Loading...
CR 94-36 Oakridge S ST Reconstruction 1; Y 0 \ <J "'" . February 10, 1994 ~ Council Report: 94-36 ",.. "" o P K \ '" OAKRIDGE SOUTH STREET RECONSTRUCTION ACCEPT FEASIBILITY REPORT ORDER PUBLIC HEARING Proposed Action. Staff recommends adoption of the following motion: "Move to accept the feasibility report prepared bv Bolton and Menk as ordered on November 2 , 1994 and that Resolution 94-18 be adopted ordering a public hearinq on March 15, 1994. .. Overview. The City Council at its regular meeting of November 2, 1994 was presented with a staff report regarding the possible reconstruction of the streets in the Oakridge South Area. This report was the first opportunity Council had to discuss this potential project since it was originally discussed during the implementation of the 1994-98 Capital Improvement Plan. Staff recommended in the report that Council . consider reconstructing these streets, as proposed ln the C.I.P. and authorize Bolten and Menk to prepare a feasibility report on the potential street reconstruction. council subsequently concurred with staff's recommendation and ordered Bolten and Menk to prepare a feasibility report on this matter. Bolten and Menk have completed their report and have determined the project to be feasible. The process they used in determining the feasibility of the project included two information meetings with the property owners, and many other meetings with individual property owners. Council is at a point where they should consider accepting the feasibility of the report and ordering a public hearing. Primary Issues to Consider 0 What are the current conditions of the streets in this area? 0 Should the Council accept the feasibility report? 0 Should the council order a public hearing? supportinq Information 0 Analysis of Issues 0 Resolution No. 94-18 0 Feasibility Report . ~~~ Lee Gustaf n, P lie Works Director . Analvsis of Issues 0 What are the current conditions of the streets in this area? The streets within the Oakridge South area are aged and exhibit wear and distress due to traffic loadings. This 1S illustrated by alligator cracking, potholes, and the exposure of pavement aggregates. A recent pavement deflection analysis of all the streets in this area confirmed that all the streets in this area should be reconstructed except for Elmo Road. The deflection analysis concluded that Elmo Road was in good shape and did not presently need any sort of rehabilitation. The lack of adequate storm sewer in this area 1S fairly obvious and is evident by the flow characteristics within the streets. The water and sanitary systems are in fairly good shape, and only require minor repairs. Street lighting in this area appears to be adequate. On and off street parking appears to be adequate for the area. Much of the area has adequate off street parking, and as such, the property owners would like to prohibit on street parking. Robinwood Lane north of 5th street is the only street where on . street parking is needed. A reconstructed street with a width wider than the existing street could easily accommodate on street parking for this section of Robinwood Lane. 0 Should the Council accept the feasibility report? Representatives from Bolton and Menk will be present at the Council meeting to make an oral presentation of their feasibility report, a copy of which is attached. Staff finds the report to be complete and recommends its acceptance. 0 Should the Council order a public hearing? Council ordered the report to be prepared without the benefit of a petition. Informational hearings have been held with the property owners, and it appears there is general support for the project. However, Council would most certainly feel more comfortable proceeding on the project if it heard directly from the property owners. Staff therefore recommends Council order a public hearing for March 15, 1994 for this purpose. As Council is aware, the public hearing is also a mandatory step in the assessment process, and this public hearing would fulfill this requirement if the project was to proceed forward. . --- -- ----- --- ----- . CITY OF HOPKINS Hennepin county, Minnesota RESOLUTION NO. 94-18 RESOLUTION ORDERING A PUBLIC HEARING TO CONSIDER RECONSTRUCTING THE STREETS WITHIN THE OAKRIDGE SOUTH AREA WHEREAS, the City Council authorized and directed the preparation of a report with reference to improvement of the streets within the Oakridge South area; and WHEREAS, the engineering firm of Bolton and Menk, Inc. has prepared the aforesaid report for the improvement herein described. NOW THEREFORE BE IT RESOLVED by the city Council of Hopkins, Minnesota: 1. The Council will consider the aforesaid improvement in accordance with the report and the assessment of abutting the non-abutting property for all or a portion of the cost of the street improvements within the Oakridge South area pursuant to Minnesota statutes . Chapter 429 at an estimated total cost of the improvement of $277,953.50. 2. A public hearing will be held in the council Chambers of the City Hall at 1010 First street South on Tuesday I the 15th of MarchI 1994 at 7:30 p.m. to consider said improvement. The city clerk shall give mailed and published notice of said hearing and improvement as required by law. Adopted by the city council of the city of Hopkins this 15th day of February, 1994. By Charles D. Redepenning, Mayor ATTEST: Jim Genellie, city Clerk . ~~ E30 L TOf'.-J & ~E:F'JI<I I ............ C. Consulting Engineers & Surveyors ., 201 W. Travelers Trail · Burnsville, MN 55337 Phone (612) 890-0509 · FAX (612) 890-8065 February 9, 1994 Honorable Mayor and City Council City of Hopkins 1010 1st Street South Hopkins, MN 55343-7573 Re: Oakridge South Street Reconstruction City Project No. 93-17 Hopkins, MN Council Members: In accordance with your request, the following feasibility report has been prepared for the reconstruction of the streets in the Oakridge South area. As a part of the study of this area, e public utilities were also analyzed as to the capacity and structural integrity of each. Necessary utility improvements have also been recommended. Through the process of studying the existing situation in the Oakridge South area, meetings were held and input was received from area residents, City util1ty personnel and other City staff members. We would like to acknowledge the cooperation and infonnation received and thank all parties for their support in helping us to thoroughly understand the problems and concerns within the project area. I will attend the February 15th Council meeting for the purpose of presenting this report and responding to any questions or concerns that YOll may have. Respectfully submitted: ~a.