Letter- Appearance by Mel WynkoopDATE: March 12, 1982
TO: William P. Craig, City Manager
FROM: Anne Norris
SUBJECT: Appearance by Mel Wynkoop
Mel Wynkoop of Mel's Remodeling, Inc. bid $4,275.00 to
install a security door to the upstairs and remove lockers
and install display cases and coat racks at the Hopkins
Community Center. The bid was accepted January 5, 1982
and the contract was signed January 11, 1982.
Mel Wynkoop now would like to be released from the contract;
he based his bid on a verbal quotation from a subcontractor and
the subcontractor now says that the work cannot be done for the
price quoted.
Mel has begun the work; he has removed the lockers from the
Community Center. However, if Mel is released from the contract,
he will accept no payment for this work.