CR 96-75 Engineering Services - Meadowbrook Storm Sewer1
April 11, 1996
Proposed Action.
Overview.
Primary Issues to Consider.
• Description of proposed project
• Costs
• Project Schedule
• Staff recommendation
Supporting Information.
• Analysis of Issues
• RCM letter proposal
• Preliminary Engineering Report
Steven J. Stadler, Director of Public Works
Council Report 96 -75
AUTHORIZE ENGINEERING SERVICES
MEADOWBROOK STORM SEWER, PROJECT #95 -15
Staff recommends the following motion: Move that Council authorize the Mayor and
City Manager to enter into an agreement for professional services related to the
Meadowbrook/Interlachen Park storm sewer project.
At the January 16, 1996 meeting, City Council authorized RCM, Inc. to prepare a
study of the stormwater issues relating to a Meadowbrook storm sewer improvement
project. RCM has prepared the report and it is attached to this Council Report. The
report contains pertinent information, including constraints impacting our project, from
the City of Edina, Meadowbrook Golf Course, Minnehaha Creek Watershed District
and Interlachen Country Club. Despite the constraints, a viable improvement project is
possible. Further, the project is best completed in a single phase, not a three -phase
• approach as described in the OP.
Staff held a public information meeting on this proposed project at 7:00 p.m. on April
9 ' only two residents attended. However, staff had the opportunity to explain the
project and answer questions due to several telephone inquiries received prior to the
meeting .
Council Report #96 -75
Page 2
Analysis of Issues
• Description of proposed project
The project would improve storm drainage in the southeastern Interlachen
neighborhood by installing a new 15 inch storm sewer pipe to replace an existing
deficient 12 inch pipe which runs into the Meadowbrook Golf Course system. The
proposed alignment of the new pipe would be from an existing manhole near the
Interlachen Park shelter building, south onto Interlachen Golf Course, then east
connecting to a City of Edina storm sewer manhole just north of Annaway Drive.
Lateral pipes would be extended to connect to the existing storm sewer at the south
end of Hawthorne Road and Meadowbrook Road. This pipe alignment costs less and
would be much less disruptive to trees and fences in the area. The alignment would
require an easement from Interlachen Golf Course.
Due to Minnehaha Creek Watershed District constraints, we cannot tie into the City of
Edina system with a pipe any larger than 15 inches. Therefore, while the project will
• provide a noticeable improvement for the area, the improvement is less than it could be
without the 15 inch pipe restriction. In order to increase capacity, our design would
have to include a stormwater detention pond in Interlachen Park. Fortunately, this is
not necessary to achieve an acceptable improvement for this drainage area.
. Costs
RCM, Inc. has proposed an engineering services fee of $20,900. This is a reasonable
fee considering there will be considerable effort needed to coordinate approvals from
the various agencies, process easements, and obtain permits.
The preliminary estimated construction cost is $108,000. The CIP budget was set for
a 3 -year (1996 - 1998), 3 -phase project estimated at $50,000 each year.
•
City Council Report 96 -75
Page 3
• Project Schedule
May 31 Complete survey, obtain alignment approvals
Jun 21 Design completion, obtain permits
Jul 2 Approve design, order bids
Aug 6 Award contract
Sept -Oct Construction
Note: The project schedule could change to allow bidding later in the year if staff
determines this would result in a more favorable bid climate.
• Staff Recommendation
Staff recommends approval of the engineering services agreement with RCM, Inc and
approval of the design as described above.
car
muller
*associates, inc.
ears
architects
land suNeyors
equal opportunity
employer
10901 red circle drive
box 130
minnetonka, minnesota
(612) 935 - 6901
fax (612) 935 - 5814
April 11, 1996
Mr. Steven Stadler
Public Works Director
City of Hopkins
1010 First Street South
Hopkins, MN 55343
RE: Engineering Services Proposal
Meadowbrook Area Storm Sewer
RCM File No. 10350.00
Dear Mr. Stadler:
RCM is pleased to provide this engineering services proposal for design and
construction phase services related to the Meadowbrook/Interlachen Park storm sewer
upgrade.
