Memo- Public Works Building Addition . I Public Works Department Memorandum From: Honorable Mayor and Members of the City ~ou~il Steven J. Stadler, Public Works Director ~ ~ To: Date: June 23, 2000 Subject: Public Works Building Addition/Renovation Project The Capital Improvement Plan includes funding to design this Public Works Building project this year ($100,000) and for construction in 2001. Staff has received and reviewed two engineering services proposals and would like to enter into an agreement with Howard R. Green Company for final design architectural and engineering services. The lump sum cost for design and construction administration/inspection services is . $78,800. Additional costs would include an estimated $2,000 for soil testing. The second architecture/engineering proposal was from Boonestro & Associates. Their fees totaled $90,000 to $117,000 depending on construction cost. Proposed Project FundinQ The project is proposed to be funded through a $1.5 million HRA revenue bond. The HRA would in-turn lease the facility to the City. The city would make annual lease payments for 15 years. Staff estimates the annual lease payments to be $150,000. These payments would be funded by the general fund and the four utility funds (water, sewer, refuse and storm sewer). Staff proposes that the general fund pay 47% or $70,000 per year and the utility funds pay 53% or $80,000 per year. The taxpayer impact of this proposal is as follows: $7/yr for a residential property with a year 2001 market value of $120,000 $12/yr for a residential property with a value of $190,000 e $94/yr for a commercial property with a year 2001 market value of $620,000 . . . The utility funds can cover the $80,000 annual payment without the need for associated rate increases. In fact, based on the current CIP it appears that a future storm sewer rate reduction may be possible on or about the year 2010. Several other cities have used alternative financing mechanisms for Public Works building projects. They include: . City of Independence: Funded an $800,000 building addition using lease-purchase from H. R.A. . City of Maplewood: Funded a $1.0 million storage facility with a fund derived from annual city-wide equipment charges. . City of Chaska: Funded an $850,000 building addition from an electrical utility fund. Proiect Benefits . Provide heated & properly ventilated indoor parking for all Public Works equipment. This equipment is valued at over $2 million. . Improve safety by allowing proper cold weather inspection of trucks. . Improve efficiency of snow & ice control operations by eliminating warm-up time for diesel engines and hydraulic systems. . Increase the useful life of equipment that is currently stored outside. . Reduce maintenance and repair costs of all equipment. . Replace a 50-year old wood framed storage building with a concrete masonry building addition that matches existing Public Works Facility. . Allow use of building #3 for sand and salt storage. This building is currently used as cold storage for street maintenance equipment. Yr 2001 - 2005 Capital Improvement Plan fundinQ Staff will be prepared to discuss future funding for the complete Capital Improvement Plan, including a future public safety facility improvements project to address Police and Fire Dept space needs. City Council Approvals If City Council approves the funding plan and the design contract then the final approvals would be advertisement and award of a construction contract. Staff would request approval for the design contract at the July 5 Council meeting. Attachments HRG Proposal CIP project sheet + project concept site plan and bldg layout I' I I I I I I I I I r I I t City of Hopkins 2001 Public Works Vehicle Storage Building ?,..t""t'$,IV<~"':l~" Proposal submitted by ~oward R. Green Company June 9, 2000 I ,I I, I: ,I :1 I t. i I I I I I I I. I I I I I I I. I Statement of Understanding It is our pleasure to submit this proposal for the 2001 Public Works Vehicle Storage Building Project. We have enjoyed working with the City of Hopkins on past projects, and hope to continue this relationship into the future. It is our understanding that this project will include the demolition of the existing Vehicle Storage Building #2 to make room for the new addition. Our structural engineers will be involved in this process to ascertain that disconnection of the existing public works building is handled properly and that any slabs on grade or eXisting footings are removed as necessary, so as not to interfere with construction of the new addition. Similar attention will be given to the demolition of the westerly 40 feet of Vehicle Storage Building #3. Any necessary additions or modifications to the newly exposed walls of the remaining Building #3 will be included as part of the project. Modifications will also be made to Building #3 that will allow the City to utilize this space for salt storage. Modifications would include new overhead door access points, structural barriers to prevent damage to the building, fill and slab repair to areas with space below, as well as other necessary items to make this a usable storage space. The new Public Works Vehicle Storage Building Addition is to be 200 feet by 106 feet. It is to be constructed with precast double tee concrete panels on the east and west to match the existing Public Works Building. Smooth precast wall panels will be used on the north. Connections to the existing Public Works Building on the south side will include tying into both double tee wall panels and smooth wall panels. These locations are usually the points where the Owner most often has future problems with leakage, movement, etc. We have staff, including registered roof consultants, who are specialized in detailing exterior components. These staff members will be involved with properly detailing these tie-in locations. It is stated that existing buildings are over 50 years old and in need of renovations. This same specialized staff would be available for any renovation work you may be considering. We will also provide all necessary mechanical and electrical engineering services to cover the electrical work and mechanical heating system. HRG's specialized staff will ensure the proper detailing of tie-ins to the wall panels to prevent future lealmge and movement pI'oblems. We will provide a topographic survey of the site, including a drawing to be incorporated into the construction documents. Landscaping, concrete curbing, and pavement detailing will also be provided for areas disturbed or modified by the work. Our registered architectural and engineering staff will closely review the new addition for all necessary code compliance issues. We will also meet with the City of Hopkins Building Official during the decision- making process as necessary to ensure good, open communication and the receipt of valuable input on the project. During our site walkthrough, Norb Kerber mentioned it may be possible to use the existing trench drain system at the east end of the Public Works Building in some modified fashion to help limit the extent of new trench drainage cost. Once the design process starts, we = ~ONard R. Green Company I I. I I I I I I I I. - - - I I I '. - would want to meet to discuss any other items the City may have or that HRG has that would help to more wisely spend the City of Hopkins' dollars. At this time, we anticipate having a registered architect and roof consultant along with registered structural, electrical, mechanical, and civil engineers involved with this project Microsoft Schedule is used within our office to schedule and monitor design production. The project can be easily broken into smaller, more manageable components. We also have intranet and extranet capabilities to help monitor, communicate, and share drawings with other consultants during the design process on larger jobs. Internal budgets are monitored, revised, and updated using Sema4 Enterprise, which is a client/server management system. This, combined with Microsoft Schedule, keeps projects on track and under budget. Benefits of the Sema4 Enterprise software include multiple methods for tracking revenue recognition and poweriullabor distribution capabilities. We believe construction administration and observation are key to a project's success. We have experienced field staff that would be periodically on site during construction. When on site, our field staff would provide daily construction reports. With expel'ienced field personnel providing construction administration and observation, your project will be completed on schedule and within budget. As part of the contract administration, we require contractor work schedules and schedule of values to be submitted. The schedule of values is broken into easily recognizable components with up to 50 tasks and values. Weekly meetings are normal project procedure. During the weekly meetings, there is a set agenda including project progress schedule, updated schedule of values along with percent complete, a time to request information, a time for request for proposals for additional work, a time to review and discuss any change orders. The meetings are followed up with meeting minutes documenting the items discussed. When pay requests are processed, we require the contractor to submit with the pay request the schedule of values and the current percent complete. When necessary, we require proof of payment to vendors and suppliers as part of the pay request procedure. This helps alleviate concern for possible liens toward the end of the project We provide numerous tests for quality in both materials and installation. Many of the tests are provided on site so application adjustments may be made. An example of on-site provided testing is the testing of the application of a built-up roof membrane. Our experienced inspectors cut a 12-inch by 12-inch section out of the newly installed roof. The sample is weighed and checked for proper laps, proper interply weights, maximum air voids, etc., in the field. The roof contractor can then immediately make Installation adjustments based on the test. Testing follows standards set by ASTM. Test results are documented in our daily field reports. Reports are put together on laptops using Microsoft Word and include digital photos documenting the progress of the work. - ~oward R. Green Company ~ i ~. I I I. I I I I l I I , .. ; I ; - r: I , , . l I I I ~: ~. . ,. I Fee Estimate We propose to provide all architectural and engineering services necessary to complete the project as described in the Request for Proposal - 2001 Public Works Vehicle Storage Building Information Packet, dated May 16, 2000, for: $78,800.00 Items not included in the above fees are: 1. Concrete testing. This is a cost typically paid by the contractor. We would specify the necessary testing and specify that the contractor arrange and pay for these tests. 2. Soil borings. We do not provide geotechnical services. If not already performed as part of the Feasibility Study, we would anticipate the need for approximately two soil borings at an approximate cost of $1,500.00 3. As discussed with Norb Kerber, the topographic survey would include the site only. It would not include underground utilities, or tie-ins to boundary lines, etc. If this is needed and not already completed, it would be an additional cost. ~oward R.Green Company .~~--_._- ~- ._--~~~_.._----- -.-.-.-- -.- -- ~- ; ":. - ... . " . '.-.-::-:-_7- .____....-.----:-::-" __ ~__ .._~~.' .. L ., . ~ ". ;. .. -' . ~" ..; .. : '; . - ~.- " CATEGORYU:'., PROJECT :IT~E. :~~'.N~!"(IBER :.".5,~:~~ C?ST ,',. .", Public Works Storage FacilitY.,.:'_ 'C",: MF-l ;:,-:~~'.: $1,500,000 SCHEDULED PROJECTACTIVITYc,; , /<-.;,.'..: _:~- '~.". . .;,.:i',' '.: 2~.O~:.':._ . 2003,:" .-,-..2.?O~. . FUT!-,RE .~'7' ~~. '.:-"-:-,.~,""".~,.~.:r,- -: . ..-...... .::'; .~:;.~..: :.::'; L~,_:;..:~ :'. ~'~'. :__. . '.:. - ._....:: .~. _ c, ~ ... :.., '..... G~~ P~b Bldg~:~j;:'\.,...':: FU~'D.ING~;:~<;t . " .7,'L-,;;~~?~__~~~,':~-~:"_~~c;;; . .... C ,'~_':, .-. Housing/' -, Redevelo'p Auth.:.:' .I.,.C. LOCATION: Jl100 Excelsior Boulevard. DESCRIPTION: Public Works vehicle storage building JUSTIFICATION: Scope of project is to remove building numbe r 2 and construct a new 200 X 106 heated storage building. Utilize building number 3, the current street equipment storage building, for salt and sand storage. Current buildings are over 50 years old and will be in need of major renovations in the near future. CURRENT STATUS/PROJECTED SCHEDULE: Plans and specifications: Year prior to construction Bid: Year of construction RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: . . ~~ ~:.~ i ~ ~. ~ r- . . . ~jWl~ M-k , J ~ I u:1 N&. oF,? e ~ t ~ISTIHb~BW6 * rL ~ ~aFtFl+' ~ OVERALL SITE PLAN t:> ~ \\l t..'o. - - -- - _ _J. , \ I , .Ql D ~-~ o i :4 ~ .5 7: ~ ~ ~ .5 t ~ f r &):J ___ - - - - - --- .. @ @ ~ o o I , I I , ! I ! I I I I I i ! i , I i>- 10 .:::> '1- :(/) :z o ;~ 15 10 .