V.1. Public Improvement Hearing 2023 Street and Utility Improvements, City Project 2022-10; KlingbeilOctober 18, 2022 Council Report 2022-092
PUBLIC IMPROVEMENT HEARING
2023 STREET AND UTILITY IMPROVEMENTS
CITY PROJECT 2022-10
Proposed Action
Staff recommends the following motion: following Public Hearing adopt Resolution 2022-065, Resolution
Ordering Improvement, 2023 Street and Utility Improvements and companion Resolution 2022-072, stating
the City’s intent to reimburse itself using bonds. This action continues an assessable project for street and
utility improvements.
Overview
At its October 4, 2021 meeting, a feasibility report concerning street and utility improvements along 12th
Avenue N from Mainstreet to 1st Street N, 14th Avenue N from Mainstreet to 2nd Street N, 15th Avenue N
from Mainstreet to 2nd Street N, 16th Avenue N from Mainstreet to 1st Street N and 2nd Street N to 3rd Street
N, and 2nd Street N from 14th Avenue N to 15th Avenue N was presented to the City Council and a public
hearing on the improvements was ordered for November 1, 2022.
In accordance with state statutes, the City Council needs to conduct a public hearing and determine
authorization of the project. Hearing notices have been mailed to all affected property owners of record.
Following the public hearing, if the project is ordered, City Council is asked to state the City’s intent to
reimburse itself using bonds.
Primary Issues to Consider
Scope of Improvements
Public Input
Assessments
Project Budget, Costs, and Schedule
Staff Recommendation
Supporting Information
Resolution 2022-065 & 2022-072
Project Map
Public Hearing Notice & Mailing Affidavit
Proposed Pending Assessment Roll
Proposal for Design and Construction Services
Feasibility Report (available upon request)
_________________________________
Eric Klingbeil, P.E., City Engineer
Financial Impact: $8,855,000 Budgeted: Y/N _Y_ Source: _PIR, SA, Water, Sanitary, Storm
Related Documents (CIP, ERP, etc.): CIP _ Notes: _________________________________________
Council Report 2022-092
Page 2
ANALYSIS OF ISSUES
Scope of Improvements
This project includes improvement of the following streets:
12th Avenue N from Mainstreet to 1st Street N
14th Avenue N from Mainstreet to 2nd Street N
15th Avenue N from Mainstreet to 2nd Street N
16th Avenue N from Mainstreet to 1st Street N and 2nd Street N to 3rd Street N
2nd Street N from 14th Avenue N to 15th Avenue N
The pavement condition index for most of the project area is below 40, which indicates failed pavement
and warrants reconstruction. Maintenance procedures such as seal coating, mill and overlay, or
reclamation are no longer effective strategies. Proposed street improvements include full reconstruction
of streets and new curb and gutter.
Water main is proposed to be replaced in the entire reconstruction area. Most of the existing main is in
excess of 60 years old and made from cast iron. New main will be ductile iron, which has better
reliability and when properly installed a longer lifecycle than cast iron. All water services will be
replaced from the main to the property line.
Sanitary sewer improvements consist of replacing old and outdated material mains. The existing sanitary
sewer mains are in excess of 60 years old and are made of and outdated material, clay. Portions of the
sanitary sewer near Mainstreet will be lined with cured-in-place-pipe (CIPP) material to avoid
excavation impacts in Mainstreet.
Proposed storm sewer improvements include new curb and gutter, removal and replacement of the
existing storm sewer mains, upsizing mains in select areas to better handle larger storm events, and
addition of storm sewer inlets to reduce water ponding in the street.
Pedestrian facilities include:
Replacement of existing sidewalk and pedestrian ramps in the reconstruction area
Addition of new sidewalk along the east side of 14th Ave N from 1st St N to 2nd St N along
Maetzold Field
Addition of new sidewalk to fill in sidewalk gaps on 1st St N from 14th Ave N to 16th Ave N.
During the scoping for this project, it was determined that there was other work that should be included
in the project. Traditionally this work was bid as a separate, standalone project but in recent years it has
been bid with the street and utility improvement project and the City has received very favorable bid
prices as a result.
This additional work will be funded by separate items in the CIP and Budget and includes the following:
Storm sewer and drainage improvements for the backyards between 13th Ave N and 14th Ave N
south of 3rd Street N.
Reclamation and resurfacing of 10th Ave S from Mainstreet to 1st St S
Reclamation and resurfacing of 9th Ave S from 1st St S to Excelsior Blvd
Reclamation and resurfacing of 1st St S from 9th Ave S to 11th Ave N
Council Report 2022-092
Page 3
Mill and overlay 9th Ave S from Mainstreet to 1st St S
Mill and overlay 1st St S from 8th Ave S to 9th Ave S
Sanitary Sewer Lining in areas across the City identified by the Public Works Department.
Citywide sidewalk repairs
Public Input
Public informational meetings regarding the improvements were held on September 14th and October
24th. The September 14th meeting format consisted of a presentation of the overall project scope, with
an open house style question and answer session. The October 24th meeting was an open house style
meeting, with special focus on proposed assessments.
A questionnaire was sent to all properties in the project area in May 2022 in advance of the
neighborhood meetings. 30 questionnaires were returned. Drainage concerns, pedestrian facility
concerns, desire for improved street surface, and property specific concerns were the most common
responses.
Assessments
The proposed street assessments are based on the City’s assessment policy, whereby 70% of the street
reconstruction cost and 50% of the water and sewer service replacement are assessed to benefiting
properties. The policy also allows for assessments to be capped should assessments exceed previous year
assessments by 20%; the costs for this project will trigger the assessment cap. A preliminary assessment
roll has been calculated and can be found in the appendix of the attached Feasibility Report. The final
assessment amounts will likely be lower than presented in the report. Currently, staff is working to
identify properties that were assessed in adjacent projects to determine if the assessment cap would have
been in a factor if the projects had been assessed as one project.
The assessment cap for residential properties is $103.05 per front foot, following the typical 3% increase
per year. Without the cap assessments could be more than double the capped rate.
Project Budget and Costs
The estimate for this project, which includes contingency, and costs for legal, administrative, and
engineering costs for all the work, totals to $8,855,000.
Project costs and funding sources are as follows:
Council Report 2022-092
Page 4
Preliminary cost estimates show the project tracking higher than the CIP budget, this is due to additional
work outside the original scope included with the project, conservative estimates for contingencies and
soft costs, and very conservative construction unit prices due volatile construction material costs in
recent years. It is anticipated that costs will come down as design progresses due to reduced contingency
and efficiencies in design.
Several portions of the project are street maintenance projects outside the original scope and are being
bid as “Add Alternates”. We will have the option of moving forward with these items or to remove them
from the project once bids are received, based on budget constraints. Currently, Add Alternates account
for approximately $770,000 of the total estimated project cost.
Project Schedule
Accept feasibility report/order public hearing October 4, 2022
Public Informational Neighborhood Meeting October 24, 2022
Public hearing/order final design November 1, 2022
Approve final plans/order bids January 17, 2023
Order Assessment Hearing February 21, 2023
Public Informational Neighborhood Meeting March 13-16 (Date TBD)
Conduct Public Assessment Hearing March 21, 2023
Adopt Assessment Roll/Award Contract March 21, 2023
Begin Construction Spring 2023
Complete Construction Fall 2023
Staff Recommendation
Staff recommends ordering the above detailed improvement with adoption of resolution 2021-065 and
adopting companion resolution 2021-072 following the public hearing.
Funding Source CIP Budget
Street Reconstruction
CIP Budget
Street Rehabilitation/
Sewer Lining/
Pedestrian
Improvements
Estimated Cost
PI-PIR/General Obligation
Bonds
$2,170,000 $450,000 $3,500,000
Assessments 1,050,000 1,185,000
Storm Sewer Fund 480,000 840,000
Sanitary Sewer Fund 1,363,000 55,000 1,520,000
Water Fund 1,430,000 1,810,000
Total $6,493,000 $505,000 $8,855,000
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2022-065
RESOLUTION ORDERING PUBLIC IMPROVEMENT
2023 STREET AND UTILITY IMPROVEMENTS, PROJECT NO. 2022-10
WHEREAS, a resolution of the City Council adopted the 4th day of October, 2022 fixed
a date for a Council Hearing on the improvements on 12th Avenue N from Mainstreet to
1st Street N, 14th Avenue N from Mainstreet to 2nd Street N, 15th Avenue N from
Mainstreet to 2nd Street N, 16th Avenue N from Mainstreet to 1st Street N and 2nd Street N
to 3rd Street N, and 2nd Street N from 14th Avenue N to 15th Avenue N ; including
pavement, curbing, sidewalk, signage, drainage, water and sanitary sewer improvements
and all necessary appurtenances, and
WHEREAS, the City Council deems it appropriate and expedient to make such
improvements, and
WHEREAS, ten days mailed notice and two weeks published notice of the hearing was
given, and the hearing was held thereon on the 19th day of October, 2021 at which all
persons desiring to be heard were given an opportunity to be heard thereon.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Hopkins, Minnesota:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the
feasibility report and the recommendations are hereby accepted.
2. Such improvement is hereby ordered as proposed in the Council Resolution
adopted the 4th day of October, 2021. The total estimated project cost is
$8,855,000 of which $1,185,000 is estimated to be assessed.
3. Bolton & Menk, Inc. is hereby designated as the engineer for this improvement
and shall prepare plans and specifications for the making of such improvement.
The Mayor and City Manager are hereby authorized to enter into a contract for
engineering and construction services for this improvement.
4. The City Attorney and City Engineer are hereby authorized to acquire necessary
easements by negotiation or condemnation.
Adopted by the City Council of the City of Hopkins this 1st day of November, 2022.
______________________
Patrick Hanlon, Mayor
ATTEST:
_______________________________
Amy Domeier, City Clerk
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2022-072
DECLARING THE OFFICIAL INTENT OF THE CITY OF HOPKINS
TO REIMBURSE CERTAIN EXPENDITURES FROM
GENERAL OBLIGATION IMPROVEMENT BOND PROCEEDS
TO BE ISSUED BY THE CITY OF HOPKINS
WHEREAS, the Internal Revenue Service has issued Treas. Reg. #1.150-2 providing that
proceeds of tax-exempt bonds used to reimburse prior expenditures shall not be deemed
spent unless certain requirements are met; and
WHEREAS, the City expects to incur certain expenditures, which may be financed
temporarily from sources other than bonds, and reimbursed from the bond proceeds;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Hopkins,
Minnesota:
1. The City intends to incur expenditures for the project described in Council Report
2022-092, for City Project 2022-10 (the “Project”), and intends to reimburse itself
for such expenditures from the bond proceeds to be issued by the City in the
maximum principal amount described in the “project”.