The proposed project will involve replacement of an existing storm sewer which drains
through Meadowbrook Golf Course. The project will extend from the existing City of
Edina storm sewer in Meadowbrook Golf Course, and will extend west to Homedale
Road. The alignment will be generally through Intertachen Golf Course, as described
in our report dated March 6, 1996. This proposal is based on the assumption that the
project will not include pond construction.
Engineering services for the Meadowbrook Storm Sewer project will be provided in
three phases as described below.
Meetings. Coordination. Easements and Permits Phase
RCM (accompanied by City staft) will meet with the City of Edina, City of Minneapolis
Park Department, managers of the Meadowbrook and Interlachen Golf Courses,
Minnehaha Creek Watershed District, and affected property owners. These meetings
will resolve design issues such as alignment, scheduling, coordination with golf course
operations, easement needs, restoration, and permit requirements.
Also as part of this phase, RCM will prepare and submit permit applications, and will
prepare legal descriptions for permanent easements for the new storm sewer.
Final Design and Bidding Phases
RCM will perform design surveys and prepare drawings, specifications, and contract
documents for the proposed project. Our proposal is based on the entire project from
Meadowbrook Golf Course to Homedale Road being constructed under a single
contract. Following acceptance of the drawings and specifications, RCM will assist the
City with advertising and receiving bids for the project.
55343 -0130
Mr. Steven Stadler
April 11, 1996
Page 2
Construction Phase
RCM will provide construction phase services as requested by the City. We understand
the City will assign one of its own personnel as on -site Resident Project Representative.
RCM's services will include:
• Attending preconstruction conference
• Shop drawing review
• Review of contractor pay estimates and change orders
• Answering questions related to the design
• Periodic she visits (up to 30 hours) to observe construction and assist City's
Resident Project Representative
• Record drawings
Schedule
RCM ASSOCIATES
RCM will commence work on meetings and coordination as soon as authorization is
received from the City. Completion of this work is dependent on factors beyond our
control. For scheduling purposes, we have assumed that design issues such as
alignment, restoration, and easement needs will be resolved within 30 days after
authorization to proceed. Once these issues are resolved, the City will authorize RCM
to proceed with final design.
Final design will commence after the alignment is defined and the City authorizes work
to begin on final design. Drawings, specifications, and legal descriptions for easements
will be submitted to the City for review within 60 days after our receipt of City's
authorization to proceed with final design.
Construction phase services will be provided in accordance with the Contractor's
schedule. Our proposal is based on the assumption that storm sewer construction will
be completed in the fall of 1996.
Compensation
For meetings, coordination, easements, and permits, RCM will be compensated on an
hourly basis at our actual hourly rates plus overhead and profit, plus actual cost of
reimbursable expenses. RCM's billings to the City for these tasks will not exceed $5,000
without prior written authorization from the City.
For final design and bidding assistance, the City will pay RCM a lump sum of $10,900.
For construction phase engineering services, RCM will be compensated on an hourly
basis at actual hourly rates plus overhead and profit, plus reimbursable expenses at
Mr. Steven Stadler
April 11,1996
Page 3
actual cost. RCM's billings to the City for construction phase services will not exceed
$5,000 without prior written authorization from the City.
We appreciate this opportunity to serve you. If you would like us to proceed, kindly
sign the bottom portion of both original copies of this proposal, and return one copy to
us. Kcep the other one for your files. The signed proposal would serve as the
agreement between the City and RCM,
Sincerely,
RIEKE CARROLL MULLER ASSOCIATES, INC.
t aagt -
Dale A. Folen, P.E.
Assistant Manager, Water Resources
Accepted by:
Rieke Carroll Muller Associates, Inc.
094
te-V,
RCM ASSOCIATES
Sam L. Claassen,P.E.
President/CEO Mayor
�iarYy Koutsoumbos, P -E-
Vice President
Paul W. Blum, P.E.