<( ~l \ll~~ o ~ 0 :...J I_ i:::> :cn i(/) I~ ..10: jo .: 3: q o ~~ 15: Ul1(/) L.J z .!..! 52 '0... \,] ~ I '~ ~~~ , @ ~ o o ~ .,; 0> .; ." ... o z w ~ Li: oCt c: III z ..::e H p... ~ E-< H C/) :{ .... " , , ~ j- ~ ?r' ~ f' - i\ tl l' ,-- :rlti - ---- "XJC> i!G ~ T. -5 ~ -.i). I. ~ ~ ?: ~ ::i ~~ t \ll' j ~ ~l~~' @I >- .. .'': en ' z o - !:: o o ~ (!} ': Z - C ..J - ::> CO en ~ 0: ~ g ..J CO ::> a. en z ~ ~' J: :.,' .'" ~ ~ 0') 0') ~ 4') ,... d z UJ ..J -. en . . . :2:PJOJ o :J C --sro=': 6f~~ :::J -+dD (Q P.) -, ()O=l* =:~N Q" CO I <:0'- <:;1"'""1-::; =r C -. -,-, (/) g.2.rr ,<c =rl=': g3~ ~O,.):J (j) c=r (Q Q :! ~ ..... ::l 0 mtO ~ xC)o.. C1o.rr roo. (i)'r:;.:CD -,-'0.. 00(0 .., ::l :3 OJOO o - c ,.-..1-0-' _::s(fl C'Dro::J <ro(D ~Xo.. a. _,....-l"- . fJ) 0 ~ 5'3 (Om -o?\ c ro 0"-' _0 -'0 () 3 0' --s . . . ~-l o=:r ..., -. roC/) 0. ""0 o::i cO r-t-r-f- C/) 0 -.co 0."" I CO ID ;-.."'0 llo...l.. ::i C roC/) r-t-::i 00 r-t-:E ::iC/) CDr+ ::;':E CJ'J 0 NO-o CD -0 I~ _CD o (f) COo r+ -n 2 CD O..Q At: ro -0. ::J 3 Cl.co :::r::J T' r-t- ...,r-t- ro::i ro ro 0""'" :::r3 ,...... c ..., en Cr-t- ~o- . (D . . . U'JOJ l"""'i"c o _. .., - O,)~ CO::! (1)(0 0,)* :::lVJ 0..1 or-+- l"""'i"=:J" ::r _. (D C/J "'0" :3 c. en' 0.. () -. CD :J =(0 tl) :E ~ 0 o c Co.. (J) -.0- """"'(0 (D 3 CD (J) r-+- . m -. :J (0 0.. 0' .., (") o < CD CD a. en m :J 0. --- C/J m ;:; . June 23, 2000 . . 2000 CAPITAL IMPROVEMENT PLAN DISCUSSIONS Overview The City of Hopkins is beginning the process of establishing the 2001 - 2005 capitlal improvement plan. Every year the city council reviews with the manager the major capital improvements planned for the next five years. The goal is to ensure the cities priorities and objectives are being met and the funding sources are reasonable and available. CIP Goals . Maintain the integrity of the city property, infrastructure and capital. . Provide funding for new property, infrastructure and capital as needed. . Forecast funding needs and tax implications to assure strong long-term financial stability. Attached is a draft of the 2001-2005 capital improvement plan. . . . SUMMARY OF IMPACTS ON MAJOR FUNDING SOURCES CURRENT REVENUES/GENERAL FUND RESERVES Funding of the Fire Station roof maintenance and the vehicle exhaust system have been delayed pending a resolution regarding space needs for the police department and the fire department. Delaying this project should create a $100,000 budget surplus in 2000, however, the labor contract settlements were $55,000 above what was budgeted in 2000 therefore taking a big bite out of the expected surplus. General fund expenditures are anticipated to increase another 3% in 200 I. The estimated levy increase is 4%. The levy is the general funds major source of revenues and therefore needs to increase to sustain the general funds anticipated operating expenses in 200 I and any capital improvement projects funded through general revenue. GENERAL OBLIGATION BONDS - P.l.R FUND Funding from bonds is used up front to pay for construction that will eventually be paid by special assessment collections, over a 10-20 year span, and the City's share (levy) of construction projects. The P.I.R. working capital will have substantial projects over the next few years with the construction of County Rd. 3 and all the other projects that have been planned. The potential of recouping landfill work costs from the PCA and rising repayments of special assessments will help its' funding level. The city issued P.l.R bonds in 1999 to fund projects in 1999. We will issue $1,250,000 in P .I.R bonds in the fall of 2001. In addition to these bonds, we will need to issue approximately $1,400,000 and $750,000 of P.LR. bonds in 2003 and 2006 respectively. The bonds will be paid from special assessments' and property tax levies for projects started between 2000 through 2007. Finance does not anticipate a need to increase the current debt service levy of $330,000 a year. MUNICIPAL STATE AID FUND Funding is sufficient for the projects listed in the elP document through 2001, and then the unencumbered allotment will be at a deficit until the year 2005. It may be necessary to sell MSA bonds in order to maintain the construction schedule or request an advance on future allotments from the state. TAX INCREMENT FINANCING FUNDS Considering all tax increment districts as a whole, cash on hand, increments above debt service, and loan repayments are sufficient to cover these projects. WATER FUND . Scveral large facility upgrades scheduled ham 1994 through 200 I wi 11 require rate increases periodically. In prior years an ample cash balance had heen nmtured in anticipation of the several needed projects. Now into the upgrade stage, a $.10 per 1,000 gallon, rate increase in 2000 was approved. The next anticipated rate increase will be in 2004 and 2008. These increases are necessary to maintain the planned projects and to payoff bonds that were issued to provide funding for the c.l.P. projects. SANITARY SEWER FUND The lo\v magnitude of capital needs over the next 5-year period will facilitate this fund in building its' working capital balance to offset allY unforeseen changes of charges from the Metropolitan Waste Control Commission. Those charges appear to have stabilized for the present. Further analysis of projected sc\ver projects and the associated rates prompted a rate decrease in 1999 from $2.50 per 1,000 gallons to $2.25 per 1,000 gallons. The ne\v rate is reflected in the projected operating income. Rb:FUSE FUND This fund continues to increase its \vorking capital balance each year. The purchase of a new refuse truck in 1999 will slightly decreased the working capital balance in 1999. This should be recouped in the following years as long as we continue to receive the $30,000 grant each year from Hennepin County. The volume base rate change in 1995 continues to reduce the operating protlts of past years. A rate change is not proposed at th is time. . STORM SEWER FUND The heavy construction over the past sevcral years necessitated a variable temporary interfund loan each year. The erp anticipates the continued pace of construction through 2001. The continLled need for projects each year pn:ventecl the fund from attaining a positive cash flow. The city implemented a storm sewer rate increase in 1l)98 of $.40 per residential equivalency factor. (REF). It became apparent that this \vas not going to be enough to cover the past projects and the future projects. lhe city implemented a rate swap between the Sanitary Sewer fund and the Storm Sewer fund thereby increasing the st(lrI11 sewer rate to $12.00 per ref up from $9.60. This rate adjustment had minimal affect on residents and businesses in the city. The rate change brought needed cash tlow to the Storm Se\ver fund and allowed the city to issue revenue bonds in 1l)C)9 to make this fund positive. The rate increase changes the total monthly charge for households to $4 per month lip from $3.20. No futmc rate changes arc perceived at this time. . ~ ~ z ~ ~ t"" ~ Cd ~ n ~ ~ >-~ ~ ~ 5. ~ 0 ~ ,g.,g. g.;><: 0 ao (D..... '-t (D (D $:: '-t..... CIl~ ::r. "0 () () e.(D'::r. 5 ~. ~ Jg oS. 8. 8. Q ~ Jg 5' ~~ (") ~ ~ ~ >-c:I>- 0 ~ (D,-... P:> ..... ;><:;><: '-t () .- \J ~ \ J '"S!. {I.l ()"d <.2. 8" '"S!. P:> '"Tj P:> ...... 1:1 (D (D (D p:> ...... <Jl =~ e. 0 <Jl 1:1 ~()- e. P" = ..... <Jl ~ ~o ~ ~'"Tj ~ - 0 ~ O~'-t ~ p:> - = 1:1 ~ $:: ~ _ (D _ ~ 0 ~ '"Tj '-t ~ 0'" ao p:> p:>:E ..... tD = (D ...... a ..... = _,..., = < = CIl P" =. = () g; I.<J ao '< ~ :;d ~ g >-< (D () 2 ~ ~ tI'J,.,..,~ (D (D_ e. p:> <~~ e; p:> p,; ~<: = = ~(D () () = (D (D = ~~ V1 >- >- ~ ~ N N -..l -..lN~ N ~ ~ = = ~ ~ ~ ~~~ ~ I,,() 8 8 I,,() I,,() N N I,,() N 00 W ~ <.2. (D (D oo~ ~ ~ 8 ~~~ ~ ~ og (Ij (Ij .......,.... ... .... "".... '" w 0 M ...... p:> ~~ ~ ~ ~ g~~ ~ 00 ~ ~ (D' I,,()-..l ~ 0 ~ I,,() wow N N ...... <: "d~ ~'< -G p:> cl P"..... <; s.:~ (D= Q ~g ~@ ~ N N -..l -..lW~ N ~ 00 ~p:> = ~ ~ ~ ~o~ ~ I,,() N 80 ~~ ao N N 00 00 ~ ~~I,,() N ~ 0 ...... ~ _ (") ~~ ~~ ~~ ~ ~~ ~o ~I,,() :-' ~~ ~....., 0 P"~ ~~ p:> w woo w wow w w - (D- ~""d w woo ~ ~NW W 00 ~~ ~~ ~ O~ ~ 0 0 0 OOON ~ N (D P 5' ~ e. ~ 0 ()..... ~ '-t 0 '-t = '" p:> 0 (D N ::::... -- ~o p:> N N -..l -..lW~ N N 8' g (D 0 = ~ ~ N N ':....l ~~000 ~I,,() ~ = CIl ..... - ~ N N 0 0 W W ~ -..l N I,,() N ~ (D = ~ _ ~~ ~~ ~o ~o ~oo ~OO~I,,()~OO ~~ ~~ g ~"d N~ N W woo ~ ~~oo W W N (DP:> o~ ~ W woo ~ ~I,,()~ W 00 ~ ~ 0..... W 0 ~ 0'1 0 0 - - ~ -..l ~ N .....;;;l ~ = - 5 (D 5' N C3 ..... a () 0 ~ = -0 ~~ =N ~ ~ ~ ~~~ ~ W ..... '-t ~ ~ I,,() I,,() - - I,,() 0 0 0 I,,() 0 ="0 ~N NNW W N ~~o N 0 No N= ~ ~ ~ ~ ~ ~ -OON ~ I,,() o~ r:t.o ~ ~ ~ " " ~~~ " ~ 0 o ..... ..... W WOO W W -..l VI W W W N~ (D= W woo ~ ~I,,()O'I W 00 . () >-c:IN O~ ~ 0 0 0 OOON ~ N :E = 0 o 2:0 ~ ...... w 12 () p:> ~ ~5. ~ ~ ~ 00 ~~~ ~ W o (p., I,,() I,,() I,,() - - - NO- I,,() ~ N '-t .~~ N N N N N - W-..l~ N 0 0 p:> ~~ ~ ~ ~ 0 0 I,,() I,,()OOO ~ N 0 ~ ~~ w W Woo 0 O':....lN W ~ ~ .- W W WOO - -NOO W ~ S' 8. 5' ~ 0 ~ ~ 0 0 N N ~ ~ ~ ~ ~. :::-: N :::-: q 0 ~ 0 ~ 00' N N 00 00 W ~ N ~ ~ ~ "~~ " W I,,() I,,() - - W ~ow I,,() ~ N N N N N - WI,,()~ N ~ 0 ~ ~ ~ ~ :-' ~~~ ~ ~ 0 ~ ~ g g ~ ~~~ ~ W ~ O~ ~ 0 0 ~ ~-~ ~ ~ >- <Jl <Jl = 8 (D CIl c::T = ~ ao ~ 5' () '-t (D p:> <Jl (D <Jl o H') W ~ 5' N o o - ~ ~ 5' N o o ~ - ~ ~ 5' N o o W g; ~ !V ~ ~ 5' N o o ~ (J ~ t;I(J 1?~g~.g' ~ el 0 g.~ ::l ~ ~ ? g 0 ;:r' ~ .....>-0 ~ tel [/1;" 0.. l'Il (tI :::s _. s' ~~~o..a S' ~ (JQ ~ a a ~ '" > (JQ ~ (J _.t..:::.. ,..,g_ Ro~ (J (l .g () (1) .g (1) ,.., (1) () ~a.::l ~~ g: o,..,1il' ~ '" e3' s g: ><: g~ [/1 0" (1) tel e'" g ~ a (1) '" ;:t> (1) III 8 i',l ~ (JQ (1) >-1 g' tTJ '" '" ~ ~ <: ::l ::l (1) S' 0.- vr E (JQ (1) ><: '" (1) III - - - \D W N -a Cx, 00 - NUl -.1 I~ .j:>. \D -.10000 -.1 Ul-.1 Ul 000 \D - - .j:>. 0\-.1 .j:>. 0-.1 UlO\ Ul - u-. \0 ~ \o~ Cx, "o':...1NCx,"o t \D 0 _O\Ul 0\0-.j:>.0\D w - _ - 0 0\000\01-'"'00 0\ "d ;..., - ...... ~ u-. 0'\ N l;J -.1 t::)-p- Ul w 0 00\-p- N Ul \D I~ ~ \D 00 w Ul Ul 00-.1 0 ...... N N 'ON u-. 'thb a .\D 0 00000 00 000 0 0 0\ 000 V'lOVlO 0 ...... tel Ul Q ~ ..... ~ N - - ...... ...... ...... () a N Cx, N u-. '" ...... - Ul I~ ...... 00 00000 0\ Ul 0\ Ul 0 ~ - -.1 0\ ...... 0 0 0 0 \D W \0 '" a'" w a w a N ...... -.1 000 0\ 0 0\ 0 0 N .j:>. 000 00 0 00 0 0\ 0 0 Ul N ...... N 0\ a l.JJ~ 0\ Ul a I~ N \DNO\ W 00 Ul 00 j--> w 00 Ul W W 0 ...... ...... ...... o~ N N a \0 Ul 000 -.1 -.1 0 -.1 W 000 \D 0 \D 0 .j:>. - ...... ...... ...... ...... .j:>. - ~ NN \0 ~ Ul 0\ I~ 0 0 \D 00 ...... -.10 N Ul N w Ul .j:>. w...... -.1 0 -.1 0 j--> Cx, N \0 "0\0 \0 a \0 a -.1 Ul 000 \DO \D 0 Ul Ul 0 000 -.1 0 -.1 0 w ...... ...... 0\ a .j:>. 0\ Ul Ul ...... I~ N ooNO\ \D .j:>. Ul 0 ...... w w 0 \D \D 0 Ul ':...1 N 'ON ':...1 ':...! a N 00 000 w w 0 Ul 0\ 000 0\ 0 0\ 0 0 .j:>. -.1 .j:>.w Ul Ul 0\ I~ 0 \D N-.1 00 w Ul N w \D w 0\ ...... ...... 0 ...... Cx, a "0"0 a a a ':...! -.1 0 00 00 00 0 00 Ul 0 00 \D 0 \D 0 0\ ...... -.1 \D .j:>. Ul W -.1 Ul .j:>. I~ \D w -N N Ul N Ul 0 ...... w wo .0 0 .0 0 w a a "0"0 ...... a ...... a Cx, 0\ 0 00 \D 0 'Ci 0 -.1 'Ci 0 00 .j:>. 0 .j:>. 0 Ul ...... w a Ul Ul Ul Ul -.1 I~ .j:>. NON 00 v) Ul \D -.1 'Ci 'Ci 0 Ul Ul 0 ...... .0\ a "0"0 u-. u-. a a 0\ 000 \D 'Ci 0 0\ -.1 000 00 0 00 0 \D ooWUl Ul Ul w I~ -.1 .j:>.NN 0\ - Ul .j:>. 0 Ul Ul 0 -.1 -.1 0 -.1 a a 0'0 .w W a '" Ul 0 00 00 00 0 0\ 0 0 00 w 0 w 0 -.1 ~ >-0(") ~CIl~ ~ S' ~ ::l ... 0 ct ~ 0 * ... !3 . C/J ~ (t) ~ ~ S' '1:l lit i4;P-!::. S' (JQ eft mQ;> aq (") !!5 > B 0:1 f? (") ~ III 0.. _. S' ~ S '1:l 0.. E S>-o (JQ 0.. <1l E .... ... en g m ~ 8. tl:i ::l (1) <1l <1l 0.. en 0 aq .... .... S' en S' (JQ ><: tl:i <1l III e; ~ 0 (1) J'0 10 ~ ~ 00 I~ eN Vl 0 0 -..l 0 -..l Vl Vl -..l ~ \0 00 '0 \0 00 ,j::. tv tv eN N 0, 0, -..l eN (j ~ J'0 ~ \{) ,j::. ~ I~ CIl Vl eN 00 0, eN eN 0 Vl -..l 0 ..., ~ '0 "tv 10 \0 ;p- eN 0 eN Vl ,j::. ..., ,j::. 0 00 0 0, t"J tl:i S III ~ 0 ~ ~ (1) tv ~ ,j::. \{) I~ ~ 0, \{) eN 0, Vl 1::2 ~ ~ eN 0, eN eN 00 00 w 00 ~ ~ Vl 0 -..l Vl eN ---- ,j::. 0 000 ,j::. tv 0 0 Vl .... ~ co u,,j::. tv I~ ~ Vl ,j::.Qo, 0, 00 Vl Q 0, ~ ~ ~ 'Oow 00 Vl Vl OQVl Vl ,j::. 0 o Q 0 ,j::. ~ ~ eN N tv 0, ,j::. ~ I~ Vl tv 0 -..l 0, ~ ~ 0 Vl Vl 0 Vl ,j::. W w 'O~ ~ 00 ",j::. -..l tv 00 tv Vl Vl 00 -..l o Q eN 0 0 ,j::. ~ ~ tv tv';..... ,j::. ~ I~ \{) tv tv Vl 0, tv 0, Vl 0 0, Vl 0 0-, '0'0 '0 w w \{) 00 ~ Vl tv eN 00 0, 0 -..l W 1010 ,j::. tv I~ Vl NO ~ 0, \{) ~ Vl 0 ,j::. 0, w '0'0 00 00 0-, -..l 00 eN Vl \{) 00 00 VlOO eN ,j::. tv tv ,j::. v> I~ 0 10 0 ~ 0, Vl 00 Vl 0 -..l ,j::. - 10 '0'0 V, w w \{) 00 0, Vl -..l -..l 00 \{) 0 00 ,j::. tv tv ,j::. ,j::. I~ 0, NO tv 0, 0 00 Vl 0 0 ,j::. 00 '0 '0'0 ~ w 10 0, 00 - Vl \{) - 00 Vl 0 -..l Vl 1010 ,j::. ,j::. I~ eN tvo tv 0\ 0\ 0 Vl 0 eN ,j::. 00 00 '0'0 ~ w "0 ~ 00 0 Vl 0\ Vl 00 eN 0 - l ~. ~~~~'"'"'"l ~ t:;;IoS"'oo (') tl:l >- ~ g.st-<~~ ~ 0 p. ~zn:g~~~ft 0 :::l P. 0 * f"I- (tl g -.