CR 2000-076 Approve Design, Order Bids, Lift Station #6 Reconstruction . . . CITY OF ~ HOPKINS April 27, 2000 Council Report: 2000-76 Approve Design, Order Bids, Lift Station #6 Reconstruction Proposed Action. Staff recommends adoption of the following motion: "Move that Council approve Sanitary Sewer Lift Station #6 Reconstruction design and authorize bids". Overview. Lift Station #6 is located on the north side of Excelsior Blvd just west of Blake Road. City Council approved design ofthis project in March, 1998 for 1999 reconstruction. The project was moved back one year due to the delay in approval of the preliminary road layout for the Excelsior Boulevard Phase II reconstruction project. The Excelsior Blvd, Phase II preliminary layout has been approved and lift station #6 design is now complete. Staff requests design approval and authority to advertise for bids. Primary Issues to Consider · Project cost/funding · Project Scope . Project Impact · Project Schedule Supporting Information · Cost Estimate . eIP Project sheet · Sanitary Sewer Fund - Working Capital Projection · Hopkins Commerce Center letter . Design drawings t' (, (~J- - . f\\ J\ :- ~_ .' 1i.. .\, , J \"./ \ I l\lJ-\ Steven i Stadler, Public Works Director Financial Impact: $ Yr 2000 - $ 237,000 Budgeted: Y - $130,000 San Sewer Fund Related Documents (CIP, ERP, etc.): CIP - Project SA-I Notes: Healthy working capital balances can absorb additional costs with minimal impact . e . Council Report 2000-76 Page 2 Analysis of Issues · Project cost/funding: The engineers opinion of probable construction cost is $197,000 plus an estimated $40,000 for city furnished equipment. The cost is well above the CIP amount because staff has simply carried forward the same project amount since the project first appeared in the CIP in 1995. Also, the current project includes a control system upgrade to be compatible with the new SCADA utilities radio control & alarm system. The above cost includes a 10% construction contingency. The sanitary sewer fund has a strong working capital balance and a healthy 5-year projection showing increasing capital balances - see attached capital projection report. . Project Scope: This project will replace the existing deteriorated wet welVdry well lift station with a City standard wet well lift station. The new wet well will be located behind the Excelsior Blvd street and sidewalk. The current lift station is located under the road pavement. Besides a new wet well, new pumps and a new above-ground control system will be installed. In addition, the new lift station will discharge into an existing sanitary sewer flowing west to the large trunk sewer running north along the east side of Hwy 169 to the Metropolitan Council Environmental Services lift station near Lake Street and Blake Road. This change reduces the flow going to City-owned lift station #5 (located on the south side of Excelsior Blvd adjacent to Meadowbrook golf course). · Project Impact There should be no sanitary sewer impact to customers connected to this lift station as the project requires bypass pumping during construction. The