CR 09-003 Accept Feasibility ReportJanuary 6, 2009
G �TY OF
C12
NOPKiNS
ACCEPT FEASIBILITY REPORT
ORDER PUBLIC HEARING
2009 STREET IMPROVEMENTS
PROJECT 08 -10
Propo d Action.
Council Report 2009 -003
Staff recommends the following motion: "Move that Council adopt Resolution 2009 -004, Resolution
Ordering Public Improvement Hearing, 2009 Street and Utility Improvements, City Project 08 -10.
This action continues an assessable project for street upgrading.
Overview.
At its October 7, 2008 meeting, the Hopkins City Council authorized Bolten and Menk, Inc. to prepare
a feasibility study concerning street and utility improvements in the Park Ridge Neighborhood and
street improvements to Blake Road south of Excelsior Boulevard. The report is complete and is now
submitted to Council for review and further action. A summary of issues is provided here,. but staff
will provide a detailed summary of the report at the scheduled Council meeting.
Primary Issues to Consider.
• Scope of improvements
• Public input
• Costs and assessments
• Schedule
• Project budget
• Assessments
• Staff recommendation
Supporting Information.
• Feasibility report
• Resolution 2009 -004
ohn R. Bradford, P.E.
City Engineer
Financial Impact: $ 3,158,000 Budgeted: Y/N Yes Source: PIR, Utility Funds,
Assessments Related Documents (CIP, ERP, etc.): CIP
Notes: N/A
Council Report 2009 -003
Page 2
Analysis of Issues
Scope of Improvements
Proposed street improvements include complete reconstruction of 1 St Street North from 5 th Avenue North to
Washington Avenue North; 2 nd Street North from 5 th Avenue North to Park Lane and from Ridgewood
Drive to Washington Avenue North; Oak Glen Drive from 1 St Street North to 2 nd Street North; Park Lane
from Washington Avenue North to 2 nd Street North; and Ridgewood Drive from Park Lane to 2 nd Street
North.
Proposed sanitary sewer improvements include the total reconstruction of the sanitary sewer system. The
replacement is necessary due to the age and condition of the pipe. There are many cracks, sags, and root
intrusions into the pipe. The cracks and roots allow ground water to enter the pipe. The cost for treating
this clear water is charged to the City by the Metropolitan Council. The services in this area are generally
made of Orangeburg pipe which is coal tar impregnated wood pulp pipe. A picture of this pipe is shown
below. Services are proposed to be replaced from the main to the right of way line.
Council Report 2009 -003
Page 3
Proposed water main upgrades includes the complete removal and replacement of the water system
including valves, hydrants and residential services from the main to the right of way. This upgrade is
necessitated by the age of the pipe, the presence of lead joints, as well as the impact the sanitary sewer
reconstruction will have upon the water main. Lead joints were used to connect cast iron pipe together by
stuffing oakum (see picture below) into the joint and pouring hot lead on top of it. The joint would be stable
as long as it wasn't jostled or the pipe disturbed.
All residential services are proposed to be replaced to the right of way line with the exception of those
replaced within the last 10 years with copper pipe. Most of the older services are lead or galvanized and
should be replaced. The added project cost of a new service is estimated to be $825 or $1,300 depending
on which side of the street the water main is located. When replaced after the 5 th Avenue N reconstruction
project, homeowners paid an average of nearly $3,000 for a new water service. This is primarily due to
the street replacement cost and traffic control.
We are proposing to share the cost of service replacements in the right of way with the property owner at a
50% rate. This is a change from the 1/3 cost share done on previous projects. The reason for the change
is that program was a voluntary replacement of the water service only. This project proposes a mandatory
replacement of both the water and sewer services.
Proposed storm sewer upgrades include the replacement of the existing clay storm sewer system because
the system is undersized, and the clay pipe material is not likely to survive the reconstruction of the
sanitary sewer system. There will be additional catch basins added to improve drainage in the
neighborhood.
A mill and overlay is proposed for Blake Road south of Excelsior Boulevard.
• Public Input
A public information meeting was held on December 18, 2007, and a resident survey questionnaire was
sent in the mail. Only 5 residents attended the meeting. Responses and feedback gathered through the
returned questionnaires have generally noted some drainage concerns in the neighborhood. The minutes
of the information meeting are in Appendix D of the attached feasibility report.
