CR 91-263 Knollwood Street ImprovementsNovember 26, 1991
Proposed Action.
Staff recommends the following motion: Move that Council
adopt Resolution 91 -149, Resolution Ordering Improvement
After Public Hearing, Knollwood Street Reconstruction,
Project 90 -01.
This action will continue an assessable project on the
streets in the Knollwood neighborhood. Plans and
specifications will be developed and bids solicited for
construction in the spring of 1992.
Overview.
The Council at its August 6, 1991 meeting ordered that a
feasibility report concerning Knollwood street improvements
be prepared. That report was presented to the Council on
November 19 and given approval at that time. Council also
authorized a public hearing concerning such a project for
December 3, 1991. Public information meetings with the
Knollwood Association have been held and issues of street
width, alternate types of curbing, utility repair, trees,
construction schedule and assessments were discussed.
Ten days mailed notice and two weeks published notice of the
December 3 hearing have been given. Attached to this report .
you will find a mailing list and a map of all parcels
notified.
Primary Issues to Consider.
Knollwood Street Improvements
Public Hearing
Council Report: 91 -263
o Recommendations in the feasibility report
o Resident concerns with a reconstruction project
o Project cost
o Deletion of parcels from project involvement
o Staff recommendation
Supporting Information.
0
0
Notice of Hearing of Improvement
Feasibility report
Minutes of November 25 neighborhood information
meeting
Resolution 91 -149
James Gessele
Engineering Superintendent
Analysis.
Recommendations in the feasibility report
An executive summary found near the beginning of the
feasibility report as prepared by RLK Associates Ltd.
outlines the consultant's recommendations concerning
this project. The following analysis further
synopsizes staff and consultant positions.
Right of Way/ easements
The City needs to obtain various easements to
memorialize storm ponds, drainage /utility lines, and
alignment of the roadway.
Storm sewer
The present storm sewer system needs to be
reconstructed for the most part, sedimentation basins
installed within the ponds, and local drainage problems
addressed and tied to the general storm system.
Sanitary sewer
Approximately one -half of the existing sanitary mains
needs to be replaced and the sewer line under the
garage at 602 Edgemoor Drive eliminated. The City
should actively encourage reconstruction of private
services if there is a need.
Water main
Approximately 3,400 feet of cast iron pipe should be
replaced with ductile iron pipe and new pipe
installation undertaken to complete a looping system.
The City should actively encourage reconstruction of
lead pipe services.
Street
Roadways should be reconstructed with concrete
surmountable curb and gutter, at a driving surface
width of 20 feet or 22 feet wide back -to -back. Parking
should be restricted on 20 foot wide streets in keeping
with minimum standards required by the State Fire Code.
Alleyway
The current alley should be reconstructed with concrete
per City Roadway Policy 8 -B and assessed to benefitting
properties.
Landscaping
Design and specifications should call for minimum tree
removal, replacement of trees with 4 " -6" size caliper,
protection of trees with retaining walls, landscape
amenities at pond's edge and along Edgemoor Drive.
Street lighting
An optional feature based on neighborhood request would
be to install ten new ornamental street lights.
Construction scheduling
An improvement project should be predicated on a
construction schedule beginning May 18 and completion
by mid - October 1992. Construction phasing can be
specified as a means of minimizing inconvenience to
residents.
o Resident concerns with a reconstruction project
The public hearing setting will afford the best
opportunity to measure residential sentiments. Staff
and the consultant has been able to measure reaction to
issues raised in the feasibility report and Council can
gauge neighborhood sentiments by reading the attached
minutes of the November 25 neighborhood information
meeting. Discussions have been open, frank and at all
times congenial. The residents do take issue with
staff positions on cost sharing of concrete curb and
gutter, roadway width and reconstruction of the alley.
Although the neighborhood petitioned for street
reconstruction with bituminous curbs, it appears
residents would be willing to accept colored concrete
curb and gutter. The cost of street construction with
bituminous curbs is estimated at $499,000, with colored
concrete curb and gutter at $517,000. Residential
sentiment is for the City to assume 100% of the cost
differential.
Residents petitioned for a twenty foot roadway width
measured back -to -back of curb. The City's position,
gleaned from Roadway Policy 8 -B, is that the twenty
feet are measured from face to face of curbs. This is
in keeping with State Fire Code requirements.
The alley serving 410 Cottage Downs and 810 and 804
Valley Way is considered by residents to be an unnamed
street and as such should be reconstructed with
bituminous surfacing. An alternative calling for
bituminous surface with either bituminous or concrete
curbing has been suggested, but the City's position has
been to adhere to Roadway Policy 8 -B and install a
concrete alley.
o Project cost
The consultant estimates a total project cost of
$834,000 including overhead. This is for a project
that encompasses those recommendations made in the
executive summary of the report and as outlined in the
above analysis. City costs are estimated to be
•• $455,000, property owner costs $379,000. Using the
adjusted front foot formula as outlined in the City's
assessing policy, assessments would range from $6,300
to $11,000 per property.
o Deletion of parcels from project involvement
Public hearing notices were mailed to all property
owners in Knollwood. This included the addresses 601,
707, 711, 715, 805 and 809 Oakridge Road. These
parcels, except 601, should be deleted from further
consideration to remove them from possible pending
assessment status. The resident at 601 Oakridge Road
is interested in construction of concrete curbing on
Oakridge to the T.H. 7 intersection and would be
subject to curb assessments should construction of such
a feature be found feasible.
o Staff recommendation
Staff recommends that a project be undertaken as
outlined in the feasibility and that Council adopt
Resolution 91 -149 ordering a public improvement.
TO WHOM IT MAY CONCERN:
NOTICE OF HEARING OF IMPROVEMENT
WHEREAS, the City Council of the City of Hopkins, Hennepin
County, Minnesota, deems it necessary and expedient that the
improvement hereinafter described, be made,
NOW, THEREFORE, notice is hereby given that the City Council
will hold a public hearing on said improvement at the following
time and place within the said city:
DATE: December 3, 1991
TIME: 7:30 p.m.
LOCATION: City Hall
Council Chambers
1010 1st Street S.
Hopkins, MN 55343
The general nature of the improvement is the construction of
streets and storm sewer and inspection and repair of sanitary
sewer, water main, gas and electrical utilities, City Project 90-
01.
Cottage Downs, Park Terrace, Bridle Lane, Valley Way,
Wilshire Walk, Edgemoor Drive, Oakridge Road, and Alleyway off
Cottage Downs.
THE TOTAL ESTIMATED COST OF SAID IMPROVEMENT IS $900,000.00.
It is proposed to assess every lot, piece or parcel of land
benefited by said improvement whether abutting thereon or not,
based upon benefits received without regard to cash valuation.
Persons desiring to be heard with reference to the proposed
improvement should be present at this hearing.
This Council proposes to proceed under the authority granted
by Chapter 429 MSA.
jghearng
Dated this 19th day of November, 1991.
Publish: Hopkins Sai`or
November 20 and 27, 1991
BY ORDER OF THE CITY COUNCIL
A. Genellie, City Clerk
ty of Hopkins, Minnesota
AFFIDAVIT OF MAILING PUBLIC HEARING NOTICE
STATE OF MINNESOTA
SS.
COUNCIL OF HOPKINS
James A. Genellie, being first duly sworn, deposed and says:
I am a United States citizen, over 21 years of age, and the
City Clerk of the City of Hopkins, Minnesota.
On October 20, 1991, acting on behalf of the said city, I
deposited in the United States post office at the City of
Hopkins, Minnesota, copies of the attached notice of hearing
on proposed street and storm sewer construction, City
Project 90 -01, enclosed in sealed envelopes, with postage
thereon fully prepaid, addressed to the following persons at
the addresses appearing on the attached copy of the mailing
list.
There is delivery service by United States mail between the
place of mailing and the places so addressed.
Signature
Subscribed and sworn to before me this 20th day of October,
1991.
6 904 0 :41/,61/
Notary Public
JAMES T. GESSELE
NOTARY PUBLIC— MINNESOTA
HENNEPIN COUNTY
My commission expires 349 -
List:Nov mb r 19, 1991 90 -01
PIN #: 24- 117 - 22 11 0041
RICHARD K. SHAPIRO
710 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 24 -117 -22 11 0042
BENJAMIN A. COHEN
602 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0043
SCOTT STEIN
122 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24-117-22 11 0044
ALVIN R. TILSEN
208 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24-117-22 11 0045
ROBERT &
KAREN RABINOVITZ
216 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0046
DARLA R. KJELDEN
306 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0647
BRUCE M. GOLDSTEIN
312 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0048
GEO NADLER
408 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0049
HERBERT Z. ROSEN
601 OAKRIDGE ROAD
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0050
ERIC BLOCK &
HELLA BUCHHEIM
414 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 110053
D. W. & J. A. JOHNSON
705 VALLEY WAY
HOPKINS, MN 55343
PIN #: 24-117-22 11 0054
MICHAEL &
KATHERINE MURPHY
203 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0055
MICHAEL &
KATHERINE MURPHY
203 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 24- 117 -22 11 0056
RICHARD K. SHAPIRO
710 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0001
RICHARD K. SHAPIRO
710 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #4 13-117-22 44 0002
MICHAEL &
KATHERINE MURPHY
203 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0003
CHARLES D. SIMPSON
301 WILSHIRE WALK
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0004
D. W. & J. A. JOHNSON
705 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0005
HOWARD P. &
ROBERTA J. LISZT
715 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0006
DONALD E. LITIN
302 BRIDLE LANE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0007
OREN J. STEINFELDT
240 BRIDLE LANE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0008
MANUEL O. JAFFE MD
102 BRIDLE LANE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0009
ARNOLD M. SOSKIN
802 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0010
DENNIS P. &
SUSAN B. BRUESEHUFF
810 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0011
ROGER J. &
MARILYN T. HORK
820 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0012
ARTHUR J. HOROWITZ
830 EDGEMOORE DRIVE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0013
JACOB R. GOLDENBERG
210 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0014
ROBERT L. &
LINDA M. BARROWS
821 PARK.TERRACE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0015
HAROLD COTTLE
302 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13 -117 -22 44 0016
NANCY G. SHILLER
825 PARK TERRACE
HOPKINS, MN 55343
List:Nov mb r 19, 1991 90 -01
PIN #: 13- 117 -22 44 0017
PAUL & CARLYN BLUM
815 PARR TERRACE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0018
JACK P. HELMS
805 PARK TERRACE
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0019
A S RESNICK
105 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0020
JUNE BARRON
115 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0021
HENRY RIEL
215 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0022
MARTIN K. &
LAURA W. LIPSHUTZ
225 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0023
SUSAN A. &
CLIFFORD F. LAKE JR
275 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0024
MAXEEN L. VASHRO
315 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0025
SCOTT & LAUREL LIFSON
325 COTTAGE DOWNS
HOPKINS, MN 55343
PAUL A. HIMMELMAN
405 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0026
PIN #: 13-117-22 44 0027
KENNETH D. &
SUSAN D. KAHN
409 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0031
EFROM H. ABRAMSON
711 OAKRIDGE ROAD
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0032
ALBERT L. WALONICK
715 OAKRIDGE ROAD
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0033
STANFORD A. &
JOAN S. WEINER
805 OAKRIDGE ROAD
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0034
R S SHIFF &
N JAFFEE -SHIFF
809 OAKRIDGE ROAD
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0035
ROBERT L. DVORSKY
410 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0036
LOUIS GAINSLEY
428 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0037
JACK SWEET
420 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0038
RANDY L. &
WENDY S. ENGEL
810 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0039
MARION APPLE .
804 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0040
RONALD L. SIMON
716 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0041
NORMAN L. & RUTH D. KAHN
712 VALLEY WAY
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0045
BILL KEENAN
c/o BT INVESTORS
1055 B. WAYZATA BLVD
WAYZATA, MN 55391
PIN #: 13-117-22 44 0046
BILL KEENAN
c/o BT INVESTORS
1055 E. WAYZATA BLVD
WAYZATA, MN 55391
PIN #: 13- 117 -22 44 0047
THOMAS R. &
SHERRY W. KELLY
413 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 13- 117 -22 44 0048
DENNIS M. &
PATRICIA M. CURRY
417 COTTAGE DOWNS
HOPKINS, MN 55343
PIN #: 19- 117 -21 22 0035
RICHARD NESLUND
15500 WAYZATA BLVD
WAYZATA, MN. 55391
PIN #: 19- 117 -21 22 0036
CHEYENNE LAND COMPANY
15500 WAYZATA BLVD
WAYZATA, MN 55391
PIN #: 13- 117 -22 44 0043
THE KNOLLWOOD ASSOC.
821 PARK TERRACE
HOPKINS, MN 55343
*0 • 107
63
0 3
(2
6e 4.19
s COTTAGE
(45)
*81.50
(10)
*70.2
ZEE .,
Sig
M■1
74
195
8 ' fi
f
1
4
(40)
u . � ..� . 1 .o�.J1'u..:, � •-' ? bt °_� (48) lay! v'(56)
PARCELS NOTIFIED FOR PUBLIC HEARING
—54—ATE-44-r— - eye --�-
„61'5 .
19.72 • •
RO 667* ACRES
„., 1 (
27
'/ (64) 1 (63) = 9 (62) (6))
107.55 -
ER
2
,n 23
EAST ( 60)
AS (60)
22
( 59)
(58)
8
O
LJ'
Pt
(27)
(104 -109
11
(40-45)
(24-31)
NOVE 236.3
(118.121 (122-129
72 73
LO 2AW
(110-117
1
*4.29 _ _
KNOLLWOOD NEIGHBORHOOD
� RIK
ASSOCIATES, LTD.
STREET AND UTILITY RECONSTRUCTION
PLANNING AND ENGINEERING
FEASIBILITY REPORT
November 11, 1991
Revised - November 15, 1991
PREPARED FOR:
THE CITY OF HOPKINS
AND
THE RESIDENTS OF KNOLLWOOD
PREPARED BY:
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153 ,
RIK
411 ASSOCIATES LTD.
November 15, 1991
Honorable Mayor and City Council
City of Hopkins
1010 South First Street
Hopkins, MN 55343
Re: Feasibility Study - Knollwood Neighborhood;
Street and Utility Reconstruction
Enclosed is the planning and engineering report regarding the feasibility
study for street and utility reconstruction in the Knollwood Neighborhood.
This report includes information from the original TKDA report dated January
11, 1990, updated information from City staff, RLK evaluation of the data and
site conditions, and input from the residents of the Knollwood neighborhood.
The intent of this report is to explore options for the reconstruction of the
Knollwood streets and utility infrastructure based upon the petition submitted
by the neighborhood August 6, 1991 requesting street, storm sewer, water main
and sanitary sewer reconstruction. The petition requested construction of a
minimum width roadway with asphalt curb vs. the city -wide standard of concrete
curb and gutter.
Discussion on the scope of the project was held with the neighborhood design
committee on October 8, 1991, and the Knollwood residents on October 28, 1991.
Their comments are attached in the form of minutes and a list of attendees is
included. A questionnaire was handed out to all of the residents by the
Knollwood Association. Most of the questionnaires were returned (attached in
the appendix). Information directly from the residents articulating their
concerns and needs are extremely valuable. Additional meetings will be
necessary with the neighborhood to finalize design options, roadway alignment,
roadway width and edge control. It is a principal goal to continue the high
level of communications between the neighborhood residents, the City staff,
and the consultant throughout the duration of this project.
The tables and figures included with this report provide a visual description
of a series of alternatives which have been explored on the Knollwood street
design options. The neighborhood residents have been supplied with copies of
this report for their review. We realize recommendations within this report
will be used as the basis for discussion as to what the final design of the
street will eventually represent. Our goal has been to collect, analyze,
interpret and report on the design data needed by the City Council, City staff
and Knollwood residents to evaluate the project. We believe this report
accomplishes that goal.
• Civil Engineering • Transportation • Infrastructure Redevelopment
• Landscape Architecture • Construction Management
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 - 1153)
Honorable Mayor and City Council
November 15, 1991
Page 2
We are pleased to be of service to the City and the Knollwood neighborhood in
the Feasibility phase of the project. It is our hope that the data has been
presented in a clear fashion to allow the necessary discussion on the project
prior to the commencement of the detailed design phase. We will attend the
November 19, 1991 City Council meeting, and subsequent public hearings, to
review the report and discuss the various alternatives included herein.
Sincerely,
RLK ASSOCIATES, LTD.
€'97 Richard L. Koppy, P.E.
President
attachments
dk :Feasstdy.Knl \WS
WS /HOPKINS /KNOLL /FEASSTDY KNL
I hereby certify that this report was prepared by me or under my
direct supervision and that I am a duly Registered Professional
En•ineer under t e laws of the State of Minnesota.
11 411
.6. . /• � � L :L .
Paul Kroehnert, P.E.
KNOLLWOOD STREET
RECONSTRUCTION
PROJECT
Reg. No.
ti./ rim
Date
I hereby certify that this report was prepared by me or under my
direct supervision and that I am a duly Registered Professional
Landscape Architect under the laws of the State of Minnesota.
/97 11
John Dietrich, ASLA Reg. No. Date
I hereby certify that this report was prepared by me or under my
direct supervision and that I am a duly Registered Professional
Engi er under the laws of the State of Minnesota.
