Memo - 2011-2015 Capital Improvement Plan0 CITY OF HOPKINS 0 MEMORANDUM Date: June 8'2U|0 To: Mayor 6LCity Council From: Christine Barkuss, Finance Director Sub�lect: 2011 — 2015 Capital Improvement Plan (C.I.P.) Attached iaaproposed C|Pwhich has undergone several staff revisions. /\tthe work session we will review tile 20|l-20|5document and incorporate any changes from tile work session discussion. Included inthis packet are the following — l. Sum muryufchanges inthe 20|\-20(5ClP Z. The cash flow statements by fund 3. Projects summarized by year and funding source fo*the years 20||-20|5 4. Individual project sheets providing description of the prqJ1ect, 'ush6otion' and funding source. 0 SUMMARY OF CHANGES IN THE 2011-2015 CIP Park Dedication Fund 1. Shady Oak Beach project has been reduced from $110,000 over 4 years to $63,000 over 3 years due to grant funds received, a savings of $47,000. 2. Skate park commitment or $7,000 ends in 2011; renewal of agreement is not budgeted. 3. New item — Miscellaneous Park Projects has been added at $10,000 for the years 2011 and 2012. 4. Hilltop Park play equipment was moved from 2011 to 2014 5. Depot Recreation Area — new project added with funding from other governmental units and/or grants. Project totals $500,000. 6. Park dedication fees adjusted for years 2012-2015 Capital Improvement Fund 1. All Pavilion projects formerly in the CIF have been moved to the Pavilion Fund 2. Arts Center carpet project adjust to $9,800 to allow for an option of wood or wood laminate flooring in the art gallery to give that room a more "gallery" feel. 3. Activity Center carpeting project moved from 2011 to 2014. 4. Parking Lot 200 moved from 2013 to 2016 5. Tax levy of $100,000 has been budgeted MSA Fund 1. Cash flow spreadsheet now shows the detail of funds due from the State on various MSA road projects. • a. 2014 — Co Rd 61— Shady Oak Rd b. 2015 — 6`h St S (1 I" — 12'h Ave) c. 2015 — Co Rd 3 PIR Fund 1. Bonds will be sold in 2010 2. Residential street improvements —page 26 of project sheets a. 2011 - $1.950,000 i. PIR - $1,040,000 — up from $900,000 ii. SA - $910,000—up from $710,000 b. 2012 - $1,730,000 i. PIR - $900,000 — same ii. SA - $830,000 —same c. 2013 - $1,640,000 i. PIR - $910,000 — same ii. SA - $730,000 — same d. 2014 - $2,100,000 i. PIR - $1,100,000 —same ii. SA - $1,000,000 - -same e. 2015 - $1,800,000 i. PIR - $900,000 ii. SA - $900,000 f. All these totals include both PIR funding and Special Assessments 3. New for 2011: Emergency vehicle preemption (EVP) signal upgrade - $40,000 0 Water Fund 1. Residential street imprmements a. 2O1 I -.S75.000 b. 2012 - $75.000 C. 20 1 ; - $80.000 d. 22014 - S80.000 e. 201; - $90.000 2. Continuation of meter replacement - 595.000 for 4.ears. ; \cars rtmai11112 3. St. Louis Park Fmcr(enc-\ Connection m0N ed from 201 1 to 2012 4. New - 8`" A\ e IRT Corridor - 5250.000 Sanitary Sewer Fund 1. Residential street impr0Nemcnts a. 2011 - S 100.000 b. 20 12 - $100.000 C. 201 : - $100.000 d. 2014 - $100.000 e. 201 5 - S 100.000 2. Lift Station Y.1 mug ed from 2010 to 201 3. New - 8`]' A\ e LRT Corridor - W0.000 Storm Sewer Fund I. Residential street impro\ements a. 201 1 - $100.000 b. 2012 - S 100.000 C. 2013 - S 1 10.000 d. 2014 - S 1 10.000 e. 201; - S 1 10.000 2. New - 8"' A \ e LRT Corridor - S 100.000 Pavilion Fund 1. Pavilion bleacher heating - S18.000 mo\ cd from CIP Fund to Pa\ Ilion Fund and mo\ cel from 2011 to 2012 2. Beginning in 201 1 all Pavilion projects \\ ill be funded b\ the Pa\ 111011 Cable TV Fund (no\\ kno\\ n as the Communications Fund) 1. Final project is the automated play back project scheduled for 201 1 is PARK CAPITAL IMPROVEMENTS FUND (301) 05/26@010 0 Actual Actual Projected Projected Projected Projected Projected Projected 2006 2009 201- 2011 2(112 2013 2014 2015 Working Capital Beginning Year 434,115 357,936 246,523 215,968 191,148 123,060 95,290 37,243 Revenues: Interest 13,465 4,740 2,465 2,160 1,911 1,231 953 372 Dedication fees 0 0 10,000 10,000 25.000 30,000 30,OOD 30,000 Joint Recrefunds 7,174 Donations -general 1,500 2,526 1,000 1,000 1,000 1,000 1,OOD Donations - benches 700 Total Revenues 22,139 7,966 13.465 13160 27,911 32,231 31,953 30.372 Expenditures: C.I.P. Projects 98,318 119,379 44,000 38,000 96,000 60,000 90,000 0 Total Expenditures 98,318 119,379 44,000 38,000 96,000 60.000 90,000 0 Working Capital Year End 357,936 2+1b,1�,1 215,988 191,148 123,060 95,290 37,243 67,615 2f0 Protects 21.000 Shady Oak BeachPlay Area Renovation (Total $63,000 (net of grant funds) paid over 3 years at $21,000 each year) 16,000 Valley Park Basketball Courts - was a 2009 project and did not get completed. 7,000 Skate Park improvements 44,000 2011 Proiects 21,000 Shady Oak BeachPtay Area Renovation 10,000 Miscellaneous Park Improvements (was in at $20,000 move $10,00010 2012) 7,000 Skate Park improvements - last year of our agreement 38,000 2012 Projects 65.000 Valley Park Play Equipment 21,000 Shady Oak Beach Play Area Renovation 10,000 Miscellaneous Pak Improvements 96,000 2013 Projects • 60,000 20f1 Projects Oaks Park Play Equipment 45,000 Park Valley Ploy Equipment 45,000 Hilltop Park Play Equipment - formerly in for 2011 90,000 2015 Proiects none - Depot Recreation Area - all funding OGU or grants 0 CAPITAL IMPROVEMENTS FUND (305) actual Actual Projected Projected P,olectea Projected (role-ted Pr0lerted 2008 200920, 0 2211 201^ 2013 2014 2015 Working Capital Beginning Year 1 � 4 214 248 5?7 235 382 157 241 211 613 25(' 62' 113 230 203 332 Revenues: Miscellaneous Interest 7 OSO 4 245 '_ 359 1 52 _ it,' 2 600 1 132 2 034 Federal Stimulus Funds Transfers In from General Fund Tax Levy 72 082 95--76 D 1 DO X,D 125 D00 125 Ono 125 300 125 00 Total Revenues 79 1r,2 99-21 f7 359 101 572 127 110 1 27 006 125 132 127 C34 Expenditures. Pavilion Projects O 3C 493 3E ]D] 15 00D C.IP. Projects 24 439 31 513 146 DCD 9 3O7 52 500 275 DOC, 36 000 C Transfer to General Fund 50 200 Total Expenditures 24 839 112 "6 140 OOD 4- 3r] 77 50C 275 000 36 DOO C Worting Capital Year End 248 537 235,832 ' 57 241 211 .1'. 