CR 91-161 Landfill Project - CO 5/6t Y O G ti CO O \4 July 31, 1991 P K` 1 Council Report: 91 -161 LANDFILL PROJECT - CHANGE ORDER NUMBERS 5 & 6 Proposed Action. Staff recommends adoption of the following motion: Move that Council authorize Change Order Numbers 5 & 6 as they concern the 7th Street S. Landfill Gas Remediation, Project 90 -18. overview. Integral to the landfill project was trench dewatering and a measuring system to gauge amount of discharge into the sanitary sewer system. Now that the project is complete, this discharge flow rate measuring system has had to be dismantled and the disturbed pavement and a driveway in the area fully restored. The installation of the original system was required by the MWCC and incorporated in Change Order No. 3. The MPCA requested the placement of additional top soil material over the landfill on an area of the site north of the refuse disposal area and also requested seeding, mulch, and disc anchoring of the same area. This is in keeping with the MPCA's requirements for establishment of vegetation on all areas overlying refuse. Primary Issues,to Consider. o What are the costs? Change Order No. 5 will cost an additional $1,870.00. Change Order No. 6 will cost an additional $22,693.05. o What are the specifics of these change orders? See the attached supplements from RCM and Associates for description of change and justification. Supporting Information. o Change Order No. 5. o Change Order No. 6. J&PAs Gessele Engineering Superintendent 0 SUPPLEMENT to - CHANGE ORDER NO. 5 for 7TH STREET SOUTH LANDFILL GAS REMEDIATION CITY OF HOPKINS PROJECT NO. 90 -18 RCM PROJECT NO. 12079 Date of Change Order: July 12, 1991 Description o Change 1. Remove the dewatering discharge flowrate measuring system and deliver the pipe, valves,. manholes, and metal enclosure to the Owner. 2. Restore the disturbed areas with the appropriate materials in accordance with the Contract Documents: Justification The Metropolitan Waste Control Commission (MWCC) required the dewatering discharge volume be measured and reported to the MWCC. The additional costs for installation and equipment rental required to provide this measuring system was incorporated in Change Order No. 3. The installation and removal of this system required restoration of the pavement and driveway in this area. Pricing Data Attached is Serial Letter No. 27 from the Contractor with the submitted costs for this additional work. The Engineer has reviewed the cost and has determined that this cost appears to be reasonable based on the additional efforts required to perform this work. k Attachments to this Supp lement 1. Letter from Contractor - 2 pages Page 1 of I AMES CONSTRUCTION, INC. 14420 COUNTY ROAD S At BURNSVILLE, MINNESOTA 55337 (612) 435 -7106 - FAX 435 -7142 ' °"`, i JUN 211991 June 20, 1991 Rieke, Carroll, Muller, Associates, Inc. 10901 Red Circle Drive Minnetonka, .Minnesota 55343 Riake Carroli P:�!ier Assliciates I.a. Box 130 Hopkins, Minn. 55343 Attention: James B. Hammer, P.E..a 4 Reference: Repair of Street at Manhole Ames Serial Letter Number 27 7th Street South Landfill Gas Remediation City of Hopkins Project Number 90 -18 Hopkins, Minnesota 9 Gentlemen:- We have repaired the street at the connection of the dewatering discharge to the sanitary manhole. As discussed, this work is extra to our contract. The cost for this repair is $1,870.00. Please see the attached invoice from Northwest Bituminous Maintenance, Inc. It is our request that a change order be issued for this amount. If there are any questions, please give me a call. Sincerely, Michael Moeller Project Manager. cc: James City of Hopkins An Equal Opportunity Employer OFFICES IN: DENVER, COLORADO - PHOENIX, ARIZONA - SALT LAKE CITY, UTAH ARM NORTHWEST BITUMINOUS - MAINTENANCE, INC.' INVOICE No. 11 ,91 I 7216 Watt 128th Street Savage, MN 56378 PHONE (612) 890.3005 OWNER'S NAME AIIES' 'CONSTRUCTION, INC. /TERRY AM PHONE 435 7106 DATE JUr`1E ? 1 STREET 14420 CO. RD PROJECT . 