Proposed Action.
Staff recommends the following motion: Move that Council accept
the feasibility report as ordered on March 2. 1993.and adopt
Resolution 93-48. Resolution Orderinq Improvement After Public
Hearinq.
This action will continue an assessable project on the block
between 11th and 12th Avenues North between Mainstreet and 1st
Street North. Plans and specifications will be developed and
bids solicited for construction in August 1993.
Overview.
council at its regular April 6 meeting considered a feasibility
study concerning the reconstruction of the above-referenced alley
and ordered a public hearing for May 18. This hearing date was
subsequently amended by Council action to June 1. Notices have
. been sent to all affected property owners. A public information
meeting was conducted with the residents on March 23 for
discussion of all improvement issues, estimated costs, and
assessment policies.
Primary Issues to Consider.
. What are the current conditions of the alley?
. What are the estimated costs of an improvement?
. Staff recommendation.
Supportinq Information.
. Notice of Hearing of Improvement
. Affidavit of Mailing and Mailing List
. Location map
. Feasibility report
· Resolution 93-48
J~SS~
Engineering superintendent
,
Analvsis.
· What are the current conditions of the alley?
The alley in its current status is considered unimproved.
Its surface consists of 1"-1 1/2" of bituminous in
deteriorated condition with poor drainage patterns. The thin
asphalt layer and bad drainage have contributed to the many
potholes and have sUbstantially increased maintenance costs.
· What are the estimated costs of an improvement?
Reconstruction with concrete pavement is estimated at
approximately $27,000. The lots on this block are
substantially uniform in width. The fairest method to assess
this project is on the per lot basis. This policy translates
into an average assessment of $1,200 per lot. The Hennepin
County Library and u.s. West properties total 6 lots each
and, although not all lots in both cases front directly on
the alley, the properties as a whole are deemed to benefit
from the improvement. The estimated assessments for the two
properties are $7,200 each.
Assessments will be based on the city's policy of 80% project
cost to be funded by the residents, 20% will be funded by the
city. The additional cost of refurbishing the alley storm
sewer will be borne by the storm sewer utility. This cost is
estimated at $1,200.
. Staff recommendation
Staff has encountered mostly positive reaction to this
project at the neighborhood information meeting. These
sentiments coupled with deteriorated conditions of the alley
lead staff to recommend adoption of the resolution ordering
plans and specifications.
<\
CITY OF HOPKINS
Hennepin County, Minnesota
NOTICE OF HEARING OF IMPROVEMENT
TO WHOM IT MAY CONCERN:
WHEREAS, the City Council of the city of Hopkins, Hennepin
County, Minnesota, deems it necessary and expedient that the
improvement hereinafter described be made,
NOW, THEREFORE, notice is hereby given that the City Council will
hold a public hearing on said improvement at the following
time and place within the said City.
DATE: June 1, 1993
TIME: 7:30 P.M.
LOCATION: CITY HALL
Council Chambers
1010 First street South
Hopkins, MN 55343
The general nature of the improvement is the construction of a
concrete alley and storm sewer improvements, City Project 92-11,
in the following described area:
the alley between 11th/12th Avenues North and Mainstreet
and 1st Street North
THE TOTAL ESTIMATED COST OF SAID IMPROVEMENT IS $28,235.
It is proposed to assess every lot, piece or parcel of land
benefitted by said improvement whether abutting thereon or not,
based upon benefits received without regard to cash valuation.
Persons desiring to be heard with reference to the proposed
improvement should be present at this hearing.
This Council proposes to proceed under the authority granted by
Chapter 429 MSA.
Dated this 20th day of April, 1993.
BY ORDER OF THE CITY COUNCIL
g/~~-~ &~ A1fj r-:
James A. Genellie, City Clerk
City of Hopkins, Minnesota
Publish: Hopkins Sailor April 28, May 5
,
AFFIDAVIT OF MAILING PUBLIC HEARING NOTICE
STATE OF MINNESOTA )
) SSe
COUNCIL OF HOPKINS )
James A. Genellie, being first duly sworn, deposed and says:
I am a United States citizen, over 21 years of age, and the
City Clerk of the City of Hopkins, Minnesota.
