CR 91-173 Award Bid - Meadowbrook Lift StationI Y O August 2, 1991 ti 5 O P K Council Report: 91 -173 AWARD OF BID MEADOWBROOK LIFT STATION • Proposed Action. Staff recommends adoption of the following motion: Move that Council adopt Resolution 91 -105 Resolution Awarding Bid - Meadowbrook Lift Station, Project 91 -06. overview. The March 1990 Water and Sewer Utility Master Plan identified certain sanitary lift stations in need of reconstruction or repair. Among these is the Meadowbrook Road Station where past remodeling efforts have made inspection and maintenance difficult. A Meadowbrook reconstruction project was identified in the City's CIP and authorized as a capital improvement. Plan and specifications were prepared by RCM Associates, Inc., and the bidding process is completed. Sealed bids were opened,August 2, and a tabulation is found below: Gilbert Mechanical Contractors $ 88,700.00 Jedlicki Inc. 89,038.00 Penn Contracting Inc. 89,900.00 New Mech 92,800.00 Ryan Construction 112,000.00 Engineer's Estimate 92,000.00 The low bidder is Gilbert Mechanical Contractors. RCM Associates has checked the bids and reviewed the qualifications of Gilbert. Primary Issu to Consider. • Should the award be made to Gilbert Mechanical Contractors? Gilbert is a qualified bidder and competent contractor who will complete the project. • Is the bid reasonable? The bid is $3300 lower than the engineer's estimate. Staff recommends award of bid to Gilbert. Supporting Information. o Engineer's recommendation o Resolution 91 -105 James Gessele Engineering Superintendent L J August 2, 1991 Mr. Jim Gessele, Engineering Supervisor City of Hopkins 1010 First St. S. Hopkins, MN 55343 RE: Award of Contract Meadowbrook Road Pump Station RCM Project No. 10113.01 Dear Jim: deke carroll After review of all the bid proposals submitted to the City of Hopkins for Ass?c muller the Meadowbrook Road Pump Station, Gilbert Mechanical Contractors, Inc., llates, Inc, of Minneapolis, Minnesota, has submitted the lowest responsible bid. Their n sneers architects bid of $88,700.00 is approximately 4% below the engineer's estimate. land surveyors equal opportunity Therefore, we recommend that Gilbert Mechanical Contractors, Inc. be employer 'awarded the project. A y 1 k.V Carlso RIEKE CARROLL MULLER ASSOCIATES, INC. PJC /jj c: Lee Gustafson, City of Hopkins Mike Lauseng, City of Hopkins Bill Cook, RCM Dick Kloskin, RCM —0 10901 red circle drive box 130 minnetonka, minnesota 55343 612- 935 -6901 CITY OF HOPKINS Hennepin County, Minnesota RESOLUTION NO: 91 -105 RESOLUTION FOR AWARD OF BID Meadowbrook Lift Station BE IT RESOLVED BY THE CITY COUNCIL OF HOPKINS, MINNESOTA, that the bid of Gilbert Mechanical Contractors in the amount of $88,700.00 is the lowest responsible bid for the construction of Meadowbrook Sanitary Lift Station, City Project 91 -06, and the Mayor and City Manager are hereby authorized and directed to enter into a contract with said bidder for and on behalf of the City. Adopted this 6th day of August, 1991. Nelson W. Berg, Mayor 0 ATTEST: James A. Genellie, City Clerk •