council Report: 92-94
1992 BITUMINOUS SEAL COAT
BID AWARD
Proposed Action
Staff recommends
contract for the
Roadways."
adoption of the
1992 Bituminous
following
Seal Coat
motion: "Award the
proiect to Bituminous
The bid opening for the 1992 project was held at City Hall on April
29, 1992.
PrimarvIssues to Consider
o Bid Tabulation and recommendation
BIDDER STREETS PARKING LOTS TOTAL BID
Bituminous Roadways 40,041. 66 820.25 40,861. 91
Astech Corp. 40,307.45 1,197.65 41,505.10
Minnesota Roadways 40,702.60 2,162.30 42,864.90
Allied Blacktop 46,406.16 4,200.00 50,606.16
Engineer's Estimate 46,700.00 1,600.00 48,300.00
All bids were submitted with required bid security and made by
qualified contractors. Reference by other cities and staff's own
knowledge of contractor prompts staff to recommend award of
contract to Bituminous Roadways.
o 1992 Seal Coat Budget
The city has budgeted $56,000 towards the current seal coat
program. The low bid is for bituminous material and aggregate
rock installed. Staff has scaled back slightly on planned
installation and the contracted work will cost approximately
$38,000, based on bid item quotes. The city needs to pay for
aggregate material delivered at a projected cost of $17,000. The
total estimated project cost of $55,000 falls within the budgeted
amount.
cf-~ L~
James Gessele, Engineering superintendent
.