CR 99-66 Approve Final Plans and Order Bids 1 y \ 0 V If:- -m .y <" . March 31, 1999 o P K \ ~ Council Report 99-066 Approve Final Plans and Order Bids - 1999 Street & Utility Improvements and City Hall West Parking Lot Reconstruction Proposed Action. Staff recommends adoption of the following motion: Move that Council adopt Resolution 99-028. Resolution approvinq plans and specifications. 1999 Street & Utility Improvements and City Hall West Parkina Lot Reconstruction. Proiect 98- 09 and authorizina bids. Overview. The City Council at its regular March 2, 1999 meeting conducted a public hearing concerning street and alley improvements in the area bounded by Mainstreet, Excelsior Boulevard, 11 th Avenue South and 13th Avenue South. Council authorized the project to proceed allowing the preparation of plans and specifications. Bolton & Menk, Inc. has prepared the plans and staff now seeks authorization to continue to the bidding phase. The approved 1999-2003 CIP also includes a 1999 project to reconstruct the City Hall west parking lot. Staff has completed design of this project and has included . it with the 1999 Street Improvement project bid package. The parking lot is near the street project area and includes similar work - new curbing, storm sewer installation and asphalt paving. Staff seeks approval to proceed with the bidding of this project, as well. Primary Issues to Consider. . 1999 Street Improvement scope and final estimated cost . Parking accommodations during construction . City Hall west parking lot scope and estimated cost . Project timetable Supportina Information. . Project area map . Reso ution 99-02 -~, rv . ') //'- Steven J. Stadler Public Works Director . . Council Report 99-066 Page 2 Analvsis of Issues. . 1999 Street Improvement Project scope and final estimated cost The following streets and alley will be reconstructed: . 1 st Street South from 11th Avenue to 13th Avenue . 1 ih Avenue South from Mainstreet to 2nd Street South . 13th Avenue from 1 st Street South to 2nd Street South . Alley south of Mainstreet from 12th Avenue to 13th Avenue Associated utility improvements include: . Replacing existing storm sewer pipe in 13th Avenue South and 1 st Street South to increase pipe capacity . Add storm sewer inlets to better intercept runoff along 1 st Street South and at 12th and 13th Avenue intersections with 1 st Street South . . Replace 610 feet of sanitary sewer pipe and insulate shallow pipe sections . Water distribution system valve replacements and one additional valve The reconstruction of 13th Avenue South from Mainstreet to 1 st Street South has been removed from the project. There is still the possibility that the city could reach an acceptable agreement with St Joseph Church on shared use of their parking lot in exchange for the vacation of a section of 13th Avenue. Therefore, staff has decided to hold off on this block of street improvement. If the ultimate decision is to retain 13th Avenue then the street reconstruction could be included in a future street project. The engineer's final opinion of probable cost is as follows: Street improvements: $290,376 Alley improvements: $26,199 Storm Sewer improvements: $279,185 Sanitary Sewer improvements: $36,295 Water System improvements: $21.500 Construction cost estimate: $653,555 Construction contingency: $32,800 Engineering costs: $120,000 . Admin/Legal fees: $15.000 Estimated Project Total: $821,355 ----- --- . Council Report 99-066 Page 3 . Parking Accommodations during construction There are an estimated 50-60 residents who park on 12th and 13th Avenues each weekday. During construction residents will be able to park on 2nd Street South and 13th Avenue north of 1 st Street South. In addition, Staff is attempting to get an agreement with St Joseph Church to allow residents to park on the south end of their parking lot. . City Hall west parking lot scope and estimated cost This parking lot will be reconstructed with concrete curb and gutter, asphalt paving and new storm sewer pipe and inlet. The estimated cost of this work is $36,400 . Project Timetable Open Bids: April 29 . Order Assessment Hearing: May 4 Assessment Hearing and Award Bid: June 1 Construction start: June 14 Construction completion: September 10 . L1 ~, ......l>- N - - ~l1\ ~. ~.' . . h - ~ .