-. p. >-rj * VlVlVl""""""""es 5' ..., .... S s ::l 4i 5' 0-- a ~~t-l.f-'~I--'Ot'Jl (JQ Q t""" 0 ~ (JQ . . . . . . . ...-+ 0 S U1.f.>.lHN-OOOO 0 g..~g n 0 <:::><:::><:::>OOVlVl ~ (1l 0 ~ ~~~ ~ (1l p. 't:l g: (JQ f/> ~ g: (1l ~ ~ tl:l tn o' :::l 0 (1l p. ~ :::l (JQ 5' f/> 5' (JQ ~ ,-., :::l >-< ~ 5' (1l (JQ ~ ~ >-< >-< a (1l [J:J l>> '-' ..., Vl --l W \D I~ Vl 10 .f.>. 10 - w 0 0\ 0 . ,-., '0 V. V. >-' Vl W >-' --l\D - 00 0\ W 0\ --l 0 0 00 10 ~ ~ ~ --l - N Vl t'j ;:; - -.I Vl I~ ~ _ 10 - lH - ~ N 't.h~ ~ e:,., - "",., Vl Vl 0 <:::> - --l 00 >-' 0 >-' 00 w :-Fl 0_ ;g~ ~ w - --l ~ i~ \D NN --l Vl - - vO\ \D j-J '0 ~N >-' ~ N Vl w _ .j>. >-' Cl' 0\ ~.j>. 0 W \D -.I ~~ Vl - 10 .j>. ~~ >-' ,-., Vl Vl 10 \D I~ ~C"l \D vVl W - 00 - \0 >-' e:,., VO\ \0 '0 ;1(') - \D 10 Vl W Vl z~ 10 -.I - \D \D 0\ ~ 0,., ~n~ - >-' - >-"d (/l~ '" >-' \0 lH Vl I~ tno .j>. \D \D lH - 0\ v\D Vl Vl UI \D t;J ~ >-' '0 '0 e:,., \0 \D 0 0 0 00 - (') w 0 0 0 .... 10 ,., - tl:l 0 l>> Z ~ >-' n w '" (1l --l 10 \D I~ - Vl w 10 w 0 .j>. 10 00 0 - Vl 0 0\ -- '" \0 \0 '0 '0 ~ w >-' --l 0 0 0 \D >-' N .j>. \D 00 0 0 w 0 0 Vl Vl 10 10 10 --l I~ 10 0 -10 --l --l Vl - >-' o Vl Vl Vl 00 >-' ~ 'O~ '0 '0 '" \D - 00 0 0 ~ \D Vl 00 0 0 w .j>. 10 - 10 Vl I~ ~ 10 0 - >-' 10 Vl 10 \D W 10 00 Vl 0 - W \0 N '0'0 '0 '0 - 00 00 - 00 0 0 \D .j>. .j>. Vl 00 0 0 \D f.I'l - W 10 - lH .j>. I~ 0 --l 0 _ Vl 0 .... 10 '"0 - 10 00 0 <:::> w V. W '0'0 '0 b \0 tn \D 00 00 0 <:::> 00 :;0 \D Vl 00 0 0 ~ ,; .::.::~, . ~ >--3 ~ ~ M ~ i:d ~ , ~ ~ ~ (") ?;; ~ ~ ~ [;l (") :::l o z ~~~~~~; ~ OS"\J\J\J>-l ~ ::;:J ....\O\O\Oooooft e-<~~ i:d~ 0 t-4\C)Wl--"'\OW ~ (1) @ _. _. 0- ~ f.l';V'V'f.I';f.I';V'g:; '"'....S'S' en "rj S' 0--- ~ a s' !"'!"!"!"~~~ (Jq ~ t-<O V1 i3 (Jq UlNVlO-.)VlO \J (1) -= 0 \J OVlOOVlO ~ ~ .... 0 -E. en - -= 2- g: (1)~ .... '0 (1) [ '"' (1) ~ ~ I:T1 o' I:l:I t:l (1) 0- t:l Qq '0 S' en [l' I ~. (Jq ,-.., g. >-<: s' s' (1) ~ Qq en ej >-<: s- a (1) '"'l ej = 0 '" ~ (1) '"'l - - v, ." N j 00 ." - 0 Vl W 0 -.) ." ~ " ,-.., '0 1.0 ~ 0\'" 00 NN Vl W 0 0 l/)..:!; - 0 0 - - '" ,-.., W \j> V, I~ N - N -.) 00 W W N ." - l/) '" ~';- 1.0 "---l ~ ." 00'" - W 00 00 l/)S 0\ \0 0 - - W 0\ W '" I~ ." N 0 W N - N W N ." \0 W 1.0 w~ w w v, '" \0 l/) -.) ." \0 l/) ." ." ." \0 00 l/) 0\ 00 - - "." N W ." _\0-.) 00 ." I~ l/) - l/) 0 l/) W - ~ 00 1.0'01.0 v, 1.0 N 0\ -.)l/)O\ l/) \0 - 0- O\NW -.) ." - -." N t I~ o -.) 0 00 0\ l/) '0'0 v, ~ 00 W N 00 - - - - '0 I~ - -.) \0 00 o l/) N - '0'0 '0 1.0 00 0 l/) 00 0 N - - - I~ .,,--.) 00 00 ooou, N 00 '0'0'0 '0 1.0 000 0 u, 000 0 N ..... - "N I~ .,,--.) 0\ W 00l/) N -.) '0'0'0 '0 1.0 000 0 l/) 000 0 N ..... :;;:: N I~ "'00-') -.) O-l/) N .j:>. 'O~'O '0 1.0 000 0 u, 000 0 N - '0 00 - 1.0 l/) N - - 00 00 1.0 l/) N - N w -.) 1.0 l/) N - N -.) ." 1.0 l/) N - N N o "u, u, N I:l:I ~ ~ () (1) N w - ~ o o ." - N N o V, l/) N r: ::~<:' ~~~I ~ ..... 00...., ~Cl> ~ ~ ~ ~ .... 1.01.000* 0 ~.~. ~ .... 0.. 0 Vl-I.O ~ (1) (1) g; 0.. .... VH>,HT> a; S e.e!.~ .... Iii "Ii ;0;- d S' jooool. ;-l ...... C/) ()Q ~ l:""'O.... ()Q I-l-.lVl...... S . . . 0 n (1) t:: 0 n ON,.... <:> ?VlO ~ ::T ~ t:!. a ....., 0 ~ - ::,.. g; 0'(1)~ 0 "0 ~. g (1) '"" -P- eo. ~ g .... eo. ~ tr1 lZl i'l. tll Vl ::l c:: 0 o' (1) 0.. ~ ::l ()Q V> V> S' (1) g' (Jq V> (1) I V> ,.-..., >-<: S' s' (1) ~ ()Q ~ ...... >-<: a (1) 0 ~ 0\ Vl I~ N 0\ W w 0\ Vl Vl -P- -P- -P- ,.... w 0 N N \0 \0 0, '0,"" W 0 0 00 00 t 00 0\ -P- N ,.... w w O-P- 0 0\ ,.-..., 0\ I~ ~ -P- ,.... w,.... N N -.l O-P- Vl ~ '"" N '0 ~\oO N - ,.... I.O-.lVlW 0 00 N W 0 0 -.lI.ON-P- N t"l '-' ~ 0\ 0\ I 1.0 ,.... O-.l 0\ W W -P- ~ ~ N - 00 -.l 00\ N ~ '0 ~ 0,':...1 N ~'tn '"" 0 ~ ,.... 0 ,.... 00 00 -.l ,.... ;::; ~ -.l ,.... woo 0\ W W c:i n Vl ,.... ,.... 0\ ij ~ 00 0\ 0\ 0\ W W 1.0 .-.l 1.0 1.0 -P- O-P- N 0 \0 \0 0, ,",,'0 ~ ~ W 00 00 ,.... O\-P- ,.... ~ 1.0 00 00 W 1.0 -P- -P- I"t1 ~ fij 0\ Vl I~ ("j W ,.... ,.... 0\ W W 00 00 0 0 ,.... 0"'" -.l ...., '0 '0 '0 '0 .0'0 '0 (5 W 0 0 0 00 W 1.0 0 0 0 00 1.0 Z tll eo. ~ (1) 0\ 0\ I~ ,.... Vl ,.... ,.... N N W N 0\ 0 0 00 00 00 -- .0 '0 '0 '0 '0 '0 W - W 0 0 0 0 W i:> 1.0 0 0 0 0 1.0 0 0 -P- 0\ 0\ I~ 0\ N,.... ,.... N N Vl - 0 00 Vl Vl 0\ '0 '0 '0'0 '0 '0 '0 W 000 0 0 W 1.0 000 0 0 1.0 0\ 0\ 0\ I~ 0\ 0\ N,.... - N N 0\ N W 0 00 N N ,.... '0 '0 '0 '0'0 '0 '0 '0 W W 000 0 0 W 1.0 1.0 000 0 0 1.0 0\ 0\ I~ 0\ N,....,.... ,.... ,.... 0\ N 0 00 1.0 1.0 W .0 '0 '0'0 '0 '0 '0 w 000 0 0 W 1.0 000 0 0 1.0 :!:~.. :E nnn'-H:::It! Qto>-l> :E 0 ~.g.g;;Jg.g. ~g~8: 0 .., E'f s' ~ .... .... .., ?; ""1o..VJI-rj ?; S' --~~~ "t)(t>'"1 S' OQ ro"'~~ (3 ""i 0 (JQ n ~ >::: 0 ~.~. n 8" S n .g (J) ::!. ~ ~ g ~ 0 .g "'~ '~"- 0.. "Cl g: r/> '" g: \0 00 ~ \0 \0 ~ toto o' to 0 0 ::; (> 0.. ::; ::; r/> (JQ S' 0.. 0.. I g' (JQ r/> r/> "'"' -< ?::>?::> S' S' '" rr~ ~ (JQ "l >-< -< ~ '" "l N "'"' 10 10 ,p" V> ~ 10 -.I w W 0 ,p" V> 00 00 0 \0 OQ \.0 w 00 w 00 \.0 \0 00 w ~ w 10 w 0 0 00 000""' ~ '-' '-' rJi >-3 ,-., 0 ,-., ~ 10 ~ 10 w 10 ~ -.I ,p" 00 00 w \0 00 ~ ~ 0 ~ N ~ N \.0 rJi 00 0\ ,p" 10 \0 i"'j Vl 00 00 -.I 0 w w ~ '-' '-' i"'j :;d ,-., \0 ~ 10 O\,p" N ~ Vl I~ -.I 0\ w w o V> 00 V> -.I V> \0 00\ \0 00 \.0 w 00 'O':...J ~ I 10 10 0 -.I o Vl 00 ~ ~ ,p" o ~ 0 0010 ,E) 0 >-< ,-., ~ 0\ V> 10 V. Ul V> I~ 0 \0 10 ~ w 0 Ul OQ ,p" \0 00\ 00 ",p" Q\ 0 n ':...J w ~':..... ':...J ~ 1-.1 00 ?; -.I 0 ~ .j:>. V> 00 N 10 0 10 10 \0 0 V> -.I \0 '-' ~ r ~ ""' 10 ~N 0\ 0\ ,~ 0 0\ W >-< N.j:>. 0 -.I ;;; 10 0 Vl 10 ~ 0 ~ v. a \.oN v. V. ~ 00 0 0 w 10 Vl 00 0 0 0 o Vl 0 V> >-3 >-< to 0 Pl :z ~ n (> 0\ 10 >-< 10 V> 0\ I~ i:::> 10 w >-< w,p" \0 0\ ,p" ,p" 0 00 V> 0 10 i:;) w v. a ~':...... a ~ ~ 00 0 0 W-.l 0 OQ N 0 0 0 00 0 0 0 0 Vl 0\ >-< ~N Vl 0\ I~ 10 -.110>-< ,p"w 00 10 0\ 000 o -.I 0 ,p" w '0'0'0 ~v. a w -.I 000 \O~ 0 00 00 000 w 0 0 0 -.I 0\ ~ ~N V> 0\ I~ V> -.J ~ 10 ~ ,p" w -.I 10 00 \0 000 NV> 0 ""' ':...J a '0'0'0 w'O a w ~ 10 000 ~ w 0 -.I 0 00 000 Vl Vl 0 00 -.I ~ >-<10 Vl 0\ I~ 10 ~ 10 ~ w,p" 0\ -.I 10 000 00 10 Vl \0 \.0 '0'0'0 '\.0:"'- a a w 000 \00 0 10 w 000 V> 0 0 00 ~::O::O::O::O::O::O1 l-l\O\O\O\O\Ooo~ """'" \0 00 w to ...... \0 ~" VlVlVlVlVlVlVlts \0""" \0\0-.) O\.p.. rn e:,.,~O\Ov,o~8" oooooov> "l 0 ~ '" ~ '" "d ~. .. =- ~ ""I .,\ ':'(", . . . SUMMARY OF IMPACTS OF ISSUEING HOUSING REHAB BONDS FOR THE PUBLIC WORKS FACILITY Funding of the Public Works Facility addition started with consideration of two different types of bond issues. We looked at a GO Referendum issue and determined that this bonding source would result in residents paying approximately $10 more a year in taxes than if we issued HRA Lease Bonds, (the original analysis is included). Finance has included a final analysis of the impact of issuing HRA bonds for the public works facility expansion. There are many variables in the assumptions being made for this analysis. Please review the attachments with the notion that these numbers are not concrete. The bottom line dollar impact for a home valued at $120,000 is $7 a year. The additional costs to the utility funds has been incorporated into the cash flow projections and can be absorbed by all utilities, (see the elP summaries). . . . ;;... t"" t"" ~ e ~ r:F'1 I ,.-,. ..... = !':I - = Q. ('tl ~ '"d = g; !':I ~ o ., ~ ~ ~ c. q ~ = Q. '"d c 0- - ;:;:. r:n ~ ;" q ~ ~ ~ q ::0 ('tl = o < ~ .... 0" = '-' := ..... r:n t-3 o ~ ~(j (j ~ Z t-3 ~ '"d ::0 o ~ (j t-3 M t; t-3 ~ t"" M ;:l M r:n ;;... ~ (j ..... t-3 ~ t-3 ~ ~ t-3 M r:n *** - - - - - - N N tv tv N I~~ ** ~ ~ ~ ~ ~ ~ 0 0 0 0 0 ~~ * ~ ~ ~ ~ ~ ~ 0 0 0 0 0 Pl< ~>-:I>-:I ~ ~ ~ ~ 00 ~ 0 _ tv W ~ ~~ rn~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~ <~~ ~ ~ ~ ~ ~ 0 0 0 0 0 0 ~ ~ ~ ~ ~ 00 ~ 0 - tv W ~ ~ Pl ..... g n ~ ~ ...... Pl ... ~~"O ro ~ ~.~ ~ >-:I ~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ ~..... ~ - - - W ~ 00 - w ~ ~ @Pl O"ro~ ~ - ~ ~ 00 ~ ~ 00 0 ~ ~ - ~Q.Pl w ~ 00 ~ tv ~ 0 ~ 00 ~ w n~ "Tj~~ ~ 0 00 - ~ ~ ~ N ~ ~ 0 @~ _. ro 0 0 0 00 ~ .jO. - ~ ~ ~ w 0.. "'" ~Q.n 0 0 0 .jO. 0 ~ 0 ~ 0 ~ tv ~~ o ~o-'a m O~'"O ...... r-n c ~ - ~ ......... l---' .......... I---" I---" ........-L I--'--' 10--1 m [Ii' it N ~J .vJ - - .!'J .!'J .W w .~ .~ I _ in~ ~ ~ - ~ ~ ~ ~ 0 ~ - ~ Pl ~ .....~o 00 0 ~ w ~ ~ ~ 00 N 00 ~ ~ ;:;: = - tv ~ ~ ~ ~ -.j ~ w 0 ~ Pl;;;' {'D' 9 .~o - -.j w ~ 0 ~ 0 N -0\ !::. ~ mm 0 00 tv ~ 0 N - 00 ~ - tv - ~'"O 0\ - w t-J tv ~ W ~ vJ 0 ~ -.Pl m ..... - _. ..... .... a-: {'D' em tv WNW W W w ~ ~ ~ ~ g. 8 ~:.... ~ 'w '~ ~ \.0 N 'L> .~ ~ =g ~ 8 ~ ~ ~ ~ N g ~ ~ ~ Pl ..... . . ,....., =~ ~ -.j tv 0 ~ ~ ~ ~ ~ ~ - ~J u W 0 tv _ 00 w 0 ~ w ~ ~ ro Q.g W N ~ ~ w 00 - 00 ~ tv.jO. = $: _. ro o ..... = ~ nPl "Tj ;J;. = e ~Q. ::s ~>-:I tv tv tv tv tv tv w w w w W ~ oPl tv ~ tv ~ ~ ~ - tv - - - 3;><: ~ 0 0 ~ ~ ~ - - ~ ~ ~ ~- tv 0\ ~ ~ w ~ w 0 ~ - 0 m= ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 000 ~ ~ ~ ~ ~ ~ ~ ~ [8 >~ Pl g >-+> = .... -. ~_ ~ ~ ~ w w W w w w ~ ~ ~~o ~'j -.j -.j W W W W W W W ~.jO. ~ ...... :;' w 00 ~ 0 0 0 0 0 0 0 0 n g.. onQe ~ ~ ~ 0 0 0 0 0 0 0 0 @~ro_ ~ .jO. -.j 0\ 0 000 0 0 0 0 Q. @!::. -.j ~ woo 0 0 0 0 0 0 ~ ~= m _.00 ~o [Ii' q w W w w W ~ ~ ~ ~ ~ ~ 0" ~ ~ ~ 0, 000 N ~ ~ - '1'0 - - 00 ~ w - tv .jO. tv ~ 0 00 ~ 0 tv ~ ~ - tv tv W 0 _ _ W N ~ 0 ~ ~ ~ ~ ~ ~ :.... 00 -.j 00 - 00 W 0 0\ W 0\ ~ o 0\ ~ 0\ W 00 - 00 ~ tv ~ >-:I o - ~ ~ tv tv tv w w w w w w W W Pl ~ 00 ~ 0 tv tv W ~ ~ ~ ~ ~~ ~ ~ ~ ~ t ~ ~ ~ g ~ ~ *~ ~ ~ ~ ~ ~ ~ ,0 ,= ,= ,= ,= -. o Q = 0 0 0 ~ ~ ~ ~ ~ q ~ ~ 0 ~ ~ ~ ~ N ~ N ~ N W ~ N 0 0 0 ~ ~ o ~ 0 w ~ = = = ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ S' S' S" S' S' S' S' S' S' S' n n !':I !':I n n n n !':I n ., ., ., ., ., ., ., ., ., ., ('tl ('tl ('tl ('tl ('tl ~ ~ ('tl ~ ('tl ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ('tl ~ ~ ~ ~ ('tl ~ ....~ _. _. )11ooI. ...... ...... ..... ...... _. _. = = = = = = = = = = - - ~ - - ~ ~ - - - ~ ('tl ('tl ~ ~ ('tl ('tl ('tl ('tl ('tl ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ > t"" l""" io!"j L: ::z I;;j rjj ! - t"'l ~ 2- c Q., ~ en '"':I e g: _. ~ ~ o ""l ~ en 'Tj ~ ~ ,~. ;:.;, :::l Q., 'i;l c 2: (;' 'JJ ~ ;;> ..... '-e. io!"j ~ a: ,~. ::c ~ :::l o ~ ;:.;, ..... o' :::I ~ .... rjj >-3 o z; n ;;;.. 2 o (j ~ ':2 -l -l > ~ l' ITJ -< .... M [fJ ;:,.... 2: o n .... .., -< .., ;:..- X ~ -l t""I rjj _ _ ,..... - - ,..... 1 J 1 J 1 J I J t J 1-< r ~ ~ ~ ~ ~ ~ 0 0 0 0 0 ro~ ~ ~ ~ ~ ~ ~ 0 0 0 0 0 "'~ ..... VI 0-, -..l 00 '-0 0 ~ 1 J '-'J ..... ...., '.- __ __ ___ "'--, -.., ~__ "--....... -.. ___ ___ ----..... (.IJ--.....:.... ~ ~ ~ ~ -0 0 0 0 coo v Vl 0-, -.J 00 ~ '0 ~ 1 J l.,J -I"- v' ~ '.... .:; CO (j1 -l ~ Vl Ul ~ ~ VI ~I ~ ~ ~ ~ ~~ \0 .......... --" --- t.....J c-.. ~ .- t J v..J 'Jl ~ ~ v~ _ ~ ~ ~ ~ ~ - ~J ~ ~ - VJ -..l 00 -I"- IJ +-- 0 v, 00 0-, ~ n r 0., 0 00:"'" 0-, - -.J i J '-c, "" :..... ri ro o 0 0 00 ~ +-- - ~ Vl -..l 00 ~< o 0 0 ./>0. 0 +-- 0 'J, 0 ..... IJ ::::;: ,< 'J] - ~ - - - ~ - - ~ - .......... tJ 1J VJ ;- >- !J JJ '",J VJ +-- .j::.. (. ' ~ ~ ,..... '-0 -.J .L. 'JI 0 0-, - -.J '" ::;: ~ S ~ ~ ~ 8. ~ ~ ~ ~ ~ ~~ '..1 ... ~ c,I ~ ~ ,~ {') ~ .j::.. 0 - -..l v) v, 0 Ul 0 IJ 0\ -. ~ o 00 t....l .j::. 0 I J ~ 00 ,~ - tJ ....,. 0\ - W tJ IJ -.J VJ +-- vJ 0 -0 ? l....l '-'J l....l '-'J VJ v) VJ +-- +-- ..... ..... ;::p \0 ~ \.0 w +- 0\ \0 - t....l GJ 'Jl ~ 8 woo 0 00 ~ - w +-- ~ -..l ~ 0\ W 00 v. - IJ IJ 0 -..l 00 ..... n ~ -.J t...) 0 V"I .~ IJl ~ Vl ~JI ;....J @ C1l (J W 0 tJ _ 00 vJ 0 0'\ '...J 0\ 0 0.. ,< () vJ tJ +- 0-, vJ 00 ~ 00 ',0 I J +- ;:::" -< ~ Vl ...., :>0 PJ ~ ;;o~5 t....l N t....l t....l I .J I J '-'J '-'J i..-J VJ v) :::. 0.. N ..... N -..l ~ \0 - - ~ - ~ n~ . -0 ~ 0 0 ~ ~ ~Jl - ~ ~ 0 c ~ IJ 0\ .+.,;;.. \0 lJ.,) ~Jl \...oJ -..j 00 t-..) C 7r rJ ~ ~ ~ ~ ~ ~ ~ ~ ? ~ ~ ,~ Vl Vl -..l W W W w w w w w ~l;o ~ ~ ~~ ~J ~ W ~J W W I~ ~ ' VJ 00 '-D 0 0 000 0 0 0 n, g.. ~ Vl "" 0 0 0 0 6 ~ b 0 ~~....,. ~ ~ 8 g g g g g g g g ~~ ....,. C/l )> W W W W w +- +-- +-- +- ~ .j::.. = , ,. ,n Vl 0\ 0\ 0\ 00 0 IJ .jC. v, -..l '-D ...., ,..... 00 +- w ~ I,) .j.o. 0- -..l IJ 0 n o tJ -.J Vl ~ I J I,) 0 -..l 00 .jC. ...., --'w t-J 00 0' Vl ..+-:.- ~JI ~ ~Jl Vl 0j ('D ~ 00 -..l 00 - 00 w 0 0\ wo-,o 0.. ~ o 0\ -.J 0-. W 00 ~ 00 '-0 l....l ..... ;:::" S C/l ::... ;;0 tJ- t..J- t..J l..I..I v.J r......J t......J ......-J t......J v-J v..) PJ -..l 00 -.J ? ~....l 1 J '-') .j::. W VJ vJ FD'.g o Vl 0- +- +- - -.J 0 0\ VJ t....l * '" .j::. +- Vl Vl +- \0 0- \0 0 Vl W n ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 0 ~ ~ ~ ~ N N N ~ N ~ ~ ~ b ~ b ~ ~ o ~ 0 ~ ~ 0 ~ N ~ ~ ~ ~ ~ ~ ~ ~ t ~ ~ ~ S' S' ci" :r S' = == ::: S' SO ~ ~ n ~ n ~ ~ ~ ~ ~ ~ ""l ""l ~ ""l ~ ~ ~ ""l ""l ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 00 w ~ ~ 00 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ --. """,. _. _. jdII. -, -. = = = = = = = = :::l = ~ ~ ~ ~ ~ ro ~ ro rn ~ ~ .o:! ~ ~ "" .... .... .,. .o:! .o:! ~ ,~ ~ '-e. ...;: '--<'. <-e. ''': ...,: ~ 1(- -)i. * * * r>-J>-J ~ ~ ~ '<on ...., .., '" n"d v 0.."'", j:::; 0 0 rJ .............. ro ..:;t .