Loading...
VII.1. Resolutions Accepting Bids and Awarding Contract for the Central Avenues Street and Utility Improvements – City Project 2024-10; Klingbeil CITY OF HOPKINS City Council Report 2025-068 To: Honorable Mayor and Council Members Mike Mornson, City Manager From: Eric Klingbeil, City Engineer Date: April 15, 2025 Subject: Accept Bids and Award Contract; Central Avenues Street and Utility Improvements – City Project 2024-10 _____________________________________________________________________ RECOMMENDED ACTION MOTION TO Adopt Resolution 2025-027, Resolution Accepting Bids, Central Avenues Street and Utility Improvements, City Project 2024-10; and Adopt Resolution 2025-028, Resolution for Award of Contract, Central Avenues Street and Utility Improvements, City Project 2024-10. OVERVIEW The bid opening for the Central Avenues Street and Utility Improvements was March 7, 2025. The low bid was submitted by RL Larson Excavating, Inc. The bid was $11,479,980.92. A total of seven (7) bids were received. RL Larson Excavating, Inc. has a good reputation with previous similar projects in the wider metro area. Staff is recommending award of the project contract to RL Larson Excavating, Inc.. SUPPORTING INFORMATION Resolutions 2025-027, 2025-028 Consultant Recommendation Tabulation and Abstract of Bid Engineering ANALYSIS OF ISSUES Bid Results and Analysis Contractor Base Bid RL Larson Excavating, Inc. $11,479,980.92 Northwest Asphalt $11,948,755.84 S.M. Hentges & Songs, Inc. $12,776,964.00 Northdale Construction Company $12,863,923.70 Kuechle Underground Inc. $13,088,414.91 Park Construction Company $13,696,286.98 Ryan Contracting $15,040,700.40 Engineers Estimate $14,180,294.50 All bids were submitted with required bid security made by qualified contractors. Project Costs Based on the low bid the total estimated project cost is $14,931,490 which includes the low bid, and soft costs. *due to rounding, totals may not add up Bids received were lower than the Engineers Estimate. In discussion with contractors, suppliers, and manufacturers it appears that construction material prices have begun to stabilize and return toward pre-covid levels. Total project costs are tracking more than $2,500,000 under CIP budgeted amount. Funding Source CIP Budget Street Reconstructio n Additional Work CIP Budget Total CIP Budget Estimated Cost* PI-PIR/General Obligation Bonds $6,037,000 $1,692,500 7,729,500 $5,552,452 Assessments 2,092,000 2,092,000 1,954,096 Storm Sewer Fund 1,248,000 39,000 1,287,000 2,594,800 Sanitary Sewer Fund 3,176,000 140,000 3,316,000 2,164,218 Water Fund 3,170,000 3,170,000 2,665,926 Total $15,723,000 1,871,500 $17,594,500 $14,931,49 0 Project Schedule Conduct Public Assessment Hearing April 15, 2025 Adopt Assessment Roll/Award Contract April 15, 2025 Begin Construction Spring 2025 Complete Construction Fall 2026 CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION 2025-027 RESOLUTION ACCEPTING BIDS CENTRAL AVENUES STREET AND UTILITY IMPROVEMENTS CITY PROJECT 2024-10 WHEREAS, pursuant to an advertisement for bids for the improvement of 9th Avenue N from 1st Street N to 3rd Street N, 10th Avenue N from 1st Street N to 4th Street N, 11th Avenue N from 1st Street N to Minnetonka Mills Road, 12th Avenue N from 1st Street N to Minnetonka Mills Road, 13th Avenue N from the regional trail N to Minnetonka Mills Road, 2nd Street N from 8th Avenue N to 12th Avenue N, 3rd Street N from 9th Avenue N to 15th Avenue N, and 4th Street N from 9th Avenue N to 10th Avenue N and 11th Avenue N to 12th Avenue N; including pavement, curbing, sidewalk, signage, drainage, water and sanitary sewer improvements and all necessary appurtenances, and bids were received, opened, and tabulated according to law, and the following base bids were received complying with the advertisement: RL Larson Excavating, Inc. $11,479,980.92 Northwest Asphalt $11,948,755.84 S.M. Hentges & Songs, Inc. $12,776,964.00 Northdale Construction Company $12,863,923.70 Kuechle Underground Inc. $13,088,414.91 Park Construction Company $13,696,286.98 Ryan Contracting $15,040,700.40 AND WHEREAS, it appears that RL Larson Excavating, Inc. of St. Cloud, MN is the lowest responsible bidder, NOW THEREFORE BE IT RESOLVED, by the City Council of the City of Hopkins 1. The Mayor and City manager are hereby authorized and directed to enter a contract with RL Larson Excavating, Inc.of St. Cloud, MN in the name of the City of Hopkins for the improvements noted above according to the plans and specifications therefore approved by the city council and on file in the office of the city clerk. 