Review CIP and ERP CITY OF HOPKINS Memorandum To: Honorable Mayor and Council Members Mike Mornson, City Manager From: Nick Bishop, Finance Director Date: November 9, 2021 Subject: Review 2022 – 2026 Capital Improvement & Equipment Replacement Plans _____________________________________________________________________ PURPOSE To provide input and guidance for the 2022 – 2026 Capital Improvement & Equipment Replacement Plans. INFORMATION Pages two through six provide a summary of the Park Improvement Fund, Capital Improvement Fund, Permanent Improvement Revolving Fund, Equipment Replacement fund and Pavilion requests for 2022. Projected cash flows are based on amounts in the recommended levy presented on November 9, 2021. Five year summary information for the Capital Improvement Plan is on pages 7 to 16 and for the Equipment Replacement Plan on pages 17 to 27. Finance Department 2 Park Improvement Fund The main sources of revenue for park improvements are franchise fees and park dedication fees. Annually, the City receives approximately $305,000 in gas and electric franchise fees used for the purposes of park improvements. Park dedication fees are received from developers as land is platted for development. They can provide a significant source of revenue for the fund, but are also uncertain and outside the direct control of the City. Their use is limited to acquisition, development or improvement activities. The City has received $279,000 of park dedication fees in 2021. There are no park dedication fees included in 2022 or 2023 projections. In 2022, the Park Improvement Fund has projected revenues of $305,474 and projected expenditures of $285,200. The projected expenditures include capital projects and debt service payments for Cottageville Park. They do not include debt service payments for Burnes Park. The fund is projected to increase its fund balance by $20,274 and end 2021 with a fund balance of $322,574. There are no changes to this fund since the October 10, 2021 work session. 2022 2023 Beginning Fund Balance 302,300 322,574 Revenues & Other Financing Sources Franchise Fees 305,022 305,022 Park Dedication Fees - - Interest Earnings 452 473 Total Revenue & Other Financing Sources 305,474 305,495 Expenditures & Other Financing Uses Current Expenditures 7,000 7,000 Capital Projects Shady Oak Beach Improvements 8,200 3,300 Central Park Picnic Shelters Rehab 60,000 - Central Park East Play Equipment Replacement 100,000 - Improve Courts at Oakes and Cottageville Park - 190,000 Debt Service Transfers Cottageville Park Bonds 110,000 110,000 Burnes Park Bonds - - Total Expenditures and Other Financing Sources 285,200 310,300 Increase (Decrease) in Fund Balance 20,274 (4,805) Projected Ending Fund Balance 322,574 317,769 Park Improvement Fund - Projected Cash Flows 3 Capital Improvement Fund This fund accounts for capital improvements at the Activity Center, City Hall/Police Station, Fire Station and Public Work Building. Its two funding sources are franchise fees from gas and electric utilities and a property tax levy. In 2022, the Capital Improvement Fund has projected revenues of $553,572 and projected expenditures of $466,400. The projected expenditures include debt service transfers for the City Hall renovation project, Activity Center projects and replacement of Fire Station boilers. The fund is projected to increase its fund balance by $87,172 and end 2022 with a fund balance of $294,354. The Activity Center-Facility Improvement project has been delayed by one year and the levy reduced by $10,000 since the August 10, 2021 work session. 2022 2023 Beginning Fund Balance 207,182 294,354 Revenues & Other Financing Sources Tax Levy 190,000 200,000 Franchise Fees 361,500 361,500 Interest Earnings 2,072 2,943 Total Revenue & Other Financing Sources 553,572 564,443 Expenditures & Other Financing Uses Current Expenditures Capital Projects Activity Center - Facility Improvements - 10,000 Activity Center - Gym Acoustic Panels 15,000 - Activity Center - Replace Carpeting 18,200 - Activity Center - Recover Chairs 10,000 - Activity Center - Painting Common Area 18,200 - Fire Station - Replace Boilers 45,000 - Activity Center - Raspberry Room Roof Replacement - 80,000 Activity Center - Lower Roof Replacement - 80,000 907 Mainstreet (HHS) Windows & Front/Back Doors - 55,000 Debt Service Transfers - City Hall 360,000 360,000 Total Expenditures and Other Financing Sources 466,400 585,000 Increase (Decrease) in Fund Balance 87,172 (20,557) Projected Ending Fund Balance 294,354 273,797 Capital Improvement Fund - Projected Cash Flows 4 Permanent Improvement Revolving Fund The Permanent Improvement Revolving Fund is used to account for street improvements, which can include streets, walkways, trails, traffic signs, traffic signals, vehicular parking and street lighting. The primary funding sources are debt and special assessments. Previous projects have received grants or funding from other governmental entities. In, 2022, the Permanent Improvement Revolving Fund is projected to receive $1,945,000 of bond proceeds. The major expenditures of the fund are 6th Ave South/7th Ave South street reconstruction project, a mill and overlay project on 2nd Ave S and a portion of trunk water main rehabilitation project. All the underlying utilities are replaced during each street reconstruction project and related costs and bond proceeds are recorded in those funds. The fund also includes proposed street lighting upgrades on Feltl Court in 2022 for $110,000. The project cannot be funded through bonds or special assessments. The 2022 recommended levy includes available tax levies for Equipment Replacement or Capital Improvements that could be reallocated to this purpose. There are no changes to this fund since the October 10, 2021 work session 2022 2023 Beginning Fund Balance 673,155 571,226 Revenues & Other Financing Sources Special Assessments (Prepaid)100,000 210,000 Interest Earnings 8,071 6,051 Bond Proceeds 1,945,000 3,480,000 Total Revenue & Other Financing Sources 2,053,071 3,696,051 Expenditures & Other Financing