Memo Dome Issues/Tait's RenovationPS03066A
CITY OF HOPKINS
MEMORANDUM
DATE: March 6, 1996
TO: The Honorable Mayor and City Council
FROM: Paul T. Steinman, Community Development Specialist
SUBJECT: Dome Issues and Tait's Renovation Project
I. PURPOSE OF MEMO
The purpose of this memo is to provide information on
various issues regarding either retaining or demolishing the
dome structure on the north side of the Boston Garden
restaurant, and also to discuss the timing issue of the
Tait's SuperValu renovation project.
II. OVERVIEW
A discussion of issues regarding retaining or demolishing
the dome has already occurred at a previous Council meeting.
At this meeting it was apparent that a decision on this
matter is linked to the timing of the Tait's SuperValu
renovation project. It was, therefore, determined that it
would be beneficial to discuss these two projects at the
same time.
Related specifically to the dome and Tait's project is a
redevelopment agreement executed between the HRA and T & H.
Markets, Inc. (Mike Tait). This redevelopment agreement
outlines the following primary issues to consider in this
discussion:
• A minimum of 20 parking spaces is to be provided on the
dome lot, and a document is to be recorded against such
property to retain these spaces for use by the general
public for parking
• Within 90 days of September 1, 1995, the parking lot was
to be fully constructed by the City
• By March 1, 1996, Mike Tait was required to begin the
renovation project
• A penalty of $100,000 was to be applied to T & H Markets
in the event of a default on the agreement
Memo to Mayor and City Council, March 6, 1996 - Page 2
III. PRIMARY ISSDES TO CONSIDER
o What are the costs involved in dome demolition at this
time?
PS03066
Staff estimates the following costs for demolition of the
dome structure and construction of the parking lot:
• Approx. $10,000- $12,000 - Dome demolition
• Approx. $40,000
• Approx. $40,000 -
• Approx. $60,000 - $65,000 -
- Parking lot construction
If the dome structure is retained, staff estimates the
following costs:
Parking lot construction
Provide a westerly face on
the dome roof
- Lighting
- Paint interior roof
- Structural steel bracing
- Other costs associated with
upgrading the aesthetic
appearance of the dome
The estimated annual operating costs associated with
retaining the dome are approximately $3,500 to $7,000 per
year. Other costs associated with retaining the dome
include roof replacement in approximately five years at a
cost of $25,000 to $50,000 and painting the interior each
five to seven years at a cost of approximately $10,000 to
$12,000 each time.
To date, the City has spent approximately $15,000 to retain
the dome in its current condition.
o What has been received from the Dome Committee?
The Dome Committee, consisting of Ed Hanlon, Bob Miller,
and Mike Tait, submitted a summary of their meetings
regarding this issue. All three of the Committee members
were, however, unable to reach a consensus on whether to
retain the dome roof. Attached to this memo is a letter
from this committee dated January 30, 1996.
o What is the timing for completion of improvements to Tait's
SuperValu?
Mike Tait has informed staff that he has submitted a
request to First Bank for financing in the amount of
approximately $1.1 million. In addition to the $1.1
million bank financing, Mr. Tait estimates he will be
Memo to Mayor and City Council, March 6, 1996 - Page 3
providing equity in the amount of approximately $400,000
and, together with the City's $200,000 Commercial Rehab
Loan, the total project will be approximately $1.7 million.
Mr. Tait has indicated that in the event First Bank does
not approve such financing, he anticipates bringing the
identical package to Citizen's Independent Bank for review.
If this financing is unsuccessful, Mr. Tait is then
proposing to reduce the dollar amount of his project to
approximately $1 million. Mr. Tait anticipates being
under construction as soon as he is able to obtain a
financial commitment from a banking institution.
One of the major delays with regard to timing of this
project has been negotiations with the current building
owner, Don Hagen, to have him agree to allow a mortgage to
be placed on the property to secure the bank financing.
Mr. Tait has informed staff that Mr. Hagen has only
recently agreed to allow a portion of the bank financing to
be secured through a mortgage lien on the property. It is
staff's understanding that the bank is currently reviewing
this proposal.
The City's Commercial Rehab Loan would likely be secured by
new equipment that Mr. Tait will be purchasing for his
renovation. Mr. Tait has indicated that the term of the
City's $200,000 loan would be five years.
IV CONCLUSION
In conclusion, it is staff's feeling that the Tait
renovation project will be proceeding regardless of the
situation with the dome. Mr. Tait has indicated he has
already spent a substantial amount of money (approximately
$100,000) to begin purchasing, installing, and training
employees on new equipment.
Staff strongly encourages that a decision be made on whether
or not to retain the dome as soon as possible.