2. The city clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposits of the successful bidder and the next lowest bidder shall be retained until a contract has been signed. Adopted by the City Council of the City of Hopkins this 15th day of April 2025. By:___________________________ Patrick Hanlon, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION 2025-028 RESOLUTION FOR AWARD OF CONTRACT CENTRAL AVENUES STREET AND UTILITY IMPROVEMENTS CITY PROJECT 2024-10 WHEREAS, Bids for the Central Avenues Street and Utility Improvements, City Project 2024-10 have been accepted NOW THEREFORE BE IT RESOLVED, by the City Council of the City of Hopkins 1. That the base bid of RL Larson Excavating, Inc. in the amount of $11,479,980.92 is the lowest responsible base bid for the Central Avenues Street and Utility Improvements, City Project 2024-10, and the Mayor and City Manager are hereby authorized and directed to enter into a contract with said bidder for and on behalf of the City. Adopted by the City Council of the City of Hopkins this 15th day of April, 2025. By:___________________________ Patrick Hanlon, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk H:\HOPK\24X134763000\1_Corres\A_Meetings\2025-4-15_Assessment Hearing\Hopkins Central Avenues Ph 2_Award Recommendation Letter.docx April 7, 2025 Mr. Eric Klingbeil, P.E., City Engineer City of Hopkins 1010 1st St S Hopkins, MN 55343 RE: Central Avenues Improvements Phase 2 City of Hopkins, Minnesota City Project No. 2024-10 Project No.: 24X.134763 Dear Mr. Klingbeil, Bids on the above-referenced project were opened at 10:00 a.m. on March 7, 2025. There were seven bidders for the project; a tabulation of bids received and a detailed bid abstract are enclosed. The low bidder on the project is R.L. Larson Excavating, Inc. with a bid of $11,479,980.92. R.L. Larson Excavating has previous experience on projects of this size and complexity in the Twin Cities metro area. Based on R.L. Larson’s experience, acceptable bid prices, and the competitive bids the City received, we recommend the City of Hopkins award the project to R.L. Larson Excavating, Inc. following the Public Assessment Hearing on April 15, 2025. If you have any questions regarding this award recommendation, please contact me at your convenience. Sincerely, Bolton & Menk, Inc. Nicholas J. Amatuccio, P.E. Municipal Project Manager | Principal BID TABULATION Central Avenues Improvements Phase 2 City of Hopkins Hopkins, MN 24X.134763 Bid Taken: 3/07/2025 Addendums: #1 – 3/04/2025 Time: 10:00 a.m. BIDDERS TOTAL AMOUNT BID 1 RL Larson Excavating Inc. $11,479,980.92 2 Northwest $11,948,755.84 3 S.M. Hentges & Sons, Inc. $12,776,964.00 4 Northdale Construction Co., Inc. $12,863,923.70 5 Kuechle Underground Inc. $13,088,414.91 6 Park Construction Company $13,696,286.98 7 Ryan Contracting Co. $15,040,700.40 ABSTRACTCentral Avenues Improvements Phase 2 City of Hopkins, MNBMI Project No. 24X.13476303/07/2025 10:00 AM CSTSection TitleLine ItemItem CodeItem DescriptionUofMQuantityUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtension1-MOBILIZATIONLUMP SUM1$700,000.00$700,000.00$400,000.00$400,000.00$489,335.00$489,335.00$595,500.00$595,500.00$256,760.00$256,760.00$102,000.00$102,000.00$832,200.00$832,200.00$650,000.00$650,000.002-CLEARINGEACH167$300.00$50,100.00$314.00$52,438.00$309.00$51,603.00$387.00$64,629.00$367.50$61,372.50$300.00$50,100.00$368.00$61,456.00$500.00$83,500.003-GRUBBINGEACH175$150.00$26,250.00$209.00$36,575.00$206.00$36,050.00$175.00$30,625.00$220.50$38,587.50$300.00$52,500.00$221.00$38,675.00$400.00$70,000.004-DECIDUOUS TREE 2" CAL B&BEACH167$650.00$108,550.00$601.50$100,450.50$497.70$83,115.90$840.00$140,280.00$497.70$83,115.90$470.00$78,490.00$604.00$100,868.00$500.00$83,500.005-REMOVE SIGN POSTEACH106$50.00$5,300.00$41.85$4,436.10$26.25$2,782.50$45.00$4,770.00$42.00$4,452.00$40.00$4,240.00$42.00$4,452.00$20.00$2,120.006-REMOVE SIGN PANELEACH135$50.00$6,750.00$41.85$5,649.75$26.25$3,543.75$45.00$6,075.00$42.00$5,670.00$40.00$5,400.00$42.00$5,670.00$20.00$2,700.007-REMOVE CURB AND GUTTERLIN FT22490$7.50$168,675.00$3.30$74,217.00$2.78$62,522.20$4.50$101,205.00$4.23$95,132.70$4.00$89,960.00$2.55$57,349.50$5.00$112,450.008-REMOVE BITUMINOUS DRIVEWAY/TRAIL PAVEMENTSQ YD863$7.00$6,041.00$6.60$5,695.80$5.55$4,789.65$4.00$3,452.00$7.93$6,843.59$3.00$2,589.00$11.10$9,579.30$12.00$10,356.009-REMOVE BITUMINOUS STREET PAVEMENTSQ YD42396$4.00$169,584.00$7.90$334,928.40$1.07$45,363.72$4.50$190,782.00$2.91$123,372.36$5.00$211,980.00$1.15$48,755.40$5.00$211,980.0010-REMOVE CONCRETE WALKSQ FT110264$1.50$165,396.00$0.85$93,724.40$0.46$50,721.44$0.50$55,132.00$1.06$116,879.84$1.00$110,264.00$1.05$115,777.20$1.50$165,396.0011-REMOVE CONCRETE STEPEACH159$100.00$15,900.00$49.30$7,838.70$100.00$15,900.00$200.00$31,800.00$528.85$84,087.15$75.00$11,925.00$161.00$25,599.00$50.00$7,950.0012-REMOVE CONCRETE DRIVEWAY/ALLEY PAVEMENTSQ YD1300$12.00$15,600.00$7.90$10,270.00$9.45$12,285.00$6.00$7,800.00$10.58$13,754.00$8.00$10,400.00$14.60$18,980.00$12.00$15,600.0013-REMOVE TRAFFIC SIGNAL SYSTEM (MINNETONKA MILLS/5TH AVE N)LUMP SUM1$15,000.00$15,000.00$9,890.00$9,890.00$7,350.00$7,350.00$14,000.00$14,000.00$9,922.50$9,922.50$9,500.00$9,500.00$9,920.00$9,920.00$9,450.00$9,450.0014-REMOVE PEDESTRIAN FLASHER SYSTEM (11TH AVE S)LUMP