.9 . . _ .., _ I II ~ """~___=_, -:.--"q, :, L~ .._~ "",-,~""""=,~""=_~,,,,^,,,,~":;,N.::::::::.:.::_. /~.---<~'=-'"~-='- '\ "----I~::~" ,..,- -!: r/,,/"/ 1 1 r/"'-:/'" 'i I ' ',. //", II I: ~~L.:~:"'" :~: I ," i" , ': I' " '1 1 \..., .:- "..'.,.,.) (J~.. .~~ 400' L /'1 . Jr---'-'-: 1 r'-'r'.-~ r-'--'-"j //~: I II' j; I I ~, f I II // 6;(/)', ,-)1 ,'/ 1 Ii WI-:Z. 11 JI, ""I! ,I I ~:CLO~> I j <it ':!l":il-, II 2 :r: I 1 i / ii" i '~,>, ': J ,I i j ! t i \ !' '''<" " I I ,Il" ~ i: < -.J ' , '~~ i ", ! ( " _,___.._ . \,,'_~,~ _, ~'.j _,',_,_, , ~,J l il<[~~ ~r~ __...J; Ii 1,1 i i /1/ r--~' --J r--'--~ I r ~'--)]' I--'~~>~i I(~ \ \ \ __ ,I I / J' ! ' J , ' , '\ , \~:'" i i : II I ks AC~E~' i ! i i I \ \ ' ' ! I ,1 Y I, I I i I I , \\\ \, (:/. . I\',~ ) I >, , ; " I; 1 I ! ,! I \; \. ,jt ~;; '111 'III ,1; 1! \\ , / . I( Ii ',l, , I ' ji ,:1 \ '\ .\ ", /~~/~ ; '. ' ] I I I, I: ," ' i' :,' , I ' ) i \) , <?>" /: i l_~~~~'~ l'.:.__.:..~,_..-J L.._.,,::..,___ll-m.'r j L... .j t \:-~<0-;:/;:' " - ,'11 ~-I r,-.~!2:,-., )ri-I-~ 1---'">rL;Tlf' NORTR._! ~.=- \ ' I ( j f I[ I I j I 1 : ." " \ \ SHADY;', 1 ( ; r I I I I I 1, J I' , \', J ( II IVli I j ! ' j I ;, :\\\ OAK ) r {II J l . r \ '.' \)\ POND i I ; i I al I i RUNOFF i \\\ II 20 AC~~S J;V1 ; i COLL~tTION I \\\ jj 1/ 1 ;~II ,!I POINl1j J ;, ~ \.', ) I I ! I ! Ii . \' \ i I II ) ( " I' ~ .. \ \ \ I / Ii/" ,V IXI["" r ! i . I , , \\ " [J I ' I ,) " , ,..' I I I ! ! ) " t\(;/T-'-' 1 r 'r:-:"71~--:;": .~I! i~---- M:::-:=l r=4 i~-: ~\\\ I Jill ( ~l ]ll ! I ~ 'I I I 'I J ' ... I I 0\ ! j l ^ It I[ ~! I i I )::\ \ II I i r II I I I j ir::' I I I ~\ ~ I II ' " i ' II ' If-l i I I' :t.\ . : ).. 'J ' '! i ft'-..(, i l - . (Jr! (, , : I ; 1 ( . :"'-f . .' , " ill II "'/1 "'I ':-)f :"'(' 1 ) f '.' ," . } , ~ ' J I . J I i .. 1-....- .~._.J -.- -,,) L__~,~ -tv1AINSTRrET-. ...----> '-. I (,) '--' , J r -- _.-- ----""'" ~-... r - ~-, ~~ -., r- r", ""''''''',".-., .-'------ ~ r- -- - j , ' Ii, ; i J I ' J j' :- I ~ I' II ' 'J I r , j , ' ' I ' f ' . I I : ; I , I I ' I ! I ' .I "I; I ,.11 J ( ! . 'I I ' ' I ',,, i , I I i J i .S I ' : ,; i ' I Ii' I"~ i I i 'I I i -, I II I i \ l II I I II I ' i I I i , I I "'-1 I , I ~ FILE NO. AHOPKN0202.00 DATE: 10/15/02 FIGURE NO. 10 PROPOSED OUTLET FLOOD MITIGATION AREA HOPKINS, MN .',. , Appendix B Table of Results Drainage Map' Calculations . . . SHADY OAK POND OUTLET SUMMARY . . Peak Pipe Dia. Elev. Outflow Option Storm (in.) (msl) (cfs) Comments 1970 ft to Excelsior Shady Oak Rd I 100yr/24hr 24 923.36 17.12 Blvd. Shady Oak 1970 ft to Excelsior Road\Dredging I 100yr/24hr 18 923.31 8.44 Blvd. Shady Oak Rd\Mtka I 100yr/24hr 18 923.34 8.44 11.93 cfs to Mtka Shady Oak Rd . Mtka\Dredging I 100yr/24hr 12 .923.15 2.87 9.77 cfs to Mtka 2590 ft down 18th Hopkins Outlet II 100vr/24hr 24 923.38 16.58 Ave. Hopkins Outlet 2590 ft down 18th Dredging II fOOvr/24hr 18 923.35 8.17 Ave. Hopkins Outlet Mtka II 100yr/24hr 18 923.34 8.16 12.27 cfs to Mtka Hopkins Outlet Mtka\Dredging II 100yr/24hr 12 923.15 2.78 9.87 cfs to Mtka 9.6 ac-ft additional Mtka\Dredging III 100yr/24hr 21 923.21 10.47 storage Lift Station IV 100vr/24hr 5000 Qpm 923.45 11.14 Lift Station Dredging IV 100yr/24hr 3000 Qpm 923.40 6.68 Lift Station\Mtka IV 1 00yr/24h r 2000 gpm 923.42 4.45 12.27 cfs to Mtka Lift Station\Mtka Dredging IV 100yr/24hr 1200 Qpm 923.08 2.7 9.66 cfs to Mtka Shady Oak Summary.xls ~ . U \' \ \ 1\ \ , \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ ~\ \ \ \ I"t.~. Ld.. [ \\\ \ \ \ \ \\ \\ " \ \ 'v \\ \ ' \\ '" "- "- " ~ \ ~ \ lJ r c:J __J -= 250 . . 500 . SCALE. 1"= 500' / c-" ~"~ , -'~~~..... -' ,.---