Staff foresees the following two scenarios taking a
substantial amount of time to complete with regard to this
issue:
PS03066A
(1) Demolish Dome
Secure bids for dome demolition
• Redesign and bid parking lot construction immediately
after dome demolition
• Begin improvements to the exterior wall of the Boston
Garden building and outdoorsman
Memo to Mayor and City Council, March 6, 1996 - Page 4
P603066A
(2) Retain Dome
• Secure architectural bids for upgrading the aesthetic
appearance of the dome structure
• Have Council undertake a process to agree on concept and
design, and proceed with getting bids and completing
such improvements
• Redesign and bid parking lot construction with the dome
structure in place
• Begin completing improvements to the exterior wall of
the Boston Garden building and Outdoorsman
Staff foresees each of these two scenarios taking a fairly
substantial amount of time to complete -- likely a minimum
three to five months. With this time frame in mind, if a
decision were made in March, the soonest the project, under
either scenario, would be substantially completed would be
late June or late August.
Attachment
IP
City of Hopkins
c/o Paul Steinman
1010 First Street South
Hopkins, Mn.55343
cc Honorable Mayor and City Council
January 30, 1996
From: Dome Issues Committee: Ed Hanlon, Bob Miller, Mike Tait
(933.00300) (938.8440) ( 938.6301)
Our committee held several meetings to discuss the issues relative to retaining the curved roof
structure over the new lot #500 addition. We agreed with the Position statement of the HBCA
Board of Directors in terms of its purpose.
It is the consensus of the committee that the Dome should remain with the following conditions;
A. Visibility; That the structure does not impede the visibility of Taits from the corner of
l Ith and Mainstreet. This has been accomplished by removing the first bay, and
should be kept in mind when adding any additional pillar support that may be
needed.
B. Appearance; The overall appearance of the structure should be enhanced by using
paints, lights, skylights and hardware that compliment the new Mainstreet scape and
that which would show off as much of the steel support structure as possible. Wall
murals of a "Market Place" nature would be very desirable. (i.e. St Lawrence Market
in Toranto)
C. Design; That the lot's marked spaces and traffic flow design should be oriented to the
spaces and traffic flow of the portion of the lot nearest to Taits. It is important that the
Taits' customer perceives the new section of parking as added parking for the
grocery store. A "one -way" version of the original design as pictured in the Sun Sailor
was our first choice. ( see attachment )
D: Enhanced Parking: "Hopkins 11th Ave Pavilion" or "Hopkins Marketplace Pavilion"
are a couple of building names that we liked. The names are submitted so as to
convey a sense o€ purpose for keeping the structure. The priority is to provide
enhanced additional parking for the retail customers in the area. This is a secondary
benefit to the businesses in the area, and a primary benefit to the downtown customer.
E. Market Place; The pavilion's second purpose would be to provide very limited use for
quality events that would help to build the Hopkins' Marketplace atmosphere. i.e. the
Farmers Market which currently operates in the open and potentially rainy conditions
of the Downtown park and an occasional Art fair use that would compliment a festival
event.
F. Use and Restrictions
Use of the structure for an event purpose should be treated as any other special event
which would require the use of a parking lot or street. i.e. A special use permit would
be applied for by a qualifying organization; We suggest that the following rules and
guidelines be accepted and used for such a purpose;
Farmers Market; Encourage its use so as to promote and facilitate a Home Grown
Minnesota farm goods market. Grocery stores licensed in Hopkins may also vend
from the pavilion during scheduled "Market" times. tts use should be limited to take up
no more than 1/3 of the spaces for parking (8) and no more than 1 day per week
(Sunday is preferred by Taits, but Saturday is ok) and no more than 4 hours
at a time (8am -noon currently)
Art Fairs; As a cultural enhancement to the area Art fairs in conjunction with a city
festival ( i.e. Mainstreet Days, Raspberry Fest. etc.) would be encouraged. Limit to
one fair per year lasting no longer than one weekend ( Sat/ Sun). Input and
guidance from the HAAA may help to ensure that the Art fairs are in fact art. It
would not be in the interest or spirit of intentions to use the pavilion for other
markets such as; Flea Markets, Auto Shows, Antique Sales etc.
Rained Out Events; Hopkins business and civic organization events that plan to use
the pavilion due to weather conditions could do so provided that request are
submitted at least 30 days prior to the need and that the final decision to relocate
the event is made 3 hours prior. i.e. Music in the park, Rasp. Fashion Show, Talent
contest.
Prohibited Use. Events that would not be appropriate for its use would be events that;
1. Are too big in scope that would aggravate parking needs of the local businesses,
2. Events that may disturb the peace of the nearby residential community.
3. Events that are longer than 2 days in length i.e. Christmas tree sale.
4. Events that take place during key grocery sell weeks. ( see Taits 10.20.96 letter)
G. Roof Drainage; We defer this issue to the experts in public works.
(see Norb Kerber 10/19/95 letter)
H. Financing Ongoing Maintenance; This is the only area that we could not reach a
consensus. We agreed that there are many options that could be explored. i.e. General
tax fund, Special assessments, Rental revenues, or private ownership. Mike Tait does
not feel it should be an expense for the general fund. Bob Miller and I feel that there is
both purpose and president to support the argument for funding the maintenance from
the general fund. Private ownership is also a viable possibility. We were not able to
bring this discussion to a conclusion due to the urgency of reporting our overall
recommendations.
In conclusion we feel that by taking it down it be would a lost opportunity for ever, however if
lip keeping it where to prove to be `, - gretful decision the risk would be minimal to raise it several
years from now.