26r. 523 1 13 230 203 362 330 352 2010 Projects 13D Doo City Hall Boiler Replacen-erd , SC5 00] pd ;nth Fec SUmulus `ands i 15 000 Art Corter- ca,pet replacement - ; anous roans & hall,.ay 145 000 - ong,na+ schedrne on the carpet s%as 207 2011 Projects 082x0 Art Center- Rcdepenninq Gallery ramet 2012 Proiects 53 000 Actwty Center - HVAC Cpgrade 12 50) Art Center- Office rarpet C25,07 2013 Prolects 275 OW AcLwry Center -H%. AC Sy,tem 2014 Projects 3n OCn) iruviy Center- Paspber-y roam carpet 2015 Projects no prcjecs MUNICIPAL STATE AID FUND (302) Actual Actual Projected Projected Projected Projected 2008 2009 2010 2011 2012 2013 Working C 57,078 235.317 813,817 941,946 1,276,366 1,614,129 Revenues Projected 2014 2015 1,955,271 State U 87,139 325,000 237,861 1,955,271 State N 258,907 360,898 325,000 325,000 State li 325,000 325,000 Project Di: (1,380,932) (325.000) (325,000) (325,000) Interes 11,997 12,679 8,138 9,419 Henna 122.209 117,991 Henne Total M! 61,270 d1 iO 61,270 61,270 358,046 (2) 61,270 61,270 Transf, MSABelar 61,270 Bond is Project Total Due 270,904 853,832 451,129 334,419 Expenditu From Stats To Date Due 5131110 TranO 5,408,756.28 3,243,792.74 2,106,963.85 1,136,828.89 CIP Sl 92,665 275,332 323,000 0 Debt s (3) AIR o4T and will be sent as funds 92,665 275,332 323,000 0 Working C 235,317 61011 941,946 1,276,366 includes r 63.17% 325,000 325,000 12,764 16,141 337,764 0 512 612 01 0 Projected Projected 2014 2015 1,955,271 (2,138,026) 87,139 325,000 237,861 1,955,271 19,553 (21,380) 341,141 344,553 303,620 0 0 4,437,849 1,000,000 0 0 4,437,849 1,000,000 1,614,129 1,955,271 (2,138,026) (2,834,406) 0 State MSI Balance F, 1,122,025 61,270 61,270 61,270 61,270 61,270 61,270 61,270 Annual Alk 320,177 325.000 325,000 325,000 325,000 325,000 325,000 325,000 Project Di: (1,380,932) (325.000) (325,000) (325,000) (325,000) (325,000) (325,000) Debt Servi Total M! 61,270 d1 iO 61,270 61,270 61,270 61,270 61,270 386,270 MSABelar 61,270 Project Total Due Paid Balance State Aid Funds due City Total From Stats To Date Due 5131110 (1) No mon can be used for debt service Excelsior Blvd 5,408,756.28 3,243,792.74 2,106,963.85 1,136,828.89 (2) Excelsients Minnetonka Blvd 1,231,889.51 950,955.56 - 950,95556 (3) AIR o4T and will be sent as funds become ache schedule. Total funds to be Total 6,640,645.79 4,194,748.30 2,106,963.85 2,087,784 45 • received tr 63.17% 2000 - Col Upgrade 2001 - Core S, CSAH7315 Intersection 2002 - Core S, Cc 61, Hwy 717th Ave/CSAR 73 Intersection Imp CSP 2003 - CoM7315 Intersection, CSAH 5 Corridor Imp 2004 - Co, CSAH 5 Corridor Imp 2005 - ExtSAH 7315 Intersection, CSAH 5 Corridor Imp 2006 - Ext 2007- Coetscape Imp 2008 - MS 2009 - non 2010 - 5thte limits - reconstruction 2011 - non 2012 - non 2014 - Cowbrook Rd and Co Rd 61 Shady Oak Road 2015 - S4ounty Rd 3 0 0 WATER FUND - WORKING CAPITAL PROJECTION Prz -t- 1, '4 2016 Working Capital Beginning Year 2,- 314 i 1 7� 1— �4- �-e 4— ---2 Revenues. Operating Revenues 1 124 C' -i 1 1 4- 4-4 Other — -7L t 122 Interest Transfer In - Storm Sewer Bond Issuance Total Revenues I 1_1_�1- :Ac �-Q 4.' 1' -- Expenditures Operation Expense �-E 5 :,4 Loss on disposal of asset '2 -4E Other Exp - int On current bonds Other Exp, - int on refunded bonds— '4 t:_ .1 4 - -�7 Other Exp - its on 2009 bonds -''4 Other Exp - irK on 2011 bonds— :4 Transfer Out - Storm Sever Loan Capital Outlay (perERP) 14 Water System Maintenance Capital Improvements 1?E 44-- �4: Capital Improvements- PW Sicill Principal Bond payment 1K 4'- 1 ;c Principal Bond payment - refunded Principal Bond pyo - 2009 debt Principal Bond pynint - 2011 debt 2z C Capital Lease (PW Facility) 4_ 4= Total Expenditures 1 a2� =C� 1 '8� '8_ P4 eK 1 43F Change in available funds 72 1 4'.; -'w 1 27 �-4 Inventory change Working Capital Ending Year (314.013) 1099,067 71,405 645,978 475.252 329,131 429,791 248.957 Rate Histo 2010 2017 f—f-li tiara Has taken fto,?l the Lh,bty MasterPlan d— by C-ty, E,ig,—r 1984 S085 1993 S105 Notes - 1997 S1 10 —r a, liht, -,tar c—[ cFt 2000 $120 2005 $1.40 a1 !,'e—r zepi---t- Per Utility Master Plan (10107) 2008 S165 -e, al 2OD9 $1.86 -at 2010 $11.90 ge— a!S',eet 2011 S1.94 �e, - a! �.,eet 't_ - S- 2012 $1.98 Zi "leet 2013 52.02 --c 201452.08 Dm1x1 state _.t4--_-., 1 T et unpin-.=_rc-!s - Se, 2015$211 1' S" 2016 $216 1 2017 $2.21•Mesa era tat rtes per rat UMP 0 Working Capital Beginning Year Revenues: Operating Revenues Grantsl0ther Govt Funding Other Interest Transfer In - Storm Sewer Fund Bond Issuance Total Revenues Expenditures Operation Expense MMC Charges (3%in lason) Interest Expense - 2009 Debt Interest Expense - 2011 Debt Transfer Out - Storm Sewer Fund Capital Outlay (per ERP) Met Council Vi Charge Capital Improvements Capital Improvements- PW Bldg Prinaoai Bore payment 12009) Principal Bond payment (2011) Capital Lease (PW Facility) Total Expenditures Change in available funds Inventory charge Working Capital Ending Year Rate Histon 1983 $1.50 1989 $1.75 1991 $200 1993 $250 1999 $2.25 RateDECREASE 2006 $2 50 rate increase Per Utility Master Plan (10107) 2008$2-70 2009 $3 10 2010 S3 40 2011S3.70 2012S4.00 2013 $4 30 profs recti 2014 S4 60 2015 $4.90 • 2016 S5 00 2017 $5 25 mese ere «M m.+sa.er+,: per me UMP 0 SEWER FUND - WORKING CAPITAL PROJECTION 06126/2010 Actual Actual Projected Projected Projected Projected Projected Projected 2= 244@ 24>Q 2011 24]2 24]2 20A 2M (17,766) (397.606) 413.499 226,675 942,562 699.099 701.729 732.710 1.453029 1379.518 1.936,000 2.109.000 2,280.000 2.451,000 2.622,000 2,793.000 190.000 21,445 19199 23.000 23.000 23,000 20,000 20.000 20.000 0 0 5,007 23,967 22,270 27,596 33,415 32.767 1.031 077 800 000 1 474,474 2.629 794 2 156 007 2,955,967 2.325.270 2.498,596 2 675 415 2845767 541,276 498,304 671.926 893,479 715,749 736,762 762.545 787,123 1.072,061 1,102, 794 1.149, 204 1.286.051 1,365,334 1.447 254 1.534.089 1626,135 21,501 33,750 32.650 31.450 30,100 28,450 25,000 40.000 38.500 37 000 35,250 0 0 0 0 0 0 35,700 6,600 166,991 167,836 450.000 100.000 275,000 100,000 100,000 450,000 50,000 60,000 60,DO0 60,000 60,000 30,000 30,000 35,000 35.000 50,000 50 000 50,000 50,000 50.000 50.D00 50 000 50.000 1.850.328 1,818934 2,342.631 2,240280 2.568,733 2.495,966 2644,434 3,078,758 (375,854) 810 860 (186,624) 715,687 (243,463) 2 630 30.961 (232.991) (3,966) 245 (307,6t11% 413,499 226,676 942,662 699.099 701,726 732,710 496,718 2009 - 2017 fbtrtclaf data was taken from rho Uti ft MasterPlan done by City Engbreer Notes• income - 2008 and forward used utility master plan rates (no fortune option) 2009 - Residential Street Improvements - $2001000, MSA Road Improvements - $50,000 2010 - Residential Street Improvements - $150.000, Lift Station #4 - $160.000. Upgrade Lift Station #1 - $220,000 LR Station 44 - 880.000 and Lift Station #r -$110.000-- revenue kom oilier gnvem"nis 2011 - Residential Street Improvements - $100,000: 2012 - Residential Street Improvements - $100,000: Lit Station Maintenance - $15,000 Lift Station #4 - $160.000 2013 - Residential Street Improvements - $100.000; 20 4- Residential Street Improvements -$100.000, 2015 - Residential Street Improvements - $100,000, 6th Ave LRT- $350.000 STORM SEWER FUND - WORKING CAPITAL PROJECTION .;ir, a � L3 ,z ete.: �. te, _ E;tE� �,rzez— :.ie-:eo Working Capital Beginning --- --- Year Revenues Operating Revenues 7 791.703 m -Z '4, E-- E-2 Other E Interest Transfer in - Water Fund T, "er In - Sanitary Sewer Fund Bond Issuance Total Revenues 4<42:' 4 Expenditures. Operation Expense 7�. — '27 -3- Bond Interest . existing bonds 2: 3 Bond Interest - refunded bonds E -r Transfer Out - Water Fund Transfer Out - Sanitary Sewer Capital Outlay (pw ERP) Capital Improvements Capital Improvements -PW Bldg 1999 Principal Bond payni I999 Principal Bd pymnt - re" 2001 Principal Bond payment 2003 Principal Bond payment Capital Lease Total Expenditures E':-44 14 Change in available funds Inventory change Villorking Capital Ending Year 351.098 851,624 160.721 551 378 947.899 1 333.795 1.525 571 1.835.128 Rate History Iver month) 1989 S4 76 per quarter 2009 - 2917 rt --1 data was taken from the L;b1 ty W11t,11 P1.1 d.