Uses Current Expenditures Capital Projects 6th Ave South/7th Ave South 1,150,000 - West Central Avenues - 3,220,000 Trunk Water Main Rehabilitation 450,000 - Pedestrian & Bicycle Access Improvements 25,000 25,000 Street Rehabilitation (Mill & Overlay)400,000 425,000 Street Sign Management 20,000 20,000 Street Lighting Upgrades 110,000 190,000 Central Business District Lighting Upgrades - 100,000 Total Expenditures and Other Financing Sources 2,155,000 3,980,000 Increase (Decrease) in Fund Balance (101,929) (283,949) Projected Ending Fund Balance 571,226 287,277 Permanent Improvement Revolving - Projected Cash Flows 5 Equipment Replacement Fund This fund accounts for the purchase of machinery and equipment. The two sources of revenue are a tax levy and equipment charges. Equipment charges are billed to various City departments and are over 99% in the General Fund. Equipment replacement has also been accomplished through the issuance of equipment certificates (debt). In 2022, the Equipment Replacement Fund has projected revenues of $1,756,540, including debt proceeds of $996,000. The projected expenditures are $1,620,477. Major purchases proposed for 2022 include a Quick Attack Pumper Fire Truck ($771,000) and Single Axle Dump Truck ($225,000). The fund is projected to increase its net position by $136,063 and end 2022 with a net position of $920,691. The levy has been reduced by 175,000 since the August 10, 2021 work session. 2022 2023 Beginning Fund Balance 784,628 920,691 Revenues & Other Financing Sources Tax Levy 75,000 250,000 Equipment Charges 669,755 709,941 Sale of Equipment 15,000 35,000 Interest Earnings 785 1,175 Equipment Certificates (Bonds)996,000 - Total Revenue & Other Financing Sources 1,756,540 996,116 Expenditures & Other Financing Uses Current Expenditures 35,248 35,600 Capital Projects Community Services - Activity Center 37,000 12,000 Community Services - Information Technology 225,729 333,085 Fire Vehicles & Equipment 787,000 105,000 Police Vehicles & Equipment 207,100 595,912 Public Works: Parks/Forestry - 199,000 Public Works: Streets/Traffic 328,400 83,500 Total Expenditures and Other Financing Sources 1,620,477 1,364,097 Increase (Decrease) in Fund Balance 136,063 (367,981) Projected Ending Fund Balance 920,691 552,710 Equipment Replacement Fund - Projected Cash Flows 6 Pavilion Requests The Pavilion Fund includes two requests for 2022. The first request is to replace and upgrade the current sound system and audio visual capabilities. The upgrade would allow for inside arena announcing, lobby music and outside rink music simultaneously. Pavilion staff is currently looking for outside funding assistance. The total cost of the project is estimated to be $70,000. The second request is to replace 60 high bay lighting fixtures with more energy efficient LED fixtures. The new LED lighting is more energy efficient and needs less maintenance. The cost of the project is estimated to be $18,000. The 2022 draft levy includes available tax levies for Equipment Replacement or Capital Improvements that could be reallocated to this purpose. There are no changes to the pavilion requests since the August 10, 2021 work session. CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP PROJECTS BY YEAR 2022 2026thru Project Name Department Project #Priority Project Cost 2022 19-CIP-AC048Activity Center - Gym Acoustical Panels n/a 15,000Comm Svcs - Activity Center 21-CIP-AC049Activity Center - Replace Carpeting in Common Area 2 18,200Comm Svcs - Activity Center 21-CIP-AC050Activity Center - Recover Chairs 2 10,000Comm Svcs - Activity Center 21-CIP-AC051Activity Center - Painting Common Areas 2 18,200Comm Svcs - Activity Center 14-CIP-AR003Arts Center - Paint Theatre 2 24,086Comm Svcs - Arts Center 19-CIP-AR002Arts Center - Outdoor Signage/lighting 2 10,000Comm Svcs - Arts Center 19-CIP-AR003Arts Center - Tile Flooring 1 18,000Comm Svcs - Arts Center 19-CIP-AR005Arts Center - Key Card Exterior & Interior Access 2 20,000Comm Svcs - Arts Center 19-CIP-AR006Arts Center - Fire Panel 2 30,000Comm Svcs - Arts Center 21-CIP-AR002Arts Center - Green Room & West Hallway Carpeting 2 16,010Comm Svcs - Arts Center 21-CIP-AR003Arts Center - Replace JC Studio Flooring 1 18,095Comm Svcs - Arts Center 08-CIP-FD123Fire Station - Replace Boilers n/a 45,000Fire 19-CIP-PV331Pavilion - Arena Lighting Replacement 2 18,000Pavilion 19-CIP-PV332Pavilion - Pav/Cent Park Sound System 2 70,000Pavilion 20-CIP-P071Central Park Picnic Shelters Rehab n/a 60,000Public Works: Parks 20-CIP-P072Central Park East Play Equipment Replacement n/a 100,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 2,375,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Rehabilitation Improvements n/a 400,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 20-CIP-S002City Street Lighting Upgrades n/a 110,000Public Works: Streets/Traffic 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 25,000Public Works: Utilities 18-CIP-U016Sewer Lining 2 52,500Public Works: Utilities 19-CIP-U017Trunk Water Main Rehabilitation 2 3,955,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 25,000Recreation 7,478,091Total for 2022 2023 08-CIP-AC024Activity Center - Raspberry Room Roof Replacement n/a 80,000Comm Svcs - Activity Center 09-CIP-AC031Activity Center - Lower Roof Replacement n/a 80,000Comm Svcs - Activity Center 19-CIP-AC045Activity Center - Facility Improvements n/a 10,000Comm Svcs - Activity Center 19-CIP-AR002Arts Center - Outdoor Signage/lighting 2 25,000Comm Svcs - Arts Center 19-CIP-AR007Arts Center - Roof Replacement 2 150,000Comm Svcs - Arts Center 19-CIP-PV330Pavilion - Indoor Turf System Replacement 2 95,000Pavilion 21-CIP-B101907 Mainstreet (HHS) Windows & Front/Back Door 5 55,000Public Works: Bldg/Equip Serv 13-CIP-P044Improve Courts at Oakes Park and Cottageville Park n/a 190,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 6,493,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Rehabilitation Improvements n/a 425,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 20-CIP-S001Central Business District Lighting Upgrades