Loading...
CR 96-114 Award Meadowbrook Sanitary Lift StationJuly 15, 1996 1 v Council Report 96 -114 5 0 p K ` N AWARD CONTRACT FOR MEADOWBROOK SANITARY LIFT STATION, LIFT STATION #5 PROJECT #96 -02 1 Proposed Action. Staff recommends adoption of the following motion: Move that Council reject bids received and direct staff to review project options, as recommended by consulting engineer. Overview. Bids were opened on Sanitary Lift Station #5 Replacement on Friday, July 12 at 10:00 a.m. - two bids were received. The low bid of $280,850 was 33% above the engineer's estimate of $210,362. The City's consulting engineer, Short, Elliott, Hendrickson, Inc. (SEH) believes the major factor impacting the bids is a non- competitive bid climate. Additionally, they feel the very tight working conditions may have also inflated bid amounts. SEH, Inc. recommends rejecting the bids and has identified several cost - saving options (described in the attached letter) for the City to consider prior to readvertising. • Primary Issues to Consider. • What is the impact of rejecting bids and readvertising for Spring, 1997 construction? The City would be required to use the existing lift station another 9 months. This is acceptable if project costs are lowered to the budgeted amount, or closer to the budgeted amount. There would be some additional cost to readvertise the project. However, this cost would be small in comparison to the possible bid savings. • Staff Recommendation Staff recommends Council reject bids. This will give staff time to evaluate options to lower project cost. Staff would then return to Council at a future Council Meeting for permission to proceed with the recommended course of action. Supporting Information • S letter with bid tabulation Steven J. Stadler, Director Of Public Works JUL -15 -1996 12:21 FROM SEH -MPLS SSEH July 15, 1996 Steve Stadler Director of Public Works City of Hopkins 1010 1st Street Hopkins, Minnesota 55343 -7573 Dear Steve: Enclosed is the tabulation of the bids received for this project on Friday, July 12, 1996. Both bids are over the engineer's estimate. A third bid was received from Lametti & Sons, Inc. three minutes after • the time established for receipt of bids. It was not opened. The impact of the low bid amount on the total project budget is as follows: SHORT ELLIOTT HENDRICKSON INC. Low Bid Amount Stucco Exterior Add Alternate Pump Package Pump Controls Package Soil Boring and Testing Forcemain Televising Design and Construction Engineering Less MCES Construction Reimbursement Less MCES Engineering and Administrative Reimbursement Permit Fees and Expenses, and Contingencies Total Budget as Bid The budget in the capital improvements program for engineering and construction for this project was $280,000. Our estimate upon completion of the design matched that total project cost estimate. The higher than expected bids would push the budget for the total project cost almost 15 percent higher than the original budget to $320,000. The major factor impacting the bids is that the bidding climate was not as competitive as it could have been because many of the contractors who do this type of work are busy working on or bidding on • other projects. One of the bidders indicated that eight other lift stations were currently advertised for bids. One of the bidders obtained plans and bid on the project only after encouragement by our office sr PAUL, MN TO 9391381 