Loading...
CR 92-190 Change Order #1 Knollwood St .'L . .. . f :\- ( '\ \. "\" y 0 :M o PK \..~ .; council Report: 92-190 September 3D, 1992 Approve Change Order No. 1 Knollwood street Reconstruction Proposed Action. staff recommends adoption of the following motion: Move that Council authorize Chanae Order No. 1 as it concerns the Knollwood Street Reconstruction Proiect. Overview. In an early August Council Update staff made Council members aware of unsuitable backfill materials encountered during utility installation and relocation associated with the Knollwood project. The report then spoke of significant amounts of bad backfill soils and that the soils engineer had already recommended importing new granular material to the site. RLK Associates then negotiated a price for trench backfill sand (disposal of .unsuitable materials and stabilization of utility trenches) and a price for subgrade stabilization rock (stabilize the top of utility trenches to prevent rutting). The contractor has been required to use these imported materials on all utility trenching at Knollwood. Throughout utility work on this project it has become evident that soils characteristics are different than that portrayed in the original soils investigation report of 1990. Borings taken in advance of this project did not indicate any problems. The city's current soils engineer has investigated the impact these deeper poor soils will have on the roadway section design. Staff will need to present an additional change order in the future. PrimarY Issues to Consider. . What is the justification for a change order? . What are the costs and source of funding? · staff recommendation Supportina Information. · Change Order No. 1 . supporting letters from RLK Associates ~~~- James Gessele Engineering superintendent .', \ ~ '. . . . Analvsis. · What is the justification for a change order? The first two items of this change order concern utility trenches: trench backfill sand and subgrade stabilization rock. In summary to the attachedRLK letters, the case is made for disposing of unsuitable materials because they have failed compaction tests and undergone severe settlement and rutting under automobile traffic. The solution is to replace these soils with imported material. The third item concerns relocation of a hydrant on Cottage Downs. The original contract specifications for hydrant relocations provided for hydrant lead extensions. In this case tha hydrant was not extended but actually moved to another location and this required considerable extra contractor labor. · What are the costs and source of funding? Costs Trench backfill sand Subgrade stabilization rock Relocate hydrant $28,880.49 15,923.25 1.500.00 Total Change Order $46,303.74 Source of Fundinq. Funding will be on a prorated basis from the three utility funds. · Staff recommendation Staff concurs with RLK Associates' assessment and recommends Council authorize this change order. ~ . . . , -:;.. CHANGE ORDER NO. 1 RLK Associates, Ltd. 922 Mainstreet Hopkins. MN 55343 TO: Widmer. Inc. P.O. Box 219 St. Bonifacius. MN 55375 CONTRACT FOR: Date: September 9, 1992 Project No. & Desc. 90-01 Knoltwood Neighborhood Contract Date: June 10. 1992 UTILmES AND ROADWAY YOU ARE HEREBY DIRECTED TO MAKE THE FOLLOWING CHANGES TO THE ABOVE MENTIONED CONTRACT: ADDITIONS: Trench Backfill Sand Sub grade Stabilization Rock Relocate Hydrant at Cottage Downs TOTAL CHANGE ORDER Unit Qty. TON TON EACH. 2,977 .37 1,273.86 1.00 ------_-....-...~----------------- CONTRACT STATUS PER THIS CHANGE ORDER The time to complete the contract is : X I f Unchanged f f Increased by Days I I Decreased by Days The date Of completion is Now Unit Price Total Price $ 9.70 $ 12.50 $ 1,500.00 $ 28,880.49 $ 15,923.25 $ 1,500.00 Original Contract Sum $ 661,435.50 Net Change Order By Previous Change Order $ Contract Sum Prior to this Change Order $ 661,435.50 I I Addition x I , Deduction Made by this change order New Contract Sum $ 46,303.74 $ 707,739.24 $ 46,303.74 ACCEPTANCE 0.00 ENGINEER: RLK ASS CIA TES, LTD. -z..,,- ~ .7 ~.,~' i'..7 By ,~~cr..::€; Date l' /~/~0 OWNER: CITY OF HOPKINS By Date CONTRACTOR: r By ~ :;._/~. ~. Date tI I . :~: .' . :; ..' ~.. . +. . .~ . : ." ~ :. .!....... ...:' :~... ",". . ... ~. .' ~ , .' : .... . 922 M~itistr~~t. :. Hopkjns, Mn'~: . ;' ",55343 (612) 933.0972 . fax: (612) 933.1153 ...' .... . PROJECT NO. 90 -0 / FOLDER NO. 4- :'. . ,. 'July 27,:; 1992 :. INITIALS' .;j. Tt'; Mr. Lee Gustafson City Of Hopkins 1010 First Street South Hopkins, MN 55353 Dear Lee: . This letter is to follow up on the Knollwood soils conditions. As we discussed on July 21, Widmer has encountered a significant amount of unsuitable backfill material during their utility installation operations. One particular area was test-rolled; deflec,tion of the compacted material exceeded 6". Based upon these conditions, RLKAssociates SOlicited a cost from Widmer for exporting the unsuitable soils and importing an acceptable backfill material. widmer has returned to us.a cost of $9.70 per ton for import material, the cost of which shall include removal of the in- place material to a location off-site. . The material'which'the. contractor is importing is a "~creen reject", and has a 100% passage of the 34 sieve and a 0% passage of the #200.GME has examihed the material and recommended it for use as trench baskfi11. Based upon our previous conversation, 'the contractor has begun using this material. At this point it is difficult to determine exactly how much of the existing material is unsuitable and how much imported fill will be required. RLK Associates will keep you p6sted an the situation so that you have a handle on the total cost in~urred due to this item. Please call if you have any questions or concerns. Sincerely, k ~e's irrzK' \/Senior Eng1neeringTechnician . . Civil Engineering. Transportation. Infrastructure Redevelopment . Landscape Architecture. Construction Management ! ,. :"~. . .-.~. '. '. " ' ". '. . . . ',. "",. ..' .. "'~...: ~. ......:..92.2..Matn~tree~.:. . .::. Hopkins, Mn. . " . '. '55343 (612) 933..()972 fax: (612) 933.1153 . September 15. 1992 .~ ". ~ . . ~.'~ -.~. ... ~ ' ::. . ..' . _r" . .: ~ ,~'-...,~.; : ..,; . ~ . ~ ~ ~ :'~ ';'., . " <' :, 1 .~. .. -. : _ . . . -. . .;.-- ... .t. ' T '. ,_.., .' ,. . . ." r. - :"Mr'.- I'mi. Gessele . ." .., ,', ~',:;:. ..:CiWofHopidris' ..... ..".,.. .' . .<.:. '. 'JOlOSouth FirsfStreet. . .. ..': ,,' ,. '.'.Hopkins;MN .55343.. ...,: ...,' ". "" -... . . '. .' ',. : ~ . ~ - .' '. ".' .,,". ".. ... ..r....'.. Re: KnollwoOO Project Application.for Payment No. 2 Change Order No.1 Dear Mr. Gessele: . Enclosed please fmd three (3) copies each of Application for Payment No. 2 and Change Order No.1. Payment No.2 is for contract work performed at the Knollwood Project thTough September 3, 1992. Including work contemplated by Change Order No. 1. Change Order No. 1 includes the following required revisions to the project contract: . Item 1: Trench Backfill Sand This change was necessary due to very soft and wet soils which were encountered during excavation of the utility trenches. An attempt was made to utilize these wet and soft soils for the backfilling of the utility trenches, but in nearly all locations where these soils were utilized, . they have proven unsuitable. These soils have failed compaction tests and have undergone severe settlement and rutting under construction and automobile traffic. Therefore, upon our recommendation and approval by the City. we have required the - Contractor to backfill utility trenches which consist of soft and wet plastic soils with sand backfill. . We have negotiated a price of $9.70/ton for "Trench BackfIll Sand". This unit price includes all costs associated with furnishing, hauling, properly installing and compacting of the trench backfill sand, as well as haul~ng off site the unsuitable excavated soils from trench. Item 2:. Subgrade Stabilization Rock Subgrade stabilization rock was required to stabilize the top of the utility trenches where severe . rutting was taking place, due to backfilling of these trenches with the excavated soft and wet plastic soils. .. Upon our recommendation and approval by the City. we negotiated a price of $ 12.50/ton fot "Subgrade Stabilization Rock." This unit price includes all costs associated with furnishing, hauling, properly installing,compactirig and shaping of the material as needed. · Civil Engineering. TransportatiQl1' Infrastructure Redevelopment · Landscape Arcl1itecture .. Construction Management ;1. .~. ..', .. . . Mr. Jim Gessele September 15, 1992 Page 2 Item 3:. Relocate Hydrant at Cottage Downs. . . , ., ~_. . . - This change was necessary due.to the fact that the ~riginal contract item f~r hydrant.r~locations orily provided "for extending the hydrant lead and placing the hydrant farther out from the main. In this instance, it was necessary to relocate the hydrant easterly, along the main and roadway , requiring the plugging of the existing lead. and requiring the contractor to tap into the main ata . new location, to provide a new hydrant lead. We have negotiated a price of $1,500.00 for this work. We recommend approval of the enclosed Change Order No.1 along with Application for Payment No.2. Should you have any questions, please give us a calL Sincerely, FDH:js cc: Lee Gustafson enclosures