- by City Engineer 1991 S6 00 per quarter 1992 S250 Notes - 1993S300 1993S300 -ree, -"p �'Q IM 5320 -n;p- 19995400 S, s'—, Ma,,- - S 1.'S� F1 ir, ­e,tS 2006$450 2;t, :.,I St,,e! t 's S' S t - , �- r.1, , 2m 1111.00 Z" 4 - er 'i TIF-- '121"t Trip 3ze .1,i rm, LzT • CABLE TV • WORKING CAPITAL PROJECTIONS 0512612010 Actual Actual Projected Projected Projected Projected Projected Projected 2008070 2010 2011 2012 2013 2014 2015 Working Capital Beginning Year 394,752 408,036 399,094 393,540 380,751 390,590 398,217 403,538 Revenues: Franchise Fees 203,285 200,908 170,000 170,000 170,000 170,000 170,000 170,000 Interest 13,633 6,167 3,991 3,935 3,808 3,906 3,962 4,035 Total Revenues 216,918 207,075 173,991 173,935 173,608 173,906 173,982 174,035 Expenditures: Expense 85,000 70,510 72,625 74,804 77,048 79,360 81,740 84,193 Transfer Out 86,920 86,920 86,920 86,920 86,920 86,920 86,920 86,920 Capital Outlay 31,714 58,587 20,000 25,000 - - - Total Expenditures 203,634 216,017 179,545 186,724 163,968 166,280 168,660 171,113 Change in available funds 13,284 (8,942) (5,554) (12,789) 9,839 7,626 5,322 2,923 Working Capital Ending Year 408,036 398,094 393,540 380,751 390,690 398,217 403,538 406,461 2009 Projects 45,000 Council Chambers Video ls ojed was done in 2008 a portion o)rnpr 1,500 Council Chambers Lectern Monitors 2010 Proleets 20,000 Council Chambers Lighting 2011 Projects 25,000 Automated Playback - digital recorder/players to control the channel - will be able to save council meetings on hard drive • Interfund ban - school lease Rev 2 " Interfund loan - school lease Exp 0 PAVILION - ICE ARENA WORKING CAPITAL PROJECTIONS Working Capital Beginning Year 3 :-4 Revenues Operating Revenues 4— Leases 'F Other Donations (bleacher heeling) Interest Advance from Equipment Rapt Transfer In Total Revenues E -,EE 5 - Expenditures Operation Expense 4 �7- Other Expense Transfer Out Capital Oullay Capital Improvements' Payment on Interfund Loan Total Expenditures Change in available funds Working Capital Ending Year (78.008) 167.489) (43,797) (13 524) (19.134) 31.333 17.598 (46,107) Pavilion Projects Schedided Pavilion Projects in 0P 2QL7 "-D ",j Lighting Upgrade Tile Replacement Heating & Cooing Rooftop Unit Eteac D -T -ep, 3 -el le't ChiW Controls z,pl—e— Interfund ban - school lease Rev 2 " Interfund loan - school lease Exp 0 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2011 thru 2015 FUNDING SOURCE SUMMARY Source 2011 2012 2013 Cable Television Fund Cl - Capital Improvement Fund ED - Economic Development Fund GU - Other Govemmental Units MS - Municipal State Aid Streets PA - Pavilion Fund PDF- Park Dedication Fund PF - Private Sector Funds PI - PIR/General Obligation Bonds PKG -Parking Fund SA - Special Assessment SF - Sanitary Sewer Fund SU - Storm Sewer Fund TF -Tax Increment Financing • WF - Water Fund • 2014 2015 Total 25,000 25,000 9,800 62,500 275,000 36,000 383,300 2,000,000 100,000 2.100,000 2,310,000 22,278,881 24.588,881 4,437,849 1,000,000 5,437,849 53,000 109,000 162,000 38,000 96,000 60,000 90,000 284,000 90,000 90,000 1,091,600 913,000 910,000 1,345,000 1,100,000 5,359,600 28,000 28,000 956,400 878,000 730,000 1,048,700 1,150,000 4,763,100 100,000 275,000 100,000 100,000 450,000 1.025,000 117,000 118,000 129,000 330,000 230,000 924,000 4,350,000 8,500,000 2,000,000 150,000 15.000,000 170,000 381,000 208,000 80,000 340,000 1,179,000 GRANDTOTAL 5,8e5,eoo 13,-sas,ouu 4,41L,uuu V.f11,04V c0,yu1,001 o�,riy,iw H'edimsdm,, May 26. 1010 City of Hopkins,'iN CAPIT.41. 1.1fPR01 F.11F_.VT PL.4A' • 2011 1111 i, 2015 PROJECTS BY FUNDING SOURCE Source Project- PrioritN 2011 2012 2013 2014 2015 Total Cable Television Fund Automated Playback 08-CIP-6054 ma 25 000 25 000 Cable Television Fund fotal 25,000 25.000 CI - Capital Improvement Fund Replace Carpet - Activity Center Rooms 08-CIP-AC015 n a 36 000 36 000 Activity CenterHVAC Upgrade 08-CIP-ACO20 n a 50 000 275 000 325 000 Replace Office Carpet - HCA Stages Theatre 08-CIP-AR006 n a 12 500 12 500 Arts CenterCarpet: Redepenning Gallery 08-CIP-.AR008 n a 9 300 9 800 CI- Capital Improvement Fu nd Iota1 9,800 62,500 275,000 36.000 383,300 ED- Economic �mens Fund Sixth Street South (11th to 12th Avenue South) 01-CIP-F504 n a 100 000 100 000 Block 64 Redevelopment Project 06-CIP-D404 n'a 2 003 000 2 000 000 • ED- Economic Development Fund total 2,000,000 100,000 2,100.000 GU -Other Governmental Un its County Road 3 01-CIP-S 1)4 n a 1 600 000 1 600 000 County Road 61 (Shady Oak Road) 01-CIP-S106 n'a 2 010 000 20 178 881 22 188 881 Highway 7 and 5th Ave North - Signal Replacement 10-CIP- 5120 3 300 000 300 000 Depot Recreation Area 10-CIP-8002 2 500 000 500 000 GU -Other Governmental t nits "Iota[ 2,310.000 22,278,881 24,588.881 MS - Municipal State Aid Streets Sixth Street South (11th to 12th Avenue South) 01-CIP-F504 n a 300 Ju0 300 000 County Road 3 01-CIP-S 104 n a 700 (q0 '00000 County Road 61 (Shady Oak Road) 01-CIP-5106 n a 4 437 849 4.437 849 AIS- Municipal State Aid Streets 1 ota1 4,437,849 1,000,000 5,437,849 PA - Pavilion Fund Pavilion tvlez Roof Replacement (North Section) 07-CIP-P315 n a 40 000 40 000 Pavilion Arena Bleacher Heating Replacement 08-CIP-P008 n ra 33 030 38 000 Pavilion Gas Fired Rooftop Furnace 09-CIP-P025 n a 9 000 9 000 Pavilion Evaporator Condenser Replacement 09-CIP-P036 n a 30.000 60 000 Ice Resufacer Water Heating System Replacement 09-CIP-P316 n a 15 000 15 000 r �J Source Project# Priority 2011 2012 2013 2014 2015 Total • PA - Pavilion Fund Total 109,000 16$000 21,000 21,000 PDF- Park Dedication Fund Shady Oak Beach Community Play Area 07-CIP-P219 n1a Play Equipment- Park Valley 08-CIP-P010 rda 45,000 Play Equipment- Hilltop Park 08-CIP-P014 nla 45,000 Play Equipment - Valley Park 08-CIP-P015 Na 65,000 Play Equipment - Oakes Park 08-CIP-P016 nla 65,000 Skate Park 08-CIP-R001 n/a Miscellaneous Park Improvements 10-CIP-P017 n1a PDF- Park Dedication Fund Total 7.000 10,000 10,000 PF - Private Sector Funds Activity Center Cafe on 14th 09-CIP-AC032 nla 60,000 PF - Private Sector Funds Total 284,000 90,000 PI - PIR/General Obligation Bonds 90,000 Residential Street Improvements 01-CIP-S101 n! Citywide Concrete Alleys 01-CIP-Sf 03 nl 900,000 County Road 61 (Shady Oak Road) 01-CIP-S106 n/ 4,850,000 Highway 7 and 5th Ave North - Signal Replacement 10-CIP- S120 Emergency Vehicle Preemption (EVP) Signal Upgrade 10-CIP-S119 • P1- PIR/General Obligation Bonds Total 100,000 200,000 300,000 PKG - Parking Fund Seal Parking Ramp Concrete Decks 10-CIP-F504 n/ PKG - Parking Fund Total 40,000 1,091,600 