Loading...
CR 2000-189 Draw Request No. 10-Westbrooke Patio Homes . ~ CITY OF , ~ November 15, 2000 "'OPKINS Council Report 2000-189 . DRAW REQUEST NO. 10 - WESTBROOKE PATIO HOMES Proposed Action Staff recommends adoption of the following motion: Move to approve draw reQuest No. 10 - Westbrooke Patio Homes. Overview In 1999 the City of Hopkins approved the creation of a housing improvement area for Westbrooke Patio Homes for the purpose of financing a variety of improvements. The majority of the work has been completed, however, there are outstanding issues with two of the contractors which will not be corrected until next spring. Under the terms of the development agreement the City can retained five percent of the contracted amount until completion of all work. However, a five percent retainage would not allow sufficient funds to pay the balance of the contracts for the work which has been completed. Since the contractors who are complete could file liens against the properties the association has requested funds to pay them in full. The estimated cost to cure the deficiencies of the remaining contractors has been conservatively estimated at $107,128. The City will have a retainage of $115,350 plus interest . after the requested draw. Primarv Issues to Consider Legally the association must pay the contractors who have completed the work. If the City does not approve of the draw request, the association would be required to use reserve funds dedicated to future improvements or obtain a short-term private loan. Because there will be sufficient funds remaining to correct any deficiencies, staff is recommending approval of the draw request. The City Attorney and project manager have reviewed the request and support staffs recommendation. Supportina Information . Financial Impact: $90,519 Budgeted: Yes Source: HIA NO.2 project fund Related Documents (CIP, ERP, etc.): Notes: WESTBROOKE . PATIO HOMES ASSOCIATION 1317 Wagon Wheel Rd. (612) 936-9692 Hopkins, MN 55343 Fax: (612) 936-0254 November 15, 2000 Ms. Kersten Elverum City of Hopkins 1010 S. First Street Hopkins, MN 55343 Re: Tenth Draw on Bond Financing Dear Kersten: With reference to the Development Agreement between the City of Hopkins and Westbrooke Patio Homes Association, Inc. dated April 20, 1999 we are submitting our tenth draw request for the release offunds. . In accordance with Section 3.3, item (b) of the Agreement: 1. Enclosed is an updated SWorn Construction Cost Statement prepared by Mr. Thomas Brown of Miller Dunwiddie, Project Manager, and attested to by Mr. Brown and myself. 2. Enclosed is an updated total Project Cost Statement, dated November 14, 2000, which has been prepared by me and attested to by Ms Heather Walker the President of the Association and myself. There have been no anticipated changes in the total of this document as of today. In accordance with Section 3.3 of the Agreement: 1. I werewith certify: a. None of the items in this tenth draw request has formed the basis for any payment heretofore made from the Project Fund. b. All the items included in this tenth draw request are necessary in connection with the Phase II Housing Improvements. c. After funds have been paid out in accordance with this tenth draw request, sufficient moneys will remain on deposit in the Project Fund, between the contingency and the retainer, to provide for payment in full of all remaining costs estimated to be incurred in . order to complete the Phase 11 Housing Improvements. 2. No event of default has occurred. A COMMUNITY OF 328 PATIO HOMES -- - . Letter to Kersten Elverum Page 2 November 15, 2000 3. Enclosed is a copy of a letter from Mr. Thomas Brown dated November 14, 2000 stating that there are sufficient funds in the construction budget to complete the project based on the progress to date. There are sufficIent funds in tile budget for any changes to date. 4. The disbursement requirements set forth in Section 3.4 of the Agreement have been satisfied. 5. The City has requested additionar information regarding contractors' payments. This information was submitted to the City on November 8,2000 in the form of a letter written by Mr. Thomas S-rown of Milter Dunwiddie, Inc. This correspondence stated the current status of each contractor, noting any deferred items, and the cost to correct the deferred items. 