CR 91-166 Campbell Addition - Champbell DriveJuly 31, 1991 Council Report: 91 -166
CAMPBELL ADDITION - CAMPBELL DRIVE
CHANGE ORDER
Proposed Action.
Staff recommends adoption of the following motion: Move that Council
authorize Change Order No. 1 as it concerns Campbell Addition and
Campbell Drive Improvement Projects 90 -20 and 90 -23.
Overview.
Before construction began on Campbell streets, a final survey of water
service curb boxes was, performed by City forces. Location and
operation were noted, and the inventory revealed extensive
misplacement of valves when the water main was originally installed.
Relocations and adjustments were necessary in order to facilitate
placement of concrete curb and gutter. Once a list was compiled, it
was presented to the contractor for quotes on work to be performed.
Primary Issues to Consider.
o What are the costs?
Change Order No. 1 will cost an additional $9305. Water
utility contingency funds will cover this additional cost.
Supporting Information.
o Change Order No. 1
ames Gessele
Engineering Superintendent
•
CHANGE ORDER
Number 1
WESTWOOD PROFESSIONAL SERVICES, INC.
14180 TRUNK HIGHWAY 5
EDEN PRAIRIE, MINNESOTA 55344 DATE: 07/29/91
(612) 937 -5150
PROJECT NO. & DESC. 90395
TO: GMH Asphalt
17018 Saddlewood Terrace
Minnetonka, MN 55345 CONTRACT DATE: April 2, 1991
CONTRACT FOR: Campbell Neighborhood Hopkins, MN
YOU ARE HEREBY DIRECTED TO MAKE THE FOLLOWING CHANGES TO THE ABOVE MENTIONED
CONTRACT:
ADDITIONS:
Relocation of Curb Stops /Boxes (Approximately 14 @ $590.00) $ 8,260.00
Adjust Curb Boxes in Street with Gate Valve Box /Cover
(Approximately 11 @ $ 95.00) $ 1,045.00
TOTAL CHANGE ORDER $ 9 ,305.00
CONTRACT STATUS PER THIS CHANGE ORDER ACCEPTANCE
The Time to Complete The
Contract is ® Unchanged
Increased 0 Decreased by Days
The Date of Completion is Now
Unchanged
Original Contract Sum $ 305,896.00
Net Change
By Previous Change Order $ 0.00
Contract Sum $ 305,896.00
Prior to This Change Order
' ^' Addition 0 Deduction
Made by This Change Order $ 9,305.00
New Contract Sum $ 315,201.00
Engineer:
Westwood Professional Services, Inc.
By r
Date
Contractor:
GMH Asphalt
By A ��
Date
Owner:
City of Hopkins
By
Date
C I T Y O F H O P K I N S
July 12, 1991
Westwood Engineering
Fran Hagen, Sr., P.E.
14180 TH 5
Eden Prairie, MN 55344
Dear Fran:
The City accepts the following prices for curb box
adjustments in the Campbell Neighborhood as quoted:
$590 Curb stop relocation and adjustment
$95 Adjustment of curb box in street and placement of
valve box over curb box
If the listed prices agree with your figures, please
expedite.
Sincerely,
Richard V. Hill
Senior Engineering Technician
RVH: j