913,000 910,000 1,345,000 SA - Special Assessment 5,359,600 Residential Street Improvements 01-CIP-S101 nl Citywide Concrete Alleys 01-CIP-S103 n/ County Road 61 (Shady Oak Road) 01-CIP-S106 n/ 28,000 SA - Special Assessment Total 830,000 730,000 1,000,000 900,000 4,370,000 46,400 SF - Sanitary Sewer Fund Eighth Avenue LRT Corridor 01-CIP-F503 nl Residential Street Improvements-Utilties 01-CIP-S102 nl 250,000 Lift Station # 4 08-CIP-11001 nl 730,000 Sanitary Sewer Lift Station Maintenance 08-CIP-11009 nl SF - Sanitary Sewer Fund Total 350,000 350,000 100,000 100,000 SU - Storm Sewer Fund 100,000 Avenue LRT Corridor 01-CIP-F503 nl •Eighth Residential Street Improvements -Utilities 01-CIP-S102 nl a a a 3 2 a a a a a a a a 53,000 109,000 16$000 21,000 21,000 42,000 45,000 45,000 45,000 45,000 65,000 65,000 60,000 60.000 7,000 7.000 10,000 10,000 20,000 38,000 96,000 60,000 90,000 284,000 90,000 90,000 90,000 90,000 1,040,000 900,000 910,000 1,100,000 900,000 4,850,000 11,600 13,000 24,600 100,000 200,000 300,000 145,000 145,000 40,000 40,000 1,091,600 913,000 910,000 1,345,000 1,100,000 5,359,600 28,000 28,000 28,000 28,000 910,000 830,000 730,000 1,000,000 900,000 4,370,000 46,400 48,000 94,400 48,700 250,000 298,700 956,400 878,000 730,000 1,048,700 1,150,000 4,763,100 350,000 350,000 100,000 100,000 100,000 100,000 100,000 500,000 160,000 160,000 15,000 15,000 100,000 275,000 100,000 100,000 450,000 1,025,000 a 100,000 a 100,000 100,000 110,000 110,000 110,000 100,000 530,000 ICednesday. i/a• 26. 2010 Source Proiect= Priorirh 2011 2012 2013 2014 2015 Total Storm Drainage System Maintenance -Alley Repai s 01-CIP-0002 n a 17 000 19 NO 19 000 20 000 20 000 94 000 Stam Water Management Projects 01-CIP-UO03 ma 200 000 200 000 SU -Storm Sewer Fu nd Total 117.000 118,000 129.000 330.000 230,000 924.000 TF - Tax Increment Financing Redevelopment, East Excelsior Boulevard 01-CIP-D401 n a 2000 000 2 000 000 Light Rail Transit Stations (2) 01-CIP-F502 n a 150 000 150 000 Bkx* 64 Redevelopment Project 06-CIP-D404 n a 3 500 ODD 3 500 000 Marketplace and Main 07-CIP-D405 n a 1 350 000 1 350 000 Blake Corridor Redevelopment 09-CIP-D406 n ra 5 DOD OJO 5 000 000 8th Avenue Redevelopment 09-CIP-D407 ma 3 000 000 3 000 000 TF - Tax Increment Financin<o 7 otal 4,350.000 8.500.000 2,000.000 150.000 15,000.000 WF - Water Fund Eighth Avenue LRT Corridor 01-CIP-F503 n a 250 000 250 000 Residential Street Improvements—Utilities 01-CIP-SI02 n a 75 300 %5 000 80 000 80 000 90 000 400 000 Meter Replacement 08-CIP-0000 ma 95 300 95 030 95 000 285 000 Emergency Chkxine Shut Off Valves 08-C/P_0008 n a 33 000 33 000 St. Louis Park Emergency Connection 06-CIP-010 n a 211 000 211 000 WF- Water Fund 1 otal 170.000 381.000 208.000 80,000 340,000 1.179.000 GRAND TOTAL 6.885,800 13.366,500 4,412.000 9,777,549 26,907,881 61,349.730 • 0 L' • Department City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2011 thru 2015 DEPARTMENT SUMMARY 2011 2012 2013 2014 2015 Total Activity Center 140,000 275,000 36,000 451,000 Arts Center 9,800 12,500 22,300 Cable TV 25,000 25,000 Development 4,350,000 10,500,000 2,000,000 16,850,000 Pavilion 53,000 109,000 162,000 Pubic Works: Parks 10,000 75,000 60,000 90,000 235,000 Pubic Works: Streets/Traffic 2,323,000 2,066,000 1,930,000 9,431,549 25,428,881 41.179,430 Pubic Works: Transportation 28,000 850,000 878,000 Pubic Works: Utiliies 112,000 499,000 147,000 220,000 20,000 998,000 Recreation 7,000 500,000 507,000 TOTAL 6,864,600 13,345,500 4,412,000 9,777,549 26,907,881 61,307,730 lCednesikrv..tlay 26 2010 Cite of Hopkins, ;\1N CAPITAL I.11PR01 'F_.1IF_.N'T PL.A.N' • 2'(111 tlu-u x015 PROJECTS BY DEPARTMENT Department Project- Priorit.N 22011 2012 2013 2014 2015 Total Activi Center Replace Carpet- Activity Center Rooms 08-CIP-P.0015 n a 36 000 36 000 Activity Center HVAC Upgrade 06-CIP-4.0O20 n a 5) 0)0 275 000 325 000 Activity Center Caf6 on 14th 09-CIP-40032 n a 9100 90 000 Activity Center Total 140.000 275,000 36,000 451.000 Arts Center Replace Office Carpet • HCA Stages Theatre 08-CIP-AR006 n a 12 500 12 500 Arts Center Carpet: Redepenning Gallery 08-CIP-4R008 n a ° 300 9 800 Arts Center Total 9,800 12,500 22,300 Cable TV Automated Playback 08-'-IP-8054 n a 25 OOO 25 000 Cable TV Total 25.000 25.000 • Develo ment Redevelopment, East Excelsior Boulevard 01-CIP-D401 n a 2000 000 2 000 000 Block 64 Redevelopment Project )5-1IP-D404 n a 5 50) 000 5 500 000 Marketplace and Main 07-CIP-D405 n a 1 350 000 1 35) 000 Blake Corridor Redevelopment 09-C1P-D406 n a 5 OO) ODO 5 000 000 8th Avenue Redevelopment 09-CIP-0407 n a 3 000 000 3 000 000 Development Total 4.350,000 10,500,000 2,000,000 16.8501.000 Pavilion Pavilion Me?- Roof Replacement (North Section; 07-CIP-P315 Ila 40 303 40 000 Pavilion Arena Bleacher Heating Replacement 08-CIP-P005 n a 33 O)0 38 000 Pavilion Gas Fired Rooftop Furnace 09-C/P-P025 n a 9100 9 000 Pavilion Evaporator Condenser Replacement 09-CIP-P036 n a 50 000 60 000 Ice Resufacer Water Heating System Replacement 09-CIP-P316 n a 15 030 15 000 Pavilion Total 53.000 109.000 162,000 Public Works: Parks Play Equipment - Park Valley 03-CIP-P)10 n a 45 000 45 000 Play Equipment- Hilkop Park 08-CIP-P014 n a 45 000 45 000 Play Equipment- Valley Park 08-CIP-P015 n a 75 ODO 65 000 Play Equipment- Oakes Park )8 -11P -P016 n a 60,300 60 000 Miscellaneous Park Improvements 1)-1-1P-2017 n a 101 000 1D 0)0 20 000 • Public Works: Parks Total 10.000 75.000 60,000 90.000 235,000 • 11"ednestlia,, Maj, 26. 2010 Department Project# Priority 2011 2012 2013 2014 2015 Total Public Works: Streets/Traffic Sixth Street South (11th to 12th Avenue South) 01-CIP-F504 n1a 400,000 400,000 Residential Street Improvements 01-GP-S101 n1a 1,950,000 1,730,000 1,640,000 2,100,000 1,800,000 9,220,000 Residential Street Improvements-Utilities 01-CIP-S102 n1a 275,000 275,000 290,000 290,000 300,000 1,430,000 Citywide Concrete Alleys 01-CIP-S103 nla 58,000 61,000 119,000 County Road 3 01-CIP-5104 Na 2,300,000 2,300,000 County Road 61 (Shady Oak Road) 01-CIP-S108 nla 6,596,549 20,628,881 27,225,430 Highway 7 and 5th Ave North - Signal Replacement 10-CIP- S120 3 445,000 445,000 Emergency Vehicle Preemption (EVP) Signal Upgrade 10-CIP-S119 2 40,000 40,000 Public Works: Streets/Traffic Total 2,323,000 2,066,000 1,930,000 9,431,549 25,428,881 41,179,430 Public Works: Transportation Light Rail Transit Stations (2) 01-CIP-F502 nla 150,000 150,000 Eighth Avenue LRT Corridor 01-CIP-F503 nla 700,000 700,000 Seal Parking Ramp Concrete Decks 10-CIP-F504 We 28,000 28,000 Public Works: Transportation Total 28,E 850,000 878,000 Public Works: Utilities Storm Drainage System Maintenance -Alley Repairs 01-CIP-0002 We 17,000 18,000 19,000 20,000 20,000 94,000 Storm Water Management Projects 01-CIP-0003 n1a 200,000 200.000 Meter Replacement 08-CIP-U000 n1a 95,000 95,000 95,000 285,000 Lift Station # 4 08-CIP-0001 Na 160,000 160,000 Emergency Chlorine Shut Off Valves 08-CIP-0008 n1a 33,000 33,000 •Sanitary Sewer Lift Station Maintenance 08-CIP-0009 n1a 15,000 15.000 St. Louis Park Emergency Connection 08-C1P-U010 We 211,000 211,000 Public Works: Utilities Total 112,000 499,000 147,000 220,000 20,000 998,000 Recreation Skate Park 08-CIP-R001 n1a 7,000 7,000 Depot Recreation Area 10-CIP-8002 2 500,000 500,000 Recreation Total 7,000 500,000 507,000 GRAND TOTAL 6,864,800 13,345,500 4,412,000 9,777,549 26,907,881 61,307,730 • 11"ednestlia,, Maj, 26. 