n/a 100,000Public Works: Streets/Traffic 20-CIP-S002City Street Lighting Upgrades n/a 190,000Public Works: Streets/Traffic 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 26,000Public Works: Utilities 18-CIP-U016Sewer Lining 2 55,000Public Works: Utilities Wednesday, November 3, 2021 7DRAFT Project Name Department Project #Priority Project Cost 16-CIP-R003Shady Oak Beach Improvements 3 10,000Recreation 8,029,000Total for 2023 2024 19-CIP-AC045Activity Center - Facility Improvements n/a 175,000Comm Svcs - Activity Center 19-CIP-AR002Arts Center - Outdoor Signage/lighting 2 10,000Comm Svcs - Arts Center 08-CIP-B121Fire Station: Replace 25 Ton AHU n/a 82,000Fire 20-CIP-PV334Pavilion - Arena Exit Door Replacement 3 105,000Pavilion 21-CIP-P073Repair Valley Park Basketball Court n/a 70,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 7,542,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Rehabilitation Improvements n/a 450,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 20-CIP-S001Central Business District Lighting Upgrades n/a 40,000Public Works: Streets/Traffic 20-CIP-S002City Street Lighting Upgrades n/a 200,000Public Works: Streets/Traffic 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 27,000Public Works: Utilities 18-CIP-U016Sewer Lining 2 60,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 10,000Recreation 8,816,000Total for 2024 2025 08-CIP-CH011City Hall- Site Landscaping Improvement n/a 100,000City Hall Administration 20-CIP-PV333Pavilion - Mezzanine Flooring Replacement 3 90,000Pavilion 08-CIP-PD215City Hall Police Station Rooftop n/a 240,000Police 08-CIP-B023Public Works - Replace Overhead Doors n/a 90,000Public Works: Bldg/Equip Serv 21-CIP-P074Repair Burnes Park Tennis Courts n/a 130,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 7,552,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 100,000Public Works: Streets/Traffic 16-CIP-S041Street Rehabilitation Improvements n/a 475,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 20-CIP-S002City Street Lighting Upgrades n/a 90,000Public Works: Streets/Traffic 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 28,000Public Works: Utilities 18-CIP-U016Sewer Lining 2 65,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 10,000Recreation 8,990,000Total for 2025 2026 09-CIP-CH032Council Chambers HVAC Unit n/a 15,000City Hall Administration 16-CIP-AC034Activity Ctr - Lounge/Comptr/Lib - Tables & Chairs n/a 23,500Comm Svcs - Activity Center 21-CIP-P075Repair Play Courts-Interlachen, Elmo & Park Valley n/a 120,000Public Works: Parks 01-CIP-S101Residential Street Improvements and Utilities n/a 7,567,000Public Works: Streets/Traffic 01-CIP-S104County Road 3 n/a 2,300,000Public Works: Streets/Traffic 13-CIP-S040Pedestrian & Bicycle Access Improvements n/a 25,000Public Works: Streets/Traffic 16-CIP-S041Street Rehabilitation Improvements n/a 500,000Public Works: Streets/Traffic 16-CIP-S042Street Sign Management n/a 20,000Public Works: Streets/Traffic 20-CIP-S002City Street Lighting Upgrades n/a 225,000Public Works: Streets/Traffic 20-CIP-S005Minnetonka Mills/5th St N Signal Replacement 5 600,000Public Works: Streets/Traffic 01-CIP-U002Storm Drainage System Maintenance - Alley Repairs n/a 29,000Public Works: Utilities 18-CIP-U016Sewer Lining 2 75,000Public Works: Utilities 16-CIP-R003Shady Oak Beach Improvements 3 10,000Recreation 11,509,500Total for 2026 Wednesday, November 3, 2021 8DRAFT Project Name Department Project #Priority Project Cost GRAND TOTAL 44,822,591 Wednesday, November 3, 2021 9DRAFT CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP DEPARTMENT SUMMARY 2022 2026thru Total20222023202420252026Department City Hall Administration 115,000100,000 15,000 Comm Svcs - Activity Center 429,90061,400 170,000 175,000 23,500 Comm Svcs - Arts Center 321,191136,191 175,000 10,000 Fire 127,00045,000 82,000 Pavilion 378,00088,000 95,000 105,000 90,000 Police 240,000240,000 Public Works: Bldg/Equip Serv 145,00055,000 90,000 Public Works: Parks 670,000160,000 190,000 70,000 130,000 120,000 Public Works: Streets/Traffic 37,934,0002,930,000 7,253,000 8,277,000 8,237,000 11,237,000 Public Works: Utilities 4,397,5004,032,500 81,000 87,000 93,000 104,000 Recreation 65,00025,000 10,000 10,000 10,000 10,000 7,478,091 8,029,000 8,816,000 8,990,000 11,509,500 44,822,591TOTAL Wednesday, November 3, 202110DRAFT CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP PROJECTS BY DEPARTMENT 2022 2026thru Total20222023202420252026DepartmentProject #Priority City Hall Administration 08-CIP-CH011 100,000100,000City Hall- Site Landscaping Improvement n/a 09-CIP-CH032 15,00015,000Council Chambers HVAC Unit n/a 115,000100,000 15,000City Hall Administration Total Comm Svcs - Activity Center 08-CIP-AC024 80,00080,000Activity Center - Raspberry Room Roof Replacement n/a 09-CIP-AC031 80,00080,000Activity Center - Lower Roof Replacement n/a 16-CIP-AC034 23,50023,500Activity Ctr - Lounge/Comptr/Lib - Tables & Chairs n/a 19-CIP-AC045 185,00010,000 175,000Activity Center - Facility Improvements n/a 19-CIP-AC048 15,00015,000Activity Center - Gym Acoustical Panels n/a 21-CIP-AC049 18,20018,200Activity Center - Replace Carpeting in Common Area 2 21-CIP-AC050 10,00010,000Activity Center - Recover Chairs 2 21-CIP-AC051 18,20018,200Activity Center - Painting Common Areas 2 429,90061,400 170,000 175,000 23,500Comm Svcs - Activity Center Total Comm Svcs - Arts Center 14-CIP-AR003 24,08624,086Arts Center - Paint Theatre 2 19-CIP-AR002 45,00010,000 25,000 10,000Arts Center - Outdoor Signage/lighting 2 19-CIP-AR003 18,00018,000Arts Center - Tile Flooring 1 19-CIP-AR005 20,00020,000Arts Center - Key Card Exterior & Interior Access 2 19-CIP-AR006 30,00030,000Arts Center - Fire Panel 2 19-CIP-AR007 150,000150,000Arts Center - Roof Replacement 2 21-CIP-AR002 16,01016,010Arts Center - Green Room & West Hallway Carpeting 2 21-CIP-AR003 18,09518,095Arts Center - Replace JC Studio Flooring 1 321,191136,191 175,000 10,000Comm Svcs - Arts Center Total Fire 08-CIP-B121 82,00082,000Fire Station: Replace 25 Ton AHU n/a 08-CIP-FD123 45,00045,000Fire