Loading...
CR 95-207 1996 Residential Street Improvements• • Supporting Information. O Feasibility report O Resolution 95 -106 J T es Gessele Engineering Superintendent e O P K ` p1 November 16, 1995 Council Report 95 -207 1996 Residential Street Improvements Accept Feasibility Report Order Public Hearing Proposed Action. Staff recommends adoption of the following motion: Move to accept the feasibility report prepared by MSA Consulting Engineers as ordered on October 3, 1995 and adopt Resolution 95 -106, Resolution Ordering Public Hearing 1996 Residential Street Improvements. Overview. Council at its October 3 meeting was presented with a staff report concerning possible reconstruction of streets in the Campbell /Peaceful Valley /Westbrooke East neighborhoods. Staff recommended that Council consider reconstruction /overlay rehabilitation of certain streets in these areas. Staff also recommended consideration of reconstructing the alley east of 6th Avenue South, between 7th and 8th Streets South. Council concurred and authorized MSA Consulting Engineers to prepare a feasibility report. MSA has completed the report and determined the project to be feasible. Council now needs to consider accepting the report and ordering a public hearing. Staff has met with the neighborhoods for informational meetings. Primary Issues to Consider. • List of streets under consideration and their condition O Staff recommendation concerning the feasibility study O Public hearing date O Proposed schedule Analysis. 0 List of streets under consideration and their condition: 8th Avenue South (6th to 8th Street South) 7th Avenue South (5th to 8th Street South) 8th Street South (6th to 8th Avenue South) Alley (east of 6th Avenue South between 7th /8th Streets South) Burnes Drive Sweet Briar Lane (670 L.F.) Pavement conditions of these roadways are generally poor, have substandard drainage characteristics, and in some cases the utilities may need to be replaced. The pavement management report indicates portions of these streets may be candidates for overlay. Otherwise total street reconstruction is the only maintenance strategy at the City's disposal. 0 Staff recommendation concerning the feasibility report. Steve Gatlin representing MSA will attend the Council session to make an oral presentation of the report, a copy of which is attached. Staff finds the report to be complete and recommends its acceptance. 0 Public hearing date Staff recommends Council order a public hearing for December 19. A public hearing is mandatory in projects that are funded in whole or in part with special assessments. Assessments are anticipated here should a project be ordered. Informational meetings have been held with affected property owners. Staff proposes to meet with the residents again to provide details of the feasibility report. These meetings would be conducted before the December 19 hearing and would facilitate more meaningful discussion and input from the public at the hearing. Council is reminded the feasibility report has been prepared without benefit of a property owner petition. All Council action concerning an improvement within the scope of the report will require a 4/5 vote. 0 Proposed schedule 1995 November - December: Meetings with neighborhood groups December 19: Public hearing and authorize plans 1996 January: Public input meetings Feb. 20: Complete plans, approve plans, order bids March 12: Open bids March 19: Order assessment hearing April 16: Assessment Hearing and adopt assessment roll May 21: Award bid June: Start construction October: Complete construction • CITY OF HOPKINS Hennepin County, Minnesota RESOLUTION NO. 95 -106 RESOLUTION ORDERING A PUBLIC HEARING 1996 RESIDENTIAL STREET IMPROVEMENTS WHEREAS, the City Council authorized and directed the preparation of a report with reference to improvement of certain streets within the Campbell, Peaceful Valley and Westbrooke East neighborhoods, and WHEREAS, the engineering firm of MSA Consulting Engineers has prepared the aforesaid report for the improvement herein described, NOW THEREFORE BE IT RESOLVED by the City Council of Hopkins, Minnesota: Adopted by the City Council of the City of Hopkins this 21st day of November, 1995. ATTEST: 1. The Council will consider the aforesaid improvement in accordance with the report and the assessment of abutting and non - abutting property for all or a portion of the cost of the street improvements along 8th Avenue South (6th to 8th Street South), 7th Avenue South (5th to 8th Street South), 8th Street South (6th to 8th Avenue South), alley east of 6th Avenue South (7th to 8th Street South), Burnes Drive, and Sweet Briar Lane pursuant to Minnesota Statutes Chapter 429 at an estimated total cost of $880,345.00. 2. A public hearing will be held in the Council Chambers of the City Hall at 1010 First Street South on Tuesday, December 19, 1995 at 7:30 p.m. to consider said improvement. The city clerk shall give mailed and published notice of said hearing and improvement as required by law. James A. Genellie, City Clerk By Charles D. Redepenning, Mayor Kirk R. Roessler, P.E. Reg. No. 20389 Ste en D. Gatlin, P.E. City Engineer Reg. No. 12754 FEAS - 158.006 FEASIBILITY STUDY FOR 1996 RESIDENTIAL STREET IMPROVEMENTS HOPKINS, MINNESOTA NOVEMBER 1995 I hereby certify that this plan, specification, or report was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Minnesota. MSA, Consulting Engineers 1326 Energy Park Drive St. Paul, MN 55108 Phone #: (612) 644 -4389 Fax #: (612) 644 -9446 Date Date 158- 006 -10 • • CI S CONSULTING ENGINEERS 1326 Energy Park Drive St. Paul, MN 55108 612-644-4389 1. 800.888 -2923 Fax: 612. 