<1' ~....,.;., o-ror- ~~ ~ a "TJ;:)ro -'f!> n ~ 0..0 ::"0-3 '<-0 9.~s. C/l '" .., v (") ::;. '" .., 0 ...., -- 2-: 0 -' (]J _, '" '" 0..:0 -.'" '" .., q a: --f!> ;2"", ~() -'0 o _ = ;::::. '" ::!- = u ~j:::; :r::g- ;1>= n.., ?s. -......., :I.", g ~ -' - (j1 ::: 'J] (") "-+...., (]J (]J '" - 0..::::1 '" !:! = ;::::. o..-rj ;. -. ITCI = e: n;=; ...., _. f!> = Cl...UQ ~9 C/l ....,. ::!- (") ....,. '" . . . . . . tz ~ ~ <::S: tJ ~ ~ --l e..~o t.J ."-.J ~ f5@8 00 lJ1 0" -r-t- Vl - -.J "" t.J;;P"'" n " "" "" 8';;3 ~;:r L-J 00 .+:-.- t-----'V(':)'-< _ 00 ~cn --- IJ 0'-. "" ~ 'J .... ~ ~ 0 N ~ VJ V7 Clflls'o P ~ !- (J~ e::= ~ Ul)..-( ~ 04 0 N >< n '" I" ........ .......... ......... g- ,-0 ~ 0 -0 0 ......... :::l 0....... Y 0 t-J ~ W (Jl:l "......... ~ ~ ~ (11 ~ t;.q ~ t-> - ..... '<' -.......J 00 t.J --"';-00, to :::0 +- _ g.~o ITI V. \0 1-> i= ~ := '~ Vl C'I 0 0\ ~~ c;-~ 0.0 t'J 00 '" 0 c tTl 3 Z ~ ~ -1 "" t" "' ...., n cr t;;: . "" ~ 8 B ~;:r S. F< L-.J \Xl Vi r.JU~~ aq~ \..Q ~ t.J (b I.IJ ('D ~~ v~ -..) - ,....,. ~ 5' ;::; (j ~ @ :s: or ON ~~ Vl ~ Vl ~""s.g <1>r;j --I +- N iI'Q orN "'0 ~ ~ ~ ~ q ~~ ~;;o ~O >< . '-d n <1> -...... ::T "' t-> tJ ~ ::" ::" ;-l ~~qg ~...., +- -.J 10 (JQ t'.J 0 >< t:. ~ 'cF.. (I; ---...., ~~ -, >-< ~ "" "" ::;~ N - - <::S: t.J t.J g :t: .~ ~ ~ e; 8 8 > ....... lJ "v-. ~ @ t...) fJ n -...l Q\........ r-+ ............, \,0 \D W . en Vl ~' _ ~. S ~ ::; n ~ ~ ~ ~ n t.J 2" ~ ~ ~ 8~t)q' g~ to..) \0 L....i _"-'l vJ \0 O.....j ro ~~ ::; n 0. -. Q 3: !.J~' ~ 0 N W V:3 VJ {A =Vjs.g ~3 ~ ~ ~ ~ =:: f.H -. "0 .......:. '.D tH "< ::I..., 1.,0 N Ul r.J 0 o < 0<1> >< .,. :3 Q <1> N g ~ e; .-+ ~'.,) ~..J 1...J ~ ';t.. ~ g V'J .+:;.. --J a~ w -;;. ~ ';fl (Tl "" "" "" tE ::Q t.J <::S: t" ~~ ~ :.0 ::.!;8 ........ 00 \.D t::~L,...J t-J lr1 0 {T;l!l 0\ DO 0\ "0 "" 10 "' ...., n " "" "" 0';;3 ~ -. '-" 0.0 '-" ~0"<1>q- 0\ -."l \0 -"" 00 -...0 L,.J (l rJ a:: "" =" 0 N _ "" "" g;~I:lQ ; t t (f~ e:~ ... 04 0 '-<: I >< 9 (l) t-J 0.0 0 0 .,,,,,e;o 00 c ~ Jg c, t=! ~ ~r:. ~ ~ (1) >>> Vl Vl CIl ~~~ C/l C/l C/l >>> w ~.,. i...!i...r,u. **"cf:. zzz rJrJrJ ~~6l >>> C/lC/lC/l tTltTllTI ZZZ ~~~ ....,....,...., <<< f:~~ 5i~~ '"1"1"'''' ;;0;;0;;0 000 :S::S::S: t-J N l'-J 000 000 ('J ___ .0 ....,....,...., 000 N tv tJ 000 000 W N- ~ !:l ::l. '-<: ~ "t:I "t:I ei" I: I: 'CI C"O"~ -=-=~ ;:;" t":l ~ ~~~ ...., 0 or '" .. 0 q ~ 8 ..,..,,,, O. a. a ==:=-:= qq~ ...... , ~ 8 .... ... 'CI -l.... a - < ~ '" <;, 8 0 ~ Q on "" ~ o ~~ ~ fh 7' 0\ .....j _ < - IJ Ul 1J~ --.j u =i C 't---l ~ :-. E" ~ ': :;.c IJl a- ('D!3....... Vl - --J . I.,) ~ -1 ~ C'~ ~ IJ , iA i7:t ::::: eo; ;.-: - IJJ 00 +- _ 0"' l~ ''2 _ ::.0 - '.J'. >-----" t-.l C- ~ Q ~ t.Fr f.A I.I'l 6V1;~ C Q\ .... 1~ g. 0 i: ~ ~ ~ ,~- ...c' r., n' r;.. LJ ? ~ -- ~ ~Q.7 g t J O. L..-J fJ=;' q 0----0 .0 0 (l;. o o. o. v. &:t &S ~ ~ I-J < ~ l-.l f- ;-' ~ ~~5 l..n >..0 1..1 (D ~ -' ". ~ s:: 0 ';:'\ i-.- :: >:: '""' tJ ;:..::: ~ .~ ~ v ""::l ~ :T 7:r 23~ ;1~1 ~~ b-':" if.: 0 ~ ;...;;::. := ~ '....J :x VI I.,) cr- ([J '-<:, e- > oJ :~~:Z: 0" c.r. r2. - ......, rr1 ~ JJ t'l ~ q :j t:1 o~~ 8;7 fA v: !/J =VJ~Q ~; lJl v... t....,l II)';: ;:r Q Vl-l :... rjl ~ \'tl I:;:'" -.... 0 T1 N +0.- N l"'""f""', -: '...."J v ~ "tl ...c' ?:;::J g g' I..J ::;" .:: ~. ~J~ :Jl 5 ~ ~.3--:8 ~. ~ q tJ ~ rJ2 .~.,) ~ ~ o~ 0' o~. - :; ',....J- ., o _ -. ;:... 'iT. 7'! 'iT. ::lX ~ :;:;; I.) -::. ~ 1-' ~:;;: f-?C:-..11 :=.E;g ,~....... _I ~~ ~ g 8 t J ! J ;: ~ ..0 t.I-I .....,. :-" rJ :~ j c IJ J ~ ;::l z ~ a ~ ;::.J) (} 1.),-- '_ &<'i ~ 0 ~ ~ -. 0-' +- ;'Q VI wvftrQ c~ ;; ~ '=: n-:.r. ~.J:=; "" :::..: ;::l ;::.' P- ," 9 ~ IJ- ~ C l~ c...):3 <.A Vi ~ = f.A -= 0 -0"'0 ~ ~ ~ 1": ;. e ~. a --...... ~ w '... Y = < \0 N rJl . I-.J g C ~ 00 K" .. :J '"' < - ~ . J (t Vl ~ t...J t..J t.J l...-.J E5;9. l7 g "'-...J - rjC; ~ I...... .0 _0 '.~ l,; .;;," 0' 0 &S f:::h ~ t~ .~ 1.0 <:;:1.0 ,..f:- ,+:- ,.0 S- ~ g C<l 1..0 _;::r;- W t..J Vl C ~!l ....\ 09 ~ "" I.) J -I ~ V; ~ g~~2 t .0 ::;: .p~~'<: o 1..J 1...,.J (I;; n '< =- - .. 0 t.... ~ i1 ~ ;VJag N Co Co J~ ==.... l'...,o..I N'~ '< I) -< ~ l-J ;--J r-J~ 7- ~ o~,~ g ?-; ~ '--'~ rJ~ -<: +- " 0 ::">:J.- U) ~. U) J'l (I)~. <"""r- f::::~ tTlMH U) ~. ~ > > p. I....j I...."" +--- '.I, '...J' 'JL o ",0 ...~ o~ 0 o' 7.ZZ rjnn ~fgA :J.- :J.- p. [/J (I) (/J t'MmM ZZZ ~~~ ;:O:;?:l?:l r::r.", "'7j :"1:, ;-n .......,-....; <<:< >>> r'e'r' r~~ M::Jm '7]"':1"T1 "':::::1:::0 000 '77<' ......, ......, ...... t J t-.l t-.l <00<0 <0 ='<0 t.J -- 0 -'-Io-J I:;' :) 0 l-.J 1-.l t-.l <0 ='<0 C ='<0 I......) r-J ........ .~, e . . . . . :::; "" "" <;;: 1-.1 ~ ~ Lj ~~g 0\ 00 \0 (lJl1JO G.J i...;""" l-.J 0\ 0-.. - 0 .... i;A "0 ::::; ~ n i:5'~ P.' n 1,.Jw I,..) := & ;;; <1' l~ G\ +:. ro-[/] ~.Jl 0 0 i'"l :::: VJ f.I'.l VJ g- g~ ~ t :;; ~V)~;= . . . It> - N ..... 0 ~ .j;. .... 00 -< - 9 _.Q ~ ~ '.{) 0 0 E: 0' <'Z 0 00 0 ~ IJQ ...... 'o~ ~? ;/ (il n o "" 7;;: . "" "" < _ '-J ~ t.J 0'1 t.J ~ E; 0 rn ~ '-D ~ 2"':A~ /V I 0 ~ r?Q. n '..0 \0 u.l ;:c..t; tJ 0\ 00 ~ ~ 3 Ro ~ ~ fh l-J J' '"""":J [I; Z ,.0:..0 J0 0 ';,3 ~ 0. g" I::J o -.] w fj<:r",.:;t o.C: u-J VI '...0 rr~ OQVJ lJ) 00 I.J ~ ...., ,'i" c: n:::: q > "" "" "" if g~ ~r-< 0\ lH )0.-0. =:IV3_0 1l.B5 ~ ~ N O'Q C" N VI . ~ N e.. ~ ~ 0"""'1 C'\ N 00 ....... Z ~i ;; -< .0'- -; n ",.0 5' tT1 ;:r 0 E; 0 I::J 0"l0'l 0\ ba:qo ~'"'O w ~ OCr h) o?:l '#- t:. '0':': tV ~ 0 ,,> "0 ~~ ~ 5' -; "" 'J -< . "" Vl < 3:: \'-J 8 -; 1-.1 '" l.o OJ E; 0 I-J > _~ _~~ ~~ ~@1'3 ~~ lJl ---l VJ ...... rJ~ ~ I..J 0\ 0 ....~ 'D ..p.. 0\ Q" -, > " n i;A "0 2:-; ....... ~ &3- I.J ~ ....., 0 [IJ +:-. Oi I'-J 0 '-< ~ D. ....J I 'w ''0 '~ S&",q E: S ~ ~ ::1 (i"\n ~g- 1.0 "- , " Q ~ ~~; ~ V:l ~ ~:; ..." ~ ~ N ~ ~~;'Q ~~ U. '" ~ '" ~'-" 8-:;: --l = N ..". 3' n ~ a =r _0 E:i ~ ~ Iv to 1..1 ~ C' --< 0 3 . LJ ~ UCl UJ n (;;': ~ '2ft. (Jl ~ ~ "" "" < 3:: 'J id g:: ~ g.E;8 9' I.J-, .;.n ~ ~ Ld W N- 00 '.{) --l t'J ........ 0; i;A "0 >-' b'3 "'" NPl-;() ,Vl :-J!.J 8 'oj ~ Q: ~ ~ ~ ~~~ 0\ L"oJ V'l ..., n 3: ~ V:l v; g- ON I-' U. N 1:1 -V1 c;I = ~ ~. ~ rI'Q ;.~ ~ ~ ~ t') ~ In ~ lJ =! .0 E;- 0 ;.0 ;.0 p [5 o. - 0 VI 0"\ 00 '-<J:;. ~~ 6~ o~ (1, >>> Ul [j) Ul S~~ @tT151 Ul Ul [j) p.>p. u.l '-'..I .,/::;.. Gol v.. u.. '$. ~ 6-0. ZZZ nnn ~~~ p.p.p. [j) Ul [j) tT1tT1tr1 ZZZ ~~~ ...,...,"'l <<< F:f::F: iiiSiSi 'Tl'TJ"r1 ;>::1:;0:;0 000 3::3::3:: t.J tv t.J 000 000 N - 0 ...,...,..., 000 N N I>,,) 000 000 L...Jo tv- -< " ~ ., ~ ... ~ " ..., ..., !r '" '" "" ......~ -=ll ;:;- t"J ':I"l V1::i!g ~ ~ 8 ~ ?: 13 "'l"'l13 ~ ~ '" c. ~. ~ :: :: ~. ~~ - ..,,,,, 13 "" ., ~ \o:l.g ., ... " = ., ~ ~ ~ e. = = &r ~ "" ., ... ... '" "" 0() 0\ = o Q = o "" ;sA t7l <:;: l-..l ~ r~ L~ e. ~ 9 '? ?' ~D ~ 2" 2: v~ IJ ~ l-.l O. c\ - 0 -I- ~..h ""0 :: ~ 7j 6~~O ( ..J ~j.) i .J 2 ~ ~ ''1 I,) V' --t-- ;:; IJl IJI 0 Ii <i' 1;;:" ,... Vi Vi \n ~ 5~ \,Q ..... _ ~V1_=: e,e. ~ 00 'fQ. ::r = I..) ~ = !': q .j... ... 00 "" r. ("~~ _ g-o~~ .0 C' ::;. ::J. 0 ,7 c 00 0 ~J '1::; '- o 0 0 ('"~ ::: =- 0 r) v, C ~ I;/:" &<; < ~ ;-.l ? tJ Q- t.J ~ ~ 0 ~ l.,..) +-...... >-1 0 <" : ~ ~ ~[- >~ t..J C1'::x. ~ ~ - .> 3. f0- bS ---0 r". ~ ~ ;; 0 b.~;1 rj ~ ~ 00 0\ l.." 13 b- 2 ~~ E.- ~ ;5 i: r~ cr ~ rj~ ~ :. ~ :;1 ....., ~ ~ 2C: SA ~ , ~.;~ fi;:: IJI tr~ ~ I~Vig:.~ ~~ b ~ ~ ~ ~< ~~. \-,} ........ c '7 --< "~ n ~ I.J 5"::: ~ ~ ~_h 5 ~:~2-g g~ c- 00 v} f~ t..) .0 C1 ? 0 .0 r~ ......0-:::; ~. 0 C :A' ,-" - o ,-' o "1:l "'. ,.. ~ "" Vi "7:::;~ . if: V': <""':"";-J ~ .....~ ~ 2:' LJ. 2.. c; g !~ --1 o 0', c::r.- l.j - > ~JI :"'-J LJ /11 ~ ;.P. X I.) C. 0 0 --. ..0 +- c' 0 '?' 5' :; ;,<; I..; > ~ tA 1fj I,) ~ -l g 0 f- ~~ !-,.J 2 '-~ fj, 2 ~J (;. --' :;.c -+::... 1..0-' c:- (IJ ~< ..... v.) _ l-.j ........ lJ1 ::l 0- 0. -l- " o.Z \J 0 fl ~ '-.>; J" V. tA [[ l.) ":. 2 N I<- Vi = ~ .-.- =' .':j ,""" J,.. t-...l U. cr~ ...e, l...l< e.. ~ ~ Ml~;r ~3 ~ UI ~ ~~ I -<' ~ ~ (1;" [~ ':i '"' I J 3 " c;::!.. C (";. ~J !..1 ~-.J 5 0 0...-: 0 :'> LJ ::x: ,]'0 U.I c;- oO Q n. Q o' o' "" '7 . v:. -b'":, <....!..) :--~ g-: ~ e. ~ g ~...J IJI C,.,.- 1.....1 , . ~ ~ t...-, \......... "" ...., IJ >----'- C' &'7 ~ f;;A I.J ~ ......:j -l- '-J l~ c'< R rJ ~:J1 '=' 1J\ 9g.~.~' o !JI ............. f../' VI ---" '-.0 r" n :: V; I.F./ g- 0 I>.J tH _ V3 ;o1.~=o :.c '9 ;--..1 -lCI ~:E ~ g ~ ~ ..:;- ,.<' 9 ~'t-J ,~~ l,oJ I...., 5 "=-~.:;. g I~~ +-- --C 0::; .--t-;.. ~O 6 O=. ('~ >>> (/'l v., [fJ C/l [1', (/j r~r ??~ F.iHt:1 ,'/I 1"..11 f./'J >>> '--,J L,';' .;...- I.J~ ~ t~ a~ ~'. 6 ZZZ n 1"':., n ;::0;:0:::::- HiT1tT1 >>> r:/'J ':J'j VJ. CJ1tTIt":1 ZZZ <'<"'7 ~~~ ",r:r: Mrnrn .--,.....,....., <<< ~f:~ -CC rnrn[T "Tj~""t'1 ;:::o;::::;::v o C' 0 ;:::;:::;::: i-' t-J \..; 2>00 :::000 I..J"- 0 ,....,.....,....., 000 tJ t.J t...J o ~ c 000 lr~ 1-..1- - .-. . . . . . . IJ1 CI1 ~ ~ @ v ~ o ~ t11 ~ ~ :;t> ;x: ~ > n >-1 CZl ,,-.... C;;" 0 ["J) . C 0 ID . g ~ (1.l fI3- (tl 8'...... ~ () '0-, ~ ...... 0 tl c: 0 c.. n. ~ c ('ll 0 ~ ["J) 0 ;:l cr' 0 _. o tl:i (Jl := 0 ~ c.. ::3 CD ~- ~ cr s::: l'.f.l ..., CD r.fl '" () s::: c:: o CIl cr rnr;::;:..- ~ \.~ ..-,0 tr.I () ~~~ P.. <::> 0 () ~ *' C;l "'1 rn 'S. .- l:Zl r+V'l..... ~ 0 _. "< "'i N Cll p.') CD ei O'Q 0.. tn (D S" 'T:l t"'t' ~ (l) 8. '"'t ..... (l) _. ["J) M- ..... '< '--" $: ~ ~ o .- -< e. r.:: rn S' ;x: ;;g <-l' (]) ..... ["J) ;tlo- ~ !:IJ (l) ~ o 0- tro g ~ (JQf7:l- (ll 0-. '-t 0-. (l) 00 J.:l ~ C' VI. ~. 0 C1l ~o 0...0 ..., 0 tr.I 0 . 0 ~H, w@ ~!::. '0 co ["J) ..... ~ 01 -< e.. s::: rn ,.... :::l [Ii o 'U ~ ["J) (A- ~ -E1'7 tv ...... .-. ~ <~>- VI 0"1 ;....... 00 0 VI 0 0 ~~\O~ ~o ~ '" t:: ~ '-0 0 0 0 CD ('\) \0 0 0 0 0 ..... iZl 0 0 0 <:> >-< t.l t'l'1 ~ S tv ta) ~ ~ o "< ta) (;A- o fi) ;:< ~ ~ {T-I Ncr'rn l.h w N 0- >--> (Il 00 00 U'l \0 rn tfl ,...... {T} ~ < s:: 1-' 0 VI N 0 VI N ae;'-O(j ",0 0. VI c;;w;;-\Oo ~ '" 0 0 0 "~\O~ 0 0 0 0 0 0 ~ '"t1 n tv j",:I ~ ~ ~ tA 0'-<:: ~ o ~ >:1 W ....... -&':l NO""(tl w tv VI rotll ...... ~ N tn ~ @ o ~ ~ ~ r.d ~ ~ ;p. X ~ >- () -3 en --. ...... rn Vl C ~ =:l (j Ct> -E.A ...... 1"-" ~ ~ (') 0'1 - 0 c:: 0 0." (tl 0 ;8~ o OJ ~ 0 0... :: Vi ' c.. t-< rn _. (t) C Vl tl) (\l ILl toO n ~ (t) O@)tD rn 0 Vi ::I j:>l ~ 0- ;:J N 1--1 0.. )R '=/:I (') 0 ~ ~ ~ ell .....' .., p) ...... - VI _. N "< (tl ell ~e? ::I tI'l ~ @ Vl ...... '"-" F-j ~ (') ~ ~ (') q' ...... ~ >: ""I t>:I .-.. (tJ -. ILl ;;:::Jg' ~ tI'l ~ {\l (Il c.. (') 0 ~=:l ::3 &=) (JQ ...... (tl .f:::o. ""1 - (b \0 ..c 00 t:: ..j::. ::;. ~N ell W o..w ....... 0 ILl I'-"t) -...... O~ ..c:.. ,0 n <:>" ~ "'0 ~ (') -. ...... '-<:: <: ~ ........ c: (t\ _. ::l ::t o "0 ~ ;:s t/'J &=) &'7 EA- N ,...... - Vt <:$:>--o VI 0'1 ......... 00 0 Vl 0 0 a~\O@ .. u "0 ~ l:: ;:-::- \.0 0 0 0 0 0 0 0 ('p (1l \0 0 0 0 0 ,....,. tzl 8 m Z "t:1 ~ N t>:I -3 ~ o~ ~ -&') f7'7 +:I:t OCJt1l W N ......... {;A N ..--.. \Zl 00 W ~ \0 (i;I ~ ....... ~ ~ <~...... .. 0 VI N 0 l.J\ N r.:> ~ \0 n 0 ,,0 l.J\ 2"~\Oo b 0 0 ~ ~ ~ ~ 0 0 0 0 0 0 ::=:l ~ Q N~ -1F:; ~ ~ O""'=: t>:I . o ~ :>< w - f;t7 Ncr'Ol w ....) 0\ .-- l'.t.l \0 \0 ~ (l) . . . ~ . . FIVE YEAR PROJECT SUMMARIES . CAPITAL IMPROVEMENT PROJECTS FIVE YEAR EXPENDITURE SUMMARY FUND PROJECT TITLE SRC 2001 PROG CAT PROJECT NUMBER 2002 2003 2004 2005 lift s:talion Recol'lst:: :. . ':YSF::" Storm Drainage System Maint SU morm Watei::.M~I'l~geni ~r:itP:r,o.J Ej!!:>', $M if"::', :.," Repaint Water Towers WF W<;1termetEFr. Radio Re.a<:l.SYI1. . .Wf'. . .. Excelsior Blvd Utility Improve WF Rl;lsidentlalStreetlmpro\'e' '''SA' PI 'MS" Residential Street Improvements SU . Wf.:. SF ....:.$A. SU .::.i3U' MS .... ......:.:..Pl: . SA Pl' MS TF GU "M'S.:;.:. ...., ..., ,;...::....,. .','" SA RebuHd/Redesign llth.Ave So- . ~A MS 'SV:: . .:...... PI Ou PI ST,H Hwy 7/CSAH 7.3 hlters-ectfot1 . . MS . PI OU MS :(m MS Ou PI Pl. PF CR PI $A CR CR CR . . ...: PF'.. CR 20,000 CR ... . ......:.15~O'0.0 . CR H.BA HRA .W.:...... TF :. TF :. ': ,.:.:.: 'S$O:;:OOO':' 14,000 , $/I.::l' . SS.l ~$~~ WA-1 .. WA,S WA-4 S~U. 12,500 '126;6M'.. 500,000 .':: ..j?0.Q;:qo.O :.:: 160,060 :. : :l P~i,)QO 120,200 12,500 . . ~~'1Z t.II:t.:i:j::i' .. . . . :'; j 1 ~:i':':i:'~':I:~~~~~~~"v:: :!:':':':'. 14,000 14,000 Utll Uti I Utll TranS: frans Trans Trans TranS: Trans TraMs .. ST-S Trans Trans. Trans Trans Trans Trans: Trans T r arts Trans Trarf&. . Trans Trafls Trans TranS: frans ST-8 Streetscape Improv-1lth Av S Trans . ST-9: . Excelsior 8lvd Stre~t$Gapq! Trans tans: ns <oms Trans Trans: Trans Trans Trans Tran:s: Trans Trans Trans Trans. Parks CF-2 Valley Park Improv Parks : CF-$ S O<lk8eaot(Red~vel Parks CF-4 Central Park Parking Lot P~ms CF,1;j Paviljon.li;1euanil'le... Parks CF-7 Downtown Park Improve Parks . cnF Rklgion;iiCtra\l'C6nn~cboriii Bldgs FF-4 City Hall HVAC Control 8tdgs fF-6PublicSaff;jtyF<lqility Bldgs MF-1 PubliC Works Storage Facility EEi O~y .ED,1 E.Excelsh:~rBtvd red(;)\i!;llop:: . Ec Dev ED-2 North Annex redevelopment Ec O~ to-3EastC80 Pmject...... .:.' .... TOTAL CAPITAL IMPROVEMENT PROJECTS ':20Q;000 ; . .p.~4, 9.QQ 216,000 . . .2~;MQ9. 336,700 4:1;2:':900' . 247,600 '420,90.0 :.: 50,000 ..7~,Qqq... .. 75,000 . lo.