construction area extends both behind the curb on the north side of Excelsior Blvd and within the traffic lanes of Excelsior Blvd. Therefore, there will be construction impact to both the traveling public and to the Hopkins Commerce Center businesses whose storefronts face Excelsior Blvd. There is a 133' long temporary construction easement area along the north side of Excelsior Blvd for the operation of construction equipment. A single lane passage will be maintained along the front of the businesses. One of the business center signs will have to be removed during construction. The contractor is required to reinstall the sign within one month of removal. Access to the business center from Excelsior Blvd will be more difficult during construction. However, the current driveway will remain open for right-in only traffic and Pierce Avenue . e It Council Report 2000-76 Page 3 access will remain open. The contractor will install temporary signs marking access points to the business center. City staff has worked closely with the business center owners describing the project impacts and schedule. The owners approved the temporary construction easement as well as a slightly expanded permanent easement area. In the construction area, traffic lanes on Excelsior Blvd will be reduced to a single lane in each direction. The estimated duration ofthe traffic control is 45 days. Staff is attempting to limit impacts of the project through construction contract incentive pay and liquidated damages. The performance period of the contract is 45 days. Of course, the contractor will not be charged for days lost due to weather or other factors outside his control. The contract includes incentive pay for early completion. If the contractor completes the work in less than 45 days, he will be paid $500 for each day up to a maximum of$7,500 (15 days). Conversely, the City will have a contractual right to impose up to $2,000 per day if the contractor exceeds the 45 day construction schedule. . Project Schedule May 31: Open bids June 6: Contract award June 29: Begin construction August 15: Completion City of Hopkins Excelsior Boulevard Utilities Improvement. Project No. 98-169-8 HOPKINS, :MINNESOTA EXCELSIOR BOULEVARD UTILTIES IMPROVEMENTS (SANITARY LIFT STATION NO.6 RECONSTRUCTION) PROJECT NO. 98-169-S Prepared By: RLK-Kuusisto, Ltd. ENGINEER'S OPINION OF PROBABLE COST APRIL 2000 Estimated Quantity Unit Description Unit Price Total 1 ea Mobilization $5,000.00 $5,000.00 ] ea Remove and Replace Commerce Center Sign $1,000.00 $1,000.00 1 Is Remove Tunnel $2,000.00 $2,000.00 1 Is Remove Existing Lift Station (Per Plan) $2,000.00 $2,000.00 540 If Remove Curb and Gutter $3.00 $1,620.00 536 sy Remove Bituminous Pavement $2,50 $1,340.00 580 sy Remove Concrete Pavement in Median $6.00 $3,480.00 50 sy Remove Concrete Sidewalk $4.00 $200.00 260 If Sawcut Bituminous Pavement Full Depth $2.50 $650.00 1 Is Lift Station (Including dewatering, sheeting, wetwell, $90,000.00 $90,000.00 top section with hatchway, vent, rails, electric, and testing) 290 cy Sub grade Excavation (EV) $7.00 $2,030.00 ]00 cy Granu]ar Borrow (L Y) $8.00 $800.00 1 Is Subgrade Prep for Roadway $1,000.00 $1,000.00 600 ton Aggregate Base Placed Class 5 $10.00 $6,000.00 210 ton Type 41 Wearing Course Mixture $60.00 $12,600.00 210 ton Type 31 Base Course Mixture $58,00 $12,180,00 25 If 12" Pye Pipe Sewer (SDR 26) $40.00 $1,000.00 18 If 8" DIP Forcemain $25.00 $450.00 1 Is l\IIH #325 Rehabilitation $3,600.00 $3,600.00 1 Is 8" Cut into Existing MH 326 (Including pipe, and $500.00 $500.00 fittings) 2 ea 8" Cut into existing 8" CIP foreemain (Including $300.00 $600.00 fittings) 2 ea Furnish and install 8" Gate valve and box $900,00 $1,800.00 1 ea Install Cone. Plug in existing FM inlet into SJ\1H 327 $200.00 $200.00 1 ea Remove and reinstall existing catch basin curb box $500.00 $500.00 including installinu tern back late . C:iC/files/Fonm/ProjectJFomlS/9816geoc I.ALS Pag~ 1 City of Hopkins Excelsior Boulwvard Utilities Improvements ProjedNo.98-169-5 1 Is Temporary by-pass pumping sanitary waste $2,000.00 $2,000.00 543 sy Bituminous Median Replacement (2" thick) $8.00 $4,344.00 50 sy Bituminous Sidewalk Replacement (2" thick) $7.50 $375.00 540 If Bituminous Curb (MnDOT 2535) $3.50 $1,890.00 1 Is TraffiC Control Phase I $6,000.00 $6,000,00 1 Is Traffic Control Phase II $2,000.00 $2,000.00 1 Is Traffic Control Phase III $8,000,00 $8,000.00 1 Is Traflie Control Phase IV $2,000,00 $2,000.00 100 If 4" Painted Solid Line White $3.00 $300.00 30 If 4" Painted Broken Line White $5.00 $150.00 50 cy 1 1/2" Cmshed Rock for Pipe Stabilization $20.00 $1,000.00 1 ea Adjust Existing Manhole $100.00 $100.00 1 ea Adjust Existing Gate Valve $80.00 $80.00 $178,789.00 Does not include cost of pump equipment and controls. Installation of these items is included herein. Total Estimated Construction Costs 10% Contingencies $178,789.00 $17,878.90 TOTAL ESTIMATED PROJECT COST $196,667.90 Note: The estimated costs are according to average prices on similar prnjects in other areas. The actual costs for this project will he determined through a bidding process und can vary with market conditions at the time of bid. . C :/CjFil~s1FonnslProject!Forms/98 16geoc I.XLS Page 2 CATEGORY Utilities FUNDING SOURCE PROJECT TITLE Lift Station Reconstruction SCHEDULED PROJECT ACTIVITY 2001 2002 2003 2000 Sewer Fund SF 130,000 Location: Lift Station 6 - 8456 Excelsior Boulevard DESCRIPTION: Reconstruction and repair of Lift Station #6 ($130,000) - 2000 NUMBER SA-1 2004 Work is scheduled to coincide with or precede the proposed Excelsior Boulevard improvements. JUSTIFICATION: . Certain lift stations have been identified in need of reconstruction or repair. Various reasons such as safety concerns, pumping capacity, condition and obsolete parts contributed to this need. CURRENT STATUS/PROJECTED SCHEDULE: Lift Station 6: Plans and Specifications Bid & Construction 1999 2000 RELATIONSHIP TO EXISTING PLANS AND OTHER PROGRAMS: Consistent with Water and Sewer Master Plan approved in 1990. . 