P.02 5 909 BAKER ROAD. SUITE590, MINNETONKA, MN 55345 812 9314501 FAX 612 931.1168 ARCHITECTURE • ENGINEERING • ENVIRONMENTAL • TRANSPORTATION ST CLOUD, MN RE: Hopkins, Minnesota Sanitary Sewer Lift Station No. 5 Replacement City Project No. 96 -02 SEH No. A- HOPKN9601.00 $280,850.00 2,000.00 9,755.40 6,574.30 3,000.00 524.00 36,930.00 - 22,900.00 - 4,122.00 7388.30 $320,000.00 CHIPPEWA FALLS, WI MADISON, WI JUL -15 -1996 12:21 FROM SEH -MPLS Steve Stadler July 15, 1996 Page 2 during the latter stages of the bidding period. TO 9391381 P.03 Review of the bids reveals that several bid items are significantly over the engineer's estimate. The most significant deviation from the engineer's estimate is for the bid on the control and generator building. Based on discussions with the contractors after the bid, it would appear that the difficulties of construction in a very tight site are reflected in this bid item. The site is just large enough to construct the new lift station and the control and generator building prior to demolition of the existing lift station. There is very little maneuvering room on site. Trees immediately adjacent to the lift station easement make additional easement of little value to the contractor. The impact of the tight working conditions may have been underestimated. It would appear that the City has several alternatives available at this point: 1. Adjust the budget for the project, accept the bids, and award the project to MC Magney Construction. MC Maguey is familiar with this type of work and is currently working on a similar project for the City of Hopkins. 2. Reject the bids and immediately rebid the project for late fall construction. The theory would be that more bidders would be interested in the project during a different timeframe. It is doubtful that sufficiently competitive bids will be received over the next few months. 3. Reject the bids and rebid the same project this winter for a spring construction start. Contractors like to get their first project of the spring construction period lined up in the winter so they know they have work for their people. This may be the way to get the most interest in this project. 4. Reject the bids and redesign the project to make use of the existing lift station structure It has been the desire of the public works staff to have a totally new lift station constructed followed by demolition of the old lift station. The belief was that the cost would be no greater than the cost of converting the existing lift station into a submersible lift station. A new lift station would likely be a tenet product than a renovated lift station. however, based on the bids received, it may be desirable to reexamine those assumptions. A redesigned lift station could be rebid in the winter for spring construction. 5. Reject the bids and rebid the project as designed against a renovated lift station. This alternative has the advantage of determining in fact which method of replacement of Lift Station No. 5 is most cost - effective. Any cost savings which might be realized as a result of alternatives 4 or 5 would be partially offset by additional design and administrative costs. Alternatives 2 and 3 would incur only minor administrative costs. Other issues and their status are as follows: 1. The conditional use permit process that the City of Saint Louis Park is requiting of this project prior to issuance of a building permit should be complete after the August 5, 1996, Saint Louis Park City Council meeting. Based on feedback from city staff, we do not JUL -15 -1996 12:22 FROM SEH -MPLS Steve Stadler July 15, 1996 Page 3 TO 9391381 P.04 anticipate any difficulties as long as the City of Hopkins agrees to a stucco exterior. 