CR 91-208 Proposal Knollwod Street` I Y O
L. - W-A
G � t
ti C!)
September 12, 1991 ° P K�� C ouncil Report: 91 -208
REQUEST FOR PROPOSAL
KNOLLWOOD STREET RECONSTRUCTION
Proposed Action.
Staff recommends the following motion: " Move that Council
authorize the Mavor and Citv Manaaer to enter into an aareement
with RLK Associates Ltd. for design and construction engineering
for street and utility reconstruction in the . Knollwood
Neighborhood.
overview.
Council at its August 6 meeting ordered a feasibility study to be
conducted concerning Knollwood street reconstruction. Staff felt
it was very important to reevaluate the City's engineering needs
in such a project and initiated an RFP process. Four consulting
firms were interviewed September 9-11, and this report recommends
entering into a contract for engineering services with one of
these f irms .
Primary Issues to Consider.
o What is the cost of these services?
o Which firm should plan /design /coordinate this project?
Supporting Information.
o Request for Proposal (RFP)
James Gessele, Engineering Superintenden
Council Report: 91 -208
Page 2
Analysis of Issues.
o What is the cost of these services?
The following are the four firms that were interviewed along
with their estimated fee percent of each phase based on an
8 -9 hundred thousand dollar project:
Bidding/
Engineer Feasibility Design Constr. Total
RLK
0.4
4.9
6.1
11.4
Bolton & Menk
0.5
4.2
5.3
10.0
TKDA
0.5
3.0
8.1
11.6
RCM
0.5
6.4
8.9
15.8
The various estimates for all phases vary from approximately
10 to 16 percent of construction, costs. In addition, each
firm charges for miscellaneous reimbursable expenses such as
copies, travel, etc. The total cost of services for all
phases could range from 90 to 142 thousand dollars for a 900
thousand dollar project. These costs appear to be
consistent with market rates for engineering and planning
services. The total fees include feasibility study, public
meetings, concepts, design, bidding and construction
coordination, inspection and surveying.'
o Which firm should plan /design /coordinate this project?
Staff recommends the firm of RLK Associates Ltd. be retained
to engineer this project.
RLK's estimated fees are within reason for the project.
Closer examination of the firm's proposal reveals that they
have committed' almost 2 percent of their total fee towards
the cost of conducting meetings with the residents of
Knollwood. This indicates RLK's emphasis on a high level of
community and staff input.
During the course of the interviews staff was impressed with
RLK's innovative approach to neighborhood street
construction and the stress it places on cost effectiveness
in completing a project. To that end it has placed heavy
stock on landscaping /amenities and the use of construction
management.and bid management techniques in reducing the bid
cost to the city.
t i
Council Report: 91 -208
Page 3
RLK Associates Ltd. has all disciplines on their staff to
compete this project. Richard Koppy, the president of the
firm, will be the project manager and have primary
responsibility for public contact. He is the former Public
Works Director of St. Louis Park and has had extensive
experience in dealing with sensitive neighborhood
improvement projects. Paul Kroehnert, a new addition to the
RLK staff and most recently responsible for site engineering
at the Mall of America, will serve as design engineer. John
Dietrich will serve as the project landscape
architect /planner. Chuck Poppler will serve as project
superintendent and will manage all field operations
The firm is located in Hopkins, raising city expectations
for expedient service.
F '
City of Hopkins
Request for Proposal
For
Engineering and Planning Professional Services
August 26, 1991
Project: Knollwood Street Reconstruction and Utility
Improvements
Contact: Lee Gustafson, Public Works Director (939
1382)
Jim Gessele, Engineering Superintendent (935-
8474)
Submittal Date: September 6, 1991
Interview Date: September 9 and 10, 1991
Appointment Date: September 17, 1991 (Council Meeting)
Professional engineering and planning services for street and
utility reconstruction in the Knollwood neighborhood 'in the
following phases:
Phase I Initial Feasibility Study
A. Analysis of neighborhood streets for geometric
design.and utilities for upgrading.
1. Examine previous study completed in January
1990.
2. Examine previous sewer televising and soils
investigation reports.
3. Prepare new report containing layouts,
opinions of construction costs, findings and
recommendations,
o Assuming reconstructed streets are
limited to 20 feet in width, identify
areas where streets can be widened to
twenty -six feet to accommodate parking.
Varying street widths should be
reflected in cost estimates.
o List project costs with and without
concrete curb and gutter.
o Street reconstruction without concrete
curb and gutter where street grades are
less than one percent should reflect
e
cost of drain tile and /or surface drains
in swale sections.
o Street reconstruction without concrete
curb and gutter should reflect cost of
heavier street section, i.e., thicker
aggregate base and bituminous sections,
and raised bituminous edge.
o List project cost with alternative
bituminous or concrete alley.
B. Preparation of preliminary assessment roll in
keeping with current assessment policies.
C. Completion date: September 27, 1991
D. Schedule
October 1 Council orders public hearing
October 2 and 9 Publish in Sailor
October 15 Public hearing and Council
orders plans and
specifications
Phase II - Design
A. Conduct neighborhood meetings during preliminary
plan design for resident input.
B. Prepare detailed plans, specifications, bidding
documents for City approval..
C. Submit plans and specifications to permitting
agencies for approval. Plans should be based on
data compatible for use with the City's Ulti -Map
system.
D. Estimated completion date: January 7, 1992
Phase III.- Bidding
A. Prepare bidding documents and assist City in
securing bids, tabulating and analyzing bid
results and furnish recommendations.
B. Schedule
January 7, 1992 Council approves plans and
specifications and orders bids
January 8, 15, -22 Bid ad in Sailor
January 30 Bid opening
Phase IV - Assessments (administered by City)
February 18, 1992 Council examines bid
tabulation and orders
assessment hearing
February 26 /March 4 Ad in Sailor
March 17 Assessment hearing and
adoption of assessment role
April 21 Award of bid
Phase V - Construction Engineering
A. Prepare contract documents, organize pre
construction conference
f;
B. Provide full -time field inspection during
construction. Monitor and ensure the meeting of
all required construction schedules. Perform
public relations and solve individual problems as
they relate to the residents.
C. Review and approve shop drawings, results of tests
and inspections.
D. Provide interpretation of contract documents,
preparation of periodic payment requests and
change orders.
E. Conduct final inspection.
F. Provide reproducible record drawings.
Additional elements required:
A. Indicate personnel proposed for project feasibility,
design and construction. Indicate in -house
capabilities for various project components. Name
spokesperson who will conduct meetings with residents
and speak before the'City Council.
B. All recommendations and investigation in written report
form.
C. Close contact with City. staff throughout all phases by
telephone and correspondence is expected.
Fees and reimbursement:
The proposal should include a schedule of hourly billing
rates for each category of professional, technical and
clerical 'employees. Include rates of miscellaneous charges
such as copies and mileage. Indicate how requests for
additional services would be billed. A method of
establishing a fee charge range for reach phase should be
indicated as an estimated percent of construction cost
Invoice period intervals are a minimum of 30 days with a
payment date of 30 days maximum from date of invoice.
Council meetings are the first and third Tuesdays of the
month with invoice deadline the previous Tuesday.