CR 94-118 AC W/RCM For Design Services
*1. ..
\ y 0
G /"'
e 0 p ~ \ ~
July 1, 1994 Council Report: 94-118
APPROVE CONTRACT WITH R.C.M. FOR DESIGN SERVICES
FOR THE PHASE II NINE MILE CREEK IMPROVEMENTS
proposed Action.
Staff recommends adoption of the following motion: "Move to approve the
desiGn service contract with R. C.M. for channel improvements alonq Nine
Mile Creek in the amount of $10.000."
Approval of this motion will allow RCM to immediately begin the design of
the channel improvements along Nine Mile Creek near T.H. 169. Advance
design of these improvements is necessary in order to meet the schedule
requirements of this project.
overview.
Earlier this year the city completed Phase I of the Nine Mile Creek
improvements. Phase I improvements consisted mainly of installing five new
culverts along various parts of the creek. The Phase II channel
~improvements were not done at the same time as Phase I due to the lengthy
~permitting process required for the channel improvements. Staff would like
to begin designing these improvements now so we will have ample time for
the permitting process, and be able to complete the improvements this
winter.
Primary Issues to Consider
o Why do the improvements need to be constructed?
o What risks are involved in the city designing the project?
o How will the design fees be funded?
o What is the schedule of this project?
supporting Information.
o Analysis of Issues
o RCM proposal Letter
b,.-'/ t /
v~/~~~
Lee Gustafsd , P ,'ic Works Director
e
J
Council Report: 94-118
Page 2
4ItAnalysis of Issues
o Why do the improvements need to be constructed?
The channel improvements are necessary in order to improve low flow
conditions in this area. The channels east and west of T.H. 169
presently have siltation problems that are preventing the water from
flowing out properly. The water is therefore backing up and flooding
out certain areas for extended periods of time. The Phase II
improvements will be designed to eliminate some of these problems and
restore the flow lines to their original design.
o What risks are involved in the city designing the project?
The main risk involved in the city designing the project would be if
the project was stopped for some reason, and was not constructed. If
this occurred, the city would under no circumstances be eligible for
reimbursement of any design fees.
o How will the design fees be funded?
The fees will be initially funded from the P.I.R. fund. The fees will
be refunded in accordance with the agreement the city has with the
Nine Mile Creek Watershed District for this project. If for some
reason the project is not constructed the Watershed District is not
~ obligated to reimburse the city.
o What is the schedule of this project?
The first 4 - 5 months of this project will be dedicated towards
design and the permit approval process. Once all this is completed,
the remainder of the project should be easy. The channel improvements
will be scheduled for construction during the months of January and
February. Final clean up and trail restoration will begin in the
spring.
.
June 13, 1994
.
Mr. Lee Gustafson
City of Hopkins
1010 first Street South
Hopkins, MN 55343
Dear Mr. Gustafson:
Thank you for the opportunity to provide the following proposal for engineering
services for ditch cleanout of parts of Nine Mile Creek and related services. This
proposal is based on the following general scope of work:
. 2400' of ditch maintenance and cleanout west of T.H. 169 in the
Cities of Hopkins and Minnetonka, including 500' of County Ditch-
41.
~GmI . 1700' of ditch cleanout and maintenance east of T.H. 169 in the City
of Edina (a part of County Ditch 41).
rieke C1eanout 500' of Nine Mile Creek West of T.H. 169.
carroll .
muller
~ciates, inc. . 2000' of trail improvement in City Park downstream of 9th Avenue
Ineers
c Itects South.
land surveyors
equal opportunity . Assist City with permits as identified in the EA W.
employer
We propose to provide plans and specifications to accomplish the construction work
outlined above for a lump sum of $10,000.00.
This lump sum includes the following design services:
. Survey to develop cross sections, alignment and grade.
. Two (2) meetings with the regulato!)' agencies (agencies may be
combined for meetings).
. Preparation of plans and specifications for the improvements.
. Prepare permit applications for DNR, COE, PCA, Hennepin County,
MnDOT, and Watershed District.
. Meeting and communicating with the City on a regular basis to
facilitate input and approval.
.901 red Circle drive . Estimate of probable construction cost.
box 130
minnetonka, minnesota 55343
612 -935-6901
fax 612-935-8814
Mr. Lee Gustafson
. June 13, 1994
Page 2
This lump sum does not include bidding and construction services. Fees for those
services can be negotiated after plans are complete. Additional regulatory agency
meetings over those mentioned above or additional work caused by the agencies
would be billed at our standard hourly rates. A proposed project schedule is
attached for your review and comment.
We hope this proposal meets with your approval and we look forward to completing
the project with you. Please call if you have questions.
Sincerely, ~
."
c1d29;;};~ ~ ~
Robert C. Robertson, P.E.
RIEKE CARROLL MULLER ASSOCIATES, INC.
RCR/ka
e
.
Proposed Project Schedule
It Nine Mile Creek - Phase 2
Ditch Cleanout
June 13, 1994
Date TasklDescri ption
July 15, 1994 . Authorize RCM to start project
July IS-August 1, 1994 . Meet with DNR, COE, PCA, Hennepin County,
MnDOT, W.S. District
. Survey cross sections
. Walk project
July I5-August 15, 1994 . Design project
. Prepare specifica'tions
July 15-August 30, 1994 . City plan/project review
September 1, 1994 . Submit plans and pennit applications to regulatory
agencies for review - W.S. District, DNR, COE,
PCA, Hennepin County, MnDOT
December 9, 1994 . Advertise for bids
. December 30, 1994 . Receive bids
January 15, 1995 . Begin construction
May 1, 1995 . Substantial completion
June 1, 1995 . Final completion
.