Station - Replace Boilers n/a 127,00045,000 82,000Fire Total Pavilion 19-CIP-PV330 95,00095,000Pavilion - Indoor Turf System Replacement 2 19-CIP-PV331 18,00018,000Pavilion - Arena Lighting Replacement 2 19-CIP-PV332 70,00070,000Pavilion - Pav/Cent Park Sound System 2 20-CIP-PV333 90,00090,000Pavilion - Mezzanine Flooring Replacement 3 20-CIP-PV334 105,000105,000Pavilion - Arena Exit Door Replacement 3 378,00088,000 95,000 105,000 90,000Pavilion Total Police 08-CIP-PD215 240,000240,000City Hall Police Station Rooftop n/a Wednesday, November 3, 202111DRAFT Total20222023202420252026DepartmentProject #Priority 240,000240,000Police Total Public Works: Bldg/Equip Serv 08-CIP-B023 90,00090,000Public Works - Replace Overhead Doors n/a 21-CIP-B101 55,00055,000907 Mainstreet (HHS) Windows & Front/Back Door 5 145,00055,000 90,000Public Works: Bldg/Equip Serv Total Public Works: Parks 13-CIP-P044 190,000190,000Improve Courts at Oakes Park and Cottageville Park n/a 20-CIP-P071 60,00060,000Central Park Picnic Shelters Rehab n/a 20-CIP-P072 100,000100,000Central Park East Play Equipment Replacement n/a 21-CIP-P073 70,00070,000Repair Valley Park Basketball Court n/a 21-CIP-P074 130,000130,000Repair Burnes Park Tennis Courts n/a 21-CIP-P075 120,000120,000Repair Play Courts-Interlachen, Elmo & Park Valley n/a 670,000160,000 190,000 70,000 130,000 120,000Public Works: Parks Total Public Works: Streets/Traffic 01-CIP-S101 31,529,0002,375,000 6,493,000 7,542,000 7,552,000 7,567,000Residential Street Improvements and Utilities n/a 01-CIP-S104 2,300,0002,300,000County Road 3 n/a 13-CIP-S040 200,00025,000 25,000 25,000 100,000 25,000Pedestrian & Bicycle Access Improvements n/a 16-CIP-S041 2,250,000400,000 425,000 450,000 475,000 500,000Street Rehabilitation Improvements n/a 16-CIP-S042 100,00020,000 20,000 20,000 20,000 20,000Street Sign Management n/a 20-CIP-S001 140,000100,000 40,000Central Business District Lighting Upgrades n/a 20-CIP-S002 815,000110,000 190,000 200,000 90,000 225,000City Street Lighting Upgrades n/a 20-CIP-S005 600,000600,000Minnetonka Mills/5th St N Signal Replacement 5 37,934,0002,930,000 7,253,000 8,277,000 8,237,000 11,237,000Public Works: Streets/Traffic Total Public Works: Utilities 01-CIP-U002 135,00025,000 26,000 27,000 28,000 29,000Storm Drainage System Maintenance - Alley Repairs n/a 18-CIP-U016 307,50052,500 55,000 60,000 65,000 75,000Sewer Lining 2 19-CIP-U017 3,955,0003,955,000Trunk Water Main Rehabilitation 2 4,397,5004,032,500 81,000 87,000 93,000 104,000Public Works: Utilities Total Recreation 16-CIP-R003 65,00025,000 10,000 10,000 10,000 10,000Shady Oak Beach Improvements 3 65,00025,000 10,000 10,000 10,000 10,000Recreation Total GRAND TOTAL 44,822,5917,478,091 8,029,000 8,816,000 8,990,000 11,509,500 Wednesday, November 3, 202112DRAFT CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP FUNDING SOURCE SUMMARY 2022 thru 2026 TotalSource20222023202420252026 AC - Arts Center Fund 321,191136,191 175,000 10,000 CI - Capital Improvement Fund 984,900106,400 225,000 257,000 358,000 38,500 GU - Other Governmental Units 1,643,60016,800 6,700 6,700 6,700 1,606,700 MS - Municipal State Aid Streets 700,000700,000 PA - Pavilion Fund 378,00088,000 95,000 105,000 90,000 PDF- Park Dedication Fund 691,400168,200 193,300 73,300 133,300 123,300 PI - PIR/General Obligation Bonds 16,055,0001,655,000 2,930,000 3,620,000 3,580,000 4,270,000 RF - Refuse Fund 18,00018,000 SA - Special Assessment 4,568,000500,000 1,050,000 1,006,000 1,006,000 1,006,000 SF - Sanitary Sewer Fund 7,164,500947,500 1,418,000 1,587,000 1,610,000 1,602,000 SU - Storm Sewer Fund 2,828,000410,000 506,000 627,000 646,000 639,000 WF - Water Fund 9,470,0003,450,000 1,430,000 1,524,000 1,542,000 1,524,000 7,478,091 8,029,000 8,816,000 8,990,000 11,509,500 44,822,591GRAND TOTAL Wednesday, November 3, 2021 13DRAFT CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP PROJECTS BY FUNDING SOURCE 2022 2026thru TotalSourceProject #Priority 2022 2023 2024 2025 2026 AC - Arts Center Fund 14-CIP-AR003 24,08624,086Arts Center - Paint Theatre 2 19-CIP-AR002 45,00010,000 25,000 10,000Arts Center - Outdoor Signage/lighting 2 19-CIP-AR003 18,00018,000Arts Center - Tile Flooring 1 19-CIP-AR005 20,00020,000Arts Center - Key Card Exterior & Interior Access 2 19-CIP-AR006 30,00030,000Arts Center - Fire Panel 2 19-CIP-AR007 150,000150,000Arts Center - Roof Replacement 2 21-CIP-AR002 16,01016,010Arts Center - Green Room & West Hallway Carpeting 2 21-CIP-AR003 18,09518,095Arts Center - Replace JC Studio Flooring 1 321,191136,191 175,000 10,000AC - Arts Center Fund Total CI - Capital Improvement Fund 08-CIP-AC024 80,00080,000Activity Center - Raspberry Room Roof Replacement n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 08-CIP-B121 82,00082,000Fire Station: Replace 25 Ton AHU n/a 08-CIP-CH011 100,000100,000City Hall- Site Landscaping Improvement n/a 08-CIP-FD123 45,00045,000Fire Station - Replace Boilers n/a 08-CIP-PD215 240,000240,000City Hall Police Station Rooftop n/a 09-CIP-AC031 80,00080,000Activity Center - Lower Roof Replacement n/a 09-CIP-CH032 15,00015,000Council Chambers HVAC Unit n/a 16-CIP-AC034 23,50023,500Activity Ctr - Lounge/Comptr/Lib - Tables & Chairs n/a 19-CIP-AC045 185,00010,000 175,000Activity Center - Facility Improvements n/a 19-CIP-AC048 15,00015,000Activity Center - Gym Acoustical Panels n/a 21-CIP-AC049 18,20018,200Activity Center - Replace Carpeting in Common Area 2 21-CIP-AC050 10,00010,000Activity Center - Recover Chairs 2 21-CIP-AC051 18,20018,200Activity Center - Painting Common Areas 2 21-CIP-B101 55,00055,000907 Mainstreet (HHS) Windows & Front/Back Door 5 984,900106,400 225,000 257,000 358,000 38,500CI - Capital Improvement Fund Total GU - Other Governmental Units 01-CIP-S104 1,600,0001,600,000County Road 3 n/a 16-CIP-R003 43,60016,800 6,700 6,700 6,700 6,700Shady Oak Beach Improvements 3 1,643,60016,800 6,700 6,700 6,700 1,606,700GU - Other Governmental Units Total MS - Municipal State Aid Streets 01-CIP-S104 700,000700,000County Road 3 n/a 700,000700,000MS - Municipal State Aid Streets Total PA - Pavilion