644.9446 CIVIL ENG NEERING Please find enclosed the preliminary feasibility study for the referenced project. This Eti VIRONM report addresses street rehabilitation, storm drainage, and utility repair improvements +u�IC.AI throughout several areas within the City of Hopkins. Also included is a preliminary cost PANNING estimate and preliminary assessment rates for the project. SOLID WASTE STRUCTURAL Please contact our office if you have questions or require further information regarding this SURVEYING project. TRAFFIC TRANSPORTATION Sincerely, EL EC T RICAN /MECHANICAL ENGINEER NG HV AC POWER DISTRIBUTION SCADA SYSTEM CONTROLS OFFICES IN: MINNEAPOLIS PRIOR LAKE ST. PAUL WASECA November 16, 1995 File: 158- 006 -10 Honorable Mayor and City Council City of Hopkins 1010 1st Street Hopkins, MN 55343 RE: FEASIBILITY STUDY 1996 RESIDENTIAL STREET IMPROVEMENTS Dear Mayor and City Council: MSA, CONSULTING ENGINEERS Steven D. Gatlin, P.E. Vice President Attachments 158/006- 1609.nov Reviewed by: Public Works Finance An Equal Opportunity Employer Department Date Transmittal Letter 1 Table of Contents 2 Introduction 3 Scope 3 Existing Conditions 4 Proposed Improvements 6 Easements and Permits 9 Project Cost 9 Financing 10 Assessment 10 Project Schedule 12 Conclusion 13 FEAS - 158.006 CITY OF HOPKINS TABLE OF CONTENTS Exhibits No. 1 and 1A 13 -14 Exhibits No. 2 and 2A 15 -16 Exhibits No. 3 and 3A 17 -18 Exhibits No. 4 and 4A 19 -20 Exhibit No. 5 21 Exhibits No. 6 and 6A 22 -23 Exhibits No. 7 and 7A 24 -25 Appendix A - Preliminary Cost Estimate 26 -2- 158- 006 -10 • • INTRODUCTION This feasibility study is submitted as required under Minnesota State Statute 429 regarding the assessment of proposed public improvements. The City of Hopkins has authorized the feasibility study for the rehabilitation of approximately 5,500 linear feet of streets and approximately 810 linear feet of alleys located within the corporate boundaries of the City. The 1996 Residential Street Improvements Program is part of the City of Hopkins Annual Pavement Management Program. More specifically, the following street and alley segment are proposed to receive improvements: • Sweet Briar Lane (Minnetonka Mills Road to 670 linear feet to the north) • Burnes Drive (Minnetonka Mills Road to Cambell Drive) • 8th Avenue South (8th Street south to 6th Street South) • 7th Avenue South (8th Street South to 5th Street South) • 8th Street South (8th Avenue South to 6th Avenue South) • Alley (Alley located north of 8th Street South and east of 6th Avenue South) The locations of the proposed improvements are presented in Exhibits No. 1 and 1A. This feasibility study investigates street improvements necessary to bring existing roadway surfaces to a condition which conforms to the City of Hopkins residential standard for a 7 -ton per axle loading. This report will provide project costs associated with two (2) different methods of roadway rehabilitation. The proposed methods of surface improvements include complete reconstruction and full width mill and overlay construction. Under those street areas proposed for street reconstruction, this report will investigate and provide recommendation for utility repair and /or replacement work as necessary to insure long term surface integrity. Proposed improvements will not alter existing street dimensions and, upon completion, the new street will meet the City's 7 -ton per axle design criteria. The identified street areas under study are currently zoned as residential. SCOPE The purpose of this report is to analyze the feasibility of rehabilitating various street surface areas as presented on Exhibit's No. 1 and 1A. It is proposed to rehabilitate existing bituminous street surface areas by either a full width mill and overlay operation with miscellaneous concrete curb repair or complete street reconstruction including curb removal and replacement. Storm drainage improvements will consist of structure adjustments necessary in matching new street grades, subgrade draintile construction in those areas showing signs of frost damage or settlement and the new construction of storm sewer in areas where drainage and standing water conditions are an issue. In addition to street and storm drainage improvements, this report will also evaluate underground watermain and sanitary sewer utilities to determine if repair or replacement work is warranted. 4 -inch diameter watermains will be replaced with new 6 -inch diameter watermains, curb stops will be relocated to the property line, lead service lines will be replaced with 1 -inch copper and in general, defective sanitary sewer mains will be removed and replaced with new PVC pipe and sanitary sewer services showing signs of damage or deterioration will be repaired. FEAS- 158.006 158- 006 -10 s Project funding will also be addressed within this report. The costs outlined in this report include an estimated construction cost based upon 1995 construction bids received on similar projects. Also included is a 30 % indirect cost which includes anticipated engineering design and construction costs, administration, legal and fiscal expenses involved with a project of this nature, and a contingency factor. Preliminary assessment rates are included in this report and were prepared in accordance with the City of Hopkins's current assessment policy. Sources for funding proposed improvements include assessments to private and City Park properties, with the remaining project costs to be funded by the City through general tax funds. The following cost splits will be utilized in this report: Cost to Property Owners City Costs Street Reconstruction 70% 30% Street Mill and Overlay 0% 100% Alley Improvements (Reconstruction) 80 % 20 % Alley Improvements (Mill & Overlay) 0% 100% Storm Sewer Construction 0% 100% Sewer and Water Service Repairs 100% 0% Sanitary Sewer Replacement /Repair 0% 100% Watermain Replacement /Repair 0% 100% Remove /Replace Hydrants and Gate Valves 0% 100% • EXISTING CONDITIONS In December of 1990, core samples were obtained by Braun Intertec, Inc. in order to evaluate existing pavement conditions of subject roads and necessary improvements needed to meet the City standard 7 -ton per axle criteria. The City of Hopkins employed Braun Intertec to perform the required tests which consisted of 14 penetration borings located on 8th Avenue South, 7th Avenue South, and 8th Street South. In addition to the penetration borings, visual observations of subject streets were made by MSA, Consulting Engineers, to determine additional construction requirements based upon existing surface pavement conditions. On segments of Sweet Briar Lane and Burnes Drive, as identified by Public Works staff requiring reconstruction, core samples were not obtained. MSA, Consulting Engineers had to rely on visual observations in the field to evaluate existing surface pavement