2. The City Manager is authorized to designate additions to Project 2022-10 in
circumstances where time is of the essence, and any such designation shall be
reported to the Council at the earliest practicable date and shall be filed with the
official books and records of the City.
3. This resolution is intended to constitute a declaration of official intent for the
purpose of Treas. Reg. #1.150-2 and any successor law, regulation, ruling or
amendment pertaining thereto.
Adopted by the City Council of the City of Hopkins, Minnesota, this 1st day of November,
2022.
By_______________________________
Patrick Hanlon, Mayor
ATTEST:
_______________________________
Amy Domeier, City Clerk
CITY OF HOPKINS
Hennepin County, Minnesota
NOTICE OF PUBLIC HEARING ON IMPROVEMENT
2023 STREET AND UTILITY IMPROVEMENTS
CITY PROJECT NO. 2022-10
«TAXPAYER_NAME»
«TAXPAYER_ADDRESS_LINE1»
«TAXPAYER_ADDRESS_LINE2»
«TAXPAYER_ADDRESS_LINE3»
RE: PID #«PID» - «PROPERTY_ADDRESS», HOPKINS, MN
TO WHOM IT MAY CONCERN:
Notice is hereby given that the City Council will hold the Public Hearing in the Council Chambers of
City Hall, 1010 1st St S, at 6:30 p.m. on Tuesday, November 1st, 2022, to consider the making of
improvements on:
12th Avenue North from Mainstreet to 1st Street North; 14th Avenue North from Mainstreet to 2nd
Street North; 15th Avenue North from Mainstreet to 2nd Street North; 16th Avenue North from
Mainstreet to 1st Street North and from 2nd Street North to 3rd Street North; and 2nd Street North from
14th Avenue North to 15th Avenue North.
Generally, the project involves the addition/replacement of storm sewer; water main replacement; water
service replacement; sanitary sewer replacement and rehabilitation; sanitary sewer service replacement;
concrete curb & gutter addition/replacement; bituminous street removal and reconstruction; and turf
restoration; pursuant to Minn. Statutes, Section 429.011 to 429.111. The area proposed to be assessed
for such improvement includes all properties located along the streets listed above and as shown below.
Plat Name Sec Twp Rng Q/Q
West Minneapolis 2nd Division 24 117 22 NE/SW
Stein Addn 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 SW/NW
The estimated cost of the improvement is $8,855,000. A reasonable estimate of the impact of the
assessment will be available at the hearing. Such persons as desire to be heard with reference to the
proposed improvement will be heard at this meeting.
/s/Amy Domeier, City Clerk
Dated: October 12, 2022
Published in Hopkins Sun Sailor on October 20, 2022 & October 27, 2022
YOUR ESTIMATED PENDING ASSESSMENT IS:
«TOTAL_PROPOSED_ASSESSMENT»
AFFIDAVIT OF MAILING PUBLIC HEARING NOTICE
STATE OF MINNESOTA )
)SS.
COUNCIL OF HOPKINS )
Jackie Caple,being first duly sworn,deposed and says:
I am a United States citizen,over 21 years of age.On October 12,2022,acting on behalf of the
City of Hopkins,I caused to be deposited in the United States Post Office at the City of
Burnsville,Minnesota,copies of the attached Notice of Public Hearing for the 2023 Street &
Utility Improvements,City of Hopkins,MN Project No.2022-010,enclosed in sealed envelopes,
with postage thereon fully prepaid,addressed to the following persons at the addresses appearing
on the attached copy of the mailing list.
There is delivery service by United States mail between the place of mailing and the places so
addressed.
Subscribed and sworn to before me this 12"day of October,2022.
Ca0.
Notary Public
CATHRYN M.DEBAKER
NOTARY PUBLIC
MINNESOTA
My Commission Expires Jan.31,2027
CENTURY LINK ELIZABETH D WRIGHT TNG INVESTMENT COMPANY
ATTN PROPERTY TAX DEPT PETER HESSE 2710 OLDE WOOD CT
1025 ELDORADO BLVD 10 12TH AVE N WAYZATA MN 55391
BROOMFIELD CO 80021 HOPKINS MN 55343
BRIAN &KATHERINE E MILLER MATT D HOSCHMILLER MICHELLE WALLIN
10 15TH AVE N MARTHA E HOSCHMILLER MATTHEW GUSTAFSON
HOPKINS MN 55343 10115TH AVE N 102 14TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343
TONY L ZAKARIASEN DEAN &VALERIE J SOLYNTJES JUDITH A PAKENHAM
102 15TH AVE N 105 15TH AVE N 106 15TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
JESSICA GREEN 16TH AVENUE HOLDINGS LLC THEODORE J BAUER
109 15TH AVE N 3100 DARTMOUTH DR SARAH FAMES
HOPKINS MN 55343 EXCELSIOR MN 55331 110 14TH AVE N
HOPKINS MN 55343
JOHN W QUINN KIM &MIKE URAHN STEPHEN H ESH
110 15TH AVE N 114 15TH AVE N 114-14TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
CRAIG M IHRY &AMANDA R IHRY
115 15TH AVE N
HOPKINS MN 55343
WESTGATE 15750 VENTURE LLC
15750 VENTURE LA
EDEN PRAIRIE MN 55344
PETER-JIM S REYNOLDS
124 14TH AVE N
HOPKINS MN 55343
WILLIAM C FREIBERG
122 14TH AVE N
HOPKINS MN 55343
WILLIAM C FREIBERG
122 14TH AVE N
HOPKINS MN 55343
VIRGINIA M MILLER
125-15TH AVE NO
HOPKINS MN 55343
SHANE REYNOLDS
118 15TH AVE N
HOPKINS MN 55343
TERESA J GOETHEL
122 15TH AVE N
HOPKINS MN 55343
PAMELA S PARISH
126 15TH AVE N
HOPKINS MN 55343
KEVIN WOLTER &AMY WOLTER MITCH A &MYKEN EDWARDS AXEL KORNFUEHRER
129 15TH AVE N 13 15TH AVE N GEORGIANNE A KORNFUEHRER
HOPKINS MN 55343 HOPKINS MN 55343 130 15TH AVE N
HOPKINS MN 55343
MAXWELL GOODMANSON SHARON A HORGDAL GREGORY BIRGY
133 15TH AVE N 134 14TH AVE N MICHELE BIRGY
HOPKINS MN 55343 HOPKINS MN 55343 134 15TH AVE N
HOPKINS MN 55343
JOAN N MARKHAM
137 15TH AVE N
HOPKINS MN 55343
STEVEN G BAIEL
1412TH AVE N
HOPKINS MN 55343
ZOE LISTON
138 14TH AVE N
HOPKINS MN 55343
JEFF R CARRIVEAU
1414TH AVE N
HOPKINS MN 55343
JOHN O'NEILL
138 15TH AVE N
HOPKINS MN 55343
MARK A &BETTY J PETERSON
14 15TH AVE N
HOPKINS MN 55343
NEAL HULTSTRAND PREMIUM MIDWEST PROPS LLC MICHAEL HOCHMAN
WHITNEY HULTSTRAND 1361 ROMEO CT ELIZABETH HOCHMAN
14 16TH AVE N CHASKA MN 55318 1412 3RD ST N
HOPKINS MN 55343 HOPKINS MN 55343
SONIA KEENEY KATHLEEN &ROBERT DOUGLASS ZELLER ASSETS LLC
142 14TH AVE N 142 15TH AVE N 1762 WOODSTONE DR
HOPKINS MN 55343 HOPKINS MN 55343 VICTORIA MN 55386
GERALD J TECHAM
145 15TH AVE NO
HOPKINS MN 55343
CAROLINE S KEMPFERT
146 14TH AVE NO
HOPKINS MN 55343
M ZIEGLER &V ZIEGLER
146 15TH AVE N
HOPKINS MN 55343
JEFFREYS KINNEY SUSAN M GALLUCCI HAN-SAN &MING-TZU LEE
1505 MAINSTREET 1521 MAINSTREET C/O JASMINE GARDEN RESTAURAN
HOPKINS MN 55343 HOPKINS MN 55343 161 MAINSTREET
HOPKINS MN 55343
PAUL &NANCY JOHNSEN 16TH AVENUE HOLDINGS LLC TIMOTHY J BUCKLEY
17 15TH AVE N 3100 DARTMOUTH DR SUSAN FAY LUNQUIST BUCKLEY
HOPKINS MN 55343 EXCELSIOR MN 55331 1812TH AVE N
HOPKINS MN 55343
JEAN M RYAN DONALD D NELSON CHRISTOPHER A HAZUKA
18 14TH AVE N 18 15TH AVE N 18 16TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
CHARLES W NEWCOMB THOMAS C HAGMANN MARLENE J STRACHOTA
20115TH AVE N LEZLIE E JOHNSON-HAGMANN 202 14TH AVE N
HOPKINS MN 55343 201 16TH AVE N HOPKINS MN 55343
HOPKINS MN 55343
ALLISON KATE JENNESS ISAAC ROVNER BRODY CHIRPICH
ANTHONY MILLER LASHAY THOMPSON 206 16TH AVE N
202 16TH AVE N 205 16TH AVE N HOPKINS MN 55343
HOPKINS MN 55343 HOPKINS MN 55343
MARTHA J KRAWCZAK DANIEL K LENZ KELLYE AHRENS
RICHARD A STEIN ARIEL J KLUGMAN LENZ 209 16TH AVE N
208 14TH AVE N 209 15TH AVE N HOPKINS MN 55343
HOPKINS MN 55343 HOPKINS MN 55343
ROBERT M LEGRAND THOMAS &PAMELA SCHULZ MARIA MANSOUR
BARBARA L LEGRAND 2115TH AVE N 2116TH AVE N
2112TH AVE N HOPKINS MN 55343 HOPKINS MN 55343
HOPKINS MN 55343
KELLY BRAY KEVIN M DAVIS KRISTIN ROBERTSON NEMEC
210 16TH AVE N 213 16TH AVE N 214 14TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