SUM1$10,000.00$10,000.00$4,180.00$4,180.00$4,200.00$4,200.00$5,300.00$5,300.00$4,194.75$4,194.75$4,000.00$4,000.00$4,190.00$4,190.00$4,000.00$4,000.0015-SALVAGE SIGN PANELEACH33$30.00$990.00$41.85$1,381.05$26.25$866.25$44.00$1,452.00$42.00$1,386.00$40.00$1,320.00$42.00$1,386.00$20.00$660.0016-SALVAGE FLASHING STOP SIGNSEACH2$250.00$500.00$104.50$209.00$525.00$1,050.00$110.00$220.00$105.00$210.00$100.00$200.00$105.00$210.00$300.00$600.0017-SALVAGE LIGHT POLEEACH3$750.00$2,250.00$489.50$1,468.50$1,837.50$5,512.50$615.00$1,845.00$491.40$1,474.20$470.00$1,410.00$491.00$1,473.00$500.00$1,500.0018-REMOVE LIGHT POLE FOUNDATIONEACH3$750.00$2,250.00$1,830.00$5,490.00$1,837.50$5,512.50$660.00$1,980.00$317.31$951.93$900.00$2,700.00$493.00$1,479.00$500.00$1,500.0019-SALVAGE BENCHEACH1$500.00$500.00$265.00$265.00$200.00$200.00$350.00$350.00$528.85$528.85$1,500.00$1,500.00$1,580.00$1,580.00$250.00$250.0020-SALVAGE PAVERSSQ FT1082$6.00$6,492.00$7.30$7,898.60$7.35$7,952.70$4.00$4,328.00$7.35$7,952.70$7.00$7,574.00$7.40$8,006.80$22.00$23,804.0021-SALVAGE RAILINGLIN FT20$20.00$400.00$26.00$520.00$15.00$300.00$66.00$1,320.00$30.56$611.20$150.00$3,000.00$52.50$1,050.00$15.00$300.0022-REMOVE RAILINGLIN FT26$35.00$910.00$21.00$546.00$10.00$260.00$25.00$650.00$10.58$275.08$100.00$2,600.00$61.30$1,593.80$15.00$390.0023-SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT1888$6.00$11,328.00$7.40$13,971.20$4.00$7,552.00$5.00$9,440.00$4.73$8,930.24$3.00$5,664.00$4.75$8,968.00$6.50$12,272.0024-SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT2426$3.50$8,491.00$3.00$7,278.00$3.00$7,278.00$3.00$7,278.00$1.94$4,706.44$4.00$9,704.00$1.95$4,730.70$5.50$13,343.0025-SALVAGE FENCELIN FT15$40.00$600.00$83.70$1,255.50$76.00$1,140.00$55.00$825.00$84.00$1,260.00$80.00$1,200.00$84.00$1,260.00$20.00$300.0026-REMOVE RETAINING WALLLIN FT593$22.00$13,046.00$11.45$6,789.85$4.00$2,372.00$45.00$26,685.00$10.58$6,273.94$10.00$5,930.00$15.40$9,132.20$18.00$10,674.0027-SALVAGE BLOCK RETAINING WALLLIN FT100$25.00$2,500.00$14.65$1,465.00$14.75$1,475.00$55.00$5,500.00$14.70$1,470.00$14.00$1,400.00$14.90$1,490.00$25.00$2,500.0028-SALVAGE BOULDER RETAINING WALLLIN FT100$50.00$5,000.00$17.80$1,780.00$17.85$1,785.00$75.00$7,500.00$17.85$1,785.00$17.00$1,700.00$18.00$1,800.00$25.00$2,500.0029-REMOVE HYDRANTEACH18$450.00$8,100.00$437.50$7,875.00$150.00$2,700.00$112.00$2,016.00$528.85$9,519.30$360.00$6,480.00$561.00$10,098.00$550.00$9,900.0030-REMOVE WATERMAINLIN FT9904$7.50$74,280.00$3.10$30,702.40$8.75$86,660.00$2.00$19,808.00$4.23$41,893.92$3.56$35,258.24$4.50$44,568.00$8.00$79,232.0031-ABANDON WATERMAINLIN FT1125$12.00$13,500.00$5.20$5,850.00$8.75$9,843.75$9.00$10,125.00$12.47$14,028.75$10.00$11,250.00$13.20$14,850.00$18.00$20,250.0032-REMOVE DRAINAGE STRUCTUREEACH81$550.00$44,550.00$446.50$36,166.50$480.00$38,880.00$550.00$44,550.00$846.15$68,538.15$610.00$49,410.00$897.00$72,657.00$550.00$44,550.0033-REMOVE STORM SEWER PIPELIN FT2705$15.00$40,575.00$12.85$34,759.25$10.00$27,050.00$24.00$64,920.00$15.87$42,928.35$14.00$37,870.00$16.80$45,444.00$25.00$67,625.0034-REMOVE SANITARY SEWER PIPELIN FT9279$5.00$46,395.00$2.10$19,485.90$7.00$64,953.00$3.00$27,837.00$2.12$19,671.48$3.56$33,033.24$2.25$20,877.75$5.00$46,395.0035-ABANDON SANITARY SEWER PIPELIN FT1200$12.00$14,400.00$6.10$7,320.00$7.00$8,400.00$8.00$9,600.00$13.54$16,248.00$12.00$14,400.00$14.40$17,280.00$22.00$26,400.0036-REMOVE SANITARY MANHOLEEACH46$725.00$33,350.00$474.00$21,804.00$490.00$22,540.00$240.00$11,040.00$846.15$38,922.90$610.00$28,060.00$897.00$41,262.00$550.00$25,300.0037-EXPLORATORY EXCAVATIONHOUR40$750.00$30,000.00$700.00$28,000.00$385.00$15,400.00$1,200.00$48,000.00$1,375.00$55,000.00$890.00$35,600.00$1,460.00$58,400.00$550.00$22,000.0038-COMMON EXCAVATION (P)CU YD36972$30.00$1,109,160.00$25.15$929,845.80$24.31$898,789.32$18.00$665,496.00$29.80$1,101,765.60$24.00$887,328.00$34.90$1,290,322.80$43.00$1,589,796.0039-SUBGRADE EXCAVATION (EV)CU YD1582$30.00$47,460.00$40.00$63,280.00$24.31$38,458.42$23.00$36,386.00$29.80$47,143.60$24.00$37,968.00$29.50$46,669.00$35.00$55,370.0040-RECLAIM BITUMINOUS SURFACE (IN PLACE)SQ YD4572$3.50$16,002.00$3.60$16,459.20$2.41$11,018.52$1.50$6,858.00$6.09$27,843.48$7.00$32,004.00$3.90$17,830.80$5.50$25,146.0041-SUBGRADE PREPARATIONSQ YD3509$3.00$10,527.00$1.90$6,667.10$1.98$6,947.82$9.00$31,581.00$5.29$18,562.61$8.00$28,072.00$1.00$3,509.00$2.50$8,772.5042-GEOTEXTILE FABRIC TYPE VSQ YD44862$1.50$67,293.00$1.40$62,806.80$1.60$71,779.20$1.50$67,293.00$2.02$90,621.24$1.42$63,704.04$0.96$43,067.52$2.00$89,724.0043-STABILIZING AGGREGATE (CV)CU YD1582$60.00$94,920.00$0.01$15.82$50.45$79,811.90$90.00$142,380.00$15.87$25,106.34$59.00$93,338.00$44.00$69,608.00$62.00$98,084.0044-SELECT GRANULAR BORROW TON27254$16.50$449,691.00$18.65$508,287.10$20.10$547,805.40$9.00$245,286.00$22.44$611,579.76$19.00$517,826.00$20.30$553,256.20$35.00$953,890.0045-CLASS 5 AGGREGATE BASETON18325$25.00$458,125.00$16.80$307,860.00$19.76$362,102.00$25.00$458,125.00$26.36$483,047.00$16.00$293,200.00$36.00$659,700.00$28.00$513,100.0046-CLASS 