CR 99-83 Approve Engineering Agreement - Lake Street Bridge
'\ y 0
\
(; /;'
~
'" '"
. April 28, 1999 o P K \ ~ Council Report 99-083
Approve Engineering Services Agreement
Lake Street Bridge Replacement
Proposed Action.
Staff recommends adoption of the following motion: Move that Council authorize
the City Manaoer to enter into an aqreement with SRF Consultinq Grouo. Inc. for
enoineerino services related to reolacement of the Lake Street bridqe.
Overview.
This local bridge is a deteriorated, 94 year old structure. City Council passed a
resolution in May, 1997 committing to replacement provided State funds were
available. Since that time State funds have been committed to this project. The
construction cost of the new bridge wi II be 100% funded with State
Transportation Bond funds. The city must fund engineering and bridge
demolition costs. Staff would now like to begin engineering work in order to
complete design by December, 1999.
Primary Issues to Consider.
. What is the estimated project cost? City cost?
. The estimated construction cost of the new bridge is $300,000 - $350,000. The
estimated city cost, the cost of engineering services and bridge demolition, is
$120,000.
. Project schedule
Complete design: November, 1999
Award project: February, 2000
Construction: May - July/August I 2000
. Engineer Selection Process and SRF engineering fees
Engineering proposals were solicited from four firms. We received two
proposals from two fully qualified engineering firms: SEH-RCM and SRF
Consulting Group, Inc. Staff selected SRF based on their qualifications,
understanding of city needs and lowest overall cost. SRF's fees total $84,500,
including an estimated $35,000 for construction services, SEH-RCM's fees were
substantially higher.
Suoportino Information
. SRF proposal
. .~ proi\ect Sheet
\" --\"\~
. Steven J. Stadler, Public Works Director
. APR-22-99 THU 01: 17 PM SRF CONSULTING GROUP INC FAX NO, 612+475+2429 P. 02
. CONSULTING GROUP, I N c.
TranspartilHon · Civil- Structur<lj- Environmenfal. Planning - Traffic - Landscape Architecture. PJrking
April 22, 1999
Mr. Steven J. Stadler, P.E.
Public Work:; Director I City Engineer
CITY Of HOPKINS
11100 Excelsior Boulevard
Hopkins, Minnesota 55343
Dear Mr. Stadler:
SUBJECT: SCOPE OF SERVlCES LAKE STREET BRlOOE
OVER TIIE Ml.NNF.HAl.IA CREEK
Per your request, we are following up with some clarification and additional information on our
Lake Street Bridge Proposal. We have ouLlined below our proposed Scope of Services in more
detail and identified our "Basic Services" and "Additional Services" which may be required
depending of the requests of the City or the regulatory agencies. Basic services are those
services included in our proposal based on the assumption stated herein. Additional services are
. services that may be required by changes to the site or desires by the City not known at the time
of the proposal.
BASIC SERVJCli:S
TASK 1 llydraulic Analysis
. Use existing Watershed HEC - 2 computer tiJes to model the proposed bridge
opening.
· Prepare Hydraulic Letter and Risk Assessment.
Basic Fcc: $ 2,000
TASK 2 Bridge Type Study
· Develop and evaluate up to three possible structure types (prepare concept
level drawings).
· Prepare basic aesthetic (reatment options.
· Develop three phOlo renderings.
· Prepare bridge type study with estimated costs,
Basic Fce: $2,500
.
One CCH]son Parkway North, Suite 150, Minneapolis, MN 55447-4443
Telephone (612) 475-0010 . fax (612) 475-2429 . http:/ /www.srfcol1$ulting.com
-....,...,..- --. -.. - -.. .-.-"-
All Equal Opportunity Employer
APB-22-88 THU 01:17 PM SRF CONSULTING GROUP INC F AX NO. 612+475+2429 P. 03
}"'fr. Steven J. Stadler, P.E. -2- April 22, 1999
. TASK 3 UI"idge Survey
. Survey bridge site and develop base map (survey work docs not include any
right-of-way work).
Basic Fee: $6,500
TASK 4 Bridge Design
. This work will include all necessary design and plan preparation [or any bridge
option that would be selected.
Basic Fee: $23,000
TASK 5 Related Utility Improvement Design
. Design and prepare construction plans for replacement of watermain and
sanitary at bridge site only.
Basic Fee: $5,000
TASK 6 Co rlstrnction Services
This fee is very difficult to estimate. Typically the in-construction services would
. be about 8 to 10% of the construction cost. We would anticipate that the
constl1lction cost would be approximately $300,000 to $350,000. Therefore, we
would estimate this fee would be between $24,000 and $35,000. Our proposal
estimated this task at $25,000.