6. No license or permit necessary for the construction of the Phase II Housing Improvements has been revoked or had its issuance challenged. In accordance with Section 3.4 ofthis Agreement 1. Enclosed is the Disbursement Direction required by the Agreement. Please note this month's Disbursement Direction requests the City of Hopkins to reduce the total minimum retainer of the project. . 2. Executed lien waivers from draw nine have been previously submitted to the City. The lien wavers were from Peterson Stucco, Drywall & Plastering Inc. and F. M. Frattalone Excavation & Grading, Inc 3. Enclosed are the invoices and other documentation for draw ten payment request. The lien waivers will be signed upon payments to the contractors and will be forwarded to the City. 4. Enclosed are copies of Change Orders (P4) for Peterson Stucco; Change Orders (FS & F6) for Frattalone Excavating; Change Orders (SS & S6) for Sunram Construction. 5. Enclosed are copies of pending Change Orders consisting of (A4 & A5) for Albrecht Construction; (P3 & P5) for Peterson Stucco; (M3) for MN State Curb & Gutter; (F7) Frattalone Excavating; (S-1) Bituminous Roadways; and (87) for Sunram Construction. The Board of Directors has approved these Change Orders. Westbrooke Patio Homes is awaiting the originals to be submitted for signature. Copies of the executed Change Orders will be submitted to the City at the time Westbrooke Patio Homes AssocIation, Inc. has signed them. . . Letter to Kersten Elverum Page 3 November 15, 2000 Please let me know if you have any questions or if there is any additional information that you need in order to process this tenth draw request. Thank you. Sincerely, ,-)-~ ( j .. . '..::;-"". , . (J}!>1';;~I"; ;L~ --- ':tp ..... ~.. / . Patricia A. Butler, General Manager Westbrooke Patio Homes Association, Inc. Enclosure Cc. Board of Directors . . WESTBROOKE . PATIO HOMES ASSOCIATION 1317 Wagon Wheel Rd. (612) 936-9692 Hopkins, MN 55343 Fax: (612) 936-0254 November 14, 2000 To: City of Hopkins 1010 First Street South Hopkins, MN 55343 DISBURSEMENT DIRECTION The undersigned Authorized Representative of Westbrooke Patio Homes Association, Inc. a Minnesota nonprofit corporation (the "Association"), hereby authorizes and requests you to amend the Development Agreement between the City of Hopkins, Minnesota and the Association, dated April 20, 1999 (the "Agreement") to release funds in excess of the minimum required retainer and to approve the following disbursements. There will be sufficient funds in the retainer plus the contingency to cover any work yet to be completed. the fonowing amounts to the rolTowing persons and for the following proper Housing Improvements cost and purpose: Payee Purpose Amount MN State Curb & Gutter Division, AVR, Inc. Curbing and other concrete work $16,836.67 . Peterson Stucco, Drywall & Plastering, Inc. Stucco Application $51,598.79 F. M. Frattalone Excavation & Grading, Inc. Tear-up, Excavating, & Grading of Roads $15,229.88 Bituminous Roadways, Inc. Laying of Bituminous Surfaces $ 6,853.80 all as defined and provided in said Agreement. The undersigned further certifies that (I) none of the items for which payment is proposed to be made has formed the basis for any payment heretofore made from the Project Fund, and (ii) each item for which the payment is proposed to be made is or was necessary in connection with the Phase II Housing Improvement, and (iii) the amount of funds to remain on deposit in the Project Fund following this disbursement is currently estimated to be sufficient to pay all future costs of Phase II Housing Improvements with the concept that the City of Hopkins approves the requested amendment to the Development Agreement between the City of Hopkins, Minnesota and the Association, dated April 20, 1999 (the "Agreement") cL? --:7 .~t }~.~CLQ}J.J/~ -/~t.. ... . o ~(lL'V t:/t:L~ Patricia Butler, General Manager Heather Walker, President f[! C!1J.d/Y>~r:.. I j 2 c) c.? () III is/DO Date / Date . A COMMUNITY OF 328 PATIO HOMES . October 31, 2000 Westbrooke Patio Homes 1999 Exterior Rehabilitation Invoice I Payment Review Form 1. MN State Curb & Gutter Final Payment Current Payment Due $] 6,836.67 . C~,1~ ide!, ''f4i,> Charles Liddy Vice President MiIIer-Dunwiddie Associates, Inc. . W:\1998 Files\9818A\E - ArchileCl Const\E3\103100-payapp-MSC&G-approval-frrn.doc -- - - --- ----- -- -- . November 14,2000 Westbrooke Patio Homes 1999 Exterior Rehabilitation Invoice / Payment Review Form 1. Peterson Stucco Final Payment Current Payment Due $51,598.79 . -t~ arles Liddy Vice President Miller-Dunwiddie Associates, Inc. . W:\1998 Files\9818A\E - Architect Const\E3\111400-payapp-stucco-approval-fnn.ctoc . October 31,2000 Westbrooke Patio Homes 1999 Exterior Rehabilitation Invoice I Payment Review Form 1. Frattalone Final Payment Current Payment Due $15,229.88 . Q/1g/ l~ LJ~ 0-Hs Charles Liddy Vice President MilIer-Dunwiddie Associates, Inc. . W:\ 1998 Files\9818A\E - Architect Const\E3\ 1031 OO-payapp-frattalone-approval-frm.doc . November 14, 2000 Westbrooke Patio Homes 1999 Exterior Rehabilitation Invoice I Payment Review Form l. Bituminous Roadways Semi-Final Payment Current Payment Due $6,853.80 . cC&&: L)~ -1+3- Vice President Miller-Ounwiddie Associates, Inc. . W;\1998 Filcs\9818A\E. Architect Const\E3\111400.payapp.BitRoadways.approval.fnn,doc . 123 North Third St., Suite 104 tel:612.337.0000 Minneapolis, MN 55401.1657 fax:612.337.0031 8 November 2000 Ms. Kirsten E]verum City of Hopkins ] 01 0 First Street South Hopkins, Minnesota 55343 RE: Westbrooke Patio Homes - MD9818A Pay Application Update Dear Ms. E]verum: Please find the following summary of the Westbrooke Patio Homes Project and the estimate for work not completed and recommended retain age to be withheld for this work. I. Albrecht Construction . Original contract included the installation of all vinyl siding, fences and guardrails. In addition, they have completed additional work related to repairs at the furnace enclosures and other miscellaneous work at Westbrooke. Contract changes included Change Orders No. Al through A4 (ADD $29,033.24) and direct payment change order AS (DEDUCT $2,088.36). Albrecht Construction's current contract amount is 5922,020.88 Remaining work items or issues that affect payment: I. Fencing work correction has to be approved and completed. This work is identified to be 1/3 of the potential 625 fence posts (206 total) @ $60.00 per post. The total to be withheld is $12,360.00 x 1.5 = $18,540.00. 2. MDA, Westbrooke and City of Hopkins punchlist has been completed and returned to MDA and to Westbrooke Patio Homes. Additional items remain to be completed and therefore we should assume that none of the punchlist has been completed. This work is valued at 160 hours @ $60.00/hr = $9,600.00 and material costs should be accommodated for $] ,500.00. The total value is assumed to be $9,600.00 + $1,500.00 = $] 1,] 00.00 x 1.5 = $] 6,650.00. 3. The electrical inspector has cited Albrecht's subcontractor for the work completed at the garage lights. This work is not complete. The remaining work is valued at 71 units @ $8,875.00 x 1.5 = $13,313.00. 4. A substantial completion date of January 4, 2000 has been established for the demolition and siding work. The punchlist work completed to date will have its own substantial completion date of October 17, 2000, when the last punchlist was returned. The fencing will not be substantially completed until the correction for the problem at the posts is completed. . ... ------..--- Ms. Kirsten Elverum November 8,2000 Westbrooke Patio Homes, MD9818A Pa!!e 2 . II. Peterson Stucco Original contract included the stuccoing of all buildings and garages where indicated, as well as, caulking of all required joints. Albrecht was required to prepare buildings and garages for stucco operations. Contract changes included (1) the elimination of stucco behind the fumaces (DEDUCT $38,704.00), (2) changing of the trim color around the windows and doors and misc. caulking (ADD $6,842.00), (3) additional caulking at fumace enclosures (ADD $2,460.00), (4) deduct for damage to key locks (DEDUCT $864.00), and (5) direct payment change order (DEDUCT $3,699.11). Peterson Stucco's current contract amount is $1,182,339.89 Remaining work items or issues that affect payment: 1. MDA, Westbrooke and City of Hopkins punchlist has been completed and retumed to MDA and Westbrooke Patio Homes. Additional items remain to be completed and therefore we should assume that none of the punchlist has been completed. This punchlist has not been verified by MDA or Westbrooke and an amount should be withheld for items that need correction. An amount of $4,000.00 is identified as the value of incomplete work. There are believed to be only minor items remallllllg. 