2 AGGREGATE SURFACING (GRAVEL DRIVEWAY/TRAIL)TON40$50.00$2,000.00$64.00$2,560.00$45.00$1,800.00$110.00$4,400.00$34.95$1,398.00$40.00$1,600.00$540.00$21,600.00$50.00$2,000.0047-BITUMINOUS WEARING COURSE (SPWEA240C)TON4378$105.00$459,690.00$90.40$395,771.20$84.50$369,941.00$92.00$402,776.00$93.98$411,444.44$86.00$376,508.00$92.10$403,213.80$87.00$380,886.0048-BITUMINOUS -NON-WEARING COURSE (SPNWB230C)TON3941$97.00$382,277.00$91.55$360,798.55$85.65$337,546.65$92.00$362,572.00$93.19$367,261.79$88.00$346,808.00$92.30$363,754.30$88.00$346,808.0049-BITUMINOUS WEARING COURSE (SPWEA340C)TON1268$110.00$139,480.00$96.15$121,918.20$90.95$115,324.60$96.00$121,728.00$100.96$128,017.28$92.00$116,656.00$94.60$119,952.80$92.00$116,656.0050-BITUMINOUS -NON-WEARING COURSE (SPNWB330C)TON1902$100.00$190,200.00$89.95$171,084.90$85.10$161,860.20$87.00$165,474.00$94.76$180,233.52$86.00$163,572.00$87.40$166,234.80$86.00$163,572.0051-BITUMINOUS MATERIAL FOR TACK COATGAL2686$3.00$8,058.00$5.20$13,967.20$4.50$12,087.00$4.00$10,744.00$3.99$10,717.14$5.00$13,430.00$3.25$8,729.50$5.00$13,430.0052-2" BITUMINOUS STREET PATCHSQ YD450$25.00$11,250.00$37.85$17,032.50$28.16$12,672.00$24.00$10,800.00$42.58$19,161.00$47.00$21,150.00$55.50$24,975.00$47.00$21,150.0053-MILL BITUMINOUS SURFACE (2")SQ YD3345$3.25$10,871.25$1.70$5,686.50$1.41$4,716.45$2.50$8,362.50$3.26$10,904.70$1.60$5,352.00$2.40$8,028.00$5.50$18,397.5054-3" BITUMINOUS DRIVEWAY/TRAILSQ YD915$35.00$32,025.00$30.15$27,587.25$24.71$22,609.65$37.00$33,855.00$56.44$51,642.60$40.00$36,600.00$29.50$26,992.50$39.00$35,685.0055-JOINT ADHESIVE (MASTIC)LIN FT22141$0.75$16,605.75$0.40$8,856.40$0.28$6,199.48$1.00$22,141.00$1.05$23,248.05$0.25$5,535.25$0.26$5,756.66$0.30$6,642.3056-MODULAR BLOCK RETAINING WALLSQ FT1375$55.00$75,625.00$56.40$77,550.00$44.05$60,568.75$60.00$82,500.00$43.05$59,193.75$41.00$56,375.00$53.30$73,287.50$55.00$75,625.0057-TIMBER RETAINING WALLSQ FT194$50.00$9,700.00$39.75$7,711.50$40.00$7,760.00$45.00$8,730.00$39.90$7,740.60$38.00$7,372.00$50.80$9,855.20$55.00$10,670.0058-6" PERF PVC UNDERDRAINLIN FT7221$17.50$126,367.50$14.65$105,787.65$24.48$176,770.08$15.00$108,315.00$28.71$207,314.91$13.00$93,873.00$20.00$144,420.00$22.00$158,862.0059-6" PERF PVC UNDERDRAIN CLEANOUTEACH62$375.00$23,250.00$363.50$22,537.00$306.00$18,972.00$550.00$34,100.00$437.29$27,111.98$220.00$13,640.00$478.00$29,636.00$375.00$23,250.0060-12" PVC STORM PIPELIN FT30$80.00$2,400.00$61.45$1,843.50$59.47$1,784.10$96.00$2,880.00$63.49$1,904.70$118.00$3,540.00$67.30$2,019.00$50.00$1,500.0061-15" C900 PVC STORM PIPELIN FT47$100.00$4,700.00$87.85$4,128.95$98.32$4,621.04$125.00$5,875.00$99.06$4,655.82$160.00$7,520.00$105.00$4,935.00$95.00$4,465.0062-15" RC STORM PIPELIN FT3783$68.00$257,244.00$62.65$237,004.95$60.39$228,455.37$75.00$283,725.00$68.86$260,497.38$77.00$291,291.00$73.00$276,159.00$62.00$234,546.0063-18" RC STORM PIPELIN FT1216$72.50$88,160.00$69.80$84,876.80$61.76$75,100.16$67.00$81,472.00$72.56$88,232.96$80.00$97,280.00$77.00$93,632.00$65.00$79,040.0064-21" RC STORM PIPELIN FT378$90.00$34,020.00$75.95$28,709.10$68.35$25,836.30$77.00$29,106.00$84.77$32,043.06$93.00$35,154.00$89.90$33,982.20$70.00$26,460.00Ryan Contracting Co.5 6 7Engineer Estimate RL Larson Excavating Inc. Northwest S.M. Hentges & Sons, Inc. Northdale Construction Co., Inc. Kuechle Underground Inc. Park Construction Company1 2 3 4Page 1 Section TitleLine ItemItem CodeItem DescriptionUofMQuantityUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionRyan Contracting Co.567Engineer Estimate RL Larson Excavating Inc. Northwest S.M. Hentges & Sons, Inc. Northdale Construction Co., Inc. Kuechle Underground Inc. Park Construction Company123465-24" RC STORM PIPELIN FT196$100.00$19,600.00$84.50$16,562.00$74.36$14,574.56$100.00$19,600.00$92.16$18,063.36$98.00$19,208.00$97.80$19,168.80$83.00$16,268.0066-27" RC STORM PIPELIN FT42$125.00$5,250.00$105.00$4,410.00$97.49$4,094.58$120.00$5,040.00$110.47$4,639.74$119.00$4,998.00$117.00$4,914.00$92.00$3,864.0067-30" RC STORM PIPELIN FT39$150.00$5,850.00$122.00$4,758.00$107.48$4,191.72$120.00$4,680.00$120.85$4,713.15$133.00$5,187.00$128.00$4,992.00$112.00$4,368.0068-36" RC STORM PIPELIN FT27$200.00$5,400.00$176.00$4,752.00$138.27$3,733.29$265.00$7,155.00$196.62$5,308.74$170.00$4,590.00$209.00$5,643.00$145.00$3,915.0069-STORM MANHOLE (48")EACH38$3,200.00$121,600.00$2,910.00$110,580.00$2,373.00$90,174.00$3,000.00$114,000.00$2,992.64$113,720.32$4,300.00$163,400.00$3,170.00$120,460.00$3,180.00$120,840.0070-STORM MANHOLE (60")EACH14$6,000.00$84,000.00$4,740.00$66,360.00$4,348.00$60,872.00$5,200.00$72,800.00$5,189.18$72,648.52$5,900.00$82,600.00$5,500.00$77,000.00$4,800.00$67,200.0071-STORM MANHOLE (72")EACH7$10,000.00$70,000.00$7,570.00$52,990.00$7,015.00$49,105.00$7,800.00$54,600.00$8,707.27$60,950.89$8,600.00$60,200.00$9,230.00$64,610.00$7,235.00$50,645.0072-STORM MANHOLE (84")EACH4$12,500.00$50,000.00$11,800.00$47,200.00$11,272.00$45,088.00$13,000.00$52,000.00$12,862.20$51,448.80$13,000.00$52,000.00$13,600.00$54,400.00$10,660.00$42,640.0073-48" DIA