We would recommended that this fee be on an hourly basis for work performed,
plus ollt-of~pocket expenses. If however the City requires a lump sum, not to
exceed cost, we would request that this fee should be revised to $35,000, since we
are unable at this time to accurately estimate the constmction cost. This fee docs
not include any material testing that would be required by a testing company.
TASK 7 Geotechnical Evaluation
· This work will be completed by STS and consist of one boring to 70 feet. STS
will prepare a Foundation Recommendation based on the results of the boring.
We have cncJoscd a copy of their proposal for your reference,
Basic Fee: $2,500
TASK 8 UNR And Watershed District Permit Applications
· Prepare DNR and Watershed District Permits. This is assumed that the
proposed bridge has aboul the same opening and no impacts upstream or
downstream,
e Basic Fee: $2,000
APR-22-99 THU 01:18 PM SRF CONSULTING GROUP INC FAX NO, 612+475+2429 P. 04
Mr. Steven J. Stadler, P,E. -3- April 22, 1999
. OPTIONAL SERVICES
TASK 8 DNR And \Vatershed District Permits
· If a structure is selected that alters the hydraulic conditions upstream or
downstream, additional work would be required to prepare the permits.
Estimated Fee: $3,000
Task 2 Bridge Type Study
· Prepare Architectural Concepts by our Landscape Architect.
Estimated Fee: $3,000
TASK 9 Public Involvement
· This work would involve preparation and attending public or neighborhood
meetings as required.
Estimated Fee; $2,000
TASK 10 Contract Documents
· The basic selvices included preparation of technical Specific Provisions with
. the assumption that the City would prepare general conditions and contract
documents, The additional services wilt include preparation of specifications,
advertising for bids and opening bids.
Estimated Fcc: $4,000
The revis.ed fee for each task is summarized below:
BASIC OPTIONAL
SERVICE SERVICE
Task I Hydraulic Analysis $ 2,000
Tao;;k 2 Bridge Type Study $ 2,500 $ 3 1000
Task 3 Bridge Survey $ 6,500
Task 4 Bridge Design $23,000
Task 5 Utility Design $ 5,000
Task 6 Construction Services $35,000*
Task 7 Geotechnical $ 2,500
Task 8 Pcmlits $ 2,000 $ 3,000
Task 9 Public Tnvolvement $ 2,000
Task 10 Specifications $ 4,000
TOTAL $78,500 .$12,000
e * Rcvised from our original proposal
APR-22-99 THU 01:18 PM SRF CONSULTING GROUP lNC FAX NO. 812+475+2429 P. 05
Mr. Steven J. Stadler, r.E. - 4- April 22, 1999
. We have enclosed some sample copies of a bridge type study, photo renderings and bridge plans
for your reference.
Our office Jlas performed a significant amount of bridge work for Cities, Counties and the State
and is familiar with all the requirements ofthe Mn/DOT Bridge State Aid Office. Jfyou wish to
call for a reference from the MnlDOT Bridge Office, Bob Miller is the Bridge Consultants I
Engineer, and his number is (651) 582-1104. I
Ifyotl have any questions or need additional information pleas'e call.
Sincerely,
SRF CONSllLT1NG GROUP, INC.
Sb' '1 . C;~
Larry A. Erickson, P.E.
Principal
LAE/sr
. Enclosures
.
...;
...;
-
-
-,ioij
j
,-
-
-....
-
.....
-
-
=-
';:
.I
=-
-
~
-
I
I
~
I
.e
)
-- -
~4
-
~ NOTTINGHAM PARKWAY BRIDGE
- OVER ELM CREEK
~~. MAPLE GROVE, MINNESOTA
-~
The City of Maple Grove retained
"- SRF for roadway engineering and
bridge design services, including
~ hydraulic analysis in association
with a proposed single-span
-- bridge at the Elm Creek crossing.
SRF's services included:
~ . Hydraulic analysis and
recommendations for the
- proposed single-span bridge
over the creek. A minor creek .... . -..w...,." _ c-., .
'~~~~~"_;.;o............
realignment was proposed to
- provide smooth hydraulic
transitions during larger
- storm events. A blend of
vegetative and rip rap was
- used for bank stabilization.
- . The Army Corps of Engineers
..... HEC-2 program was used to
-. analyze fill impacts to the
existing floodway. Models
were revised and a letter of
- mapping revisions was . The bridge is a 58-foot single
-
submitted to FEMA. span prestressed concrete
- beam bridge with a cast-in-
. Aesthetic studies were place concrete deck. The
- performed by SRF's landscape roadway is on a horizontal
~ architects to develop a curve requiring special
structure that enhanced the attention to geometries.
- rural creek setting. Stone
form liner treatments were SRF also provided construction
I selected with a decorative inspection services for the
ornamental railing. project.