SARAH HAVLIK C R &S E JOHNSON MICHAELS DECOSSE
214 16TH AVE N 217 15TH AVE N PATRICIA DECOSSE
HOPKINS MN 55343 HOPKINS MN 55343 217 16TH AVE N
HOPKINS MN 55343
WILLIAM R STEINKE JESSICA A KLUGMAN AUSTIN HATCH &HANNAH HATCH
218 16TH AVE N 219 15TH AVE N 22 14TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
BRUCE H &MARY T BAUER
22-15TH AVE NO
HOPKINS MN 55343
DALE L BRAKEMEIER
5080 HOLIDAY RD
MINNETONKA MN 55345
DOUGLASS &SANDRA G ORTIZ
22116TH AVE N
HOPKINS MN 55343
MARY KAY BROKAW MARY ANN &ROBERT FOLSTAD ALEXANDER W MARQUARDT
222 14TH AVE N 222 16TH AVE N ABBEY E MARQUARDT
HOPKINS MN 55343 HOPKINS MN 55343 225 15TH AVE N
HOPKINS MN 55343
JOAN M STATELY DENNIS E DORE/BARBARA B DORE RONALD J FRERICKS
225 16TH AVE N 226 14TH AVE N 226-16TH AVE NO
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
ROGER W MILLER TONY &KRISTIN MILLER DHS HOLDINGS LLC
BARBARA A MILLER 413118TH AVES 5156 W 95TH ST
229-16TH AVE N MINNEAPOLIS MN 55407 BLOOMINGTON MN 55437
HOPKINS MN 55343
MARK HUIBREGTSE ADAM TSTROM STACEY JEANNE TUPPER
233 15TH AVE N 233 16TH AVE N 234 16TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343 HOPKINS MN 55343
KELLY O'BRIEN DUFOUR
DANIEL JOHN FLEISSNER
236 14TH AVE N
HOPKINS MN 55343
RUTH M MICHL
242 16TH AVE N
HOPKINS MN 55343
JAMES G LEHAN
238 16TH AV N
HOPKINS MN 55343
MICHAELE &JOAN M OPITZ
245 16TH AVE N
HOPKINS MN 55343
ARCHIE SKALBECK
24116TH AVE N
HOPKINS MN 55343
SCOTT A WOLF
246 14TH AVE N
HOPKINS MN 55343
PLAZA HOLDINGS LLC ADAM J MINTER KYLE W BRESIN
9617 OAK RIDGE TR CHRISTINE H TAN ELYSSA B MC INTYRE
MINNETONKA MN 55305 25 12TH AVE N 25 15TH AVE N
HOPKINS MN 55343 HOPKINS MN 55343
PETER B HIRSCH ERIKS HAGENESS DECHEN WANGMO
25 16TH AVE N EMILY A HAGENESS 26 15TH AVE N
HOPKINS MN 55343 26 14TH AVE N HOPKINS MN 55343
HOPKINS MN 55343
LYNN M HARRIS COMMUNITY HSG DEVEL CORP THOMAS B PROUT
26 16TH AVE N C/O MASTER COMM GROUP 29 12TH AVE N
HOPKINS MN 55343 614 1ST ST N SUITE 100 HOPKINS MN 55343
MINNEAPOLIS MN 55401
LAURAL WOOD ANTHONY M POHLEN SHARON EVANS
DOUGLAS ALEXANDER WEIHER ESTHER Q VAN STAM 30 14TH AVE N
29 15TH AVE N 29 16TH AVE N HOPKINS MN 55343
HOPKINS MN 55343 HOPKINS MN 55343
TINA ZELINKA GREGORY J GOZOLA MARK L &KATHRYN M HUCKA
30 15TH AVE N CINDY A GOZOLA 33 12TH AVE N
HOPKINS MN 55343 30 16TH AVE N HOPKINS MN 55343
HOPKINS MN 55343
LOREN W BROWN MATTHEW C KILANOWSKI GOLDCREST LLC
2710 OLDE WOOD CT 33 16TH AVE N 1137 CEDAR VIEW DR
WAYZATA MN 55391 HOPKINS MN 55343 MINNEAPOLIS MN 55405
MICHAEL HIGGINS/BETH HIGGINS
3088 GABLER AVE SE
BUFFALO MN 55313
SUSAN GONYEA
37 12TH AVE N
HOPKINS MN 55343
DAVID G PRCHAL
3415TH AVE N
HOPKINS MN 55343
ABBY G WOLF &CULLEN J PRICE
37 15TH AVE N
HOPKINS MN 55343
J C FAHLSTROM &TD LAMA
3416TH AVE N
HOPKINS MN 55343
MARY A REITTER
37 16TH AVE N
HOPKINS MN 55343
KELLY A KEMPF
38 14TH AVE N
HOPKINS MN 55343
SUMBA PROPERTIES LLC
37 12TH AVE N
HOPKINS MN 55343
J ERICKSON &B LOESCHKE
38 15TH AVE N
HOPKINS MN 55343
CHERYL K.NEWSTOM
4116TH AVE N
HOPKINS MN 55343
DENISE A ANDERSON
3816TH AVE N
HOPKINS MN 55343
BRIANNA ROONEY
42 14TH AVE N
HOPKINS MN 55343
MARK J WEAVER RANDY W CHINN KEVIN W THOMAS
CHUENCHOM SUPUNNIAM NAOMI J CHINN 45 15TH AVE N
42 15TH AVE N 42 16TH AVE N HOPKINS MN 55343
HOPKINS MN 55343 HOPKINS MN 55343
CPY PROPERTIES II LLC CATHERINE ORN TNG INVESTMENT COMPANY
16506 LIMERICK LANE 46 16TH AVE N 2710 OLDE WOOD CT
MINNETONKA MN 55345 HOPKINS MN 55343 WAYZATA MN 55391
-Public Notice Ad Proof-
Ad ID: 1265505
Copy LIne: Nov 1 PH 2023 St & Utility Imp
PO Number:
Start: 10/20/22
Stop: 10/27/2022
Total Cost: $320.00
# of Lines: 36
Total Depth: 4.1
# of Inserts: 2
Ad Class: 150
Phone # (763) 691-6000
Email: publicnotice@apgecm.com
Rep No: SE700
Date: 10/12/22
Account #: 412490
Customer: CITY OF HOPKINS ~
Address: 1010 1ST ST S
HOPKINS
Telephone: (952) 935-8474
Fax: (952) 935-1834
This is the proof of your ad scheduled to run on the dates
indicated below. Please proof read carefully. If changes are needed,
please contact us prior to deadline at
Cambridge (763) 691-6000 or email at publicnotice@apgecm.com
Publications:
SS St Louis Park_Hopkins
Ad Proof
Not Actual Size
CITY OF HOPKINS 2023 STREET AND UTILITY IMPROVEMENTS PUBLIC HEARING
TO WHOM IT MAY CONCERN:
Notice is hereby given that the City Council will hold the Public Hearing in the Council Chambers of City
Hall, 1010 1st St S, at 6:30 p.m. on Tuesday, November 1st, 2022, to consider the making of improvements on:
12th Avenue North from Mainstreet to 1st Street North; 14th Avenue North from Mainstreet to 2nd Street
North; 15th Avenue North from Mainstreet to 2nd Street North; 16th Avenue North from Mainstreet to 1st
Street North and from 2nd Street North to 3rd Street North; and 2nd Street North from 14th Avenue North
to 15th Avenue North.
Generally, the project involves the addition/replacement of storm sewer; water main replacement; water ser-
vice replacement; sanitary sewer replacement and rehabilitation; sanitary sewer service replacement; concrete
curb & gutter addition/replacement; bituminous street removal and reconstruction; and turf restoration; pursu-
ant to Minn. Statutes, Section 429.011 to 429.111. The area proposed to be assessed for such improvement
includes all properties located along the streets listed above and as shown below.
Plat Name Sec Twp Rng Q/Q
West Minneapolis 2nd Division 24 117 22 NE/SW
Stein Addn 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 SW/NW
The estimated cost of the improvement is $8,855,000. A reasonable estimate of the impact of the assess-
ment will be available at the hearing. Such persons as desire to be heard with reference to the proposed
improvement will be heard at this meeting.
Amy Domeier, City Clerk
952-548-6304
Published in the
Sun Sailor
October 20, 27, 2022
1265505
Not Actual Size
Ad: 1
$320.00
CITY OF HOPKINS 2023 STREET AND UTILITY IMPROVEMENTS PUBLIC HEARING
TO WHOM IT MAY CONCERN:
Notice is hereby given that the City Council will hold the Public Hearing in the Council Chambers of City
Hall, 1010 1st St S, at 6:30 p.m. on Tuesday, November 1st, 2022, to consider the making of improvements on:
12th Avenue North from Mainstreet to 1st Street North; 14th Avenue North from Mainstreet to 2nd Street
North; 15th Avenue North from Mainstreet to 2nd Street North; 16th Avenue North from Mainstreet to 1st
Street North and from 2nd Street North to 3rd Street North; and 2nd Street North from 14th Avenue North
to 15th Avenue North.
Generally, the project involves the addition/replacement of storm sewer; water main replacement; water ser-
vice replacement; sanitary sewer replacement and rehabilitation; sanitary sewer service replacement; concrete
curb & gutter addition/replacement; bituminous street removal and reconstruction; and turf restoration; pursu-
ant to Minn. Statutes, Section 429.011 to 429.111. The area proposed to be assessed for such improvement
includes all properties located along the streets listed above and as shown below.
Plat Name Sec Twp Rng Q/Q
West Minneapolis 2nd Division 24 117 22 NE/SW
Stein Addn 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 NW/SW
Gibbs 1st Addn to West Mpls 24 117 22 SW/NW
The estimated cost of the improvement is $8,855,000. A reasonable estimate of the impact of the assess-
ment will be available at the hearing. Such persons as desire to be heard with reference to the proposed
improvement will be heard at this meeting.