On April 30, 1993, acting on behalf of the said city, I
deposited in the United States Post Office at the City of
Hopkins, Minnesota, copies of the attached notice of hearing
on proposed assessments, Alley Reconstruction A, Project 92-
11, enclosed in sealed envelopes, with postage thereon fully
prepaid, addressed to the following persons at the addresses
appearing on the attached copy of the mailing list.
There is delivery service by United States mail between the
place of mailing and the places so addressed.
/
SUbscribed~worn to before me this 30th day of April,
1993.
~NO!~
'- ...v'......;,..",..,...,,'.....
f' JAMES T. GESSElE
!~w'; NOTARY PU511C_MINNborA ~
.~~ .;i { HENNEPIN C9UNTY
~., My commiSSion expIres 3.19.95 .~
~........,.~...;...,v~~
.~c _'" 'IQ 4 -j,.J.'j3
24.117-22310041 24.117-22310042 24-117-22310043
.n. Co. Gov. ctr.1 Prop. Mgmt. Henn. Co. Gov. ctr.1 Prop. Mgmt. Henn. Co. Library, ASD
o 6th st So A-2208 300 6th St So A-2208 Hopkins Library
Mpls, MN 55487 Mpls, MN 55487 Ridgedale Dr. @ Plymouth Rd
Mtka, MN 55305
24.117-22310044 24-117-22310044 24-117-22310045
Chuck Kritzler Henn. Co. Library, ASO Tax Dept. Attn. Klaus Cox
Henn. Co. Library, Hopkins Hopkins Library Us West Inc
2211th Ave No Ridgedale Dr. @ Plymouth Rd 6300 S. Syracuse Way Suite 700
Hopkins, MN 55343 Mtka, MN 55305 Englewood, Co 80111
24-117-22310045 24-117-22310049 24-117-22310050
Attn. Alma Fitzloff Ray Krieg J. J. Johnson & K. M. Solie
Us West Inc 11041 Xerxes Ave So. 25 12th Ave No
2800 Wayzata Rm 350 Bloomington, MN 55431 Hopkins, MN 55343
Mpls, MN 55405
24-117-2231 0051 24.117-22310052 24-117-22310053
K.J. & A.D. Bahmer Floyd U. & S. Nelson James Marvy
29 12th Ave No 33 12th Ave No 4112th Ave No
Hopkins, MN 55343 Hopkins, MN 55343 Hopkins, MN 55343
24-117-22310054
Marvy Adv Photography Inc
.2th Ave No
kins, MN 55343
,
"
- , ~/
-, ..... ~ , - ,
17 : ~ ,
., . " :5 tal) .\ 15 ( ....)
-
" 9 , - \.' . \ ' i
'/>
:1'\ t.I ( all T (':'"&' .r -~
-~
I
1)
I
12
, ~
,
~- :z
, lO:'fJ) w
t
: >
..........
. <(
;' 6
; T
.
&
-
.;
,
,,'
-
\
-
-- .~MA1N~- - SCUTH HCPKINS RECEVELCP\ENT FROJ NO
--.. -
- - - - - -
- -
. 66 66
I
I.
I
-
, - .
"~ -> ....
1
-
o.
f)
LJ .
....
...
,'V
-I"
I'
.
,"
. I
.
1-" .
,-
:
,
FEASIBILITY REPORT
CONCRETE ALLEY PAVING
11TH AVE N/12TH AVE N/1ST ST N/400' SOUTH
CITY PROJECT NO. 92-11A
MARCH 30, 1993
Introduction
The 1993-97 Capital Improvement Plan (C.I.P.) includes an alley paving
project for each year of the five year plan. The 1993 plan identified
two alleys that staff determined were necessary to upgrade with
concrete paving due to the high maintenance and drainage problems
associated with them. The city Council reviewed these proposed alley
paving proj ects during their review of the C. I . P., and subsequently
authorized staff to begin the initial analysis of these projects upon
their adoption of the C.I.P. .