conditions. In those street areas where boring information is available, existing pavement sections generally consist of 2 to 3 inches of bituminous pavement placed over 3 to 5 inches of Class 5 aggregate base materials. At several locations within the project site, boring report information indicated that Class 5 base materials were not encountered. Underlying street subgrade materials primarily consist of a 2 to 3 foot layer of poorly graded sand with silt, placed over a 3 to 4 foot layer of sandy lean clay to clayey sand type material. Core information provided for alley improvements indicates existing pavement section to generally consist of 1 to 3 inches of bituminous pavement placed over 9 to 12 inches of Class 5 aggregate base materials. Subgrade materials are of a very unstable nature and primarily consist of wet black peat near the south end and sandy lean clay near the north end of the alley. FEAS - 158.006 -4- 158- 006 -10 Pavement Condition The 1994 Pavement Condition Index Report, as prepared by Braun Intertec, was reviewed as part of the preparation of this feasibility study. The Pavement Condition Index is a procedure that produces a pavement rating number used to prioritize street improvements and manage the City's overall transportation system. A major objective of prudent pavement management is to identify street sections that are still in fair condition, but need rehabilitation work. The timely identification of streets that need rehabilitation work is more prudent than waiting until the street has aged and deteriorated to the point that reconstruction is the only feasible alternative. Using this approach, street surfaces can be kept at a higher service life for lower long -term costs. Based on the Pavement Condition Index Report, 8th Street, 7th Avenue, and 8th Avenue South have aged and deteriorated to a condition in which major rehabilitation is appropriate. Reconstruction efforts will include measures to decrease the rate of decay in the future. These measures include edge drains, subgrade subcutting and subgrade replacement with clean, well draining granular borrow materials. These additional measures will serve to remove subsurface moisture which is the primary cause of frost heave and soil strength loss. Three (3) additional sections of City street have deteriorated at a lesser rate and at this time, only require the full width mill and overlay alternative. Two (2) additional streets, not discussed in Braun Intertec's Pavement Evaluation report, have been identified by Public Works staff as requiring reconstruction. These street areas, Sweet Briar Lane and Burnes Drive are rural in nature with existing street widths of 30 feet and no curb and gutter. Comparing this area of the project to adjacent street areas reconstructed within the last 5 years, and reviewing Braun Intertec's Pavement Evaluation Report dated October 1990 for Althea Lane, Campbell Drive, Herman Court, and Herman Terrace Street surface areas, we can safety assume that subsurface soil, water table and existing pavement sections are or will be similar. Reconstruction efforts in this area do not need to be as substantial and would include typical reconstruction without the expensive subgrade correction provisions. Storm Drainage Conditions Generally, existing storm drainage improvements within the project site are adequate in size to handle storm water runoff generated from the area. However, MSA's inspection of existing site conditions have uncovered one (1) critical area where storm sewer improvements, as required to remove surface runoff, are necessary in considering long term preservation of street reconstruction improvements. Existing storm sewer with respect to 8th Street South consists of open ditch and culvert pipe along the north side. Ditch grades generally flow to the west, where at the intersection of 8th Avenue South an 18 inch CMP culvert carries storm water runoff under 8th Street South and discharges into City Park property. An open ditch carries storm water runoff from the culvert discharge location to the west where it outlets into Nine Mile Creek. Watermain Conditions An existing 4 inch diameter watermain travels the entire length of 7th Avenue South from 8th Street South to 5th Street South and provides service to those properties abutting the system. By FEAS - 158.006 -5- 158- 006 -10 today's standards, this section of 4 inch diameter watermain is inadequate in size to effectively service the area. Low water pressures, inadequate fire flows, and frequent maintenance repairs are normally a direct result of an older, smaller watermain system. All other watermains within the project site are of adequate size being a standard 6 inch diameter main. Exhibits No. 2 and 2A show existing conditions. Sanitary Sewer Conditions In August of 1988, and August of 1991, existing sewer laterals within the project site were televised by Visu -Sewer Clean & Seal, Inc., in order to evaluate existing sewer conditions to determine if sewer repairs were necessary. The City of Hopkins employed Visu -Sewer to perform the required testing, analyze the acquired data, and prepare a written log report of their findings. MSA, Consulting Engineers has thoroughly reviewed this information and has found that substantial sewer repair work and maintenance is warranted under those streets recommended for total reconstruction. A particular area of critical concern is that section of 18 inch RCP sanitary sewer which is located under 8th Street South and flows from the west to the east. This section of existing trunk sewer includes offset joints, root intrusion, leaking joints, misaligned pipe sections and large sections of sagging pipe. Televised inspection report information indicated most of this sewer to be underwater. Existing conditions are shown on Exhibits No. 3 and 3A. PROPOSED IMPROVEMENTS Street Improvements Proposed street sections throughout the project site will match existing street widths of either 30 feet or 38 feet and will be either reconstructed completely, or rehabilitated by the mill and overlay alternative. The following streets are proposed to be constructed to a total street width of 30 feet back to back of curb: Street Name • Sweet Briar Lane • Burnes Drive • 8th Street South (6th to 8th Avenue South) Improvement /Curb Type Reconstruct /D-412 Reconstruct /D-412 Reconstruct /B -618 The following streets are proposed to be constructed to a total street width of 38 feet back to back of curb: Street Name • 8th Avenue South (8th to 7th Street South) • 8th Avenue South (7th to 6th Street South) • 7th Avenue South (8th to 7th Street South) • 7th Avenue South (7th to 6th Street South) • 7th Avenue South (6th to 5th Street South) FEAS- 158.006 -6- Improvement /Curb Type Mill and Overlay /B -618 Reconstruct /B -618 Reconstruct /B -618 Mill and Overlay /B -618 Mill and Overlay /B -618 158- 006 -10 Significantly deteriorated street sections, such as 7th Avenue, 8th Avenue, and 8th Street South would receive complete reconstruction improvements which would also include subgrade replacement and draintile construction associated with removing moisture from the subgrade. The milling and overlay alternative would be utilized for those streets that can be rehabilitated, but show higher potential for reflective cracking. Pavement typical sections are shown on Exhibits No. 4, 4A, and 4B. The approximate length of streets to be reconstructed is 3,500 linear feet, while the total mill and overlay length is 2,000 linear feet. In addition to street rehabilitation improvements, this report also recommends surface improvements associated with the existing alley located north of 8th Street South and east of 6th Avenue South. Normally, Hopkins City policy requires improving all City alleys with a concrete paved surface. However, this alley segment warrants a bituminous paved surface. Excessive peat depths, as identified in Braun Intertec's Pavement Evaluation Report dated December 1990, and the Alley's close location to an existing wetland area dictate that the construction of a concrete paved surface is not feasible from an engineering standpoint. It is not practical to construct a rigid concrete pavement over such unstable subsoil. In addition to the engineering related issues, long term maintenance effects were also considered in this recommendation. If the alley was constructed of concrete, it is very likely that the pavement would exhibit differential settlement in the future resulting in an uneven surface causing severe maintenance problems. Proposed improvements over this alley section include a combination of the reconstruction and overlay alternatives. It is proposed to reconstruct, to a width of 14 feet, the north -south section of the existing alley. This section of alley, from the north end to the south end, is approximately 480 linear feet in length and is constructed over 4 to 6 feet of wet black peat. Reconstructive efforts would include existing bituminous and aggregate base removal, 2 foot subcut of underlying subgrade materials (primarily black peat), placement of geotextile fabric, 2 foot subgrade replacement with a select granular borrow material, 6 inches of Class 5 aggregate base, and a 2 inch lift of bituminous wear course materials. Further removal of underlying peat materials would make this section of existing alley cost prohibited. The remaining east -west sections of the existing alley also require surface rehabilitation. Moderately deteriorated pavement surfaces and fair to good subgrade materials warrant only a 2 inch mill and overlay at this time. The total length of existing alley to be milled and overlayed is approximately 330 linear feet. Total project costs associated with reconstruction and rehabilitation improvements are presented in the cost section of this feasibility study (Appendix A). Storm Sewer Improvements As noted in the existing conditions section of this feasibility report, one (1) area within the project site will require storm sewer improvements necessary in conveying surface runoff from street areas. Proposed storm sewer improvements along 8th Street South will serve to eliminate standing water conditions, improve pavement strength and overall performance, and provide a finished product which is appropriate for the surrounding neighborhood. Improvements include the construction of catch basins, manholes, pipe aprons as necessary to collect runoff from proposed swale areas lying north of 8th Street, storm sewer pipe ranging in size from 12 inch diameter to 27 inch diameter and partial filling of existing ditch areas to create a drainage swale. In addition FEAS- 158.006 -7- 158- 006 -10 27 inch diameter and partial filling of existing ditch areas to create a drainage swale. In addition to storm sewer improvements, a detention - sediment removal basin may be required prior to discharging storm water runoff into Nine Mile Creek. This issue will be further explored during engineering design with the local governing Watershed District to insure that all criteria are met. Construction costs associated with a detention - sediment removal facility have been included in this report. In addition to storm sewer improvements required for 8th Street South, structure adjustments within other areas of the project site will be necessary to provide surface continuity with the new pavement surface. Proposed storm sewer improvements are presented on Exhibit No. 7. All project costs associated with storm sewer improvements are presented in the cost section of this feasibility study (Appendix A). By regrading Burnes Drive and Sweet Briar Lane and installing concrete curb and gutter, we feel that existing drainage can be improved. Stormwater runoff will be directed to Minnetonka Mills Road where existing storm sewer is available one or two blocks away. Watermain Improvements As noted in the existing conditions section of this feasibility report, 7th Avenue South from 8th Street to 5th Street South has an existing 4 inch diameter watermain below it's street surface. In this report, 7th Avenue South from 8th Street to 7th Street is the only street section recommended for complete reconstruction. Upon completing reconstruction improvements, and with proper maintenance, the City of Hopkins can expect a road surface life of approximately 20 years. Therefore, in order to insure road surface integrity and minimize unnecessary repair, this report recommends upgrading the existing 4 inch diameter system to a larger 6 inch diameter system. Proposed