~ on A. Rippk, .E. Project Manager JAR/dc . MANKATO, MN FAlr~MONT, MN SLEEPY EYE, MN BURNSVILLE, MN AMES, lA i1n E',7uui C'I i/-~',-'(liJI7IIV ElfI/-'/.,"\ei . FEASlliILITY REPORT OAKRIDGE SOUTH . STREET RECONSTRUCTION HOPKINS, MN CITY PROJECf #93-17 FEBRUARY 9, 1994 . - - --- ----- . CERTIFICATION SHEET I hereby certify that this plan, specification or report was prepared by me or under my direct supervision, and that I am a duly Registered Professional Engineer under the laws of the State of Minnesota. ') "')>-1 j ,';" d .c <;_ ;:']--7" '-{( P (/ <:(J 1;{ Ronald A. Roitzel Date: ~~ /.91 ~('I(/ Reg. No. J8986 . I hereby certify that this plan, specification or report was prepared by me or under my direct supervision, and that I am a duly Registered Professional Engineer under the laws of the State of Minnesota. ~ ~' C-~- i .. J~n ~pp:e" ";A~ Date: ,:]/9 /;'/1 Reg. No. 11577 . . TABLE OF CONTENTS PAGE TITLE SHEET CERTIFICATION SHEET TABLE OF CONTENTS TYPE OF WORK 1 BACKGROUND 1 EXISTING CONDITIONS 2 Streets Watermain Sani tary Sewer Storm Sewer e PROPOSED IMPROVEMENTS 6 Bituminous Streets Watermain Sanitary Sewer Storm Sewer Sidewalks Driveway Aprons Street Signing Street Lighting Turf Restoration ESTIMATED COST AND ASSESSMENT RATE 10 RIGHT -OF- WAY IEASEMENTSIPERMITS 12 PROJECT SCHEDULE 12 FEASIBILITY AND RECOMMENDATION 12 . . FEASffiILITY REPORT STREET RECONSTRUCfION OAKRIDGE SOUTH AREA CITY PROJECT NO. 93-17 HOPKINS, MINNESOTA 1. TYPE OF WORK This report examines the reconstruction of the existing streets including the addition of new concrete curb and gutter, turf restoration and appurtenant sewer work in the Oakridge SOllth area. Specifically the project involves: 1. Bituminous street reconstruction and turf restoration along Robinwood Lane, 5th Street and Elmo Service Road. 2. New sanitary sewer extension to the Elmo Park Water Treatment Plant; 3. New storm sewer improvements along 5th Street and Elmo Service Road; 4. Sanitary sewer repair along Robinwood Lane; and e 5. Relocation and replacement of existing valves and hydrants. 2. BACKGROUND This report was ordered by the City Council on October 28, 1993. Council Resolution No. 93- 181 was passed requesting that a study be made for the improvement of the streets in the area known as Oakridge South. The improvements to be considered are: reconstruction of the bituminous street; improved drainage through storm sewer system extensions and concrete curb and gutter construction. As a part of this study, underground utilities were to be checked for adequacy and structural integrity. The project location is shown in Figure 1. Two neighborhood meetings were held for the purpose of informing the affected property owners about the improvements being considered and receiving their comments about problems and concerns to be addressed. Also, separate meetings were held with the owners of the Hopkins House, Elmo Park Apartments and MGM Liquors. These individual meetings afforded opportunities to discuss issues directly effecting their respective properties and operations. Minutes from both of the neighborhood meetings, as well as notes from meetings with various individual property owners are located in Appendix B. . OAKRIDGE SOUTH PAGE 1 . 3. EXISTING CONDmONS The Oakridge South area is a combination of single family and multi-family residential areas along Robinwood Lane and Elmo Road together with commercial areas along 5th Street and the North Service Drive of Trunk Highway (TH) No.7. The Elmo Park Water Treatment plant is located on the north side of the Elmo Service Road. 3.1 Streets The streets within the Oakridge South area are presently classified as local/collector type streets with bituminous surfacing. There is off-street, 900 angle parking adjacent to the streets to serve the many apartment dwellings throughout the area. The streets within the project area are aged and exhibit wear and distress due to traffic loadings. This is illustrated on the surface by alligator cracking, pot holes and the exposure of pavement aggregates. Deflection testing analysis was completed by Braun Intertec in December 1993 on all of the roadways in the project area. A summary of the existing pavement sections is listed in Table 1. Table 1 . Summary Existing Pavement Section 5th Street Robinwood Lane Elmo Service Elmo Road Road Street Width 36' ~50' 30' -44' 20' Pavement Section: Bituminous 4y:t 311z' I 4" 5" Aggrega te Base 2112" 9"-14" 2YS" 3'-10' Subgrade Sand/Clay Sandy Clay & Loam Sand/Clay Clay Bituminous curb presently exists along Robinwood Lane from 5th Street to Hopkins Crossroads as well as along the east edge of the Elmo Service Road. Concrete vertical curb presently exists along Elmo Road following the perimeter of each parking bay opening. The existing street layout is shown on Figure 2. . OAKRIDGE SOUTH PAGE 2 . 3.2 Watermain The existing watermain within the project area ranges in diameter from 6 inch to 16 inch. Watermain, as shown in Figure 3, is located: 1. From the Elmo Park Water Treatment plant, south along the Elmo Service Road to Robinwood Lane, then continues south along Robinwood Lane; 2. Along the east-west leg of the Elmo Service Road; 3. Along Robinwood Lane from 5th Street to Hopkins Crossroads; 4. Along the North Service Road of TH No.7; 5. Along the east boulevard of Hopkins Crossroads completing the loop around the Oakridge South area. A private 6 inch lateral watermain exits along Elmo Road and dead ends at the most interior parking area. A single meter is located at the intersection of Elmo Road and the North Service Drive of TH No.7. City staff has determined that this watermain is a private service line. . A review of the Water Utility Master Plan dated March, 1990, suggests some improvements to the Elmo Park Water Treatment Plant which are presently under construction and beyond the scope of this report. The fire flows were deemed adequate for this area at the time of the master plan report. Fire hydrant pressure tests are recommended to confirm availability of adequate fire flows. Many private services have been replaced with copper service lines from the watermain in the street to the building connection. These replacements are primarily due to the age and extensive usage of these lines. Owners along the project area are encouraged to check the material type of their service line as well as its age and condition, and review for possible replacement in conjunction with this project. 3.3 Sanitary Sewer The existing sanitary sewer within the project area is 8-inch diameter vitrified clay pipe (Vep) with some lengths along Hopkins Crossroads being cast iron pipe (CIP). The sanitary sewer, as shown in Figure 3, is located: 1. Along the centerline of Robinwood Lane from Hopkins Crossroads to the North Service Road of TH No.7; . OAKRIDGE SOUTH PAGE 3 . 2. In the east boulevard of Hopkins Crossroads from Robinwood Lane to the North Service Drive of TH No.7; 3. In the north boulevard of the North Service Drive of TH No.7 from Hopkins Crossroads to Elmo Road; 4. Under TH No.7 from the North Service Drive, (approximately 115' east of the Elmo Road intersection) to the South Service Drive (at the intersection of 14th Avenue) and serves as the outlet for the Oakridge South area as well as the potential development of 50i: acres to the north and east. A private 8-inch diameter sanitary sewer is located along the centerline of Elmo Road. Due to the fact that this sewer is privately owned and maintained, no further analysis of this line was completed under this study. A review of the Sanitary Sewer Utility Master Plan, dated March, 1990, indicated problem areas in the sanitary sewer along Robinwood Lane from 5th Street to Hopkins Crossroads. These deficiencies included slight vertical and horizontal misalignment, cracked pipe and minor roots in the pipe joints. The sanitary sewer system in the Oakridge South area, (except the line along Elmo Road) was televised in October, 1993. A review of the televising report . confirms the deficiencies in the sewer line along Robinwood Lane as described above. The sanitary sewer condition was evaluated and recommended improvements are discussed later in this report. 