~, OPQ 153,500 ST-2 50,000 . . "H'7!;5;:OQO':':':': 75,000 96,O~P: . . . 14,000 .' 3,ObO;000 . 1,000,000 50,000 . ](),OQO 75,000 . . .. ... 2Biooo:: 7,000 50,000 ?i'l,QOO' 75,000 ".. ..., 50,000 7:~,OOO 75,000 OttyWide:COiic~i:it~' :AUy $T,4 County Ro.ad :3 :21?,i,)OO,:: 75,000 :1,600,000- 700,000 .. "'140,000 50,600 ST-5 Fifth Avenue South 212,100 : :79,$00:. . 209,700 73,600 :::: :$.:ti:~~Q' :.":: 810,000 4OQ:;Q90.. : 48,700 . :197;600" 85,150 '. .' '. .,"'. ".. County Road 61 (Shady Oak) ST-6 2,700,000 .'. .. \321\(lQQ:.. . . ..167;400::: 71,800 :";30,OPQ 135,000 ST,7. 1"7-0,00.0 . 300,000 200~(l()O . 50,000 . :700;000" . . 75;000 200,000 60,000 CSAH 73/5 IntersectIOn ST-13 120,000 35QjQ90 Mlnnetonka Blvd COrridor 100,000 ..... '150iOOO" 50,000 340,OQO: ST-14 st. Joseph's Parking lot . SuperValu Warehouse Exp CityWkle Skl"walk Rep<1ir.. City Parking Lot Improve . J1Q/{QQ 300,000 ;;:Q,OOO 105,000 Z4!:5/)OQ . ST'15 ST-16 WS^l PA.l .20,00.0 20,000 . 20,000 20,000 ... . 20,000 :4:~,000 59, i,)OO. :' H H 65,000 2:50,000. . . 20;000" 25,000 . "20.;000 100,000 .' . 3, s.~0, 000 1,400,000 "::2,000.;000 . 12,298,000 .:. L500,*)00:.::'... :. . . 10,189,900 17,838,150 ::,:...:'" 10,456,600 3,964,200 493,500 TOTAL FOR 5 YEAR PERIOD 42,942,350 PROPOSED PROJECTS BY FUNDING SOURCE 2001 2002 2003 2004 2005 FUTURE SPECIAL ASSESSMENT Trans PA.1 city Parking Lot Improve SA 245,000 Trans ST.1 Residential Street Improvements 5.A 103,000 223,600 504,000 412,600 106,000 Trans 5T.3 Citywide Concrete Alleys S.A 56,000 28,000 Trans ST 5 Fifth Avenue South SA 50,600 212.100 Trans ST.6 County Road 61-Shady Oak Rd 5A 48,700 Trans ST.7 Redesign/Rebuild 11 th Avenue South SA 167,400 197,500 TOTAL 571,400 548,400 716,100 412,600 106,000 0 TAX INCREMENT FINANCING E.c Dev ED 1 E Excelsior Blvd Redevelopment TF 2,000,000 Ec Dev ED.2 North Annex Redevelopment T.F 12,298,000 Ec Dev ED.3 East CBD Project TF 1,500,000 Trans ST.5 Fifth Avenue South TF 51,800 Trans PP.1 Light Rail Transit Stations (2) TF 150,000 Trans PP.4 Security System Installation TF 54,700 TOTAL 1,500,000 12,349,800 2,000,000 0 0 204,700 SANITARY SEWER UTILITY Utll SA 1 Lift Station Reconstruction SF 350,000 Util SA-2 Lift Station Reconstruction SF 150,000 Trans ST.2 Residential st Improvements.Util SF 75,000 75,000 75,000 75,000 75,000 Trans Pp.2 Ninth Avenue LRT COrridor SF 350,000 TOTAL 75,000 75,000 75,000 425,000 75,000 500,000 STORM SEWER UTILITY util 5S.1 Storm Drainage System Maintenance SU 12,500 12,500 14,000 14,000 14,000 Utll SS.2 Storm Water Management Proj SU 125,000 165,000 Trans ST.2 Residential Street Improvements SU 50,000 50,000 50,000 50,000 50,000 Trans ST-3 Citywide Concrete Alley SU 14,000 7,000 Trans ST.7 RebUild/Redesign 11th Ave So SU 30,000 Trans PP-2 Ninth Avenue LRT COrridor SU 100,000 TOTAL 231,500 234,500 64,000 64,000 64,000 100,000 WATER FUND Utll WA.1 Repaint Water Towers WF 500,000 Utll WA.3 Watermeter RadiO Read System WF 200,000 200,000 Utll WA.4 Excelsior Blvd Utility Improve WF 160,000 Trans ST-2 Residential Street Improvements WF 75,000 75,000 75,000 75,000 75,000 Trans PP-2 Ninth Avenue LRT COrridor WF 250,000 TOTAL 935,000 275,000 75,000 75,000 75,000 250,000 PAVILION FUND TOTAL 0 0 0 0 0 0 OTHER GOVERNMENTAL UNITS Trans ST.4 County Road 3 GU 3,000,000 75,000 1,600,000 Trans ST.6 County Road 61 (Shady Oak) GU 810,000 2,700,000 Trans ST-9 ExcelSior Blvd Streetscape Impr GU 170,000 75,000 Trans ST.11 Hwy 7/CSAH 73 Intersection GU 750,000 Trans ST-13 CSAH 73/5 Intersection GU 350,000 Trans ST.14 CSAH 5 COrridor Improvements GU 150,000 TOTAL 3,350,000 1,880,000 2,850,000 1,600,000 0 0 HOUSING & REDEVELOPMENT AUTHORITY Bldgs FF.6 PubliC Safety Facility HRA 3,390,000 Bldgs MF.l PubliC Works Storage FaCility HRA 1,400,000 TOTAL 1,400,000 0 3,390,000 GRAND TOTAL 10,189,900 17,838,150 10,456,600 3,964,200 493,500 1,844,200 Total for Five Year Period 42,942,350 PROPOSED PROJECTS BY FUNDING SOURCE 2001 2002 2003 2004 2005 FUTURE CURRENT REVENUES - GENERAL FUND e: WS.l Clty,Wlde Sidewalk Repair C.R 20,000 20,000 20,000 20,000 20,000 CF.2 Valley Park Improvements CR 20,000 45,000 Parks CF.3 Shady Oak Beach Redevelopment CR 50,000 Parks CF.4 Central Park Parking Lot C.R 65,000 Parks CF.7 Downtown Park Improvements CR 20,000 Parks CF.8 Regional Trail Connections CR 15,000 20,000 20,000 Bldgs FF.l Fire StatIOn Apparatus Floor C.R 25,000 Bldgs FF.2 Fire Station Wheelchair lift CR 28,000 Bldgs FF.3 Fire Station Floor Drains CR 8,000 Bldgs FF.4 city Hall HVAC Control Upgrade CR 25,000 100,000 Bldgs FF.5 Fire Station Room Ventilation CR 7,500 TOTAL 105,000 150,000 185,000 20,000 20,000 68,500 GENERAL RESERVES Parks CF 1 Park Stage GR 80,000 TOTAL 0 0 0 0 0 80,000 CABLE TELEVISION FUND TOTAL 0 0 0 0 0 0 ECONOMIC DEVELOPMENT FUND Trans PP 3 Sixth st So (11 th to 12th Ave So) ED 100,000 TOTAL 0 0 0 0 0 100,000 GRANT-I N-AI D TOTAL 0 0 0 0 0 0 0 P.I.R./G.O. BONDS Trans PA.1 city Parking Lot Improvements PI 105,000 Trans ST.] Residential Street Improvements PI 120,200 336,700 216,000 247,600 153,500 Trans ST.4 County Road 3 PI 140,000 Trans ST.5 Fifth Avenue South PI 79,800 41: ST.8 Streetscape Improve-11th Ave So PI 135,000 ST.9 Excelsior Blvd Streetscape Imp PI 60,000 300,000 200,000 ns ST.I0 Second Street NE PI 35,000 Trans ST.l1 Hwy 7/CSAH 73 Intersection PI 50,000 Trans ST-14 CSAH 5 COrridor Improvements PI 50,000 Trans ST 15 St Joseph's Parking Lot PI 110,000 340,000 TOTAL 530,200 1,216,700 495,800 247,600 153,500 35,000 MUNICIPAL STATE-AID STREETS Trans ST-1 Residential Street Improvements MS 420,000 Trans ST-4 County Road 3 MS 1,000,000 75,000 700,000 Trans ST.5 Fifth Avenue South MS 73,600 209,700 Trans ST.6 Co Rd 61 . Shady Oak Road MS 400,000 321,000 Trans ST.7 Rebuild/Redeslgn 11 th Avenue So MS 71,800 85,150 Trans ST-10 Second Street NE MS 206,000 Trans ST-ll Hwy 7/CSAH 73 Intersection MS 200,000 Trans ST.13 CSAH 73/5 Intersection MS 120,000 Trans ST.14 CSAH 5 COrridor Improvements MS 100,000 Trans PP.3 Sixth St So.l1th to 12th Ave So MS 300,000 TOTAL 1,191,800 858,750 605,700 1,120,000 0 506,000 PRIVATE SECTOR FUNDS Trans ST 16 Public Improvements SuperValue PF 300,000 Bldgs CF.6 Pavilion Mezzanine P.F 250,000 TOTAL 300,000 250,000 0 0 0 0 REVENUE BONDS TOTAL. 0 0 0 0 0 0 IH CAPITAL IMPROVEMENT PROJECTS Total Expenditures by Funding Source 2001 2002 2003 2004 2005 FUTURE G.R. 80,000 C.R. 105,000 150,000 185,000 20,000 20,000 68,500 P.F. 300,000 250,000 T.F. 1,500,000 12,349,800 2,000,000 204,700 M.S. 1,191,800 858,750 605,700 1,120,000 506,000 S.A 571,400 548,400 716,100 412,600 106,000 W.F. 935,000 275,000 75,000 75,000 75,000 250,000 S.F. 75,000 75,000 75,000 425,000 75,000 500,000 S.U. 231,500 234,500 64,000 64,000 64,000 100,000 E.D. 100,000 P.1. 530,200 1,216,700 495,800 247,600 153,500 35,000 G.U. 3,350,000 1,880,000 2,850,000 1,600,000 H.R.A. 1,400,000 3,390,000 GA RB. TOTAL 10,189,900 17,838,150 10,456,600 3,964,200 493,500 1,844,200 Total for 5 year period (does not include future projects) 42,942,350 KEY General Fund Reserves GR Current Revenues, General Fund C.R Grant.ln-Ald GA P.I RIG 0 Bonds PI Municipal State.Ald Streets M.S Pnvate Sector Funds P F. Revenue Bonds RB Real Estate Sales Fund RE Special Assessment SA Tax Increment Financing TF Sewer Fund S.F Economic Development Fund ED Storm Sewer Utility S.U Water Fund WF Refuse FUllu R.F Pavilion FUlld PA Other Governmental Units GU Housing and Redevelopment Authonty HRA CAPITAL IMPROVEMENT PROJECTS PROPOSED EXPENDITURES FOR FUTURE PROJECTS PROG PROJECT FUND ,~ NUMBER PROJECT TITLE SRC 2001 2002 2003 2004 2005 FUTURE SA'2 LIft SlMlol'l R~Gotl$t(lictlon::,' SF . . l60,DOb . . Trans PP.1 light Rail TranSit Stations (2) TF 150,000 Trans PP.2 Ninth A\I$I)Jj~ ~RI:GQi'r-ido(. Vir. , :....: , .. " . .' 260,DQO .' ,'" ..., , '''. Trans SF 350,000 Trans :. . .$V' . . 199,(190. Trans PP.3 6th st S(llth -12th Ave S) ED 100,000 Trans , , M~:"': ." ,. ~QO,9l)~ ,.. . Bldgs FF-1 Fire StatIOn Apparatus Floor CR 25,000 mags . . .' FF'2 f,lr:e St~Wm Wh~Ei!~li'~ir-Pft:;.: :::'CR':: .:' :~$,:OOO . ... ',""", Bldgs FF.3 FI re Station Floor Drai ns CR 8,000 Bld~ FF'5 f,lt-e st<1tki~Rdo~.Ve/1~ .:eR,' :< . 7,500 Bldgs PP.4 Security System Installation TF 54,700 Tra(js S~)O S$corKI :Street /Ill:. , "PI: 3S,DOq Trans MS 206,000 Pi;lr!< Rec Cr'l DOWntown Parll: stage.., r.R .., . . ",'. .::so.,Doa .. ..." ,,,. ... TOTAL FUTURE PROJECTS 1,844,200 . UTILITIES . . CATEGORY Utilities FUNDING SOURCE PROJECT TITLE Reconstruct San itary Sewer Lift Station #7 SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 er Fund SF 350,000 LOCATION: Lift Station #7-.Valley Park (South end of 6th Avenue South) DESCRIPTION: Reconstruct and repair Lift Station #7 JUSTIFICATION: NUMBER SA.! 2005 Reconstruction necessary due to safety concerns, to improve reserve capacity and general condition. CURRENT STATUS/PROJECTED SCHEDULE: Lift Station #7 Plans and specifications 2003 Bid and construction 2004 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: 5 YEAR COST $350,000 FUTURE II CATEGORY PROJECT TITLE NUMBER 5 YEAR COST Utilities Storm Drainage System Maintenance 55-1 $67,000 FUNDING SCHEDULED PROJECT ACTIVITY SOURCE 2001 2002 2003 2004 2005 FUTURE . Storm Sewer SU 12,500 12,500 14,000 14,000 14,000 LOCA TION: i, \1 2001 . Nine Mile Creek I DESCRIPTION: 2001/2002. Stabilize creek banks of Nine Mile Creek headwaters and provide maintenance access to Creek ($25,000) 2003/2005 - Repair and maintenance of concrete alleys. JUSTIFICATION: Without the Nine Mile Creek headwaters project the City has no reliable access to the County Road 3 box culverts for maintenance purposes. . CURRENT STATUS/PROJECTED SCHEDULE: ~ ~ I City's portion of tile Nine Mile Creek Headwaters project to be paid in years 2001 and 2002. RELATIONSHiP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with the Storm Water Management Plan. . . r CATEGORY Utilities FUNDING SOURCE PROJECT TITLE Storm Water Management Projects SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER SS.2 2001 2005 ~ rm Sewer su 125,000 165.000 LOCATION; 2001 . Monroe Avenue/Second Street NE 2002 . Shady Oak pond and Fi rst Street North (18th Avenue North to Shady Oak pond) DESCRIPTION; 2001 . Enhance ditch system capacity from Monroe Avenue North intersection to Auborn Townhomes. Create new detention pond fadl ity. Install box culvert at Madison Ave North. Rehab pipe crossing at Monroe and 2nd St NE. 2002 . Provide outlet pipe to Shady Oak Pond into Minnetonka, lower 18th Avenue/First Street North intersection, install new pipe in First Street North from 18th Avenue to Shady Oak pond. JUSTI FICATION: The Monroe Avenue/Second Street NE intersection is prone to localized flooding and there is threat to homes in the neighborhood. Shady Oak pond has no outlet and floods streets and residential property jf not pumped. Intersection lowering and new pipe to Shady Oak pond will alleviate flooding in alley and private property in the #10 block between 17thl18th Avenues North. CURRENT STATUS/PROJECTED SCHEDULE: 2001 Proiects Plans and specifications Bid and construction 2002 Proiects Plans and specifications Bid and construction 2001 2002 2000 2001 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with City Council approved Action Plan of October 21,1997, the City's Storm Management Plan, and Shady Oak Road reconstruction timetable. . 5 YEAR COST $290,000 FUTURE CATEGORY Utilities FUNDI NG SOURCE PROJECT TITLE Repaint Water Towers SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER WAl 2001 2005 ,'Naier Fund WF 'iOn.DOO . LOCATION: Blake Tower. 