2010 CAPITAL RvEPROVEMENT PLAN 2011 d7rit 2015 City of Hopkins, MN Project s 08-CIP-AC015 Project Name Replace Carpet - Activit- Center Rooms Future Carpetingin Activity Center Ra>nccrr\ Rooriu. I\ Gamc Room: halhca >. I)cpartment 1,:tn its Center ( untact I acilrtic, I)irectou ape Impm\anent t ,cful I ifc < au^_nr\ I3u11dMUN \stn in ( cnicr Priurih n a uUtl Project ( o,t: 536.0110 Justification Carpet is 18 dears old. worn and require, i-cp1acciiicni. 1 Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 36 300 36 Din Total 36.000 36,000 Funding Sources 2011 2012 22013 2014 2015 Total Cl - Capital Improvement Fund 36 000 36 Dap Total 36,000 36,000 0 : I I .L,,/.., t',., '/, _ • • CAPITAL IlAPROVEMENT PLAN 2011 /lu-u 2015 City of Hopkins, MN Project # 08-CIP-ACO20 Project lame Activity Center HVAC Upgrade Future Department Activity Center Contact PW Director ry pe Improvement Useful Life Category Buildings: Activity Center Priority n/a Total Project Cost: $325,000 ice existing gymnasium AC units With heat and air units. Replace existing low pressure steam boiler with hop water boiler. install new hot • supply lines. Rework existing base board radiation units for hot water. Install new VAV coils in existing fan units (7). Install new AC unit heat fan unit in Historical Society room. Upgrade air makeup unit for kitchen area Install or integrate system controls With other city 2012: ENGINEERING 2013: CONSTRUCTION Justification Existing low pressure stem boiler is 25 years old. Supply piping for radiation units is 54 years old. Piping is located in tunnel area around perimeter of building. Life of existing piping is a concern. Have had one failure in 2001. Cost of replacing piping would he extremely high. Upgrading system will allow better control of the building and reduce energy costs. Air exchange in winter months would be improved. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 50,000 275,000 325,000 Total 50,000 275,000 325,000 Funding Sources 2011 2012 2013 2014 2015 Total Cl - Capital Improvement Fund 50,000 275,000 325,000 Total 50,000 275,000 325,000 Budget Impact/Other Sisk of major failure of the 50 plus years old piping is a concern. Repairs would only be temporary as one failure would be a sign of the entire listribution sy stem surpassing its useful life. Existing equipment has surpassed its expected life. No major disruption of use of this building. Pate 2 Wediresdtn% tla), 26. 2010 CAPITAL IMPROVEMENT PLAN 2011 ihru 2015 City of Hopkins, MN Project # 09-CIP-AC032 Project Name Activity Center Calc on 14t Future Dc1)artinctit \Cu\it\ lrntcr (untact P\\ U1rat��r • I�pc Inlpl\+\Cntent ( .(fill I i1c ( ate_ur\ BLI1I Irtle, \Cu\ t\ C enter Prioril\ It a Mal 1'11 icct ( +.t: 5911.111111 General -The Activity Center CaIC on I Ith pwicct i, ,t project ainud ;,t .I uomnu trend anwnL ,ellik,r CcntrrS t+) mach out t+.+ OLIIILrr aLid i ncc, such as the baby boom generation. I his, I,roject \\ ill Ir.ulli+rnl (he \cti\ it\ ('cntcr 1'1_01 I) a u-adiIit) n:ll ,enior Co III] IIIlnit\ cc Mer into, a re,tauI'd nt. gathering place. learning center. and health Cluh -that hal,I,Cn, to halC Cu,tonlCr, \\ho nld\ r,,n C ill ,: C In,nl �0-00 (hut ,till 011ell to+ Lill ;12C>I. The original model of Cafd conuu1JI16 1;lcihl\ \t,1, dC\ Cloyed in ( Iica_C,, al Id 11,1, hc:n ,LI CC,aulh_ in;} Iin1CmCJ in other Citic,. I hC Cu},it❑I improvement portion of this ne\\ {,n+tCCI in\ol\C> Lill 11/111,-, the cv,ting kitChCII in a Cale ILl,hion that MILIId ,ir\c It)( d in the uIt' Ill ill _ until Lifter lunch to people seated in what is currCntl\ the loun_C ,IrC:,. :tailed - The project involves o},Cning ill, a I,on-tio,n of the \\,III hit\\ CCn the kitihin and II'Un_C .,rC,t and hulldin ' ,t scall .,tom" \h,n i, nc+t the rving line area of the kitchen. I hi, net+ \\.III gill elo,c offthc kitchen un the _\ Ill ,ide .old crC;ltc a lwll\o.l\ liv Cnu;lnCC and C\it Crum the est doors. The kitchen needs to he rCJC>iLIICd Irunl it', },l -c\ iuu> >Chuo+l Cal;tCri;l 1,1\01.11 to at ,nl.,llCI. "Cate" kitchen ;u Cal tt ith the 1Ippl_u},riatC uipment to serve breakfasts and ,,old\\ ich ,Lil,ld ,out, haled ILII1Che>. I It,:It,:lo,un_e al -ca Carpet \\ ill he rC},Wccd \\ ith tile. a Co111},utcr Llt tahlc \\ ill he ded for internet access in the lou n_C. Sources: Sources have, et to he idcmilicd but l,o,,ihlC l\;:rulCr, in the lvo+jCct Could ilICludC: I hC I to},kin, I li>tulicall tioriin. I l++ltkill, hstrict, a new non-profit 1 ricnd, of the .\cti\ it\ ('enter" ol'_,uuialion. Justification It is well documented that bab\ ho+onlcr, are not uulii.in_ u.lditional ,Cnior CCntrn ,I> I cadik ❑, ,Cnior, ha\e in the pa>t. People do not \ i>it ,Cniol centers because it's for people of tilde tile\ _'O there IUr the ;Illd ,el"\ ICe, tile\ lJCCd. I hC _'0a1 \+I the (.Ili 1, h, .ttll',ICI the \01,1111-'er UI\ICI' adult - lounger in outlook, attitude alnd \ car, - thole \\ hu \\ 01.11d hCIIClit but ,Cldunl u,C ",enior" ,C\ icc,. to incrc,l,c },,lrulcr,hip. \ i,ihilit_\ and service reach. to improve thequalit\ ofliIc IM- our older adult,. ,11111 to iIICrCa,C ,,lti,4 Coon ot,cr\iCc, • The cafe concept would salisfj se\ eral ('it\ ,tr,tC_iC _oat, ,All a, huildin_ on the ,rllall to\\ n liCl of I to},kin, throuCh dC\ Clul,in_ new method, that are more responsive to citizen, .incl Cu,tonlCl,. If 1,,11111Crin_ \\ illi the I li,torical "ocict\ the Ill oieet \\ ill CnhaI)CC the ,cn,e ill• 1,1acc. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 90 000 90 000 Total 90.000 90,000 Funding Sources 2011 2012 2013 2014 2015 Total PF - Private Sector Funds 90 J00 90 000 Total 90.000 90,000 Budget Impact/Other The operational goal of the cafe \\ould hC to hi—cak e\ en Li, a Hod ,Cr\ ice. but the ('al \could dra\\ Cu,tonler, to the .