2. A substantial completion date of January 4,2000 has been established for the stuccowork. III. MN State Curb & Gutter Original contract included the installation of all curbs and gutters, sidewalks, and drainage in sidewalks as shown in the drawings. In addition, surveying was required for the establishment of the curb elevations. Contract changes included (1) deleting the surveying from their contract and adding it to Frattalones (DEDUCT 6,032.00), (2) deleting misc. sidewalks/curbing from project, adding new postal pads, adding . an additional 6" apron. replacing the steps at the pool, and demolition of existing postal pads (ADD$7,424.52) and (3) add for some additional concrete walks (ADD $900.00). MN State Curb & Gutter's current contract amount is $143,124.52. Remaining work items or issues: I. MN State Curb & Gutter has been out to seal the locations of the curbing where cracking has occurred. They have agreed to come back next spring to address any additional cracks. Also, a portion of the curbing needs to be replaced where considerable cracking has occurred near 1135 South Landmark Trail. MSC&G has been very responsive and they have indicated that they will correct deficiencies identified. 2. December I, 1999 has been the date established for substantial completion. IV. Frattalone Excavating Original contract included all site work for the new bituminous and curb & gutter, grading as necessary to provide proper drainage from the site. Contract changes included (] ) the stann modifications at Trailwood South and the addition of surveying and layout to Frattalone's contract (ADD $61,500), (2) misc. soil corrections (ADD $9,262.00), (3) misc. soil corrections (ADD $4,566.00), (4) misc. bollard removal and concrete removal (ADD $912.00), (5) cleanup backcharge for Sunram (ADD $450.00), (6) Minnesota Pollution Control Agency (MPCA) work and additional surveying (ADD $4,442.00) and (7) direct payment change order (DEDUCT $3,255.] 7). Frattalone's current contract amount is $374,545.83 Remaining work items or issues: . 1. December], ] 999 has been the date established for substantial completion of the roadways. 2. No hold back of funds is required for this contractor as all items have been addressed to date. -- - .-.---. ----... Ms. Kirsten Elverum November 8.2000 Westbrooke Patio Homes, MD981 8A Page 3 . V. Bituminous Roadways Original contract included all bituminous required for the project utilizing two (2) 1-112" lifts to be installed at two different times during the project. Contract changes included (1) additional bituminous modifications (ADD $828.00), (2) deduct for bituminous curbing work (DEDUCT $2,575.00), and (3) deduct for portion of valve repair (DEDUCT $1,500.00). Bituminous Roadway's current contract amount is $178,963.00. Remaining work items or issues: l. December 1, 1999 has been the date established for substantial completion of the roadways. 2. An amount of$5,500.00 is recommended to be retained to insure the owner that all bituminous slopes away from the garages, ponding areas are addressed, and for some additional bituminous required near Building #2. The value of $2,500.00 is arrived at by the amount of an estimate received from a different asphalt company to complete work not completed by Bituminous Roadways this year. This same amount would be required next year if additional work were required. 3. An amount of $ 1,875.00 is recommended to be retained to address areas where bituminous has splattered onto stucco at base of approximately 25 garage locations. This will be correct by painting the locations where this has occurred to match the acrylic stucco finish. VI. Sun ram Construction Original contract included the installation of all new retaining walls, removal of existing retaining walls where indicated and the installation of the new bollards at the garages. Contract changes included (1) the water line modifications required at the pool (ADD $5,054.69), (2) install additional retaining wall behind . unit #30 and eliminate smaller wall not needed (ADD $6,600.00), (3) add and delete retaining walls per Proposal Request #1 (ADD $11,544.00), (4) add additional retaining walls per Proposal Request No.3 (ADD $8,730.00), (5) add for draintile behind unit #30 and deduct for cleanup by Frattalone (ADD $3,371.40), (6) deduct two retaining walls not required (DEDUCT $6,848.00) and (7) direct payment items, survey & damage (DEDUCT $2080.00). Sunram's current contract amount is $137,372.09. Remaining work items or issues: l. A substantial completion date has been established as December 1, 1999 for all retaining walls excluding the two-tiered walls at the pool. The two-tiered pool retaining walls are 1,750 square feet of wall and should be valued at $15.00 to $18.00 per square foot to replace. The value of the work to replace the two-tiered wall is estimated to be $31,500.00 x 1.5"" $47,250.00. 