~ ~ 133~lSNIVt'i ~... ;> I() I.. S. ~ ,.: . [':\,r:,' '. 1"."" .. . .,' Hi'" t;..! : . ~ . J I .",...; t;.<.:".::. 10'":): ........ t ~:. '.' : .... :.:" . -.., ....--- I" 0 ,....,. H::' ~ r'" fil < i/,:, , u , . [/] l2 r" t \ \ :~,~ :'~..~ ;:. b i'b} z '-' .','.:, '" ~ It ;.:...-.... qh <..:.....; " i3 iii : )}!"{' ...... . eel .. ~ ~ 0 no :l 8 ~ .......'... ::':',.:..," ) _ W '" !i! ';f::\, .:I: ~ ~ fL, J ~~ 11 ~ : 2J I ~:~::':;~:: '~r.<;- [f] ~~.\.~, lz. ....... 0 w ~,~~.~:,:~ ::;: "0 w ~~l.. i ~ [f]> ~o .'";<'i.:;'" CQ zO:: j 0 wO- 1I1 ::l1::;: , 0 -z )<:> w ~~;::;: ~ ~- . l~ .J[/] 0 ~~~ " I - :>:: \ ~ 0- l;jol1O l:itw:I: , t;;~ I- , 1I1 0> I 0> ~ 0> I ~ ; TUOS t~ ,siO I I I lw I I 1iJ .. 0 :sD w C=:=f 0:: , 0 . ' t? 1I1 D 0 0 w "Q ~ CJ VJ ::> ~D z 0:: 0 W < ~ ~ 0.. LJ .w ' ' ~ --' 0:: ~ ' ' c? ~D ~. ~ J lz. .... w I ~ u '-' 0' CJ o l c::=J I D 9 I ; 'CJ----- :__om ' ' ......-::"'"_1 _ _ .." - ...-." .--" . . ' -~ - - - . ._,- '- ' -- -- .. -!l - g - --- ~~-_. I [S ~; i D l ' ' [J' ' . , . ' . ' ' . ' . 1 9~u~ L?~Ld ~ ~ ~ ~ 1 i .)jll ~ ~ - - 8 II Hlnos 133illS QNl ~ I i -- CITY OF HOPKINS Hennepin County, Minnesota . RESOLUTION No. 99-028 RESOLUTION APPROVING PLANS AND SPECIFICATIONS 1999 STREET & UTILITY IMPROVEMENTSIPROJECT 98-09AND CITY HALL WEST PARKING LOT RECONSTRUCTION AND AUTHORIZING ADVERTISEMENTS FOR BIDS. WHEREAS, pursuant to a resolution passed by the Council on March 2, 1999, plans and specifications for improvements to the alley between 12thll3th Avenues south ofMainstreet,lih and 13th Avenues South and 1 st Street South, (Project 98-09) including street reconstruction, alley reconstruction, replacement of deficient utilities, bituminous overlay, and, WHEREAS, plans and specifications for Projects 98-09 have been prepared by Bolton & Menk, Inc. and have been presented to Council for approval, and, WHEREAS, it is beneficia] to also include reconstruction of the City Hall west parking lot into a single contract bid package for advertisement and award, and, WHEREAS, city staff has prepared construction plans for the City Hall west parking lot which have been presented to Council for approval, and, NOW THEREFORE, BE IT REOLSOVED by the City Council of Hopkins, Minnesota: . 1. Such plans and specification, a copy of which are attached hereto and made a part hereot: and hereby approved and ordered place don file in the office of the City Clerk. 2. The City Clerk shall prepare and cause to be inserted in the official paper and in the Construction Bulletin an advertisement for bids upon the making of such improvement under such approved plans and specifications. The advertisement shall be published three times, at least three weeks before date set for bid opening, shall specify the work to be done, shall state that bids will be received by the clerk until 10:00 a.m., on the 291h day of April, 1999, at the City Hall and that no bids shall be considered unless sealed and filed with the clerk and accompanied by a certified check or bid bond, payable to the City of Hopkins, Minnesota for 5% of the amount of such bid. ., The clerk and city engineer are hereby authorized an instructed to receive, open, and read -'. aloud bids received at the time and place herein noted, and to tabulate the bids received. The Council will consider the bids and award of contract at the regular City Council meeting of June 1, 1999, in the Council Chambers. Adopted this 6th day of April, 1999. Charles D. Redepenning ATTEST: . Terry Obermaier, City Clerk ---.-------