STORM SEWER OVERFLOW STRUCTUREEACH1$12,000.00$12,000.00$2,820.00$2,820.00$4,646.00$4,646.00$6,500.00$6,500.00$3,423.38$3,423.38$7,700.00$7,700.00$3,630.00$3,630.00$6,500.00$6,500.0074-15" RC PIPE APRONEACH2$1,800.00$3,600.00$1,060.00$2,120.00$1,075.00$2,150.00$1,400.00$2,800.00$1,346.35$2,692.70$2,200.00$4,400.00$1,430.00$2,860.00$2,550.00$5,100.0075-RANDOM RIPRAP CLASS III (LV)CU YD16$100.00$1,600.00$154.00$2,464.00$95.00$1,520.00$200.00$3,200.00$203.87$3,261.92$127.00$2,032.00$216.00$3,456.00$100.00$1,600.0076-STORM CATCH BASIN (3'X2')EACH63$2,000.00$126,000.00$1,890.00$119,070.00$1,650.00$103,950.00$2,000.00$126,000.00$2,139.62$134,796.06$1,900.00$119,700.00$2,270.00$143,010.00$2,450.00$154,350.0077-48" DIA STORM STRUCTURE SPECIAL (SAFL BAFFLE W/ 4' SUMP)EACH7$12,000.00$84,000.00$10,600.00$74,200.00$11,554.00$80,878.00$11,000.00$77,000.00$11,756.85$82,297.95$10,000.00$70,000.00$12,500.00$87,500.00$11,500.00$80,500.0078-60" DIA STORM STRUCTURE SPECIAL (SAFL BAFFLE W/ 4' SUMP)EACH1$15,000.00$15,000.00$13,600.00$13,600.00$14,526.00$14,526.00$14,000.00$14,000.00$14,781.69$14,781.69$12,000.00$12,000.00$15,700.00$15,700.00$14,500.00$14,500.0079-48" DIA STORM STURCTURE SPECIAL (SNOUT SKIMMER W/ 3' SUMP)EACH1$10,000.00$10,000.00$4,840.00$4,840.00$4,745.00$4,745.00$5,000.00$5,000.00$6,089.92$6,089.92$6,300.00$6,300.00$6,460.00$6,460.00$8,900.00$8,900.0080-CASTING ASSEMBLY (R-3067-V)(STORM)EACH86$1,000.00$86,000.00$818.00$70,348.00$692.00$59,512.00$1,000.00$86,000.00$1,144.05$98,388.30$1,000.00$86,000.00$907.00$78,002.00$980.00$84,280.0081-CASTING ASSEBMLY (R-3067-C)(STORM)EACH5$1,050.00$5,250.00$754.50$3,772.50$626.00$3,130.00$950.00$4,750.00$1,144.05$5,720.25$960.00$4,800.00$836.00$4,180.00$980.00$4,900.0082-CASTING ASSEMBLY SPECIAL (R-1733)(STORM)EACH44$1,250.00$55,000.00$624.50$27,478.00$990.00$43,560.00$800.00$35,200.00$1,216.64$53,532.16$1,600.00$70,400.00$1,150.00$50,600.00$1,050.00$46,200.0083-ADJUST FRAME & RING CASTINGS (STORM)EACH27$875.00$23,625.00$532.00$14,364.00$512.00$13,824.00$380.00$10,260.00$964.85$26,050.95$980.00$26,460.00$1,150.00$31,050.00$650.00$17,550.0084-CONNECT TO EXISTING STORM PIPEEACH42$1,750.00$73,500.00$1,400.00$58,800.00$1,000.00$42,000.00$630.00$26,460.00$1,823.39$76,582.38$2,000.00$84,000.00$1,930.00$81,060.00$2,850.00$119,700.0085-CONNECT TO EXISTING DRAINAGE STRUCTUREEACH11$2,100.00$23,100.00$1,520.00$16,720.00$1,000.00$11,000.00$6,300.00$69,300.00$2,564.17$28,205.87$4,000.00$44,000.00$2,720.00$29,920.00$3,250.00$35,750.0086-INFILTRATION BASIN EXCAVATION (EV)CU YD2148$40.00$85,920.00$27.10$58,210.80$24.31$52,217.88$23.00$49,404.00$29.80$64,010.40$22.00$47,256.00$29.70$63,795.60$26.00$55,848.0087-INFILTRATION BASIN SELECT GRANULAR BACKFILLTON2845$22.50$64,012.50$18.85$53,628.25$22.00$62,590.00$18.00$51,210.00$24.55$69,844.75$21.00$59,745.00$22.60$64,297.00$22.00$62,590.0088-PERENNIAL PLANTINGS (INFILTRATION BASIN/RAIN GARDEN)EACH1415$40.00$56,600.00$8.10$11,461.50$18.65$26,389.75$35.00$49,525.00$18.38$26,007.70$18.00$25,470.00$32.60$46,129.00$18.00$25,470.0089-8" PVC SDR 35 SANITARY SEWER PIPELIN FT6693$60.00$401,580.00$47.30$316,578.90$48.32$323,405.76$60.00$401,580.00$61.13$409,143.09$83.00$555,519.00$64.80$433,706.40$85.00$568,905.0090-10" PVC SDR 35 SANITARY SEWER PIPELIN FT1297$75.00$97,275.00$59.55$77,236.35$62.79$81,438.63$65.00$84,305.00$71.40$92,605.80$88.00$114,136.00$75.70$98,182.90$95.00$123,215.0091-12" PVC SDR 35 SANITARY SEWER PIPELIN FT639$85.00$54,315.00$60.05$38,371.95$70.27$44,902.53$85.00$54,315.00$77.86$49,752.54$94.00$60,066.00$82.60$52,781.40$100.00$63,900.0092-15" PVC SDR 26 SANITARY SEWER PIPELIN FT674$150.00$101,100.00$96.10$64,771.40$117.79$79,390.46$144.00$97,056.00$135.53$91,347.22$190.00$128,060.00$144.00$97,056.00$120.00$80,880.0093-8" DUCTILE IRON SANITARY PIPELIN FT80$85.00$6,800.00$93.10$7,448.00$86.58$6,926.40$115.00$9,200.00$92.94$7,435.20$122.00$9,760.00$98.60$7,888.00$90.00$7,200.0094-10" DUCTILE IRON SANITARY PIPELIN FT20$95.00$1,900.00$138.00$2,760.00$108.93$2,178.60$130.00$2,600.00$108.15$2,163.00$137.00$2,740.00$115.00$2,300.00$105.00$2,100.0095-12" DUCTILE IRON SANITARY PIPELIN FT20$115.00$2,300.00$138.00$2,760.00$125.60$2,512.00$145.00$2,900.00$128.32$2,566.40$170.00$3,400.00$136.00$2,720.00$125.00$2,500.0096-CONSTRUCT 8" SANITARY OUTSIDE DROPLIN FT17$1,500.00$25,500.00$610.50$10,378.50$655.00$11,135.00$1,650.00$28,050.00$529.99$9,009.83$650.00$11,050.00$562.00$9,554.00$1,250.00$21,250.0097-CONSTRUCT 10" SANITARY OUTSIDE DROPLIN FT4$2,000.00$8,000.00$818.00$3,272.00$775.00$3,100.00$2,000.00$8,000.00$839.50$3,358.00$1,100.00$4,400.00$890.00$3,560.00$1,800.00$7,200.0098-CONSTRUCT 12" SANITARY OUTSIDE DROPLIN FT4$2,500.00$10,000.00$839.00$3,356.00$875.00$3,500.00$2,200.00$8,800.00$987.57$3,950.28$1,200.00$4,800.00$1,050.00$4,200.00$2,000.00$8,000.0099-COARSE AGGREGATE BEDDING (TYPE B)LIN