2. City inspection has not been completed. 3. Warranty and closeout information for balance of project has not been received. VII. Swanson & Y oungdale S&Y have expended $2,483.00. There are no remaining painting items left in Phase I\. VIII. Lawnranger/Groundbreak The Lawn RangerlGroundbreak has expended $43,423.50 of the $50,000 budgeted for this item. The balance remains. . . - -..-- Ms. Kirsten Elverum November 8, 2000 Westbrooke Patio Homes, MD9818A Page 4 . CURRENT CONTRACTIPAYMENT STATUS AND RECOMMENDATION 1. Peterson Stucco, Drywall & Plastering, Inc. Contract Amount $1,182,339.89 Paid To Date $1,126,737.09 Balance Due $ 55,602.80 Less Amount for Punch list Work ($ 4,000.00) *described above Amount Due $ 51,602.80 2. Albrecht Construction Services Contract Amount $ 922,020.88 Paid To Date $ 888,349.83 Balance Due $ 33,671.05 Less Amount for Corrective Work ($ 48. 503.00) *described above Amount Short on Retainer ($ 14,831.95) 3. Sunram Construction, Inc. Contract Amount $ 137,372.09 Paid To Date $ 120,983.16 Balance Due $ 16,3 88.93 Less Amount for Corrective Work ($ 47,250.00) *described above Amount Short on Retainer ($ 30,861.07) . 4. F.M. Frattalone Excavating and Grading, Inc. Contract Amount $ 374,545.83 Paid To Date $ 359,315.95 Balance Due $ 15,229.88 Less Amount for Corrective Work ($ 0.00) Amount Due $ 15,229.88 5. Minnesota State Curb & Gutter Division, A VR, Inc. Contract Amount $ ]43,124.52 Paid To Date $ ] 26,287.85 Balance Due $ 16,836.67 Less Amount for Corrective Work ($ 0.00) Amount Due $ 16,836.67 6. Bituminous Roadways, Inc. Contract Amount $ 178,963.00 Paid To Date $ 164,734.20 Balance Due $ 14,228.80 Less Amount for Corrective Work ($ 7,375.00) *described above Amount Due $ 6,853.80 . Ms. Kirsten Elverum November 8, 2000 Westbrooke Patio Homes, MD981 8A Page 5 ~ . 7. Swanson & Y oungdale Contract Amount $ 2,483.00 Paid To Date $ 2,483.00 Balance Due $ 0.00 Less Amount for Corrective Work $ 0.00 Amount Due $ 0.00 8. Lawn RangerlGroundbreak ~ Landscape Allowance $ 50,000.00 Paid To Date $ 43,423.00 Balance $ 6,577.00 Less Amount for Corrective Work $ 0.00 Amount Due $ 0.00 SUMMARY Total Project Budget $3,037,800.00 Total Contracted Amount $2,984,272.21 Paid to Date $2,832.3 14.08 Balance Due $ 151,958.13 Pay Draw #10 Total $ 90,522.3 5 Current Amount Retained $ 61,435.78 . Contingency (Budget minus (-) Contract Amt.) $ 53,527.79 Amount Designated to Landscaping $ 6,577.00 Total Contingency $ 46,950.79 Amount Retained for Corrective Work $ 61,434.98 Amount Short for Corrective Work $ 45,693.02 Value of Correct ivel Incomplete Work $ 107,128.00 The value of the amount retained (6 1,434.98) plus the contingency ($46,950.79) slightly exceeds the value of the amount necessary for the corrective work ($107,128.00). The corrective work is valued at 1.5 times its actual value. Also, the value identified for the pool wall correction is overstated because the materials will likely be reused rather than all new Keystone brought in. Westbrooke Patio Homes Association could release Pay Draw #10 and still have funds with the amount retained and the contingency available if the contractors failed to complete the corrective work. Albrecht Construction has begun their corrections and has given every indication that they will resolve their matters with Westbrooke Patio Homes. Sunram Construction has not formally responded to the correspondence related to the pool retaining wall. MDA has spoken to Sunram Construction and they have indicated that they intend to repair the wall but that they may challenge whether all of the lower wall is their responsibility. We will wait for their formal response. . Ms. Kirsten Elverum November 8, 2000 Westbrooke Patio Homes, MD9818A Page 6 . MDA has forwarded the pay application information to Westbrooke, however, we will finalize all items contained in this correspondence once we have received your feedback. Please review this infonnation and call with any questions that you may have. TIffi/thb C: File Doug Strandness, Dunbar-Strandness Pal Butler, WBPH Chuck Liddy, MDA W:\ 1998 Fi les\98] 8A \F - Owner C onsl\F I \ I ] 0 800-city-westbrookeu pdate .Itr.doc . . ------