Richard L. Koppy, P E. Reg. No. 11083 ate
TABLE OF CONTENTS
PLANNING AND ENGINEERING FEASIBILITY STUDY
REPORT SECTIONS
PAGE
Executive Summary
Project Schedule
Summary of Estimated Project Costs & Assessment Data
Planning and Engineering Feasibility Report
Project Location 1
Study Objective 1
Mission Statement 1
History 3
Planning and Engineering for the Knollwood Project 4
Right of Way /Easements 4
Utilities 5
Storm Sewer System Serving Area 5
Sanitary Sewer Reconstruction 13
Watermain System Reconstruction 21
Private Utilities 22
Street Analysis 24
Alleyway (Public Drive) 34
Miscellaneous Design Items 37
Landscaping and Retaining Walls 37
Street Lighting 40
Coordination with the City of St. Louis Park 40
Traffic Problems, Vehicular and Pedestrian 42
Construction Schedules and Phasing 43
Permits for Construction 45
Financing 45
Statement of Project Feasibility 47
TABLES AND FIGURES
Figure 1 Location Map 2
Figure 2 Tree Removal and Parking Areas 6
Figure 3 Existing Storm Sewer 7
Figure 4 Sedimentation Basin Detail 9
Figure 5 Typical Castings Detail 10
Figure 6 Alternate A - Bituminous Curb 12
Figure 7 Proposed Storm Sewer 14
Figure 8 Proposed Storm Sewer with Underdrains 15
Figure 9 Existing Sanitary Sewer and Water Main 16
Figure 10 Sanitary Sewer - Alternate Routes 18
Figure 11 Proposed Sanitary Sewer 20
Figure 12 Proposed Water Main 23
Figure 13 Typical Section - Alternate B 28
Figure 14 B618 Concrete Curb and Gutter Detail 29
Figure 15 Typical Section - Alternates C and D 30
Figure 16 Mountable Concrete Curb and Gutter Detail 31
Figure 17 Typical Section Alternate E 32
Figure 18 Typical Section - Alternate F 33
Figure 19 Alley Detail 35
Figure 20 Tree Loss Impact 39
Figure 21 Alternative Street Lighting 41
Figure 22 Construction Phasing 44
Figure 23 Sample Assessment 48
Figure 24 Driveway Openings 49
EXEMTIVE SUMMARY
Planning and Engineering Feasibility Report
Study Objective: Enhancement of a residential neighborhood to the extent that
the residents are comfortable and satisfied to be residing in their local
environment. At the same time, providing an infrastructure and physical
improvement plan that relates to the City's general physical plant allowing
public services to be performed effectively, efficiently and at a cost that is
equitable with other neighborhoods throughout the City.
Recommendation: Based on this study, the Knollwood Street and Utility
reconstruction is feasible and the resulting benefit will equal or exceed the
proposed assessments to the abutting properties.
It is therefore recommended that the Hopkins City Council proceed with the
project as suggested in the Project Schedule. It is recommended the final
assessment hearing be held for the first segment prior to awarding a contract
as shown on the proposed Project Schedule.
Proiect Cost: The overall project cost for the Knollwood street and utility
reconstruction is estimated to be $833,791. This estimate includes the
construction cost, overhead and consultant fees. A preliminary assessment
roll is included with the report. It has been prepared based upon Policy #7-
D.
Content of Feasibility Report:
Right of way/easements Recommendations
Obtain drainage and utility easement for ponds and all utility lines
Obtain easements for roadway to allow the street to be maintained in its
general alignment. Easements would have to be granted by property owner
prior to construction with costs of right of way to offset assessment
costs.
Storm Sewer Recommendations
Reconstruct storm sewer system as shown on Figure 7 including
sedimentation basins within the ponds in order to improve water quality.
o Include private property drainage areas into overall system.
Outflow of storm water to Minnehaha Creek will not exceed current
levels.
Sanitary Sewer Recommendations
o Reconstruction of approximately 50% of sanitary trunk line as shown on
Figure 11.
o Eliminate sanitary sewer under 602 Edgemoor garage
o Encourage private service reconstruction if the need is appropriate.
o Replace any lines which may need replacement in the next 15 -20 years.
This is being evaluated as part of the sanitary sewer television and
cleaning program that is on -going in the Knollwood neighborhood. A
final report should be available by December 3, 1991.
Water Main Recommendation
o Replace approximately 3,400 lineal feet of cast iron pipe with ductile
iron pipe as shown on Figure 12.
o Complete two dead end watermains with loop routes
o Encourage private service reconstruction if lead lines exist between
street and house service.
Street Analysis Recommendation
o Maintain general alignment for new roadway
o Street width driving surface 20' with back of edge control at 22' width
as shown on Figure 15.
o Utilize colored concrete mountable curb and gutter for edge control
o Anticipate life expectancy of 35 years
Driveway aprons are not to be installed
o Parking may be restricted on 20' wide streets
o Narrow roadway where significant trees /landscape features are existing.
Reconstruct Edgemoor Drive with concrete curb /gutters on both sides.
o Replace /repair all private utilities during the period of construction.
Alleyway - Unnamed Roadway Recommendation
o Construct in concrete per City policy and assess to benefiting
properties (see Figure 19)
o Option to vacate alleyway and maintain as a private drive
Landscape and Retaining Walls
Maintain rural character of roadway and yard appearance
O Proactive tree services to reduce tree loss
Replacement plant material to be significant in size,
size
It
- 6 " caliper
Provide landscape installation at pond edge, Edgemoor buffer, and
boulevard plantings
Maintain existing walls where possible
Install retaining walls where applicable to protect trees
Tree removal to be kept to a minimum
Enhance buffer area on the east side of Edgemoor Drive
Street Lighting
Provide additional lights where requested
Installation of a new ornamental street lighting system proposed to
consist of 10 lights. See Figure 21 for a sample ornamental light.
Construction Scheduling
Project to begin May 18 and be completed by mid - October 1992
Minimize the inconvenience to residents accessing their property at all
times.
Refer to Figure 22 for a tentative construction phasing.
Phase 1 Initial Feasibility Study
RLK Completion Date
Council orders public hearing
Publish in Sailor
Property Owner Meetings
Public Hearing
Phase II Design
Design Development
Final design, contract document,
specifications
RLK Completion Date
Phase III Bidding
RLK Completion Date
Council approves plans, orders bids
Bid ads in Sailor
Bid Opening
Phase IV Assessments
Council orders assessment hearing
Ad in Sailor
Property owner meetings
Assessment Hearing
Award of Bid
Phase V Construction Engineering
PROJECT SCHEDULE
OCTOBER 28, 1991
KNOLLWOOD NEIGHBORHOOD IMPROVEMENT PROJECT
Construction begins after
road restrictions lifted
November 8, 1991
November 19, 1991
November 20, 27, 1991
October 28, 1991
November 20, 25, 1991
December 3, 1991
November 19, 1991
January 1, 1992
January 1, 1992 thru
February 19, 1992
February 14, 1992
February 27, 1992
February 18, 1992
February 19, 26 and
March 4, 1992
March 11, 1992
March 17, 1992
March 18, 25, 1992
March 16 thru 27, 1992
April 7, 1992
May 12, 1992
May 18, 1992
•
Project Description
Streets (Alternate C)
Storm Sewer
Sanitary Sewer
Watermain
Alternate Items:
Alley south of Cottage Downs
Colored concrete for Curbs
Sprinkler system adjustments
EXPENDITURES AND REVENUE SUMMARY
PROJECT COSTS
Total
Project City
Costs Costs
$483,324
$119,717
$ 90,857
$ 98,020
$ 6,045
$ 34,528
$ 1,300
$144,997
$119,717
$ 90,857
$ 98,020
$ 1,209
_ 0 _
0
Project Total Cost Estimates $833,791 $454,800 $378,991
(includes 10% project contingency, 15% engineering, 5% administration)
PRELIMINARY ASSESSMENT INFORMATION
In accordance with Policy #7 -D
Total Estimated Project Cost: $833,790
Total number of assessable residential lots: 48
Total number of adjusted assessable frontage: $5,922.65
City Cost: $454,800
Property Owner Cost: $378,991
Project Cost (rate per foot) $140
Assessment Rate (without alternates) $57.00 per foot
(with alternates except alley) $63.00 per foot
Special
Assessments
$338,327
- 0 -
- 0
- 0
$ 4,836
$ 34,528
$ 1,300
RLK ASSOCIATES, LTD.
PLANNING AND ENGINEERING FEASIBILITY REPORT
PROJECT BACKGROUND INFORMATION ON THE KNOLLWOOD STREET RECONSTRUCTION PROJECT
PROJECT LOCATION
The project involves the reconstruction of streets and utilities for the
Knollwood neighborhood as identified on Figure 1. The neighborhood is located
in the northeast corner of Hopkins, north of Highway 7 and east of Oak Ridge
Road abutting the Cities of St. Louis Park on the east and Minnetonka on the
north.
STUDY OBJECTIVE
RLK Associates' principal objective is to work with the residents of the
neighborhood and the City officials to accomplish a successful neighborhood
improvement project. We look at this project as a public - private partnership
to improve one sector of the City for all the taxpayers of the City. A low
maintenance area achieved through an improvement project that beautifies and
enhances a particular neighborhood is a benefit to all the members of the
City.
MISSION STATEMENT
A "guiding light" is the mission statement of a resource team as they approach
a unique neighborhood improvement challenge. For the Knollwood Street
Reconstruction Project, the following statement has guided the staff of RLK
Associates. " Enhancement of a residential neighborhood to the extent that
the residents are comfortable and satisfied to be residing in their local
environment. At the same time, providing an infrastructure and physical
improvement plan that relates to the City's general physical plant allowing
public services to be performed effectively, efficiently and at a cost that is
equitable with other neighborhoods throughout the City."
The project involves more than simply the replacement of deteriorated
infrastructure with new infrastructure. It will involve close communication
with residents, City staff and a unique ability of the design team to produce
a quality product tailored to the Knollwood neighborhood. RLK Associates is
committed to tailor a streetscape project for this neighborhood within the
expectations of the City of Hopkins as a whole.
This feasibility study will identify alternatives to the roadway width and
edge control for the Knollwood project. It is our intent to bring new ideas
and a sensitivity to this street reconstruction project so that at the
conclusion of this project, the City and residents of Knollwood will be
satisfied with the function, cost and appearance of the street improvement.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 1
`ASSOCIATES LTD/
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax (612) 933 -1153
LOCATION MAP
RLK ASSOCIATES, LTD.
HISTORY
A considerable amount of history on the Knollwood Street Reconstruction
Project needs to be understood if we are to gain the trust and respect of the
neighborhood. Much of the TKDA material from the previous study dated
January, 1990, was reviewed in preparation of this report. Upon review of the
material in the petition from the residents, a fair amount of the existing
TKDA material can be utilized in the renewed Minnesota Statutes Chapter 429
process.
Ultimately, the roadway width, edge condition, landscape features and plant
material will impact the final design. These items will be reviewed, compared
to the contents of the petition, and factored into the recommendations of the
feasibility report.
The petition submitted by the Knollwood Neighborhood, at the August 6, 1991
City Council meeting is the second request by this neighborhood for a street
reconstruction project. The first petition submitted in December 1989
resulted in the City Council authorizing TKDA to prepare a feasibility study.
TKDA prepared the analysis on the utility and roadway system and prepared
appropriate cost estimates. The project range for the reconstruction cost
this project in 1990 dollars was estimated at $800,000.
During the early months of 1990 public hearings were held on the street
reconstruction; however, a number of issues regarding roadway width and use of
concrete curb and gutter were not acceptable to the neighborhood. The City's
roadway policy was in conflict with what the neighborhood desired as a final
product, therefore, the first petition for roadway construction did not
proceed beyond the feasibility report.
The new petition submitted at the August 6, 1991 City Council meeting by the
Knollwood neighborhood specifically requests the following:
Continuous asphalt raised edge curb and gutter in lieu of concrete curb and
gutter
o Greater than 55% of all property owners' signatures were achieved (26
total). This was in accordance with City Policy #7 -D.
o Design modifications to address actual drainage and maintenance concerns
were requested.
o Unobtrusive and flat - laying gutters (non-raised) to collect storm water
for drainage into the underground storm sewer system were requested.
o Asphalt paving with center draining was requested for the alley serving
the three properties south of Cottage Downs.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 3
RLK ASSOCIATES, LTD.
Street Width - 20 feet overall (back to back of raised asphalt edge)
Streets currently 20 feet or greater in width shall be reconstructed to
those same respective widths Streets currently less than 20 feet in
width shall be reconstructed to 20 feet in width unless existing and /or
adverse conditions are present and the City council approves a width
narrower than 20 feet.
The residents understand that streets less than 26 feet in width may be
subject to parking restrictions on an "as needed" basis at the time of
construction or in the future, if needed.
City staff will review streets for emergency vehicle needs and will
report to City Council with recommendations.
o City staff will work with neighborhood to identify areas and appropriate
justifications where street width may be increased to provide
unrestricted parking (26 feet maximum width).
The City roadway policy allows for the above petitioned items. However, at
issue is the City's desire to install a project which will be properly
engineered and provide a 30+ year life expectancy. Without proper edge
control, a bituminous roadway mat in a neighborhood such as Knollwood will not
endure for 30+ years without significant maintenance expenditures.
At issue with the neighborhood is maintaining a "rural" character of the
roadway as it presently exists, the absence of the white ribbon of concrete
curb and gutter, irregularity of the roadway, and mature trees within the
street right of way. The petition submitted by the Knollwood neighborhood
identifies the critical issues which are to be incorporated into the street
and utility reconstruction. The "rural" passive character in Knollwood is
noticeable and offers its residents a quality neighborhood environment.
A street reconstruction project should enhance the infrastructure without
negating the visual appearance of the neighborhood. At the same time, the
infrastructure and physical conditions should relate to the City's general
physical plant, allowing public services to be performed effectively,
efficiently and at a cost that is equitable with other neighborhoods
throughout the City. RLK Associates feels this should be the overall goal
guiding this improvement project.
PLANNING AND ENGINEERING FOR THE KNOLLWOOD PROJECT
RIGHT OF WAY /EASEMENTS
The pond at Wilshire and Valley Way is privately owned while the pond at
Bridle Lane and Valley way is owned by the Knollwood neighborhood association.
Neither pond is proposed to be owned by the city. Drainage and maintenance
easements should be obtained for the two ponds proposed to be utilized for
storm water ponding.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 4
RLK ASSOCIATES, LTD.
Additionally, there are other easements necessary for the utilities that exist
within the Knollwood reconstruction area. Several segments of utility pipe is
located on private property. In one case, the sanitary sewer appears to be
aligned under the footing for a building structure. These utilities have
served the neighborhood in these locations since the origin of the
subdivision. During the detailed design process with the property owners
involved in the process, these easement requirements will be determined to a
more specific degree.
The existing street right of way is generally 40 feet in width. There are
several locations where the street was not constructed on the right of way.
Temporary or permanent construction easements may be required. An option to
discuss is whether the street should be moved to the center of the existing
right of way during this construction project. If this is done, a minimal
number of easements and /or property acquisition will be necessary. However,
by moving the street into the center of the right of way, approximately 4
trees will have to be removed. If the street is generally left in its present
alignment, these same trees can be saved. Figure 2 shows the location of the
trees that will have to be removed if the street is centered on the right of
way; easements will be necessary to eliminate the tree loss.
Given the large size of the Knollwood lots, it is recommended that the street
be left in its general location and new easements and /or property acquisition
be commenced to accommodate this alignment. Within this report, our estimates
of impact have been made under the assumption this recommendation will be
acceptable to the Knollwood property owners.
In order to control the construction costs on this project, and keep the
assessments within a reasonable range, it is not anticipated any funds will be
available to purchase property or easement rights. If this is necessary, the
cost of acquisition is recommended to be applied to the assessable part of the
reconstruction project costs. The appropriate assessment proportion contained
in Policy #7 -D would then be applied.
During the course of the Knollwood Reconstruction project, it is recommended
that all cases of the need for easements /property acquisition be considered
and appropriate action be taken.
UTILITIES
Story Sewer System Serving Area
The existing internal storm sewer system for the Knollwood area is minimal.
Figure 3 demonstrates the storm sewer utility. The two pond areas collect
greater than 80% of storm runoff from the neighborhood, and eventually the
discharge is directed along Bridle Lane to the 15" storm sewer line, lying
directly east of Edgemoor Avenue. This 15" pipe outlets just south of the
Hopkins - St. Louis Park city line and discharges into a ditch running
easterly then southeast into a 15" RCP which runs south under Highway 7 and
connects to a 30" RCP that runs east towards Highway 169 and then to Minnehaha
Creek.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 5
0
cc
STATE
CITY OF MINNETONKA
922 Mainstreet
Hopkins. Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
LEGEND
KNOLLWOOD STREET RECONSTRUCTION
TREE REMOVAL
AND
PARKING AREAS
SUGGESTED PARKING BAY AREA
TREE TO BE REMOVED
TREE TO BE REMOVED
F EASEMENTS ARE NOT OBTAINED
FIGURE_ 2
O
cc
Q
cc
`ASSOCIATES LTD/
CITY OF MINNETONKA
(612) 933-0972
fax: (612) 933-1153
922 Mainstreet
Hopkins, Mn.
55343
KNOLLWOOD STREET RECONSTRUCTION
EXISTING STORM SEWER
FIGURE 3
RLK ASSOCIATES, LTD.
An area in the northwest corner of the development west of the alley at 410
Cottage Downs drains into an existing 12" pipe running west to Oakridge Road.
The existing pipe in Oakridge Road flows north to the Minnetonka city system.
The northeast drainage system of the neighborhood consists of a 12" pipe
running from the east side of the lot at 215 Cottage Downs, west to Valley
Way, then south along Valley Way to the Bridle Lane pond. Approximately 60%
of the existing storm sewer system is proposed to be utilized with the new
street system. The northeast drainage system, described above within Cottage
Drive, will be re- utilized. A portion of the Bridle Lane- Edgemoor Drive
system will be used, but the majority of this system will be reconstructed.
Recommendation: The public and private drainage areas will be incorporated
into a new storm sewer system, utilizing new catch basins, piping and storage
capacity in the two ponds. Anew outlet to control the high water level of
the Bridle Lane pond will stabilize the entire storm drainage system.
Discharge of the storm water into the Highway 169 /Minnehaha watershed will not
exceed pre - development levels.