45 5 YEAR COST $130,000 FUTURE . - . SANITARY SEWER FUND - WORKING CAPITAL PROJECTION l2.2.2 2QQ.Q 2.QQl 2.QQ2 2.Q.!ll .2.ill:M ~ Working Capital Beginning Year 1,341,994 1,399,994 1,249,994 1,317,994 1,382,994 ,445,994 505,994 Add From Operations - (incl. Int.) 158,000 155,000 153,000 150,000 148,000 145,000 142,000 CIP 90,000 295,000 75,000 75,000 75,000 75,000 75,000 Capital Outlay 10,000 10,000 10,000 10,000 10,000 10,000 10,000 Working Capital Ending Year 1,399,994 1,249,994 1,317,994 1,382,994 1,445,994 ,505,994 1,562,994 Rate History Balance 12/31/2004 1,505,994 1983 $1.50 1989 $1.75 w 1991 $2.00 00 1993 $2.50 1999 $2.25 REFUSE FUND - WORKING CAPITAL PROJECTION l.2.2.2 ~ 2.QQl 2.QQ2 2QQ.3. 2.Q!M 2.Q.Qj, Working Capital Beginning Year 723,162 600,962 610,962 618,962 624,962 627,962 627,962 Add From Operations ~ (ine!. Int.) 20,000 20,000 18,000 16,000 13,000 10,000 7,000 Grants 30,000 Capital Outlay 142,200 10,000 10,000 10,000 10,000 10,000 10,000 Working Capital Ending Year 600,962 610,962 618,962 624,962 627,962 627,962 624,962 Rate History Balance 12/31/2004 627,962 1989 $15.10 1991 $17.25 1995 $11.00-14.45 -...I-...........~. .~:;,:,~,~; ~~~~~~, ~ '. '~J,:~~.i~~~:,;j :;!; .,:;~~;:.:i~~~~:::;'::~:;:;~~~i~'~t~',_~i~~~,~~~~;;'}"~~,'fj:~~~~~~'(~'{I~:;; :t!t:;;,;t~,::.;jttli~'~i~-..~~ic'--~:~ ~J:;:L'~ .';;'~~~~-iff~'~..l.i,:! ~I.~., :"~~~!o-\\~~'.':-' ;'--,~i,;j~~-i"lI.."'~;;r..; '.;L~'::, 'Kd,ji;,J.'!!'i:.'.';~;:li-j' J. ,,,. ~'~-<1 :{.'!;..J:~ I'.: :~i~iJj.~ :;.... ',-'.i ;~';'.~~~.; '.,~i~\!',,-~' ." ;:_. .~:~._ .-.J "..;1 ,';.;!;: ~i}_;- "';'~-':X': . HOPKINS COMMERCE CENTER 650 Pillsbury Center 200 South Sixth Street Minneapolis, Minnesota 55402-1409 April 24, 2000 City of Hopkins 10 10 First Street S Hopkins MN 55343 Attention: Mr. Gessele, Engineering Supt. Re: Property at Blake Road and Excelsior Blvd. Dear Mr. Gessele: . This is a brief note to thank you for your letter of April 20th outlining the procedures for the construction of the subject property. You have given me considerable comfort in dealing with our tenants in view of the procedures which you have set forth. Thank you very much. I am this day signing the temporary and permanent easement, and returning same to your attomey, Mr. Steiner. Very truly yours, HOPKINS COl\tIMERCE CENTER '- \. ~\ L.7_........(.:---;.-lo"k--+- ...-......,.. j, ....." ---=--1 ~ M. E. Newman l\1EN/res Cc: Mike Salloway . . ~ ! ~ f I ! ~ ~ . e EXISTING SANITARY SEWER COLLECTION SYSTEM ~ City of Hopkins 1010 First Street South Hopkins, Mn. 55343 a f1 ~Sd~ ~. - i. .~ ~ L - " _ . T- PROJECT LOCATION -,- -~ J ~~~. -. 1. TillE SHEET 2. SI TE PLAN 3. PLAN PROFILE 4. LIFT STATION DETAIL 5. MISC_ DETAILS 6. PHASE I TRAFFIC CONTROL PLAN 7. PHASE II TRAFFIC CONTROL PLAN 8. PHASE III TRAFFIC CONTROL PLAN 9. PHASE IV TRAFFIC CONTROL PLAN 10. SECTION THROUGH TRAFFIC LANES AT SMH 325 SHEET --.lli'DEX D ~ ~ Ul~ Zo~ ~g::~ D-:i- ttl ~ ~:~ ~ s Z 11'1 ~gg ~ >-~~ I~ !:::i3"- - u.. g > c , ~ ~ ~ <I ~ i'! .. III U ~ .. ~ c c 0 ~ ~l~~-~ ~ .... "" l:: '" C C U ~I < c c ~ ~ ~ ~ ~----"! HOPKINS, MINNESOTA EXCELSIOR BLVD. UTILITIES IMPROVEMENT PROJECT NO. 98169 (~) iii! ~!! 11 .. ~...='! {~ S .- Ij ~ ~ . CURRENT EXCELSIOR BLVD. R/W TEMPORARY CONSTRUCTION EASEMENT LOT 4 't. 