Council Report 2009 -003
Page 4
• Schedule
The cost and scope of this project necessitate an extended construction schedule over two construction
seasons. Phasing is shown in the attached feasibility report on figure 1 -3. Phase 1 of this project will
include all street and utility work on Park Lane from Ridgewood Drive to Washington Avenue; 1 St Street
from Oak Glen Drive to Washington Avenue; 2nd Street from Ridgewood Drive to Washington Avenue; and
all of Ridgewood Drive.
Phase 2 will be constructed in 2010 and include 2 nd Street form 5 Avenue to Park Lane; 1 St Street from 5 t "
Avenue to Oak Glenn Drive; Park Lane from Ridgewood Drive to 2 nd Street; and all of Oak Glen Drive.
We are also proposing to finalize the assessments after construction. There are two reasons for this.
First, with the economy in the shape that it is in, having assessments due in 2011 gives the residents some
time to plan. Second, assessing the Phase 2 property owners a year prior to the start of construction may
be objectionable to those residents.
The proposed schedule is listed below:
Oct. 7, 2008
Order Feasibility Study
Dec 18, 2008
Neighborhood Meeting
Jan 6, 2009
Approve Feasibility Study, Order Public Hearing
Feb 3, 2009
Public hearing, order project, and final design
Apr, 7, 2009
Approve plans & Specifications, Authorize Bidding
May 19, 2009
Accept bids, Award Bid
Jun -Oct, 2009
Construction — Phase 1
Jun -Sept 2009 Construction — Phase 2
October 2009 Public Assessment Hearing /Adopt Assessment Role
• Proj ct Budget
The estimate costs for this project are as follows:
PIR
$1,244,000
Assessments
611
Storm Sewer Fund
398,000
Sanitary Sewer Fund
395,000
Water Fund
510,000
Total
3
• Assessments
The proposed street assessments are based on the City's Assessment Policy whereby 70% of the street
reconstruction cost is assessed to the benefiting properties. The 2009 residential assessment cap is
$70.17 per front foot based on a 3% increase to the 2008 assessment cap. Commercial properties are not
capped and will be assessed at a rate of $157.67 per front foot. Because the lots in this neighborhood are
fairly uniform, and the benefits of the project are generally spread equally among these lots, we are
Council Report 2009 -003
Page 5
proposing to use a unit assessment. The unit assessment is base on an 80 foot lot with the assessments
capped at $5,613.60. Burnes Park and the commercial properties will be assessed at a front foot rate.
The cost of water and sanitary sewer services are in addition to the street assessments. With a 50%
share of the service cost, the additional assessment will be approximately $900 to $1,225 per unit. This
puts final assessment totals at approximately $6850 per unit.
We are proposing to change the assessment term from 10 years to 15 years due to the mandatory
replacement all water and sewer services and the burden this places on property owners. At the 7%
interest rate used on recent assessment projects, typical monthly payments would be approximately $60
per month.
As noted earlier, the assessment role will not be adopted until after construction in 2010. The first
payment would be May 15, 2011 for those who do not pre -pay their assessment.
Staff recommendation
Staff recommends accepting the feasibility report and ordering a public hearing for February 5, 2007.
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION NO. 2009 -004
RESOLUTION ORDERING PUBLIC IMPROVEMENT HEARING
2009 STREET AND UTILITY IMPROVEMENTS
CITY PROJECT 08 -10
WHEREAS, the City Council authorized and directed the City Engineer to
prepare a report with reference to the aforesaid improvement, and
WHEREAS, the City Engineer has caused to be prepared the aforesaid report for
improvements on 1 St Street North, 2 nd Street N, Oak Glen Drive, Park Lane, Ridgewood
Drive, and Blake Road;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Hopkins, Minnesota:
1. The Council will consider the improvement of such street in accordance
with the report and the assessment of abutting property for all or a portion
of the cost of the improvement pursuant to Minnesota Statutes Chapter
429 at an estimated total cost of $3,158,000.
2. A public hearing shall be held on such proposed improvement on
Tuesday, the 3 rd day of February, 2009 in the Council Chambers of the
City Hall at 1010 First Street South at 7:30 P.M and the City Clerk shall
give mailed and published notice of said hearing and improvements as
required by law.
Adopted by the City Council of the City of Hopkins this 6 th day of January, 2009.
0