3.4 Storm Sewer A 12 inch diameter reinforced concrete pipe storm sewer presently collects runoff water along Robinwood Lane from the Hopkins Crossroads to the North Service Drive. From this point, the storm sewer flows south under TH 7 through an existing 12 inch diameter storm sewer. Another 12 inch diameter storm sewer serves as the outlet for the existing backflushing pond for the Elmo Park Water Treatment plant and connects to the 15 inch diameter storm sewer at Robinwood Lane. Storm sewer is also present just outside the project area along the North Service Drive at the intersections with Robinwood Lane, Elmo Road and the Elmo Service Road. Private storm water inlets exist along the east side of Robinwood Lane which abuts the Elmo Park Apartments. These inlets are french drains and presently do not appear to be connected to the existing storm sewer system. There is an existing drain tile connected at the private catch basin in the e northwest corner of the Elmo Park Apartment property and appears to flow OAKRIDGE SOUTH PAGE 4 . to the northeast. This tile line will be investigated further in the design phase. It was noted at the neighborhood meeting of January 26, 1994, that there is a drainage agreement between the golf course property and the Elmo Park Apartments property. There is no storm sewer serving the Elmo Road area. Presently, surface water flows overland easterly and southerly to the intersection of the North Service Drive of TH 7 and Elmo Road. There is no storm sewer serving the Elmo Service Road area. Presently, surface water flows overland in an easterly and southerly direction to the Elmo Service Road intersection with the North Service Drive of TH 7. The 15 inch storm sewer tlowing south between manholes 9 to manhole 10 in Robinwood Lane connects to the manhole at the North Service Drive at an elevation approximately 1 foot lower than the outlet pipe in the same manhole. This elevation difference restricts the flow in the sewer and contributes to storm sewer backup problems. Thus, this line has been reviewed for replacement in order to eliminate the flow restriction. The existing storm sewer layout is illustrated on Figure 4. . I . OAKRIDGE SOUTH PAGE 5 . 4. PROPOSED IMPROVEMENTS 4.1 Bituminous Streets Robinwood Lane from the North Service Drive of TH 7 to Hopkins Crossroads, 5th Street from Robinwood Lane to Hopkins Crossroads and the Elmo Service Road from Robinwood Lane to the North Service Drive are all functionally classified as local/collector type streets and, as slich, are proposed to be designed and constructed to a 9-ton standard. Elmo Road is functionally classified as a local street and presently meets the structural capacity of a 9-ton design. Therefore, no street improvements for Elmo Road are recommended at this time. The street improvements are shown in Figure 2 and described as follows: . 5th Street - In order to improve area drainage, 5th Street will be reconstructed with a new vertical alignment. Concrete curb and gutter will be constructed along both sides of the street to direct surface water to the catch basins. Driveover curb will be installed along the perpendicular off-street parking areas. The street width is proposed at 36 feet (measured face-of-curb to face-of-curb), centered within the 50' right-of-way. This section of 5th Street is presently designated as . a no-parking area. . Elmo Setvice Road - Due to the lack of structural integrity, Elmo Service Road is recommended for reconstruction. The vertical alignment will approximate the inplace alignment in order to match the existing parking areas. Concrete curb and gutter win be constructed along both sides of the street to direct surface water to the catch basins. Driveover curb will be installed along the perpendicular parking areas. The street width is proposed at 26 feet (measured face- of-curb to face-of-curb), centered within the 30' right-of-way along the north and east segments and shifted to match the west line of the 30' right-of-way along the west segment just north of Robinwood Lane. . Robinwood Lane ~ For the segment north of 5th Street, the bituminous surface will be removed and the majority of the aggregate base will be left in place. The bituminous surface will be replaced together with 3- inches of new aggregate base to conform with the existing vertical alignment. For the segment south of 5th Street, the bituminous surface and aggregate base will be removed, the street regraded and a much stronger pavement section constructed to provide for the increased truck traffic projected for this segment. e OAKRIDGE SOUTH PAGE 6 . Concrete curb and gutter will be constructed along both sides of the Robinwood Lane in order to help define the edge of the roadway and to direct stormwater runoff to the catch basins. Driveover curb will be installed along the perpendicular off-street parking areas. The existing street width is proposed to be narrowed to 36 feet (measured face-of- curb to face-of- curb) between the North Service Drive and Elmo Service Road with the east curb line 4 feet from the east right-of-way line in order to match the Elmo Service Road to the north. Robinwood Lane from the Elmo Service Road to Hopkins Crossroads will be widened to 36 feet (face-of-curb to face-of-curb) centered within the 50' right-of-way. The proposed pavement sections and street widths are described in Table 2 below. Pavement section designs are influenced by the load bearing capability of the inplace aggregate base and subgrade soils. Table 2 Proposed Pavement Section 5th Street Robinwood Lane Elmo Service . Road South of 5th North of 5th Street Width: 36' 36' 36' 26' Bituminous 6"(1) 6" 4" 4" I Aggregate Base 8r1 8" Existing(2) 6" (1) Depth of material; inches (2) Will include 3 inches of virgin material and 6 inches of existing material. Along the existing bituminous offstreet parking areas, street construction will extend 3 feet beyond the back of the proposed curb. The balance of the parking area may be reconstructed by each property owner with costs assessed directly back to the individual owner. The estimated cost for bituminous parking lot reconstruction is $12.00 per square yard and the estimated cost for concrete curb and gutter is $6.00 per linear foot. 4.2 Water The existing trunk and lateral watermain network within the project area (see Figure 3) is deemed adequate based on the Water Utility Master Plan, dated . March 1990. OAKRIDGE SOUTH PAGE 7 . The fire hydrants located at the intersection of 5th Street and Robinwood Lane and 5th Street and Hopkins Crossroads are proposed to be replaced and relocated behind the proposed curb. A number of existing valves and hydrants in the area are proposed to be replaced under this project. As the property owners review the condition of their existing service lines, some of these lines may be replaced from the main to the building. This, however, is up to each individual property owner since the entire cost is their responsibility. 