Amy Domeier, City Clerk
952-548-6304
Published in the
Sun Sailor
October 20, 27, 2022
1265505
PRELIMINARY ASSESSMENT ROLL
2023 STREET & UTILITY IMPROVEMENTS
CITY OF HOPKINS, MN
CITY PROJECT NO. 2022-010
BMI PROJECT NO. 0T1.127595
PID PROPERTY ADDRESS TAXPAYER NAME TAXPAYER ADDRESS (LINE 1)TAXPAYER ADDRESS (LINE 2)TAXPAYER ADDRESS (LINE 3)
PROPOSED STREET
ASSESSMENT
PROPOSED WATER
SERVICE ASSESSMENT
PROPOSED SEWER
SERVICE ASSESSMENT
TOTAL PROPOSED
ASSESSMENT
2411722310148 10 11TH AVENUE NORTH CENTURY LINK ATTN PROPERTY TAX DEPT 1025 ELDORADO BLVD BROOMFIELD CO 80021 -$-$2,850.00$2,850.00$
2411722310058 10 12TH AVENUE NORTH ELIZABETH D WRIGHT PETER HESSE 10 12TH AVE N HOPKINS MN 55343 5,018.54$1,575.00$1,325.00$7,918.54$
2411722310057 14 12TH AVENUE NORTH STEVEN G BAIEL 14 12TH AVE N HOPKINS MN 55343 5,667.75$1,575.00$1,325.00$8,567.75$
2411722310056 18 12TH AVENUE NORTH TIMOTHY J BUCKLEY SUSAN FAY LUNQUIST BUCKLEY 18 12TH AVE N HOPKINS MN 55343 4,637.25$1,575.00$1,325.00$7,537.25$
2411722310049 21 12TH AVENUE NORTH ROBERT M LEGRAND BARBARA L LEGRAND 21 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722310050 25 12TH AVENUE NORTH ADAM J MINTER CHRISTINE H TAN 25 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722310051 29 12TH AVENUE NORTH THOMAS B PROUT 29 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722310052 33 12TH AVENUE NORTH MARK L & KATHRYN M HUCKA 33 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722310055 34 12TH AVENUE NORTH GOLDCREST LLC 1137 CEDAR VIEW DR MINNEAPOLIS MN 55405 41,800.00$6,190.00$11,450.00$59,440.00$
2411722310053 37 12TH AVENUE NORTH SUSAN GONYEA 37 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722310054 41 12TH AVENUE NORTH SUMBA PROPERTIES LLC 37 12TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320096 10 14TH AVENUE NORTH TNG INVESTMENT COMPANY 2710 OLDE WOOD CT WAYZATA MN 55391 6,384.98$1,575.00$1,325.00$9,284.98$
2411722320095 14 14TH AVENUE NORTH JEFF R CARRIVEAU 14 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320094 18 14TH AVENUE NORTH JEAN M RYAN 18 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320093 22 14TH AVENUE NORTH AUSTIN HATCH & HANNAH HATCH 22 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320092 26 14TH AVENUE NORTH ERIK S HAGENESS EMILY A HAGENESS 26 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320138 27 14TH AVENUE NORTH COMMUNITY HSG DEVEL CORP C/O MASTER COMM GROUP 614 1ST ST N SUITE 100 MINNEAPOLIS MN 55401 73,500.00$-$3,000.00$76,500.00$
2411722320091 30 14TH AVENUE NORTH SHARON EVANS 30 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320090 34 14TH AVENUE NORTH MICHAEL HIGGINS/BETH HIGGINS 3088 GABLER AVE SE BUFFALO MN 55313 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320089 38 14TH AVENUE NORTH KELLY A KEMPF 38 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320088 42 14TH AVENUE NORTH BRIANNA ROONEY 42 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320120 102 14TH AVENUE NORTH MICHELLE WALLIN MATTHEW GUSTAFSON 102 14TH AVE N HOPKINS MN 55343 10,305.00$1,575.00$1,325.00$13,205.00$
2411722320119 110 14TH AVENUE NORTH THEODORE J BAUER SARAH F AMES 110 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320118 114 14TH AVENUE NORTH STEPHEN H ESH 114-14TH AVE NO HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320117 118 14TH AVENUE NORTH WILLIAM C FREIBERG 122 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320116 122 14TH AVENUE NORTH WILLIAM C FREIBERG 122 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320115 124 14TH AVENUE NORTH PETER-JIM S REYNOLDS 124 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320114 134 14TH AVENUE NORTH SHARON A HORGDAL 134 14TH AVE N HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320113 138 14TH AVENUE NORTH ZOE LISTON 138 14TH AVE N HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320112 142 14TH AVENUE NORTH SONIA KEENEY 142 14TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320111 146 14TH AVENUE NORTH CAROLINE S KEMPFERT 146 14TH AVE NO HOPKINS MN 55343 5,636.84$1,575.00$1,325.00$8,536.84$
2411722230092 202 14TH AVENUE NORTH MARLENE J STRACHOTA 202 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230157 208 14TH AVENUE NORTH MARTHA J KRAWCZAK RICHARD A STEIN 208 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230090 214 14TH AVENUE NORTH KRISTIN ROBERTSON NEMEC 214 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230089 222 14TH AVENUE NORTH MARY KAY BROKAW 222 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230088 226 14TH AVENUE NORTH DENNIS E DORE/BARBARA B DORE 226 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230153 236 14TH AVENUE NORTH KELLY O'BRIEN DUFOUR DANIEL JOHN FLEISSNER 236 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230152 246 14TH AVENUE NORTH SCOTT A WOLF 246 14TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722320102 9 15TH AVENUE NORTH TNG INVESTMENT COMPANY 2710 OLDE WOOD CT WAYZATA MN 55391 6,928.05$1,575.00$1,325.00$9,828.05$
2411722320073 10 15TH AVENUE NORTH BRIAN & KATHERINE E MILLER 10 15TH AVE N HOPKINS MN 55343 7,272.24$1,575.00$1,325.00$10,172.24$
2411722320103 13 15TH AVENUE NORTH MITCH A & MYKEN EDWARDS 13 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320072 14 15TH AVENUE NORTH MARK A & BETTY J PETERSON 14 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320104 17 15TH AVENUE NORTH PAUL & NANCY JOHNSEN 17 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320071 18 15TH AVENUE NORTH DONALD D NELSON 18 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320105 21 15TH AVENUE NORTH THOMAS & PAMELA SCHULZ 21 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320070 22 15TH AVENUE NORTH BRUCE H & MARY T BAUER 22-15TH AVE NO HOPKINS MN 55343 5,564.70$1,575.00$1,325.00$8,464.70$
2411722320106 25 15TH AVENUE NORTH KYLE W BRESIN ELYSSA B MC INTYRE 25 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320069 26 15TH AVENUE NORTH DECHEN WANGMO 26 15TH AVE N HOPKINS MN 55343 4,740.30$1,575.00$1,325.00$7,640.30$
2411722320107 29 15TH AVENUE NORTH LAURA L WOOD DOUGLAS ALEXANDER WEIHER 29 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320068 30 15TH AVENUE NORTH TINA ZELINKA 30 15TH AVE N HOPKINS MN 55343 4,122.00$1,575.00$1,325.00$7,022.00$
2411722320108 33 15TH AVENUE NORTH LOREN W BROWN 2710 OLDE WOOD CT WAYZATA MN 55391 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320067 34 15TH AVENUE NORTH DAVID G PRCHAL 34 15TH AVE N HOPKINS MN 55343 6,183.00$1,575.00$1,325.00$9,083.00$
2411722320109 37 15TH AVENUE NORTH ABBY G WOLF & CULLEN J PRICE 37 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
PRELIMINARY ASSESSMENT ROLL
2023 STREET & UTILITY IMPROVEMENTS
CITY OF HOPKINS, MN
CITY PROJECT NO. 2022-010
BMI PROJECT NO. 0T1.127595
PID PROPERTY ADDRESS TAXPAYER NAME TAXPAYER ADDRESS (LINE 1)TAXPAYER ADDRESS (LINE 2)TAXPAYER ADDRESS (LINE 3)
PROPOSED STREET
ASSESSMENT
PROPOSED WATER
SERVICE ASSESSMENT
PROPOSED SEWER
SERVICE ASSESSMENT
TOTAL PROPOSED
ASSESSMENT
2411722320066 38 15TH AVENUE NORTH J ERICKSON & B LOESCHKE 38 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320065 42 15TH AVENUE NORTH MARK J WEAVER CHUENCHOM SUPUNNIAM 42 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320110 45 15TH AVENUE NORTH KEVIN W THOMAS 45 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320121 101 15TH AVENUE NORTH MATT D HOSCHMILLER MARTHA E HOSCHMILLER 101 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320012 102 15TH AVENUE NORTH TONY L ZAKARIASEN 102 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320122 105 15TH AVENUE NORTH DEAN & VALERIE J SOLYNTJES 105 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320011 106 15TH AVENUE NORTH JUDITH A PAKENHAM 106 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320123 109 15TH AVENUE NORTH JESSICA GREEN 109 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320010 110 15TH AVENUE NORTH JOHN W QUINN 110 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320009 114 15TH AVENUE NORTH KIM & MIKE URAHN 114 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320124 115 15TH AVENUE NORTH CRAIG M IHRY & AMANDA R IHRY 115 15TH AVE N HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320008 118 15TH AVENUE NORTH SHANE REYNOLDS 118 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320007 122 15TH AVENUE NORTH TERESA J GOETHEL 122 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320125 125 15TH AVENUE NORTH VIRGINIA M MILLER 125-15TH AVE NO HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320006 126 15TH AVENUE NORTH PAMELA S PARISH 126 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320126 129 15TH AVENUE NORTH KEVIN WOLTER & AMY WOLTER 129 15TH AVE N HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320005 130 15TH AVENUE NORTH AXEL KORNFUEHRER GEORGIANNE A KORNFUEHRER 130 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320127 133 15TH AVENUE NORTH MAXWELL GOODMANSON 133 15TH AVE N HOPKINS MN 55343 7,728.75$1,575.00$1,325.00$10,628.75$
2411722320004 134 15TH AVENUE NORTH GREGORY BIRGY MICHELE BIRGY 134 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320128 137 15TH AVENUE NORTH JOAN N MARKHAM 137 15TH AVE N HOPKINS MN 55343 10,305.00$1,575.00$1,325.00$13,205.00$
2411722320003 138 15TH AVENUE NORTH JOHN O'NEILL 138 15TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320002 142 15TH AVENUE NORTH KATHLEEN & ROBERT DOUGLASS 142 15TH AVE N HOPKINS MN 55343 6,234.53$1,575.00$1,325.00$9,134.53$
2411722320129 145 15TH AVENUE NORTH GERALD J TECHAM 145 15TH AVE NO HOPKINS MN 55343 5,710.00$1,575.00$1,325.00$8,610.00$
2411722320001 146 15TH AVENUE NORTH M ZIEGLER & V ZIEGLER 146 15TH AVE N HOPKINS MN 55343 4,637.25$1,575.00$1,325.00$7,537.25$