Manager, Municipal Engineering
City of Hopkins, Minnesota
Charles Redepenning
Steve Mielke
City Manager
Dated: April 11. 1996 Dated:
tm
rieke
carroll
moiler
associates, inc.
meers
itects
nd surveyors
equal opportunity
employer
1 red cirele drive
'15bx 130
minnetonka, Minnesota
(612) 935 -6901
fax (612) 935 -8814 /
55343 -0130
March 6, 1996
Mr. Steven Stadler
Public Works Director
City of Hopkins -
1010 First Street South "
Hopkins, MN 55343
RE: Preliminary Engineering Report
Meadowbrook / Interlachen Park Storm Sewer
RCM File No. 10350.01
Dear Mr. Stadler:
Affected Parties
We have completed our study of the Meadowbrook / Interlachen Park storm sewer
upgrade according to our Agreement with the City dated January 11, 1996. This letter
report summarizes our findings. We welcome the opportunity to discuss this project
further with city staff and the City Council. -
The proposed project will involve replacement of an existing storm sewer that drains
through Meadowbrook Golf Course. The downstream end of the storm sewer will
connect to a newly constructed City of Edina storm sewer in the southwestern part of
Meadowbrook Golf Course. The storm sewer will eventually extend upstream to
Interlachen Park, at the southern end of Homedale Road.
Several parties could be affected by construction of the proposed storm sewer beyond
residents of Hopkins. The following discussion summarizes the primary issues, based on
initial discussions with each organization.
Edina .
The City of Edina has constructed part of the outlet storm sewer for the
proposed Hopkins storm sewer, and is planning to construct the rest of the
system during 1996.
Edina has allocated some capacity in the new storm sewer system for draining
runoff from a small watershed in Hopkins. Edina has requested that Hopkins
limit the discharge to be equal to the gravity flow capacity of a 15 -inch pipe.
-The- existing storm sewer in Edina is under Annaway Drive, extends upstream
though the yard of a home at 4603 Annaway Drive, and ends at the border
between that property and the Meadowbrook Golf Course. The remaining storm
sewer, to be constructed this year, will be aligned under Malt Lane,
Merilane, and through the Meadowbrook Golf Course to a pump station and
pond on the edge of Minnehaha Creek.
Mr. Steven Stadler
March 6, 1996
Page 2
At the comer of Mait Lane and Annaway Drive, the new storm sewer is
proposed to be set about 4 feet higher than the existing pipe. This will cause the
pipe under Annaway Drive and the private yard to always be submerged.
Edina would like Hopkins to install at least one sump manhole to remove grit
from the runoff.
The City of Edina is planning to contact Hopkins about cost sharing. They have
estimated the contributing watershed area split to be 60 percent in Edina, 30
percent on Minneapolis Park Board Property, and 10 percent in Hopkins.
Meadowbrook Golf Course
The Minneapolis Park Board is the owner of this golf course. The proposed
project will benefit the golf course, because the existing storm sewer (or drain
tile) across the course reportedly surcharges and damages turf areas during heavy
rainfall events
Due to the location of the Edina storm sewer, Hopkins must coordinate with the
Minneapolis Park Board to develop an agreement for an acceptable storm sewer
route. RCM has sent a sketch of options to the Head of Operations for the
course, and requested their recommendations for the preferred route.
Park Board staff mentioned a couple of general restrictions for the work. First,
the entrance to the course must always remain open. Short term blocking of the
access road to the "cart shack," near the proposed storm sewer, should be
possible. Second, the Park Board does not want to allow removal of any mature
trees. The proposed project can probably work within these restrictions.
At the start of design, the actual route across the golf course property should be
established by a site visit with golf course and park board staff. The final plans
must be submitted to the Park Board for review and approval.
Minnehaha Creek Watershed District
The Watershed District has jurisdiction over the watershed area of the proposed
storm sewer. The City of Edina and the Meadowbrook Golf Course have an
agreement with the Watershed District regarding operation of the pump station
that drains the proposed Edina storm sewer and other land on the golf course.