4.3 Sanitary Sewer The existing sanitary sewer within the project area (see Figure 3) was televised in October 1993. A review of the video tape and its accompanying report indicated that there are some sags, open and misaligned joints and cracked pipe along Robinwood Lane from the North Service Drive of TH 7 to just north of 5th Street. The area north, from 5th Street to Hopkins Crossroads along Robinwood Lane, exhibits root growth in the pipe joint, extensive roots at a service connection and cracked pipes in several locations. The sanitary sewer along Robinwood Lane has been identified by the Sewer Utility Master Plan as a problem area. This was probably due to the roots in the joints on the north end, the sags in the pipe line on the south end and grease build up e in the line, all of which restrict flow. Mineral deposits were also noted in some pipe joints on Robinwood Lane from 5th Street to the North Service Drive of TH 7. These deposits are a sign of groundwater infiltration during periods of high water table conditions. It is recommended that the pipe section just north of Manhole 75 (Robinwood I Lane - just north of the North Service Drive) containing a significant sag and off-set joint be replaced. The pipe lengths with root growth at the joints (Robinwood Lane - 5th Street to Hopkins Crossroads) should be considered for chemical treatment and grouting either in conjunction with this project or separately by City staff. All other minor sags and cracked pipe presently cause only minor flow restrictions and do not warrant replacement at this time. City staff however, should continue to maintain cleaning efforts throughout these sewer lines. A new 8 inch sanitary sewer line is proposed from Robinwood Lane north along Elmo Service Road to the Elmo Park Water Treatment Plant holding pond. This sewer will provide an outlet for the future wastewater discharged from the water treatment plant. In order to correct the severe vertical pipe deflection causing significant flow . restriction within the existing line and to provide increased capacity, a 12 inch OAKRIDGE SOUTH PAGE 8 . pve sanitary sewer line is proposed for placement under TH 7. This sewer will be placed in a 20 inch steel casing pipe that will be jacked and augured under TH 7 in order to avoid disruption of traffic. 4.4 Storm Sewer The storm sewer along Robinwood Lane (see Figure 4) from the North Service Drive of TH 7 to the Hopkins Crossroads was also televised in October 1993. This report indicated that the pipe condition is fairly good with some isolated areas of minor cracked pipe. This report also noted sand filling one-quarter to one-half of the pipe between manholes 4, 5 and 6 along Robinwood Lane. It is recommended that this pipe be cleaned out as it is creating a flow restriction. The inlet invert in manhole 10 is approximately 1 foot lower than the outlet invert. Therefore, the section of 15 inch sewer between manholes 9 and 10 along Robinwood Lane (see Figure 4), is presently operating under pressure- flow conditions causing upstream flow restrictions. In order to improve the condition at manhole 10, and to maintain the same pipe capacity, this Hne is recommended to be replaced with an 18 inch sewer pipe. Many of the inplace catch basins along Robinwood Lane will not be located . within the proposed curb line. With the widening of Robinwood Lane from 30' to 36', the proposed catch basins will be reconstructed in the curb line. New grates and curb boxes will be installed on the catchbasins. There were no complaints at the neighborhood meetings regarding flooding due to stormwater runoff and there is no long range plan to improve the 12 inch sewer outlet pipe under TH 7. Also, the Storm Water Master Plan dated August, 1990, did not indicate any problems in this area. Therefore, it is recommended that the inplace system rem am and catch basins be reconstructed at the new curb lines. A new 12 inch and 15 inch storm sewer is planned for 5th Street, extending approximately 200 feet west from the existing storm sewer at the intersection of Robinwood Lane. This is to facilitate the new street grades in this area and to promote drainage away from the existing building and into the street. A new 12 inch to 18 inch storm sewer is planned for the Elmo Service Road from the North Service Drive of TH 7 northerly to the northeast corner of Elmo Service Road. This is to catch the overland surface flow along Elmo Service Road and to provide a possible future connection point to the north. The location of proposed storm sewer construction is shown on Figure 4. . OAKRIDGE SOUTH PAGE 9 . 4.5 Sidewalks In order to meet the American Disabilities Act (ADA) guidelines, pedestrian ramps are proposed to be constructed in the existing sidewalk along Elmo Road. City staff has deemed all other existing sidewalks within the project area as access walks to private residences and would not need to meet the ADA guidelines. The sidewalk improvements are shown on Figure 2. 4.6 Driveway Aprons For those driveways to residences along Robinwood Lane north of 5th Street, a six-inch (6") thick concrete driveway apron is proposed for the full driveway. The concrete apron will extend 5 feet from the back of curb. Those driveways connecting existing bituminous parking lots will be replaced with bituminous pavement. The proposed driveway apron improvements are shown on Figure 2. 4.7 Street Signing The existing street signing, including stop signs and street name signs wi]] be removed and replaced by the contractor. Additional "NO P ARKlNG" signs are proposed along the west side of Robinwood Lane from the North SeIVice . Drive to 5th Street and along Elmo Service Road all as agreed by the adjacent property owners. 4.8 Street Lighting Existing street lighting will remain in place and no improvements are scheduled at this time. Some poles may need to be relocated in order to facilitate the construction of the proposed street section. 4.9 Landscaping and Turf Restoration In order to provide a more aesthetically desirable entrance into the Oakridge South neighborhood, trees are proposed along the west side of Robinwood Lane between the North SeIVice Drive and 5th Street and also along 5th Street between Hopkins Crosstown and Robinwood Lane. To facilitate the proposed trees, additional buffer areas will be constructed along 5th Street as well as along Robinwood Lane between the North Service Drive and 5th Street. The turf area behind the curb will be restored with sod following the placement of topsoil. Those areas behind the curb which are presently bituminous will be replaced with bituminous. See Figure 5 far a typical proposed street cross section along Rabinwood Lane just north of North Service Drive and Figure 6 for a before and after layaut of 5th Street. The landscaping and turf restoration costs are included in the street costs. . OAKRIDGE SOUTH PAGE 10 . 5. ESTIMATED COST AND ASSESSMENT RATE Estimated construction costs presented below include a 10 percent contingency factor. Overhead costs, estimated at 25 percent, include legal, engineering, administrative and fiscal costs. Final costs and assessments will be determined by using actual construction costs of the proposed work. The following parcels have been identified as abutting and benefitting from the proposed bituminous street improvements within the Oakridge South area. 1) Elmo Park Addition 2) Robinwood 5th Addition, Lots 1-10, Block 1 3) Robinwood 5th Addition, Lots 1-9, Block 2 4) Union Oil 2nd Addition, Lot 1, Block 1 5) RLS No. 1053, Tracts A, B, C and E 6) Parcel 4 along north side of 5th Street (Metes and Bounds description) Proposed construction costs for the Oakridge South area improvements (including bituminous street, curb and gutter, storm sewer, sanitary sewer, watermain, sidewalk, landscaping and turf restoration) are itemized in the tables located in Appendix A and are summarized as follows: . A. STREETS 1) Robinwood Lane: 5th Street to North Service Drive $ 74,294.00 2) Robinwood Lane: 5th Street to Hopkins Crossroads 60,142.50 3) 5th Street: Hopkins Crossroads to Robinwood Lane 48,526.50 4) Elmo Service Road 91,946.25 5) Elmo Road Sidewalk Repair 3,044.25 Subtotal Streets $277,953.50 B. WATER $ 11,935.00 C. SANITARY SE\VER 1) Oakridge South Area $ 20,564.50 2) TH 7 46,315.50 D. STORM SEWER 95.979.13 Total Construction Costs $452,747.63 Overhead Costs (20%) 90.549.52 TOTAL IMPROVEMENT COSTS $543,297.15 . OAKRIDGE SOUTH PAGE 11 . 