2411722230093 201 15TH AVENUE NORTH CHARLES W NEWCOMB 201 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230094 209 15TH AVENUE NORTH DANIEL K LENZ ARIEL J KLUGMAN LENZ 209 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230095 217 15TH AVENUE NORTH C R & S E JOHNSON 217 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230096 219 15TH AVENUE NORTH JESSICA A KLUGMAN 219 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230097 225 15TH AVENUE NORTH ALEXANDER W MARQUARDT ABBEY E MARQUARDT 225 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722230098 231 15TH AVENUE NORTH DHS HOLDINGS LLC 5156 W 95TH ST BLOOMINGTON MN 55437 3,478.99$-$-$3,478.99$
2411722230099 233 15TH AVENUE NORTH MARK HUIBREGTSE 233 15TH AVE N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722320078 11 16TH AVENUE NORTH 16TH AVENUE HOLDINGS LLC 3100 DARTMOUTH DR EXCELSIOR MN 55331 6,633.33$1,575.00$1,325.00$9,533.33$
2411722320052 14 16TH AVENUE NORTH NEAL HULTSTRAND WHITNEY HULTSTRAND 14 16TH AVE N HOPKINS MN 55343 6,923.93$1,575.00$1,325.00$9,823.93$
2411722320079 17 16TH AVENUE NORTH 16TH AVENUE HOLDINGS LLC 3100 DARTMOUTH DR EXCELSIOR MN 55331 6,341.70$1,575.00$1,325.00$9,241.70$
2411722320051 18 16TH AVENUE NORTH CHRISTOPHER A HAZUKA 18 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320080 21 16TH AVENUE NORTH MARIA MANSOUR 21 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320050 22 16TH AVENUE NORTH DALE L BRAKEMEIER 5080 HOLIDAY RD MINNETONKA MN 55345 6,183.00$1,575.00$1,325.00$9,083.00$
2411722320081 25 16TH AVENUE NORTH PETER B HIRSCH 25 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320049 26 16TH AVENUE NORTH LYNN M HARRIS 26 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320082 29 16TH AVENUE NORTH ANTHONY M POHLEN ESTHER Q VAN STAM 29 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320241 30 16TH AVENUE NORTH GREGORY J GOZOLA CINDY A GOZOLA 30 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320083 33 16TH AVENUE NORTH MATTHEW C KILANOWSKI 33 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320240 34 16TH AVENUE NORTH J C FAHLSTROM & T D LAMA 34 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320084 37 16TH AVENUE NORTH MARY A REITTER 37 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320047 38 16TH AVENUE NORTH DENISE A ANDERSON 38 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320085 41 16TH AVENUE NORTH CHERYL K. NEWSTOM 41 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320046 42 16TH AVENUE NORTH RANDY W CHINN NAOMI J CHINN 42 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320086 45 16TH AVENUE NORTH CPY PROPERTIES II LLC 16506 LIMERICK LANE MINNETONKA MN 55345 5,152.50$1,575.00$1,325.00$8,052.50$
2411722320045 46 16TH AVENUE NORTH CATHERINE ORN 46 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230065 201 16TH AVENUE NORTH THOMAS C HAGMANN LEZLIE E JOHNSON-HAGMANN 201 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230045 202 16TH AVENUE NORTH ALLISON KATE JENNESS ANTHONY MILLER 202 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230066 205 16TH AVENUE NORTH ISAAC ROVNER LASHAY THOMPSON 205 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230044 206 16TH AVENUE NORTH BRODY CHIRPICH 206 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
PRELIMINARY ASSESSMENT ROLL
2023 STREET & UTILITY IMPROVEMENTS
CITY OF HOPKINS, MN
CITY PROJECT NO. 2022-010
BMI PROJECT NO. 0T1.127595
PID PROPERTY ADDRESS TAXPAYER NAME TAXPAYER ADDRESS (LINE 1)TAXPAYER ADDRESS (LINE 2)TAXPAYER ADDRESS (LINE 3)
PROPOSED STREET
ASSESSMENT
PROPOSED WATER
SERVICE ASSESSMENT
PROPOSED SEWER
SERVICE ASSESSMENT
TOTAL PROPOSED
ASSESSMENT
2411722230067 209 16TH AVENUE NORTH KELLY E AHRENS 209 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230043 210 16TH AVENUE NORTH KELLY BRAY 210 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230068 213 16TH AVENUE NORTH KEVIN M DAVIS 213 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230042 214 16TH AVENUE NORTH SARAH HAVLIK 214 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230069 217 16TH AVENUE NORTH MICHAEL S DECOSSE PATRICIA DECOSSE 217 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230041 218 16TH AVENUE NORTH WILLIAM R STEINKE 218 16TH AVE N HOPKINS MN 55343 5,152.50$1,575.00$1,325.00$8,052.50$
2411722230070 221 16TH AVENUE NORTH DOUGLAS S & SANDRA G ORTIZ 221 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230040 222 16TH AVENUE NORTH MARY ANN & ROBERT FOLSTAD 222 16TH AVE N HOPKINS MN 55343 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230071 225 16TH AVENUE NORTH JOAN M STATELY 225 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230039 226 16TH AVENUE NORTH RONALD J FRERICKS 226-16TH AVE NO HOPKINS MN 55343 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230072 229 16TH AVENUE NORTH ROGER W MILLER BARBARA A MILLER 229 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230038 230 16TH AVENUE NORTH TONY & KRISTIN MILLER 4131 18TH AVE S MINNEAPOLIS MN 55407 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230073 233 16TH AVENUE NORTH ADAM T STROM 233 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230037 234 16TH AVENUE NORTH STACEY JEANNE TUPPER 234 16TH AVE N HOPKINS MN 55343 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230036 238 16TH AVENUE NORTH JAMES G LEHAN 238 16TH AV N HOPKINS MN 55343 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230074 241 16TH AVENUE NORTH ARCHIE SKALBECK 241 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230035 242 16TH AVENUE NORTH RUTH M MICHL 242 16TH AVE N HOPKINS MN 55343 4,843.35$1,575.00$1,325.00$7,743.35$
2411722230075 245 16TH AVENUE NORTH MICHAEL E & JOAN M OPITZ 245 16TH AVE N HOPKINS MN 55343 5,461.65$1,575.00$1,325.00$8,361.65$
2411722230034 246 16TH AVENUE NORTH PLAZA HOLDINGS LLC 9617 OAK RIDGE TR MINNETONKA MN 55305 4,933.00$1,575.00$1,325.00$7,833.00$
2411722230154 1412 3RD STREET NORTH MICHAEL HOCHMAN ELIZABETH HOCHMAN 1412 3RD ST N HOPKINS MN 55343 3,478.99$-$-$3,478.99$
2411722310059 1201 MAINSTREET WESTGATE 15750 VENTURE LLC 15750 VENTURE LA EDEN PRAIRIE MN 55344 7,700.00$-$-$7,700.00$
2411722320097 1401 MAINSTREET PREMIUM MIDWEST PROPS LLC 1361 ROMEO CT CHASKA MN 55318 5,900.00$4,810.00$5,750.00$16,460.00$
2411722320101 1421 MAINSTREET ZELLER ASSETS LLC 1762 WOODSTONE DR VICTORIA MN 55386 7,700.00$5,570.00$2,800.00$16,070.00$
2411722320074 1505 MAINSTREET JEFFREY S KINNEY 1505 MAINSTREET HOPKINS MN 55343 8,200.00$5,890.00$2,800.00$16,890.00$
2411722320077 1521 MAINSTREET SUSAN M GALLUCCI 1521 MAINSTREET HOPKINS MN 55343 6,100.00$4,750.00$2,700.00$13,550.00$
2411722320053 1601 MAINSTREET HAN-SAN & MING-TZU LEE C/O JASMINE GARDEN RESTAURAN1601 MAINSTREET HOPKINS MN 55343 5,400.00$6,010.00$2,750.00$14,160.00$
PRELIMINARY TOTAL AMOUNT TO BE ASSESSED 1,184,328.82$
N:\Proposals\Hopkins\Hopkins 2023 Street & Utility Improvements\Final Design and Construction\Klingbeil 101822.docx
October 18, 2022
Mr. Eric Klingbeil, P.E., City Engineer
City of Hopkins
1010 1st St S
Hopkins, MN 55343
Re: Proposal for Professional Engineering and Surveying Services
2023 Street and Utility Improvements – Final Design & Construction Services
City of Hopkins, Minnesota
Dear Mr. Klingbeil:
We are pleased to offer you our proposal for professional engineering and surveying services for the final design
and construction phases of the City of Hopkins’ 2023 Street and Utility Improvements. This proposal is based on
the preliminary engineering report prepared as part of the feasibility phase of the project and has been prepared in
the form of our standard agreement, consistent with past projects. Our proposed efforts include all remaining
engineering efforts on the project, totaling $845,420 for 6,120 proposed labor hours. The enclosed Detailed Work
Plan and Estimate of Project Fees further detail our proposed level of effort.
In addition to the enclosed standard agreement, Exhibit I details our proposed process and scope of work to be
performed. The schedule presented in Exhibit I illustrates a streamlined schedule, for council meetings, consistent
with the approach followed in years past for assessment projects. The proposed project schedule is intended to meet
the City’s desire to have a bid opening in February and contract award in March. Upon authorization by the Council
on November 1st, we will proceed with final design of the improvements immediately to meet all required deadlines.
As always, thank you for allowing Bolton & Menk, Inc. to submit this proposal for your consideration. Upon your
review and approval of this agreement, please sign and return one copy to our office. If you have any questions
regarding this proposal or would like to discuss any of its details, please do not hesitate to call me. We truly
appreciate and value our continued working relationship with the City of Hopkins.
Sincerely,
Bolton & Menk, Inc.
Nicholas J. Amatuccio, P.E. Michael J. Waltman, P.E.
Associate Project Manager Principal Engineer
Burnsville Office Manager
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 1 of 9
AGREEMENT FOR PROFESSIONAL SERVICES
2023 STREET & UTILITY IMPROVEMENTS
FINAL DESIGN & CONSTRUCTION PHASE ENGINEERING SERVICES
CITY OF HOPKINS, MINNESOTA
This Agreement, made this 1st day of November 2022, by and between CITY OF HOPKINS, 1010 1st St
S, Hopkins, MN 55343, hereinafter referred to as CLIENT, and BOLTON & MENK, INC., 12224
Nicollet Avenue, Burnsville, MN 55337, hereinafter referred to as CONSULTANT.
WITNESS, whereas the CLIENT requires professional services in conjunction with the 2023 STREET &
UTILITY IMPROVEMENTS and whereas the CONSULTANT agrees to furnish the various professional
services required by the CLIENT.