improvements are shown on Exhibit No. 5. Proposed watermain improvements include complete removal of all watermain pipe, hydrants, gate valves, and services to the right -of -way and replacement with a new 6 -inch diameter system. Additional fire hydrants and gate valves will be added to the system as required to standardize. This work is proposed only under that section of 7th Avenue South recommended for reconstruction. Watermain improvement within other areas of the project will primarily consist of repairs and adjustments as needed. Estimated project costs for these repairs and improvements are outlined in Appendix A. Sanitary Sewer Improvements As noted in the existing conditions section of this feasibility report, MSA, Consulting Engineers has thoroughly reviewed televised information as documented by Visu -Sewer Clean & Seal, Inc. dated August of 1988 and August of 1991. The televised reports, as provided by the City of Hopkins, show substantial evidence that miscellaneous sanitary sewer repair work is warranted throughout the project site. As with proposed watermain improvements, this report has focused on those sections of street recommended for complete reconstruction. Proposed sanitary sewer improvements primarily consist of miscellaneous spot repairs on existing 8 inch VCP sewer laterals. One major area of concern, identified in Visu- Sewer's report, is the existing 18 inch RCP trunk sewer located under 8th Street South. This section of trunk sewer provides service to a large area, by the nature of it's size, and could potentially cause severe problems if not replaced. FEAS- 158.006 -8- 158- 006 -10 Proposed improvements include complete removal of approximately 780 linear feet of existing 18 inch RCP sanitary sewer and replacement with new 18 inch PVC pipe. In addition to trunk sewer replacement, two (2) existing manholes will require complete removal and replacement. Construction operations shall provide for a structurally sound system capable of supporting new roadway improvements and eliminating costly repairs. Proposed improvements /repairs are shown on Exhibits No. 6 and 6A. In addition to recommended repair on sections of deteriorated sanitary sewer, the entire line should be cleaned after construction and root treated for those segments showing signs of existing root intrusion. Estimate project costs for sanitary sewer repair and reconstruction work are shown in Appendix A. EASEMENTS AND PERMITS All street and utility construction work will be conducted within existing City park areas and roadway right -of -ways. No additional easements will be required for proposed improvements. As discussed earlier in this report, storm sewer improvements, as well as, sanitary sewer and watermain replacement/repair work is required. The following agencies will require permits for these improvements: • Minnesota Health Department - Watermain construction • Minnesota Pollution Control Agency - Sanitary sewer construction • Nine Mile Creek Watershed District - Storm sewer construction PROJECT COST The estimated construction costs for proposed street improvements are presented in Appendix A included at the back of this report. The estimated indirect cost items such as engineering, city administration, fiscal, legal expenses, and contingency costs have been estimated at 30 %. The following is a summary of the anticipated costs for the project. A. Sweet Briar Lane and Burnes Drive Improvements FEAS - 158.006 Street Reconstruction Sanitary Sewer Repair TOTAL COST $164,530 -9- $139,830 24.700 158- 006 -10 B. 7th Avenue, 8th Avenue, and 8th Street South Improvements FINANCING Street Reconstruction (8th Street South) Street Reconstruction (7th Avenue & 8th Street Mill & Overlay Storm Drainage Improvements Watermain Replacement /Repair Sanitary Sewer Repair City Park - Parking Lot Alley - Reconstruct /Mill & Overlay TOTAL COST GRAND TOTAL ASSESSMENT FEAS - 158.006 - $106,600 Avenue) 238,050 83,135 94,550 62,350 72,150 17,560 41.420 $715,815 $880,345 Based upon an anticipated construction cost of approximately $677,190, the estimated total project cost is $880,345. This cost includes 30% for indirect and contingency costs. The recommended means of financing the rehabilitation of streets within the project site, identified on Exhibits No. 1 and 1A, is through a combination of special assessments to benefitted properties and City financing. The benefitted properties are proposed to be assessed in accordance with the City's current assessment policy. The City will assume a portion of the project costs for street rehabilitation improvements and all project costs associated with the utility maintenance and repairs. Assessments will be paid either upon completion of the assessment hearing or over a period of time established by Council action at a interest rate obtained during the time of bond sale. Estimated assessment rates per lot equivalent are as follows: • Sweet Briar Lane and Burnes Drive Improvements - $3,626 per parcel • 7th Avenue and 8th Avenue South Reconstruction - $4,629 per parcel • Alley - Reconstruction/Mill & Overlay Improvements - $932.80 per parcel Assessments are proposed to be levied against the benefitted properties as outlined in the City of Hopkins current assessment policy for street reconstruction. Contrary to the City of Hopkins' current assessment policy, total project costs associated with 8th Street reconstruction improvements are proposed to be funded by the City. This amendment to the policy will provide for an economically feasible project for those residents abutting 7th Avenue South being assessed for reconstruction improvements. In addition, the City of Hopkins may have a difficult time proving benefit to those properties abutting 6th and 8th Avenues South. 