6. RIGHT-OF-WA Y/EASEMENTS/PERMITS The proposed improvements will be limited to the existing street right-of-way for 5th Street, Robinwood Lane and Elmo Service Road. However, additional roadway easement will be needed to accommodate the turning radiuses along Elmo Service Road. Construction easements will be needed for work outside the right-of-way which may include parking areas and driveway aprons. Permits will be required from the Department of Health and MPCA for the work on the watermain and sanitary sewer respectively. 7. PROJECf SCHEDULE Present Feasibility Report & Order Public Improvement Hearing . February 15, 1994 Public Improvement Hearing and Order Plans & Specifications . . . March 15, 1994 Approve Plans & Specifications and Advertise for Bids. . . . . . . . . April 19, 1994 Open Bids .......................................... May 13, 1994 . Order Assessment Hearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . May 17, 1994 Public Assessment Hearing . . . . . . . . . .. . . . . . . . .. .. . . .. . ... .. .. . . a June 7, 1994 Award Bid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . " July 19, 1994 Commence Construction .. .. .. f... .. .. ... .. . . .. .. .. t . .. .. .. ... .. .. . .. . .. .. . .. . .. August 1, 1994 Construction Completion ............................... October 1, 1994 Final Project Cost Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . " November 1994 8. FEASffiILITY AND RECOMMENDATION From an engineering standpoint, the project is feasible and practical and caD best be accomplished by letting competitive bids for the work. It is recommended that the work be done under one contract in order to complete the work in an orderly and efficient manner. . OAKRIDGE SOUTH PAGE 12 - . . APPENDIX A COST ESTIMATE TABLES . --- ---- -- ---- - - ---- ---- . PRELIMINARY ENGINEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN FEBRUARY 4,1994 TABLE A- STREET - #1- ROBINWOOD LANE: 5TH STREET TO NORTH SERVICE DRIVE SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Common Excavation CY 1450 5.50 7,975.00 2 Aggregate Base, Class 5 TON 1700 7.50 12,750.00 3 Bituminous Base Course, Type 31 TON 625 24.00 15,000.00 4 Bituminous Wear Course, Type 41 TON 625 26.00 16,250.00 5 Bituminous Tack Coat GAL 175 2.00 350.00 6 Concrete Curb & Gutter, B618 LF 1240 6.00 7,440.00 7 Adjust FramelRing Casting EA 3 200.00 600.00 8 Sodding w/4" Topsoil & Fertilizer SY 1750 2.50 4,375.00 9 Trees EA 7 400.00 2,800.00 Estimated Construction Costs 67,540.00 10% Contingencies 6,754.00 TOTAL CONSTRUCTION COST 14,294.00 e . - . PRELIMINARY ENGINEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN JANUARY 24, 1994 TABLE A- STREET - #2 - ROBINWOOD LANE: 5TH STREET TO HOPKINS CROSSROADS SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Cornman Excavation CY 500 5.50 2,750.00 2 Aggregate Base, Class 5 TON 400 7.50 3,000.00 3 Bituminous Base Course, Type 31 TON 515 24.00 12,360.00 4 Bituminous Wear Course, Type 41 TON 515 26.00 13,390.00 5 Bituminous Tack Coat GAL 210 2.00 420.00 6 Concrete Curb & Gutter, B618 LF 1855 6.00 11,130.00 . 7 6" Concrete Dwy. SY 160 35.00 5,600.00 8 Adjust Frarne/Ring Casting EA 6 200.00 1,200.00 9 Sodding w/4" Topsoil & Fertilizer SY 1450 2.50 3,625.00 10 Trees EA 3 400.00 1,200.00 Estimated Construction Costs 54,675.00 10% Contingencies 5,467.50 TOTAL CONS1RUCTION COST 60,142.50 e - - - . PRELIMINARY ENGINEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN JANUARY 24,1994 T ABLE A - STREET - #3 - 5TH STREET: HOPKINS CROSSROADS TO ROBINWOOD LANE SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT ] Common Excavation CY 900 5.50 4,950.00 2 Aggregate CL5 TON 920 7.50 6,900.00 3 Bituminous Base Course, Type 31 TON 385 24.00 9,240.00 4 Bituminous Wear Course, Type 41 TON 385 26.00 10,010.00 5 Bituminous Tack Coat GAL 105 2.00 210.00 6 Concrete Curb & Gutter, B618 LF 1270 6.00 7,620.00 7 Sodding w/4" Topsoil & Fertilizer Sy 90 2.50 225.00 8 Trees EA 8 400.00 3,200.00 9 Landscaping Rock TON 80 22.00 1,760.00 Estimated Construction Costs 44,115.00 10% Contingencies 4,411.50 TOTAL CONSTRUCTION COST 48,526.50 . .TABLE A ~ STREET - #4: ELMO SERVICE ROAD SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Common Excavation CY 1625 5.50 8,937.50 2 Aggregate Base CL5 TON 1900 7.50 14,250.00 3 Bituminous Base Course, Type 31 TON 690 24.00 16,560.00 4 Bituminous Wear Course, Type 41 TON 690 26.00 17,940.00 5 Bituminous Tack Coat GAL 285 2.00 570.00 6 Concrete Curb & Gutter, B618 LF 3330 6.00 19,980.00 7 7" Concrete Driveway SY 60 35.00 2,100.00 8 Sodding w/4" Topsoil & Fertilizer 1300 2.50 3,250.00 SY Estimated Construction Costs 83,587.50 10% Contingencies 8,358. 75 TOTAL CONSTRUCTION COST 91,946.25 TABLE A - STREET - #5: ELMO ROAD SIDEWALK REPAIR SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Remove Bituminous Pavement SY 45 1.50 67.50 2 Remove Concrete Curb LF 205 2.00 410.00 3 Remove Concrete Walk SF 130 1.00 130.00 4 Concrete Ped. Ramp SF 130 3.00 390.00 5 Concrete Curb, V6 LF 205 6.00 1,230.00 6 Bituminous Pavement SY 45 12.00 540.00 Estimated Construction Costs 2,767.50 10% Contingencies 276.75 TOTAL CONSTRUCTION COST 3,044.25 . TABLE A - STREET ~ #6: TOTALS #1 Robinwood Lane: 5th Street to North Service Drive $ 74,294.00 #2 Robinwood lane: 5th Street to Hopkins Crossroads $ 60,142.50 #3 5th Street: Hopkins Crossroads to Robinwood Lane $ 48,526.50 #4 Elmo Service Road $ 91,946.25 #5 Elmo Road: Sidewalk Repair $ 3,044.25 TOTAL STREET CONSTRUCfION COSTS $277,953.50 . . . PRELIMINARY ENGINEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN JANUARY 24,1994 TABLE B - WATER SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Remove Existing Hydrant & Valve EA 5 250.00 1,250.00 2 6" DIP Watermain LF 100 16.00 1,600.00 3 6" Valve & Box EA 5 500.00 2,500.00 4 Hydrant EA 5 1100.00 5,500.00 Estimated Construction Costs 10,850.00 10% Contingencies 1,085.00 TOTAL CONSTRUCfION COST 11,935.00 . PRELIMINARY ENGINEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN . JANUARY 24,1994 TABLE C#l - SANITARY SEWER - OAKRIDGE SOUTH AREA [ SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 8" PVC Sanitary Sewer LF 310 17.00 5,270.00 2 48" Dia. Manhole 0'-8' EA 1 1300.00 1,300.00 3 Connect to Existing Manhole EA 1 750.00 750.00 4 Pipe Treatment For Roots LF 875 2.00 1,750.00 5 Remove VCP & Replace w/8" pve 150 55.00 8,250.00 (> 10' Lengths) LF 6 Aggregate Backfill TON 250 5.50 1,375.00 Estimated Construction Costs 18,695.00 I 10% Contingencies 1,869.50 TOTAL CONSTRUCfION COST 20,564.50 TABLE C#2 - SANITARY SEWER - T.H. 7 SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Remove Existing Manhole EA 1 700.00 700.00 2 Abandon Existing Sewer LF 215 7.00 1,505.00 3 8" PVC Sanitary Sewer LF 10 16.00 160.00 4 12" pve Sanitary Sewer LF 230 18.00 4,140.00 5 20" Steel Casing Pipe LF 120 140.00 16,800.00 6 48" Dia. Manhole 0'-8' EA 2 1300.00 2,600.00 7 48" Dia. Manhole (>8') LF 8 125.00 1,000.00 8 Connect to Existing Manhole EA 2 500.00 1,000.00 9 Bituminous Pavement Repair SY 710 20.00 14,200.00 Estimated Construction Costs 42,105.00 10% Contingencies 4,210.50 TOTAL CONSTRUCTION COST 46,315.50 . PRELIMINARY ENG INEER'S