'f- . '\ <e/ --,--' --,--' --,--' LOT 3 EXISTING BLDG 007 027 LOT 2 LOT 7 q4 1 ABANDONED I IF"T C:;TATlnN 1 L r ~o ~Of~ .w. ~~~ g: it ~ z "' ::> -. ~ ~ '" -' w OJ Z '" o 0 ~ Vi u -' :> w '" U ~ x <J) "' z o u ~I:I ~~~ ~ ~ ~ 5 a:: <1> < w :l ... a:: :r I I ~ ~ o ~ (~ ~ll ~I!~ ~l o "~ ~N ~ " (fJ"t Zo 0> -"'''' ~a.- ~~ ~ :I: ~ 0 5~ \5 ~ ~ >- CD ::i I- '" a. -0 u~ , ~ ~ 885 930 o . '. . . . . . . . . i ,:.1 P~ClFlU: f-A . u .~. . ......r:.....,.'I~ . ......:.........i~ ............1"...... .... ................:-............tJs...... , ! A. !~- ._J_.:=:..~~~~..~........ .......... r:. !~- .........J~..L.......... ..1..... !(2) 10....Sw 1)tp ~ ~ORCEr.lAlN ~ ,1.50% 1."(...S!>5.60. ~....__.... "'-T60-rrow'i C~'B95 . . . ................. .--....-.--.. . . . . . . o . ... . . . . .. " " . .. " " . . . . - .. .. . . .. 1 PROFJ~ B-B : 1 _ I : ~ROF1LF ~-c - - ~ 1 NOrf: UlllJTlES SflAll aE L~lED AND 1 'J:tt='~~~_~~_:ftr:-~::~t='~~j __._.:~~L . . . . .. . .' . " ... - . t.E.f'9pl30l~ H---. ~SmuCT NE~ INVERt (SE~ DETAIl, ~~T 4) iRDAOVE F'U1l1PS. PWlSG,:&. ELE.CTRlCIR ~6.J ij-'ll: ~ .. : j-}1~~1:~~~fj"-:E~~i1~~~~~~:t . ..... ..... . . . . . .. .... . i : - i !: ; i i 1 " .. " . - .. . :: .: :: .. .. .- ". . . . . . . 40 io "io iOO '0 "to 40 to 20 80 1~O 885 930 o -"'- it') '" z '" " Ul'l! . ~~ ~ ~ ~~ ~ m o.Jo Il: ~~~ ~ ~ o~~ ~ g ~ [I) g ..J tj u~a.. 0- S II II ~f~ ~ 0 I i i ~ ~ ~~ ~i ...'- ..., C/) B _...-- I.-~ ... '" J J EXCELSIOR BLVD -: 1027 I I I I PROPOSED uJ STA.11ON WllH 1WO 6001 GI'Il ri:~~~ r,MPS. I ~ (SEE""f 48'xl>: 0El.l0 &< RE~~ (SEE PROFILE C) I ~~~pi~~ 2~~M~ER I ~6;fdJ~i94.35 I 007 CONNECT TO ACCESS MH 324 RE=91840 BOTTOM =907.70 N S ~ EXISTING J ??l ~ ~ o ~ nil ~! Ii ~ LEGEND 0 REFLECTIVE DRUM WITH WARNING LIGHTS TYPE III BARRICADE WARNING FLASHING ARROW REGULA TORY OR ADVANCE WARNING SIGN \ ~~L07 LASHING ARROW Ii) o EXCELSIOR TYPE UI BARRICADE W /FLASHING ARROW Ii) VI ~ '" z z-' (I)~ E~ ~ ~ PJ ~5g ~ll..tC OU..J a..~ CJ) UUCD ~ g ~ E~Q ~ 0 B ~~~ :;3 f-_~ >- CD c: <:)ww ~a::a.. Ztf) u~ ~~ ~ xu. ~ w EXISTING i EXCELSIOR BLVD :11 ~_ ~---'-~--- --------- ~ T ~o --- ---------::::= ~:::~~~ --~~--~~--~~~-- -------- - i o ~ nil ~!!I " ~! (~) , " ~ -----------------------------:~-:~~-~~ _._........._._-t-_._-e- - - - - -- '//////////////// < -<- ---------------------------------------------- ------- > 0 ISLAND AREA TO BE REPAVED FOR TEMPORARY BY-PASS. 2" BITUMINOUS WEAR COURSE 2- BITUMINOUS SASE COURSE 8" ClASS 5 AGGREGATE BASE 0 0 PHASE II. TRAFFIC CONTROL "" - " BOX FROM EXlS?C8 - BACK PLAIT CASTING -~ GATE VAL 'IE BOX -~ nNG CURB )E OF E.B. LANE ->1- EXCELSIOR BLVD. ~oo o i~ '" ~ z w --' (f)~ ~ ZOm ;Z ~~~ 8 ~ ~Flo ~ : ~ Z l.I. 0 ~~~ g ~ ~ ~ "' ~:~l:~ uQ tf) '" " ~ J: g 0. ;;~ ~8~ AFFlC PURPOSE - ,. DIVERT WESTBOUND TO NORTH SINGLE LANE FOR TEMPORARY BY-PASS INSTALLATION. 2. PHASE. I TRAfFIC CONTROlS SHALL REMAIN IN PLACE CURING PHASE 11 (SEE SHEET 6). LEGEND PHASE 1 iill ~i! ~ 0 REFLECTIVE DRUM WITH WARNING LIGHTS II TRAFFIC CONTROL -$ ......... "TYPE III BARRICADE r ~! ...... REGULA TORY OR ADVANCE WARNING SIGN ~ B:I ADVANCE WARNING FLASHING ARROW - IDE APARiJ,(t)rrs - ,350' 15 CHANNEUNG DRUMS 0 25' C.c. SPAONG z z z <-' " <-' " <-'0 ~ ~ 0 o ~o ~ ~ ~ ~ ~ ~ " " 0" ~ 9 Z 0 Z or in Vi "in "' u ~ d '" ~ ~ ; Z g ~~ EO "' ~ ~ "' - TYPE III BARRICADE EO '" l!' W Z W Z W Z ~ ~ W/FLASH1NG ARROW <-'~ u "' w u "' ~ :5 " Z <DW Z ~ Z ~ ~ ~ Z ~ <~ :; t ;; t: ~ t w fLASHING ARROW OW ~ ~ ~ ~ "' ~ "' ~ ------ 0-- .