6th Avenue South residents receive no street improvements from the proposed improvements, and 8th Avenue residents receive mill and overlay improvements at no cost. We have discussed this amendment 158- 006 -10 with City staff and believe it provides equitable treatment for all affected property owners. A summary of the assessment policy for such a project is presented below. The assessment rates presented are based upon preliminary cost estimates and will be revised based upon the actual construction costs. Street Reconstruction (8th Street South) 0% 100% Street Reconstruction (All Other Streets) 70% 30% Street Mill & Overlay Improvements 0% 100% Storm Drainage Improvements 0% 100% Watermain Replacement/Repair 0% 100% Sanitary Sewer Replacement /Repair 0% 100% City Park - Parking Lot Improvements 0% 100% Alley - Reconstruction Improvements 80% 20% Alley - Mill & Overlay Improvements 0% 100% Sewer and Water Service Line Repair 100% 0% The methods of determining the assessment per lot equivalent and per front foot are presented below. The preliminary cost estimates are included as Appendix A. As indicated in the above table, residents are not assessed for storm sewer improvements, mill and overlay improvements, City Park improvements, and repair work to existing utilities. An additional item of note is that the assessment amount is based upon the projected construction costs with respect to the City of Hopkins Assessment Policy; yet, conditions of Minnesota Statute Chapter 429 must also be complied with regarding the benefit of the improvement to the affected properties. A. Sweet Briar Lane and Burnes Drive Improvements FEAS - 158.006 Improvements Assessed Amount City Share Street Reconstruction $97,881 $41,949 Sanitary Sewer Repair 0 24.700 TOTALS $97,881 $66,649 Benefitting Parcels = 27 Parcels Assessment per Parcel = $97,881 =27 = $3,626 per parcel or $97,881+2,463.71 LF = $39.73 per LF Assessed City Share 158- 006 -10 • • B. 7th Avenue, 8th Avenue, and 8th Street South Improvements FEAS - 158.006 Improvements Assessed Amount City Share Street Reconstruction (8th Street South) $0 $106,600 Street Reconstruction (All Other Streets) $166,635 $71,415 Street Mill & Overlay 0 83,135 Storm Drainage Improvements 0 94,550 Watermain Replacement /Repair 0 62,350 Sanitary Sewer Replacement /Repair 0 72,150 City Park - Parking Lot 0 17,560 Alley - Reconstruct/Mill & Overlay 13.992 27.428 TOTALS $180,627 $535,188 Benefitting Parcels: Street Reconstruction = 36 Parcels Alley- Reconstruction/Mill & Overlay = 15 Parcels Assessment Rates: Street Reconstruction $166,635 =36 = $4,629 per parcel or $166,635_ 2,393.76 LF = $69.62 per LF Alley- Reconstruction/Mill & Overlay $13,992 =15 = $932.80 per parcel or $13,992+1,017.30 LF = $13.76 per LF PROJECT SCHEDULE City Council Receives Feasibility Report/ November 21, 1995 Public Hearing Date Ordered Public Hearing /City Council Orders Plans and Specifications December 19, 1995 City Council Receives Plans and Specifications/ February 20, 1996 and Sets Bid Opening City Council Receives Bids, Schedule Assessment Hearing March 19, 1996 City Council Holds Assessment Hearing April 16, 1996 City Council Awards Contract May 21, 1996 Construction Begins June 3, 1996 -12- 158- 006 -10 Construction Complete August 30, 1996 CONCLUSION The total project cost of 1996 Residential Street Improvements within the City of Hopkins is estimated at $880,345. The project would be completed in accordance with the schedule provided in this report in the spring and summer of 1996. A portion of the project would be funded through special assessments to the benefitted properties, as previously discussed, with remaining costs to be funded by the City of Hopkins. The 1996 Residential Street Improvements project is technically feasible from an engineering standpoint and will have to further be evaluated by Council whether or not this project is economically feasible. FEAS - 158.006 158- 006 -10 ■••••''''''.' 1) 24 1 24 2 22 3 21 4 20 5 19 1316— 18 1 7 17 8 16 9 15 10 14 11 1321 6TH S nEET 12 24 1 ...:4 ) ) •!..... ;;;. •••*: ....-: ..... ... • • • • • 24 1 0 CP 24 1 0 23. 2' • 23 2 23 --CA 2 22 .. .-;;2. ,Zt. 22 3 22 3 C..:it .,, ',.• .4:;: 4 21 4 21 4 .1:.. 20.% . , 5 20 615 20 5 t4 0 6 19 •,-..; 6 by 19 tr 7 18 . ‘7 18 7 8 17 8 17 8 :•••••••:.:, .......:.:.:. 16 9 16 9 10 m 15 wY/A 10 D 15 -- Ca 10 11 14 ..c 11 14 ----- 11 to 12 < .....::::*": 7 13 12 < 13 STR 12 •*".. r < MILL AND OVERLAY RECONSTRUCTION (11 5TH 8TH STREET STREET ISO. 1 20 19 18 17 16 2 15 14 SO. 1 2 3 4 5 6 7 8 9 10 SO. 14 13 12 11 10 9 S 8 16 63 9 15 1 9 2 3 4 "6 5 6 7 10 14 11 13 12 7, 1 2 3 4 1 6 7 8 9 10 1 2 3 4 4 5 6 7 14 3 13 12 5 (16) 7 '6 ( ( e:Iter (5) (4) 3 2 8 (0 6 5 71 4 3 1 2 PT OU1LOT 1 o 300 1.■=5.0=M5 !SA COMM REES CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS LOCATION MAP HP006—EX1 (4) .M, ( 24 23 22 8 21 ( (5) (9) (1) (2) (3) B C ISA CONSOLTMC ERRORS ST. ---- 0 z m Z w > Q 1 2 .3 2 F- 4 L) Hvv. NO. 7 RECONSTRUCTION CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS LOCATION MAP 0 200 ENINORIT HP006 -EX1 SA CQKSOCTIN NCIIIII>is 22 . < : 6 7 8 60 9 10 j 11 1 j 12 Q 3 2. 5 1 (12) ( (14) (15) (16) 24 23 22 21 20 19 18 17 16 15 14 7TH 13 I c 46 4, 46 45 44 43 42 41 40 39 38 37 35 34 33 32 31 30 29 1 Q 2 3 4 61 5, 6 _ v: I 20 •L. 28 21 27 22 26 23 25 24 I 6" I. 8TH `v 18 7 I 8 17 8 9 16 9 10 15 10 j 11 (i�1 14 11 . t3 STRET 12 a' 4 I- 12 Q 1 2 3 4 5 6 7 8 9 10 11 � 14 15 16 17 18 19 22 21 20 19 24 1 23 2 3 4 5 62 (11) ( ( ( r.` ( ?' ( (2) I 1 i • 3 2 5 6, B [ 1 6 STREET So. 20 19 18 17 16 2 15 14 so. 2 3 4 5 6 7 8 9 10 1 14 13 12 11 10 93 8 16 6 15 14 13 1 O 2 3 4 uJ 5 Z 6 Q 7 10 ( 6 1 2 3 .2 .t_3 I � 5 I L. 2 3 .!,- PT OUTLOT A 1 45 3 13 I 1 2 3 4 6 7 14 12 CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS EXISTING WATERMAIN 0 300 HP006 -EX1 ----- ( 24 23 22 8 21 ( V CONSULTING ENGINEERS ST. d z 1 2 3 = r- 4 10 CITY OF HOPKINS 1996 MRESIDENTIAL STREET IMPROVEMENTS EXISTING WATERMAIN EN IJ OT HP006 -EX1 CONSOLTIRG EXCEEDS 24 1. b H 3 •a: 5 19 8 60 9 m 10 W 11 12 < 24 23 22 21 20 19 18 17 18 15 14 7TH 13 5TH t 2 3 4 615 , '7 8 9 10 D 12 < 0 0 24 23 22 21 20 19 18 17 16 15 14 13 s 1 2 3 4 � 5 Tab 7 8 9 10 11 IFFET 24 23 22 21 20 19 18 17 16 15 14 11i" 18 18" ° 8TH STREET 1 1 SO. 1 2 3 4 62 8 9 0 10 11 (y� T 12 < STREET ■ S0. 20 19 18 17 16 2 15 14 13 • .•12 11 S0. 