ESTIMATE OAKRIDGE SOUTH AREA HOPKINS, MN JANUARY 24,1994 TABLE D - STORM SEWER SPEC OR ITEM DESCRIPTION APPROX. UNIT ITEM NO. AND UNIT OF MEASURE QTY. PRICE AMOUNT 1 Remove Existing Structure EA 11 500.00 5,500.00 I 2 12" RCP LF 465 23.75 11,043.75 3 1511 RCP LF 290 26.50 7,685.00 4 18" RCP LF 1100 29.25 32,175.00 5 48" Manhole (0'-8') EA 3 1100.00 3,300.00 6 48" CB;MH (0'-8') EA 9 1100.00 9,900.00 7 48" CB;MH (> 8') LF 10 100.00 1,000.00 8 72" CB/MH (0'-8') EA 2 2200.00 4,400.00 9 72" MH (>8') LF 2 300.00 600.00 10 4811 Catchbasin (0'-8') EA 9 1100.00 9,900.00 11 MH Casting EA 4 225.00 900.00 12 Granular Foundation TON 100 8.50 850.00 Estimated Construction Costs 87,253.75 10% Contingencies 8,725.38 TOTAL CONSTRUCfION COST 95,979.13 . . . APPENDIX B SUMMARY OF NEIGHBORHOOD MEETINGS . . NEIGHBORHOOD INFORMATIONAL MEETING MINUTES OAKRIDGE SOUTH AREA IMPROVEMENT HOPKINS, MINNESOTA DECEMBER 14, 1993 In attendance were the following people: Lucille Soderholm 724 Robinwood Lane Marian Moss 707 Robinwood Lane David Haye Hopkins House Ardyce Lebewitz Elmo Park Apartments John Stangar Elmo Park Apartments Lee Gustafson City of Hopkins Jim Gessele City of Hopkins Jon Rippke Bolton & Menk Ron Roetzel Bolton & Menk Jim Johnson Bolton & Menk The key issues which were discussed at the neighborhood meeting are listed below: . 1. Existing drainage problems are accelerating the pavement deterioration. 2. Drainage problems include the following: a) Periodically, back flushing at the water plant causes water to flow overland south along Robinwood Lane, through private parking lots, into the Hopkins House parking lot, adjacent to the Hopkins House building and along and down the north foundation wall. b) Surface drainage from the street flows onto private property. This drainage either flows into existing catchbasins located outside the right-of-way, or through grass swales and eventually back onto the bituminous surface. c) Drainage along 5th Street proceeds westerly along the north wall of the Hopkins House and then southerly, off the right-of-way and onto adjacent parking lots. d) Catchbasins are located in the street surface and not along the curb and presently do not have curb boxes. . NEIGHBORHOOD MTG.-12114/93 PAGE 1 OF 3 e 3. Parking is mainly off street parking. However, there is no clear distinction between the roadway and the parking areas. This includes parking areas along Robinwood Lane, the service road and north side of 5th Street. Entrances into parking lots should be defined. 4. Due to the continuous pavement from the street to the parking areas, should the parking areas be reconstructed as well? 5. Minimum street widths should match the existing width. Preferably, however, the street width minimum should be 26' within the 30' right-of-way. Robinwood Lane is to be considered at 36' width to account for truck movements between 5th Street and the frontage road and to allow for parking on both sides of Robinwood Lane north of 5th Street. 5th Street will be considered at 36' due to the probable future rerouting of the frontage road traffic through this area. 6. A sanitary sewer extension along Robinwood Lane to the back flushing holding pond is proposed. The existing sanitary sewer pipe in the project area has been televised. Sag and joint problems are known to exist in the line crossing T.H.7, south of the project area. Review of the sewer televising will be completed in Phase II. 7. The hydrant located in the island at the intersection of Robinwood Lane and 5th e Street will probably be relocated to the east boulevard. Other hydrants win be reviewed by City staff. 8. Sanitary sewer and water service lines are recommended for review and possible upgrade by the property owners. The City staff would complete a televising of the sewer service line for each property owner if requested. 9. The letter dated December 9, 1993, from the MPCA to Mr. Dave Hayes, Hopkins House, indicates that a release of petroleum has occurred from the storage tank facilities along 5th Street and has resulted in contamination of soils and/or ground water. Hopefully, this matter can be resolved privately before construction begins this summer. 10. Dumpsters should be placed in a designated location. 11. Boulevard areas, including newly created buffer zones along Robinwood Lane and 5th Street, will be considered for additional landscaping, mainly trees with open grates. 12. Pavement tests were completed on Robinwood Lane, 5th Street, the service road and Elmo Road. The pavement and subgrade were generally found to be in goad condition. The status of Elmo Road win be discussed between the City staff and the . Elmo Park owners. NEIGHBORHOOD MTG.-12/I4193 PAGE 2 OF 3 . 13. The right-turn only exit from T.H.7 onto the frontage road and Robinwood Lane intersection should be reviewed for improving the layout and traffic movement. Possible signage improvements will also be considered. 14. Owners of single family residences on Robinwood Lane, north of 5th Street, expressed mixed concerns about the street width. Widening would help with the on- street parking congestion but residents wouldn't want to risk losing trees. There was considerable interest in the cost and assessments required for this project. Mr. Jim Gessele discussed the assessment policy and indicated that no costs have been compiled as of this date. Following this discussion, the meeting was adjourned. e . NEIGHBORHOOD MTG. 12/14/93 PAGE 3 OF 3 e PROPERTY OWNER MEETING MINUTES OAKRIDGE SOUTH AREA IMPROVEMENTS HOPKINS, MINNESOTA JANUARY 4, 1994 These minutes are a summarization of the meetings with most of the property owners which will be impacted by the Oakridge South Improvements. 1. Hopkins House - Dave Hayes A. Drainage Mr. Hayes indicated that whenever the water treatment facility backflushed, a significant amount of water would t10w down the street surface, hit the north side of the Hopkins House and at times, flow under the north access door. This issue will be addressed from two sides, the first is the improvements to the water treatment plant which would eliminate the need for backflushing into the storm sewer. The second is the addition of full concrete curb and gutter along Robinwood Lane and 5th Street adjacent to the north wall of the Hopkins House. This will redirect the typical rain runoff away from the . building wall. During our site drive-over, it was suggested that a catch basin should be installed behind the curb in the low area, adjacent to the building. B. Street WidthIParking/Access It was indicated by Mr. Hayes that he does not need the parking along Robinwood Lane just north of the frontage road. A street width of 36 feet would be adequate, however, prohibiting the parking of trucks in this area would allow better access for his delivery trucks. Mr. Hayes also indicated that there is adequate parking for the Hopkins patrons either in the parking area adjacent to the building or in the overflow lot north of 5th Street. Two access points into the parking lot north of 5th Street would be adequate. Location of these openings could align with openings on the south side of 5th Street. Access for truck deliveries to the northwest corner of the building was critical. Additional length of drive-over curb is needed beginning at the northwest corner of the building and proceeding west along 5th Street is needed to allow for the truck turning movements. 