Water Quality: Water clarity in the Wilshire Walk pond appeared good during
a late October 1991 observation, but the clarity was very turbid in the Bridle
Lane pond . It may be advisable to provide a small sedimentation area by
means of a riprap dike and overflow weir in the southwest corner of the Bridle
Lane pond around the inlet from the Wilshire pond. Cost for a sedimentation
basin similar to the concept plan shown on Figure 4 is approximately $3,000.
An observer of the pond would not notice the sedimentation basin since it
would be under the water surface. However, the construction of this basin
would considerably aid the City personnel in maintaining the water quality,
reducing and removing sediments in the pond. Future dredging activities would
be limited to the basin area. The cost of this component of the storm sewer
system would be paid for through the City's Storm Sewer Fund. A further
analysis of the pond's depth and storage capacity will be investigated in
later design stages. If it is found the ponds need to be dredged for storm
water management, the cost will be paid for from the appropriate fund. If,
however, the pond is to be dredged for aesthetic reasons, the cost would be
paid for by the homeowners association.
Water quality data in the 1990 RCM Storm Water plan will be evaluated and the
ponds analyzed according to National Urban Runoff Program (NURP) methods as
developed by the United States Environmental Protection Agency. The existing
pond depths need to be determined and the possible need for dredging to obtain
a quality of outflow water from the Bridle Lane pond. Dredging of the ponds
could be accomplished at the time of the street reconstruction. The last time
the ponds were cleaned out was approximately 20 years ago. The ponds will be
utilized as an integral part of the Knollwood storm sewer system. It is
proposed that all storm sewer improvements will utilize sedimentation controls
at the outfall structures as shown on Figure 4.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 8
OUTLET PIPE
RLK
\ASSOCIATES LTD.
y
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
10' -15' MAX.
CLASS IV RIPRAP
NORMAL WATER LEVE
';•� 2 .�,.• J: •:., . � 2
_ • - 0 Air) cP o �� � ° •
t Q o. :� o Qfl o� • 0 • •
SEDIMENTATION
BASIN
DETAIL
FIGURE 4
No. A 8 • G H
i Type . lbs.
R-4370-1 a?,
� .V.t.!A:1: .
Y•` !LV.. }• : S- :• :'i
::+::
1. A: •'�"•'• " " ?� _7
l' a
r y � ' � V
:V'•T W }'`i:
' 3iTli. • .•: ?
t :t ,
Yak 1!1 \!J' V ?.6�•.�r .V
ti.'`.(S ?i.•f. V: ii.7RV.
:'' ?i'?
C
.!.11]N. •• •t
?•:�!.!,X,! : ,�7,•�,!i: �•J :?
.::,,_�: >_:!:
' .
7
�ti:
.
� : ��? ' ? \ ' S � l :!:!.!.1
' : - { • ? . fir •: {•:
1::,::i 7 i' I,i
• • �. T17 S:•: '•::::•:Y•,.'T,.'TF.�.•�:•:.
y([ ' S'v
,l l M I11171::1!I I Il t: C:: �.:::
:•. .!.� � ::
t }.1.�! y :,
x1,111 11111:111 1111 i l : t tl:::l:
f's t
:::•::• :: �!� • ?�'.•. • JJ:
!; : ? i ! : •• ':
!SI: :,:•':: :y.:v ::
C
.
.�' 11
: ::YY
•v:
7 6
„ %,,,: ;,;,, : ,,,
• L4370-9 22
Itz
'f M' !. ••,.,
•
: ' t., ?.? ok':a,
^.• :.T.:. ^ : . J A?'e S ... .1 :
J 5� :. X . ? ?!'?•
• •. :J t .Lti •:.V
:: :7K } :•• • v. ?..R.ti`:ii* ' :: :•:
• } • • L4•••: ;, •.. (J
.:• • } : ?• } }S' !: _'tt } '�X T � t 1 ? ? ? : ' '`i �•XJ :,
.VJ: •; y� ....
S' 4'•Y? •'? :! :! :?
. •.... .1: 1:,•: •:.
? :. \� :,y�yy?{S�1'!J : :•
• .:Y
•. yy��
: {• ?x•"1
.:141)$$:::
.,!TRT
•• ?O,' }R, /t�4: iii ii:?1''TYf� :ti ? :: : ' :: :•:
S::::::::::::::.:::.
y ,
:?•• . 1.
T :�• • : 7f A'lA • •, i ,,� JS . :•:KV:•: ?: Y:
• :?' :• :•Y• : : :: ! : : :• :tit' :�. J.. :
:�
:` : : ?• :• :• :• :• :'J :.SS..
:+:41÷:c•-*
is:(:10:1:4*1
? : : :. ...
:;:
J } : :: ..�; : }:+ ;: ? . fi r ? ,�• 1 :4 1••r
:
;
R- 3250 -CL Curb Inlet Frame, Grate, Curb Box
Heavy Duty Total Weight 500 Pounds
R- 3250 -BL
- 3250.81. CURB FACE
R- 3230.0 CURB FACE
221. a1—
38
Heavy Duty
Total Weight 385 Pounds
26
i �7H -1
y i
si
221
26
274
38
• — ► M--_ _>_. G
Same as above except furnished
with tapered face curb box.
(see drawing below).
1
2 21
R- 3501 -TR inlet for Roll Type Curb
23i
—5a 9-
R-4370 Series Heavy Duty Round
Drainage Grates
most crates listed can be furnished with iigntweicht cost iron
ar.cie frames wren specified. Frame is of 1/2. metal as shown
on Dace 2 For severe - impacted locoing conditions,
inouire about *nese grates in Ductile Iron.
31
25
29 0
Not recommenoeo for bicycle traffic. For safety stanaaras see pages 88
ro93.
Rated as Medium Duty Heavy Duty.
•
Type C
J:::• �1� : :• :? Ji: ? �! : ! 1 :. : : � : ? :•i: ?•Ill j?
.......... :..r.
V::.J•i•
Illustrating R- 3250 -CL
IMPORTANT_Rerr;,e coo screws from taro box when
concrete curd ^cs set
Illustrating R- 3501 -TR (flow rient). If
flow left is required, order as R- 3501 -TL.
en 7
C -J
ASSOCIATES LTD• J
922 Mainstreet
Hopkins. Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
TYPICAL CASTINGS
DETAIL
FIGURE 5
RLK ASSOCIATES, LTD.
Catch Basin Design: Neighborhood residents expressed a desire to have catch
basins that were nearly invisible to the people passing through on the streets
of Knollwood, either by motor vehicle or as a pedestrian. The design of the
catch basin is a function of the edge control that is used on the project.
Figure 5 demonstrates the style of catch basins that would be used dependent
upon the type of edge control. Later in the report, in the edge control
section, the types of catch basins that have been considered will be briefly
described. The quantity of runoff that can be handled by the different types
of catch basins is not a significant decision factor.
Private Property Drainage Areas: At the October 28th neighborhood meeting,
the property owners were requested to review their experience with drainage
problems on their private yards and communicate the problems to RLK
Associates. This information with the survey data from the questionnaires is
included on a chart that is contained in the appendix. Additionally, several
problems were passed onto RLK from the past consultant thru their review of
the project. This data is also included on the chart in the appendix. These
problem areas will be identified and studied further during the detailed
design phase of the project.
Open Drainage Ditch
Between 810 and 820 Edgemoor Drive a culvert is proposed to collect water at
this low area. A drainage ditch is proposed to run parallel with Edgemoor
Drive toward the intersection of Bridle Lane where it will be collected into
the storm sewer system. Location of the ditch will be aligned to avoid
disruption to the mature trees. All ditch areas will be reseeded and re-
established in a natural grass character.
Perforated Underdrains /Bituminous Curb Alternate: If the bituminous curb
alternate is chosen, it is recommended that perforated underdrains at least
100 feet each way from the street low points be constructed. This would
provide maximum subsoil drainage along the pavement edge, and help to prevent
early pavement edge deterioration and breakup. Figure 6 demonstrates the
characteristics of the underdrains that are connected to the storm sewer catch
basins. It should be noted that Braun Engineering Company, who did the soil
borings for the neighborhood project in 1989, made the original recommendation
for the underdrains in a report dated March 2, 1990. It was based upon soil
types, groundwater conditions, and pavement drainage characteristics.
The bituminous pavement edge is the most vulnerable component of the street
product as evaluated over a long period of time. Addition of the underdrains
helps to assure a longer life for this type of edge control. The additional
cost for underdrains is $46,800.
Recommendation: The public and private drainage areas will be incorporated
into the new storm sewer system, utilizing new catch basins, piping and
storage capacity in the two ponds. A new storm sewer is needed to connect the
two ponds and connection to the storm sewer east of Edgemoor Avenue. A new
outlet to control the high water level of the Bridle Lane pond will stabilize
the entire storm drainage system. Discharge of the storm water into the
Highway 169 /Minnehaha Creek Watershed basin will not exceed current drainage
outflow levels.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 11
6" CLASS 5
12" SELECT
GRANULAR
BACKFILL
NOTES:
1. SELECT GRANULAR BACKFILL MODIFIED
TO 7% PASSING NO. 200
2. SELECT GRANULAR & PERFORATED
UNDERDRAINS TO BE USED AT LEAST
100 FEET EACH WAY FROM ROADWAY
LOW POINTS
ASSOCIATES LTD
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
10' TO CENTERLINE
1-1/2" 41 BIT. WEAR
2" 31 BIT. BASE
6" MIN.
12"
12" MIN.
r ALTERNATE A
BITUMINOUS CURB
III
4" BIT. CURB
SHOE FORMED
FINE FILTER
AGG.
4" TP PERF.
PIPE W/
GEOTEXTILE
WRAP
2" MIN. FILTER
AT ALL POINTS
BELOW PIPE
FIGURE 6
RLK ASSOCIATES, LTD.
Recommendation (continued)
It is recommended that sedimentation basins be incorporated into the
stormwater system at each outfall point in the ponds, two are recommended.
Figure 7 graphically demonstrates the proposed reconstruction plan. Positive
drainage improvement throughout the Knollwood neighborhood area will result
with the implementation of this drainage plan.
Water quality in the neighborhood ponds will be enhanced subsequent to the
construction project. Limited dredging of both ponds will be bid as an
alternate in the construction package. During the detailed design process,
further interaction with the neighborhood will lead to clarification of the
design details relating to these water quality issues. Ultimately,
reconstruction of any component of the storm sewer system will be in
accordance with the state guidelines of water quality protection. At the
request of the neighborhood representatives, no aerators or fountains will be
bid or included at this time.
The storm sewer reconstruction proposal is estimated at $119,717, including
overhead. This includes the sedimentation basins, dredging estimates, storm
sewer manholes, and storm sewer pipes. The perforated underdrains, -shown in
the storm sewer system on Figure 8, have not been added to this estimate.
They are only recommended if the bituminous curb alternate is chosen. This
will be discussed more thoroughly later in the report.
Sanitary Sewer Reconstruction
The existing sanitary sewer main system consists primarily of 8" VCP, 3 foot
sections installed 35 -40 years ago. Throughout the years, various sections
have been replaced by the Public Works Department. Figure 9 displays
graphically the existing layout of the sewer system. Much of the system is in
fair to poor condition with cracked pipe, offset joints, roots in joints,
mineral deposits, sags in pipe, etc. The sewer system was televised in 1989
and due to the pipe's condition TV cameras could not be pulled through the
pipe in some locations. A chart was prepared based upon past television logs
and cleaning data. It is included within the appendix to this report.
It would be advisable to replace any pipe which has the potential to cause
serious periodic maintenance problems or require spot replacement involving
street excavation within the next 15 to 20 years. The last televising of the
sanitary sewer system was done in 1987. The City decided to complete another
TV evaluation of the sewer system in the fall of 1991. Replacement
recommendations will be reviewed when the City completes re- televising of the
system which is currently ongoing. The sewer televising and evaluation report
(a new chart will be prepared) is expected to be complete by the end of
November, 1991. A recommendation on the refurbishment of the sanitary sewer
system will be available prior to the public hearing on the Knollwood
Reconstruction project.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 13
cc
STATE
CITY CF MINNETONKA
•
•
KNOLLWOOD STREET RECONSTRUCTION
EXISTPIG STORM SEWER
PROPOSED STORM SEWER
RIX
ASSOCIATES LTD
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
PROPOSED STORM SEWER
FIGURE 7
STATE HWY.
NO. 7
KNOLLWOOD STREET RECONSTRUCTION
}>-- -- EOSTNG STORM SEWER
PROPOSED STORM SEWER
4 PERFORATED PVC UNDERDRAINS
SELECT GRANULAR BORROW
RIX
�ASSOCSATES LTD./
922 Mainstreet
Hopkins, Mn.
55343
(612) 933-0972
fax: (612) 933 -1153
PROPOSED STORM SEWER
WITH UNDERDRAINS
FIGURE 8
STATE
ASSOCIATES LTD J
922 Mainstreet
Hopkins. Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
LEGEND
—t
KNOLLWOOD STREET RECONSTRUCTION
t EXISTING WATER MAIN
EXISTING SANITARY SEWER
AND WATER MAIN
EXISTING SANITARY SEWER
FIGURE 9
RLK ASSOCIATES, LTD.
The existing pipe diameter of 8" is sufficient to provide adequate capacity
for existing and future flows. There are no plans pending to increase the
number of homes within the neighborhood, or in upstream areas flowing through
the area such as the Oak Ridge Country Club golf course. Scheduling and
staging of the sanitary sewer work is critical with respect to other elements
of the project, especially the water main. Construction will be done in
stages as set forth in the plans and specifications to minimize service
disruption and maintain street access to residences.
Private service renovation: During the neighborhood meetings, residents
expressed concern over several unique sewer service problems. These problems
and others that have been ascertained from different sources will be reviewed
during the detailed design phase to assure the private service problems are
corrected during the reconstruction project. Funds that are expended for work
on the private services are assessable directly to the benefiting properties.
The sanitary sewer estimates account for 20 or about 1/2 of the service wyes
to be replaced and reconnected to the existing service pipes. At least three
residences have a history of sewer back -up problems. At 122 Wilshire Walk,
where there is no basement, it has been reported that the shower stall back-
ups repeatedly. At 413 Cottage Downs back -ups have been reported. Later in
this section, discussion will focus on 602 Edgemoor Drive. The service all
the way up to the house may have to be replaced as part of the project.
Additional problems may be uncovered as a result of the communications with
the residents. Each of the problem areas will be examined closely.
Wilshire Walk Sanitary Sewer: Figure 9 shows the sanitary sewer layout on
Wilshire Walk from Oakridge Road to Edgemoor Drive. An item of particular
concern is the eight inch sewer from the east end of the Wilshire Walk cul -de-
sac to Edgemoor Drive. There are four significant problems with this 484 foot
length of pipe.
1) The pipe is located under an attached garage at 602 Edgemoor Drive.
2) There are no records of an easement for this pipe. Since it is
undesirable to have an active sewer under a building, it may be
difficult to gain an easement for the operation of the sewer in this
location.
3) The pipe length of 484 feet between manholes exceeds that which is
considered good practice for sewer maintenance cleaning.
4) This segment of pipe appears to be in poor condition based upon
television inspections. Major repair or replacement seems to be
evident. The property owner has reported that his service pipe backs up
occasionally during discharge of laundry washwater. This could be
caused by the poor condition of the main or the service connection.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 17
BRIDLE LANE
ALTERNATIVE SANITARY SEWER ROUTE LOCATIONS ARE
PROPOSED TO ELIMINATE THE SEWER LINE RUNNING
UNDERNEATH THE GARAGE AT 602 EDGEMOOR
ASSOCIATES LTD.,
922 Mainstreet
Hopkins. Mn.
55343
(612) 933
fax: (612) 933 -1153
SANITARY SEWER
ALTERNATE ROUTES
FIGURE 10
RLK ASSOCIATES, LTD.
Solutions involve cleaning the existing pipe, lining the sewer pipe with
plastic, or relocating the sewer pipe outside of the existing location. If
this is done, the existing pipe would be abandoned in place. The service pipe
for 602 Edgemoor Drive will have to be examined carefully to see what the
recommendations are for the private connection to the new pipe.
If relocation is adopted, a new route must be reviewed. During the
feasibility study process, three possible relocation routes were examined.
These three routes are shown on Figure 10. For discussion purposes, the
routes are lettered A, B, and C. Route A and B are undesirable because they
would cause a considerable impact to the adjacent property in the way of tree
and shrubbery loss. Route A, running to the east to Edgemoor Drive, passes
through a wooded knoll requiring trench depths up to 14 feet and removal of
several trees of trunk diameters greater than 4 inches.
Route B, running south toward Highway 7 than east to the sewer line in
Edgemoor Drive, passes closely between the residences at 122 and 208 Wilshire
with less than 40 feet of clearance between the houses. This route also
requires the removal of a number of mature trees and shrubbery. Additionally,
this route would require an estimated 200 feet more piping than the northerly
route.
Route C has its problems but appears to be the most desirable of the three
alternates. By locating the sewer pipe approximately 7 feet east of the west
lot line at 710 Edgemoor Drive, one 18" Oak tree and some shrubbery would be
lost. The Oak tree is immediately east of a power pole and has been severely
trimmed, presumably by the power company for power line clearance. The cost
estimate for route C is $8,700, including the replacement of the landscaping
with new material. No costs are allocated for the easement rights that would
be requested by the City prior to commencing construction on this alignment.
During the detailed design process, these alternates would be thoroughly
discussed with the neighborhood residents that are effected.
If a plastic liner were placed in the sanitary sewer line between the Wilshire
Walk cul -de -sac and Edgemoor Drive, the cost estimate is $28,000. This
estimate of cost includes leaving the sewer line in place, under the
structure, and placing the plastic liner.