NOW, THEREFORE, in consideration of the mutual covenants and promises between the parties hereto,
it is agreed:
SECTION I - CONSULTANT'S SERVICES
A. The CONSULTANT agrees to perform the various Basic Services in connection with the proposed
project as described in Exhibit I.
B. Upon mutual agreement of the parties hereto, Additional Services may be authorized as described
in Exhibit I or as described in Paragraph IV.B.
SECTION II - THE CLIENT'S RESPONSIBILITIES
A. The CLIENT shall promptly compensate the CONSULTANT in accordance with Section III of this
Agreement.
B. The CLIENT shall place any and all information related to the project in its custody at the disposal
of the CONSULTANT for its use. Such information shall include but shall not be limited boundary
surveys, topographic surveys, preliminary sketch plan layouts, building plans, soil surveys,
abstracts, deed descriptions, tile maps and layouts, aerial photos, utility agreements, environmental
reviews, and zoning limitations. The CONSULTANT may rely upon the accuracy and sufficiency
of all such information in performing services unless otherwise instructed, in writing, by CLIENT.
This obligation shall not include information that is classified as private or confidential under the
Minnesota Government Data Practices Act (MGDPA), unless access to such information is
essential to the CONSULTANT’s scope of services, in which case the CLIENT shall establish in
writing, and CONSULTANT shall comply with, any conditions governing access to and use of
such private or confidential information.
C. The CLIENT will guarantee access to and make all provisions for entry upon both public and
private portions of the project and pertinent adjoining properties.
D. The CLIENT will give prompt notice to the CONSULTANT whenever the CLIENT observes or
otherwise becomes aware of any defect in the proposed project.
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 2 of 9
E. The CLIENT shall designate a liaison person to act as the CLIENT'S representative with respect to
services to be rendered under this Agreement. Said representative shall have the authority to
transmit instructions, receive instructions, receive information, interpret and define the CLIENT'S
policies with respect to the project and CONSULTANT'S services.
F. The CLIENT shall provide such legal, accounting, independent cost estimating and insurance
counseling services as may be required for completion of the consultant services described in this
agreement.
G. The CLIENT will obtain any and all regulatory permits required for the proper and legal execution
of the project.
H. The CLIENT will hire, when requested by the CONSULTANT, an independent test company to
perform laboratory and material testing services, and soil investigation that can be justified for the
proper design and construction of the project. The CONSULTANT shall assist the CLIENT in
selecting a testing company. Payment for testing services shall be made directly to the testing
company by the CLIENT and is not part of this Agreement.
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 3 of 9
SECTION III - COMPENSATION FOR SERVICES
A. FEES.
1. The CLIENT will compensate the CONSULTANT in accordance with the following schedule
of fees for the time spent in performance of Agreement services.
Schedule of Fees
Classification Hourly Rates
Sr. Project Manager – Sr. Principal Engineer/Surveyor $155-280/Hour
Sr. Project Manager – Principal Engineer/Surveyor $165-225/Hour
Project Manager $145-195/Hour
Project/Design Engineer /Planner/Surveyor/Landscape Architect $130-195/Hour
Specialist (Nat. Resources; GIS; Traffic; Other) $105-165/Hour
Senior Technician (Inc. Survey1) $125-185/Hour
Technician (Inc. Survey1) $105-160/Hour
Administrative/Corporate Specialists $90-125/Hour
Structural/Electrical/Mechanical/Architect $120-$180/Hour
GPS/Robotic Survey Equipment No Charge
CAD/Computer Usage No Charge
Routine Photo Copying/Reproduction No Charge
Routine Office Supplies No Charge
Field Supplies/Survey Stakes & Equipment No Charge
Mileage No Charge
1No separate charges will be made for GPS or robotic total stations on Bolton & Menk, Inc. survey assignments; the
cost of this equipment is included in the rates for Survey Technicians.
2. Total cost for the services itemized under Exhibit I, Section A (Basic Services) is estimated to
be $845,420. Itemization of this cost is as shown in the attached DETAILED WORK PLAN
and PROJECT FEES tables, attached hereto as Exhibit II.
3. In addition to the foregoing, CONSULTANT shall be reimbursed at cost plus an overhead fee
(not-to-exceed 10%) for the following Direct Expenses when incurred in the performance of the
work.
a. CLIENT approved outside (facilities not owned by CONSULTANT) computer services.
b. CLIENT approved outside professional and technical services.
c. Outside reproduction and reprographic charges.
d. Expendable field supplies and special field equipment rental.
e. Other costs for such additional items and services that the CLIENT may require the
CONSULTANT to provide to fulfill the terms of this Agreement.
4. Additional services as outlined in Section I.B will vary depending upon project conditions and
will be billed on an hourly basis at the rate described in Section III.A.1.
5. The payment to the CONSULTANT will be made by the CLIENT upon billing at intervals not
more often than monthly at the herein rates. Itemized invoices identifying all work completed
shall be submitted to the CLIENT by CONSULTANT and paid in the same manner as other
claims made to the CLIENT.
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 4 of 9
SECTION IV - GENERAL
A. STANDARD OF CARE
Professional services provided under this Agreement will be conducted in a manner consistent with
that level of care and skill ordinarily exercised by members of the Consultant's profession currently
practicing under similar conditions. No warranty, express or implied, is made.
B. CHANGE IN PROJECT SCOPE
In the event the CLIENT changes or is required to change the scope of the project from that
described in Section I and/or the applicable addendum, and such changes require Additional
Services by the CONSULTANT, the CONSULTANT shall be entitled to additional compensation
at the applicable hourly rates. The CONSULTANT shall give notice to the CLIENT of any
Additional Services, prior to furnishing such additional services and the CLIENT must approve an
Additional Services in writing. The CLIENT may request an estimate of additional cost from the
CONSULTANT, and upon receipt of the request, the CONSULTANT shall furnish such, prior to
authorization of the changed scope of work.
C. INDEPENDENT CONTRACTOR
The CONSULTANT shall at times be deemed an independent contractor. The CONSULTANT is
not to be deemed an employee or agent of the CLIENT and has no authority to make any binding
commitments or obligations on behalf of the CLIENT except to the extent expressly provided
herein. All services provided by the CONSUTANT pursuant to this agreement shall be provide on
an independent contractor basis not as an employee of the CLIENT for any purpose including, but
not limited to, income tax withholding, workers’ compensation, unemployment compensation,
FICA taxes, liability for torts, and eligibility for employee benefits.
D. LIMITATION OF LIABILITY
CONSULTANT shall indemnify, defend, and hold harmless CLIENT and its officials, agents and
employees from any loss, claim, liability, and expense (including reasonable attorneys’ fees and
expenses of litigation) arising from, or based in the whole, or in any part, on any negligent act or
omission by CONSULTANT’S employees, agents, or subconsultants. In no event shall CLIENT
be liable to CONSULTANT for consequential, incidental, indirect, special, or punitive damages.
CLIENT shall indemnify, defend, and hold harmless CONSULTANT and its employees from any
loss, claim, liability, and expense (including reasonable attorneys’ fees and expenses of litigation)
arising from, or based in the whole, or in any part, on any negligent act or omission by CLIENT’S
employees, agents, or consultants. In no event shall CONSULTANT be liable to CLIENT for
consequential, incidental, indirect, special, or punitive damages.
Nothing contained in this Agreement shall be construed as a limitation on or waiver of any
immunities or limitations on liability otherwise available to the CLIENT. Nothing contained in this
Agreement shall create a contractual relationship with or a cause of action in favor of a third party
against either the CLIENT or the CONSULTANT. The CONSULTANT'S services under this
Agreement are being performed solely for the CLIENT'S benefit, and no other entity shall have any
claim against the CONSULTANT because of this Agreement or the performance or
nonperformance of services provided hereunder. The CLIENT agrees to include a provision in all
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 5 of 9
contracts with contractors and other entities involved in this project to carry out the intent of the
paragraph.
E. INSURANCE
1. The CONSULTANT agrees to maintain, at CONSULTANT’S expense a commercial general
liability and excess umbrella general liability insurance policy or policies insuring CONSULTANT
against claims for bodily injury, death or property damage arising out of CONSULTANT’S general
business activities. The general liability coverage shall provide limits of not less than $2,000,000
per occurrence and not less than $2,000,000 general aggregate. Coverage shall include Premises
and Operations Bodily Injury and Property Damage; Personal and Advertising Injury; Blanket
Contractual Liability; Products and Completed Operations Liability.
2. The CONSULTANT also agrees to maintain, at CONSULTANT’S expense, a single limit or
combined limit automobile liability insurance and excess umbrella liability policy or policies
insuring owned, non-owned and hired vehicles used by CONSULTANT under this Agreement.
The automobile liability coverages shall provide limits of not less than $1,000,000 per accident for
property damage, $2,000,000 for bodily injuries, death and damages to any one person and
$2,000,000 for total bodily injury, death and damage claims arising from one accident.
3. CLIENT shall be named Additional Insured for the above liability policies.
4. The CONSULTANT agrees to maintain, at the CONSULTANT'S expense, statutory worker's
compensation coverage together with Coverage B, Employer’s Liability limits of not less than
$500,000 for Bodily Injury by Disease per employee, $500,000.00 for Bodily Injury by Disease
aggregate and $500,000 for Bodily Injury by Accident.
5. During the period of design and construction of the project, the CONSULTANT also agrees to
maintain, at CONSULTANT’S expense, Professional Liability Insurance coverage insuring
CONSULTANT against damages for legal liability arising from an error, omission or negligent act
in the performance of professional services required by this agreement. The professional liability
insurance coverage shall provide limits of not less than $2,000,000 per claim and an annual
aggregate of not less than $2,000,000 on a claims-made basis.
6. Prior to commencement of this Agreement, the CONSULTANT will provide the CLIENT with
certificates of insurance, showing evidence of required coverages. All policies of insurance shall
contain a provision or endorsement that the coverage afforded will not be canceled or reduced in
limits by endorsement for any reason except non-payment of premium, until at least 30 days’ prior
written notice has been given to the CLIENT, and at least 10 days’ prior written notice in the case
of non-payment of premium.
F. OPINIONS OR ESTIMATES OF CONSTRUCTION COST
Where provided by the CONSULTANT as part of Exhibit I or otherwise, opinions or estimates of
construction cost will generally be based upon public construction cost information. Since the
CONSULTANT has no control over the cost of labor, materials, competitive bidding process,
weather conditions and other factors affecting the cost of construction, all cost estimates are
opinions for general information of the CLIENT and the CONSULTANT does not warrant or
guarantee the accuracy of construction cost opinions or estimates. The CLIENT acknowledges that
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 6 of 9
costs for project financing should be based upon contracted construction costs with appropriate
contingencies.