When the water level in the Creek is too high, the pump station must not
operate. Runoff will collect in the pond on the golf course until the creek level
decreases
Edina has not yet submitted a permit application to the District for the storm
sewer segments planned to be constructed in 1996. Hopkins should submit a
permit application after or concurrent with the Edina application.
Mr. Steven Stadler
March 6, 1996
Page 3
Interlachen Country Club
Due to the limited space for the proposed storm sewer within Hopkins corporate
limits, RCM met with the golf course superintendent to discuss the possibility of
constructing the storm sewer partly on the property of Interlachen Golf Course.
This course is within the Edina Corporate limits.
Interlachen is willing to consider a storm sewer and easement across their
property as long as the system can improve site drainage on the golf course.
Specifically, they would like an overflow outlet for the ponds in the northeast
corner of the course. They would also like a catch basin installed in the low tree
and brush area south of Homedale Road.
Construction on the golf course property should not occur during the months of
June, July, or August. Heavy equipment must not cross the golf course, so the
contractor will need access from the Hopkins side of the course. Golf course
crews are willing to seed the disturbed areas to restore them, as long as finish
grading is done by the contractor.
Final decisions related to the project must be approved by the Interlachen
Country Club Board of Directors.
Design Criteria and Evaluation
Typical design criteria for storm sewers in Hopkins recommend that pipes should carry
the peak runoff rate from a 10 -year design storm. Building structures near ponding areas
or flooding areas should be protected from flooding during a 100 -year design storm.
Refer to section 2.4.5 in the Hopkins Storm Water Management Plan for further
definitions.
Minnehaha Creek Watershed District has rules that do not allow any increased runoff
rates beyond existing conditions.
The City of Edina has developed a plan, using ponding and a pump station in the
Meadowbrook Golf Course, that allows a slight increase in discharge rate from Hopkins,
but has the disadvantage of no discharge being allowed during flooding of the creek. The
capacity allowance for Hopkins is equal to about 3 to 4 cfs. The conditions during pump
station shut -down should not significantly affect Hopkins, since the excess water will be
held on Meadowbrook Golf Course property.
The available capacity is Less than the peak flow from a 10 -year design storm, but will
allow runoff from that storm to drain away within about 13 hours. Runoff from a 100-
year design storm would drain away in about 27 hours. Excess runoff will stand in the
park area at the south end of Homedale Road and in the Interlachen Golf Course until
it drains away. To increase the storm sewer capacity within Hopkins, or limit overflows
to the golf course, a pond would need to be constructed in the park.
Mr. Steven Stadler
March 6,1996
Page 4
Standing water in the park area should not affect any homes along Homedale Road,
since water would overflow into the golf course at a point at least 3 feet below the lowest
home.
Homes at the south end of Hawthorne Road will likely continue to experience street
flooding as in the existing conditions, but the occurrence should be less frequent. Part
of the existing problem at this point is due to the blocked pipe downstream (to be
replaced), and part is due to the configuration of the cul -de -sac, with berms around it.
To allow the new storm sewer pipe to drain completely between storms, the downstream
end of the Hopkins storm sewer must be set at or above the overflow point in the Edina
storm sewer. The preliminary design was based on an outlet elevation of 887.5 feet MSL
as shown in the design plans prepared by the City of Edina. This elevation must be
verified after construction of the Edina storm sewer so the downstream invert elevation
can be adjusted accordingly.
Pipe Alignment Alternatives
Two pipe alignment alternatives were investigated. The first alternative is entirely in the
Hopkins city limits, called the "Hopkins Alignment." The second alternative is partly on
the property of the Interlachen Golf Course, called the "Interlachen Alignment." The
starting and ending points of the two alternatives are the same.
The Hopkins Alignment would connect to the upstream end of the existing Edina storm
sewer at the city limits, pass on the north side of the Meadowbrook Golf Course cart
shack, and continue west along the alignment of the existing pipe. At Meadowbrook
Road, the catch basin would be replaced, and the pipe would turn south. About 10 feet
north of the city limit, the pipe would turn west, and be placed parallel to the southern
property lines within the existing utility easement. City staff is checking the documented
status of this easement. In the park at the south end of Homedale Road, the pipe would
turn north, and eventually connect to the existing manhole northeast of the park building
(warming shed).