Recommendation: Figure 11 describes the recommended renovation program for
sanitary sewer. Please remember that this recommendation will be augmented by
the Fall, 1991 sanitary sewer cleaning and televising program. It is
recommended to 1) replace the 8" sanitary sewer main and manholes which RLK
anticipates needing repair within 15 -20 years; 2) coordinate sanitary repair
with water main /storm sewer trenching and replacement; 3) construct the
alternate shown on Figure 10, route C to eliminate the sewer pipe under home
at 602 Edgemoor Drive. Route C alternative pipe location will necessitate
property owner agreement and utility easements for the underground pipe
location. Current estimate is that 50% of the sanitary sewer main line will
be reconstructed at a cost of $90,900. In the appendix is a detailed cost
estimate on this utility reconstruction proposal.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 19
CITY OF MINNETONKA
STATE
--i— -1 EXISTING WATER MAIN
EXISTING SANITARY SEWER
REPLACE EXIST. SANITARY SEWER
LIE SAN. w (ALT. A)
\U\\ \\ \ \ \ \\
KNOLLWOOD STREET RECONSTRUCTION
ASSOCIATES LTD..
922 Mainstreet
Hopkins, Mn.
55343
(612) 933-0972
fax: (612) 933 -1153
PROPOSED SANITARY SEWER
FIGURE 11
RLK ASSOCIATES, LTD.
Watermain System Reconstruction
The existing water main, shown on Figure 9, is cast iron with lead joints.
The reconstructed portions of the sanitary sewer system and construction of
new storm sewer in some areas will damage the existing water main joints
through vibration during trenching and compaction operations. In addition,
the existing watermain will interfere with new sanitary or storm pipe in some
areas, making it necessary to relocate and rebuild some water main. It is
proposed to rebuild the existing water main wherever it is adjacent to
sanitary sewer that is proposed for reconstruction or new storm sewer. Where -
ever new watermain is placed, ductile iron pipe (DIP) would be used in
replacement of the Cast Iron Pipe. It may be necessary to do the water -main
work first to make room for relocation of sanitary sewer and new storm sewer.
It is proposed to close a loop on Valley Way by constructing a new 6" DIP
watermain from Bridle Lane to Park Terrace. This improvement will eliminate a
dead -end, potentially stagnant water problem. The. City staff has indicated
there is good water pressure in the Knollwood neighborhood. During the
detailed design procedure, the water and fire departments will be consulted
about the proposed relocation and /or placement of new fire hydrants.
Currently the water main under Wilshire Walk east of Valley Way is a dead end.
If Route C for the sanitary sewer is constructed the water main will be looped
between Wilshire Walk and Bridle Lane. The length for this additional water
main would be 400+ L.F. at a total cost of approximately $7,000. This $7,000
has been included into the water main cost estimate.
Private Services Replacement: The residents were briefed at the October 28th
public meeting about the possibility of lead service water pipes. During the
detailed design portion of the project, further information on the condition,
age, size, type of materials, maintenance problems and location of the private
service line will be investigated. Each resident is responsible for their
service line. There is no better time for review of this infrastructure
component than during the neighborhood utility and street reconstruction
project.
During the public meeting on October 28th, residents commented on the existing
sprinkler systems in the boulevard areas adjacent to the roadways. Prior to
construction the City will send out forms asking individual property owners to
identify whether underground sprinklers are present. According to City
policy, homeowners with underground sprinklers within the public right of way
will be responsible for marking the lines and replacing the system subsequent
to construction. The Construction Manager will oversee the removal of marked
systems to see that minimal damage is done to the private sprinkler
systems.
A second option would be to allow the Construction Manager to coordinate the
replacement of the irrigation systems with the general contractor, and at the
end of the project assess back the irrigation costs to the respective property
owner. By allowing RLK to coordinate the irrigation repairs, the property
owner will be assured of a complete project at the conclusion of the
restoration phase.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 21
RLK ASSOCIATES, LTD.
Recommendation: Figure 12 demonstrates the recommended replacement of
3,800 lineal feet of 6" CIP watermain with DIP. The cost estimate of $99,060
includes items for 20 service connections, ten 6" gate valves and 4 new
hydrants. Allow the Construction Manager to coordinate the reinstallation of
the underground sprinkler and assess the work effort back to the individual
property owners. At the completion of the current sanitary sewer televising
program, the work proposal for the watermain system will be re- evaluated.
Private Utilities
The private utility companies consisting of the gas company -- Minnegasco, the
electrical company -- Northern States Power Company, the telephone company
US West, the cable television company Southwest Cable and any other private
service company working in the Knollwood neighborhood periodically or
regularly will be notified of the pending project upon completion of the
public hearing process. All utility company facilities will have to be
reconstructed if they are in the way of any of the City reconstruction
efforts.
The Minnegasco facilities would be replaced per City memorandum dated February
1, 1990. These locations need to be upgraded with the exact location of the
proposed roadway and utilities during the detailed design process. US West
has buried cable on the west end of Wilshire Way and along the east edge of
the roadway of Edgemoor Drive. These facilities will also be reviewed more
thoroughly as the design proceeds forward.
Apparently the facilities owned by NSP, U.S. West and Cable T.V. exist on
overhead NSP poles serving the individual residences. These three overhead
systems are proposed to be maintained and continued in their present state.
During the detailed design process, the consulting engineer will review the
economic advantage of placing open conduit for the future undergrounding of
the aerial facilities. This decision will be made after consultation with the
utility companies and the neighborhood property owners concerning cost
assessment formulas.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 22
ASSOCIATES LTD.
STATE
CITY OF MINNETONKA
922 Mainstreet
Hopkins. Mn.
55343
(612) 933-0972
fax: (612) 933 -1153
LEGEND
PROPOSED WATER MAIN
KNOLLWOOD STREET RECONSTRUCTION
- EXISTING SANITARY SEWER
REPLACE EXIST. WATER MAN
NEW WATER MAN
FIGURE 12
RLK ASSOCIATES, LTD.
Alignment
STREET' ANALYSIS
It is recommended to center the street on centerline of right of way where
possible. Where necessary to preserve 6" diameter or larger trees or fit
between existing walls and /or narrow right of way such as Edgemoor Avenue, the
street should be aligned accordingly. Figure 2, discussed earlier in the
easement section of this report, locates some of the areas where trees impact
the alignment off the roadway.
As mentioned earlier, the existing street right of way is generally 40 feet in
width. There are several locations where the street was not constructed on
the right of way. By moving the street into the center of the right of way,
approximately 4 trees will have to be removed and up to 15 additional trees
will be severely impacted. If the street is generally left in its present
alignment, some of these same trees can be saved and the potential for tree
loss greatly reduced. Figure 2 shows the location of the trees that will have
to be removed if the street is centered on the right of way; easements will be
necessary to eliminate the tree loss.
This is an issue that demands that the sensitivities of the property owners be
highlighted. Future meetings will focus on the wishes of the effected
property owners. A consensus agreement on the roadway alignment may be
difficult to achieve. Where agreement is not possible, the roadway will be
realigned in the center of the existing right of way.
Edge Control
In order to protect the long term investment of this street reconstruction
project, the use of edge control i.e., concrete curb and gutter is
recommended. The durability and ability to channel storm water, while
basically doubling the life expectancy of the road cannot be ignored. The
visual intrusion of a white concrete edge is RLK's understanding of the
primary reason why concrete curb and gutter is not desired on this project.
New developments in construction of concrete products allows for the
opportunity of a colored concrete curb line, one which would closely match the
bituminous pavement. There are many other color alternates that are available
based upon the desire of the neighborhood. For example, an earthtone brown
concrete could be used instead of a darker concrete. At future public
meetings, this subject will be explored more intensely with the neighborhood.
RLK proposes utilizing a colored concrete curb and gutter for edge control
which will achieve the objectives of the City for long term life of the
roadway, and of the neighborhood for maintaining a consistent visual character
between the roadway and landscaped yards. Therefore, from a visual
perspective, the petition request could essentially be met while alleviating
the City's maintenance concerns about the lack of edge control. The colored
concrete edge control is a more expensive option than standard curb and
gutter; however, the initial investment of an additional $26,500 for colored
concrete should be considered in order to implement an edge control option.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 24
RLK ASSOCIATES, LTD.
The colored concrete is a departure from the City policy #7 -D standard curb
and gutter. The cost of the colored concrete curb over and above the standard
concrete curb will have to be paid for by the entire neighborhood
organization. The additional cost for the colored concrete curb would be less
than the bituminous curb option and still provide the visual esthetics desired
by the neighborhood.
From a visual perspective the color can be appealing depending upon the
audience' viewpoint. Relative to the engineering application, there is not a
loss of strength or function through the use of the colored concrete. The
extra cost is a function of mixing control features to insure the concrete has
the same properties as regular concrete with a consistency and uniformity of
color throughout the mix. Different admixtures are used in the colored
concrete that effect the air entrainment mixture. Therefore, unique mixing
features have to be incorporated in the color concrete mix design to insure
the specifications of strength and durability are met. The Minnesota
Department of Transportation (MnDOT) has used colored concrete recently on
several of its projects. They have developed a specification that has been
transmitted to the consulting engineer. In consultation with MnDOT officials,
there is no doubt that the use of the product will be successful in the
production of colored curb and gutter for the Knollwood neighborhood.
The chart on the following page compares the proposed alternates that are
consistent with City policy #7 -D on a roadway life cycle cost basis. The
issues are life expectancy, guarantee and maintenance burden of a street
reconstruction project without edge control and economics. The entire
reconstruction project is being paid for by an assessment at 70% and city
participation at 30 %. The City needs to be assured that the long term
maintenance of a system such as the petition proposes does not add an
additional maintenance strain on the City versus a standard street
reconstruction project.
Data contained in the chart is consistent with a study that was done by the
City of Minnetonka and published on January 24, 1990 in a report entitled
"Preliminary Life Cycle Cost Analysis -- Urban Street Standard Versus Current
Minnetonka Street Standard ". This report is available in the consulting
engineer's office for the reader's review upon request. The conclusions of
the study indicate that concrete curb and gutter with properly designed storm
sewer have a dramatic effect on savings to the taxpayer in street maintenance
over the life of the street facility. Approximately $193,000 per mile of
street over a 35 year period can be saved in maintenance costs if edge control
is used versus no edge control. The chart that is demonstrated below is based
upon applying these savings in the Knollwood neighborhood to the City of
Hopkins.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 25
RLK ASSOCIATES, LTD.
The Equivalent Uniform Annual Cost (EUAC) is a relative figure which depicts
the average annual cost of constructing and maintaining an element of public
infrastructure over its' useful life. It is typically used to measure the
cost - effectiveness of one alternate versus that of another. The EUAC
calculation factors all the capital costs and maintenance costs elements
together to produce a dollar amount on a per foot basis that is reflective of
the average annual cost to construct and maintain the roadway over its useful
life as a City street.
Overlay
[All costs Capital Annual & Seal Equivalent
on a lineal Life Cost per Charges Coating Uniform Annual
foot basis] Expectancy Lin.Foot Mtce. Charges Costs (EUAC)
26 ft. wide
Bituminous
Roadway w/o
Edge Control
26 ft.wide
Bituminous
Roadway with
Concrete Curb
Edge Control
25 years
35 years
$90 $0.19 $0.45 $5.51
$125 $0.12
$0.29 $4.46
The Knollwood neighborhood has 6640 feet of roadway length. The savings per
year to the City is approximately $7,000 with the street constructed with
edge control versus the street with no edge control. This equates to an
astounding $175,000 savings over the estimated 25 year life of the bituminous
street without edge control.
Analysis of Streets for Reconstruction: Currently the streets within the
study area vary in width from less than 20 feet to over 26 feet in width
without any edge control. The proposed streets are recommended to incorporate
an edge control situation or a series of under drains in order to improve the
long term investment of the residents and city. The petition submitted by the
residents spoke to a bituminous curb edge and a street width of 20 - 26 feet
in width. Fire and police vehicles require an open drive area of at least 20
feet in width. Any street reconstructed with a driving surface of less than
26 feet may have restrictions applied to on- street parking in accordance with
City Policy #7 -D, Section 8.04. In the case of restrictions, parking of
residents and guest vehicles will have to be provided for on the private
property of the individual lots. An option to consider is "parking areas "
built into the roadway at selected locations that can be used for overall
resident on- street parking. Figure 2 identifies 5 suggested areas for an
parking bay.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 26
RLK ASSOCIATES, LTD.
Concrete Driveway Aprons
Concrete driveway aprons are typically included in Hopkins street projects
having concrete curb and gutter. For this project, residents have expressed
objections to concrete aprons for aesthetic reasons, similar to objections to
concrete curb and gutter (see paragraph 6 on the following page under Street
Width discussion). Therefore, concrete aprons have not been included in the
project or the detailed estimates in this report. If the recommendation to
build mountable concrete curb and gutter is chosen, the concrete gutter can be
extended across driveway entrances. This would provide positive drainage, as
well as permitting vehicle traffic to easily enter and exit. For maximum
vehicle ride quality, the 4 inch curb height can be lowered across the
driveway openings. If concrete aprons were included, see Figure 24, the
estimated quantity is 850 square yards, and the total estimated cost is
$19,890.
Street Widths
Six alternatives were reviewed regarding street width and edge control.
Figures are referred to illustrating typical details of the design option.
Effective driving surface width of 20 feet:
Alternate A - 20 foot face of bituminous curb to face of bituminous curb (see
Figure 6)
Alternate B - 20 foot face of B6 -18 concrete curb and gutter to face of
concrete curb and gutter (see Figures 13 and 14)
Alternate C - Mountable concrete curb and gutter, 18 feet edge to edge of
gutter, equivalent to 20 feet of driving surface (see Figures 15 and 16)
Alternate D - Mountable colored concrete curb and gutter, (edge control) 18
feet edge to edge of gutter (see Figures 15 and 16)
Effective driving surface width of 26 feet:
Alternate E - 26 feet face of B6 -18 concrete curb and gutter to face of
concrete curb and gutter (see Figure 17)
Variable surface width from 20 feet to 28 feet:
Alternate F -18 feet edge to edge of gutter (equivalent to 20 feet of driving
surface) to 26 feet edge to edge of gutter (equivalent to 28 feet of driving
and parking surface), Mountable curb and gutter (see Figures 2, 16 and 18)
Refer to appendix for cost estimates for each of the above alternates
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 27
O
N
W CC
W
LLI
0 P-
- V o3 Q W
CC CO MI
CC W
(M w
U
cc
0
N
3z
= Q
>
i 1-a
o Q
Wiz§
Z mJ
4a
Q1 3
8 '4'5
Luz;
▪ mI—.
tl3
m
n i g
0
J
U
tC
tM
Cc
LL
Z
Q in
uJ
co Q
cc
Q
C) H
El. Q
>-
1-
B618
Concrete
Cu. Yds.
L/F Per
Per L/F
Cu. Yd.
0.0582
17.2
T
1
SLOPE 3/4" per ft.
10' TO
SLOPE 3/4" per ft.
.4
A
4
18"
26"
3" R
3" R
1
4 c
NOTE EXPANSION JOINT SPACING 100'
8"
1/2" R
d
4
4
A
1
6
1
13 1/2"
1
ASSOCIATES LTDy
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
B618 CONCRETE
CURB & GUTTER
DETAIL
FIGURE 14
cc
LL.
Mountable
Concrete
Cu. Yds.
L/F per
per L/F
Cu. Yd.
0.0540
18.5
SLOPE 1/4"
PER FOOT
\ LTD
16' w /PARKING LANE
T
7"
1
12"
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
28"
\
\
\
\
• a -A a 4 \ a
•
.R =12"
a .
4 Q \ •
\ a
d v v \
16"
\
\
\
\
NOTE EXPANSION JOINT SPACING 100'
ALTERNATES C & D
MOUNTABLE
CONCRETE CURB &
GUTTER DETAIL
A \ \
f
4"
10 -1/2"
6-1/2"
FIGURE 16
cc
cc
ILI CC
W
U
CC 1- '1
ZCS<
8 65 CO m
M W
mUU
O !
ffi(c
11§
tog
3 j . •
;gig
8>gc2
F- W O � W
o Q
a a
2
m i
m
I
ti
cc
LL
1
ch
cig
RLK ASSOCIATES, LTD.
Recommendation: Due to the low traffic volumes, the physical
characteristics of the street right of way, and the petition submitted by the
residents, RLK proposes the following roadway widths be constructed. A 20
foot driving surface with edge control so that the effective width of the
street will be approximately 22 feet to the back side of the edge control.
The width and edge control would consist of design details consistent with the
characteristics of Figures 15 and 16. The two exceptions are:
1)
At locations where it is necessary to protect significant landscape
features (i.e., plant materials, retaining walls, etc.) the driving
surface be reduced to approximately 18 feet in width and the back to
back of the edge control would be 20 feet in width.
2) At intersections and corners in the roadway wider radiuses are proposed
in order to accommodate the turning movements of the vehicular traffic.
It is further recommended that the colored curb and gutter concept be
implemented in the Knollwood neighborhood The exact specifications relating
to the color of the concrete would be worked out during the detailed design
phase of the project. The overall assessable project costs will be divided on
a 70% private/30% City basis with the exception of the added cost of the
colored concrete edge control. The cost estimate of this recommendation is
$517,900.
Alleyway (Public Drive)
A short publicly maintained section of roadway that is unnamed exists south of
Cottage Downs approximately 100 feet west of Valley Way and is described on
Figure 19. It serves three properties: 410 Cottage Downs, 804, and 810 Valley
Way. City Public Works crews have maintained this roadway over the past
years; maintaining the bituminous surface with patching and seal coating, and
snow plowing the area during the winter months. Additionally, the City picks
up trash and recycling materials from the appropriate containers that are
placed on this roadway, which is in the rear yard area of the residencies.
The petition requested reconstruction of the street with bituminous pavement
and center drainage.