FT1000$10.00$10,000.00$16.80$16,800.00$6.50$6,500.00$31.00$31,000.00$14.17$14,170.00$49.00$49,000.00$20.10$20,100.00$24.00$24,000.00100-8" CIPP LINING LIN FT1947$55.00$107,085.00$37.65$73,304.55$37.80$73,596.60$40.00$77,880.00$37.80$73,596.60$45.00$87,615.00$38.60$75,154.20$37.00$72,039.00101-10" CIPP LINING LIN FT668$65.00$43,420.00$42.90$28,657.20$43.05$28,757.40$45.00$30,060.00$43.05$28,757.40$50.00$33,400.00$43.90$29,325.20$41.00$27,388.00102-12" CIPP LINING LIN FT322$75.00$24,150.00$62.75$20,205.50$63.00$20,286.00$66.00$21,252.00$63.00$20,286.00$69.00$22,218.00$64.30$20,704.60$60.00$19,320.00103-SEAL SANITARY MANHOLEEACH2$5,000.00$10,000.00$4,130.00$8,260.00$4,147.50$8,295.00$4,400.00$8,800.00$4,147.50$8,295.00$4,000.00$8,000.00$4,230.00$8,460.00$4,100.00$8,200.00104-TRIM PROTRUDING TAPEACH3$550.00$1,650.00$523.00$1,569.00$525.00$1,575.00$550.00$1,650.00$525.00$1,575.00$500.00$1,500.00$536.00$1,608.00$500.00$1,500.00105-6" PVC SDR 26 SANITARY SEWER SERVICE PIPELIN FT9700$45.00$436,500.00$26.00$252,200.00$45.25$438,925.00$35.00$339,500.00$38.18$370,346.00$46.00$446,200.00$40.50$392,850.00$48.00$465,600.00106-6" PVC SDR 26 SANITARY SEWER SERVICE RISER PIPELIN FT430$50.00$21,500.00$20.45$8,793.50$57.83$24,866.90$35.00$15,050.00$72.81$31,308.30$56.00$24,080.00$77.20$33,196.00$52.00$22,360.00107-8" X 6" SDR 26 PVC SERVICE WYEEACH197$675.00$132,975.00$690.00$135,930.00$678.67$133,697.99$285.00$56,145.00$322.91$63,613.27$1,200.00$236,400.00$342.00$67,374.00$650.00$128,050.00108-10" X 6" SDR 26 PVC SERVICE WYEEACH54$750.00$40,500.00$865.50$46,737.00$844.50$45,603.00$460.00$24,840.00$481.57$26,004.78$1,400.00$75,600.00$511.00$27,594.00$750.00$40,500.00109-12" X 6" SDR 26 PVC SERVICE WYEEACH22$850.00$18,700.00$972.00$21,384.00$952.94$20,964.68$575.00$12,650.00$585.31$12,876.82$1,500.00$33,000.00$621.00$13,662.00$850.00$18,700.00110-15" X 6" SDR 26 PVC SERVICE WYEEACH18$1,500.00$27,000.00$1,370.00$24,660.00$1,233.86$22,209.48$1,100.00$19,800.00$959.86$17,277.48$2,600.00$46,800.00$1,020.00$18,360.00$1,250.00$22,500.00111-CASTING ASSEMBLY SPECIAL (R-1733)(SANITARY)EACH40$1,400.00$56,000.00$1,040.00$41,600.00$1,240.00$49,600.00$1,000.00$40,000.00$1,391.04$55,641.60$1,600.00$64,000.00$1,250.00$50,000.00$1,050.00$42,000.00112-SANITARY MANHOLELIN FT440$550.00$242,000.00$422.00$185,680.00$475.00$209,000.00$425.00$187,000.00$446.13$196,297.20$550.00$242,000.00$473.00$208,120.00$425.00$187,000.00113-CONNECT TO EXISTING SANITARY SEWER SERVICEEACH291$450.00$130,950.00$266.50$77,551.50$507.00$147,537.00$150.00$43,650.00$201.16$58,537.56$380.00$110,580.00$213.00$61,983.00$450.00$130,950.00114-SANITARY SEWER MAIN POINT REPAIREACH2$5,000.00$10,000.00$2,090.00$4,180.00$3,270.00$6,540.00$4,000.00$8,000.00$7,202.00$14,404.00$18,000.00$36,000.00$7,640.00$15,280.00$2,850.00$5,700.00115-CONNECT TO EXISTING SANITARY SEWER PIPEEACH13$3,500.00$45,500.00$1,250.00$16,250.00$1,055.00$13,715.00$425.00$5,525.00$1,137.26$14,784.38$2,100.00$27,300.00$1,210.00$15,730.00$18,250.00$237,250.00116-CONNECT TO EXISTING SANITARY MANHOLEEACH1$4,500.00$4,500.00$2,640.00$2,640.00$1,830.00$1,830.00$1,560.00$1,560.00$2,349.54$2,349.54$3,800.00$3,800.00$2,490.00$2,490.00$3,850.00$3,850.00117-HYDRANTEACH19$7,500.00$142,500.00$8,310.00$157,890.00$6,606.00$125,514.00$7,700.00$146,300.00$6,793.57$129,077.83$7,900.00$150,100.00$7,210.00$136,990.00$8,880.00$168,720.00118-DUCTILE IRON FITTINGSPOUND3024$15.00$45,360.00$14.00$42,336.00$12.18$36,832.32$25.00$75,600.00$14.92$45,118.08$19.00$57,456.00$15.80$47,779.20$12.50$37,800.00119-6" GATE VALVE & BOXEACH20$2,750.00$55,000.00$2,270.00$45,400.00$2,278.00$45,560.00$2,800.00$56,000.00$2,401.50$48,030.00$3,100.00$62,000.00$2,890.00$57,800.00$2,850.00$57,000.00120-8" GATE VALVE & BOXEACH40$3,500.00$140,000.00$3,120.00$124,800.00$3,140.00$125,600.00$3,700.00$148,000.00$3,332.47$133,298.80$3,900.00$156,000.00$3,870.00$154,800.00$3,650.00$146,000.00121-6" DIP WATERMAINLIN FT250$80.00$20,000.00$68.15$17,037.50$69.55$17,387.50$120.00$30,000.00$81.31$20,327.50$85.00$21,250.00$86.20$21,550.00$75.00$18,750.00122-8" DIP WATERMAINLIN FT9604$85.00$816,340.00$75.45$724,621.80$78.71$755,930.84$90.00$864,360.00$95.57$917,854.28$98.00$941,192.00$101.00$970,004.00$85.00$816,340.00123-10" DR 11 DIPS HDPE/8" DR 18 DIPS FPVC HDD WATERMAINLIN FT534$150.00$80,100.00$114.00$60,876.00$92.00$49,128.00$90.00$48,060.00$82.65$44,135.10$104.00$55,536.00$87.70$46,831.80$125.00$66,750.00124-1" TYPE K COPPER SERVICE PIPELIN FT9021$50.00$451,050.00$27.70$249,881.70$46.93$423,355.53$33.00$297,693.00$41.90$377,979.90$50.00$451,050.00$44.40$400,532.40$44.50$401,434.50125-1" CURB STOP & BOXEACH276$650.00$179,400.00$454.50$125,442.00$630.54$174,029.04$540.00$149,040.00$417.50$115,230.00$620.00$171,120.00$477.00$131,652.00$485.00$133,860.00126-1" CORPORATION STOPEACH276$425.00$117,300.00$331.50$91,494.00$453.84$125,259.84$270.00$74,520.00$169.11$46,674.36$490.00$135,240.00$179.00$49,404.00$350.00$96,600.00127-2" TYPE K COPPER SERVICE PIPELIN FT5$100.00$500.00$148.00$740.00$85.16$425.80$60.00$300.00$86.25$431.25$310.00$1,550.00$91.50$457.50$100.00$500.00128-2" CURB