151 Tyler Avenue South DESCRIPTION: Repaint Blake water tower 2001 JUSTIFICATION: The Moline and Blake towers are showing signs of rusting under the exterior paint, and should be repainted. ICURRENT STATUS/PROJECTED SCHEDULE: I Bid and repaint 2001 (Blake) RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Normal repaint for Blake tower in 2001 5 YEAR COST $500,000 FUTURE . CATEGORY Utilities FUNDING SOURCE 2001 PROJECT TITLE Watermeter Radio Read System SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER WA-3 5 YEAR COST $400,000 2005 FUTURE ater Fund WF 200,000 200,000 LOCATION: City wide DESCR I PTI ON: Install a radio read system on the watermeters JUSTI FICATION: The system will allow the Finance Department to move from a quarterly billing system to a monthly utility bill. The monthly billing system has benefits for both the City and the customers, It will provide a better cash flow for the City, and smaller monthly bills for the customer, CURRENTSTATUSJPROJECTEDSCHEDUL~ 1999: Installation in Bellgrove, Knollwood, and Drillane neighborhoods, 2000: Installation in Avenues East, Park Ridge, and Oakwood neighborhoods. RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: . TRANSPORTATION . e CATEGORY Transportation FUNDING SOURCE ssess Perm Improve Munl 51 Aid LOCATION: 2001 2002 2003 2004 2005 DESCRIPTION: 2001 PROJECT TITLE Residential Street Improvements SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2005 NUMBER 5T.1 SA PI M5 103.000 120,200 223,600 336.700 504,000 216,000 412,600 247,600 420,000 106,000 153.500 16th Avenue from 1st St North to 2nd St North - Reconstruction 14th Avenue North from 4th St Nortl1 to South Service Drive - Partial reconstruction 8th Avenue from 1st Street North to Co Rd 3 - Mill/overlay 2nd St North from Shady Oak Road to 21st Ave North - Reconstruction West Park Road. Reconstruction 1 st Street North from 17th Ave to Shady Oak Road. Partial reconstruction Mainstreet. Mill/overlay 13th Ave South from Mainstreet to 1st Street South. Reconstruction 2nd Street North from 9th to 12th Avenue. Reconstruction 18th, 19th, 20th Avenues South; 1 st Street South from 17th to 19th Avenue. Reconstruction 5th Street South from Minnetonka to 11th Avenue South. Reconstruction Parkridge neigh borhood streets. Partial reconstruction Park Valley neighborhood streets. Partial reconstruction 7th Street South from 6th Avenue South east to end. Mill/overlay Program to improve streets needing repair or reconstruction as indicated by street condition survey, or as part of an area street improvement. titication: Pavement Management analysis shows a minimum $300,000 street improvement commitment (seaJcoating, mill/overlays, reconstruction) to maintain current overall street conditions and backlog. The numbers assume a 70% assessed and 30% general city share of costs for reconstruction projects and 100% city costs for sealcoat and mill/overlay projects. Sea Icoat project costs budgeted in street mai ntenance budget. Costs for sanitary sewer and water main reconstruction are not shown. CURRENT STATUS/PROJECTED SCHEDULE: Public Hearing. year prior to planned construction Plans and Specifications. yea r prior to planned construction Bid and Assessment. year of planned construction RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with the City Council adopted Roadway Improvement Policy, street ratings, and Pavement Management Program. . 5 YEAR COST $2,843,200 FUTURE CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Residential Street Improvements. Utilities SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER 5T2 2 o OJ. 2005 .=tur m Sewer ~:IU Nater Fund WF :',ewer' Fund SF 5U,uOD 75,000 75 000 50,000 75,000 75,000 \ i !JO,UOO 75,000 75,000 50,000 75,000 75,000 50,000 75,000 75,000 LOCATION: Locations to be determined as they are consistent with the street reconstruction program, DESCRI PTION: Program to reconstruct deteriorated water main and sanitary sewer and to provide storm sewer i III prove ments in conj unction with street improvement projects, JUSTIFICATION: I n most cases wllere street reconstruction takes place, storm sewer facilities either need upgrading or Ileed to be Installed new, In some cases, water main and sanitary sewer need to be reha b Illtated in conj u nctio n with st reet reconstruction. The num bers assu me the City funding 100% of major storm sewer, water main, and sanitary sewer construction! ,econstruction, These costs are to be used in conjunction with street reconstruction costs shown on ST-l CURRENT STATUS/PROJECTED SCHEDULE: Public Hearing. year prior to planned construction Plans and Specifications year prior to planned construction Bid. year of planned construction RELATIONSHIP TO EXiSTING PLANS AND OTHER PROGRAMS: Consistent wltll the Storm Water Management Plan, Water and Sewer Utility Master Plan, and teleVIsion II1spectlOlls L~_,~._~~_ 5 YEAR COST $1000,000 FUTURE . . . CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Citywide Concrete Alleys SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ST.3 2001 2005 p Assessment SA Storm Sewer SU 56,000 14,000 28,000 7,000 LOCATION: 2001: Alley between 5th/6th Avenues North, 2nd/3rd Streets North Alley between Shady Oak Road and City limits, north of Bradford Road 2002: Alley west of 19th Avenue North, north of 3rd Street North DESCRIPTION: Program to construct concrete alleys in areas designated as poor on the Alley Condition Survey. JUSTIFICATION: The City has had a policy of constructing concrete alleys for a number of years. This policy has proved to be sound by the concrete alleys' durability and low maintnenance costs. The Alley Condition Survey indicates t!"~ere are approximately 8,000 feet of alley in poor condition The estimated cost to rebuild these alleys is $350,000 over six years. Current policy has the City share at 20% of the cost in residential areas. The amount recommended would allow the City to complete reconstruction of the alleys (cu rrently rated as poor) by the year 2002. The City will experience cost savings due to lower maintenance costs. CURRENT STATUS/PROJECTED SCHEDULE: Approximately 1250 feet per year for four years. Public Hearing. year prior to project Plans, Specifications, Bid, Construction - year of project RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with the City Council adopted Roadway Improvement Policy and Alley ratings. 5 YEAR COST $105,000 FUTURE CATEGORY Transportation FUNDING SOURCE PROJECT TITLE County Road 3 SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2001 i:;ttler Gvmnt GU iv1unl St !l.rd Me; ,;'erm Improve PI 3,00(1000 1. 000000 75,000 75,000 1,5UO,000 700,000 140,000 NUMBER 5T.4 2005 Note: GO lJOIlLi payments to be flnallced by a combination of existing TIF revenue, Municipal state Aid road funds, JdditlGnal TIF revenue created by eCOnomic cJevelopment. grallt lullds alld as a last resort, general City revenue LOCATION: County Road 3 from Shady Oak Road to Meadowbrook Road. iiDESCRIPTION: I Llghti ng, landsca pi ng, street, etc, improvements a 10 ng Excelsior Bou levard from the east to west city limits JUSTIFICATION: :1 II I' DeficienCies in terms of roadway condition, traffic/pedestrian movement, safety and aesthetics appear in all four segments of County Road 3: o Segment 1 from Shady Oak Road to 11th Avenue South Upgrade eXisting undivided roadway, upgrade 11th Avenue intersection to meet future needs, implement beautification program. o Segment 2 from 11 ttl Avenue South to Hwy 169 Med ia n pavers construct 1 on o Segment 3 from Hwy 169 to Blake Road Upgrade existing narrow undiVided roadway. resolve safety issues at railroad crossi ng, I m prove north. south dc-cess, accou nt for future LRT access, add ress ':1 red eve 10 p me nt needs. i; 0 Segment 4 from Blake Road to Meadowbrook Road I Upgrade roadway, implement beautification program. ,ICURRENT STATUS/PROJECTED SCHEDULE: I Segment 1 Segment 3 :: Construction 1998/1999 Planning and AcquiSition II Bidding/Construction Segment 2 Planning Biddi ng a nd Co nstru ctlon (Median upgrades only) Segment 4 Planning and Acquisition Bidding and Construction 2001 2002 I il RELA TIONSHI P TO EXI STI NG PLAN S AND OTHER PROGRAMS: H Consistent With Hennepin County CIP and Council action. 1999/2000 2000/2001 2003 2004 5 YEAR COST $5,590000 .UTURE . . . CATEGORY Transportation FUNDING SOURCE 2001 PROJECT TITLE Fifth Avenue South SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ST.5 5 YEAR COST $677.600 2005 FUTURE Assess c'erm Improve Mncpl State Ad TIF SA Pi MS TF 50.600 212,100 79,800 209.700 73,600 51,800 LOCATION: 2002. 2003. Fifth Avenue from Mainstreet to County Road 3 Fifth Avenue from T.H. 7 to Mainstreet DESCRIPTION: 2002. Resurfacing and partial reconstruction of Fifth Avenue from Mainstreet to County Road 3, Includes lighting and landscaping requirements. 2003. Resurfacing and partial reconstruction of Fifth Avenue from T.H. 7 to Mainstreet. Includes sidewalk north of Minnetonka Mills Road. JUSTIFICATION: Fifth Avenue was last graded and surfaced to its 44 foot width in 1964. The roadway is showing extreme wear and stress and its age alone indicates its condition on the downward side of the pavement deterioration cu rve. Fifth Avenue is a major access route to Mainstreet from County Road 3. As such it should be afforded the same amenities or theme treatment as those installed on Mainstreet. CURRENT STATUS/PROJECTED SCHEDULE: 2002 Projects Plans and specifications 2001 Bid and construction 2002 2003 Proiects Plans a nd specifications 2002 Bid and construction 2003 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: ConsIstent with the City Roadway Imrovement Policy, street condition ratings, State Aid CIP, and County Road 3 reconstruction timetable. . 2001 PROJECT TITLE County Road 61 (Shady Oak Road) SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER STb 5 YEAR COST $4,27Q 700 CATEGORY Transportation FUNDING SOURCE 2005 FUTURE Jther Units GU Iv11lcpl :otilte AI,j MS ';p Assess '01\ 810.0UO 400,000 48 700 2,700.000 321.000 Note' GO bonrl payments to be financed by" combination of existillg TIF revenue, MuniCipal State Aid road funds. additional TIF revenue created by economic development, grant funds and, as a last resort, general City revenue LOCA. TION: Shady Oak Road from County Road 3 to T.H. 7, Malnstreet from 20th Avenue to Shady Oak Road , DESCRIPTION: Lighting, landscaping, street, etc, improvements from County Road 3 to T,H. 7 Reconstruction and amenities on Malllstreet from 20th Avenue to Shady Oak Road. JUSTIFICATION: DefiCiencies appear on Shady Oak Road in terms of roadway conditions, traffic/pedestrian movement, safety, and aesthetiCS. Upgrade an undivided roadway, resolve safety issues with number of driveway access po I nts a nd intersection at Mal nstreet. Lightl ng needs upgradi ng a nd provide bea utifi cat Ion progra m. ReconstiuctlOll Df Mainstreet fDr 1 block sectiDn needs to be done to conclude the upgrading ot all of Mainstreet CURRENT STATUS/PROJECTED SCHEDULE: Planning and Acquisition 2002 8iddl ng a nd Co nstru chon 2003 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent With Hennepin County CIP, City's desire to upgrade the roadway, and reconstruction program for all of Malnstreet. . CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Rebuild/Redesign 11th Avenue South SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ST.7 2001 2005 c> Assess Mun State Aid Storm Sewet SA MS SU 167.400 71,800 30,000 197,500 85,150 LOCATION: Segments: 2001 - 2002 - Westbrooke Way to Smetana Soo Line Bridge to Westbrooke Way DESCRIPTION: Segments 1 and 2: Improve pavement condition, curbing and drainage, incorporate sidewalk/trail improvements. Connect storm sewer to Westbrooke Patio Homes proposed system in Segment 1. JUSTIFICA TION: Partial reconstruction is necessary to replace section of tipped curb to improve drainage. Section of storm sewer may need to be upgraded because of neighborhood flooding issues south of Westbrooke Way. Surface condition can be upgraded with milling and overlay procedure. CURRENT STATUS/PROJECTED SCHEDULE: 2001 Proiect 2002 Project Plans and specifications Bids and construction 2000 2001 Plans and specifications Bids and construction 2001 2002 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with City roadway improvement policy. 5 YEAR COST $551,850 FUTURE CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Streetsca pe 1m provements..11 th Ave nue South SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 C'erm Improve PI 135.nno LOCATION: 11th Avenue Soutll, First Street South to Mainstreet , DESCRiPTiON: i 'i Streetscape 1m p rovements to visu ally tie Mal nstreet to upgraded Excel sior Bouleva rd. Work includes Ilghti ng, sidewal k, and la nd scapi ng 1VI111 and overlay street surface JUSTIFICATION: An Improved 11 th Avenue corridor IS needed to provide an enhanced connection between Excelsior Boulevard and the central business district. Street surface shows distress and degradation due to many utility patches. i ~ II I, \! II I I [ !CURRENi STATUS/PROJECTED SCHEDULE: II PI an ni ng IDesigrl: Construction: 2000 2001 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: NUMBER ST8 2005 Provides consistent tranSition between Marnstreet and Excelsior Boulevard streetscape themes. Ii 5 YEAR COST $135000 FUTURE . e e CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Excelsior Boulevard Streetscape Improvements SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 NUMBER ST-9 2005 er Gov Units GU Perm Improve PI 170,000 300,000 75,000 200,000 60,000 LOCATION: Excelsior Boulevard from 9th Avenue So to Highway 169 DESCRIPTION: Street lighting, landscaping, pedestrian improvements along Excelsior Boulevard. JUSTIFICATION: Work is needed to bring the function and appearance of this segment of Excelsior Boulevard up to standards of previously completed segments_ CURRENT STATUS/PROJECTED SCHEDULE: 2001 Planning/Design 2002 Install lighting and north side improvements 2003 Construct south side improvements RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with CSAH 3 Corridor Study recommendations, within guidelines of Hennepin County Roadside Enhancement Partnership Program. Will be designed/constructed in consideration of Metro Transit future transit station/park and ride improvements 5 YEAR COST $805,000 FUTURE CA TEGORY Transportat I all FUNDING SOURCE PROJECT TITLE Highway 7 . 