The City recognizes this section of roadway as an "alley". Alleys in City
Policy #7 -D, Section 9. are defined as "...minor roadways which service
parcels of property along the rear property line." Section 9.02 states "an
alley shall be concrete construction. Alley width is generally 10 feet in
residential areas..." The significance of the alley designation involves the
method of construction, as mentioned, and the assessment formula. When the
City reconstructs an alley, 80% of the total project cost will be recovered by
assessing the benefiting property for the cost of the improvement. A later
section of this report specifically discusses assessments with regard to City
Policy #7 -D and the financial impact on the neighborhood property owners.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 34
1
I
\ \ � ' /
\` \
i
; \ - k
/
Av's" •
/
Z
f
co
Lir
cc
LL
cv
c)
Q1 a)
N N
co co
W W
co
RLK ASSOCIATES, LTD.
An interesting finding in the consultant's analysis is that there is not an
existing public right of way throughout the length, or area, of this alley.
Approximately 200 feet X 20 feet of public right of way is shown on the
property description maps. Additional easements or property dedication may
required if this street is to be reconstructed and maintained as a public
"alley
An option for the property owners to consider would be to request a vacation
of the existing public right of way to the effected property owners. Than the
street would be considered a "private driveway" serving the same property
owners. The City policy concerning reconstruction would not apply; the
property owners could agree on reconstructing the driveway as they have
requested in their petition using bituminous materials. Or they could leave
the driveway in its current physical condition and repair it as they decide in
the future. Under this option all maintenance responsibility would be the
burden of the adjacent property owners.
The City may request covenants on the deeds of the three properties during the
vacation process. This would guarantee the right of the three property owners
and their future "assigns" to use the private driveway for access to their
property.
Two reconstruction options have been reviewed by the consultant relative to
this alley way, or unnamed public drive. Option One involves constructing a
6" to 8" concrete pavement according to the City Policy #7 -D.
The following preliminary design notes concern Option One:
1) The design thickness of the concrete pavement will be adequate for heavy
trash collection vehicles and dependent upon the condition of the
subgrade soils. Pavement width would be 10 feet.
2) The 80% special assessment /20% City participation formula are applicable
against all construction costs
3) Additional property easements /right of way may have to be dedicated to
the City to allow continued maintenance of this alleyway as a public
roadway.
4) Other design characteristics include a stabilized, compacted subgrade
base; center "V" type cross - section for the concrete pavement with no
curbs on the edges; and a positive drainage surface so all rear -yard
drainage is allowed to run to Cottage Downs via the alley pavement.
5) The preliminary cost estimate for this option is $6,000. Details on the
cost calculations are contained in the appendix to this report.
Option Two involves construction of the alleyway utilizing bituminous
pavement. Since this option does not conform to Policy #7 -D, if it is to be
used, the alleyway would have to be vacated and made into a private driveway,
as discussed earlier in this section of the report. The following preliminary
design notes concern Option Two:
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 36
RLK ASSOCIATES, LTD.
1) The bituminous pavement thickness would be 2 ", dependent upon the
subgrade soils condition, laid upon a 6" Class 5 gravel base.
2) Whether the 80% private /20% public assessment formula would be in effect
would have to be decided at the assessment hearing. Currently, the City
Policy does not allow bituminous alleyways.
3) Additional easements or right of way would not be needed if the alleyway
is vacated.
4) Other design characteristics include those listed under Option One, item
#4, with this addition: The City would require that garbage and
recycling containers be moved to the public street for Public Works
collection purposes. It would be possible, if desired by the property
owners, to construct a landscaped, screened area along Cottage Downs
where these containers could be stored. Features such as these can be
reviewed more thoroughly through communications with the property owners
during the detailed design phase.
5) The cost estimate for construction of a 12 foot bituminous roadway
through this alleyway is $1,895. Details of this cost estimate
calculation are contained in the appendix to this report.
MISCELLANEOUS DESIGN ITEMS FOR THE KNOLLWOOD
NEIGHBORHOOD IMPROVEMENT
LANDSCAPING AND RETAINING WALLS
The abundance of mature trees, curvilinear roads, ponds, and the architectural
quality of the homes identifies Knollwood as one of the premier neighborhoods
within the southwestern suburban area. The proposed project will focus on the
street and underground utilities, with as much attention as possible given to
the mature tree and landscape features so that the disruption and tree loss
will be held to an absolute minimum. The location of utilities, the impact
trenching will have on the root system and construction necessary for the
roadway will be analyzed.
A number of trees are within the right of way, the road and utility alignment
will be reviewed to save as many trees and landscape features as possible.
RLK cannot guarantee trees will not die as a result of the construction, but
through protective measures prior to and during construction, penalties and
mitigative care by tree care specialists, it is anticipated tree loss will be
reduced and contractors closely monitored. All significant trees proposed to
be removed will have new trees installed in the same proximity; RLK proposes
the replacement trees to be at least 3" to 4" in caliper size.
The landscape estimate includes the cost for the following:
o Retaining walls where necessary to protect trees and /or
significant site elements
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 37
RLK ASSOCIATES, LTD.
Pond Enhancements
The ponds provide a unique character to the neighborhood. It is RLK's
intention to place an emphasis on landscaping the pond's edge with perennial
flowers, shrubbery, and trees. By planting bulbs, such as daffodils, iris and
hardy chrysanthemums a season -long splash of color will be achieved. Shrubs
and trees are to be selectively placed to enhance viewsheds, provide year
round color, and private areas where benches may be selectively placed. The
opportunity exists through the placement of plant material to recreate the
romantic setting of an English landscape garden.
During the forthcoming neighborhood meetings, these landscape concepts will be
discussed with the members of the neighborhood. Their input to the process
will ultimately decide the bid alternates for the project.
Pond enhancement items Such as aerators and fountains were discussed at the
preliminary meeting of the Knollwood neighborhood. These issues were to be
discussed internally with the neighborhood. Until the City or RLK Associates
is notified, RLK will not invest any time on these pond enhancement items.
Recommendation:
Tree care to prepare significant trees for the construction season
Replacement of landscape features, i.e., brick wing walls, private
lights and /or address post /mail boxes
Added tree planting throughout the neighborhood and to increase
the buffer edge along Edgemoor. The type and size of the planting
will be determined during the detail design phase.
Site amenities as requested by the neighborhood such as benches
and /or walkways. It should be noted site amenities specifically
requested by the neighborhood may be bid as alternates and added
to the entire contract.
1) Alignment of the roadway within the right of way to minimize the amount
of tree removal.
2) Alternatives for new retaining walls to protect plant material
Keystone at $16.00 /sq. ft.
Limestone at $20.00 /sq. ft.
Fieldstone Boulders $24.00/sq. ft.
3) Tree losses are proposed to be held to a minimum. Figure 20 is a
identification of the tree loss impact.
4) Sloping of lawns will be integrated into the street construction program
to soften impact of new roadway.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 38
PROPOSED TREE LOSS CHART
Knollwood Project
Trees to be removed
Tree
18" Oak
Pond 15'Spruce
Pond 8'Spruce
8'Spruce
Location
830 Edgemoor
716 Valley Way
804 Valley Way
804 Valley Way
Trees to be removed unless right -of -way is purchased
Pond 2 -24 "Silver Maple
24" Oak (Island)
Pond 20' Austrian Pine
Pond 8" Green Ash
Potential Tree Loss - Mitigative Measures Needed
24" White Oak
24" White Oak
38" White Oak
DBL 18" and 20"
Cottonwood
16 ",16 ",18 ",36"
Cottonwood
36" Oak
1 .5' Conifer
40" Red Oak
DBL 24" Oak Island
36" Oak
30" Elm
36" Oak
302 Bridle Lane
705 Valley Way
302 Bridle Lane
302 Bridle Lane
810 Edgemoor
802 Edgemoor
802 Edgemoor
413 Cottage Downs
413 Cottage Downs
414 Wilshire Walk
408 Wilshire Walk
312 Wilshire Walk
705 Valley Way
302 Cottage Downs
413 Cottage Downs
302 Cottage Downs
Suggested Mitigative Measures to Assist Trees to Survive Construction
o Prune all Hardwoods (Oak, Elms) in cold weather months
o Trenching between Red Oak trees to inhibit oak wilt
o Protective fencing under canopy of tree
o Restrict equipment and stockpiling of materials under drip line of trees
o Institute a fertilization program by a qualified tree care professional
ASSOCIATES LTD)
922 Mainstreet
Hopkins, Mn.
55343
(612) 933-0972
fax: (612) 933 -1153
TREE LOSS IMPACT
FIGURE. 20
•
RLK ASSOCIATES, LTD.
5) Private irrigation systems will be reviewed and repaired on a lot by lot
basis and be under the control of the Construction Manager for
restoration.
STREET LIGHTING
NSP has committed, if requested, to replace the six existing cobra head lights
and wooden poles with a shoebox, cut -off fixture on an ornamental fiberglass
pole for a total price of $3,000.00. The new system would be owned and
maintained by NSP. The neighborhood would pay the capital replacement cost
through the special assessment procedure. Operating costs would be paid out
of the City Traffic Department Street Light Operation Fund.
Additional lighting has been requested by some residents on Edgemoor Avenue.
A Street light petition will have to be completed and approved according to
City policy prior to the installation of any additional light standards.
Discussion on the specifics of this request will be addressed at the future
neighborhood meetings and coordinated within the street design process. The
lights will be placed as a part of this neighborhood improvement project. All
existing lights and proposed locations will have to be serviced with new
underground conductors. The conduits are included in the cost estimate for
this improvement project.
NSP has a number of alternative designs which are approved for installation in
neighborhoods such as Knollwood; please refer to Figure #21 for a couple of
alternative lighting designs.
Within the landscape estimate, approximately $30,000 has been designated for
the installation of up to 10 ornamental light standards which will provide the
Knollwood neighborhood a signature in regard to street lighting. The new
light system chosen to be implemented will be researched further in the detail
design phase.
COORDINATION WITH THE CITY OF ST. LOUIS PARK ON EDG 1OOR DRIVE
The eastern half of the Edgemoor Drive right of way is within the City of St.
Louis Park. This area is primarily a wooded and landscaped area that aids in
the screening of the Amhurst neighborhood in St. Louis Park from the Knollwood
neighborhood. Amhurst was developed in the early 1980's and consists of
townhomes with access only from the east.
During the feasibility study phase, the staff of St. Louis Park was contacted
about participation on an improvement project to Edgemoor Drive. Their
response was there would be no benefit to the St. Louis Park property by the
improvement of Edgemoor Drive. There is no area for additional property
development ;neither is there access to Edgemoor Drive from any St. Louis Park
property owners. As a result, the City staff was not willing to suggest a
spirit of cooperation would exist on a project of this type; especially
through which assessments would be levied on St. Louis Park property.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 40
25'
24'
23'
22'
21'
20'
19'
18'
17'
16'
15'
14'
13'
12'
11'
10'
9'
8'
7'
6'
5'
4'
3'
2'
1'
EST. COST = $700 /POLE
ec+
0 I
SHOEBOX ORNAMENTAL
LIGHT TRADITIONAL
STYLE
ACORN
DESIGNER
STYLE
LANTERN
DESIGNER
STYLE
EST. COST = $3500 /POLE
• ASSOCIATES LTD.}
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
ALTERNATIVE STREET
LIGHTING
POLE & FIXTURE
FIGURE 21
RLK ASSOCIATES, LTD.
The City of St. Louis Park's boundary will limit the placement of the easterly
edge of Edgemoor Drive since the right of way is only 33 feet wide. The City
of Hopkins may wish to negotiate with the City of St. Louis Park to acquire
all the excess St. Louis Park property to the fence line of the Amhurst
property. The City of Hopkins would then have full control on this buffer
area adjacent to the Knollwood neighborhood area. Since St. Louis Park sees
no benefit in the ongoing improvement, they may be open to this approach.
The City of Hopkins has at least two options, as seen by RLK, on the matter of
the improvements to Edgemoor Drive. First, the City could complete the
project by constructing a complete roadway along Edgemoor Drive and assessing
the cost of the improvements to the neighborhood as a whole with City
participation limited to the 30% amount indicated by Policy #7 -D. Provided
Edgemoor Drive is considered a side street in accordance with Section 11.08,
this first option is being recommended.
Secondly, the City could improve Edgemoor with a complete roadway and pay the
easterly half of the street improvement cost out of City subsidized funds.
There is no definition that can be applied to this unique circumstance in
Policy #7 -D. Therefore, the City Council should review this as a separate
decision package within the scope of the project.
TRAFFIC PROBLEMS, VEHICULAR AND PEDESTRIAN
Vehicular traffic problems were reviewed in the neighborhood from traffic
signing to visibility at intersections and on curves. At the October 28th
property owner meeting, this issue was also discussed. The people in
attendance indicated, very clearly, they felt there was no problem with
traffic. Surveys that were turned into the City indicated a few minor
problems. For example, sight distance on Valley Way north of Wilshire Walk
was cited as a problem that should be reviewed. Also, the sight distance at
the intersections of Wilshire Walk and Cottage Downs with Oak Ridge Road cause
motorist inconvenience. One resident commented that speeding of traffic
occasionally posed a problem. He was concerned the new streets would
exacerbate this problem.
There was no concern mentioned about parking problems on the narrow streets.
Observations during the preparation of the feasibility study noted that few
vehicles park on the streets.
Pedestrian problems were not mentioned as a problem by any of the residents
relative to the need for trails or sidewalks. However, the need for
additional street lighting was pointed out by several residents.
During the detailed design phase of the project, these items will be looked at
to a closer degree with the residents as the specific design is prepared.
Within this report, recommendations have been made for wider street widths on
Cottage Downs and Wilshire Walk near Oak Ridge Road. This would help
alleviate the sight distance problem and enhance the traffic maneuvering area
in these areas of the neighborhood. Additional lighting is also commented on
in that appropriate section of this report. These items will be solidified
during future meetings with the neighborhood residents.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 42
RLK ASSOCIATES, LTD.
Once the street project is completed, the traffic movement problems that
relate to excess vehicular speed and parking problems due to street width will
have to be examined. Operation of vehicles should not change appreciably
after the implementation of these recommended improvements. However, it may
be necessary to add traffic control signs at one or more locations within the
neighborhood based upon actual experience.
CONSTRUCTION SCHEDULES AND PHASING OF WORK ACTIV1T1JS
During the neighborhood meeting on October 28, the issue of construction
phasing was discussed at length. It is very obvious this is one of the prime
concerns of the neighborhood residents. Figure 22 has been prepared as an
example of the construction phasing sequence strategy that may be used during
the implementation phase of this project.
Several items are important to mention concerning construction in this area:
1) The construction project would be phased so that only portions of the
neighborhood area are experiencing construction disruption at a specific
time. The underground construction will begin early in the process,
with the street work being completed near the end of the construction
process.
2) Each resident will have access to his property during the project at all
times, with the exception of periods of time when utility or street
construction is ongoing directly near the residents driveway. These
periods of disruption will be minimized to hours, not days, of
disruption. At no time will the resident be unable to access their
property with their vehicle for a period of more than a couple of days,
if at all, during the course of the project.
3) A full time inspector representing the City shall be assigned to the
project. He shall maintain optimum communications with the property
owners to deal with the problems of construction.
4) A newsletter will be prepared twice a month explaining the details of
the construction project. The residents will be continually updated on
the status of the progress of the construction activities.
5) Meetings will be held on a "needs basis" with the residents as the
construction progresses through the neighborhood. As with the
newsletter, the goal is to inform the residents of what is happening
with the construction activities.
6) The schedule for the Knollwood project is included in the earlier
sections of the report. It is expected that construction will begin, at
the earliest, in mid -May and be completed by mid - October.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 43
922 Mainstreet
Hopkins, Mn.
55343
(612) 933-0972
fax: (612) 933 -1153
FIGURE 22
oa
CITY OF MINNETONKA
STAB HWY.
PHASE 1
PHASE 2
ititmensimol
PHASE 3
PHASE 4
PHASE 5
o_
cn
cn
LL
0
}
U
RLK ASSOCIATES, LTD.
PERMITS FOR CONSTRUCTION OF THE KNOLLWOOD PROJECT
Permits will be required for the project from the Minnehaha Creek Watershed
District due to the storm sewer work. The Minnesota Pollution Control Agency
will require a permit because of the sanitary sewer improvements. Finally,
the Minnesota Department of Health will require a permit because of the work
on the watermain system.
FINANCING OF THE PROJECT
Preliminary cost estimates have been completed for the project design
alternatives as discussed in this report. These actual estimates of cost are
contained in the appendix to this report. A summary of the recommended
project costs broken into City participation and special assessments are shown
in the table below:
Project Description
Total
Project City Special
Costs Costs Assessments
Streets (Alternate C) $483,324 $144,997 $338,327
Storm Sewer $119,717 $119,717 - 0 -
Sanitary Sewer $ 90,857 $ 90,857 - 0 -
Watermain $ 98,020 $ 98,020 - 0 -
Alternate Items:
Alley south of Cottage Downs $ 6,045 $ 1,209 $ 4,836
Colored concrete for Curbs $ 34,528 - 0 - $ 34,528
Sprinkler system adjustments $ 1,300 - 0 - $ 1,300
Project Total Cost Estimates $833,791 $454,800 $378,991
A portion of the cost of the project, approximately 46 per cent, is proposed
to be assessed to the benefiting properties on an adjusted front foot basis
based upon the contents of City policy #7 -D for Roadway Improvements. On page
48 is a fairly elaborate table indicating the preliminary estimated costs for
each property broken down into categories. The categories demonstrate the
estimated project costs for each property for each property in the Knollwood
neighborhood, estimated city costs, and estimated special assessments. These
costs have been prepared from the preliminary cost estimate data that has been
generated through the completion of this feasibility study. They are not
based upon a detailed design nor bid prices procured through a competitive
bidding process. Therefore, it is likely these numbers will change!
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 45
RLK ASSOCIATES, LTD.
