Loading...
Letter- Appearance by Mel WynkoopDATE: March 12, 1982 TO: William P. Craig, City Manager FROM: Anne Norris SUBJECT: Appearance by Mel Wynkoop Mel Wynkoop of Mel's Remodeling, Inc. bid $4,275.00 to install a security door to the upstairs and remove lockers and install display cases and coat racks at the Hopkins Community Center. The bid was accepted January 5, 1982 and the contract was signed January 11, 1982. Mel Wynkoop now would like to be released from the contract; he based his bid on a verbal quotation from a subcontractor and the subcontractor now says that the work cannot be done for the price quoted. Mel has begun the work; he has removed the lockers from the Community Center. However, if Mel is released from the contract, he will accept no payment for this work.