2. The Minneapolis Park Board anticipates completion of processing of their pemrit for this project at the July 22 Park Board meeting. The Park Board is asking for additional landscaping, including some vines on the south face of the building. We are still in discussion with them on this issue as we do not feel there is enough room on the site for additional plantings. When the trees proposed on the current site plan are mature, it is questionable whether any of the golfers would even be able to see the building. The Park Board will also be requesting that the decorative limestone landscaping material, the modular block retaining wall, and the building faces all have compatible (probably tan) colors. 3. Other permits should be issued shortly. 4. The easement that the City of Hopkins obtained in 1948, which has been quit claimed in favor of the Metropolitan Council Environmental Services (MCES), has an expiration date of December 31, 1997. The Minneapolis Park Board has begun the process of extending the duration of that easement. They have indicated a reluctance to convert the easement to a permanent easement. 5. The MCES has indicated verbally (through Jim Roth) that they would be agreeable with award of the bids as received. In addition, they will begin the process of relinquishing their easement rights on this site other than as necessary to own and maintain the metering station. We recommend that the bids be rejected. We further recommend that you and your staff further consider alternatives 3-5. We are available to assist you in advancement of this project as you deem appropriate. Sincerely, el R. Boxru, P. Project Manager ymb c: Jim Roth, MCES Enclosure t+WORneROC OPICNCOI1b0X7CUMgIps,EC W?D 1 1 Lt Engineer's Estimate MC Mammy Construction ITEM UWr ESTIMATED QUANTITY UNIT PRICE TOTAL AMOUNT UNIT PRICE TOTAL COST Crider Construction 2 3 4 5 6 7 $ B 10 11 1 1 2 13 14 15 18 17 18 19 20 21 22 23 24 25 26 1127 23 20 30 31 32 33 34 35 30 37 38 39 40 41 42 43 44 45 46 47 48 49 TRAFFIC C TRAFFIC C ONTROL BUILDING DEMOLITION REMOVE CONC. SIDEWALK REMOVE CONC, CURB AND GLITTER SAWCUT CONC. PAVEMENT REMOVE CONC. PAVEMENT SAWCUT BITUMINOUS PAVEMENT REMOVE BITUMINOUS PAVEMENT REMOVE AND REPLACE RCP STORM SEWER ABANDON EXISTING FORCEMAIN CLEARING GRUBBING SILT FENCE, PREASSEMBLED SITE GRADING REMOVE UNDERGROUND FUEL TANK AGGREGATE BASE, CLASS 5 (100% CRUSHED) TYPE 41A BIT. WEARING COURSE MIXTURE 4' CONCRETE BASE 4' CONC CONCRETE WALK 6" CONCRETE DRIVEWAY CONC. CURB AND GUTTER, DES, 9618 18' DIP, 01., 53 SANITARY SEWER CONNECT TO EXISTING MANHOLE WET PIT SEWAGE PUMPING STATION VALVE VAULT METER VAULT 6" DIP. CLASS 53 FORCEMAIN CONNECT TO REHABILITATED FORCEMAIN CLEAN EXISTING 10" C.I.P. 10' NOMINAL C.I.P.P. BYPASS PUMPING REINSTALL FENCE REINSTALL PEDESTRIAN GATE REINSTALL VEHICLE GATE WIRE FENCE SODDING 2 112' REDMOND LINDEN 8' BALSAM FIR 3'HIGHBUSHCRA4BERRY LIMESTONE ROCK MULCH PLASTIC EDGER LANDSCAPE FABRIC CONTROL ANO GENERATOR BUILDING MODULAR BLOCK RETAINING WALL, MECHANICAL EQUIPMENT ELECTRICAL EQUIPMENT INSTALL METER R.T.U. ENCLOSURE WJCONC, PAD ELEC 1 ' CAL FO MCES METE 849 STATON TOTAL ESTIMATED COST LS, L.S. LS. S.F. LF, LF, S.F. LF. S.F. L.F. EACH EACH EACH LF, LS. L.S. UV IN-SY 1N•37 S.F. S.F. L.F. L. EACH LS. L.S. L.S. LF. EACH LF. 1,F.