Loading...
CR 92-05 Storm Sewer - Bursch Site v "" December 24, 1991 o P K \ ~ Council Report: 92-5 STORM SEWER - BURSCH SITE CHANGE ORDERS 1 & 2 - RESOLUTION ACCEPTING WORK Proposed Action: staff recommends adoption of the following motion: Move that Council authorize Chanqe Orders 1 and 2 and adopt Resolution 92-3. Resolution Acceptinq Work. Storm Sewer - Bursch site. This action closes the construction phase of City Project 91-03 by accepting and approving the improvement work completed. Overview The rerouting and installation of storm sewer pipe at the Bursch Restaurant site is complete, and the contractor has agreed to final paYment. Change Orders 1 and 2 are submitted with this report and become part of the final payment to the contractor. Primary Issues to Consider o What is the substance of the two change orders? o What is the final construction cost? o staff recommendation? Supportinq Information o Change Orders 1 and 2 o RCM letter of recommendation o Resolution 92-3 ~~ James Gessele Engineering Superintendent CR: 92-5 Page 2 Analysis of Issues o What is the substance of the two change orders? Change Order No. 1 involves the reconstruction of an existing storm sewer manhole and of a catch- basin. The manhole needed additional invert work to facilitate flow and the catchbasin was in deteriorated condition and needed to be rebuilt. This was unanticipated work and the contractor quoted $1500 to perform the additional tasks. Change Order No. 2 is merely a compensating document to account for actual contract quantities. The net result in this Change Order is an increase in contract work of $3,971.86. o What is the final construction cost? The final project cost was $57,004.66 as opposed to the original contract amount of $51,532.80. Funding for this project has been through TIF monies. o staff recommendation? The necessary documents for final payment (lien waivers, state of Minnesota Withholding Affidavits) have been submitted. Final inspections by the city and the consultant engineer have been performed and the work has been found to be acceptable. staff concurs with ReM Associates that final paYment should be made in the amount of $4,258.13. JG12241B (Instructions on reverse side) No. 1 PROJECT: Hopkins Theatre Site Plan Improvements City of Hopkins 1010 South 1st Street Hopkins, MN 55343 DATE OF ISSUANCE: October t1~j)J~ch,;o. 9/-0 ~ OWNER: (Name, Address) F'OI n:-:I;;' , If'\ L_'_I\.I\li, C -J CONTRACTOR: G.l. Contracting OWNER's Project No. P-lJ"'I-ij; c~ 9 /_o'3"\l~'~' J/0 ENGINEER: Rieke, Carroll, Muller Assoc., Inc CONTRACT FOR: General Construction . ENGINEER's Project No. 10112.02 You are directed to make the following changes in the Contract Documents. Description: 1) Reconstruct invert in existing storm sewer manhole. 2) Reconstruct existing catchbasin. Purpose of Change Order: 1) Requested by City to direct flow through manhole more smoothly. 2) Catchbasin casting could not be adjusted without rebuilding structure. Existing structure was deteriorated. Attachments: (List documents supporting change) Pri ce quotati on from the Contractor for reconstruct; ng catchbasin. Price for MH invert -is $850.00. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: Original Contract Price Original Contract Time s 51,532.80 Final Completion - July 1, 1991 days or dau Previous Change Orders No. to No. Net change from previous Change Orders s o o days Contract Price prior to this Change Order Contract Time Prior to this Change Order s 51,532.80 Final Completion - July 1. 