2. Liquor Store - Ed Swadden The key issue here is access. A meeting with Mr. Swadden indicated that he would e be willing to eliminate the access point near the 5th Street;Hopkins Crosstown intersection if a right-in/entrance"only access point was granted from Hopkins Crosstown near the southwest corner of the property. However, during our site drive-over, it was noted that delivery trucks block the second access in the northeast corner of the property and that the right-in only access from the Hopkins Crosstown PROPERTY OWNER MTG.-l/4194 PAGEIOF3 . would not be feasible during this project. Therefore, it was suggested at this time to narrow the opening near the 5th StreetlHopkins Crosstown intersection to 26 feet and continue with the two access points along 5th Street. 3. Laundromat - Herb Mason Mr. Mason was not available last week to meet with us. However, based on comments from Mr. Hayes, Hopkins House, we will keep the 900 parking along the north side of the laundromat but provide curb islands to delineate the parking area from the driveway access points on both the east and west sides of the parking area, all along the south side of 5th Street. We will send a site layout plan to Mr. Mason for comment. 4. Elmo Park Apartments - Ardyce Lebewitz A. Drainage/Street Curb Present drainage catch basins on private property will remain in place. The street drainage, however, will be redirected along the new curb lines and into the public storm sewer. Street grades will be lowered as much as possible in order to allow the parking areas to drain into the street. However, there was not a commitment at this time to reconstruct the parking areas beyond 3 feet of the new curb and gutter. Therefore, the curb grades will need to match the existing parking areas with a reasonable 3 foot transition. The City agreed to . pay for the bituminous repair 3 feet behind the new curb. B. Street WidthlParking The street width of the service road and Robinwood Lane (just south of the treatment plant) will be 26 feet. The service road will be centered on the 30' right-of-way and Robinwood Lane will match the west curb line with the west 30' right-of-way line. This will allow for additional boulevard width along the east side of Robinwood Lane from the service road south to the frontage road. Due to the need for parking by the patrons of the apartments, it was agreed to provide driver-over curb around the corners of the intersection of the service road and Robinwood Lane as well as the northeast corner of the service road. This radius would allow for emergency vehicle access and would require a roadway easement as well as a temporary construction easement. Ms. Lebewitz indicated that parking along Robinwood Lane just north of the frontage road could be prohibited and a 36' width is adequate. However, during the site drive-over, it was suggested that this width be 42 feet to provide for the occasional parking which does occur here. This will allow for maneuverability of delivery trucks as well as garbage trucks. . C. SidewalklU tilitieslDumpsters/Misc. Sidewalks along the frontage road and Robinwood Lane were designed for access to private property and not a public walkway. Therefore, no reconstruction for curb cuts and pedestrian ramps will be necessary. The PROPERTY OWNER MTG.-1/4194 PAGE 2 OF 3 . sidewalk along Elmo Road, however, will be evaluated against the City sidewalk ordinance in order to determine if pedestrian ramps are necessary. The overhead electrical utilities will remain in place. There will be a couple of power poles (one significant) along the east side of Robinwood Lane which will need to be relocated. Trash dumpsters will be established in a designated location with a 6 inch concrete pad. Sanitary sewer service lines will be televised by the owner. Of particular interest is the service on the east side of Robinwood Lane which flows under the dumpster location and has a history of bi-annual cleaning. The privacy fence along the east side of Robinwood Lane will be removed and replaced. . . PROPERTY OWNER MTG.-l/4/94 PAGE 3 OF 3 . NEIGHBORHOOD INFORMATIONAL MEETING MINUTES OAKRIDGE SOUTH AREA IMPROVEMENTS HOPKINS, MINNESOTA JANUARY 26, 1994, 7:00 P.M. In attendance were the following people: 1. Larry Lutz, School District #270 2. John Okerstrom, Hopkins House 3. Ardyce Lebewitz, Elmo Park Apartments 4. Keith Scott, Oakridge Golf Course 5. Lee Gustafson & Jim Gessele, City of Hopkins 6. Ron Roetzel & Jon Rippke, Bolton & Menk, Inc. Introductions were made of all those present and Mr. Gustafson presented the background of the project in that it was initiated by City staff and would require a 4/5 vote by the City Council on March 15, 1994, in order to proceed with the construction of the project. Prior to this date, however, the Feasibility Report will be presented to the City Council on February 15, 1994, and with a public improvement hearing tentatively scheduled for March . 15, 1994. The balance of the proposed schedule was discussed with the June 7th date noted as the public assessment hearing. It was stated that this schedule is still tentative and subject to revisions. The public, however, will be notified of the public improvement hearing as well as public assessment hearing. Ron Roetzel, Bolton & Menk, presented the proposed street improvements which included the following: 1. Widening Robinwood Lane north of 5th Street from 30 feet to 36 feet. 2. Narrowing Robinwood Lane south of 5th Street from 44 feet to 36 feet. On-street parking would be prohibited along this section of Robinwood Lane. Additional landscaping is proposed. See attached sketch, Figure 5. 3. 5th Street will be narrowed from 50 feet to 36 feet. Curb islands are proposed along the north and south sides of 5th Street in order to establish the edge of the roadway and the parking lot entrances. On-street parking will continue to be prohibited along this roadway. Additional landscaping is proposed for the roadway. (See attached sketch, Figure 6). 4. Elmo Service Drive will be widened from 20 feet to 26 feet width, centered along the existing 30 foot right-of-way. A roadway easement will be required in the northeast . and northwest corners of Elmo Service Drive in order to accommodate the 50' curb radius. A 40' radius is proposed at the intersection of Elmo Service Drive and Robinwood Lane. These larger radii are needed to provide adequate turning space for emergency vehicles and to delineate the edge of roadway from the private parking areas. Mr. Lutz, School District 270 representative, indicated an interest of placing NEIGHBORHOOD MTG.-1126194 PAGEIOF2 . additional trees along the east side of Elmo Service Drive. However, also under consideration for this area is additional off-street parking. Mr. Lutz will discuss this with City staff. 5. Concrete curb and gutter, Design B618, is proposed along all of the street improvements. Drive over curb, Design D418, is proposed along all of the perpendicular parking areas along Robinwood Lane and Elmo Service Drive. 6. Proposed utilities were discussed including the storm sewer extension along 5th Street, the sanitary sewer extension along Elmo Service Drive and various repair areas still under review. The hydrants along the north Robinwood Lane will be relocated behind the new curb. The hydrant at the Robinwood Lane and 5th Street intersection as well as the one at Hopkins Crossroads and 5th Street will be removed and replaced with a new hydrant. 