•0 LS. L.S. L S. LS, LF. L.S. L.S, EACH EACH TON LF. $.Y LS. LS. LS. L.S. 'S• $ 1.0 1.0 1.0 495.0 30.0 85,0 750.0 85.0 750.0 24.0 1,0 1.0 1.0 200,0 1.0 1.0 1015.0 355.0 870.0 360.0 100.0 30.0 45,0 1.0 1.0 1.0 1.0 80.0 1.0 430,0 1.0 1,0 1.0 1,0 20.0 1.0 2.0 3,0 5.0 2.5 80.0 22.0 1.0 200.0 1.0 1.0 1.0 1,0 37,400.00 $1,500.00 515,000.00 40.40 52.00 35,00 54.00 32.00 30.50 530.00 $10100.00 00 325010 $100.00 $4.00 $5,000.00 $1,000.00 32.00 32.50 35.00 52.00 33.00 512,00 3100,00 31,000.00 540,000.00 $5,000,00 $4,000,00 350.00 31,000.00 53.00 360'00 33,000.00 3500,00 3500.00 3800,00 320.00 42;000.00 3300,00 5260.00 535.00 365,00 $2.00 31.75 512,000.00 $20.00 810,000.00 333,300.00 $1.000.00 00 00 37,400,00 51.500.00 515.000.00 3198.00 560.00 $425.00 33,000.00 $170,00 3375.00 230.00 $100,00 3250.00 5100.00 5900,00 55,000.00 $1,000.00 32,030.00 3887.50 33,350.00 5720,00 3300.00 3360.00 54500,00 $1,000.00 340,000,00 $5,000.00 34,000.00 $3,00000 51,000,00 31.280.00 334,400.00 33.000.00 $600,00 5500.00 $800.00 5400.00 $2,000.00 3690,00 3780.00 4175.00 3182.50 5160.00 838.50 $12,000.00 54,000.00 310,000.00 333,300.00 $1,000.00 33 700.00 5210,381.50 I 26,000.00 3,000.00 5,000,00 1.00 10.00 9.00 200 4,00 1.00 50.00 1,000,00 600.00 1,200.00 4,00 5.50000 3,500.00 2.00 8.00 8.00 3.00 5.00 10,00 200.00 1,000.00 35,000.00 15,000.00 14,500.00 60.00 1,200.00 9.00 62.00 4,00000. 800.00 200.00 500,00 20.00 2,000.00 250.00 300.00 250.00 100.00 2.00 5.00 40,000,00 1200 5,000.00 44,000.00 2,00 0.00 5 500,00 328,000.00 $3,000.00 $5.000.00 3495.00 5300.00 3765.00 31,500.00 5340,00 5200,00 81,200,00 31.000.00 $600.00 81.200.00 $800,00 55,500.00 33,500.00 $2,030.00 $2,130.00 45,360.00 81,080,00 $500.00 330000 30.000.00 31,00000 535,00000 $15,000.00 $14,500.00 53,600.00 31,20000 53,870.00 522,360,00 54,000.00 3800.00 3200.00 350000 8400.00 $2,000.00 $500.00 5900.00 $1,250.00 5250.00 516000 3110,00 540.000.00 52,400.00 55,000.00 $44,000.00 52.000.00 '.6 500,00 5230,650,00 , UNTr PRICE 16800.00 2,090.00 16.94000 0.60 4.00 4,80 1.20 3.60 0.40 42.50 150.00 300.00 300.00 2.80 2,02000 4,640.00 4.00 17,60 23.20 4.30 17.40 563.00 731,00 71,14000 16.160.00 16.630.00 43.00 1.700,00 9.30 59.00 8.600.00 930.00 230,00 35000 12.00 1,800.00 175.00 230.00 160.00 100.00 2.00 3,00 43,70000 12,110.00 46,400.00 1,16000 2 9 �0 00 TOTAL COST 318,800.00 $2,090.00 316,940.00 3297.00 $120.00 $408.00 5900.00 5306,00 5300.00 31,020.00 515000 5300.00 $300,00 5560.00 82,020.00 34,640.00 54,000.00 *0.246.00 $51,044.00 3430.00 552200 $26,335.00 5731.00 371,140.00 316,160.00 $18,930.00 32.560.00 31,700.00 53,009.00 525,370.00 30600.00 5930.00 3230.00 3350,00 3240.00 $1,600.00 335000 $690.00 $800,00 5250.00 5160.00 543,700.00 L $2,1000.00 $40400.00 $ 000.00 32 00000 0965,180.00 Saniialy Sewer Lift Station No. 5 Replacement Hopkins, Minnesota July 12, 1996 No. A•H0PKN98o1,00 JUL - 15 - 1996 12:22 FROM SEH -MPLS BID TABULATION TO 9391381 P,05 TOTAL P.05 BIDDER 5% BID BOND BID AMOUNT Lametti & Sons ,, 1-6 GHT Construction MC Magney Construction Zg °, tom. Rice Lake Contracting Municipal Builders J &D Enterprises Gridor Construction 34.3 1jO s cSEN Client: City of Hopkins Project: Lift Station No. 5 Replacement City Project No. 96 -02 SEH No.: A- HOPKN9601.00 BIDS RECEIVED Date: 7/12/96