CR 91-117 Landfill Project Change Order . . . i ( \ I I \ "( y 0 :~ , .y CO o P K \ ~ council Report 9l-117 May 16, 1991 LANDFILL PROJECT CHANGE ORDER Proposed Aotion. Staff recommends adoption of the following motion: Move that Council authorize Change' Order No. 2 and Work Chanqe Directive 'No. 5 as they concern the 7th Street South Landfill Gas Remediation, proiect 90-18. overview. When plans were drawn up for the methane remediation project, of paramount concern to the' design engineer was placement of the membrane barrier bottom below the mean groundwater elevation. At the design and bidding stage of the project, this bottom elevation was determined to be 888.0. Following the bid stage, Braun Intertec advised that new data concerning groundwater at the site made it necessary to lower the bottom of the barrier to elevation 884.0. A work change directive was issued to the contractor advising him for the need of deeper trenching, and the contractor replied by requesting additional compensation. These requests are reflected in change Order No. 2 and Work Change Directive No.5. Primary Issues to Consider. o What are the specifics of Change Order No.2? o What are the specifics of Work Change Directive No.5? supporting Information. o Change Order No.2, o Work Directive No. 5 '~ J~eSSele / Engineering Superintendent . . . .~ CR: 9l-ll7 Page 2 Analysis of Issues. o What are the specifics of Change Order No. 21 The Change Order would add a lump sum amount of $20,000 for additional dewatering of the trenches associated with lowering the elevation of the liner system. The impact of this change order upon the original contract price is outlined in the attached Change Order No. 2 document. o What are the speoifics of Work Change Directive No. 51 RCM Associates directed the contractor to change the bottom elevation of the membrane barrier from 888.0 to 884.0 and to increase the burial depth of the ,membrane anchoring system by one foot. This directive came from the engineer ,to address the possibility of lower groundwater elevations. This change in work was also suggested by the engineer for Westbrooke Patio Homes Association to allow for greater dispersion, as landfill gases exit the barrier system and, finally, the change became an MPCA requirement. The engineer deemed this change in work to be of such scope that it should be completed without any changes in contract unit prices. The contractor has concurred and the cost for the increase in work amounts to $256,349.90. The costs are outlined in work Change Directive No. 5 as attached. " CHANGE ORDER NO. 2 . PROJECT: 7th Street South Landfill Gas Remediation Hopkins, Minnesota Date: Aoril23. 1991 OWNER: City of Hopkins Owner's Project No.: , 90-18 TO: (Contractor): Ames Construction, Inc. 14420 County Road 5 Burnsville, MN 55337 Engineer's Project No.: 12079 Contract Date: Aorill. 1991 You are hereby directed to make the following change in the Contract Documents. Description of Change: Refer to the attached Supplement to this Change Order (one page). $ 1.332.82 1.20 (30.834.70) $1.301.986.50 20.000.00 $1.321.986.50 CHANGE IN CONTRACT TIME Original Final Completion Date for Section 1 Original Final Completion Date for Section 2 Final Completion Date for Section 1 by previous Change Orders Final Completion Date for Section 2 by previous Change Orders Final Completion Date for Section I from this Change Order Final Completion Date for Section 2 from this Change Order July 8. 1991 August 1. 1991 July 8. 1991 Au~mst1. 1991 July 8. 1991 August I. 1991 Engineer's Recommendation, RIEKE CARROLL MULLER ASSOCIATES, INC. by ~N.;i. ~.....