Fund 19-CIP-PV330 95,00095,000Pavilion - Indoor Turf System Replacement 2 Wednesday, November 3, 2021 14DRAFT TotalSourceProject #Priority 2022 2023 2024 2025 2026 19-CIP-PV331 18,00018,000Pavilion - Arena Lighting Replacement 2 19-CIP-PV332 70,00070,000Pavilion - Pav/Cent Park Sound System 2 20-CIP-PV333 90,00090,000Pavilion - Mezzanine Flooring Replacement 3 20-CIP-PV334 105,000105,000Pavilion - Arena Exit Door Replacement 3 378,00088,000 95,000 105,000 90,000PA - Pavilion Fund Total PDF- Park Dedication Fund 13-CIP-P044 190,000190,000Improve Courts at Oakes Park and Cottageville Park n/a 16-CIP-R003 21,4008,200 3,300 3,300 3,300 3,300Shady Oak Beach Improvements 3 20-CIP-P071 60,00060,000Central Park Picnic Shelters Rehab n/a 20-CIP-P072 100,000100,000Central Park East Play Equipment Replacement n/a 21-CIP-P073 70,00070,000Repair Valley Park Basketball Court n/a 21-CIP-P074 130,000130,000Repair Burnes Park Tennis Courts n/a 21-CIP-P075 120,000120,000Repair Play Courts-Interlachen, Elmo & Park Valley n/a 691,400168,200 193,300 73,300 133,300 123,300PDF- Park Dedication Fund Total PI - PIR/General Obligation Bonds 01-CIP-S101 11,510,000650,000 2,170,000 2,885,000 2,895,000 2,910,000Residential Street Improvements and Utilities n/a 13-CIP-S040 200,00025,000 25,000 25,000 100,000 25,000Pedestrian & Bicycle Access Improvements n/a 16-CIP-S041 2,250,000400,000 425,000 450,000 475,000 500,000Street Rehabilitation Improvements n/a 16-CIP-S042 100,00020,000 20,000 20,000 20,000 20,000Street Sign Management n/a 19-CIP-U017 450,000450,000Trunk Water Main Rehabilitation 2 20-CIP-S001 140,000100,000 40,000Central Business District Lighting Upgrades n/a 20-CIP-S002 815,000110,000 190,000 200,000 90,000 225,000City Street Lighting Upgrades n/a 20-CIP-S005 590,000590,000Minnetonka Mills/5th St N Signal Replacement 5 16,055,0001,655,000 2,930,000 3,620,000 3,580,000 4,270,000PI - PIR/General Obligation Bonds Total RF - Refuse Fund 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 18,00018,000RF - Refuse Fund Total SA - Special Assessment 01-CIP-S101 4,568,000500,000 1,050,000 1,006,000 1,006,000 1,006,000Residential Street Improvements and Utilities n/a 4,568,000500,000 1,050,000 1,006,000 1,006,000 1,006,000SA - Special Assessment Total SF - Sanitary Sewer Fund 01-CIP-S101 6,444,000500,000 1,363,000 1,527,000 1,527,000 1,527,000Residential Street Improvements and Utilities n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 18-CIP-U016 307,50052,500 55,000 60,000 65,000 75,000Sewer Lining 2 19-CIP-U017 395,000395,000Trunk Water Main Rehabilitation 2 7,164,500947,500 1,418,000 1,587,000 1,610,000 1,602,000SF - Sanitary Sewer Fund Total SU - Storm Sewer Fund 01-CIP-S101 2,505,000225,000 480,000 600,000 600,000 600,000Residential Street Improvements and Utilities n/a 01-CIP-U002 135,00025,000 26,000 27,000 28,000 29,000Storm Drainage System Maintenance - Alley Repairs n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a Wednesday, November 3, 2021 15DRAFT TotalSourceProject #Priority 2022 2023 2024 2025 2026 19-CIP-U017 160,000160,000Trunk Water Main Rehabilitation 2 20-CIP-S005 10,00010,000Minnetonka Mills/5th St N Signal Replacement 5 2,828,000410,000 506,000 627,000 646,000 639,000SU - Storm Sewer Fund Total WF - Water Fund 01-CIP-S101 6,502,000500,000 1,430,000 1,524,000 1,524,000 1,524,000Residential Street Improvements and Utilities n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 19-CIP-U017 2,950,0002,950,000Trunk Water Main Rehabilitation 2 9,470,0003,450,000 1,430,000 1,524,000 1,542,000 1,524,000WF - Water Fund Total 44,822,5917,478,091 8,029,000 8,816,000 8,990,000 11,509,500GRAND TOTAL Wednesday, November 3, 2021 16DRAFT EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN - ERP PROJECTS BY YEAR 2022 2026thru Project Name Department Project #Priority Project Cost 2022 01-ERP-0038Activity Center - Kitchen Storage 5 17,000Comm Svcs - Activity Center 01-ERP-0042Activity Center - Replace Sanitizer/Heat Booster 2 20,000Comm Svcs - Activity Center 01-ERP-1105Art Center Jaycee Studio Audio Visual n/a 13,500Comm Svcs - Arts Center 01-ERP-0003CH - Network Server n/a 25,000Comm Svcs - IT 01-ERP-0006Computers n/a 34,729Comm Svcs - IT 01-ERP-0009Network Infrastructure Upgrade n/a 0Comm Svcs - IT 01-ERP-0017IT - Office 365 n/a 44,000Comm Svcs - IT 01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT 01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 42,000Comm Svcs - IT 01-ERP-0024IT - Sandbox Security Appliance n/a 45,000Comm Svcs - IT 01-ERP-0211PD - Network Server n/a 25,000Comm Svcs - IT 01-ERP-0105Quick Attack Pumper/Rescue (Rescue 8)n/a 771,000Fire 01-ERP-0126Fire - Fire Helmets n/a 16,000Fire 01-ERP-0401HRA Copier n/a 16,500HRA 01-ERP-0200Marked Patrol Vehicles (7)n/a 110,000Police 01-ERP-0203PSO - Utility 4x4 n/a 72,100Police 01-ERP-0227Police Equipment n/a 25,000Police 01-ERP-03031 Ton Dump Truck (2)n/a 53,400Public Works: Streets/Traffic 01-ERP-0305Single Axle Dump Truck (2)n/a 225,000Public Works: Streets/Traffic 01-ERP-0309Skid Loader (2)n/a 50,000Public Works: Streets/Traffic 01-ERP-0555Generator (2)n/a 43,000Sewer 01-ERP-0560Sewer Televising Camera and Van 1 180,000Sewer 1,838,229Total for 2022 2023 01-ERP-0038Activity Center - Kitchen Storage 5 12,000Comm Svcs - Activity Center 01-ERP-0003CH - Network Server n/a 26,250Comm Svcs - IT 01-ERP-0004Telephone System n/a 89,600Comm Svcs - IT 01-ERP-0006Computers n/a 36,465Comm Svcs - IT 01-ERP-0015Backup Server n/a 72,120Comm Svcs - IT 01-ERP-0017IT - Office 365 n/a 44,000Comm Svcs - IT 01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT 01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 42,000Comm Svcs - IT 01-ERP-0211PD - Network Server n/a 26,250Comm Svcs - IT 01-ERP-0109Extrication Tool (1)n/a 32,000Fire 01-ERP-0127Fire - Lucus Device n/a 18,000Fire 01-ERP-0131Fire - Station Alerting System n/a 55,000Fire 01-ERP-04004x4 3/4 Ton Truck n/a 41,100HRA 01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police 01-ERP-0214Tactical Ballistic Vests / Helmets - SWAT 3 76,512Police 01-ERP-0215Police - Portable Radios