The basic cost for the estimated assessments includes the property owners
portion of the costs for the street construction as articulated in Policy
#7 -D. The alternates, including coloring for the concrete curbs explained
earlier in the report; and adjustments to the sprinkler systems that may be
found in the boulevard area, are shown as assessed 100 percent to the
benefiting property owners. The alley south of Cottage Downs is assessed only
to the three benefiting properties that abut the alleyway.
The totals for each of the categories, as do all the costs in this report,
include a 30% overhead factor. This factor represents approximately 15
percent cost for planning & engineering, approximately 5 percent for City
administration and capital interest costs, and an approximate 10 percent
contingency fee applied against the project costs.
The cost for the easterly half of the Edgemoor Drive street has been included
in the project costs, applied against all the properties in the Knollwood
neighborhood and assessed on a 70% property owner /30% City basis. If another
alternate for funding this cost is found, the overall neighborhood cost would
be revised accordingly.
Funds for right-of-way acquisition or easements are not included in the
assessed or City cost. It is anticipated that the right -of -way and /or
easements that are needed will be dedicated at no direct cost to the City.
These details will be discussed at forthcoming property owner and City
meetings.
On the next page after the preliminary assessment role table is a sample
assessment write -up sheet that demonstrates the cost impact of the assessment
on a typical 100 foot lot in the Knollwood neighborhood. This sample is shown
for an assessment spread over 15 years at 8% interest. Additionally, an
example of an assessment spread over 20 years has been shown. It is
recommended the City consider the 20 year assessment period with these
assessments. Assessments in the Knollwood neighborhood are above the average
assessments for neighborhood street improvements because of the large lots
that exist. Longer periods of time would aid in reducing costs on an annual
basis.
STATEN' OF PROJECT FEASIBILITY
The project as described in this planning and feasibility report is feasible
to construct as proposed. It is the opinion of the planners and engineers who
authored this report that the project will equal or exceed the proposed
assessments to abutting properties.
It is recommended that the project be pursued as recommended herein, and that
a public hearing be set for December 3, 1991.
FEASIBILITY STUDY - KNOLLWOOD NEIGHBORHOOD Page 46
PRELIMINARY ASSESSMENT ROLL
TOTAL ESTIMATED PROJECT COST $833,790 CITY COSTS $454,800
TOTAL # OF ASSESSABLE RESIDENTIAL LOTS 48 PROPERTY OWNER BASIC COST $338,327
TOTAL # OF ADJUSTED ASSESSABLE FRONTAGE 5,922.65 PROPERTY OWNER ALTERNATES $40,664
AVERAGE ASSESSABLE COST (W /0 ALTERNATES) PER LOT $7,048
PROJECT ESTIMATED ESTIMATED
ASSESS. COSTS PROJECT CITY
ADDRESS OF PROPERTY FOOTAGE RATE /FOOT COSTS COSTS *
Knollwood Project
Percentages
102 Bridle Lane
240 Bridle Lane
302 Bridle Lane
105 Cottage Downs
115 Cottage Downs
210 Cottage Downs
215 Cottage Downs
225 Cottage Downs
275 Cottage Downs
302 Cottage Downs
315 Cottage Downs
325 Cottage Downs
405 Cottage Downs
409 Cottage Downs
410 Cottage Downs
413 Cottage Downs
417 Cottage Downs
420 Cottage Downs
428 Cottage Downs
601 Edgemoor Drive
602 Edgemoor Drive
603 Edgemoor Drive
710 Edgemoor Drive
802 Edgemoor Drive
810 Edgemoor Drive
820 Edgemoor Drive
830 Edgemoor Drive
707 Oakridge Road
707 Oakridge Road
805 Park Terrace
815 Park Terrace
821 Park Terrace
825 Park Terrace
705 Valley Way
712 Valley Way
715 Valley Way
716 Valley Way
804 Valley Way
810 Valley Way
122 Wilshire Walk
203 Wilshire Walk
208 Wilshire Walk
216 Wilshire Walk
301 Wilshire Walk
306 Wilshire Walk
312 Wilshire Walk
408 Wilshire Walk
414 Wilshire Walk
TOTALS
Notes:
*
**
**
**
**
5922.65
120.33
150
150
100
100
117.78
100
100
100
138.83
100
114.6
135.74
100
115.55
103.27
100
100
100
100
100
100
150
144.92
132.99
130.86
129.78
150
150
150
149.58
150
150
150
127.21
150
150
150
150
100
129.14
100
100
150
100
100
100
132.07
5922.65
BASIC COST ALTERNATES
ESTIMATED ESTIMATED ESTIMA
ASSESSMENT ASSESSMENT SPECIAL
COST COST ** ASSESSMENT
$139.76 $827,745 $454,800 $338,327 $40,664 $378,991
(w /o alley) 54.94% 40.87% 4.91% 45.79%
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$139.76
$16,817
$20,964
$20,964
$13,976
$13,976
$16,461
$13,976
$13,976
$1',976
$19,403
$13,976
$16,016
$18,971
$13,976
$16,149
$14,433
$13,976
$13,976
$13,976
$13,976
$13,976
$13,976
$20,964
$20, 254
$18,587
$18,289
$18,138
$20,964
$20,964
$20,964
$20,905
$20,964
$20,964
$20,964
$17,779
$20,964
$20,964
$20,964
$20,964
$13,976
$18,049
$13,976
$13,976
$20,964
$13,976
$13,976
$13,976
$18,458
$9,239
$11,518
$11,518
$7,678
$7,678
$9,044
$7,678
$7,678
$7,678
$10,660
$7,678
$8,799
$10,423
$7,678
$8,872
$7,929
$7,678
$7,678
$7,678
$7, 678
$7,678
$7, 678
$11,518
$11,128
$10,212
$10,048
$9,965
$11,518
$11,518
$11,518
$11,485
$11,518
$11,518
$11,518
$9,768
$11,518
$11,518
$11,518
$11,518
$7,678
$9,916
$7,678
$7,678
$11,518
$7,678
$7,678
$7, 678
$10,141
$6,873
$8,568
$8,568
$5,712
$5,712
$6,728
$5,712
$5,712
$5,712
$7,930
$5,712
$6,546
$7,753
$5,712
$6,600
$5,899
$5,712
$5,712
$5,712
$5,712
$5,712
$5,712
$8,568
$8,278
$7,596
$7,475
$7,413
$8,568
$8,568
$8,568
$8,544
$8,568
$8,568
$8,568
$7,266
$8,568
$8,568
$8,568
$8,568
$5,712
$7,376
$5,712
$5,712
$8,568
$5,712
$5,712
$5,712
$7,544
$723 $7,596
$901 $9,469
$901 $9,469
$601 $6,313
$601 $6,313
$707 $7,435
$601 $6,313
$601 $6,313
$601 $6,313
$834 $8,764
$601 $6,313
$688 $7,234
$815 $8,569
$601 $6,313
$2,294 $8,894
$620 $6,519
$601 $6,313
$601 $6,313
$601 $6,313
$601 $6,313
$601 $6,31
$601 $6,3
$901 $9,46
$870 $9,148
$799 $8,395
$786 $8,261
$779 $8,192
$901 $9,469
$901 $9,469
$901 $9,469
$898 $9,442
$901 $9,469
$901 $9,469
$901 $9,469
$764 $8,030
$901 $9,469
$901 $9,469
$2,501 $11,069
$2,501 $11,069
$601 $6,313
$776 $8,152
$601 $6,313
$601 $6,313
$901 $9,469
$601 $6,313
$601 $6,313
$601 $6,313
$793 $8,337
$139.76 $827,750 $454,766 $338,301 $40,368 $378,671
Includes cost of the Concrete alley; 80% Assessments, 20% City.
The cost of the concrete alley alternate is added to 410 Cottage Downs, and
804 & 810 Valley Way. The other alternates include coloring for the concrete
curbs and adjustment cost for the sprinkler systems in the boulevard area.
ASSOCIATES LTD
SAMPLE ASESSMENT
ANNUAL ASSESSMENT
LOT ASSESSMENT TOTAL OVER TIME
WIDTH RATE ASSESSMENT 15 YRS. 20 YRS.
100' $63.00 /L.F. $6,500
plus $200
interest on
capital
150' $63.00 /L.F. $9,700 Average $1,133 988
Year
plus $250
interest on
capital
If your frontage is 100 feet on Cottage Downs, or any other street in
the Knollwood neighborhood, and the assessment rate is set at the
Assessment Hearing based on competitive contractor bids by the City
at $63.00 per lineal front foot, the assessment would be $6,300 plus
interest on the period of construction. The City allows payment to
be spread over time If 15 years at an 8% interest rate is allowed,
the average annual cost for the improvement would be $759. The
assessment can be divided into two payments -- May and October. in
this example the first half and second half payment would be $380
each.
o
922 Mainstreet
Hopkins. Mn.
55343
(612) 933 -0972
fax: (612) 933 -1153
■
Average $759 $662
Year
1st Half
Taxes $380 $331
2nd Half
Taxes $380 $331
1st Half
Taxes $ 567 $494
2nd Half
Taxes $ 567 $494
KNOLLWOOD
RESIDENTIAL
LOT
SAMPLE ASSESSMENT
FIGURE 23
CONCRETE
THICKNESS SCHEDULE
DRIVEWAY 1 THICKNESS 1 SPEC
RESIDENTIAL
6"
CONCRETE TO BE
MN/DOT 3432
CR 3A32M MIX .
CBS IGN WITH 6%
z :% AIR CONTENT
COMMERCIAL
8"
RADIUS
5 FT.
VERTICAL CURB
C(PANSION JOINT 5 FT. SECTION
MATERIAL
GUTTER LINE
2 FT. TYPICAL DRIVEWAY
I.5 FT. WITH "8" TYPE CURB GUTTER
5 FT_
TYPICAL CURB & GUTTER
TYPE UD"
922 Mainstreet
Hopkins, Mn.
55343
(612) 933 -0972
ASSOCIATES LTD. fax: (612) 933 -1153
22 FT. MAX.RES1DENTIAL
10 FT. MIN. RESIDENTIAL
24 FT. MAX COMMERCIAL
MIN. ELEVATION AT
BACK OF APRON SHALL
BE EQUALTO HEIGHT
OF CURB
22 FT. MAX.RESIDENTI AL
10 FT. MIN. RESIDENTIAL
•
24 FT MAX. COMMERCIAL
MIN_ ELEVATION AT
BACK OF APRON SHALL
BE EQUAL TO HEIGHT
OF CURB
• TYPICAL DRIVEWAY
WITH '‘D" TYPE CURB 8 GUTTER
3' R.
Slope 3/4
Per h..
1/2' R.
3
GUTTER LINE
CITY OF HOPKINS TYPICAL
DRIVEWAY OPENING DETAIL
EXPANSION JOIN-
MATERIAL
1
tiR
J
TYPICAL CURB & GUTTEF
TYPE "B
APPENDIX
Streets and
Restoration
* *Public Drive,
Cottage Downs
** *Storm Sewer
*Sanitary Sewer
Water Main
**
* **
1,895
119,717
90,857
99,320
SUMMARY
PRELIMINARY COST ESTIMATE
KNOLLWOOD STREET RECONSTRUCTION
HOPKINS, MINNESOTA
20' TYPICAL DRIVING SURFACE 26' F -F
ALT. A ALT. B ALT. C ALT. D ALT. E
Bit. Curb B -618 Mountable Mountable B -618
Curb Conc. Curb Colored Conc. Curb
Conc. Curb
$499,015 $475,810 * ** $483,324 $517,852 $516,052
1,895
119,717
90,857
99,320
1,895
119,717
90,857
99,320
Estimated Project
Cost $810,804 $787,599 $795,113 $829,641 $827,841
Alternate Route C - Relocate Sewer Main, Wilshire Walk to Bridle Lane
Poly Liner Alt. is $107,887, line main with poly liner, Wilshire Walk to
Edgemoor Drive.
Option B - Bituminous
Option A is $6,045, 7" concrete pavement
Does not include costs for perforated underdrains.
1,895
119,717
90,857
99,320
1,895
119,717
90,857
99,320
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
ALTERNATE A - BITUMINOUS CURB WITH PERFORATED UNDERDRAINS
STREET CONSTRUCTION AND RESTORATION (20' F.F. WIDTH)
Item
No.
1. Bituminous Removal S.Y. 16,400.0 $ 1.25 $ 20,500.00
2. Concrete Driveway Rem. /Replacement S.Y. 100.0 20.00 2,000.00
3. Adjust Gate Valves EACH 6.0 100.00 600.00
4. Common Excavation C.Y. 10,900.0 2.50 27,250.00
5. Subgrade Correction C.Y. 2,500.0 8.00 20,000.00
* 6. Granular Borrow C.Y. 2,500.0 6.00 15,000.00
7. Subgrade Preparation R.S. 66.4 20.00 1,328.00
8. Class 5 Aggregate Base TON 5600.0 6.00 33,600.00
9. Bit. Wear Course, Mn /DOT 2341 TON 1400.0 15.00 21,000.00
10. Bit. Base Course, Mn /DOT 2331 TON 1900.0 12.00 22,800.00
11. Bit. Material for Mixture TON .200.0 140.00 28,000.00
12. Bit. Curb L.F. 13,280.0 3.50 46,480.00
*13. Perforated Underdrains L.F. 3500.0 6.00 21,000.00
14. Topsoil Borrow C.Y. 2,900.0 7.00 20,300.00
15. Sodding S.Y. 22,000.0 2.00 44,000.00
16. Restoration /Landscaping /Lighting L.S. 1.0 60,000.00 60,000.00
Estimated Construction Cost $383,858.00
+30% Engineering, Legal, Administration & Financing $115,157.00
Estimated Project Cost $499,015.00
*For Alternate "A" only
Description
APPENDIX - 2
Unit
Unit Quantity Price Amount
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
ALTERNATE B - B -618 CONCRETE CURB AND GUTTER
STREET CONSTRUCTION AND RESTORATION (20' FACE TO FACE WIDTH)
Item Unit
No. Description Unit Quantity Price Amount
1. Bituminous Removal S.Y. 16,400.0 $ 1.25 $ 20,500.00
2. Concrete Driveway Rem. /Replacement S.Y. 100.0 20.00 2,000.00
3. Adjust Gate Valves EACH 6.0 100.00 600.00
4. Common Excavation C.Y. 10,900.0 2.50 27,250.00
5. Subgrade Correction C.Y. 2,500.0 8.00 20,000.00
6. Subgrade Preparation R.S. 66.4 20.00 1,328.00
7. Class 5 Aggregate Base TON 5500.0 6.00 33,000.00
8. Bit. Wear Course, Mn /DOT 2341 TON 1070.0 15.00 16,050.00
9. Bit. Base Course, Mn /DOT 2331 TON 1400.0 13.50 18,900.00
10. Bit. Material for Mixture TON 160.0 140.00 22,400.00
11. Concrete Curb and Gutter, B -618 L.F. 13280.0 6.00 79,680.00
12. Topsoil Borrow C.Y. 2,900.0 7.00 20,300.00
13. Sodding S.Y. 22,000.0 2.00 44,000.00
14. Restoration /Landscaping L.S. 1.0 60,000.00 60,000.00
Estimated Construction Cost $366,008.00
+30% Engineering, Legal, Administration & Financing $109,802.00
Estimated Project Cost $475,810.00
APPENDIX - 3
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
*ALTERNATE C - MOUNTABLE CONCRETE CURB AND GUTTER
STREET CONSTRUCTION AND RESTORATION (18' Edge to Edge of Gutter,
20' Driving Surface Width)
Item
No.
Description
APPENDIX - 4
Unit
Unit Quantity Price Amount
1. Bituminous Removal S.Y. 16,400.0 $ 1.25 $ 20,500.00
2. Concrete Driveway Rem. /Replacement S.Y. 100.0 20.00 2,000.00
3. Adjust Gate Valves EACH 6.0 100.00 600.00
4. Common Excavation C.Y. 10,900.0 2.50 27,250.00
5. Subgrade Correction C.Y. 2,500.0 8.00 20,000.00
6. Subgrade Preparation R.S. 66.4 20.00 1,328.00
7. Class 5 Aggregate Base TON 5900.0 6.00 35,400.00
8. Bit. Wear Course, Mn /DOT 2341 TON 1130.0 15.00 16,950.00
9. Bit. Base Course, Mn /DOT 2331 TON 1480.0 13.50 19,980.00
10. Bit. Material for Mixture TON 170.0 140.00 23,800.00
11. Concrete Curb and Gutter, mountable L.F. 13,280.0 6.00 79,680.00
12. Topsoil Borrow C.Y. 2,900.0 7.00 20,300.00
13. Sodding S.Y. 22,000.0 2.00 44,000.00
14. Restoration /Landscaping /Lighting L.S. 60,000.0 1.00 60,000.00
Estimated Construction Cost $371,788.00
+30v Engineering, Legal, Administration & Financing $111,536.00
Estimated Project Cost $483,324.00
*For Alternate "F" total cost, add total square yards parking area
times $10.90/s.y. x 1.3
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
ALTERNATE D - MOUNTABLE COLORED CONCRETE CURB AND GUTTER
STREET CONSTRUCTION AND RESTORATION (18' Edge to Edge of Gutter,
20' Driving Surface Width)
Item
No.