- -1 < r- . 0 . . . . ~ , . - - ~ '-11} -------------------------------------------- ----------------------------------------------------------------------------------------------- ~ - ~ TYPE :s BARRICADE 2-CHANNElING BARRELS EXCELSIOR BLVD ~oo [" 'I - ~ " II : ~ ~ I I I ~ --- - a: ""j I I' I """ - 1027 410' 23 CHANNELING "i25'"O:C ~ l= ~ g REMOVE EXISTING CONe. CONST. TEMP. BY-PASS i i Q.N AREA "" ~* (;) ** * \ ~~" (;) \ (;) PHASE III TRAFFIC CONTROL --------- -------- ----- -- -----------:~~~~~~~~~~!~~:~;~- EXCELSIOR BLVD II 0 (;) i 00 o ENTER TO RETAIL AREA TO REMAIN OPEN () ~oo a "- IX) l!l 15 -' (I)~ ~ ~O(7) Z ~g:~ 0 ci g;~~ u :; :I:~ g E : I.L.::I <C 0 O~ ~ ~ ~ ?::~ [ ~ ~ U~ ~ w :I; ~ 0. m :ii ------------------------ 2. PHASE J TRAfF!C CONTROlS IN PLACE DURING PHASE HI 'RAFFIC E!:ib i PURPOSE- 1. DIVERT WESTBOUND TRAFFIC TO SINGLE: LANE ALONG TEMPORARY BY-PASS rOR NEW LIFT STATION INSTALLATION. SHAll RE~A!N (SEE SHEET 6) TYPE J BARRICADE BLVD 2-CHANNELlNG BARRELS EXCELSIOR - - '0,,, - 7027 ! II ~ I I ~ s! I ~n fiol ~ " ~ ~ ~~ il ~ i ~ W 0:: :J: VI CI 0 U o 50 ~:r ~ LEGEND o REFLECTIVE DRUM WlTH WARNING LIGHTS PHASE I TRAFFIC CONTROL ----.... TYPE '" BARRICADE ....L. REGULA TORY OR ADVANCE WARNING SGN BI ADVANCE WARNING FLASHING ARROW ~ '""""'",5 ~ 350' ~. 15 CHANNEUNG DRUMS 0 25' O.C SPACING ~ 0 0 0 0 t5 ~~ ~~ ~~ ~~ ~ id ~d !d ~~ ~ 3:~ 3:~ i:~ 3:~ -~~~~~~~~ ~ ~ :5 ~ S ~ S ~ ~ ~ ;;i: ;;:;: ~~ ~~ FlASHING ARROW~~ ~ ~ ~ ~ ~ 11: ~ g = / - - - - - ~. -.... - ..... - I _ _._ _ . . ~, ===== === --- ~--------------------------~---------------------------------- -----------------------------~----------------------------------------------------------------- > ~ illl ~l!li gl (~) c c PHASE IV TRAFHC_ CONTROL - - . TYPE 3 BARRICADE 2-OiANNEUNG BARRELS EXCELSIOR BLVD - - - - "'" - '0<7 .!Y - o 25' D.C. GL - S, 3'1 2 PHASE I TRAFFIC CONTROlS SHALL REMAIN . IN PLACE OURING PHASE IV (SEE SHEET 6) = . _._-,--1 -----~- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - _....: - - - - - - - - - - -- ~ (- - -- ~ 0 0C GC C RAPID on.. CURB I - :A TCH8, r GATE VALVE BOX TO MATCH ISLAND ~ 8 WITH 6" BITUMINOUS CURB * )E OF W B. LANE J1 EXCELSIOR BLVD ~~o ""'ARTl.ftN7's A o "'" *m "' ~ z '" " cn~ ~~~ . 0..""' ~ 0-0> ..J :J:~~ : ,,-" 0 og~ ~ :>-ffi6 w I- ~ u u~o.. [;} ~ ~ I ~I ~I "t~] :;::; t- 00 o 0 ~ ~ i 6 II:: !II < W => W co: :J: <h ~~ ~~ LEGEND 0 REFLECTIVE DRUM WITH WARNING LIGHTS ~ TYPE III BARRICADE ...... REGULA TORY OR ADVANCE WARNING SIGN B:J ADVANCE WARNING FLAShiNG ARROW - 0( APARTf.lENTS !~ 350' 15 CHANNEUNG DRUMS 0 25' 0 C. SPACING - TYPE III BARRICADE W/FLASHING ARROW FLASHING ARROW - "'-"--.- z z o ~o F OF Vi ~;;n ~ ~~ j::: t3..... z "'''' ~ ~S 325' <:>0 ~ ~ Z 0 '" ~ ~~ U < Z ~ ;:: ~ ~ ~ <:> 0 ~ ~ ~~ U < Z ~ ;:: ~ ~~ ~o 325 I ~ ~ Z " '" < ~ ~ W 0 U" Z < 0 > < 00 < " .o~O <",< .g~~ I J ~ Q > , o ~ (~ PHASE V TRAFFIC_CONTROL 1 r nil ~I!ll gi ~