n/a 290,000Police 01-ERP-0217Taser Replacement n/a 90,000Police 01-ERP-0218Building Video Server n/a 22,000Police 01-ERP-08001/2 Ton Pickup Truck n/a 35,400Public Works: Parks/Forestry Wednesday, November 3, 2021 17DRAFT Project Name Department Project #Priority Project Cost 01-ERP-0804Log Truck n/a 163,600Public Works: Parks/Forestry 01-ERP-03004x4 1/2 Ton Pickup with Plow n/a 28,900Public Works: Streets/Traffic 01-ERP-03041 Ton Traffic Boom Truck n/a 136,400Public Works: Streets/Traffic 1,464,997Total for 2023 2024 01-ERP-1107Art Center Theater Projection Screen 2 6,700Comm Svcs - Arts Center 01-ERP-0003CH - Network Server n/a 27,037Comm Svcs - IT 01-ERP-0006Computers n/a 37,559Comm Svcs - IT 01-ERP-0012Core Network Switch n/a 20,000Comm Svcs - IT 01-ERP-0017IT - Office 365 n/a 45,320Comm Svcs - IT 01-ERP-0020IT - Patching Automation Software 1 10,000Comm Svcs - IT 01-ERP-0022IT - Windows 10 Enterprise Upgrade n/a 63,000Comm Svcs - IT 01-ERP-0211PD - Network Server n/a 27,038Comm Svcs - IT 01-ERP-1003Pavilion - Floor Scrubber n/a 11,600Pavilion 01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police 01-ERP-0212Squad Car Camera Systems/ Body Worn Camera n/a 160,000Police 01-ERP-0220Squad Computers n/a 90,000Police 01-ERP-0221Records Management System n/a 150,000Police 01-ERP-0814Trailer Flatbed n/a 10,000Public Works: Parks/Forestry 01-ERP-03031 Ton Dump Truck (2)n/a 49,500Public Works: Streets/Traffic 01-ERP-0308Front End Loaders (2)n/a 268,600Public Works: Streets/Traffic 1,093,754Total for 2024 2025 01-ERP-1109Art Center Floor Scrubber n/a 10,800Comm Svcs - Arts Center 01-ERP-0003CH - Network Server n/a 27,849Comm Svcs - IT 01-ERP-0005Financial Software - Various Depts.n/a 315,000Comm Svcs - IT 01-ERP-0006Computers n/a 38,686Comm Svcs - IT 01-ERP-0014Distribution Network Switches n/a 57,000Comm Svcs - IT 01-ERP-0017IT - Office 365 n/a 46,680Comm Svcs - IT 01-ERP-0020IT - Patching Automation Software 1 10,300Comm Svcs - IT 01-ERP-0211PD - Network Server n/a 27,849Comm Svcs - IT 01-ERP-0052Electronic Inspections Processing 2 16,231Community Services 01-ERP-0108Self Contained Breathing Apparatus (SCBA) (45)n/a 250,000Fire 01-ERP-0112Thermal Imaging Camera (2)n/a 16,180Fire 01-ERP-0125Fire Radios - Portable and Mobile Devices n/a 386,000Fire 01-ERP-0200Marked Patrol Vehicles (7)n/a 117,400Police 01-ERP-0201Sergeant's Vehicle n/a 64,154Police 01-ERP-0227Police Equipment n/a 25,000Police 01-ERP-0900Refuse Truck (RAP-R) (2)n/a 275,200Refuse 1,684,329Total for 2025 2026 01-ERP-0035Activity Center - Floor Scrubber n/a 6,700Comm Svcs - Activity Center 01-ERP-1102Art Center Kitchen Catering Equipment n/a 7,100Comm Svcs - Arts Center 01-ERP-0003CH - Network Server n/a 28,684Comm Svcs - IT 01-ERP-0006Computers n/a 39,847Comm Svcs - IT 01-ERP-0015Backup Server n/a 78,808Comm Svcs - IT 01-ERP-0017IT - Office 365 n/a 48,080Comm Svcs - IT 01-ERP-0020IT - Patching Automation Software 1 10,609Comm Svcs - IT 01-ERP-0024IT - Sandbox Security Appliance n/a 45,000Comm Svcs - IT 01-ERP-0211PD - Network Server n/a 28,684Comm Svcs - IT 01-ERP-0113Emergency Preparedness Sirens n/a 38,500Fire Wednesday, November 3, 2021 18DRAFT Project Name Department Project #Priority Project Cost 01-ERP-0131Fire - Station Alerting System n/a 75,000Fire 01-ERP-1000Pavilion Ice Resurfacer n/a 165,000Pavilion 01-ERP-1001Pavilion - Electric Ice Edger n/a 8,900Pavilion 01-ERP-1002Pavilion Arena Scoreboard n/a 12,000Pavilion 01-ERP-0200Marked Patrol Vehicles (7)n/a 128,000Police 01-ERP-0202PSO / Parking Enforcement Vehicle n/a 60,000Police 01-ERP-0203PSO - Utility 4x4 n/a 86,100Police 01-ERP-0218Building Video Server n/a 17,000Police 01-ERP-07104X4 3/4 Ton Truck n/a 42,100Public Works: Bldg/Equip Serv 01-ERP-0808Riding Mowers (2)1 17,700Public Works: Parks/Forestry 01-ERP-0816Toolcat n/a 80,200Public Works: Parks/Forestry 01-ERP-0317Sign Machine (Traffic)n/a 18,100Public Works: Streets/Traffic 01-ERP-05513/4 Ton Utility Truck n/a 45,200Sewer 01-ERP-05013/4 Ton Utility Truck n/a 46,900Water 1,134,212Total for 2026 GRAND TOTAL 7,215,521 Wednesday, November 3, 2021 19DRAFT EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN - ERP DEPARTMENT SUMMARY 2022 2026thru Total20222023202420252026Department Comm Svcs - Activity Center 55,70037,000 12,000 6,700 Comm Svcs - Arts Center 38,10013,500 6,700 10,800 7,100 Comm Svcs - IT 1,605,444225,729 346,685 229,954 523,364 279,712 Community Services 16,23116,231 Fire 1,657,680787,000 105,000 652,180 113,500 HRA 57,60016,500 41,100 Pavilion 197,50011,600 185,900 Police 1,818,066207,100 595,912 517,400 206,554 291,100 Public Works: Bldg/Equip Serv 42,10042,100 Public Works: Parks/Forestry 306,900199,000 10,000 97,900 Public Works: Streets/Traffic 829,900328,400 165,300 318,100 18,100 Refuse 275,200275,200 Sewer 268,200223,000 45,200 Water 46,90046,900 1,838,229 1,464,997 1,093,754 1,684,329 1,134,212 7,215,521TOTAL Wednesday, November 3, 202120DRAFT EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN - ERP PROJECTS BY DEPARTMENT 2022 2026thru Total20222023202420252026DepartmentProject #Priority Comm Svcs - Activity Center 01-ERP-0035 6,7006,700Activity Center - Floor Scrubber n/a 01-ERP-0038 29,00017,000 12,000Activity Center - Kitchen Storage 5 01-ERP-0042 20,00020,000Activity Center - Replace Sanitizer/Heat Booster 2 55,70037,000 12,000 6,700Comm Svcs - Activity Center Total Comm Svcs - Arts Center 01-ERP-1102 7,1007,100Art Center Kitchen Catering Equipment n/a 01-ERP-1105 13,50013,500Art Center Jaycee Studio Audio Visual n/a 01-ERP-1107 6,7006,700Art Center Theater Projection Screen 2 01-ERP-1109 10,80010,800Art Center Floor Scrubber n/a 38,10013,500 6,700 10,800 7,100Comm Svcs - Arts Center Total Comm Svcs - IT 01-ERP-0003 134,82025,000 26,250 27,037 27,849 28,684CH - Network Server n/a 01-ERP-0004 89,60089,600Telephone System n/a 01-ERP-0005 315,000315,000Financial Software - Various Depts.n/a 01-ERP-0006 187,28634,729 36,465 37,559 38,686 39,847Computersn/a 01-ERP-0009 00Network Infrastructure Upgrade n/a 01-ERP-0012 20,00020,000Core Network Switch n/a 01-ERP-0014 57,00057,000Distribution