Backqround
The alley bounded by 11th Ave N/12th Ave N/1st st N/400' south is
presently considered an unimproved alley. Its surface consists of a
1" - 1.5" asphalt layer that has poor drainage characteristics. The
combination of the thin asphalt layer and the poor drainage patterns
have resulted in this alley developing many potholes over the years
thereby substantially increasing maintenance and other associated
problems.
Proposed Design
The proposed alley improvement project provides for the construction
of a concrete pavement surface 12 feet wide and six inches thick in
accordance with the City of Hopkins' improvement policy. New alley
aprons will also be constructed on 1st st N and on 12th Ave N to
better match existing grades on these streets. Driveway aprons will
be paved between the new alley surface and the paved driveways with
similar material as the top surface of the driveway. Gravel will be
placed in driveway openings in all situations other than matching
concrete or asphalt driveways. There will be no sod restoration on
this proj ect. Black dirt and seed will be placed in all disturbed
turf areas along the alley.
The pavement will include a "V" design, slightly depressed in the
middle, to channel water towards the middle of the alley instead of
towards adjacent properties. It is also proposed that the pavement
grades be established to direct the drainage to an existing storm
sewer catch basin located on the south end of the alley.
Feasibility Report: Project No. 92-11A
Page 2
Proposed Fundinq
It is proposed that the concrete pavement portion of the project
be
assessed in accordance with city policy, 80% against
abutting
benefitted properties and 20% against the City of
Hopkins. It is
further proposed that the storm sewer portion of the project be paid
entirely from the storm sewer utility fund, and also
the 20%
assessment against the City of Hopkins.
It has been determined that the fairest method to assess this project
is on a per lot basis. The Hennepin County Library will be assessed
for 6 lots as a direct benefit. U.S. West will be assessed for 6 lots
as an indirect benefit. A summary of the estimated
costs and
assessments are provided below. Assessments per lot are shown on the
attached site plan.
Proiect Costs
Contract Costs $22,035.00
Engineering $ 5,000.00
Total $27,035.00
80% share of Total Project Cost
per assessment policy $21,628.00
18 assessable lots in project
resulting in a per lot assessment of: $ 1,200.00
Assessment Period 10 years
Interest Rate 8%
Recommendation
It is recommended that the City Council accept the
city Engineer's
feasibility report as outlined herein, and order the improvement made
subsequent to holding a public hearing.
Respectfully submitted
/:/'7
~/ d~~
. / //~ -c ,.. ---.I }//? 4?/7 L-
Lere GustafsOn, P~E.
City Engineer
Hopkins Alley Improvements
Cost Estimate for Alley "A"
RCM project No. 10169.01
March 1993
unit Pavement st. Sewer
Description Unit ~ Cost Cost Cost
Remove Bituminous Pavement SY 780 $2.00 $1,560.00
Remove Concrete Sidewalk SF 200 $1.00 $200.00
Remove Concrete Curb & Gutter LF 60 $2.00 $120.00
Remove Concrete Driveway Apron SF 170 $1. 00 $170.00
Remove & Reinstall Steel Posts EA 10 $25.00 $250.00
Sawcut Bituminous LF 300 $2.00 $600.00
Bituminous Patching SY 75 $25.00 $1,875.00
tIlcrete Pavement SY 725 $22.00 $15,950.00
Concrete Driveway Apron SF 170 $3.00 $510.00
6" Concrete Sidewalk SF 200 $3.00 $600.00
Connect to Existing Catch Basin EA 1 $300.00 $300.00
12" RCP,CL.V LF 10 $30.00 $300.00
2' x 3' Box Catch Basin EA 1 $600.00 $600.00
Seeding LS 1 $200.00 $200.00
SUBTOTAL $22,035.00 $1,200.00
ENGIN. $5,000.00
TOTAL $27,035.00 $1,200.00
- - -. - - - - - -
----
9+84
CONSTUCTION
-1 EXISTING 12TH AVENUE NORTH
:: AT FLOWLINE.