17th Ave/CSAH 73 Intersection Improvements SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 NUMBER SToll 2005 i: '1'!~~lInl State Aid ,'erm Improve I'Jtlller Gov Units LOCATION: MS PI GU 200,000 50,000 750,000 17th Avenue North/CSAH 73 from 4th Street North to 5th Street West including Highway 7 intersectIOn. DESCRIPTION: Street improvements to improve traffic and pedestrian safety and improve intersection level of service Upgrade Higllway 7 intersection traffic signal system to eight phase to include dedicated left turn lanes on all four approaches. JUSTIFICATION: Deficiencies exist in roadway conditions and vehicular and pedestrian safety. CURRENT STATUS/PROJECTED SCHEDULE: Plan ni ng and acq u isitl 0 n: 2001 Bidding and COllstruction: 2002 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent With MnDOT, Hennepin County and City of MlIlnetonka Capital Improvement Plans. 5 YEAR COST $1,000,000 FUTURE . e . CATEGORY Transportation FUNDING SOURCE PROJECT TITLE CSAH 73/CSAH 5 Intersection SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ST-13 2001 2005 nl state Aid MS er Gov Units GU 120,000 350,000 LOCATION: CSAH 73/CSAH 5 Intersection DESCRI PTION: Construct intersection improvements including traffic signals, modified geometrics, pedestrian ways, and landscaping to: o Improve pedestrian safety o Improve vehicular and traffic flow and eliminate confusion at the intersection o Improve intersection aesthetics JUSTI FICATION: The existing 4-way stop and poor geometrics have contributed to long-standing problems, Including safety concerns for pedestrians, local and regional traffic and the adjoining residential properties and neighborhood area. CURRENT STATUS/PROJECTED SCHEDULE: Preliminary planning Design 2000 Construction 2001 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Construction citizen task force. recommended, City Council approved intersection improvements. . 5 YEAR COST $470,000 FUTURE CATEGORY I Transportatio 11 FUNDING SOURCE PROJECT TITLE I Minnetonka Blvd (CSAH 5)) Corridor Improvements I SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 Munl ::;[Qte i\,lcl MS "tiler GOY Unit'. GU Ferrn IrnrlJUvie FI 100 000 150,000 50,(;,:"0 LOCATION: Minnetonka Boulevard from Hopkins Crossroads to Atwater Street DESCRIPTION: NUMBER 5T.14 2005 COrridor' improvements Including: multi.purpose trail, landscapIng, curbing, landscaping and neighborhood slgnage i JUSTI!'ICATION: I Improvements are needed to upgrade the appearance of this road corridor and to help calm traffic flow. ~CURRENTSTATUS!PROjECTEDSCHEDUl~ ! Planning and acquisition 2000/2001 Bidd Illg a nd co nstt.u ctlOIl: 2002 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: COllslstent wiUl City Cou nei I actioll and City task lorce reco III mendations. 5 YEAR COST $300.000 FUTURE . j . . CATEGORY Tra nsportation FUNDING SOURCE PROJECT TITLE S1. Joseph's Parking Lot Improvements SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ST-15 2001 2005 m Improve PI 340,000 110,000 LOCATION: Parki ng area between 12th and 13th Ave So and 1 st St So and Mai nstreet DESCRIPTION: Existing parking lot improvements including lighting, crack sealing, and striping. Construct new 70 stall parking lot at the NW corner of 12th Ave So and 1st St So. JUSTIFICATION: Additional parking areas are necessary to handle central business area demand and reduce on.street parking problems. CURRENT STATUS/PROJECTED SCHEDULE: Planning/design and public use agreement with S1. Joseph Church: 2000/2001 Bidding and construction: Phase I 2001 - Improvements to existi ng parki ng lot Phase II Property acquisition and contruct new parking lot RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: May require the vacation of a portion of 13th Av So between Mainstreet and 1st St So. 5 YEAR CDST $450,000 FUTURE CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Publ ic I III provements-Su perVal u Warehou se Expansion SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 NUMBER ST.16 2005 Private fUlldlng PF 300.000 ,LOCATION: 5th St So and 6th St So from 6th Ave to 11 th Ave So DEseRI PTION: Public Improvements necessary as a result of SuperValu perIShable warehouse expansion project. Improvements include reconstruction of portion of 5th St So to align with 5th St east ot 6th Ave So. Partial reconstruction of 5th St and 6th St So to reduce road pavement width to 32 ft. Construct new bo u leva I'd a nd multipurpose trai I along south side of 5th /6th Streets from 6th Ave to 11th Ave So. Construct intersection modifications at 5th/6th Streets and loth Avenue South intersection. JUSTIFICATION: I mprovem ents a re needed to improve pedestrian connecti ons, improve vehicu lar safety and create an improved buffer between Su perVal u faci liti es and operations and single tam i Iy residential areas. CURRENT STATUS/PROJECTED SCHEDULE: Planning and acquisition: 81 ddl ng and constru ctl on: 2000/2001 2001 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent With SuperValu perishable warehouse expansion project development agreement and conditional use permit. 5 YEAR COST $300,000 FUTURE . CATEGORY Trans portall on FUNDING SOURCE rent Revenues LOCATION: City-Wide DESCRIPTION; 2001 CR 20,000 PROJECT TITLE City-Wide Sidewalk Re air SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER WS.1 2005 20,000 20.000 20,000 20.000 Perform sidewalk maintenance on all public sidewalks and construct ADA improvements. JUSTIFICATION: Zone 2 Zone 3 Zone 4 Zone 1 Zone 2 2001 2002 2003 2004 2005 Routine sidewalk maintenance is necessary to ensure sidewalks are safe for pedestrian use. Maintenance is also necessary to remove hazards that may cause an injury and result in the City being held liable for the injury. Yearly projects will call for replacement of intersection pedestrian ramps that fall below accessibility standards as set down by the Americans With Disabilities Act. CURRENTSTATUS/PROJECTEOSCHEDUL~ Plan/Bid/Contract. Each Year RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS; Consistent with overall maintenance of general public infrastructure. 5 YEAR COST $100,000 FUTURE CATEGORy PROJECT TITLE City Parking Lot Improvements SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER PA.l Tt.ansportatlon FUNDING SOURCE 2001 2005 Pel III Imrrnve I I FI I I lCi5 1)1)0 ~,p As:;ess ""D, 24:, ono LOCATION: 2001: Lut', sun iinrl 600 DESCRI PTIOI\I Redesign and leconstruct City Lots 500 and 600 north of Mainstreet between 9th and 11th Avenues North JUSTIFICA nON. Lots 500 and 600 are on or approaching a critical pOint on a deterioration curve. Seal coats and crack sealing will not redeem them Mill and overlay are a minimum improvement needed. Project costs noted above are for total replacement of the bituminous pavement and curb installation, To address downtown parking Issues an analysis IS recommended for 2000, a feasibility report In 2000, and possible construction beyond what is here recommended in 2001. licURREN1 Sf A TUS; PROJECTED SCHEDULE: Lots 500 and 600 Plan - 1999/2000 Bid and Construction. 2001 I II :1 i!RELATlONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Lots 500 and 600 improvements based on comprehensive parking analysis. 5 YEAR COST $350,000 FUTURE . . . . PARKS & RECREATION . . CATEGORY Park & Rec FUNDING SOURCE NUMBER CF.2 5 YEAR COST $65,000 rrent Revenu es CR 20,000 45,000 LOCATION: Valley Park DESCRIPTION; Parking Addition (20,000) 2002 Hockey Rink Upgrade (45,000) 2003 J USTIFICA TION: Parking Addition Valley Park is getting more use each year as a community park; as these uses grow, the demand for additional parking is created. CURRENT STATUS/PROJECTED SCHEDULE: RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with Park Board adopted Park Guidelines and CIP Priority List of 4/20/90. CATEGORY Park & Rec FUNDING SOURCE PROJECT TITLE NUMBER Shady Oak Beach Redevelopment CF-3 SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2005 5 YEAR COST $50000 2001 FUTURE . GellerJI FlIwl Reserves CR 50,000 LOCATION: Shady Oak Beach DESCRIPTION: The 1994 Shady Oak Beach study identified structural and ADA problems_ A Shady Oak Beach master plan was developed and associated improvements approved by the cities of Minnetonka and Hopkins_ Phase I work, completed in 1996, included demolition of deep water docks, purchase of new, removable deep water dock system and construction of a fishing pier and canoe launch area_ Phase II work began in September of 1997 and includes a reconfigured entrance drive and 175 space parking lot, new changing/restroom/entry control bUildings, new concession/life guard station building, upgraded picnic shelter, canoe/paddle boat rental area, sanitary sewer system upgrade and other beach improvements_ JUSTIFICAT!ON: All beach improvements will be agreed upon with the City of Minnetonka_ CIP funding must be Identified to allow HopkIns to participate in the toint redevelopment of Shady Oak Beach Based 011 the traditional 2/3 Minnetonka, 1/3 Hopkins participation, the $1,685,000 project will cost Hopkins $561,000 budgeted over five years from 1997-2001. . CURRENT STATUS/PROJECTED SCHEDULE: 1996: Phase I work completed Phase II design Phase II work began in September Phase II work completed by August 1 1997: 1998 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with Park Board adopted resolution regarding a joint study_ . CATEGORY Park & Rec FUNDING SOURCE PROJECT TITLE Central Park Parking Lot SCHEDULED PROJECT ACTIVITY rrent Revenues CR 65,000 LOCATION: North side of Central Park, west of volleyball courts. DESCRIPTION: Number of parking stalls - 31 Ha nd icap/van access stalls - 2 JUSTIFICATION: NUMBER CF-4 Current parking lot is 25 years old and has deteriorated quickly in the last several years. Poor drainage (no storm sewer) and no permanent curbing has accelerated this deterioration. CURRENT STATUS/PROJECTED SCHEDULE: Design: 2003 Construction: 2004 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consl stent with Park Board mai ntenance standa rds. . 5 YEAR COST $65,000 CA TEGORY Park & Rec FUNDI NG SOURCE 2001 PnvatE Funds PI' LOCATION: Pavilion, 11000 Excelsior Boulevard DESCRIPTION: PROJECT TITLE Pavilion Mezzanine SCHEDULED PROJECT ACTIVITY 2002 2003 2004 250,000 install elevator to mezzanine, and install the floor, ceiling, partitions, sprinkler system and other items In this area. JUSTIFICATION: NUMBER U-6 2005 The original construction of the Pavilion provided the rough-in features for the mezzanine area The plan is to finish off this area so it could be used for City and athletic functions CURRENT STATUS/PROJECTED SCHEDULE: RElA TIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Non-ranked on Park Board priority liSt. 5 YEAR COST $250,000 FUTURE CA TEGORY PROJECT TITLE Park & Rec FUNDING SOURCE Downtown Park 1m rovements SCHEDULED PROJECT ACTIVITY 2003 2004 2001 2002 'rent enues CR 20,000 LOCATION: Downtown Park Pavers DESCRIPTION: Remove and replace center red concrete area of Downtown Park with pavers and new benches. JUSTIFICATION: Existing concrete is cracked, posing tripping hazards. Benches in need of replacement. Existing benches are 20 years old. CURRENT STATUS/PROJECTED SCHEDULE: Unscheduled RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: . NUMBER CF.7 2005 5 YEAR COST $20,000 FUTURE CATEGORY Park & Rec FUNDING SOURCE 2001 PROJECT TITLE NUMBER Regional Trail Connections CF-B SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2005 Current Revenues CR 15,000 20,000 20,000 LOCA nON: Develop various intra-city connections to existing regional trails DESCRIPTION; Park Board IS currently identifying trail connections that could be developed beginning In the year 2001. JUSTIFICATION: Safe Intra city connections to the expanding use patterns on the regional trails IS necessary. ; CURRENT STATUS/PROJECTED SCHEDULE: Unscheduled ! RELATiONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Regional trail plan under review 5 YEAR COST $55,000 FUTURE . . GENERAL PUBLIC BUILDINGS . . CA TEGORY Gen Pub Bldg FUNDING SOURCE PROJECT TITLE NUMBER City Hall HVAC Control U rade FF-4 SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2005 5 YEAR COST $125,000 2001 FUTURE ent evenues CR 25,000 100,000 LOCATION: Hopki ns City Hall 1010 First Street South DESCRIPTION: Upgrade of current pneumatic heating, ventilating, and air conditioning system at City Hall. JUSTIFICATION: The current HVAC system for City Hall and the police station needs to be upgraded. Our present system is a very complicated air operated system that needs constant monitoring in order to heat and cool City hall. By upgrading the controls and adding additional cooling coils, we could adjust the system for better efficiency and comfort with a potential for savings in heating and cooling costs. CURRENT STATUS/PROJECTED SCHEDULE; Specifications, engineering. 