Network Switches n/a 01-ERP-0015 150,92872,120 78,808Backup Server n/a 01-ERP-0017 228,08044,000 44,000 45,320 46,680 48,080IT - Office 365 n/a 01-ERP-0020 50,90910,000 10,000 10,000 10,300 10,609IT - Patching Automation Software 1 01-ERP-0022 147,00042,000 42,000 63,000IT - Windows 10 Enterprise Upgrade n/a 01-ERP-0024 90,00045,000 45,000IT - Sandbox Security Appliance n/a 01-ERP-0211 134,82125,000 26,250 27,038 27,849 28,684PD - Network Server n/a 1,605,444225,729 346,685 229,954 523,364 279,712Comm Svcs - IT Total Community Services 01-ERP-0052 16,23116,231Electronic Inspections Processing 2 16,23116,231Community Services Total Fire 01-ERP-0105 771,000771,000Quick Attack Pumper/Rescue (Rescue 8)n/a 01-ERP-0108 250,000250,000Self Contained Breathing Apparatus (SCBA) (45)n/a 01-ERP-0109 32,00032,000Extrication Tool (1)n/a 01-ERP-0112 16,18016,180Thermal Imaging Camera (2)n/a 01-ERP-0113 38,50038,500Emergency Preparedness Sirens n/a 01-ERP-0125 386,000386,000Fire Radios - Portable and Mobile Devices n/a 01-ERP-0126 16,00016,000Fire - Fire Helmets n/a 01-ERP-0127 18,00018,000Fire - Lucus Device n/a 01-ERP-0131 130,00055,000 75,000Fire - Station Alerting System n/a Wednesday, November 3, 202121DRAFT Total20222023202420252026DepartmentProject #Priority 1,657,680787,000 105,000 652,180 113,500Fire Total HRA 01-ERP-0400 41,10041,1004x4 3/4 Ton Truck n/a 01-ERP-0401 16,50016,500HRA Copier n/a 57,60016,500 41,100HRA Total Pavilion 01-ERP-1000 165,000165,000Pavilion Ice Resurfacer n/a 01-ERP-1001 8,9008,900Pavilion - Electric Ice Edger n/a 01-ERP-1002 12,00012,000Pavilion Arena Scoreboard n/a 01-ERP-1003 11,60011,600Pavilion - Floor Scrubber n/a 197,50011,600 185,900Pavilion Total Police 01-ERP-0200 590,200110,000 117,400 117,400 117,400 128,000Marked Patrol Vehicles (7)n/a 01-ERP-0201 64,15464,154Sergeant's Vehicle n/a 01-ERP-0202 60,00060,000PSO / Parking Enforcement Vehicle n/a 01-ERP-0203 158,20072,100 86,100PSO - Utility 4x4 n/a 01-ERP-0212 160,000160,000Squad Car Camera Systems/ Body Worn Camera n/a 01-ERP-0214 76,51276,512Tactical Ballistic Vests / Helmets - SWAT 3 01-ERP-0215 290,000290,000Police - Portable Radios n/a 01-ERP-0217 90,00090,000Taser Replacement n/a 01-ERP-0218 39,00022,000 17,000Building Video Server n/a 01-ERP-0220 90,00090,000Squad Computers n/a 01-ERP-0221 150,000150,000Records Management System n/a 01-ERP-0227 50,00025,000 25,000Police Equipment n/a 1,818,066207,100 595,912 517,400 206,554 291,100Police Total Public Works: Bldg/Equip Serv 01-ERP-0710 42,10042,1004X4 3/4 Ton Truck n/a 42,10042,100Public Works: Bldg/Equip Serv Total Public Works: Parks/Forestry 01-ERP-0800 35,40035,4001/2 Ton Pickup Truck n/a 01-ERP-0804 163,600163,600Log Truck n/a 01-ERP-0808 17,70017,700Riding Mowers (2)1 01-ERP-0814 10,00010,000Trailer Flatbed n/a 01-ERP-0816 80,20080,200Toolcatn/a 306,900199,000 10,000 97,900Public Works: Parks/Forestry Total Public Works: Streets/Traffic 01-ERP-0300 28,90028,9004x4 1/2 Ton Pickup with Plow n/a 01-ERP-0303 102,90053,400 49,5001 Ton Dump Truck (2)n/a 01-ERP-0304 136,400136,4001 Ton Traffic Boom Truck n/a 01-ERP-0305 225,000225,000Single Axle Dump Truck (2)n/a 01-ERP-0308 268,600268,600Front End Loaders (2)n/a 01-ERP-0309 50,00050,000Skid Loader (2)n/a 01-ERP-0317 18,10018,100Sign Machine (Traffic)n/a 829,900328,400 165,300 318,100 18,100Public Works: Streets/Traffic Total Wednesday, November 3, 202122DRAFT Total20222023202420252026DepartmentProject #Priority Refuse 01-ERP-0900 275,200275,200Refuse Truck (RAP-R) (2)n/a 275,200275,200Refuse Total Sewer 01-ERP-0551 45,20045,2003/4 Ton Utility Truck n/a 01-ERP-0555 43,00043,000Generator (2)n/a 01-ERP-0560 180,000180,000Sewer Televising Camera and Van 1 268,200223,000 45,200Sewer Total Water 01-ERP-0501 46,90046,9003/4 Ton Utility Truck n/a 46,90046,900Water Total GRAND TOTAL 7,215,5211,838,229 1,464,997 1,093,754 1,684,329 1,134,212 Wednesday, November 3, 202123DRAFT EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN - ERP FUNDING SOURCE SUMMARY 2022 thru 2026 TotalSource20222023202420252026 AC - Arts Center Fund 38,10013,500 6,700 10,800 7,100 Equipment Replacement Fund 6,228,6211,585,229 1,328,497 1,067,454 1,398,329 849,112 HRA - Housing and Redevelopment Authority 57,60016,500 41,100 PA - Pavilion Fund 197,50011,600 185,900 PKG - Parking Fund 8,0008,000 RF - Refuse Fund 357,00081,800 275,200 SF - Sanitary Sewer Fund 275,000223,000 6,800 45,200 WF - Water Fund 53,7006,800 46,900 1,838,229 1,464,997 1,093,754 1,684,329 1,134,212 7,215,521GRAND TOTAL Wednesday, November 3, 2021 24DRAFT EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN - ERP PROJECTS BY FUNDING SOURCE 2022 2026thru TotalSourceProject #Priority 2022 2023 2024 2025 2026 AC - Arts Center Fund 01-ERP-1102 7,1007,100Art Center Kitchen Catering Equipment n/a 01-ERP-1105 13,50013,500Art Center Jaycee Studio Audio Visual n/a 01-ERP-1107 6,7006,700Art Center Theater Projection Screen 2 01-ERP-1109 10,80010,800Art Center Floor Scrubber n/a 38,10013,500 6,700 10,800 7,100AC - Arts Center Fund Total Equipment Replacement Fund 01-ERP-0003 134,82025,000 26,250 27,037 27,849 28,684CH - Network Server n/a 01-ERP-0004 76,00076,000Telephone System n/a 01-ERP-0005 315,000315,000Financial Software - Various Depts.n/a 01-ERP-0006 187,28634,729 36,465 37,559 38,686 39,847Computersn/a 01-ERP-0009 00Network Infrastructure Upgrade n/a 01-ERP-0012 20,00020,000Core Network Switch n/a 01-ERP-0014 57,00057,000Distribution Network Switches n/a 01-ERP-0015 150,92872,120 78,808Backup Server n/a 01-ERP-0017 228,08044,000 44,000 45,320 46,680 48,080IT - Office 365 n/a 01-ERP-0020 50,90910,000 10,000 10,000 10,300 10,609IT - Patching Automation Software 1 01-ERP-0022 147,00042,000 42,000 63,000IT - Windows 10 Enterprise Upgrade n/a 01-ERP-0024 90,00045,000 45,000IT - Sandbox Security Appliance n/a 01-ERP-0035 6,7006,700Activity Center - Floor Scrubber n/a 01-ERP-0038 29,00017,000 12,000Activity Center - Kitchen Storage 5 01-ERP-0042 20,00020,000Activity Center - Replace Sanitizer/Heat Booster 2 01-ERP-0052 16,23116,231Electronic Inspections Processing 2 01-ERP-0105 