--- .. ~~, r~ Contractor's Acceptance, AMES CONSTRUCTION, INC. .wner's Order, CITY OF HOPKINS by by., Page I of I ,:.iiiiio.. ...... . . SUPPLEMENT to CHANGE ORDER NO.2 for 7TH STREET SOUTH LANDFILL GAS REMEDIATION CITY OF HOPKINS PROJECT NO. 90-18 RCM PROJECT NO. 12079 Date of Change Order: April 23, 1991 Justification The Bidding DocuIIlents required the bottom of the HDPE liner to be at elevation 888.0. Following the bid opening, the Owner's geotechnical engineering consultant advised it was required to lower this elevation to 884.0. This change was included in Work Change Directive No.4 issued on March 21, 1991. The Contractor responded to this directive with their Serial Letter No.8 (see attached copy), requesting additional compensation for the additional dewatering required by this elevation change. Pricin2 Data The attached copy of the Contractor's Serial Letter No.8 includes the proposed additional contract amount of $20,000. The Engineer has reviewed this matter and has determined that this amount appears to be reasonable. Page 1 of 1 " , , <l~01JTI .t5~': ~s'sociates, inc. engineers arcl1itects land surveyors equal opportunity employer . April 26, 1991 Mr. Michael Moeller Project 'Manager Ames Construction, Inc. 14420 County Road 5 Burnsville, MN 55337 RE: 7th Street South Landfill Gas Remediation Hopkins, Minnesota City Project No. 90~18 RCM Project No. 12079 RCM Serial Letter No. 14 Work Change Directive No.5 Dear Mr. Moeller: Enclosed ,are two (2) copies of Work Change Directive No.5 for your review. If acceptable, please execute both copies and return one executed copy. If not acceptable, please refer to the instructions on the form. Please call if you have questions. Sincerely, Enciosure (2) c: James Gessele; City of Hopkins (w / encl.) Jonathan ScolI; Doherty Rumble & Butler (w / encl.) G~orge Anderson; RCM (w / encl.) 10901 red circle drive box 130 minnetonka. minnesota 55343 612~935-6901 '; WORK CHANGE DIRECTIVE NO. 5 . PROJECT: 7th Street South Landfill Gas Remediation Hopkins, Minnesota Date: Aoril 24. 1991 OWNER: City of Hopkins Owner's Project No.: 90-18 TO (Contractor): Ames Construction, Inc. 14420 County Road 5 Burnsvi1le, MN 55337 Engineer's Project No.: 12079, Contract Date: April 1, 1991': You are hereby directed to execute promptly this Work Change Directive which interprets the Contract Documents or orders minor changes in the Work without change in Contract Unit Price or Contract Time. If you consider that a change in Contract Unit Price or Contract Time is required, do not execute this form, but please submit your itemized proposal to the Engineer immediately and before proceeding with this Work. If your proposal is found to be satisfactory and in proper order, this Work Change Directive will in that event be superseded by a Change Order. The purpose of this Work Change Directive is to replace Work Change Directive No.4 in order to account for the additional dewatering costs added to the contract in Change Order No.2. . . Description of Change: 1. Change the elevation of the bottom of the HDPE geomembrane from 888.0 to 884.0 as shown throughout the revised Drawings. 2. Increase the burial depth of the HDPE geomembrane anchoring system by one foot. The additional one foot of material overlying the geomembrane shall consist of Fine Filter Aggregate as shown on revised Sheet 2 of the Drawings. . 3. Change the grading plan as shown on revised Sheet No.6 of the Drawings to provide a minimum 2 percent slope on the landfill proper. 4. Payment for additional dewatering work of this Work Change Directive shall be in accordance with Change Order No.2. Payment for the remaining additional work of this Work Change Directive shall be at the Bid Unit Price and is estimated as follows: Purpose of Change: 1. This change was made to account for the possibility of lower groundwater elevations. 2. This change was suggested by WPHA to allow greater dispersion as landfill gases exit the barrier system after construction to reduce the possibility of vegetation stress. 3. This change is an MPCA requirement. I, .ttachments: This change is incorporated in the revised, Drawings marked "Construction Document 3/18/91- issued on March 20, 1991. ENGINEER: Rieke Carroll Muller Assoc., Inc. By:~lyJ~ DATE: t-/Z-6/c", CONTRACTOR'S ,ACKNOWLEDGEMENT BY: DA TE: . Page 2 of 2