2001 Installation - 2002 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: CATEGORY Pu b Bldg FUNDING SOURCE PROJECT TITLE Public Safety Facility SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER FF.6 2001 2005 GO Bond Issue HRA 3,3'30000 LOCATION: Undetermined DESCR I PTIO N: This option provides for a new fire station and remodeling of the police and fire area in City Hall to accommodate the police. JUSTIFICATION: The Police and Fire Departments are in need of additional space. The City is considering options of how to handle the cramped conditions in the Police Department and the upcoming storage needs of the Fire Department. The costs included here are only building costs. Land purchase costs would be additional. CURRENT STATUS/PROJECTED SCHEDULE: RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: 5 YEAR COST $3,390,000 FUTURE . CATEGORY Gen Pub Bldg FUNDING SOURCE 2001 PROJECT TITLE NUMBER Public Works Storage Facility MF-l SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2005 Housing! HRA Redevelop Auth 1.400,000 LOCATION: 11100 Excelsior Boulevard DESCRIPTION: Public Works vehicle storage building JUSTIFICATION: Scope of project is to remove building number 2 and construct a new 200 X 106 heated storage building. Utilize building number 3, the current street equipment storage building, for salt and sand storage. Current buildings are over 50 years old and will be in need of major renovations in the near future. CURRENT STATUS/PROJECTED SCHEDULE: Plans and specifications: Year prior to construction Bid: Year of construction RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: 5 YEAR COST $1.400,000 FUTURE t;; . . . '~'L...:.--'- "'.,." . ECONOMIC DEVELOPMENT . .._~;<-:.~-.e,.,;,;,~~.~~:.~~~~.~~.~--=~~:~,-~,!!",~~-",~~'~':"~~"~.oi.'~~~r;~~~~:;~~~~~~;~~~~;~~ii;~~~'"'.:~~~-2~~~~~;.~~',~;_~~~:::_~:-.; .... : CATEGORY Econ Dev FUNDING SOURCE PROJECT TITLE Redevelo ment, East Excelsior Boulevard SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 NUMBER ED.! 5 YEAR COST $2,000,000 2005 FUTURE -.....~. '"'Increment TF 2,000,000 LOCATION: North side of Excelsior Boulevard from Monroe Avenue to approximately Tyler Avel1ue. DESCRIPTION: Redevelopment of older commercial area. Based on the existing zoning it would involve both commercial and industrial uses. JUSTIFICATION: Excelsior Boulevard is being upgraded in thi's area, which will provide for additional property on the north side of the roadway. The buildings in this area are older and no longer the highest and best use for this property. The funding amount is an estimate and will vary depending on the scope of the project. CURRENT STATUS/PROJECTED SCHEDULE: The schedule for this project is still tentative. RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with Comprehensive Plan and City Vision Process. " " " " " " " .----.J..~~~~.::-:'~_~~ti.l&~"O-_-~~~L.~~L~;~-..~,'~ri~'~~..;~_:.:...;.,~~~~~~~.~;.:L~i~~i~-:c~~,l')~~:~-~-~T.'~...~~:.~~~:,;,.~~~:,j~z~t~\.~~.:~~t~iii~~~~~>.;~-i-:.;:~"i}...~~.i"':J;~-.~,,,;~~i,~ ,- CATEGORY Econ Dev FUNDING SOURCE PROJECT TITLE North Annex Redevelopment Project SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ED.2 5 YEAR COST $12,298,000 2001 2005 FUTURE Tax Increment TF 12,298,000 . LOCATION: Northeast quadrant of Highway 169 and Excelsior Boulevard. DESCRIPTION: Redevelopment of SuperValu North Annex property. The project would involve construction of approximately 525,000 sq ft office building. The TIF would be used for land writedown, demolition, parking improvements and off. and on.site improvements. JUSTIFICATION: The existing facility was formerly owned by Red Owl. It was constructed in the mid-1950's and is no longer the highest and best use for this property. . CURRENT STATUS/PROJECTED SCHEDULE: The schedule for this project is still tentative. RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with development agreement between SuperValu and the HRA dated July 1998. fdentified in the comprehensive plan as a redevelopment site. Use would be consistent with Business Park zoning. II . CATEGORY Eco n DEw FUNDING SOURCE 2001 PROJECT TITLE East CaD Pro' ect SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER ED.3 5 YEAR COST $1,500,000 2005 FUTURE Increment TF 1,500,000 LOCATION: Mainstreet between 5th and 8th Avenues. DESCRIPTION: Redevelopment of a commercial block fronting on Majnstreet. Tax increment dollars would be used for acquisition, demolition, and possible assistance with structured park if required. JUSTIFICATION: The City has concentrated the majority of its redevelopment efforts in the last several years at 11th Avenue and Mainstreet. An interest has been expressed by the City Council to undertake a redevelopment project to anchor the easterly portion of the CaD, CURRENT STATUs/PROJECTED SCHEDULE: Porject date is tentative. Will require execution of development agreement. RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Identified as part of City Focus Group Process undertaken in 2000. , . ~_~=--~::~.:~4~~~~: ,L'~~:-'~""'.~.~ ,~u-~,-~_~"--~_~c~~"..,:i-".r~:~~~rJ.-':-';"'~'::-=-~',,"",L~ _~~:"'-;:;,i~.~;~~~.:~~:.::,.~;'~_~jT-;..:.-~~~~~~.~t::~~2-~~~~'~-';-~~~~;~.GL;;;'~~ i~..'ir~~.i~~I~;r.;;~!~ . . PROPOSED EXPENDITURES FOR FUTURE PROJECTS . CATEGORY Utilities FUNDING SOURCE 2001 PROJECT TITLE Lift Station Reconstruction SCHEDULED PROJECT ACTIVITY 2002 2003 2004 Sewer Fund SF LOCATION: Sanitary Sewer Lift Station #1 DESCRIPTION: Reconstruct existing wet well/dry well with wet well design for ease of maintenance and sta ndard ization with other I ift stations. JUSTIFICATION: Eliminates a confined space, simplifies future maintenancelrepairs. CURRENT STATUS/PROJECTED SCHEDULE: Future project RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: None NUMBER SA-2 2005 5 YEAR COST $0 FUTURE 150.000 CATEGORY Tra nspo rtation FUNDING SOURCE PROJECT TITLE Light Rail Transit Stations (2) SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER PP.l 2001 2005 I a:.; I ncn~rllent IF I: I:LOCATION: 'I i 1) Intersection of Third Street South and Fifth Avenue South 2) Second Street Northeast DESCRIPTION: Su p p lemental i III prove Illents to two light Rai I Tra nsit (LRT) stations in the proposed HCRRA locations. j' IJUSTIFICATION: The HCRRA proposes to construct two stations along the Southwest Corridor. The proposed expenditures would be in addition to tile funds expended by the HCRRA. Tile additional funds would be used to ensure the stations are high quality in appearance. CURRENT STATUS/PROJECTED SCHEDULE: Dependent on HCRRA plans. RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with plans for LRT stops in Hopkins by Hennepin County. 5 YEAR COST $0 FUTURE 1 5n Don . . . CATEGORY Transportation FUNDING SOURCE PROJECT TITLE Ninth Avenue LRT Corridor SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER PP.2 2001 2005 r Fund er Fund storm Sewer WF SF SU LOCATION: Ninth Avenue From County Road 3 to First Street North DESCRIPTION: Relocation of utilities and reconstruction of street to accommodate light rail transit line from County Road 3 to First Street North. JUSTIFICATION: In 1984 the City hired J.J. Bakker to analyze the proposed I ight rail transit corridors in Hopkins. The study recommended that the r,0rthwest route of the Southwest Corridor not cross County Road 3 at TH 169. Rather, the study recommended that the northwest route be extended north on Ninth Avenue to First Street North and then continue northwestward on the proposed corridor. CURRENT STATUS/PROJECTED SCHEDULE: Dependent on HCRRA plans RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with recommendations made in 1 ~84 Bakker study. 5 YEAR COST $0 FUTURE 250.000 350,000 100.000 !I CATEGORY l'I.~Transportatlon FUNDING I SOURCE PROJECT TITLE Sixth Street Soutll (11th to 12th Avenue South) SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2004 [con [lev ED \~llcpl Stat", Ad iv1S LOCATION: Sixth Street South from 11th Avenue South to 12th Avenue South. ! DESCRIPTION: Extension of roadway and box culvert crossing at Nine Mile Creek. JUSTIFICATION: 1. Offer a second access to the industrial area (fire access). 2 Direct some of the existing Industrial traffic north. away from the residential IIitersectlon at Seventh Street and 11 th Avenue .3 Connect A current dead.end alley, west ot 11 th Avenue. J I: ilCURRENT STATUS/PROJECTED SCHEDULE: I: I, Planlllllg/DIScussion 1995. 1998 Plans and Specifications 1998 - 2000 " I' Bidding and Construction 1998.2000 LeATloN'"" TO EXISTING PLANS ANO OTHER PROGRAMS Currently on MSA Plans NUMBER 5 YEAR COST PP.3 $0 2005 FUrURE 100.000 . 31J0.000 . . CATEGORY Pub Bldg FUNDING SOURCE PROJECT TITLE Fi re Station Apparatus Floor SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2001 Current Revenues CR LOCATION: Fire Station DESCRIPTION: Resurface a ppa ratus floor JUSTIFICATION: NUMBER FFl 2005 Resurface apparatus floor to put a nice finish on floor. The current floor still has the original finish. CURRENT STATUS/PROJECTED SCHEDULE: Plan/Bid/Contract in 2004 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with replacement of floor drai ns. 5 YEAR COST $0 FUTURE 25.000 r CATEGORY ! Pub Bldg !I FUNDING I SOURCE 2001 PROJECT TITLE Fire Station Wheelchair lift SCHEDULED PROJECT ACTIVITY 2002 2003 2004 l~lJrrent Revenues rR LOCA TION: Fire Station DESCRIPTION: Fire Station wheelchair 11ft JUSTIFICATION: Wheelchair access is required to the 2nd flool. per the Americans with Disabilities Act. licURRENT STATUS/PROJECTED SCHEDULE: I I Plan/Bid/Contract In 2002 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Co ns istent with the Fi res Station rem ode ling project. NUMBER FF.2 2005 5 YEAR COST $0 FUTURE 28.000 . CATEGORY Pub Bldg FUNDING SOURCE 2001 PROJECT TITLE Fi re Station Floor Orai ns SCHEDULED PROJECT ACTIVITY 2002 2003 2004 Cu rrent Revenues CR LOCATION: Fire Station DESCRIPTION; Replace floor drains. JUSTIFICATION: Replace current drains with longer drains and place sand traps in all drains. NUMBER FF.3 2005 We currently spend $600 per year to have drains cleaned. This change will allow us to do it ourselves. CURRENT STATUS/PROJECTED SCHEDULE: Plan/Bid/Contract in 2003 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS; 5 YEAR COST $0 FUTURE 8.000 CATEGORY Pub Bldg FUNDING SOURCE PROJECT TITLE Fi re Station Room Venti lation SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2001 Current Revenues CR LOCATION; Fire Station DESCRIPTION: Place vents in shop and weight room. JUSTI "ICATION. NUMBER FF.5 2005 Vent both rooms. Vent shop fumes When doing work in shop; vent weight room as people are worki ng out CURRENT STATUS/PROJECTED SCHEDULE: Plan IBid (Contract in 2005 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: 5 YEAR COST $0 FUTURE . 7.500 . . CATEGORY PROJECT TITLE NUMBER PPA Gen Pub Bldg FUNDING SOURCE Secunty System Installation SCHEDULED PROJECT ACTIVITY 2002 2003 2004 2001 2005 Tax Increment TF LOCATION: Parking ramp DESCRIPTION: Installation of video security system in parking ramp. JUSTIFICATION: Use of the parking ramp has increased substantially upon completion of the theater/restaurant project on the former Suburban Chevrolet site. The purpose of this improvement is to provide better security for users of this facility. CURRENT STATUS/PROJECTED SCHEDULE: Planning and discussion Bid and construction Futu re Future RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: . 5 YEAR COST $0 FUTURE 54,700 II CATEGORY I Transportation FUNDING SOURCE 2001 PROJECT TITLE Second Street N.E SCHEDULED PROJECT ACTIVITY 2002 2003 2004 FJ?rrrl lrTlprove 11\1nCPI State AICI I' ILOCATION: I r I r. jjDESCRIPTION: I' I F'I MS Second Street N.E between Blake Road and T.H 169 Improvements to Second Street N.E between Blake Road and Tyler Street involving the installation of landscaping and lighting, NUMBER 5T10 2005 5 YEAR COST $0 FUTURE . 35.uOO 206.000 The ell rrent roadway condition Index indicates mode rate deel i ne that can be reversed with bitu mlnou 5 milling and overlay . II II I/CURRENT STATUS/PROJECTED SCHEDULE: II I! iRELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS, il Consistent With sidewalk pliln and City's pavement management program. I I I . CATEGORY Park & Rec FUNDING SOURCE PROJECT TITLE Pa rk Stage SCHEDULED PROJECT ACTIVITY 2002 2003 2004 NUMBER CF.l 2001 2005 eral Reserves GR LOCATION: Downtown Park DESCRIPTION: Stage for parklrecreation purposes. JUSTIFICATION: Portable stage has created problems with A.D.A. accessibility, is getting old, has created employee safety concerns. CURRENT STATUS/PROJECTED SCHEDULE: Design: 1999 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Previously discussed and studied in Novem ber 1994. 5 YEAR COST $0 FUTURE 80,000