\Cti\ it_\ ( Cnter to l,autiii}laic .n the aetiyitites many programs and actk itis, ofl'crCd h\ 1110 CCntCI thu, inrrC,1,in_ i,rouun, wed nlCmhCl,hil, IC\ Cnue,. • 11 CAPITAL IMPROVEMENT PLAN 2011 ihru 2015 City of Hopkins, MN Project # 08-CIP-AR006 Project Name Replace Office Carpet - HCA Stages Theatre Future Remove and replace carpet and carpet base in Stages Theatre 260 sq yards x $48/pard = $12,480 Justification arpet is 13 dears old as of 2010. Carpet will have exceeded its u I can no longer be cleaned in these areas. Department Ans Center Contact Public Works Director Ti pe Improvement Useful Life 10 years Category Buildings: Arts Center Priority n/a Total Project Cost: $29,500 ticket office and Facility Manager's office, and coat room. has separated from backing %vhich has caused it to Expenditures 2011 2012 2013 2014 2015 Total Future Construction/Maintenance 12,500 12,50017,000 Total 12,500 12,500 Total Funding Sources 2011 2012 2013 2014 2015 Total Future Cl - Capital Improvement Fund 12,500 12,500 17,000 Total 12,500 12,500 Total Budget Impact/Other dote: Repeat project in 2021 at $17.000 Pate Il nesdtn% Mn, 26. ?010 CAPITAL JWROVEMENT PLAN City of Hopkins, MN 2011 ,hru 2015 Dcparhnell t \ctntt\ Crntcr ( untact P\\ Oir"lor • 0 CAPITAL HvII'ROVEMENT PLAN • City of Hopkins, MN Project # 08-CIP-AR008 Project Name Arts Center Carpet: Redepenning Gallery Future 2011 thru 2015 and replace carpet and carpet base in Redepenning Gallen. coat room and JC Department Arts Center Contact Public Works Director T� pe Improvement t'seful Life 10 years Category Buildings: Arts Center Priority n/a Total Project Cost: S21,800 and dressing rooms. Gallen flooring to be replaced with wood or wood laminate. Coat room and JC Studio dressing rooms to be replaced with carpet. ESTIMATED PROJECT SCHEDULE: Future - Repeat project in 2022 at $12.000. Justification Carpet is 13 years old ac of 2009. Carpet will have exceeded its useful life. Expenditures 2011 2012 2013 2014 2015 Total Future Construction/Maintenance 9,800 9,800 12,000 Total 9,800 9>8N Total • Funding Sources 2011 2012 2013 2014 2015 Total Future Cl - Capital Improvement Fund 9,800 9,800 1 12,000 Total 9,800 9,800 Total Budget Impact/Other Change from $8.700 to $ • to reflect change in product from carpet to wood or wood laminate for the art gallen,. Pace 6 J*dnesdm•..11ui- 26. '010 CAPITAL IMPROVEMENT PLAN 2011 digit 2015 City of Hopkins, MN Project # 08-CIP-BO54 Project dame Automated Pla-, back Future an playhack > arm lw thr ,tltJio. M-parintrnl C ahlc I \ ( untact \„t C rt\ \lana_cr 16 .\ pe Imprmcment t .0-111 1 ifc ( atc,.nw\ I;IJ_, \Jmmi,trati\rt iftice, Priorih n a I ural Pr,.jcct ( usr: s2n.00l1 Justification Automated Pla)hack of video pmgLurn, ,nch .t, the cOxutcjl mL:Ctill �, .mJ "thCr r\Cnh C0mmtmih intcrr,t, Can he urhic,,cd hN expanding on the bulletin board ,N arm to include t)\ l) hla\cr,. \ (1:,..11111 Jlrict 10 hard Jrj\C, 11 ,t,,ra .: rccrnJ hla hack ,"tem,. It provides absolute control of)our Ivwuantntin_ tht a .nt aut0nt,rtcd ,stem. I he ,stem i, u>cr I'ricndh AHLI r,ut he ,utrndcd to h\ nout-technical people. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 25 000 25 X00 Total 25,000 25,000 Funding Sources 2011 2012 2013 2014 201-5 Total Cable Television Fund 25 000 25,000 Total 25.000 25,000 • 0 CAPITAL HOPROVEMENT PLAN M City of Hopkins, MN Project # 01-CIP-D401 Project lame Redevelopment, East Excelsior Boulevard Future 2011 thru 2015 side of Excelsior Boulevard from Highway 169 to approximately Blake Road. Department Development Contact ED Director T} pe Improvement Useful Life Unassigned Category Economic Development Priority n/a Total Project Cost: $2,000,000 ;development of older commercial area. Based on the adopted redevelopment plan, it would involve commercial. and residential uses. Identified the East End Redevelopment Study. Justification .celsior Boulevard was upgraded in this area providing for additional property on the north side of the roadway. The buildings in this area are ler and no longer the highest and best use for this property. The funding amount is an estimate and will vary depending on the scope and timing the project. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 2,000,000 2,000,000 Total 2,000,000 2,000,000 • Funding Sources 2011 2012 2013 2014 2015 Total TF - Tax Increment Financing 2,000,000 2,000,000 Total 2,000,000 2,000,000 Budget Impact/Other • 1'a_e 8 N ednesckn•..l1nr '6. 2010 CAPITAL B4PROVEMENT PLAN 2011 d7rii 2015 ��T Dcpm artcnt 1Y11V I):�rluhment City of Hopkins, (onlact 1 1) Uir"tor I N pc Impro%cmcni ( sJul I il'c ( atcenrN I u n nu 1)c%dopm nt Future n a Description I utal I'rujcct ( �L tii,jllll.11llll Redevelopment of block bemeen 51h and 61h .k\ Cnite>. 1101-th 01 Main>IIVCL >Offlh Of I>t titr,:et \rn•th. l h: rurrrnt ,rh Juk i> 1i01- �:unau-urtitln to start in late 2012. Justification Will redevelon older commercial and rc,i&,ntial arc❑, Expenditures 2011 2012 2013 2014 201-5 Total Construction/Maintenance 5 500 000 5500010 Total 5.500.000 5,500.000 Funding Sources 2011 2012 2013 2014 2015 Total ED - Economic Development F 2 000 000 2 000 030 TF - Tax Increment Financing 3.500 003 3 500 J30 Total 5,500.000 5.500,000 0 1 0 1 • CAPITAL MPROVEMENT PLAN • City of Hopkins, MN Project # 07-CIP-D405 Project Name Marketplace and Main Future 2011 thru 2015 Department Development Contact ED Director T.N pe Improvement Useful Life Category Economic Development Priority n/a Total Project Cost: $1,350,000 Redevelopment of property between 6th and 8th Avenues north of Mainstreet (former Luther Company property). $900.000 of public assistance %vas provided in 2007. Construction is projected for 2010/2011 Justification Alill redevelop older commercial area. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 1,350,000 1,350,000 Total 1,350,000 1,350,000 Funding Sources 2011 2012 2013 2014 2015 Total TF - Tax Increment Financing 1,350,000 1,350,000 Total 1,350,000 1,350,000 Budget Impact/Other C] Pace 10 N'ednes&n% Way 26. ?0/0 CAPITAL INTROVEMENT PLAN 2011 ii7ru 2015 City of Hopkins, MN Project # 09-CIP-D406 Project Name Blake Corridor Rede-, elopment )vpartnu•n1 I)0%dopment Contact I I) Uirraor is pc Impro%rmrnt I �cful I it'c ( aU•20n I owirnuh: I o d,I)nrnt Future I'riurit� n a tion I ulaI 1'rojcct (o.t: 55.11110,1100 pment ofpmperties alem-, the Hlak,: RZO,t i C rri i r i1)1:1UJi11' the Collauc\ ills Park arca. Justification I Removal of blighted and/orobsolrtc ,u'urturC1. i111111'0\ C aCCC�S 10 tr.in.it an.i imprmC 1i\ahiIit\ )I the ,u�u Expenditures 2011 2012 2013 2014 2015 Total Land Acquisition/Demolition 5 000 000 5.000 0210 Total 5.000.000 5,000,000 • Funding Sources 2011 2012 2013 2014 2015 Total TF - Tax Increment Financing 5 G00 000 5 000 000 Total 5.000.000 5,000,000 :7 t... . ', , :i _ CAPITAL INTROVEWNT PLAN . City of Hopkins, MN Project # 09-CIP-D407 Project Name 8th Avenue Redevelopment Future 2011 thru 2015 Department Development Contact ED Director TN pe Improvement Useful Life Category Economic Development Priority n/a Total Project Cost: $3,000,000 of 8th Avenue to support the LRT station and provide an improved link to downtown Hopkins. Justification rhe uses and densities along 8th Avenue, particularly, on the west side. are not supportive of light rail transit and do not serve to draw the 3edestrian or bicyclist to Mainstreet. Redevelopment of the corridor will provide for an important link between the LRT Station and the downtown issumin2 both are successful. Expenditures 2011 2012 2013 2014 2015 Total Land Acquisition 3,000,000 3,000,000 Total 3,000,000 3,000,000 Funding Sources 2011 2012 2013 2014 2015 Total TF - Tax Increment Financing 3,000,000 3,000,000 Total 3,000,000 3,000,000 Budget Impact/Other • t'ase 12 it ednesdar, Min -26. 