I Year: 1997
Cost: $310,000
Client: City of Maple Grove
I-
I
I~ ~ CONSULTING
GROUP, I N c.
I
DAKOTA COUNTY CSAH 50
RECONSTRUCTION
. LAKEVILLE AND FARMINGTON,. MINNESOTA
~
-
-
.
~
- ,~
- SRF computer rendering of CSAH 50,
....
-. Through a turnback agreement including municipal utilities, · Final design and
- with the Minnesota Department signals, trails and landscaping. construction documents
- of Transportation, Dakota · Wetland permi t faciIi ta tion
- County received jurisdiction SRF Consulting Group, Inc.
- over CSAH 50 (old TH 50). The provided complete engineering · Wetland mi tiga bon design
four-mile segment connecting services for the project, including: · Hydraulic analysis
- the cities of Lakeville and
Farmington needed upgrading · Design surveys · Multiple box culvert design
-
to adequately serve as a major · Preliminary design · Bridge design
- cross-co un try rou te.
· Feasibility study · Section 4(f) coordination
- The roadway is a four-lane · Environmental Assessment
- urban and suburban design, Worksheet
-
~
~
Year: 1996
- Cost: $8 million
Client: Dakota Connty
--
- ~ CONSULTING
GROUP, I N c.
CSAH 33 OVER THE
REDWOOD RIVER
LYON COUNTY, MINNESOTA
~
-
.~
-
.
- "!!!
-
-
~
-
~
-
-
~ _CSAH 33 over the Redwood River,
--::>lZF Consulting Group, Ine was '-'. -~~~'~.~_~~~::'~~~";::'~:::~7t~:~~-:::.....,~:~~~ ~~_~~o:':'~: ,....,-"'r'~-N:.'~_.,'_ ~-_ . - ."-""-" '._, - _'_,",.
.. '
retained by Lyon County to
IIiiiiI complete preliminary and final
.
- design and plan preparation for
- several short span bridges over
rivers and creeks throughout
- Lyon County. These structures
~ replaced functionally obsolete
bridges on the county and
- township road system. Bridge
types ranged from one- to three-
span struchlres of prestressed
- concrete, cast-in-place concrete
- or rolled steel beam_ All bridges
- are supported by pile bent abut-
ments and pile bent piers. CSAH 33 over the Redwood River
..
. Year: 1982
Client: Lyon County
Highway Department
~.
.- ~CONSULTING
- GROUP, I N c.
...~
-----
-
-- 34TH AVENUE BRIDGE OVER
... MINNEHAHA CREEK
- MINNEAPOLIS, MINNESOTA
-.
-
Iii
..:=:;
--
~
-
-
-
-
-
.
"'iii The 34th Avenue Bridge over
- Minnehaha Creek replaced a
- struchlrally and functionally
""9P obsolete structure adjacent to
the intersection of 34th Avenue
--- South and Minnehaha Parkway.
-
- The location of the in-place
- bridge resulted in an undesirable
- intersection geometry. To
enhance the intersection as well
.- as the trail system along
Minnehaha Creek, the creek
- was realigned to the north and
the new bridge designed to
- span the pedestrian/bike trail
-- and Elm Creek.
- To enhance the quality of the
- sensitive park setting for the
bridge, a shallow, single span Cost: $450,000
..:;::0;. cast-in-place post-tensioned Completion Date: 1975
- concrete box girder structure Client: City of Minneapolis
-
121 feet in length was selected.
An ornamental metal railing,
- stone veneer and breakaway
-- surface treatment were used to
further complement the bridge
~ and its unique site_ ~ C-~ONSULTING
-
GROUP, I N C.
-
.
-
.oil
-
- THE OLSON MEMORIAL HIGHWAY
- PEDESTRIAN BRIDGE
=. MINNEAPOLIS, MINNESOTA
-
~
-
~
~
~
"-'
-
-
~
-
--
.-
-=
-
~
~
-
-
-
-
- SRF Consulting Group, Ine.
prepared this winning entry for
- a pedestrian bridge competition
~ sponsored by the City of Cost: Estimated cost is $975,000
Minneapolis and Glenwood/ Completion Date: 1996
- Lyndale Community Groups.
Clients: City of Minneapolis
- The design competition called GJenwood/Lyndale Community
for a secure and easy-ta-use G rou ps
- neighborhood pedestrian cross-
- ing. Aesthetics were empha-
sized with a "neighborhood"
- compatibility design theme.
- Gently rising, generously wide Detail of bridge deck with roof and railing
ramps approach a colored steel- treatments
- canopied bridge-crossing which
..... accommodates pedestrians
~ and bicyclists. ~ CONSULTING
- GROUP, I N c.
-
-,