Description
1. Bituminous Removal S.Y. 16,400.0 $ 1.25 $ 20,500.00
2. Concrete Driveway Rem. /Replacement S.Y. 100.0 20.00 2,000.00
3. Adjust Gate Valves EACH 6.0 100.00 600.00
4. Common Excavation C.Y. 10,900.0 2.50 27,250.00
5. Subgrade Correction C.Y. 2,500.0 8.00 20,000.00
6. Subgrade Preparation R.S. 66.4 20.00 1,328.00
7. Class 5 Aggregate Base TON 5900.0 6.00 35,400.00
8. Bit. Wear Course, Mn /DOT 2341 TON 1130.0 15.00 16,950.00
9. Bit. Base Course, Mn /DOT 2331 TON 1480.0 13.50 19,980.00
10. Bit. Material for Mixture TON 170.0 140.00 23,800.00
11. Concrete Curb and Gutter L.F. 13,280.0 8.00 106,240.00
Mountable Colored
12. Topsoil Borrow C.Y. 2,900.0 7.00 20,300.00
13. Sodding S.Y. 22,000.0 2.00 44,000.00
14. _Restoration/Landscaping/Lighting L.S. 60,000.0 1.00 60,000.00
Estimated Construction Cost
+30% Engineering, Legal, Administration & Financing
Estimated Project Cost
Unit
Unit Quantity Price Amount
$398,348.00
$119,504.00
$517,852.00
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
*ALTERNATE E - B -618 CONCRETE CURB AND GUTTER
STREET CONSTRUCTION AND RESTORATION (26' F -F STREET WIDTH)
Item
No.
Description
APPENDIX - 6
Unit
Unit Quantity Price Amount
1. Bituminous Removal S.Y. 16,400.0 $ 1.25 $ 20,500.00
2. Concrete Driveway Rem. /Replacement S.Y. 100.0 20.00 2,000.00
3. Adjust Gate Valves EACH 6.0 100.00 600.00
4. Common Excavation C.Y. 11,500.0 2.50 28,750.00
5. Subgrade Correction C.Y. 2,700.0 8.00 21,600.00
(incl. gran. backfili)
6. Subgrade Preparation R.S. 66.4 20.00 1,328.00
7. Class 5 Aggregate Base TON 7000.0 6.00 42,000.00
8. Bit. Wear Course, Mn /DOT 2341 TON 1400.0 15.00 21,000.00
9. Bit. Base Course, Mn /DOT 2331 TON 1950.0 13.50 26,325.00
10. Bit. Material for Mixture TON 214.0 140.00 29,960.00
11. Concrete Curb and Gutter, B6 -18 L.F. 13,100.0 6.00 78,600.00
12. Topsoil Borrow C.Y. 2,900.0 7.00 20,300.00
13. Sodding S.Y. 22,000.0 2.00 44,000.00
14. Restoration /Landscaping /Lighting L.S. 60,000.0 1.00 60,000.00
Estimated Construction Cost $396,963.00
+30% Engineering, Legal, Administration & Financing $119,089.00
Estimated Project Cost $516,052.00
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
STREET CONSTRUCTION AND RESTORATION
PUBLIC DRIVE, 410 COTTAGE DOWNS
Item
No.
1. Common Excavation
2. 7" Concrete Pavement
OPTION "A"
7" CONCRETE, 10' WIDE
Unit
Description Unit Quantity Price Amount
C.Y.
S.Y.
Estimated Construction Cost
+30% Engineering, Legal, Administration & Financing
Estimated Project Cost
100.0$
220.0
2.50 $ 250.00
20.00 4,400.00
$ 4,650.00
$ 1,395.00
$ 6,045.00
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
STREET CONSTRUCTION AND RESTORATION
PUBLIC DRIVE, 410 COTTAGE DOWNS
Item
No.
OPTION "B" - Bituminous
12' Wide, 2" 2331 Bituminous Wear, 6" Class 5 Aggregate Base
Description
*Cost estimate is for portion on public right of way only.
Unit
Unit Quantity Price Amount
1. Common Excavation C.Y. 100.0 $ 2.50 $ 250.00
2. Class 5 Aggregate Base TON 70.0 6.00 420.00
3. Bituminous Wear Course
MnDOT 2331 TON 32.0 15.00 480.00
4. Bituminous Material
for Mixture TON 2.2 140.00 308.00
Estimated Construction Cost $ 1,458.00
+30% Engineering, Legal, Administration & Financing $ 437.00
Estimated Project Cost $ 1,895.00
PRELIMINARY COST ESTIMATE
Knollwood Street Reconstruction
Hopkins, Minnesota
STORM SEWER (without underdrains)
Item Unit
No. Description Unit Quantity Price Amoun
. 12" RCP Storm Sewer L.F. 1660.0 $ 18.00 $ 29,880.00
. 15" RCP Storm Sewer L.F. 730.0 19.00 13,870.00
3. 18" RCP Storm Sewer L.F. 100.0 21.00 2,100.00
4. 12" Apron EACH 8.0 400.00 3,200.00
5. 15" Apron EACH 3.0 500.00 1,500.00
6 18" Apron EACH 1.0 550.00 550.00
7 Catch. Basin EACH 31.0 900.00 27 900.00
8. Connect to Existing Storm Sewer EACH 5.0 250.00 1,250.00
9. Rip Rap, Class II C.Y. 28.0 30.00 840.00
*10. Rip Rap, Class IV C.Y. 100.0 30.00 3,000.00
11. Pond Dredging L.S. 1.0 8,000.00 8,000.00
Estimated Construction Cost
+30% Engineering, Legal, Administration & Financing
Estimated Project Cost
*For dike for sedimentation area in Bridle Lane Pond.
APPENDIX - 9
$ 92,090.00
$ 27,627.00
$119,717.00
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
SANITARY SEWER
POLYETHYLENE LINER FOR EXISTING MAIN, WILSHIRE WALK TO EDGEMOOR DRIVE
Item
No.
Description
Unit
Unit Quantity Price Amount
1. U- lining and service wyes L.F. 484.0 $ 45.00 $ 21,780.00
2. 8" PVC SDR 35 SS 0 -10' L.F. 1405.0 16.00 22,480.00
3. 8" PVC SDR 35 SS 10 -12' L.F. 650.0 18.00 11,700.00
4. 8" PVC SDR 35 SS 12 -14' L.F. 200.0 20.00 4,000.00
5. 8" PVC SDR 35 SS 14 -16' L.F. 40.0 21.00 840.00
6. Standard Manholes 0 -10' EACH 9.0 1,000.00 9,000.00
7. Spot Repair EACH 2.0 500.00 1,000.00
8. 8" x 4" PVC Wye EACH 23.0 50.00 1,150.00
9. Connect to Existing Service EACH 23.0 80.00 1,840.00
10. 4" PVC SDR 35 Service Pipe L.F. 400.0 8.00 3,200.00
11. Rock Stabilization L.F. 2000.0 3.00 6,000.00
Estimated Construction Cost
+30% Engineering, Legal, Administration & Financing
Estimated Project Cost
APPENDIX - 10
$ 82,990.00
$ 24,897.00
$107,887.00
IP
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
SANITARY SEWER, ALTERNATE ROUTE "C"
RELOCATE MAIN, WILSHIRE WALK TO BRIDLE LANE
Item Unit
No. Description Unit Quantity Price Amount
1. 8" PVC SDR 35 SS 0-10' L.F. 1885.0 16.00 30,160.00*
2. 8" PVC SDR 35 SS 10-12' L.F. 650.0 18.00 11,700.00
3. 8" PVC SDR 35 SS 12-14' L.F. 200.0 20.00 4,000.00
4. 8" PVC SDR 35 SS 14-16' L.F. 40.0 21.00 840.00
5. Standard Manholes 0-10' EACH 10.0 1,000.00 10,000.00**
6. Spot Repair EACH 2.0 500.00 1,000.00
7. 8" x 4" PVC Wye EACH 23.0 50.00 1,150.00
8. Connect to Existing Service EACH 23.0 80.00 1,840.00
9. 4" PVC SDR 35 Service Pipe L.F. 400.0 8.00 3,200.00
10. Rock Stabilization L.F. 2000.0 3.00 6,000.00
Estimated Construction Cost
+30% Engineering, Legal, Administration & Financing
Estimated Project Cost
* Includes 480 1.f. for relocation of main, Wilshire Walk to Bridle Lane, $7,680
** Includes 1 manhole for relocation, Wilshire Walk to Bridle Lane, $1,000
APPENDIX - 11
$ 69,890.00
$ 20,967.00
$ 90,857.00
PRELIMINARY COST ESTIMATE
Knollwood - Street Reconstruction
Hopkins, Minnesota
WATERMAIN
Item
No.
Description
APPENDIX - 12
Unit
Unit Quantity Price Amount
1. Connect to Existing Watermain EACH 15.0 $ 400.00 $ 6,000.00
2. 6" DIP Watermain L.F. 3800.0 13.00 49,400.00
3. 6" Gate Valve EACH 10.0 400.00 4,000.00
4. 6" Hydrant EACH 4.0 1,200.00 4,800.00
5. 1" Corporation Stop EACH 20.0 50.00 1,000.00
6. 1" Curb Stop EACH 20.0 80.00 1,600.00
7. 1" Copper Service L.F. 400.0 10.00 4,000.00
8. Connect to Existing Service* EACH 20.0 100.00 2,000.00
9. Fittings LB. 1600.0 1.50 2,400.00
10. Sprinkler Adjustment L.S. 1.0 1,000.00 1,000.00
Estimated Construction Cost $ 76,200.00
+30% Engineering, Legal, Administration & Financing $ 22,860.00
Estimated Project Cost $ 99,060.00
*Connection to existing service is between the main and property line. Any
replacement of the private water service between the house and right of way is the
property owner's responsibility.
Aa)
E • $4 of
T3 a0r-1
$_1 • O a -r4
O 0 U) S
E a) 1:1
-r4
O 043
-r4 0 (0
4. c0 W r-1
E'O
9 • >,
4-1 a)
'0 C. • ) 11 3
>.'0
w r1 0
4s -4-4 4(}
rn a) -4-4
a) 0 -r1 U
'O 40 e4-4 0
4-) -r4 U
ra O E a) (0
O 0)0)4) )
14 r 14 0 A
P4 -
a)1
t a .0 ' 0
•r O f a °
44 >-. O U)
a 4) 4-) to E
50CT0r.4 •
O b 1 0 CD .0
14 10 •r4aO
w 0 -N a 1-4 -r4
-4-t 4.4 (0 44..
U1 40 a) c0
O 14 r4 E a)bl
a) 'O.4- O 0-r1
r-4 (04J
A 00A0U)
O O O -r1
14 N $4 (0 >
a 0a4a0
'O -.4
0)14100
4014bO14
40 '0 40-0 4)
• pro- >
rta) rt -'.-4
Sa .0 00 S-1 4-4
H >+'O Q.,w
N a)
c0
E w v)
1-4 3 W
.A tn0 0
0 •r4 0
Q. 0 4 CD
.0 r-4 ur
U -1-) 0 U)
N c0w -r4
00(4)
Q) r-1 A -r1
0 +
O w EH
• a0
0 •
CT •CU U)
44 E0
• O
c.1 ni al A
N�3 4)
'0 >. Sa
N 0(0
-003-0
(0 Sa 1 40
'0 -4 3
0
a) b b�
4-1
-r1 .0 o
4-4 •4 $
r4C>1
(1) 4-
.0 0 -r10
w 0 0 0'
-r1 b
O U)00
+ 4 00•'-4
14 40
ED t4
• E ro
• S4 (1)
H O N
E U)>.0
O EU)14
1.4 a)
E 44
14 >. >. 0 0 •
O as • (0 • -.4 w
4.) 3'0 3'0 '0 w 0
U) '0O '00 44 a) '0 -C -C E
O (0 U) c0 U) 10 a 0 • CPU Sa W
U 0 - E UA ° -4-4 E v 0 N 4 �- 4
a) a a) • N 4-4 O to 0 4) C 3 w
Sao 0 ++A wA 0000 $4a) 0 0 •
S - 1 0 1.1 >r 4-1 $.4 .1-1 4.) 0 -r4 3 w O w 0 0 U)
0-r4 CIO O0 00 t41c0040O 14u) '0
C.) 4- 3 >w >4-1 as 0440 $•44-)00 30
0 0 r-4 • A V 'O 0 01 3 0 a) 0
'O a w >. 0 0 0 W O 0 r-4 .0 0 04
CD a) 0> 0> .0U10'0 -) .0 a )4 -
'0 S4 a) r-4 40 (0 0 0 m $- 0'0 44 0 .0 0
0 0 0r4 3 A 3 .0 . 0 0 0 - 1 ( 0 0 -r1 -r4 O O w d)
a) 9.4 (0 4) a) 10 0 4 >r 0 14 > 0 -r4 - r4 Q1
E a> 0 >r 0 >. 0 1-4 40 0.0 4-) 3 3
E 43 as Q. 0'- 0/ $4-0 0 w
O -P0 0) E OE .N •0 440 0a)
O 0 -ri '0 '0 0 3 4. -r4 O 0 to U.Q
a) a) .r4 0) -r4 a) a) O 0 w r-4 > 0 $4 • b
C4 0a) >0 >'O 00OU1'O O •-4-+O0 .-10
c a 0(0 0AS 0 3.4•x4 -r4 E>.ca4-) 0 as
0 -r1 S.4 14 $4 14 0 0 -4-) X $4 O 10 c0 0 - ri 0 -r4
Ua a0' a0' Uw01 0LQ 14 3A-r1r -4 404
a)
r-4
40
b -4
O 0
-4.4 -r4
to '0
-r1 0) U
r-4 U >
1a
(1) r•I
O 0.41:
O a) C•
0
-'-4
to a) 44
(0 0.0 0 a te )
.0 ° 0 N O 001 • 1
O U)0 r-4 tr) U 0 0
+ 4 ES -4 c0 '0 AaOOto
O 0.0 > 'O w0 >. S4 S4 0 0 O
0.-44) (I) 0 143 0 U a) .0 r-4 01.4
r o 0 N 3Z 3 044 , 44 44
44 44 '0 44 (4) .0 r 44 10 0 .0 020 ...
10 a0 a) -404 000 taanDcoons
004 104 > • 0c) 44 ...I-) (1) • - r $w $ 0 4 0
E U 0 a) 0 40 . s ~ a) U ) 0 $ 00 o c0 A -r4
0 0 0 w ,C 3 OW (I) 40 r0 o Sa ,C
14 (0 .) a) 0 -44 0 3 • E 0.- 0 S4
w 0 .0 • -,.1 w 14 10 .0 0 U) >•.-r1 O
a) 0 U) 0.4. CD 14 -r4 4) > c0 3
0 003 00 4.4r -4 44 '0040E
a,~ w w -r4 -'-4 0 0-4- 0 (1) sa 01
- .-4 -.-4 r-4 U! 4.1 0) Q' Q' -r1 a)'0 A .0 W •r4
Oa (11 4- b •14 0 >4 c0 44 a 0 (t3 4)
E a 'O A(0 Sa10.p cr1 -r40 000
01 U) 0 0 0 .4 0 E ft 04P4 as -r1 3 Q
CO a) •r-1 0 0> .SCaC140 4- -40 40U) a
0 U) • • -P -I-4 040 10 '. •
-r4 0 >I 'CS 14 w 40 14 -r4 •r4 -4.1 4f1 10 to 0 a-) 0
O 40 al a) 0 (II 01, $43031.4 4 o r a) a)
1403 b+ 00 a 30 -1) U)wa)A
'0 0' 04 14 E0 to 0 0 000 14 3
0 • w 0w 14 0E Or O O
O 010-0 r 0 $4 a 0 4)04) '0 0 >U)4)
4 - 4 143 S4 P4 -r4 O w 4-1 O -1.) 4-1 -r4 01 a -r4 -r1 0 U)
10 04. O 4) 0 > 10 14'O'0 H S4 E b'' c0
>-4-1.0 > O a) (1).--1 > O 0 W 0 fit 0 a) 0 a
•r4 0 0'r-4 a a a) 0.'0 -41 4-) 0 w a 0
14 44 - r4 0 -r4 -14 0 - r - 1144 0--4 14 0 w w - 0 - r4 - r4 r 0
C ro 14 O a a ro 4 0 0 a -r4 to 0 '.O.4 -4 A P:14 03 -r1
z
'0 0
4''. 0
CO -r4
0 CO a) 1n
O 0>O 0 a 0
4443 Q. S44 3'0 04-3
AO>,'0 >+H 01 0)a)
r-4 O A .0 '0.-I
O r 0 w 4 4.1 .N b
.-4 (33 0 0)w 0) .0 03
-r4 > > U) .4.)
4-) in en (6 .-1 •• r-4 - 1.4 1414
00•- 4.4 b0) 0 0 00
aNNb Oco U.-1 z
O
w
U1
-r-4
r-4
O
a
0
z
r- 4
rt
>
N
>4 0
3 R4
a).°
r♦
>3
a)
a
a � 3
• 0
00
4.)
1.1 r�1
-r1 O >
3 4-
O • U
400E
000
av(
c 0 400
-r4 r-4 4a
r•-1
E 40 0
4 >ro
• -r4 I •ri
'0 c4
a) 4 b 4)
a to
U)
$44.1 N
-ri -44 14 o
4--1 44 (')
a) (1) 1.4
O 0c0>.
O U)Ac0
Z U3
'0
0
CCI
14 >4
O 40
U3 0
(
CD a)
>v
O -r4
� 0 MI
• 44
'0 0 -
( 0
'0 0 >4,-+
O 14 w rt
N •.�
0.12 a) r-4 'O
aO 0' -'4
0 0'O 4
4.1 14 •r4 "4 U
044- 14 m
W cu
3 4 0 0 S4
O 0 0 aw
� O 40
O (1) +) +)
N - Q+ b'► 0 th
w a -r4 - 14
U -r4 -i.)'10
0 E 0 N -r-4
0 14 -rl 0 >
00(0 >0
0.1214 04
U N'O 4-4 a
to
rt
A
.0
4-)
U
-N
0
-r4
4-4
00
S4 14
RI 0
03 0
'0 U
w
�
/.0
'0 4
0
0 0
aCO
0
N
4)
.r4 0
O 0
4410'
i 0
w
0
1 A
0
•r4 e4•
rai
R I
w C?