5 PROJECT NAME HOPKINS LANDFILL GnS REMIDIA NO. lo:* CITY BURid SVILLL STATE ZIP STREET MN. 55337 11TIi AV SO AND 7TH ST. EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY 11 5/1.6/31 IiOPKINS STATE ;1;;. ZIP PROJECT DESCRIPTION PRICE AMOUNT BLACKTOP CONSTRUCTION ( PARKING LOT) FURNISHES AND INSTALLED 54.14 TOPS MIX. s43. G :. ::% , 048 00 BL l.Ci�T0P PATCNING (STREEE) J.'::I :)UT, PREPARE r A2:D INSTALL 22 ToN ; :IIX ;; 5 . Q: :1 i.�i i n 1, i •' I: L; PLEASE PAY ON If VOICE. NO STATEMENT WILL BE SENT UNLESS REQUESTED. YOUR BUSINESS IS APPRECIATED i SUPPLEMENT to CHANGE ORDER NO. 6 for 7TH STREET SOUTH LANDFILL GAS REMEDIATION CITY OF HOPKINS PROJECT NO. 90 -18 RCM PROJECT NO. 12079 Date of Change Order: July 24, 1991 Description of Chancre 1. Place six (6) inches of Topsoil Borrow material on an area of the site north of the refuse disposal area. This area was measured by the Contractor and Engineer to be 4.85 acres, corresponding to a topsoil volume of 3,912 cubic yards. 2. Seed, mulch, and disc anchor this same area, using -No. 700 seed mixture. 3. The work of this Change Order shall be in accordance with the Contract Documents. Justification The Minnesota Pollution Control Agency (MPCA) requires vegetation be established on all areas overlying refuse. Pricing Data Payment for the Work of this Change Order shall be as follows: Unit Item Unit Quantit Price Amount Topsoil Borrow CY 3,912 $5.15 $20,146.80 Seed (Mixture 700) and Mulch Acre 4.85 525.00 2.546.25 Total Increase Amount for this Change Order $22,693.05 Page 1 of 1 CHANGE ORDER NO. 5 PROJECT: 7th Street South Landfill Gas Remediation Hopkins, Minnesota OWNER: City of Hopkins TO: (Contractor): Ames Construction, Inc. 14420 County Road 5 Burnsville, MN 55337 Date: July 12, 1991 Owner's Project No.: 90 -18 Engineer's Project No.: 12079 Contract Date: April 1, 1991 You are hereby directed to make the following change in the Contract Documents. Description of Change: Refer to the attached Supplement to this Change Order (I page). CHANGE IN CONTRACT PRICE Original Bid Price $1,332,821.20 Net change from previous Change Orders 20-203.89 Contract Price prior to this Change Order $1.353,025.09 Net increase (decrease) from this Change Order 1.870 00 Contract Price including this Change Order S CHANGE IN CONTRACT TIME Original Final Completion Date for Section 1 July 8. 1991 Original Final Completion Date for Section 2 _ August I 1991 Final Completion Date for Section I by previous Change Orders July 8. 1991 Final Completion Date for Section 2 by previous Change Orders August 1. 1991 Final Completion Date for Section 1 from this Change Order I July 8. 1991 Final Completion Date for Section 2 from this Change Order August 1. 1991 Engineer's Recommendation, RIEKE CARROLL MULLER ASSOC., INC. Contractor's Acceptance, AMES CONSTRUCTION, INC. by •� date = 7 / Z /V_ by -� • 1' spa 1� date AlIkO wner's Order, CITY OF HOPKINS by date Page 1 of 1 CHANGE ORDER NO. 6 0 PROJECT: OWNER: TO: (Contractor): 7th Street South Landfill Gas Remediation Hopkins, Minnesota City of Hopkins Ames Construction, Inc. 14420 County Road 5 Burnsville, MN 55337 Date: _ July 24, 1991 Owner's Project No: 90 -18 Engineer's Project No: 12079 Contract Date: April 1, 1991 You are hereby directed to make the following change in the Contract Documents. Description of Change: Refer to the attached Supplement to this Change Order (1 page). * CHANGE IN CONTRACT PRICE Original Bid Price Net change from previous Change Orders Contract Price prior to this Change Order Net increase (decrease) from this Change Order Contract Price including this Change Order _ $1.332.821.20 22.073.89 $1.354.895.09 22,693.05 $1.377.588.14 CHANGE IN CONTRACT TIME Original Final Completion Date for Section 1 Original Final Completion Date for Section 2 Final Completion Date for Section 1 by previous Change Orders Final Completion Date for Section 2 by previous Change Orders Final Completion Date for Section 1 from this Change Order Final Completion Date for Section 2 from this Change Order Engineer's Recommendation, RIEKE CARROLL MULLER ASSOC., INC. Contractor's Acceptance, AMES CONSTRUCTION, INC. �'Jwner's Order, CITY OF HOPKINS , by by July 8. 1991 August 1. 1991 July 8. 1991 August 1. 1991 July 8. 1991 August 1. 1991 date 2' Z4' 9 ,/_ date - 1 ( q date Page 1 of 1