Item 84-136 Contract AmendmentPROJECT: llth Street South
ER: City of Minnetonka
OWNER'S PROJECT NO. 4770 (City)
TO:
BY:
DATE:
ENGINEER
BY:
OPUS CORPORATION
(Larry A. Donlin, Mayor)
10 -31 -84
• he above changes are approved:
CITY OF HOPKINS
CONTRACT AMENDMENT 4/ 1
DATED 10 -31 -84
You are directed to make the changes noted below in the subject contract.
OWNER: City of Minnetonka BY:
Nature of Change: Due to the instability of the subgrade of llth Street, it was necessary.
0 at the instruction of Braun Engineering, the soils engineers for the project, to force the
organic soils along the shear plane to the north, requiring excessive amounts of common
borrow, which Opus Corp furnished to us at the contract price.
Original Contract Price $ 497,106.79
Total of Previously Authorized Change Orders $ -0
Net decrease resulting from this Change Order S -0-
Net increase resulting from this Change Order $ 90,336.40
Current Contract Price Including All Change Orders $ 587,443.19
This Change Order results in the following adjustment of Contract Time:
Date
CONTRACTOR
BY:
DATE: DATE:
James F. Miller, City Manager
DATE:
NONE
PLEASE NOTE: The above Contract Amendment has been checked and it has been determined that
the Contractor at this point has completed % of the total contract; therefore,
there is more than adequate bond capacity available to cover this amendment.