The estimated construction cost for the Hopkins Alignment is about $120,000. This
alternative has the advantage of being located entirely within the Hopkins city limits.
However, it has the disadvantage of significant disturbance to existing trees, fences, and
a tennis court that are within the easement. As many as 37 trees, 6 -inch diameter or
larger. would need to be removed to construct the storm sewer along this alignment.
These trees are the primary visual barrier between the golf course and the homes. In
addition, a temporary easement would need to be obtained from the land owners since
the construction could not all occur within the existing 20 -foot wide easement.
The Interlachen Alignment would connect to the upstream end of the existing Edina
storm sewer at the city limits, pass on the north side of the Meadowbrook Golf Course
cart shack, but then turn southwest toward the Interlachen Golf Course. A storm sewer
Mr. Steven Stadler
March 6, 1996
Page 5
lateral would be placed along the existing alignment to drain the southern end of
Meadowbrook Road. The main storm sewer would be aligned through the golf course
to minimize tree loss. The pipe would be placed through the existing tree and brush area
south of Homedale Road, then through the park, similar to the other alignment.
Laterals would be extended to connect to the existing 12 -inch storm sewer from
Hawthorne Road, and the golf course pond.
The estimated construction cost for the Interlachen Alignment is about $108,000. This
alternative would be less disruptive to trees and fences in the area than the other option.
The route considered through the golf course would not affect any golfing areas. The
primary tree losses would be confined to the tree and brush area south of Homedale
Road, so the visual barrier would remain intact A few trees outside of this area could ✓
also be lost Implementation of this alignment will require obtaining an easement from
Interlachen Country Club.
Conclusion
Construction of the proposed storm sewer will provide a benefit to the area. The existing
storm sewer draining this area will be removed from the Meadowbrook Golf Course,
leaving no outlet. Further, the pipe within Hopkins is substantially plugged or crushed,
and does not allow video inspection to determine the cause of the problem. While the
proposed storm sewer does not meet the standard design criteria for storm sewers, it will
improve drainage in the area compared with the existing conditions.
Either alignment is technically possible to construct. The City can select the most
favorable option considering all of the issues. Splitting the project into two phases may
be possible for the Hopkins Alignment, but is not recommended for the Intelachen
Alignment.
Please call with any questions.
Sincerely,
RIEKE CARROLL MULLER ASSOCIATES, INC.
PDAIL-
Dale A. Folen, P.E.
Assistant Manager, Water Resources
DAF(aec
losure
The capacity of the proposed 15 -inch storm sewer is equal to a design storm of less than
a one year recurrence. Runoff from more intense storms will stand in the park at the
south end of Homedale Road and overflow into the Interlachen Golf Course: The
existing system operates this way, and the proposed system will allow the overflows to
occur less frequently.
The City of Hopkins may want to consider ponding in the park to reduce overflows to the
golf course. The advantage of a pond would be to allow better storm drainage Side the
City. For example, Larger storm sewers could be constructed to drain the land around
Hawthorne or Maple Hill Roads to a pond.
The design criteria for the pond could be selected by the City. Two possible pond sizes
are shown on the attached drawings. The first figure shows a pond which would hold
excess runoff from a 10 -year storm, and allow storm sewers upstream of the pond to be
sized for that same storm. The cost of this option would be about $50,000 added to the
cost of the storm sewer project.
The second figure shows a pond that would hold excess runoff from a 100 -year storm.
The larger pond construction would cost about $80,000. This estimate includes the cost
of demolishing the existing hockey boards and reconstructing them in the bottom of the
pond.
1
Hockey Rink
High Water Level
Pond Shape for 10 -Year Design
Meadowbrook J Interlachen Park Storm Sewer Report
1
High Water Level
Pond Shape for 100 -Year Design
Hockey Rink
Hopkins, MN Meadowbrook / Interlachen Park Storm Sewer Report - March 1996