1988-070
CITY OF HOPKINS
Hennepin County, Minnesota
RESOLUTION NO. 88-70
RESOLUTION DECLARING COSTS TO BE ASSESSED AND
ORDERING PREPARATION OF PROPOSED ASSESSMENTS
WHEREAS, certain improvements, all as more fully
described in Exhibit A hereto attached and hereby made a
part hereof have been previously ordered and completed:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF HOPKINS, MINNESOTA, as follows:
1. That the cost of each such improvement to be
specially assessed is hereby declared to be the cost of the
amount to be assessed, whichever is greater, which appears
in said Exhibit A.
2. That the City Clerk, with the assistance of
Director of Engineering, forthwith calculate the proper
amount to be specially assessed for each such improvement
against every assessed piece or parcel of land within the
various districts or locations affected without regard to
cash valuation, as provided by law, and he shall file a copy
of such proposed assessments in his office for public
inspection.
The Clerk shall, upon the completion of such proposed
assessments, notify the Council thereof.
Passed and adopted by the Council of the City of
Hopkins, Minnesota, this 2nd day of August, 1988.
JAMES A. GENELLIE
City Clerk
JERRE A. MILLER
City Attorney
DONALD J. MILBERT
Mayor
E X H I BIT A
1. Project 87-01 Installation of fire protection sprinkler
system at 21 Harrison Avenue North, the area proposed to
be assessed being Lots 14, 15 and 16 and that part of
Lot 17 lying SEly of NWly 15 ft. thereof incl. adj. 1/2
of alley vac. and adj. 1/2 of st. vac. 4/67, West
Minneapolis Center (P.I.D. 19-117-21 31 0043), and the
total cost for the project being $34,860. '
2. Project 87-02 Fire hydrant installation at 1002-2nd
street Northeast, the area proposed to be assessed being
Tract M and that part of Tracts P and L Reg Land Survey
No. 561 lying NEly of a line run from a point on the
NWly line of said Tract P a dis of 66.79 ft SWly from
the most Nly cor of said Tract P to a point on the Sly
line of said Tract L a dis of 770.15 ft E from the most
Wly cor of said Tract L also that part of Lot 91 Aud.
Sub. No. 239 lying E of a line run from a point on the
N line of said Lot 91 a dis of 31.21 ft W from the most
Ely cor of said Lot 91 to a point on the SEly line of
said Lot 91 a dis of 29.96 ft SWly from the most Ely
cor thof (P.I.D. 19-117-2l 13 0019) and that part of
Tracts P and L Reg Land Survey No. 561 lying SWly of a
line run from a point on the NWly line of said Tract P
a dis of 66.79 ft SWly from the most Nly cor of said
Tract P to a point on the Sly line of said Tract L a
dis of 770.15 ft E from the most Wly cor of said Tract
L also that part of Lot 91 Aud. Sub. No. 239 lying Wly
of a line run from a point on the N line of said Lot 91
a dis of 31.21 ft W from the most Ely cor of said Lot
91 through a point on the SEly line of said Lot 91 a
dis of 29.96 ft from the most Ely cor thof (P.I.D.
19-117-21 13 0020), and the total cost for the project
being $7,015.
3. 87-04 Improving an Alley at 358-19th Avenue North by
concrete surfacing, the area proposed to be assessed
being (P.I.D. 23-117-22 14 0030) Lot 1 and North 16 ft
of Lot 2 and (P.I.D. 23-117-22 14 0041) Lot 30 and North
16 ft of Lot 29, all in Block 3, West Minneapolis Third
Division, the total cost being $4,692.
4. 87-07 Installation of a wat r main xtension, th area
proposed to be assess d being that part of NW 1/4 of SW
1/4 desc as beg at a pt on N line thof dist 250.82 ft E
from the intersection of said N line with SEly r/w line
of C.M. st. P & PRy, th SWly to a pt on a line drawn
SEly at ria's to said r/w line and dist 150 ft from said
pt of intersection th SWly par and dist 150 ft SEly of
said r/w line to W line of NW 1/4 of SW 1/4 th S to SW
cor thof th E along S line thof to W line of Westbrooke
Patio Homes th N along said W line to N line of NW 1/4
of SW 1/4 th W to beg, except road, Sec 25 T 117 R 22
(P.I.D. 25-117-22 32 0092); Lot 1, Block 1 (P.I.D. 25-
l17-22 33 0003) and Lot I, Block 2 (P.I.D. 25-117-22
33 0004), Opus 2 Ninth Addition; and Lot 1 (P.I.D. 25
117-22 33 0005) and Lot 2 (P.I.D. 25-117-22 33 0006),
Block 1, Hills of Oakwood, the total cost being $28,350.