7. Ms. Lebewitz and others expressed concern with disruption of traffic, construction schedules and blocked streets. The owners were asked to notify City staff when a particular event is scheduled and access is critical. The contractor could work around these events in order to minimize the disruption. 8. The owners were informed that both the watermain service and the sanitary sewer . service from the main to the building is their responsibility. Therefore, if they know of any service lines which are giving them trouble, they should request a repair/replacement at this time. 9. Mr. Scott indicated that there was a drainage agreement between property owners which allowed a drain tile (presently in the north side of Elmo Park Apartments and south of Elmo Service Drive) to flow under Elmo Service Drive near the northeast corner and outlet onto the golf course property. Further investigation of this system win be completed during the design phase. Mr. Jim Gessele then presented the City assessment policy and the basis for determining the preliminary assessments. A copy of the preliminary assessment schedule is attached. Several questions arose regarding individual parcels. Concerns were also expressed about the timing of the assessments and the owner's inability to include the work in their 1994 budgets. Following assurances that the property owners would have an opportunity to discuss their concerns with the council, the meeting was adjourned. . NEIGHBORHOOD MTG.-1126194 PAGE20F2 .. ..1 ij . I OAK~/ME' SO()7?J' ..... ..... ,..... I N'~/c:;H /Jo,e I/~]) ST~flftS . . ~... .: .~~c . ~ ..... - .. . , INF"O AlEIff/A1&, / he.. /9+ ~NAtffC AZJPRESS 7EL..E"PHtJAJE" k~o ( .L A YM'f L-l-,,- . 10 <J I <:1 fl,^- 'r 1 (,f"I:,. s.t...v., .$'I-f 1-/13 if. Jo:::'~~ . ~r.J. t/.(~~:>vl l:r 0 I j/ it"J:7 7 "..: .. ,,;.; ry..:;s-"" ;;??!( ')C....-f't...D.~ a- ~~(p ~u:;;( 1<- I") I). Hot.} kc,.,s c rr..>$SIO~J.. :...,.. :s1 (;::: I;),pO '.. -1 L.ebt.t.J,"t2;..' 13U\ HuJ() /. ,'.'. 0/ b ~ _ /' .. ..., ~.. : "~",~l<,-, (e::: f I H ~ u 1-( 7 () u (J II / ( r:!I/:Jr:-C R~ (ef":? s - ..77. <- / . uN k: (( IPC-C' C.C . ... \ ... \ , I I , i . . . . I , . i I I i I I I I .. . ., .. . . " , . , . ~ ,.... ! , . , ' , -. - ~ ~--- -t' W ~ 01 It: -.... ::3 ~ '< CIl Cl 00 k: 'N' 'j ~:. :j" Ii 1 \: 1, '" !, ..... L51" ~ a. ~ ~O c(g .I3 ~ :E 02 ZZ >-Ot>::i: 1-(.1) ZlJJWui' -~3Z c..>On::S2 >~ll-g, oE:!: (.) ,.........., I - -:~ --- ,.. ~ . :S ~ ! S S~ilii11n[ A a i ~ ~ i ~1 Jdlj . S~ t1 i I ~ I .. . .. ..-- - -.. . ---. - .- r-- -. - --- -------- -----"- - - 8\ ~ .... :!l '. .~ ::! . ~ . ~~ ,,0' o ~ ~ ~ ;:~ ai ~ ffi I'" ~ I ~ .. ~ ~ &! ~ a ~\ \ ... II t;:; I II 13 I 1\ \ II O't'Oll 30lM13S Ol'fl] :.:~.::;. .~> --".-, ~---.:-. ~ ::-.~ --. .' ,'-- ~- ~ ..... . -. . ", ~ ~~' L- .- - . n . <I< _,-- --- J \ \:J ~ J"'~-~=~1 \ . \ ~ _ If' l ..;.=-- : t! :\ [7"'- -_.- ~-- p Il~- ~____~--_J) \ I __-------:11.. , I -----------"" O 'L ~--------~ , Ie n - --~-- __--,,_-dF-=--=C:--=:-i ... ~ 11 \ \' O'l'Oll - 0l'f13 l ",:' I \ II I' o \1 1\ I ~h d I ~ Q rr2.JOJ-\ \ ~i5 l~ :1, ,Oi~~o . _ !,?I JJ \ ~5g~ . \ U_JI I [fill;' I ::EwW. ___ I -06~ [_ __._ l \ t;J Q et: S2 uJet:1l..1l.. __ __- : ffi ~ j; ~ u ~ ., ... <> >:: '" ... ., ~ ., '" 8 . . ~ : . F' .... / /,; -~ ----- - ------ - ! . ,,,_,,, """",- - ~ I i _ ~ ~ i ~ 1 . .:di~ 811 ~I Itl ~ .... w II 11~oCID ~~ &..., ;:!;~ ,.. << I I ... ~ 3 c ~~z~~~ . ~.~ i3 J. '" I olf ~ ~ ~~~~i! fi1 5 ~ ~ 011 I I ~ : II & o@ I I ; I 3JlM3S 01'f13 0'1'011 '-'- ..~_. .- il ~ I J I II - I I '" I--=- \ ~ '" I --I I~ J _ ___ _r--L~ __-=---~~~. ... I I ___u _____ u I_-_~ '-- .--... I ~ ~ I f'.',..--., '--"'l : L I '. ,;:' -:m, A~ ~ ~ "l - --;-.:.. _~= ~ u < [' I T ~ . ': '[ ~~ I I I z~J,~ o ! jl i.; ~~~~ ~ 1- 1 ':1 'i; Ilj ~ g ~ I n r I Ihl ~~t;' I I I QWW,,; I II r 'f:ll,! I , ~~~~ . I I, II :,1 ~ ~ fj ~ ] , -- -- ~ J .- I I --- ----- u " --~ ~ ~ - . - · 0 .... 0 ~ '" ~ '" z .- . --.- - -l- .......--- ~ i I - _ ~ --- ~ I , , I _ i , u.. f.1 L ~ ~__! u.__=.:.:::~_ ~_.~ _:.:::_ ~ ~ ~ .~ ~~ ,_U_ .~ _-= __--~~-= -~-=--SO~IISS0~ SNllIdON :.<: ~ I rJ~ ~Ii .:.:l ~ . ~ ~ ~ ~ 'I! o ' ~ f--'o :; ..:1 " ~ oil ilJ f .... ... I!!'" '" ill Ht~. o~::~ 0 \ ~... ~ ill ?i- ~ l · H > C ffi Ii ~~ l ~ ~ &! g z~ ~ I ~ 1\ I ~ i I I' pt. i 'I' \! I' ~\ \ ..@ '* I: _ \ 1 \ I I .~-~-~qg9gg~--~ :=::__ u:'= ~.:<~~.~ --.-- -'- cc~. ~ ..' - -.' - ---..- _.- ._ __?If:'~-'- '. . . ------' -. '. ::.:.::.:. -. <c.::::. "-." < ,", ..'~.... .... -.... "-'. ........ ,-...... ~~T:] \-\j-\~::-:~:-::-:<:~<~: , - ,- /'~---- \ I Z :- '::. / .~ .... . . I ...:S :)U \ --> ( r--- ~6~ U~ .J:])?' .' d ~i . ~~~ (k::'50Z 0.. zz . J .--.~[ ./ \ .' .-.- -- ~o - -Ult:i WWWul ~=~~~~= -~- \::.:::?:~:-:?-::::-:2-: WCl6Z ~g(k::2 a::o..Q.. E~~~ ~T~~=., '~l \ (-- r -- ,~2::. 'r] !i: 0 , ' \. , 'l~~< . j' "...' __ : i t=--- .~ ?;. . --- . ~\ \\D ~ ~' L~-~ I- \ ' I- ~- (/) \ tf) " . - - - ~ ............... '-.... --~-,----'----- .... , -- --~---- -,-- :r:. .............'-.. ~ .. 'I:. ......., /. t-- t-- - ,. Lf) U1 ......, ......- .....~. -.............. --. -E \ - > I ~ . . ~! ~ .. ~ ~ s ~ i ~ i > Od i ~ z c t o ~ i sO'VOtlSSOClJ SNI>ldOH SGV'OClSSOClJ SNI){dOH tp .. o ~ .' ~ ! ~ .. "' il t~.c: ~~ ~ o;t ;'i~ ~ '" r . :z:~ ffi ~S~~; ~ ~~~J ~ ~ Iii II " I . ~ : f 0 ~ I r 3::lI^ij3S om3 O'l'Oij ..-" .I' .I' n L_~.~~...~~ --==:J ---J '" C ,- C! j .. j-- ----1 ____..--r---~ ~- ~ ... I L___~ 0 ~ I--;~-';------l ... II> 0 ~I ~ ~ ~ 'I ~l1i1 ~ ~~o ~\ ~~ .13 Ll 11. oz ::E zz 0 ~L -51ti'i rJ ~LoJLoJui (!)6~ 1Il0~~ ::::i: i2 1l.15 --- n:::::::E:l: 00 _~J . In (.) . ~ . - } It ~~) k~~"I"'~~ -- m ... .I' ~ 3NYl - I ~ ,..,.. . -~ ....... , ~ .> ----- ~ I il ~ ~ ~ 1 ! . 'd i ; z ~ ! ~ i l o .' I]:l ~ ~ - -- I I . w I --.l lL 0 0::: CL 0 L5 z I-- O:::~ (j) <ern X 0:::0::: W -:::) L____ ~u Wo O:::z (fJI ::::JW 0:::: om w - z >m ~n 00::: I:::) ::::J____ Wu -- GG 1.= 2: li! zz-<( rn 0::: i=';2W J 0 w (J)n:::(Y. j ~~ ~<:(<( rJa.. zw~o o~ (/) (') /' F= ~~ , / ~:s: / fdo ~ I-- ',- (1)0 :!E CCo::: ~o"" ~ x W 0::: ~ (/) W ()~lii~ ~ ~~~~ :::) IX) CJ ~ 0 r z . <( '; ..... eJ to CD ~-- .....-- i t-o__ (I.- ~ - ~ 0 z -. -> I , ~-......,...:. I ~ ~ i CCo::: i >< W I w~ i I ui Z ~ g I ~ ( ~: I"LI " ~ - i . I z :!i I . 05 b ~ ~ 3 B ~ p:j ~ ~ ~\I'II g \ ~~ 1<0 . ~l tl~.o~~tJ 0 " I !;!:I: :I: '" ~z :0 :0 ~ ~ z~ ~ !~~I~~i~ ~I~~~ ~~ ~ ~~~~I~lll~i ~ ~ 1\ 1 t I · 1 j .,. I I I \ j .o@ : * · i-I I I I I = _-_;~~::-=~.~~-~~ ~~~\J- ~:-=: ".' ~~.:~~~-:~:~~~~::~-.. <:;:~. ~~:.:>~::~-::~ .-.I-----.-.-~--... -- ---..---~. ,. " ""......... . ~Jt'---"I----r:::r::~.-l-~-11 ~ -- .-=--- 1-- ~ -- J :'~ '.:'.::::: '. '- ".~. " I II _/..~------- - l I ----, /--- \ _ _ I, II Jr,- -- - -- I~:-':.. / I ~ --_.-- -, , ~ l. . - - \ - ( r- - -- l \ C' --J~l \L> ,-It] l---- -] -j' -::-;: J I~~ J .. _ -, - ~~oz _ =:.J-J:: -- - - ~5zZ ~~,___ _<#. _-'.:- -0 " . :::::::~:::-=_-:::::::~ ,/ \ ___---- . ~ _,'-', 8C1)~ - ._~_~~~=- ._< <:::::>:>;:::___--. d~~ =_C=-=::'-I=~---l \ ,J -~- ::. ~r-:''::-- '. l ~~€~ \ -, ~~\ l' \ \\J: \ --1 ,;,~, , " ' \ ' . - '-- r----- - - -- -- ........ ' T.r --'- - -- - ,.--. j ---~ - .. ~----'- . r- - -.-----. -'- ------., - ~----- - ,I \ <','--\ I \ ~------- ;-----::::----- .. ---- - ---- --- - 8 \ \\:\ c \ [ ---=-= - 8 -:~, L- .--- a:: ' 0:: ----.---- I- \\ l-- ,.-----~'I VI 1_ __ . If) ......::--.. -- -- --- ...:.==~.=-= ~_ ___ _L~__ - I :r: :r: ..... -, to \ \ 'I :;:; ~ : \ ,11 ----. - 9 \ \ \ II ---- ---- ~ <:-. 25 ~ ~ , ---- ". ~ . I ~_ ........ '.......-. -J - ~ ~ If' ' -.1 ~ 'i ~ " _'" 1 Z j , __ _ _.:~--..::~ = -1 l--. ..- . _---- _ :-- _ ----- ~ i 1 =....;-=" Z ~ O~ ~ .' sa\lo~SSO~J SNI>ldOH sa\lo~SSO~J SNI>ldOH 6! .~ p;l ~ ~