1 2 3 4 5 6 7 8 9 10 14 13 12 11 10 9 3 8 15 t (n o 2 3 4 W 5 z 6 Q 7 10 e. 3 : 4 co 1 2 3 4 5 0 • (12) (13) (14) (15) (16) 7 `6 46 4, 46 45 44 43 42 41 40 39 38 37 36 35 34 33 - ST 31 30 29 28 26 25 2 3 4 5 6 7 8 10 11 13••\` 14 15 16 17 18 19 20 21 r 22 23 24 03 t� (11) (8) (9) (7) ? ( (4) (2) 6 • bi ' • 3 2 4 5 8 ( 5 2 1 3 4 ,.1 i .. ::)2 PT OUTLOT A • 1 2 3 4 1 5 6 7 a 9 10 2 3 4 4 5 6 7 14 3 13 12 CITY OF HOPKINS 196 RESIDENTIAL STREET IMPROVEMENTS EXISTING SANITARY SEWER 0 300 ENNOBEIT HP006 -EX1 ------ (4) M (8) 24 23 22 8 21 ( 5) ST. 0 z ( ( (2) (3) A Lv D Z B > Q C 1 2 3 = 4 In IN CONSU!IT1 C ENGINEERS CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS EXISTING SANITARY SEWER HP006 -EX1 ROW \1 St CONSULTING ENGINEERS 14' 19' EXISTING B618 C&G 19' MILL 2" OF EXISTING BIT. SURFACE - 2 2341 TYPE 41 BITUMINOUS OVERLAY TYPICAL STREET SECTION 14' NOTE: SPOT SUBGRADE CORRECTION AS DETERMINED IN THE FIELD. MILL ENTIRE STREET WIDTH TO A 2" DEPTH AND OVERLAY TO A 2" DEPTH WITH BIT. WEAR COURSE, 2331 TYPE 41 (SEE EXHIBIT NO. 1A FOR LOCATIONS) CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS STREET SECTION (MILL AND OVERLAY) ROW ENa0 0 05J HP006 -EX1 ** STREETS TO BE RECONSTRUCTED TO A WIDTH OF 38FT BACK TO BACK OF CURB WITH B -618 CURB & GUTTER 8TH AVENUE SOUTH 7TH AVENUE SOUTH * ** STREETS TO BE RECONSTRUCTED TO A WIDTH OF 30FT BACK TO BACK OF CURB WITH B -618 CURB & GUTTER 8TH STREET SOUTH ROW 4" PERFORATED DRAINTILE WITH FILTER WRAP (WHERE REQUIRED) VSL CONSULTING ENGINEERS VARIES 8- 618CURB & GUTTER 1'(TYP) VARIES 30' OR 38' 8 -6 2.002 TYPICAL STREET SECTION 1 1/2" 2331 TYPE 41A BITUMINOUS WEAR COURSE TACK COAT 2" 2331 TYPE 318 BITUMINOUS BASE COURSE 6" CLASS 5 AGGREGATE BASE 24" SUBGRADE CORRECTION, BACKFILLED W /SELECT GRANULAR BORROW, 3149.2B RECONSTRUCT AND SUBCUT (SEE EXHIBIT NO. 1) FOR LOCATION VARIES CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS STREET SECTION (RECONSTRUCTION) ROW HP006 -EX1 * STREETS TO BE RECONSTRUCTED TO A WIDTH OF 30FT BACK TO BACK OF CURB WITH D-412 CURB & GUTTER SWEET BRIAR LANE BURNES DRIVE ROW VARIES D & GUTTER . 30' B-B Z00% 'TYPICAL STREET SECTION RECONSTRUCT (SEE EXHIBIT NO. 1A) FOR LOCATION VARIES 1 1/2" 2331 TYPE 41A BITUMINOUS WEAR COURSE TACK COAT r 2331 TYPE 318 BITUMINOUS BASE COURSE 5" CLASS 5 AGGREGATE BASE ROW CONSULTING ENCINI1RS CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS STREET SECTION (RECONSTRUCTION) nD HP006-EX1 CONSOCTEIC ENGINEERS 8 7 8 60 9 10 j 11 0 12 < — I — 1 5 2 ., _� 1 3 4 1 (12) (13) (14) (15) (16) 24 23 22 21 20 19 18 17 16 15 14 13 A ommta PI IIIIIm =ma] mmu! MINIILIN 5'1 sA l::I !VA Emma MEN 8TH REMOVE AND REPLACE EX. GATE VALVE 5TH 2 3 4 615 , 6 _ b: 8 9 10 j 2 3 4 5 5 7 8 9 10 14 15 16 17 18 19 20 21 r- 22 23 24 STREET STREET . � so. —I — I I— I _ I I —I— !.::.• -•� 2 1 — DD I HYDRANT V /VALVE 3: z 20 19 18 17 16 2 15 14 13 1 2 3 4 5 6 7 8 9 10 1J 1 1 S0. — I— I —LI —I- 14 13 12 t O Cn 2 3 16 11 4 W 10 5 9 3 6 8 15 14 13 7 10 I ATE VALVE 1 4 F- :2 1 3 1 PT OUTLOT A • D:- 1 2 3 4 1 5 6 7 8 9 10 1 2 3 4 5 6 7 14 3 13 12 I - 1— CfTY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS PROPOSED WATERMAIN 0 300 IA> SO. REMOVE AND REPLACE EX. HYDRANT W /VALVE WATERMAIN TO BE REMOVED AND REPLACED WITH 6 "DIA DIP HP006 -EX1 23 19 to 10 M 11 MNININLM IIIINEIN NEMO Esi to NIMMI =ma iismdm INIMI:1 BUIE= MOR 2ii- �� u� g I _ ION nal ��ry rc • 0 • • • 1 24 • 3 i � 4 . '-" 20 ^`' 5 1. 6 1 � i, b 7 8 6 0 12 24 23 22 21 20 19 18 17 16 15 14 7TH 13 5TH 1 O 2 3 4 61s , 6 . b: 7 8 9 10 j 11 Li.1 12 a STREET 24 23 22 21 20 19 18 17 16 15 2 3 4 5 7 8 496 9 10 14 11 13 FEET 19 24 23 22 21 20 18 17 16 9 10 11 13 STR -T a 15 14 1 0 2 3 4 5 62 7 8 I So. 20 19 18 17 16 2 15 14 13, -12 1 1 1 S0. 2 3 4 5 6 7 8 9 10 14 1 N 11 4 W 10 5 13 2 12 3 93 6 8 7 16 63 9 15 10 14 11 13 _ 0 12 1 ` . � 2 3 4 1 5 8 7 8 9 10 2 3 4 4 5 6 7 14 3 is 12 0 2 — 3 4 5 18" (12) ( (14) ? "1 (15) ti (16) ° D 7 '6 (1) 6 5 4. 1 3 2 1 I1 (9) REMOVE EXISTING ■AND REPL (8) NEW T PVC 2 SANITARY SEWER L Y 3 1 • p � r ouTtor a 4 ..:2 • : REMOVE EXISTING A CE WITH 0 300 ND REPLACE WITH CRY SEWER. REMOVE AND REPLACE TWO(2) EXISTING MANHOLES. \1St CONSIllTINC BNCINEBRS CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS PROPOSED SANITARY SEWER EN UO 17 HP006 —EX1 ---- (4) M ( 24 23 21 (7) (5) 22 8 ( (1) (2) (3) c 1 2 3 = I- 4 t.() V St CONSULTINC MHOS ST. d Z D Z B > Q HWY NO. 7 CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS PROPOSED SANITARY SEWER el REMOVE EXE AND REPLACE WITH W 8 "PVC SANITARY SEWER 1 HP006 -EX1 22 c3 24 1 /60 23 • 2 .,.' 5 6 7 8 60 9 10 j 11 W 12 < HMI s MIIMMUI MENEM 11111MM1 j ' E MIIMMM MEW/ =EMMA EMI= MENEM MOM Emma EMMNIM i.1 iL1MMI. MEM.! M• mom NUMMI EMMA MIME MIIMMENI MIEN Emma p is IMMIIIMM WEIIIMMO - X4•1 !s!. (9) (8) ( Eel (2) 5 Erg 8 5 1 24 23 22 21 20 19 18 17 16 15 14 7TH 13 5TH 1 0 2 3 4 615, 6 S: ; 7 8 9 10 11 WL 12 < PROPOSED DETENTION /SEDIMENT REMOVAL FACILITY AREA STREET I I S0. 24 23 22 21 20 19 18 17 16 15 1 2 3 4 5 Tab 7 8 9 10 14 11 13 SIR 24 23 22 21 20 19 18 17 16 1 0 2 3 4 5 62 7 8 9 1 0 II 14 1 1 STRET 1 a 2 15 20 19 18 17 16 2 15 14 11 SO. 1 2 3 4 5 6 7 8 9 10 15" 27' 8TH STREET 15 SO. 14 13 12 11 10 8 16 63 ' 9 15 1 O Cr) 2 3 4 W 5 93 6 w 7 10 14 11 13 4.9 12 (1 6 3 4 ..:z 5 2 PT OUThOT A 1 2 3 4 1 6 7 8 9 10 2 3 4 4 5 6 7 14 3 13 12 0 300 CONSULTING ENGINEERS CITY OF HOPKINS 1996 RESIDENTIAL STREET IMPROVEMENTS PROPOSED STORM SEWER HP006 -EX1 Sweet Briar Lane and Burnes Drive Reconstruction: I. Street Reconstruction Improvements Item Quantity Unit Unit Cost Extended Cost Bituminous Pavement Removal 5,170 SY $3 $15,510 Concrete Pavement Removal 310 SY $6 $1,860 Common Excavation 2,400 CY $5 $12,000 Subgrade Preparation 14.0 Rd Sta $100 $1,400 Class 5 Aggregate Base 2,100 TON $7.50 $15,750 Type 31 Bituminous Base 670 TON $24 $16,080 Type 41 Bituminous Wear 510 TON $26 $13,260 Bituminous Tack Coat 220 GAL $1.50 $330 6" Concrete Driveway Restoration 310 SY $28 $8,680 Concrete Curb and Gutter, D-412 2,340 LF $6 $14,040 Select Topsoil Borrow 180 CY $10 $1,800 Sodding, Lawn, and Boulevard 1,550 SY $2 $3,100 Casting Adjustments 12 EA $150 $1,800 Subgrade Testing 1 LS $450 $450 Bituminous Testing 1 LS $700 $700 Concrete Testing 1 LS $800 $800 Construction Cost $107,560 30% Indirect and Contingency Costs $32,270 Total Reconstruction Cost $139,830 FEAS - 158.006 APPENDIX A Preliminary Cost Estimate City of Hopkins - 1996 Residential Street Improvements -26- 158- 006 -10 II. Sanitary Sewer Repair Remove /Repair Existing 8" VCP Sewer 200 LF $80 $16,000 Connect to Existing Manhole 2 EA $1,500 $3,000 Construction Cost $19,000 30% Indirect and Contingency Costs $5,700 Total Sewer