1991 days or dale Net Increase (cUS&~~of this Change Order Net Increase (decrease) of this Change Order $ 1,500.00 o d.ays Contract Price with all approved Change Orders Contract Time with all approved Change Orders $ 53,032.80 Final Completion - July 1, 1991 d.ays or date ~ RECOMMENDED: APPROVED: ~Yd~~W Enilneer (0 .- { So _I( i' Owner by EJCDC 'No. 1910-8-B (1983 Edition) Prepared by the Engineers. loint Contract Documents Committee and endorsed by The ....ssocialed General Conlractors of America. G. L. CONTRACTING. INC. r. o. . 0 X 3.. 0 . ~ I 1 I .. 2 1 W. .. 7 t h ST. HOPKINS. MN 553..3 MTKA.. MN 553..3 (612) 935.16..5 Date: 10/9/91 ill ~&&ll\Yl&[]] OCT 11 1991 ReM 10901 Red Circle Drive P.O. Box 130 MTKA MN 55343 Rlus-Cllffa/!.A!ullar ~&~!ltjlllu me. Box 130 HOi1kim;. Mmn. 55343 Attn: Dick Kloskin Re: CB at Hopkim Twater As per our oonversation on 1019/91 the price to reconst.nx:t tOO ca1chbasin is $650.00 Thwk You G:~ Contrcu:1ing Inc,' _~ D ~C#~~~ Ralph Murphy ~ i .. EQUAL OPPORTUNITY EMPLOYER .. CHANGE ORDER No. 2 (Final) - PROJECr . .~~.~~~ ~~. .T~~~ ~.~~.. ?~ ~.~. .~~ .~~.. ~mr:irovements DATE OF ISSUANCE .~.~Y.~.~~.r:..~?L.~~.~~..... EFFECTIVE DATE ...~.qY.~~l?!=.r:..?g~.J~.~L............. OWNER.. ~].ty. .Q."(. .IiQ.p.~.ifJ.~.. ........... .~. ....... ........................................................... ........ OWNER's Contract No. .. .91-;03......... ................. CONTRACTOR ..G...~:.. ~.qntr.gf1:J.1)9........ ENGINEER gj.~K~..~p.xr.QJ.l. .t:1!J.l J.~r: .A~?Q~:-,.. J.D~:. You are directed to make the following changes in the Contract Documents. Description: Fi na 1 Change Order Reason for Change Order: The purpose of this Change Order is to establish the final quantitiE and the Final Contract Amount. Attachments: (List documents supporting change) Supplement to Change Order No. 2 (1 page) CHANGE IN CONTRACT PRICE: CHANGE IN CON1RACT TIMES: Original Contract Price ~ 51,532.80 Original Contract Tunes Substantial Completion: Ready for final, ~yment: June 15, 1991 JUly 1, 1~~1 do.ysordalc:s Net changes from previous Change Orders No. ..L to No.-L $ 1=,500.00 (Add) Net change from previoos Change Orders No. -.L to No...l o do.ys Cootract Price prior to this Change Order $ 53,032.80 Contract Times prior to this Change Order Substantial Completion: June 15, 1991 Ready for final payment: J U 1 y 1, 1991 days or dales , $ Net Increase ()(e<:)QgeXof this Change Order 3,971.86 Net Increase (decrease) of this Change Order o days Contract Price with all approved Change Orders s 57,004.66 Contract Tunes with all approved Change Orders Substantial Completion: June 15, 1991 Ready for final payment: J U 1 y 1, 1991 .ysorcbres By: Owner (A~ SipIabm:) ) I ACCEPTED:.." / 8'- ::/i-J. ..l/ ./ " .'" .'.." , ~~.;'... .1.7' .. ....-:' By: -,l~/ :' /,f'/2'~~ .