5. 87-08 Installation of fire protection sprinkler system
at 107 Shady Oak Road, the area proposed to be assessed
being (P.I.D. 23-117-22 44 0016) the property commencing
at SW cor of Tract A, Reg. Land Survey No. 610, th W
along the extension of the S line of Tract A, R.L.S. No.
610 to W line of SE 1/4 of SE 1/4, th N along said W
line dis 398 ft th E 168 ft th S 90 ft. th E to W line
of 20th Avenue South, th S along 20th Ave. So. to N line
of R.L.S. No. 610, th W to NW cor of Tract A, R.L.S. No.
610 th S to pt. of beg., ex road Sec 23 T 117 R 22,
total cost being $35,259.
6. 88-01 Installation of a sprinkler system for fire
protection at 10-12th Avenue South, the area proposed
to be assessed being Lots 7 and 8, including 1/2 of
vacated alley, Block 8, West Minneapolis (24-117-22 34
0085); total cost being $30,903.60.
7. 88-02 Installation of a sprinkler system for fire
protection at 907-915 Hopkins Center, the area proposed
to be assessed being Tract C, Tract D, Tract E and
Tract F, Registered Land Survey No. 953 (P.I.D. 24-117-
22 31 0003, 24-117-22 31 0004, 24-117-22 31 0005, 24-117
22 31 0006); total cost being $24,234.
8. 88-03 Installation of a sprinkler system for fire
protection at 901 Mainstreet, the area proposed to
be assessed being Lot 10, Block 68, West Minneapolis
Second Division (P.I.D. 24-117-22 31 0014); total cost
being $19,003.95.
9. 88-05 Installation of a sprinkler system for fire
protection at 1410 Mainstreet, the area proposed to
be assessed being the property commencing at a pt
in the S line of Excelsior Avenue 389 ft W from E
line of SW 1/4 of SW 1/4, th W along said S line a
dis of 239 4/10 ft th S 350 ft par with the Eline
thereof th E 259 2/10 ft par with the S line of
Excelsior Avenue, th Nly to beg. (P.I.D. 24-117-22
33 0003); total cost being $37,038.75
10. 88-09 Construction of a parking ramp at 26-10th Avenu
South, the area proposed to be assessed being 1011 First
Street South described as Lots 14, 15 & 16, also Lots 18
through 22 incl said Blk 6 & th S 15 ft of Lot 23 said
Blk 6 incl the adj 1/2 of the vac alley (24-117-22 34
0123) and Lot 17 incl 1/2 vac alley (24-117-22 34 0049)
total cost being $$391,998 for construction and $12,000
for maintenance.
11. Stump removal at 1020 Oakridge Road, N 80 ft of SE 1/4
of NW 1/4 of SE 1/4 except road, Sec 13 T 117 R 22
(13-117-22 42 0012), total cost being $271.00.
12. Tree removal at l25-12th Avenue South, Lot 12, Block
10, West Minneapolis (24-117-22 34 0108), total cost
being $511.20.
13. Weed removal at 633-8th Avenue South, Lot 16, Block 61
West Minneapolis (P.I.D. 25-117-22 13 0075) and Lot 15
Block 61, West Minneapolis (P.I.D. 25-117-22 13 0074),
total cost being $104.00.
14. Snow removal at 805 Mainstreet, Lot 9, Block 67, West
Minneapolis 2nd Division (P.I.D. 24-117-22 42 0067),
total cost being $130.20.
15. Delinquent utility bill at 402-10th Avenue North, Lot
3 and that part of Lot 2 lying S of N 19-6/10 ft
thereof, Block 105, West Minneapolis Second Division
(P.I.D. 24-117-22 21 0006), total cost being $332.00.
16. Delinquent utility bill at 1702 Mainstreet, North 122
ft of Lots 6, 7 and the E 25 ft of Lot 5, Block 2,
Boulevard Manor (P.I.D. 23-117-22 44 0036), total
cost being $396.60.
17. Delinquent utility bill at 25-9th Avenue North, N 40
ft of Lot 18, Block 67, West Minneapolis 2nd
Division (P.I.D. 24-117-22 42 0075), total cost
being $346.50.
18. Delinquent utility bill at 221-13th Avenue North,
Lot 16 and N 25 ft of Lot 15, Block 91, West
Minneapolis Second Division (P.I.D. 24-117-22 24 0080)
total cost being $199.60.