Proposed Action.
Staff recommends adoption of the following motion: Move that Council approve plans.
as presented. and authorize bids for the rehabilitation and paintinQ of Moline water
tanks. Proiect 98-06.
Overview.
The Moline water tower was last painted in 1987. The steel tank is showing significant
signs of corrosion. The current capital improvement plan (CIP) includes this year 2000
project with an estimated cost of $500,000. In August, 1999 City Council authorized
design of this project. A detailed interior inspection and thorough review of underwater
video taping has shown that there is enough corrosion to warrant complete repainting.
The engineer's estimate of construction cost is $665,575. The increase is primarily due
to safety and venting rehabilitation work that is also included in the project. The plans
are completed and are now presented to Council for approval and ordering of bids.
. Primary Issues to Consider.
. Description of Improvements
. Paint color and graphics
. Project schedule
. Impact on water distribution system
Supportina Information.
. Project schedule
. Construction cost estimate
~~
Steven J. Stadler, Public Works Director
.
.
.
.
Council Report 200-005
Page 2
Analysis of Issues.
. Description of Improvements
. Complete corrosion control and painting of interior and exterior of tank with
antennas and cable in-place using necessary containment system. The
interior surfaces of the ground tank shows 40 - 50% requiring repainting. The
elevated tank interior surfaces shows 20 - 25% corroded areas.
. Install new tank vents
. Install new overflow pipes
. Install new electrical wiring and lighting
. Install new exterior ladder and roof platform
. Hopkins lettering
. Paint color and graphics
Staff is recommending the tank exterior be painted the same color as the Minnetonka
Ridgedale Tank with vertical Hopkins uppercase lettering in blue located on three
sections of the tank wall. The existing tank has black uppercase lettering on two
sections of the tank wall and the Hopkins logo on two sections.
. Project Schedule
The project schedule is as follows:
Open bids:
Contract award:
Construction start (earliest):
Tank out of service (earliest):
Substantial completion:
Final completion:
February 3, 2000
February 17, 2000
March 27, 2000
April 24,2000
August 1, 2000
September 1, 2000
. Impact on water distribution system
The water system will be more susceptible to minor pressure fluctuations due to the
elevated storage being reduced in half. However, past history has shown that
pressures will be maintained by the Blake elevated tank. In the event of a fire flow
event, we can open a valve to the Minnetonka system to maintain pressure. The water
tanks will not be taken out of service until the water filter work is completed at the Elmo
Treatment plant.
.
.
.
MEMO
.. ~SE'"H=lCll1
TO:
Mike Lauseng, City of Hopkins
Steve Stadler, City of Hopkins
FROM:
Dale Folen, P.E., Project Manager
Short Elliott Hendrickson, Inc. (SEH-RCM)
RE:
Rehabilitation and Recoating of Existing Moline Water Storage Tank
Hopkins, Minnesota
SEH-RCM Project No. AHOPKN9908.00
City Project 98-06
DATE:
December 27, 1999
Proposed Bidding Schedule
Event
Date
Complete Final Design
January 4, 2000
Council Approval to Advertise for Bids
January 4, 2000
Submit Advertisement - Local (Legal) Paper:
Submit Advertisement - Construction Bulletin
(Thurs @ 12:00) January 6, 2000
(Tues @ 15:00) January 11,2000
First Advertisement for Bids - Local (Legal) Paper:
Second Advertisement for Bids - Local (Legal) Paper:
(Wed) January 12, 2000
(Wed) January 19, 2000
First Advertisement for Bids - Construction Bulletin
Second Advertisement for Bids - Construction Bulletin
(Fri) January 14, 2000
(Fri) January 21, 2000
Open Bids
February 3, 2000
Council Award Construction Contract
February 15,2000
Notice of Award
Receive Agreement & Documents from Contractor
Notice to Proceed (tentative Pre-construction conference met:ting date)
February 17, 2000
Man:h 6, 2000
March 10, 2000
Start Construction (Earliest Limit)
Allow Tank Out of Service (Earliest Limit)
Substantial Completion (Operational Tank)
March 27, 2000
April 24, 2000
August 1, 2000
Final Completion (Clean-up)
September 1, 2000
H:\CIVIL \Projeets\HOPKINS IHuPKK90R. OO\WPDOCS ISched _bid. wpd
.
Rehabilitation and Recoating of Existing
Moline 2.1 MG Taro Standpipe
Hopkins, Minnesota
City Project No. 98-06
SEH No. A-HOPKN9908.00
Engineer's Estimate
12/2811999
.
Estimate
No. Item Unit Quantitv Unit Price Total
1 Mobilization LS 1 $ 15,000.00 $ 15,000,00
2 Seal Weld Inside Roof Manhole LS 1 $ 175.00 $ 175,00
3 Elastomeric Caulking LF 1200 $ 5.00 $ 6,000,00
4 Add Toeplate to Existing Roof Guardrail LS 1 $ 1,000,00 $ 1,000.00
5 Add Fall Arrest System to EXisting Ladder in Dry Tube LS 1 $ 1,300.00 $ 1,300,00
Add Removable Screen to Existing Vent Holes in Dry
6 Tube LS 1 $ 1,000.00 $ 1,000.00
Remove Existing Mushroom Vent on Tank Roof and
7 Replace with New Aluminum Vent LS 1 $ 6,500.00 $ 6,500.00
8 Add New Aluminum Vent to Tank Roof LS 1 $ 7,200.00 $ 7,200.00
Remove 10-inch Motorized Valve and Approximately
9 40 feet Pipe from Elevated Tank LS 1 $ 2,200.00 $ 2,200.00
Remove existing a-inch Gate Valve from Tank Drain
10 and Replace with New 8-inch Gate Valve LS 1 $ 900.00 $ 900,00
11 Add 24-inch Painters Manhole to Tank Roof LS 1 $ 2,300.00 $ 2,300,00
12 Remove and Replace Grout under Footer Plate LS 1 $ 3,000.00 $ 3,000,00
13 Add Shell Manhole to Tank LS 1 $ 5,000.00 $ 5,000.00
14 Remove and Replace Overflow Pipes LS 1 $ 8,000.00 $ 8,000.00
15 Add Catch Basin under Overflow Pipe LS 1 $ 4,600,00 $ 4,600.00
16 Remove and Replace Electrical Wiring & Lighting LS 1 $ 25,000.00 $ 25,000,00
Remove Existing Ladder in Pilaster from Ground to
Upper Platform and Add Rail to End of Upper
17 Platform LS 1 $ 1,500,00 $ 1,500,00
Add New Ladder and Roof Platform and Guardrail to
18 Outside of the Tank from the Ground to the Roof LS 1 $ 12,000.00 $ 12,000.00
Add Vents to Upper Portion of Ground Storage
19 Portion of Tank HR 1 $ 2,200.00 $ 2,200.00
20 Grinding HR 300 $ 85.00 $ 25,500,00
21 Interior Wet Paint System LS 1 $230,000,00 $ 230,000,00
22 Exterior Paint System (Antennas and Cable In-place) LS 1 $220,000,00 $ 220,000.00
23 Logos and Lettering LS 1 $ 12,000,00 $ 12,000.00
24 Two-year Anniversary Inspection LS 1 $ 3,200,00 $ 3,200.00
25 Necessary Containment LS 1 $ 70,000.00 $ 70,000.00
Total Engineer's Estimate of Construction Cost $ 665,575.00
.