:r:
---- f-
a:::
:!.s::..y_ __ I.P.F. I.P.F. I.P.F. 0
<IE EXISTING CONC I --- -----r---- --- I ---J Z
'ALK AND APRON. I f-
BLOCK 70 . t:1
$1200 \ $1200 $1200 $1200 $1200 II $1200 g:
fRUCT 12' WIDE 19 20 21 22 23 24 I (f)
~ETE APRON PER , I
- TO ALIGN WITH ST A 9+84 TO 10+50. I I t;
)SED ALLEY. ~ TRANSITION FROM CONC.
APRON TO INVERTED CROWN ...-
] 0 MAINTAIN DRAINAGE ONTO S REET. \ PROTECT TIMB
\ RET. WALL IN
IRE PAVEMENT PLACE.
)TED. 8LK.SPRC. I
': --PROTECT FENCE IN PLACE :
I LOC ST I STA. 14+53
END CONSTRU
BIT MA TCH EXIST/:
~ . AT FLOWLINE.
1tK,SP~C'I.P.F.1 0 \GRAV. I.~.
I.P.F. 12 Di
P.POLE ' '~P.POLE
IE EXISTING STEEL PO RELOCATE I PST -
I INTERFERE WITH BIT. aapST BIT.
'RUCTION. RIENSTALL PARKING
ENT TO PAVEMENT. LOT. LT. 6
S A. 11 +30 I I
$ CONNECT TO EXIST. \
7200 CATCH BASIN. INY. 921.95 I REMOVE AND
INSTALL 10 LF 12" RCP I EXISTING CON
@ 2.0%/.. AND 2' X 3' BOX \ I AND APRON F
CA TCH tjASIN W NEEHAH _
10+00 TO STA. 11 +20 R-3349-A CAS1i'NG OR EQUAL. DE I AIL.
:ACTOR SHALL REMOVE, TC - 92555 WEST ulNNEAP LIS 2ND A ITION
GE AND REPLACE EXISTING INY -= 92'205 M 0
lETE PARKING STOP StOCKS. " 1 I \ \ \ REMOVE AND
ENTAL) I 6 5 4. 3 2 1 30LFS618
I $~600 I \ $1200 $1200 I $1200 C & G.
---._--:-;---.. . - -.. .. 1m ..... .--:-:-:-::-~--:----:-- I W" ..... J __ p' ._ ___... I ...._ .. __.n j ___... _. .... . ._. I u.------
I") N!. I'}(D -- <'II ('oj 001 ,.,.,; - .. 0 mi.. -. <01- .. .. I'1t . O"~' U)
;;; ~ I .' -.~~~~'.~:.:-- =~.. =.~...~.. ~ ~:- :;==: :2! _.. ..... ~..-- . ;::1= ~j: ~ ~.
u-~~-l-~--:--:..~~-. ~~~ ..~~-.~.~--~:~=..:~~~~.~~.~-~=.-..~~ ~~_~_~____ ~~ -. .~..~....___.~ - _..__~___ ,~__~~_~___~ _.___.
,
CITY OF HOPKINS
Hennepin County, Minnesota
RESOLUTION NO. 93-48
RESOLUTION ORDERING IMPROVEMENT AFTER PUBLIC HEARING
WHEREAS, a resolution of the city Council adopted the 20th day of
April, 1993, fixed a date for a Council hearing on the
proposed improvement of an alley on the block between
11th/12th Avenues North, Mainstreet and 1st Street North,
and
WHEREAS, the Council deems it appropriate and expedient to
reconstruct the alley with concrete pavement, and
WHEREAS, ten days mailed notice and two weeks published notice of
the hearing was given, and the hearing was held thereon on
the first day of June, 1993, at which all persons desiring
to be heard were given an opportunity to be heard thereon,
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
HOPKINS, MINNESOTA:
1. Such improvement is hereby ordered as proposed in the
Council resolution adopted the 20th day of April, 1993.
2. RCM Associates, Inc. is hereby designated as the
engineer for this improvement and shall prepare plans
and specifications for the making of such improvement.
Adopted by the City Council of the City of Hopkins this 1st day
of June, 1993.
BY:
Nelson W. Berg, Mayor
ATTEST: