Loading...
CR 92-209 Change Order Knollwood Street . . . r '\ october 14, 1992 \ "{ y 0 - o p' K \ ~, Council Report '92-209 APPROVE CHANGE ORDER NO. 2 KNOLLWOOD STREET RECONSTRUCTION proposed Action. Staff recommends adoption of the following motion: Move that Council authorize change Order No. 2 as it concerns the Knbllwood street Reconstruction Project. overview At its October 6 meeting council was provided information concerning the poor subgrade soils encountered during Knollwood street reconstruction and how that precipitated change Order No. 1. Council was also informed of an additional change order request in the near future. This report outlines the need for a second order. ' Primary o o o Issues to Consider What is the justification for a change order? What are the costs and source of funding? Staff recommendation SUDDortina Information o change Order No. 2 o Supporting letter from RLK Associates ~~ James Gessele ' Engineering Superintendent . . . CR92-209 Page 2 Analysis o what is the justification for a change order? The first six items under "Additions" concern extra utility work. In summary, additional expense was encountered in replacement of unsuitable trench soils, relocation of hydrants, the use of 24" steel casing instead of 16" for sanitary sewer relocation, and extra pipe fittings to accommodate reconnection of residential sewer services to the new sewer main. The last two items under "Addition" concern the use of select granular borrow and'geotextile fabric. Thesetwo items were recommended by the field soils engineer to provide adequate subsoil drainage in the roadway and stabilizing support of the gravel base and bituminous courses. The attached letter from RLK Associates gives a more detailed accounting of the recommended additions to the original contract. o What are the costs and source-of funding? Costs Trench backfill sand Over depth hydrant relocation 24" steel casing Sewer pipe and connections Select granular borrow Geotextile fabric Deductions $14,165~49 5,400.00 19,845.00 5,274.00 12,150.00 33,622.20 (22,327.50) Total Net Change Order $68,129.19 Source of fundinq utility items will be funded from utility funds. The select granular borrow and fabric items will be funded by the contracts contingency fund or PIR funds. o staff recommendation. Staff concurs with RLK Associates' assessment and recommends Council authorization of this change order. + . . " . CHANGE ORDER NO.2 RLK Associates, Ltd. 922 Mainstreet Hopkins, MN 55343 Date: September 28, 1992 TO: Widmer, Inc. P.O. Box 219 St. Bonifacius, MN 55375 Project No. & Desc. 90-01 Knollwood Neighborhood Contract Date: June 10. 1992 CONTRACT FOR: UTILITIES AND ROADWAY ------------------- ----------- You are hereby directed to make the following changes to the above mentioned contract: ADDmONS: Unit Q!y,. Unit Price Total Price Trench Backfill Sand TON 1,460.36 $ 9.70 $ 14,i65.49 Over Depth Hydrant Relocation EACH 6.00 900.00 5,400.00 . 24" Steel Casing, Jacked L.F. 147.00 135.00 19,845.00 8" x 6" PVC Wye EACH 18.00 85.00 1,530.00 6" PVC Service Pipe L.F. 158.00 16.00 2,528.00 6" PVC Bend EACH 38.00 32.00 1,216.00 Select Granular Borrow, Mod.(CV)* C.Y. 1,500.00 8.10 12,150.00 Geotextile Fabric S.Y. 18,679.00 1.80 33.622.20 Subtotal Additions $ 90,456.69 *Volume (CV) to be computed by applying appropriate shrinkage factor to vehicle measure (LV) DEDUCTIONS 6" Water Main L.F. 553.00 17.50 (9,677.50) DIP - Class 52 16" Steel Casing - Jacked L.P. 110.00 115.00 02.650.00) $ 22,327.50 . Subtotal Deductions TOTAL CHANGE ORDER $ 68,129.19 1'" . . . . ." CHANGE ORDER NO.2 (CONTINUED) CONTRACT STATUS PER THIS CHANGE ORDER The time to complete the contract is r I I I Unchanged I I Increased by Days I I Decreased by Days The date of completion is Now Original Contract Sum $ 661,435.50 Net Change Order By Previous Change Orders $ 46,303.74 Contract Sum Prior to this Change Order $ 707,739.74 I I Addition I 'Deduction Made by this change order New Contract Sum $ 68,129.19 $ 775,868.93 ACCEPTANCE ENGINEER: RLK ASSOCIATES, LTD. BY('~o;L Date z.- z- :te ~~jfJr~L;ff OWNER: CITY OF HOPKINS By Date CONTRACTOR: By' /!JAn...;~ --can/4-; 7 Date "' 922 Mainstreet Hopkins, Mn. 55343 (612)933-0972 fax: (612)933~1153 October 13, 1992 Mr. Jim Gessele City of Hopkins 1010 South First Street Hopkins, MN 55343 Re: Knollwood Neighborhood Project Change Order No.2 Dear Jim: This letter is to explain the need for the items in Change Order No.2, submitted to you on September 28, 1992. . Under "Additions", Trench Backfill Sand was needed to replace unsuitable soils in utility trenches, as in Change Order No.1. Over Depth Hydrant Locations was for moving hydrants, further out from the edge of the street, having ,water main depths greater than standard depth. The 24" steel casing was to replace the proposed 16" casing for a sanitary sewer relocation between Edgemoor Drive and Wilshire Walk. Due to large boulders in the ground, it was thought that a 24" casing would be needed in order to remove large rocks impeding the progress of the casing "push" ~ The 8" x 6" PVC wyes, 6" PVC bends, and 6" PVC pipe were to accommodate reconneciions from the new sewer mains to non-standard 6" residential services. The Select Granular borrow, Modified (sand) was recommended by our Soils Engineer to proVoide adequate subsoil drainage in subcuts which are to be drained by perforated underdrains. The Select Granular Borrow sand in the original contract has more fine particles, is less expensive, and is not considered "clean" enough to provide adequate subsoil drainage to the underdrain pipes. ,This is a "partial" quantity, and more will be needed in a later change order. The Geotextile Fabric was also recommended by our Soils Engineer for use under the Class 5 gravel base over the entire project. This is considered necessary to provide adequate subgrade support under the gravel base and pavement courses, and spread traffic loads more uniformly ~,over utility trench areas and other spots in the roadbed having more settlement potential. . Under "Reductions", 553 feet of 6" watermain was deleted and not installed adjacent to new sanitary mains. This was a cost saving measure, due to the expense of Trench Backfill Sand, and done only where the water main had not been exposed or disturbed by sanitary sewer construction and where there was no past history of water main breaks. This 553 feet of pipe will not be added as a quantity to the regular payments. . Civil Engineering · Transportati(ln · Infrastructure Redevelopment , . , . Landscape Architecture · Construction Management * -~ ~ ~ . . . Mr. Jim Gessele October 13, 1992 Page 2 The 16" Steel Casing, 110 L.F. will be deleted from a fQ.ture payment, as it has already been included in Payment No.3. The 24" casing will be added to a future payment, after approval of Change Order No.2. Please be assured that we are making every effort to keep these additional costs as low as possible, while maintaining high quality and ensuring low long-term maintenance costs. If you have any questions, please call. Sincerely, RLKASe:1~(~~ Paul D. Kroehnert, P.E. , PDK:js cc: Chuck Poppler Dick Koppy Fritz Widmer