STOP & BOXEACH1$1,200.00$1,200.00$1,130.00$1,130.00$1,202.00$1,202.00$1,000.00$1,000.00$935.73$935.73$1,400.00$1,400.00$992.00$992.00$1,000.00$1,000.00129-2" CORPORATION STOPEACH1$850.00$850.00$961.50$961.50$959.00$959.00$730.00$730.00$597.76$597.76$1,200.00$1,200.00$634.00$634.00$1,000.00$1,000.00130-INSTALL FLUSHING STATIONEACH1$5,000.00$5,000.00$1,250.00$1,250.00$385.00$385.00$4,200.00$4,200.00$1,718.75$1,718.75$3,600.00$3,600.00$2,630.00$2,630.00$1,200.00$1,200.00131-GROUNDING ANODEEACH306$150.00$45,900.00$67.50$20,655.00$87.00$26,622.00$500.00$153,000.00$121.55$37,194.30$104.00$31,824.00$129.00$39,474.00$125.00$38,250.00132-TRACER WIRE ACCESS BOX (NON ROADWAY)EACH277$150.00$41,550.00$102.50$28,392.50$68.00$18,836.00$225.00$62,325.00$156.12$43,245.24$85.00$23,545.00$166.00$45,982.00$85.00$23,545.00133-TRACER WIRE TEST STATION (HYDRANT)EACH19$175.00$3,325.00$122.00$2,318.00$72.00$1,368.00$230.00$4,370.00$160.69$3,053.11$90.00$1,710.00$170.00$3,230.00$85.00$1,615.00134-HYDRANT EXTENSIONLIN FT4$1,250.00$5,000.00$1,800.00$7,200.00$2,541.00$10,164.00$3,500.00$14,000.00$2,226.42$8,905.68$2,800.00$11,200.00$2,360.00$9,440.00$1,200.00$4,800.00135-CONNECT TO EXISTING WATER SERVICEEACH276$425.00$117,300.00$91.65$25,295.40$458.00$126,408.00$265.00$73,140.00$200.25$55,269.00$440.00$121,440.00$212.00$58,512.00$350.00$96,600.00Page 2 Section TitleLine ItemItem CodeItem DescriptionUofMQuantityUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionUnit PriceExtensionRyan Contracting Co.567Engineer Estimate RL Larson Excavating Inc. Northwest S.M. Hentges & Sons, Inc. Northdale Construction Co., Inc. Kuechle Underground Inc. Park Construction Company1234136-CONNECT TO EXISTING WATERMAINEACH11$2,750.00$30,250.00$1,250.00$13,750.00$1,000.00$11,000.00$1,200.00$13,200.00$2,209.25$24,301.75$3,800.00$41,800.00$2,340.00$25,740.00$2,500.00$27,500.00137-4" POLYSTYRENE INSULATIONSQ YD100$55.00$5,500.00$31.10$3,110.00$36.00$3,600.00$40.00$4,000.00$50.91$5,091.00$60.00$6,000.00$54.00$5,400.00$30.00$3,000.00138-FORD TYPE A-1 CURB BOX COVEREACH50$275.00$13,750.00$174.50$8,725.00$185.00$9,250.00$443.00$22,150.00$302.12$15,106.00$180.00$9,000.00$192.00$9,600.00$195.00$9,750.00139-TEMPORARY WATER SERVICEEACH276$500.00$138,000.00$483.50$133,446.00$433.42$119,623.92$1,100.00$303,600.00$528.85$145,962.60$450.00$124,200.00$561.00$154,836.00$550.00$151,800.00140-4" CONCRETE WALKSQ FT100678$8.00$805,424.00$5.90$594,000.20$6.41$645,345.98$8.00$805,424.00$6.31$635,278.18$6.08$612,122.24$5.80$583,932.40$7.50$755,085.00141-CONCRETE STEPEACH159$320.00$50,880.00$235.50$37,444.50$183.75$29,216.25$620.00$98,580.00$236.25$37,563.75$230.00$36,570.00$318.00$50,562.00$185.00$29,415.00142-CONCRETE CURB & GUTTER DESIGN B618LIN FT22556$20.00$451,120.00$19.90$448,864.40$18.38$414,579.28$23.00$518,788.00$19.95$449,992.20$19.00$428,564.00$20.50$462,398.00$23.50$530,066.00143-6" CONCRETE WALKS (PED RAMPS)SQ YD1160$150.00$174,000.00$148.50$172,260.00$136.51$158,351.60$130.00$150,800.00$163.23$189,346.80$135.00$156,600.00$134.00$155,440.00$95.00$110,200.00144-6" CONCRETE DRIVEWAYSQ YD1001$95.00$95,095.00$85.95$86,035.95$87.07$87,157.07$95.00$95,095.00$100.23$100,330.23$75.00$75,075.00$80.40$80,480.40$95.00$95,095.00145-8" CONCRETE DRIVEWAY/ALLEYSQ YD1115$115.00$128,225.00$94.75$105,646.25$115.00$128,225.00$116.00$129,340.00$113.88$126,976.20$88.00$98,120.00$87.50$97,562.50$105.00$117,075.00146-TRUNCATED DOMESSQ FT1680$72.50$121,800.00$76.35$128,268.00$52.50$88,200.00$66.00$110,880.00$77.71$130,552.80$73.00$122,640.00$53.00$89,040.00$75.00$126,000.00147-INSTALL SALVAGED PAVERSSQ FT322$15.00$4,830.00$33.45$10,770.90$33.60$10,819.20$22.00$7,084.00$33.60$10,819.20$32.00$10,304.00$33.90$10,915.80$22.00$7,084.00148-INSTALL SALVAGED FENCELIN FT15$80.00$1,200.00$131.00$1,965.00$105.00$1,575.00$55.00$825.00$131.25$1,968.75$100.00$1,500.00$131.00$1,965.00$25.00$375.00149-INSTALL SALVAGED BLOCK RETAINING WALLLIN FT100$75.00$7,500.00$50.20$5,020.00$50.40$5,040.00$16.00$1,600.00$50.40$5,040.00$48.00$4,800.00$80.70$8,070.00$50.00$5,000.00150-INSTALL SALVAGED BOULDER RETAINING WALLLIN FT100$100.00$10,000.00$50.20$5,020.00$50.40$5,040.00$76.00$7,600.00$50.40$5,040.00$48.00$4,800.00$80.70$8,070.00$50.00$5,000.00151-TRAFFIC CONTROL LUMP SUM1$75,000.00$75,000.00$57,500.00$57,500.00$36,460.00$36,460.00$61,000.00$61,000.00$57,750.00$57,750.00$55,000.00$55,000.00$63,000.00$63,000.00$50,000.00$50,000.00152-PEDESTRIAN CROSSWALK FLASHER SYSTEM (11TH AVE S)SYSTEM1$35,000.00$35,000.00$24,300.00$24,300.00$26,250.00$26,250.00$30,000.00$30,000.00$24,373.65$24,373.65$25,000.00$25,000.00$24,400.00$24,400.00$24,000.00$24,000.00153-SIGN POST U CHANNELEACH43$275.00$11,825.00$157.00$6,751.00$105.00$4,515.00$165.00$7,095.00$157.50$6,772.50$150.00$6,450.00$158.00$6,794.00$125.00$5,375.00154-SIGN POST WITH FOUNDATIONEACH67$450.00$30,150.00$314.00$21,038.00$332.00$22,244.00$330.00$22,110.00$315.00$21,105.00$300.00$20,100.00$315.00$21,105.00$755.00$50,585.00155-SIGN