Repair Cost $24,700 FEAS- 158.006 -27- 158- 006 -10 7th Avenue, 8th Avenue and 8th Street South Rehabilitation: I. Street Reconstruction Improvements (7th Avenue & 8th Avenue South) Item Quantity Unit Unit Cost Extended Cost Remove Concrete Curb & Gutter 2,400 LF $3 $7,200 Bituminous Pavement Removal 5,110 SY $3 $15,330 Concrete Pavement Removal 30 SY $6 $180 Common Excavation 2,800 CY $5 $14,000 Subgrade Excavation 4,120 CY $6.50 $26,780 Select Granular Borrow 4,120 CY $10 $41,200 Subgrade Preparation 13.2 Rd Sta $100 $1,320 Class 5 Aggregate Base 2,420 TON $7.50 $18,150 Type 31 Bituminous Base 695 TON $24 $16,680 Type 41 Bituminous Wear 570 TON $26 $14,820 Bituminous Tack Coat 170 GAL $1.50 $255 6" Concrete Driveway Restoration 30 SY $28 $840 Concrete Curb & Gutter, B -618 2,440 LF $6.50 $15,860 Select Topsoil Borrow 160 CY $10 $1,600 Sodding, Lawn & Boulevard 1,650 SY $2 $3,300 Perforated Drain Tile 200 LF $7 $1,400 Casting Adjustments 15 EA $150 $2,250 Subgrade Testing 1 LS $450 $450 Bituminous Testing 1 LS $700 $700 Concrete Testing 1 LS $800 $800 Construction Cost $183,115 30% Indirect and Contingency Costs $54,935 Total Reconstruction Cost $238,050 FEAS- 158.006 -28- 158- 006 -10 II. Street Reconstruction Improvements (8th Street South) Item Quantity Unit Unit Cost Extended Cost Bituminous Pavement Removal 2,100 SY $3 $6,300 Common Excavation 1,850 CY $5 $9,250 Subgrade Excavation 1,850 CY $6.50 $12,025 Select Granular Borrow 185 CY $10 $18,500 Subgrade Preparation 7.20 Rd Sta $100 $720 Class 5 Aggregate Base 1,100 TON $7.50 $8,250 Type 31 Bituminous Base 290 TON $24 $6,960 Type 41 Bituminous Wear 220 TON $26 $5,720 Bituminous Tack Coat 110 GAL $1.50 $165 Concrete Curb & Gutter, B -618 1,200 LF $6.50 $7,800 Select Topsoil Borrow 80 CY $10 $800 Sodding, Lawn & Boulevard 900 SY $2 $1,800 Perforated Drain Tile 300 LF $7 $2,100 Casting Adjustments 6 EA $150 $900 Subgrade Testing 1 LS $300 $300 Bituminous Testing 1 LS $400 $400 Construction Cost $81,990 30% Indirect Contingency Costs $24,600 Total Reconstruction Cost $106,600 FEAS - 158.006 -29- 158- 006 -10 III. Street Mill and Overlay Improvements Item Quantity Unit Unit Cost Extended Cost Remove Existing Concrete Curb 400 LF $3.50 $1,400 Mill Bituminous Surface 7,500 SY $2.50 $18,750 Subgrade Correction 750 SY $10 $7,500 Subgrade Preparation 19.8 Rd Sta $100 $1,980 Type 41 Bituminous Wear 1,000 TON $26 $26,000 Bituminous Tack Coat 400 GAL $1.50 $600 Concrete Curb & Gutter, B -618 400 LF $10 $4,000 Sodding, Lawn & Boulevard 160 SY $2 $320 Casting Adjustments 16 EA $150 $2,400 Bituminous Testing 1 LS $700 $700 Concrete Testing 1 LS $300 $300 Construction Cost $63,950 30% Indirect and Contingency Costs $19,185 Total Street Mill & Overlay Cost $83,135 FEAS - 158.006 -30- 158- 006 -10 IV. Storm Drainage Improvements Item Quantity Unit Unit Cost Extended Cost Clearing 4 EA $200 $800 Grubbing 4 EA $200 $800 Remove Existing 18" CMP Culvert 220 LF $7 $1,540 Granular Foundation Material 300 TON $12 $3,600 12" RCP Storm Sewer, CL III 58 LF $26 $1,510 15" RCP Storm Sewer, CL III 550 LF $28 $15,400 18" RCP Storm Sewer, CL III 98 LF $30 $2,940 21" RCP Storm Sewer, CL III 320 LF $32 $10,240 27" RCP Storm Sewer, CL III 120 LF $35 $4,200 15" RC Pipe Apron 4 EA $350 $1,400 27" RC Pipe Apron 1 EA $700 $700 48" Diameter Manhole, 0 -8' Deep 8 EA $1,200 $9,600 24" x 36" Catch Basin, 0 -8' Deep 3 EA $1,000 $3,000 Random Rip -Rap 20 CY $60 $1,200 Subgrade Testing 1 LS $800 $800 Detention/Sediment Removal Facility 1 LS $15,000 $15,000 Construction Cost $72,730 30% Indirect and Contingency Costs $21,820 Total Storm Sewer Cost $94,550 FEAS -158 006 -31- 158- 006 -10 V. Watermain Replacement /Repair Item Quantity Unit Unit Cost Extended Cost Connect to Existing Watermain 2 EA $1,500 $3,000 Remove Existing 4" Watermain 680 LF $6 $4,080 Remove Existing Hydrant 1 EA $350 $350 Remove Existing Gate Valve 2 EA $100 $200 Furnish & Install 6" DIP, CL 52 730 LF $26 $18,980 Hydrant With Gate Valve 6" Gate Valve 2 2 EA EA $1,700 $500 $3,400 $1,000 Reconnect Existing Services 16 EA $300 $4,800 Remove Existing Lead Service 280 LF $5 $1,400 Remove Existing Curb Stop 7 EA $50 $350 Furnish and Install 1" Service Connection 7 EA $400 $2,800 Furnish and Install 1" Copper Service 280 LF $12.50 $3,500 Fittings 1,000 LBS $1.50 $1,500 Granular Foundation Material 150 TON $12 $1,800 Disinfection Testing 1 LS $500 $500 Subgrade Testing 1 LS $300 $300 Construction Cost $47,960 30% Indirect and Contingency Costs $14,390 Total Watermain Cost $62,350 FEAS - 158.006 -32- 158- 006 -10 VII. City Park - Parking Lot Improvements Item Quantity Unit Unit Cost Extended Cost Bituminous Pavement Removal 680 SY $3 $2,040 Mill Bituminous Surface 500 SY $2.50 $1,250 Common Excavation 230 CY $5 $1,150 Class 5 Aggregate Base 280 TON $7.50 $2,100 Type 31 Bituminous Base 95 TON $24 $2,280 Type 41 Bituminous Wear 140 TON $26 $3,640 Bituminous Tack Coat 40 GAL $1.50 $60 Striping 1,000 LF $0.50 $500 Sodding, Lawn & Boulevard 120 SY $2 $240 Bituminous Testing 1 LS $250 $250 Construction Cost $13,510 30% Indirect and Contingency Costs $4,050 Total City Park Costs $17,560 VI. Sanitary Sewer Replacement /Repair Item Quantity Unit Unit Cost Extended Cost Remove /Repair Existing 8" Sewer 130 LF $80 $10,400 Remove /Replace Existing Manhole 2 EA $2,000 $4,000 Remove /Replace Existing 18" Sewer 780 LF $45 $35,100 Connect to Existing Manhole 4 EA $1,500 $6,000 Construction Cost $55,500 30% Indirect and Contingency Costs $16,650 Total Sanitary Sewer Cost $72,150 FEAS - 158.006 -33- 158- 006 -10 VIII. Alley Reconstruct /Mill & Overlay Improvements Item Quantity Unit Unit Cost Extended Cost Bituminous Pavement Removal 1,100 SY $3 $3 ,300 Mill Bituminous Surface 750 SY $2.50 $1,875 Common Excavation 300 CY $5 $1,500 Subgrade Excavation 640 CY $6.50 $4,160 Select Granular Borrow 640 CY $10 $6,400 Subgrade Preparation 8.1 Rd Sta $100 $810 Class 5 Aggregate Base 350 TON $7.50 $2,625 Type 41, Bituminous Wear 200 TON $26 $5,200 Geotextile Fabric 1,200 SY $3.50 $4,200 Sodding, Lawn & Boulevard 320 SY $2 $640 Seeding 0.25 AC $2,000 $500 Subgrade Testing Bituminous Testing 1 1 LS LS $300 $350 $300 $350 Construction Cost $31,860 30% Indirect Costs $9,560 Total Alley Cost $41,420 FEAS - 158.006 -34- 158- 006 -10