2010 CAPITAL HSAPROVEMENT PLAN 2011 il7ru 2015 '_-r MN Ikp;u'hncnt Pa\ili��n City ofr Hopkins, ( MINN PuMit \\orl., Ihrccior Project # 07-CIP-P31 5 Project dame Pavilion Mez. Roof Replacement (North Section) I .\ pe Imhn,%cmrnt l �cl'ul I ife ( atcCor\ I31dg Pay illion Future Priurih n a Description71 1 oral Pr,ijcct ( ),I: 540.00(1 Removal and replacement ofexi>tin m:tt�:ri.tl and th �i>tin_ hall.t t. 1 Justification Existing roofinembt•ane has e\e'Ccrlc,i it, u,rful Nil' .1111 1. r\hrriCnrine ,i,tln I;tilur around hencu•atirm, and pint, :,6,n ill) hullin` ,m,t\ Ii•rmt the outside curb. Leaks have bLen rchuurd )it ,c\ ral Expenditures Construction/Ma in ten an ce Total 2011 2012 2013 2014 2015 Total 40 ON 40 000 40,000 40,000 Funding Sources 2011 2012 2013 2014 2015 Total PA - Pavilion Fund 40 000 40 000 Total 40,000 40,000 can potential]be hath ful to the ,t«l i-ool'dc.I, and m,n c,ut,L� d.un.tg to 1�11uihmCnt and interim of P1\ ilirm. 01 • 1'.,, _a _�', CAPITAL INTROVEMENT PLAN • City of Hopkins, MN I* Project # 08-CIP-P008 Project mme Pavilion Arena Bleacher Heating Replacement 2011 thru 2015 Department Pavilion Contact Public Forks Director T} pe Improvement Useful Life 15 years Category Bldgs: Pavillion Future Priority n!a MscriptioII 71 Total Project Cost: $38,000 Replace the arena's current bleacher infrared heating system with a new efficient system. Justification ['he current system is 18 years old and no longer produces adequate heat due to deterioration of the major components. Replacement is warranted rather than repair due to the age of the system and the type of repairs needed. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 38,000 38,000 Total 38,000 38,000 Funding Sources 2011 2012 2013 2014 2015 Total PA - Pavilion Fund 38,000 38,000 Total 38,000 38,000 savings on utilities and greater satisfaction from user groups. Inadequate bleacher heat is the major complaint among Pavilion users. • Pane 14 tt ednesda,v. itm• 26, 2010 CAPITAL HAPROVEMENT PLAN City of Hopkins, MN Project # 09-CIP-PO25 Project game Pavilion Gas Fired Rooftop Furnace Future 2011 rima 2015 Ih•pm•Inuvtl 1'al ikon ( ontact Puhh� \\or6, Director and replace existing ga. fired roolior furnaCC u,Cd I01- Malin-, the tC.un room.. LTED PROJECT SCHLIA I I_- ',wnmCr -'ul �\pc Impm\rmrnt It cful I ilc 2ii \Car, ( alcum-N olds,, Pay illion I'riorih n a I oral Project ( —t: 59.000 Justification Current unit was installed during con,u-.rction of the LiciIit\ in 1990 I'I,ill ncd rCl,l.tccmcm I,)r Cnd of c,,tinlatr i u,CI'll I lifC. Expenditures 2011 2012 2013 2014 2015 Total Construetion/Mainten ance 9 0)0 9 1000 Total 9.000 9,000 Funding Sources 2011 2012 2013 2014 2015 Total PA - Pavilion Fund a Opp 9 DM Total 9.000 9,000 on utilities due to increase in CIl iCicnc% ol'nCN\ unit. • 01 CJ r �J CAPITAL MPROVEMENT PLAN City of Hopkins, MN Project# 09-CIP-PO36 Project Name Pavilion Evaporator Condenser Replacement Future 2011 thru 2015 Department Pavilion Contact Public Works Director T% pe Improvement Useful Life 15-25 years Category Bldgs: Pavillion Priority n/a Description Total Project Cost: $60,000 3emove and replace existing condenser with a new condenser, sump tank, pump and fan motors. TED PROJECT SCHEDULE: 2015 Justification xisting condenser has extensive scaling and has experienced a loss in et7icienc) causing higher head pressures and putting greater strain on :ompressors. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 60,000 60,000 Total 60,E 60'000 Funding Sources 2011 2012 2013 2014 2015 Total PA - Pavilion Fund 60,000 60,000 Total 60,000 60,000 ven the age, scaling, and corrosion of the existing condenser a Freon leak could potentially develop causing greater expense and need for repair. Pane 16 If' dnesdm•. Alay 26. ?010 CAPITAL IMPROVEMENT PLAN 2011 ihrir 2015 � T Department I'at ili,n City of Hopkins, �/11V ( ontact Puhlr Project # 09-CIP-P316 Project Name Ice Resufacer Water Heating System Replacement ape Intpm\anent t cful I ifc 20 rar ( alcuon lil.lss'. 11mlhk-n Future PriorilN n a )tion l (,cal 1'rojed (,,.t: 515.01111 the three existing water hcam., a>cd to heat the ice rc>urt'.trin , ut r aild rcplacc \\ ith n,:,+ \\ atcr hr.ttin_ ,\ .tem. Justification )ne of three heaters used is umnahlc Auld the othcr 1\rrr \xatcr heater, ha\c c„rm,i„n m,1 maj,u calin= i uc.. \II three \\atcr hcatcr,, �\cr,: part 01' he facilitN construction in 1990. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 5 000 15 000 Total 15.000 15,000 Funding Sources 2011 2012 2013 2011 2015 Total PA - Pavilion Fund 5 000 15 001 Total 15.000 15,000 on utilities due to inereaa,� in oI'nc\� \>tcm. C 0 • CAPITAL INDROVEMENT PLAN 2011 rhru 2015 City of Hopkins, MN Project # 07-CIP-P219 Project Name Shady Oak Beach Community Play Area Future !placement of the Shade Oak Beach water pla} area innetonka and Hopkins. Department Public Works: Parks Contact Public Works Director T) pe Improvement Useful Life Category Pars/Fores!Pay.: Comm. Facil. Priority n/a Total Project Cost: $330,000 a community play area designed to be a destination attraction for residents of Justification rhe existing water play equipment at the site +vas installed when the beach was renovated in 1998 to encourage use of the site when weather :onditions were not conducive to swimming. The system is in need of replacement due to health and safety requirements as well as aging -quipment. Staff is recommending that the water play area be replaced with a community playground area designed to be a destination attraction 'or families with children 12 years of age and under. Use of this equipment on a seasonal basis would extend beyond the beach operating season and be available for use during the fall months as well. Prior —330.000 Total Prior Funding Sources 288,000 PDF- Park Dedication Fund 2011 2012 2013 2014 2015 Total 21,000 21,000 42,000 Total Total 21,000 21,000 42,000 expenses for the beach in 2008 were $200.200 with revenues of $230.700. :tion of this protect will enhance beach attendance during the normal beach operating season as well as post -season use. It is anticipated that pass sales will increase due to the addition of a high quality community paly arm of the existing water play area and underground confined space that houses the operational equipment will result in reduced annual nenditures of annroxinamteh $5.000. Pate I8 Ilednes&n•. kAn- 26. 2010 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN 2011 ihru 2015 Dcpartincni 110lic\\ork, ll:itk, ( untact Public \\ ,rk„ I)trL:enor is • 0 CAPITAL INTROVEMENT PLAN 2011 thru 2015 Department Public Works: Parks Ah City of Hopkins, MN Contact PW Director I* I* Project# 08-CIP-Polo Project lame Play Equipment - Park Valley Future .eplace park play equipment 014 ----------- 45.000.00 Justification 1lpgrade of park play equipment atter 20 - 25 years of use. F) pe Improvement Useful Life Category Parks/Fores/Pay.: Comm. Facil. Priority n/a Total Project Cost: $45,000 Pace 20 Wednesdcn'. 