G. CONSTRUCTION SERVICES
It is agreed that the CONSULTANT and its representatives shall not be responsible for the means,
methods, techniques, schedules or procedures of construction selected by the contractor or the
safety precautions or programs incident to the work of the contractor.
H. USE OF ELECTRONIC/DIGITAL DATA
Because of the potential instability of electronic/digital data and susceptibility to unauthorized
changes, copies of documents that may be relied upon by CLIENT are limited to the printed copies
(also known as hard copies) that are signed or sealed by CONSULTANT. Except for
electronic/digital data which is specifically identified as a project deliverable by this
AGREEMENT or except as otherwise explicitly provided in this AGREEMENT, all
electronic/digital data developed by the CONSULTANT as part of the PROJECT is acknowledged
to be an internal working document for the CONSULTANT’S purposes solely and any such
information provided to the CLIENT shall be on an “AS IS” basis strictly for the convenience of
the CLIENT without any warranties of any kind. As such, the CLIENT is advised and
acknowledges that use of such information may require substantial modification and independent
verification by the CLIENT (or its designees). Provision of electronic/digital data, whether
required by this Agreement or provided as a convenience to the Client, does not include any license
of software or other systems necessary to read, use or reproduce the information. It is the
responsibility of the CLIENT to verify compatibility with its system and long-term stability of
media. CLIENT shall indemnify and hold harmless CONSULTANT and its Subconsultants from
all claims, damages, losses, and expenses, including attorneys' fees arising out of or resulting from
third party use or any adaptation or distribution of electronic/digital data provided under this
AGREEMENT, unless such third party use and adaptation or distribution is explicitly authorized by
this AGREEMENT.
I. DATA PRACTICES
All data collected, created, received, maintained, or disseminated, or used for any purposes in the
course of the CONSULTANT’S performance of the Agreement is governed by the Minnesota
Government Data Practices Act, Minnesota Statutes Section 13.01, et seq. or any other applicable
state statutes and state rules adopted to implement the Act, as well as state statutes and federal
regulations on data privacy. The Consultant agrees to abide by these statutes, rules and regulations
and as they may be amended. In the event the CONSULTANT receives a request to release data, it
shall notify CLIENT as soon as practical. The CLIENT will give instructions concerning release of
data to requesting party and CONSULTANT will be reimbursed as Additional Services by CLIENT
for its reasonable expenses in complying with the request.
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 7 of 9
J. PERIOD OF AGREEMENT
This Agreement will remain in effect for the longer of a period of two years or such other explicitly
identified completion period, after which time the Agreement may be extended upon mutual
agreement of both parties.
K PAYMENTS
If CLIENT fails to make any payment due CONSULTANT for services and expenses within 60
days after date of the CONSULTANT'S itemized invoice, a service charge of one and one-half
percent (1.5%) per month or the maximum rate permitted by law, whichever is less, will be charged
on any unpaid balance. In addition after giving seven days' written notice to CLIENT,
CONSULTANT may, without waiving any claim or right against the CLIENT and without
incurring liability whatsoever to the CLIENT, suspend services and withhold project deliverables
due under this Agreement until CONSULTANT has been paid in full all amounts due for services,
expenses and charges.
L. TERMINATION
This Agreement may be terminated by the CLIENT for any reason or for convenience by the
CLIENT upon seven (7) days written notice. The CONSULTANT may only terminate for non-
payment by CLIENT upon CLIENT’s failure to cure upon 30 days written notice.
M. CONTINGENT FEE
The CONSULTANT warrants that it has not employed or retained any company or person, other
than a bona fide employee working solely for the CONSULTANT to solicit or secure this Contract,
and that it has not paid or agreed to pay any company or person, other than a bona fide employee,
any fee, commission, percentage, brokerage fee, gift or any other consideration, contingent upon or
resulting from award or making of this Agreement.
N. NON-DISCRIMINATION
The provisions of any applicable law or ordinance relating to civil rights and discrimination shall be
considered part of this Agreement as if fully set forth herein.
The CONSULTANT is an Equal Opportunity Employer and it is the policy of the
CONSULTANT that all employees, persons seeking employment, subcontractors, subconsultants
and vendors are treated without regard to their race, religion, sex, color, national origin, disability,
age, sexual orientation, marital status, public assistance status or any other characteristic protected
by federal, state or local law.
O. CONTROLLING LAW
This Agreement is to be governed by the law of the State of Minnesota.
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 8 of 9
P. DISPUTE RESOLUTION
CLIENT and CONSULTANT agree to negotiate all disputes between them in good faith for a
period of 30 days from the date of notice of dispute prior to proceeding to formal dispute resolution
or exercising their rights under law.
Q. SURVIVAL
All obligations, representations and provisions made in or given in Section IV of this Agreement
will survive the completion of all services of the CONSULTANT under this Agreement or the
termination of this Agreement for any reason.
R. SEVERABILITY
Any provision or part of the Agreement held to be void or unenforceable under any law or
regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and
binding upon CLIENT and CONSULTANT, who agree that the Agreement shall be reformed to
replace such stricken provision or part thereof with a valid and enforceable provision that comes as
close as possible to expressing the intention of the stricken provision.
S. AUDIT DISCLOSURE
The CONSULTANT must allow the CLIENT, or its duly authorized agents, and the state auditor or
legislative auditor reasonable access to the CONSULTANT’s books, records, documents, and
accounting procedures and practices that are pertinent to all services provided under this Agreement
for a minimum of six years from the termination of this Agreement.
[remainder of the page intentionally blank]
City of Hopkins Standard Agreement (Modified from 2004 Standard Form) VER. 12/05/2017
Page 9 of 9
SECTION V - SIGNATURES
THIS INSTRUMENT embodies the whole agreement of the parties, there being no promises, terms,
conditions or obligation referring to the subject matter other than contained herein. This Agreement may
only be amended, supplemented, modified or canceled by a duly executed written instrument signed by
both parties.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in their behalf.
CLIENT: City of Hopkins, Minnesota CONSULTANT: Bolton & Menk, Inc.
Mike Waltman, P.E., BMI Office Manager
11/1/2022
Date
Date
Marcus Thomas, P.E., Sr. Principal Engineer
11/1/2022
Date
City of Hopkins October 18, 2022
1
EXHIBIT I
FINAL DESIGN, CONSTRUCTION OBSERVATION, ADMINISTRATION & STAKING
2023 STREET AND UTILITY IMPROVEMENTS
CITY OF HOPKINS, MINNESOTA
A. BASIC SERVICES
In accordance with the City of Hopkins’ Preliminary Engineering Report, Bolton &
Menk, Inc. has been requested to complete final design, bidding assistance, construction
staking, construction observation and construction administration services for the City’s
2023 Street and Utility Improvements. The project area includes the following corridors:
▪ Street & Utility Reconstruction
▪ 12th Avenue N, Mainstreet to 1st Street N
▪ 14th Avenue N, Mainstreet to 2nd Street N
▪ 15th Avenue N, Mainstreet to 2nd Street N
▪ 16th Avenue N, Mainstreet to 1st Street N and 2nd Street N to 3rd Street N
▪ 2nd Street N, 14th Avenue N to 15th Avenue N
▪ Sidewalk along 1st Street N, 14th Avenue N to 16th Avenue N
▪ Street Resurfacing and Spot Utility/Concrete Improvements (Add Alternates)
▪ 9th Avenue S, Mainstreet to Excelsior Blvd
▪ 10th Avenue S, Mainstreet to 1st St S
▪ 1st St S, 8th Ave S to 11th Ave S
▪ Storm sewer north of Maetzold Filed between 13th Ave N and 14th Ave N
▪ CIPP Lining in the street & utility reconstruction area and other areas of the City
Building from tasks 1 through 3 of our preliminary design scope of services, detailed
tasks associated with the work are itemized in the attached Detailed Work Plan and are
described below.
Task 4: Final Design & Bidding Services
Final Design
Final design for the 2023 Street and Utility Improvements will be completed based on the
Preliminary Engineering Report completed by Bolton & Menk, Inc. in September 2022.
Final plans and specifications will be completed in compliance with the City of Hopkins’
Engineering Guidelines and consistent with plan content for the 2022 Street & Utility
Improvement project. Detailed construction plans will be prepared in Civil3D design
software at 25 scale. The plans and specifications will include:
• Plan and profile views of the street reconstruction and utility improvements at 25
scale.
• Cross sections will be shown for reconstructed streets at approximately 25'
spacing and at each driveway.
• Required construction details.
City of Hopkins October 18, 2022
2
• Special provisions for elements of work not addressed in the MnDOT 2020
Standard Construction Specifications.
Final plans will be submitted for review and comment by private utility owners. Permit
applications as noted in the Preliminary Engineering Report will be completed and
submitted to the permitting agency. Upon completion of construction plans and
specifications, a final estimate of construction cost will be prepared and submitted to the
client. The project will be advertised, bids will be taken, and recommendation will be
made to accept or reject bids. Meetings included during final design include one (1)
private utility coordination meeting, up to two (2) City Staff meetings for design review,
one (1) neighborhood meeting prior to the assessment hearing and construction, and two
(2) City Council meetings for final plan presentation and conducting the Public
Assessment Hearing.
Impacts to some trees and privately maintained landscaping within the public right-of-
way are anticipated. Coordination efforts will be undertaken with homeowners regarding
tree removals and landscaping impacts prior to construction. Letters will be sent to each
affected property to inform the owner of the known or potential tree and/or landscaping
impacts to their property. The Construction Observer and/or Project Manager will
respond to questions of the owner(s) and will coordinate on-site meetings as necessary to
coordinate any impacts prior to construction.
Special Assessments Assistance
For this project, the City of Hopkins intends to assess this project prior to awarding the
contract, based on the bid of the lowest responsible bidder. Bolton & Menk will prepare a
final assessment roll after bids have been opened and will attend the public assessment
hearing to assist City Staff. Bolton & Menk will assist City Staff with the assessment
process and associated statutory requirements, as well as aid in responding to property
owner inquiries throughout the process. Bolton & Menk will attend and facilitate one
neighborhood meeting prior to the final assessment hearing to provide additional
information on assessment amounts, payment options, and any remaining questions on
the proposed improvements.
Tasks 5: Construction Services
Construction Staking
Construction staking indicating cuts to the line and grade of the proposed utilities will
typically be performed at intervals of 50 feet. These utilities include sanitary sewer pipe
and manholes; watermain pipe, hydrants, and bends; storm sewer pipe, manholes, and
catch basins. Curb stakes will be provided along the reconstructed roadways at intervals
of 25 feet.