771,000771,000Quick Attack Pumper/Rescue (Rescue 8)n/a 01-ERP-0108 250,000250,000Self Contained Breathing Apparatus (SCBA) (45)n/a 01-ERP-0109 32,00032,000Extrication Tool (1)n/a 01-ERP-0112 16,18016,180Thermal Imaging Camera (2)n/a 01-ERP-0113 38,50038,500Emergency Preparedness Sirens n/a 01-ERP-0125 386,000386,000Fire Radios - Portable and Mobile Devices n/a 01-ERP-0126 16,00016,000Fire - Fire Helmets n/a 01-ERP-0127 18,00018,000Fire - Lucus Device n/a 01-ERP-0131 130,00055,000 75,000Fire - Station Alerting System n/a 01-ERP-0200 590,200110,000 117,400 117,400 117,400 128,000Marked Patrol Vehicles (7)n/a 01-ERP-0201 64,15464,154Sergeant's Vehicle n/a 01-ERP-0202 60,00060,000PSO / Parking Enforcement Vehicle n/a 01-ERP-0203 158,20072,100 86,100PSO - Utility 4x4 n/a 01-ERP-0211 134,82125,000 26,250 27,038 27,849 28,684PD - Network Server n/a 01-ERP-0212 152,000152,000Squad Car Camera Systems/ Body Worn Camera n/a 01-ERP-0214 76,51276,512Tactical Ballistic Vests / Helmets - SWAT 3 01-ERP-0215 290,000290,000Police - Portable Radios n/a 01-ERP-0217 90,00090,000Taser Replacement n/a 01-ERP-0218 39,00022,000 17,000Building Video Server n/a 01-ERP-0220 90,00090,000Squad Computers n/a Wednesday, November 3, 2021 25DRAFT TotalSourceProject #Priority 2022 2023 2024 2025 2026 01-ERP-0221 150,000150,000Records Management System n/a 01-ERP-0227 50,00025,000 25,000Police Equipment n/a 01-ERP-0300 28,90028,9004x4 1/2 Ton Pickup with Plow n/a 01-ERP-0303 102,90053,400 49,5001 Ton Dump Truck (2)n/a 01-ERP-0304 136,400136,4001 Ton Traffic Boom Truck n/a 01-ERP-0305 225,000225,000Single Axle Dump Truck (2)n/a 01-ERP-0308 268,600268,600Front End Loaders (2)n/a 01-ERP-0309 50,00050,000Skid Loader (2)n/a 01-ERP-0317 18,10018,100Sign Machine (Traffic)n/a 01-ERP-0710 42,10042,1004X4 3/4 Ton Truck n/a 01-ERP-0800 35,40035,4001/2 Ton Pickup Truck n/a 01-ERP-0804 81,80081,800Log Truck n/a 01-ERP-0808 17,70017,700Riding Mowers (2)1 01-ERP-0814 10,00010,000Trailer Flatbed n/a 01-ERP-0816 80,20080,200Toolcatn/a 6,228,6211,585,229 1,328,497 1,067,454 1,398,329 849,112Equipment Replacement Fund Total HRA - Housing and Redevelopment A 01-ERP-0400 41,10041,1004x4 3/4 Ton Truck n/a 01-ERP-0401 16,50016,500HRA Copier n/a 57,60016,500 41,100HRA - Housing and Redevelopment Authority Total PA - Pavilion Fund 01-ERP-1000 165,000165,000Pavilion Ice Resurfacer n/a 01-ERP-1001 8,9008,900Pavilion - Electric Ice Edger n/a 01-ERP-1002 12,00012,000Pavilion Arena Scoreboard n/a 01-ERP-1003 11,60011,600Pavilion - Floor Scrubber n/a 197,50011,600 185,900PA - Pavilion Fund Total PKG - Parking Fund 01-ERP-0212 8,0008,000Squad Car Camera Systems/ Body Worn Camera n/a 8,0008,000PKG - Parking Fund Total RF - Refuse Fund 01-ERP-0804 81,80081,800Log Truck n/a 01-ERP-0900 275,200275,200Refuse Truck (RAP-R) (2)n/a 357,00081,800 275,200RF - Refuse Fund Total SF - Sanitary Sewer Fund 01-ERP-0004 6,8006,800Telephone System n/a 01-ERP-0551 45,20045,2003/4 Ton Utility Truck n/a 01-ERP-0555 43,00043,000Generator (2)n/a 01-ERP-0560 180,000180,000Sewer Televising Camera and Van 1 275,000223,000 6,800 45,200SF - Sanitary Sewer Fund Total WF - Water Fund Wednesday, November 3, 2021 26DRAFT TotalSourceProject #Priority 2022 2023 2024 2025 2026 01-ERP-0004 6,8006,800Telephone System n/a 01-ERP-0501 46,90046,9003/4 Ton Utility Truck n/a 53,7006,800 46,900WF - Water Fund Total 7,215,5211,838,229 1,464,997 1,093,754 1,684,329 1,134,212GRAND TOTAL Wednesday, November 3, 2021 27DRAFT 2022 –2026 Equipment Replacement & Capital Improvement Plans November 9, 2021 Equipment Replacement Fund Funding Sources -$1.76 million User Department Charges $669,755 in 2022, a 6% increase o 99.88% in General Fund o 0.06% in Economic Development and Communications Funds $250,000 Tax Levy in 2022 Reduced by $175,000 Equipment Certificates (bond proceeds) of $996K in 2022 Equipment Replacement Fund 2022 projects total $1,620,477 Fire -$787,000 Streets/Traffic -$328,400 Information Technology -$225,729 Police -$207,100 Activity Center -$37,000 Equipment Replacement Fund Bond Proceeds of $996,000 Quick Attack Pumper Fire Truck -$771,000 Single Axle Dump Truck -$225,000 Equipment Replacement Fund Projecting a $136,063,063 increase to fund balance Ending balance in Equipment Replacement Fund of $920,691 Capital Improvement Plan Funds Supported by Tax Levy Arts Center Capital Improvement Park Dedication Permanent Improvement Revolving Pavilion Directly Funded Water Sanitary Sewer Storm Sewer Refuse Capital Improvement Fund Funding Sources Tax Levy, $190,000 in 2022 Reduced by $10,000 Franchise Fees, $361,500 in 2022 Bond Proceeds, none planned Capital Improvement Fund $106,400 of projects in 2022 Activity Center & Fire Station Reduced by $10,000 Bond Payments of $360,000 City Hall Projected to increase fund balance by $87,172 Permanent Improvement Funding Sources Bond Proceeds, $1.945 Million in 2022 Paid by tax levy & special assessments Bond issuance will also include amounts for Water, Sewer & Storm Sewer Fund Prepaid Special Assessments of $100,000 Permanent Improvement Previously included projects 6th Ave South/7th Ave South -$1.15 million Trunk Water Main -$450K May not actually need support from this fund Pedestrian & Bicycle Access, Street Rehabilitation and Sign Management -$445K Permanent Improvement Previously proposed, but not funded City Street Lighting Upgrade -$110,000 Feltl Court Current lighting is an end of useful life and not efficient Reallocate equipment replacement or capital improvement levies Pavilion Fund 2022 Requests Replace and Upgrade Sound System -$70,000 Replace 60 high bay lighting fixtures with LED fixtures -$18,000 Reallocate equipment replacement or capital improvement levies Next Steps –2022 Budget Meeting Date Meeting Type Subject Details November 16 Regular Meeting Approve CIP and ERP December 6 (Monday) Special Meeting Truth in Taxation Hearing -Overview of 2022 Budget and Tax Levy -Public Comment December 7 Regular Meeting Approve Final Budget and Tax Levy December 21 Regular Meeting Approve Final Budget and Tax Levy -Last scheduled meeting to approve