<:oiliniaor (Authori!zcd SiplilR:) '. . ,-, " "0' / - ) .,,! ....J,~ .J Date: /,/1 '/ ~ -1.1 ,. RECOMMENDED: By: ~ ~)Zt,;T,,~ En,pnccr (Authorized Sipa!urc) 11/2Z/91 . . APPROVED: Date: Date: EJCDC No. 1910-8-B (1990 Edition) Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of A~rica. SUPPLEMENT to CHANGE ORDER NO.2 HOPKINS THEATRE SITE PLAN IMPROVEMENTS CITY OF HOPKINS PROJECT NO. 91-03 ReM PROJECT NO. 10112.02 Date of Change Order: November 22, 1991 The final quantities and final Contract Amount shall be as follows: Estimated Final Unit Item Description Unit Quantity Ouantity Price Amount I Mo biliza tion LS 1 1 $1,500.00 $1,500.00 2 Demoli tion . LS 1 1 4,695.70 4,695.70 3 Saw Concrete LF 70 34 4.20 142.80 4 Sa w Bituminous LF 520 469 2.10 984.90 5 8" Sanitary Sewer Repair LS 1 2 1,026.80 2,053.60 6 12" RCP Class V LF 55 93 16.60 1,543.80 7 18" RCP Class V LF 38 38 34.60 1,314.80 8 36" RCP Class V LF 201 198 49.00 9,702.00 9 26"x43" Arch RCP Class III LF 16 18 60.70 1,092.60 10 RCP A Transition EA 1 1 756.80 756.80 11 Manhole (7' diameter) EA 3 3 3,899.70 11,699.10 12 Catchbasin EA 1 1 1,209.40 1,209.40 13 6" Concrete Drive Pvmnt SY 210 214.11 24.90 5,331.34 14 4" Concrete Sidewalk SF 200 266.5 2.40 639.60 15 MnDOT 31 B Bit. Base Mix TN 90 60.72 32.60 1,979.47 16 MnDOT 41A Bit. Wear Mix TN 100 144.43 37.00 5,343.91 17 Bit. Mat'!. for Tack Coat GL 60 25 1.90 47.50 18 Agg. Base, Cl. 5, 100% Crushed TN 310 396.07 10.60 4,198.34 19 B618 Concrete C & G LF 30 84.6 15.00 1.269.00 Final Amount for Original Work $55,504.66 Less Original Contract Amount (51.532.80) Increase in Contract Amount for Original Work. $3,971.86 20 Change Order No. 1 LS 1 1 $1,500.00 $1,500.00 Summary of Contract Amount Changes Original Contract Amount $51,532.80 Change Order No. I 1.500.00 Contract Amount Prior to this Change Order $53,032.80 Increase in Contract Amoun,t from this Change Order 3.971.86 FINAL CONTRACT AMOUNT including this Change Order $57,004.66 Page I of 1 December 19, 1991 Mr. James Gessele Engineering Superintendent City of Hopkins 1010 First St. South Hopkins, MN 55343 <l(gDTITI RE; Hopkins Theatre Site Plan Improvements Hopkins, Minnesota City Project No. 91-03 RCM Project No. 10112.02 Payment Application No.3 (Final) rieke carroll muller associates, inc. enQineers -hiteets ,j surveyors equal opportunity employer Dear Mr. Gessele; Enclosed are three (3) signed originals of Payment Application No. 3 received from G.L. Contracting. This constitutes the Final Payment Applica tion for this project. With receipt of the Final Change Order and the closeout submittals being transmitted to you today under separate cover, we recommend the City of Hopkins make this final payment in the amount of $4,258.13 as requested. Please call if you have questions. Sincerel y, y~t0~ James B. Hammer, P.E. RIEKE CARROLL MULLER ASSOCIATES, INC. JBHj jj Enclosures (3) c: Ralph Murphy; G.L. Contracting (w j encl.) J01 red circle drive box 130 minnetonka. minnesota 55343 612-935-6901 CITY OF HOPKINS Hennepin County, Minnesota RESOLUTION NO: 92-3 RESOLUTION ACCEPTING WORK - STORM SEWER, BURSCH RESTAURANT SITE WHEREAS, pursuant to a written contract signed with the City on May 20, 1991, G.L. contracting Inc. of Minnetonka, Minnesota, has satisfactorily completed the improvements near the Bursch Restaurant site (City Project 91-03) in accordance with such contract, NOW, THEREFORE, BE IT RESOLVED BY THE CITY OF HOPKINS, MINNESOTA: 1. The'work completed under said contract is hereby accepted and approved. 2. The City Clerk and Mayor are hereby directed to issue a proper order for the final paYment on such contract, taking the contractor's receipt in full. Adopted by the council this 7th day of January, 1992. Nelson W. Berg, Mayor ATTEST: James A. Genellie, city Clerk JG12241B/3