; 0 •
(0 0) 0)
3 04
.0 0.e
-
X U) A
z
W
co N
0
c4 a)
atr
ro
Wa
0
z
H
a
w
0
>
a
z
z
'd
U
-0 a
O Sa U O
O a) 4) S4
-rl > S-i -r1 4.1
O a OVU3
N til sa w
Sao .O BOO
S-1 O 4 0
O -rl -I-4 -rl S-c G)
0 3 O a)'o
U a 3 •r1
'CI a co W co
W >, 3 N
O O .- to
N .-4 S.1 co
E co N O a)
E -a, -c.► A
o TS 01 N .N
U .--1 • c O
W •.1 Q -rl'O O
04 0 3 g.--1 co
A O -
a U W . A 4J
M 0
• Sf
W4-)
S.1 0
U O
U
G)
U
a a)
cd'd
N
4)
O al
-rl >
RS CU
z c
0
o 'o
Ei no co
a) r-1
b tfri-1-1
E) ft-44 aj
W 0 a)
.0 tr
MM0
O s~ $4 4 )
A -rl
RS O
0 4) S4 -rl Cm
0 0 Ti m
-.1 cd NO
Eta WQ)-rl
O 0'o 40
)4 O O -r1 Sa
41 -.4 a EoV
to co
c sa
0
O • >, 0
O 4 a) E
QJ
3 b� ro 'O
4-) 03 W
A go -rio
O•- O
>i0 c0 043
r-1 0 't3 3 0
ri O O
ate'
CO
CD
04
-Ft
04
0 a)
O w
4.3
0
1 4 1
tow
0 0 `o
b •,.1 U tr
16 its - .bd
-
.N 0 0 -44.-4
WE` to 040
E 0 -•r4 $4 0
C.) a E '
'0
O to -.4
Z •ri E
O
0
0
to 4
-r4 $4 r 0 '0
1.) •rl 0 0
03 rt0 0
C4 44 (5
w
N
O
O r
0
O R3 0
44 44 a
't3
0
0
c7
44
S
-rl
R3
w
0
U
Rf
'-4
01 •
O w
H •
•a
O rt1 M
H OM
•ri a)
Q . O 0
044-1.4
a •rt r-4
0 0
E x'.
RS U 0.
'0 0
(6.0
RI
a) 04(1
0 04 0
0
0 0 - r♦ 0
O R$ 0
aw P4
w
N
0.
- r+ 0
«3 0
w a
r24
0
cr
O 0 0
O 0
t? Oa
W
a
tD
0•
CO
0
- 44
r1
0
U
RS
'4
01
s{
0
00 0
.v a +4
$4 >n H s.i
0 H -r4 0
0 a) RS 0
a > 44 04
'CI .
in o a)
d' R5 C: r-1 - tr
•r1 . . al RS N
` 'C3 U H
■ 0 t11 (0 -44 .Q to 0 to 0 $4 E
co S4 +► H (1) E E tT 4) R3 0 RS 0
• 0• U 01 'O O N 54 0 •-4 0 M
0 0 - •O w - 44 4-4 01 - a) 004 RS
1.1 0 - 44 - U) • .0 U) 0 t� I .J . Q $4 0 O
> 0 to b a) tr • H O0 .0 0to 0
- 0 o .- O R} '0 0 4- Of - 0 U1 I•f U ORS ri
O 0 Q. a) Y- too u) 01 a) a) 0 54 N •ri > H 0 A
U
- 4 '0 b • ' d w 4. .0 N a � -w .4 - .0 5 4 0 3 p+ .4 , •
a Z M .. .1 tf1 -� '.4 a) to 0 0. 4.5 '-f a) ' 4 ) - .0
ro ra N 0 R3 .rib .0 05 E o -..f -r1 E • .0 E o -r4 'C3 4.1 co
o N 0 4a tD r-1 3 O H • a) M H 5 C 3 RS .1J 0 O r-
a) H 0 0 r-1 M 0 a) 0 •rl 044 H r4 S t6 o Q)
...g ON a) 0 u)'tO U) tr 0. E 0 .0 0 N ae to a .0 ... 0RSM 0 tra) ER3 .054 0+)H 0 t!) E -tom 0 0 0 0 4
d3 N cr .,.i • 10 tr O .x O -44 / H R3 -r1 0 H -'•1 433 (6 r- H -.4 a) -r1 'O
H r 0
$4 E R3 U1
-1 U S� 01 , .0 H .-4 01.- C: t2+ 54 '-f 1.4 0 H
0 a) x .1.) a) .0 0 R3 .v 0.0 .0 .0 RS ca .0 .0 .0 515 0 H
H Z - to -0 E 0 .-4 U RS N -�0'U3 -0't S a) 0 to -0 U .N a) 0 a) '0 0
- 0 N 0.0 S4.0 •rl 1-P RS 0 RS RS 0 0 '0 H RS -rl C: '0 H'( - co
01 Z ■ 4-) -1..) (0 0 0. 4-1 a) 0 03 - U RS 16 0. - w b 0. b 0 E
C3' 0) 0R3 001 •'i E 0U U - U)0 4 U • .0 a)
R I E 0 •• a) u - c o t o -.4 0 02 -.-1 '0 01 U ) 4 0 5 •ri U ) O (6 (6 0' 03 M
01 • a) 5-i U) 4.1 ca U 4- CA U - ri 404 r•1 •rf 44 0 (0 0 •rf RS tr 44 4.) 0 0 4-3 54 -44 '0
Mr-4 -44 -44W -440 -ri -44,0 ..r4... U) 0 N -rt -44 0 •.1 0 a) a) W
a) cr .0 a) H C: 0 > t0 N - 0 0 0 0 0 -rf 0 U O 0 U) 4) -rf to E a)
E 0 E .Q tr E 54 4.1 .05 Q. 05'0 01 03 RS a) H 04 0 0144 U H 44 A Q.N
0 0 14 0 a) •ri RS (i) 44 O R3 -rf -rf 0 -.4 -'4 14 0 0 a) .-I O -.4'4.4W 04.1 O -.40
vl .0 0. D3 'b CO 0 CO 0 Z (0 L4 (1) 03 C• N U 0 t0 'O.0 Z U2 O 0 CO 0 U) 04 5.0
4.)
U1
R3
a)
- - -
N RS E U1 - - - .x „x
3$4 3 CO 3 t` O O r) U e�' 0 rn - -c a) 01 a) r- IV .-
0 N OM OM >M 03 RSM RSN >rn >4**1 >44 ON ON MN N
0 H 0 0 (13 54 H H R3 RS RS RS RS
C, 0 0 30 H0 1-10 5.10 30 30 M0 00 aO 00 CD
O 0 x 0.0 a) -v -0 0 4-) a) .$.) 0 -0 43 4J 4.1 4.) 54 H -1.)
- '4 01 H 0' 05 >+ E E E >. >. >+ (1) (1) - ri -Pi
-0 CO CO CO 0 CO 03 a) t`- '0 In 'Cr a) el a) N a) M r-i r- ri 01 4 tt 4 e-
03 1.)0 4.)d• . ..-1M .'1.M ,X iv) .xM r4M r-1M r•1N 't3(Y) 'ON 01 c 03
U .1..) .y.) .;.) ri 54 H 54 .-4 '.4 r-1 - - '-4 r4
O 044 0= 0= R3 .0 RS= R3 .Z' RS x RS .T. R3 .T. 03 x 504 Z• 1 - i x -rl x -ri =
a 0 0 oz OZ >Z 04Z 04Z 04Z >Z >Z •E CO fil z z 3E
a)
a)
U)
0 41
b -rl -r4
IO cO a)
b
a) .
W E 0
EU A
Ow
U a4 w •
-,444
0.
0,0
(1)
at0
0
WO
-r{
00
wc,
a)
a
Ai cri
x
o O
O O
—4 14
.0
4?
U1 -A
4J 3
-r1 LO
O . EN
Q+ O ow
a) -rl r-i9 -1
'0 O 444
r-4
00
O -1-► Q
44 N N
E.N 0 E M
-rl a) M m
E W q. -- -� I
W U)
U)� U) -.-1...v
4-)W 00
O 0 171M
0 4-) O -r1 s.1
1:4 IO AG U) 0
a) a) a)
> > >
-ri -r1 -pi
kr' 14 r 14 c
QV' ON C1r
0 WO 0 $40 0 0 0 -0
4- E 'O E N E n
CO a)•t' a)d' wN
O 0 0 M
a wz wz wZ
KNOLLWOOD NEIGHBORHOOD MEETING MINUTES
Hopkins Raspberry Room
November 25, 1991 7:00 p.m.
CALL TO ORDER
The meeting was opened at approximately 7:15 p.m. by Lee Gustafson, Director
of Public Works. Mr. Gustafson introduced the project, provided a synopsis of
the background to date and indicated it is the City's and RLK's intent to
gather input and comments from the neighborhood regarding the study prepared
by RLK Associates.
The consultants, Dick Koppy and John Dietrich were introduced and the meeting
turned over to Dick Koppy to present the findings and recommendation.
The executive summary was utilized as the outline for the discussion and the
following minutes identify the discussion which took place.
Attached is a copy of the executive summary and list of the individuals in
attendance.
DISCUSSION
A preliminary assessment roll has been prepared. No detail design has been
done at this time. Financing: 15 years , at 8%
Colored curb. Why is it at 100% to the neighborhood? The City considers it
as an extra
Lee Gustafson suggested 70 -30 split on items contained in road policy 7D vs. a
100% aesthetic feature.
A 20 foot roadway offers a number of attributes. Why doesn't the City
consider picking up the cost of the colored curb, not a give and take on the
City's part.
Policy 7D does not contain colored curb clarification, City Council may have
to decide how this assessment will be handled.
What is the benefit to the owners?
1. Majority of residents signed a petition for street improvements.
Council could force an improvement. City legally has the right to do
whatever they want in the right of way.
2. The City is trying to have a joint venture and find an acceptable option
and attempt to maintain in acceptable long term condition. The answer
is to improve the streets. A petition was signed by the majority of
residents in order to obtain the lowest price to have it done.
3. View foils of all existing and proposed utilities roadways and widths
were shown on the overhead projector. Slides were also used to
illustrate the appearance of features and proposed improvements.
Meeting Minutes - Knollwood
November 25, 1991
Page 2
The neighborhood is requesting:
1. Bituminous curb - looks the same as existing roadway
City desire from a maintenance /policy view.
1. Concrete curb and gutter - colored is not part of 7D
Streets
1. Maintain general alignment as currently exists, acquire easements from
private property owners /no purchase of right of way will be done.
2. Maintain general alignment to preserve trees, walls, etc.
Storm Sewer
If the road is existing on private property currently, are assessments
necessary.? Are rights grandfathered in? Legally, we as consultants,
have to build the project on public right of way.
Standing water at 810 and 820 Edgemoor, swale to the drainage system depending
on tree location, may be underground.
1. Outflow will not exceed present flow into Minnehaha Creek Watershed
2. Back of report lists problem areas in detail - want to know of areas
which we need to take care of.
3. Propose mountable curb and gutter to provide edge control, water removal
and life extension of the roadway surface.
Discussion on approaching the property owners on easements and the pond issue.
The privately owned pond has no existing easement.
Neighborhood wants to know /propose color of rip rap for sedimentation pond.
Existing storm - Dredging as we place the sedimentation basins with a future
clean out planned. Further study is needed on pond maintenance and quantity
of dredging. Primarily, the storm water capacity and sediment ponds are
adequate drainage system. What is the City's responsibility to maintain the
ponds since the water is directed to them? Aeration and water clarity are not
a purely aesthetic issue.
Aeration of the pond was discussed; additional service on the aerators,
conduit to be pulling to the island, expense of the aeration. DRC committee
will study aeration issue and get back to City /Consultant with direction.
Sanitary Sewer Lines
1. Existing and proposed sanitary sewer maps with alternatives were shown.
Meeting Minutes - Knollwood
November 25, 1991
Page 3
2. Televised the lines - findings to be reported at the public hearing on
December 3 to include costs, esthetics, service to neighborhood, etc.
3. Alternatives to removing pipe from under 602 Edgemoor.
4. Careful evaluation of sanitary sewer will be necessary to determine the
cost and amount of work to be performed.
5. What type of guarantee does the neighborhood have regarding replacing
pipe which will need replacement in 15 -20 years? RLK is making that
determination now.
6. Hedge and tree replacement is not assessable and will be replaced where
utility lines are run, e.g. Alternate C for sanitary.
Existing Watermain
1. Existing and proposed watermain maps were shown.
Discussion included the fact that existing watermain is cast iron pipe.
Contact property owners and recommend lead service pipe be replaced.
However, it was stated that there is no State law saying lead line be
replaced. New watermain will be ductile iron pipe.
2. Looping of two dead end mains. Will improve fire protection and
pressure.
3. Replacing of watermain and sanitary sewer will be closely tied due to
location of each other.
Curb
Discussion took place on bituminous curb vs. colored curb. If colored
concrete to be used it was felt the split should be 70/30. This is for
Council to decide. It was felt that it would be better for the City to split
70/30 than to have City crews making regular maintenance repairs to the
bituminous curb. The cost savings to be realized by the City would be
significant to have concrete in vs. bituminous. The City should pay for 100
% of the difference between the bituminous curb option and colored concrete,
in order to meet the City objectives.
There will be a petition presented to Council for the December 3 meeting
representing the views of the neighborhood.
Landscaping
Budget proposed will be used to address the following:
1. Restoration of boulevard and lawns.
2. Retaining walls where necessary
3. Planting of perennial flowers /shrubs at pond's edge.
Meeting Minutes - Knollwood
November 25, 1991
Page 4
4. Replacement of plant material lost due to construction.
5. Mitigative measures for saving significant trees
6. Increase buffer on Edgemoor Avenue.
7. A total of four trees are proposed to be removed, additional trees may
be affected upon detail design investigation. Specifications may be
written to protect trees and have contractor replace and water the
plants for the first year.
8. Attempt to keep the new road away from the existing trees and not
encroach closer than the existing road.
9. Utility trenching locations will have to be closely monitored.
Other Discussion
The City may attempt to acquire the right of way to the Amhurst fence.
Maintenance of the fence was discussed to be left with Amhurst. It was
recommended direction come from the DRC on what is needed from the
encroachment into St. Louis Park.
RLK Associates will work with a design committee from the neighborhood.
Project to be bid in mid -March with improvements beginning in May thru
October, 1992.
The neighborhood wishes will be taken into account.
First assessment to be made in April of 1992 with recommendation of 20 years.
RLK will have input from private utilities as to their future design and
coordinate their improvement with project.
Construction phasing presented. Most likely will be under one general
contractor. Attempt to keep disruption to a minimum with access to properties
at all times. Road surface will most likely be gravel until the end of the
project. Paving will be done at the end. Construction to be between May to
mid - October.
Actual time of construction in your area will be six weeks (plus- minus).
Meeting adjourned at 10:00 p.m.
Name
John Dietrich
Dick Koppy
Randy Engel
Tom Kelley
Ben Cohen
Jack Helms
Harry Smith
Charles Simpson
Genevieve Simpson
Arthur H.
Irene Barron
Sharron Steinfeldt
Oren Steinfeldt
KNOLLWOOD NEIGHBORHOOD MEETING
November 25, 1991
Hopkins Raspberry Room 7:00 p.m.
Representing
RLK Associates, Ltd.
RLK Associates, Ltd.
810 Valley Way
413 Cottage Downs
602 Edgemoor Drive
805 Park Terrace
825 Park Terrace
301 Wilshire Walk
301 Wilshire Walk
830 Edgemoor Drive
115 Cottage Downs
240 Bridle Lane
240 Bridle Lane
1
Phone Number
933 -0972
933 -0972
933 -6813
835 -7000 (work)
938 -0204
938 -2514
933 -2023
935 -6091
935 -6091
935 -2129
938 -6263
935 -4253
935 -4253
CITY OF HOPKINS
Hennepin County, Minnesota
RESOLUTION NO: 91 -149
RESOLUTION ORDERING IMPROVEMENT AFTER PUBLIC HEARING
KNOLLWOOD STREET RECONSTRUCTION, PROJECT 90 -01
WHEREAS, a resolution of the City Council adopted the
nineteenth day of November, 1991, fixed a date for a
Council hearing on the proposed improvement of Cottage
Downs, Park Terrace, Bridle Lane, Valley Way, Wilshire
Walk, Edgemoor Drive and alleyway off Cottage Downs
pursuant to a petition of affected property owners;
WHEREAS, ten days mailed notice and two weeks published
notice of the hearing was given, and the hearing was
held thereon on the third day of December, 1991, at
which all persons desiring to be heard were given an
opportunity to be heard thereon,
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF
HOPKINS, MINNESOTA:
1. Such improvement is hereby ordered as proposed in
the Council resolution adopted the nineteenth day of
November, 1991, and amended as follows:
a. Using the guidelines of Roadway Policy #8 -B,
the City shall participate in 30 percent of
concrete curb and gutter construction costs
whether the concrete is colored or of the standard
type.
b. Although no parking restrictions are being
considered as a result of this project, Council
reserves the right to examine this issue in the
future and streets may be subject to parking
restrictions on an "as needed" basis or based upon
general City parking requirements.
c. The alleyway off Cottage Downs shall be
reconstructed with a bituminous surface and
concrete curb and gutter to a 10 foot face -to -face
width. 70 percent of reconstruction costs shall
be borne by the entire neighborhood, and the City
shall participate in 30 percent of the costs.
d. Parcels of land addressed at 601, 711, 715,
805 and 809 Oakridge Road shall be deleted from
further project consideration.
•
Adopted by the City Council of the City of Hopkins,
Minnesota, this third day of December, 1991.
ATTEST:
2. RLK Associates, Ltd. is hereby designated as the
engineer for this improvement and shall prepare plans
and specifications for the making of such improvement.
B
James A. Genellie, City Clerk
Nelson W. Berg, Mayor