PANELS TYPE CSQ FT516$35.00$18,060.00$36.60$18,885.60$76.65$39,551.40$39.00$20,124.00$36.75$18,963.00$35.00$18,060.00$36.80$18,988.80$38.00$19,608.00156-SIGN PANELS TYPE DSQ FT203$45.00$9,135.00$47.05$9,551.15$42.00$8,526.00$50.00$10,150.00$47.25$9,591.75$45.00$9,135.00$47.30$9,601.90$55.00$11,165.00157-INSTALL SALVAGED SIGN PANELEACH33$100.00$3,300.00$104.50$3,448.50$78.75$2,598.75$111.00$3,663.00$105.00$3,465.00$100.00$3,300.00$105.00$3,465.00$150.00$4,950.00158-INSTALL SALVAGED FLASHING STOP SIGNSEACH2$750.00$1,500.00$366.00$732.00$1,207.50$2,415.00$387.00$774.00$367.50$735.00$350.00$700.00$368.00$736.00$350.00$700.00159-STREET SWEEPER WITH OPERATORHOUR120$175.00$21,000.00$167.50$20,100.00$175.00$21,000.00$165.00$19,800.00$168.00$20,160.00$180.00$21,600.00$179.00$21,480.00$145.00$17,400.00160-LIGHT FOUNDATION - DESIGN E MODIFIEDEACH3$1,500.00$4,500.00$1,630.00$4,890.00$2,625.00$7,875.00$2,100.00$6,300.00$1,634.85$4,904.55$1,600.00$4,800.00$1,630.00$4,890.00$1,600.00$4,800.00161-INSTALL SALVAGED LIGHT POLEEACH3$1,500.00$4,500.00$1,460.00$4,380.00$3,150.00$9,450.00$2,000.00$6,000.00$1,465.80$4,397.40$1,400.00$4,200.00$1,470.00$4,410.00$1,400.00$4,200.00162-INSTALL SALVAGED BENCHEACH1$1,000.00$1,000.00$550.00$550.00$395.00$395.00$680.00$680.00$500.00$500.00$1,500.00$1,500.00$1,580.00$1,580.00$1,500.00$1,500.00163-STABILIZED CONSTRUCTION EXITEACH6$2,000.00$12,000.00$1,570.00$9,420.00$1,800.00$10,800.00$3,500.00$21,000.00$1,586.54$9,519.24$900.00$5,400.00$0.01$0.06$1,500.00$9,000.00164-STORM DRAIN INLET PROTECTIONEACH174$200.00$34,800.00$148.00$25,752.00$100.00$17,400.00$135.00$23,490.00$126.92$22,084.08$670.00$116,580.00$212.00$36,888.00$135.00$23,490.00165-TOPSOIL BORROW (SPECIAL) (LV)CU YD1200$40.00$48,000.00$42.45$50,940.00$48.00$57,600.00$33.00$39,600.00$43.66$52,392.00$40.00$48,000.00$54.70$65,640.00$34.00$40,800.00166-FILTER TOPSOIL BORROW (ENGINEERED SOIL MIX) (LV)CU YD630$50.00$31,500.00$44.15$27,814.50$54.00$34,020.00$55.00$34,650.00$43.66$27,505.80$48.00$30,240.00$65.40$41,202.00$42.00$26,460.00167-HYDROMULCH & SEED MIX 25-131SQ YD2916$3.00$8,748.00$1.90$5,540.40$1.05$3,061.80$3.00$8,748.00$1.94$5,657.04$1.85$5,394.60$1.05$3,061.80$1.05$3,061.80168-EROSION CONTROL BLANKET & SEED MIX 33-261SQ YD950$4.00$3,800.00$2.20$2,090.00$2.30$2,185.00$3.00$2,850.00$2.21$2,099.50$2.10$1,995.00$2.35$2,232.50$2.50$2,375.00169-SODDING TYPE LAWNSQ YD26110$8.00$208,880.00$8.30$216,713.00$8.39$219,062.90$9.00$234,990.00$8.30$216,713.00$7.90$206,269.00$8.40$219,324.00$8.00$208,880.00170-SILT FENCELIN FT460$4.00$1,840.00$2.00$920.00$2.88$1,324.80$3.00$1,380.00$2.00$920.00$1.90$874.00$2.90$1,334.00$3.00$1,380.00171-BIOROLLLIN FT735$4.00$2,940.00$2.80$2,058.00$3.10$2,278.50$3.00$2,205.00$2.84$2,087.40$2.70$1,984.50$3.10$2,278.50$3.00$2,205.00172-HARDWOOD MULCH (4" THICK)SQ YD50$20.00$1,000.00$31.35$1,567.50$68.55$3,427.50$33.00$1,650.00$68.25$3,412.50$65.00$3,250.00$52.50$2,625.00$65.00$3,250.00173-STONE BLOCKSEACH8$1,250.00$10,000.00$418.50$3,348.00$425.00$3,400.00$1,000.00$8,000.00$420.00$3,360.00$400.00$3,200.00$424.00$3,392.00$850.00$6,800.00174-INSTALL SALVAGED RAILINGLIN FT20$150.00$3,000.00$75.00$1,500.00$132.40$2,648.00$135.00$2,700.00$342.30$6,846.00$300.00$6,000.00$158.00$3,160.00$20.00$400.00175-FABRICATED RAILINGLIN FT26$325.00$8,450.00$341.00$8,866.00$218.50$5,681.00$350.00$9,100.00$342.30$8,899.80$350.00$9,100.00$342.00$8,892.00$200.00$5,200.00176-CROSSWALK SPECIAL - STAMPED BITUMINOUSSQ FT269$69.00$18,561.00$62.75$16,879.75$63.10$16,973.90$67.00$18,023.00$63.00$16,947.00$60.00$16,140.00$63.00$16,947.00$60.00$16,140.00177-4" BROKEN YELLOW - MULTI COMPONENT LIQUIDLIN FT2658$1.50$3,987.00$0.40$1,063.20$0.42$1,116.36$0.50$1,329.00$0.42$1,116.36$0.40$1,063.20$0.43$1,142.94$0.40$1,063.20178-4" DOUBLE YELLOW - MULTI COMPONENT LIQUIDLIN FT183$2.00$366.00$2.50$457.50$2.52$461.16$3.00$549.00$2.52$461.16$2.40$439.20$2.55$466.65$2.40$439.20179-4" SOLID WHITE - MULTI COMPONENT LIQUIDLIN FT67$1.00$67.00$1.30$87.10$1.26$84.42$1.50$100.50$1.26$84.42$1.20$80.40$1.30$87.10$1.20$80.40180-24" SOLID WHITE STOP BAR - THERMOPLASTIC (GR IN)LIN FT151$27.50$4,152.50$18.85$2,846.35$18.90$2,853.90$20.00$3,020.00$18.90$2,853.90$18.00$2,718.00$19.20$2,899.20$18.00$2,718.00181-PAVEMENT MESSAGES - THERMOPLASTIC (GR IN)EACH2$500.00$1,000.00$418.50$837.00$420.00$840.00$450.00$900.00$420.00$840.00$400.00$800.00$426.00$852.00$400.00$800.00182-CROSSWALK WHITE - THERMOPLASTIC (GR IN)SQ FT3252$13.50$43,902.00$11.50$37,398.00$11.55$37,560.60$13.00$42,276.00$11.55$37,560.60$11.00$35,772.00$11.70$38,048.40$11.00$35,772.00183-CROSSWALK GREEN - THERMOPLASTIC (GR IN)SQ FT144$30.00$4,320.00$11.50$1,656.00$11.55$1,663.20$13.00$1,872.00$11.55$1,663.20$11.00$1,584.00$11.70$1,684.80$11.00$1,584.00184-LANDSCAPE ALLOWANCELUMP SUM1$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00$100,000.00BASE BID TOTAL:$14,180,294.50$11,479,980.92$11,948,755.84$12,776,964.00$12,863,923.70$13,088,414.91$13,696,286.98$15,040,700.40Page 3