Construction Observation and Administration
This project is proposed to be constructed during the 2023 construction season and is
anticipated to occur over multiple phases of construction between late April and early
November. The projected fee estimate is based upon a 28-week construction season. Full
City of Hopkins October 18, 2022
3
time construction observation is proposed for this project with the assistance of an intern
during the peak 12 weeks of the construction season. The contractor’s use of several
construction crews across the multi-phased project will be necessary for timely
completion.
Duties of the Lead Construction Observer will include attendance at the pre-construction
meeting and all construction-related meetings, service as a liaison between the City and
the contractor, review of the completed work to determine if the project is in general
conformance with the plans and specifications, review and scheduling of all materials
testing, maintenance of construction documentation, tracking quantities, project closeout
including checking in on punch list items, and communication with affected property
owners, as necessary, to address their construction-related concerns and issues.
Communication will include door-to-door notices as often as daily, phone calls, text
messages, emails, and in-person meetings. The Construction Manager will support the
Construction Observer and Intern to ensure that all duties are being fulfilled to satisfy
resident requests, achieve contract compliance, and coordinate needs between the
Contractor and City.
Administration duties by the Project or Construction Manager include a pre-construction
meeting, weekly project meetings including minutes, review of shop drawings, sending
out weekly email updates to resident subscribers, preparing and mailing out monthly
newsletters to residents, maintaining a project website, and preparation of pay estimates.
Observation and administration services will be completed on an hourly basis.
Record Drawings & GIS Integration
Record drawings detailing the completed improvements as recorded by the construction
observer will be completed and furnished to the City in hard copy and electronic format.
These record drawings will also be integrated with the City’s GIS web application in
PDF. Utilities, curb stops, and structures will be located (horizontally) after construction
using a handheld GPS unit and will also be incorporated in the GIS schematic layout as
GIS entities.
The following is a preliminary schedule for the 2023 Street & Utility Improvements:
Preparation of Final Plans & Specifications ........... November 2, 2022 – January 17, 2023
Approve Final Plans & Specifications /
Authorize Advertisement for Bids ........................................... January 17, 2023
Bid Opening ............................................................................................ February 10, 2023
Council Sets Public Assessment Hearing Date ................................. February 21, 2023
Neighborhood Meeting 3 ..................................................................... March 13 – 16, 2023
Council Accepts Bids / Conduct Public Assessment Hearing /
Adopt Assessment Roll / Award Bid .......................................... March 21, 2023
Construction ........................................................................................ May – October 2023
City of Hopkins October 18, 2022
4
B. ADDITIONAL SERVICES
Consulting services performed other than those authorized under Section I.A. shall be
considered not part of the Contract Services and may be authorized by the CLIENT as
additional services. Additional Services consist of those services which are not generally
considered to be Contract Services; or exceed the requirements of the Contract Services;
or are not definable prior to the commencement of the project; or vary depending on the
technique, procedures or schedule of the project contractor. Additional services may
consist of the following:
1. Cost of postage for mass mailing (those with greater than 100 recipients).
2. All other services not specifically identified in Section A.
DETAILED WORK PLAN
ESTIMATED PERSON-HOURS
2023 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES
CITY OF HOPKINS, MINNESOTA
10/18/2022
CLIENT:CITY OF HOPKINS, MINNESOTA
PROJECT:
CONSULTANT:
2023 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES
BOLTON & MENK, INC.
Task No.Work Task Description
4.0 FINAL DESIGN & BIDDING
4.1 Utility Engineering and Design 20 60 120 40 240
4.2 Roadway Engineering and Design 20 60 180 260
4.3 Plan Set Production 240 80 120 440
4.4 Field Visits 8 8 4 20
4.5 Private Utility Coordination 4 20 20 10 54
4.6 Construction Quantities and Cost Estimates 4 40 40 40 40 164
4.7 Construction Specifications 4 40 4 30 78
4.8 Permit Applications 4 16 16 4 8 4 52
4.9 Bidding Assistance, Addenda, Award Recommendation 8 16 8 4 4 30 70
4.10 Final Assessment Roll Preparation 4 12 16
4.11 QA / QC 60 80 20 4 164
4.12 Project Meetings (City Staff - 2), 1 Neighborhood Meeting, Public Communication 32 64 24 12 40 16 188
4.13 City Council Meeting (2 meetings)10 10 20
SUBTOTAL HOURS: TASK 4 170 426 468 332 186 0 56 40 8 0 0 0 80 1766
5.0 CONSTRUCTION SERVICES
5.1 Construction Phase Startup (Precon, Resident Coordination, Contractor Coordination, etc.)8 24 40 40 40 152
5.2 Construction Administration (28 weeks @ 10 hrs/week)60 280 150 80 570
5.3 Construction Observation (Lead 28 weeks @ 55 hrs/week, Intern 12 weeks @ 40 hrs/week)560 1540 480 2580
5.4 Construction Staking 60 120 560 740
5.5 Record Drawings 8 8 80 96
5.6 Project Closeout, Punch List 12 60 20 80 172
5.7 GIS Integration 4 4 16 20 44
SUBTOTAL HOURS: TASK 5 80 376 0 632 1756 480 0 190 20 60 120 560 80 4354
TOTAL HOURS 250 802 468 964 1942 480 56 230 28 60 120 560 160 6120
Survey Manager
/ L.S.
Surveying
Technician
Construction
Manager
Construction
Intern
Survey Crew
(1-man)ClericalConstruction
Observer
Communications
Specialist
Water
Resouces
Engineer
GIS Specialist
ESTIMATED PERSON-HOURS
TotalsPrincipal
Engineer Project Manager Engineering
Technician
ESTIMATE OF PROJECT FEES
2023 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES
CITY OF HOPKINS, MINNESOTA
10/18/2022
CLIENT:CITY OF HOPKINS, MINNESOTA
PROJECT:
CONSULTANT:
2023 STREET & UTILITY IMPROVEMENTS: FINAL DESIGN & CONSTRUCTION SERVICES
BOLTON & MENK, INC.
AVERAGE RATE:$196.00 $165.00 $120.00 $155.00 $120.00 $90.00 $185.00 $115.00 $135.00 $186.00 $125.00 $178.00 $99.00
4.0 FINAL DESIGN & BIDDING
4.1 Utility Engineering and Design $3,920.00 $9,900.00 $0.00 $18,600.00 $0.00 $0.00 $7,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $39,820.00
4.2 Roadway Engineering and Design $3,920.00 $9,900.00 $21,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $35,420.00
4.3 Plan Set Production $0.00 $0.00 $28,800.00 $12,400.00 $14,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $55,600.00
4.4 Field Visits $0.00 $1,320.00 $0.00 $1,240.00 $0.00 $0.00 $740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,300.00
4.5 Private Utility Coordination $784.00 $3,300.00 $0.00 $3,100.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,384.00
4.6 Construction Quantities and Cost Estimates $784.00 $6,600.00 $4,800.00 $6,200.00 $4,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $23,184.00
4.7 Construction Specifications $784.00 $6,600.00 $0.00 $0.00 $0.00 $0.00 $740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,970.00 $11,094.00
4.8 Permit Applications $784.00 $2,640.00 $0.00 $2,480.00 $0.00 $0.00 $740.00 $0.00 $1,080.00 $0.00 $0.00 $0.00 $396.00 $8,120.00
4.9 Bidding Assistance, Addenda, Award Recommendation $1,568.00 $2,640.00 $960.00 $620.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,970.00 $9,238.00
4.10 Final Assessment Roll Preparation $784.00 $1,980.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,764.00
4.11 QA / QC $11,760.00 $13,200.00 $0.00 $3,100.00 $0.00 $0.00 $740.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $28,800.00
4.12 Project Meetings (City Staff - 2), 1 Neighborhood Meeting, Public Communication $6,272.00 $10,560.00 $0.00 $3,720.00 $1,440.00 $0.00 $0.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $1,584.00 $28,176.00
4.13 City Council Meeting (2 meetings)$1,960.00 $1,650.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,610.00
SUBTOTAL FEES: TASK 4 $33,320.00 $70,290.00 $56,160.00 $51,460.00 $22,320.00 $0.00 $10,360.00 $4,600.00 $1,080.00 $0.00 $0.00 $0.00 $7,920.00 $257,510.00
5.0 CONSTRUCTION SERVICES
5.1 Construction Phase Startup (Precon, Resident Coordination, Contractor Coordination, etc.)$1,568.00 $3,960.00 $0.00 $6,200.00 $4,800.00 $0.00 $0.00 $4,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $21,128.00
5.2 Construction Administration (28 weeks @ 10 hrs/week)$11,760.00 $46,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $17,250.00 $0.00 $0.00 $0.00 $0.00 $7,920.00 $83,130.00
5.3 Construction Observation (Lead 28 weeks @ 55 hrs/week, Intern 12 weeks @ 40 hrs/week)$0.00 $0.00 $0.00 $86,800.00 $184,800.00 $43,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $314,800.00
5.4 Construction Staking $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $11,160.00 $15,000.00 $99,680.00 $0.00 $125,840.00
5.5 Record Drawings $0.00 $1,320.00 $0.00 $1,240.00 $9,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $12,160.00
5.6 Project Closeout, Punch List $2,352.00 $9,900.00 $0.00 $3,100.00 $9,600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $24,952.00
5.7 GIS Integration $0.00 $660.00 $0.00 $620.00 $1,920.00 $0.00 $0.00 $0.00 $2,700.00 $0.00 $0.00 $0.00 $0.00 $5,900.00
SUBTOTAL FEES: TASK 5 $15,680.00 $62,040.00 $0.00 $97,960.00 $210,720.00 $43,200.00 $0.00 $21,850.00 $2,700.00 $11,160.00 $15,000.00 $99,680.00 $7,920.00 $587,910.00
TOTAL FEES $49,000.00 $132,330.00 $56,160.00 $149,420.00 $233,040.00 $43,200.00 $10,360.00 $26,450.00 $3,780.00 $11,160.00 $15,000.00 $99,680.00 $15,840.00 $845,420.00
Communications
Specialist GIS SpecialistConstruction
Manager
Construction
Intern
Survey
Manager / L.S.
Surveying
Technician
Survey Crew
(1-man)Clerical Totals
PROJECT FEES
Principal
Engineer Project Manager Engineering
Technician
Construction
Observer
Water Resouces
Engineer