11my 26. 2010 Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 45,000 45,000 Total Funding Sources 2011 45,000 2012 2013 2014 2015 45,000 Total PDF- Park Dedication Fund 45,D00 45,000 Total 45,0OO 45,000 Pace 20 Wednesdcn'. 11my 26. 2010 CAPITAL IMPROVEMENT PLAN 2011 1hrii 2015 City of Hopkins, MN Project # 08-CIP-P014 Project \Mme Play Equipment - Hilltop Park Future I)cpartmcnI Puhlic \1 urk P;irks (unLut I ;t�rlitir� I)ire�Ax' Npe ImproNrmrnt t �cful I He ( afcL,'un Park, I ores P,n l onim I acid PrioriIN n a Expenditures 2011 2012 2013 2014 2013 Total Construction/Maintenance 45 000 45 )00 Total 45.000 45.000 Funding Sources 2011 2012 2013 2014 2015 Total PDF- Park Dedication Fund 45 50U 45 D,0 Impact/Other Total 45.000 45.000 I , ,, ,.., t 1, 1 :1� : , ; 11 C. 0 r� LJ s L� CAPITAL RvIPROVEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project # 08-M-1`015 Project Name Play Equipment - Valley Park Future Department Public Works: Parks Contact Facilities Director 17� pe Improvement Useful Life Categon Parks/Fores/Pay.: Comm. Facil. Priority n(a Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 65,000 65,000 Total 65,000 65,000 Funding Sources 2011 2012 2013 2014 2015 Total PDF- Park Dedication Fund 65,000 65,000 Impact/Other Total 65,000 65,000 Pace 22 I*dnesday. lfuv 26. 2010 CAPITAL IMPROVEMENT PLAN 2011 thrii 2015 City of Hopkins, MN Project # 08-C1P-P016 Project Name Play Equipment - Oakes Park Future Departntu-Fit PuhLc 1l,,rl,. Park, ( unlact I s ilrttc I)irret r' I % he Inthm cment t'Jul I iIc ( atc,-'nn Parks I orc> Pa% lonnn I a,il Priurirh n a Expenditures 2011 2012 2013 2014 2015 Total ConstruetioNMaintenance 60 J00 60 000 Total 60,000 60,000 Funding Sources 2011 2012 2013 2014 2015 Total PDF- Park Dedication Fund 60 NO 80 000 Total 60,000 60,000 Budget Impact/Other , � , , 'J.) ., _ , • • CAPITAL IMPROVEMENT PLAN 2011 thru 2015 Department Public Works: Parks City of Hopkins, MN Contact Pw Director Project # 10-CIP-PO17 Project Name Miscellaneous Park Improvements T} pe Improvement Useful Life Category Parks/Forcstry Future Priority n/a tion Total Project Cost: $20,000 nents to various neighborhood and community parks to maintain safe and enlo}able play areas, shelters and landscaping. Justification ?arks are periodically in need of play equipment container area repairs, play equipment repairs. shrub and tree replacements picnic shelter repairs, etc. In order to keep the parks safe and enjoyable for residents. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 10,000 10,000 20,000 Total 10,000 10,000 20,000 • Funding Sources 2011 2012 2013 2014 2015 Total PDF- Park Dedication Fund 10,000 10,000 20,000 Total 10,000 10,000 20,000 Impact/Other • Page 2 t It ednesday. Alai" 26. 2010 CAPITAL H PROVEMENT PLAN 2011 ,hrit 2015 City of Hopkins, MN Project # 01-CIP-F50.1 Project\ame Sixth Street South (11th to 12th ANenue South) Future Sixth Street South from I Ith AN enuc '011111 to 1201 AN cnuc '�rnnh. Extension of roadway and bo\ cul\ crt .r t„inc at \inc \lilt 0-,cA. Dcparlinc nI I'uhlic \ ork, tiU'c;t, I r;otic ( ontact Puhlrc \1 „rk, I)ircct:,r pc Impro\cmcnt l ,rful I irr I na„iencJ ( alcuor) I ram titrcch I'riorit\ n a oral 1'1-oicct ( 1,,I: ' 4400 IOO Justification This project %%ill tiller a second accc>, to the indu,tri,tl .,rca tlirc accc„i "ill dircrt 10111r r,t'thc C\illiI12 r dUS11'i,tl trallir nrrrth- ma\ C1, 1,t the residential intersection at Seventh '�u L -t :111,1 I I th \N cuuc. ill c01111crt a current dna i -c1, i ,:II; . \�r>t k11' I I th A\ OILI . Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 403 030 400 333 Total 400,000 400.000 Funding Sources 2011 2012 2013 2014 2015 Total ED - Economic Development F 103 03C 100 3S0 MS - Municipal State Aid Stree 3303 030 300 000 Total 400.000 400,000 on MSA plans. 9 11 • • CAPITAL IlVIPROVEMENT PLAN City of Hopkins, MN Project # 01-CIP-S101 Project Name Residential Street Improvements Future 2011 thru 2015 Department Public Works: Streets/Traffic Contact Public Works Director rt pe Improvement Useful Life Unassigned Category Trans: Streets Priority n/a 'rotas Project Cost: $11,660,000 to improve streets needing repair or reconstruction as indicated by street condition survey, or as part of an area street improvement. 2011: Central Hopkins Reclamation Project - 14th & 15th Avenue North between 2nd Street North and South Sen ice Drive: 16th Avenue North between 3rd Street North and South Service Drive: 3rd Street North between 15th and 17th Avenues: 4th Street North between 12th and 17th Avenue. South Service Road between 12th and 16th Avenues. North service road between Oarkridge road and 12th Avenue. 2012: Central Hopkins Street Reclamation Project - 20th Avenue North between Mainstreet and 3rd Street: 19th Avenue North between Mainstreet and 1 st Street North: 18th Avenue North between Mainstreet and 4th Street: 16th Avenue North between Mainstreet and 1 st Street North: 14th Avenue North between Mainstreet and 2nd Street North: 2nd Street North between 14th and 15th Avenue South. 2013: Central Hopkins Reclamation Project - Minnetonka Mills Road between 1 lth and 7th Avenue: 11th Avenue North between 1st Street and 3rd Street: 9th Avenue North between 2nd Street and Mainstreet: 3rd Street North between 8th and I lth Avenues: 4th Street North between 10th and 1 lth Avenue: 8th Ave North between Ist and 2nd Street. 2014: Park Valley and Peaceful Valley Reclamation Project - East and West Park Vallee Road: 9th Avenue South between Westbrooke Way and 7th Street South: 6th Street South between 10th Avenue and 6th Ave South: 7th Street South between 10th Avenue and East Park Valle} Road: 5th Ave South between 5th Street South and 7th Street South 2015: Presidential Avenues South and 1st Street and 2nd Street South. between Monroe and Harrison. street improvements determined through Pavement Management Program. Prior Expenditures 2011 2012 2013 2014 2015 Total 274407500 constructioNMaintenance 1,950,000 1,730,000 1,640,000 2,100,000 1,800,000 9,220,000 Total Total 1,950,000 1,730,000 1,640,000 2,100,000 1,800,000 9,220,000 Prior Funding Sources 2011 2012 2013 2014 2015 Total 274 4-070 0-01 PI - PIR/General Obligation Bo 1,040,000 900,000 910,000 1,100,000 900,000 4,850,000 Total SA - Special Assessment 910,000 830,000 730,000 1,000,000 900,000 4,370,000 Total 1,950,000 1,730,000 1,640,000 2,100,000 1,800,000 9,220,000 Page 26 Hidrresdoy. A", 26. 20/0 CAPITAL MPROVEMENT PLAN City of Hopkins, MN Public hearing -) ear prior to plami cd CO n,ll u a i o n Plans and specifications - year prior to hlunn:d :on,t t:tion Bid and assessment - 3 ear of plaimcd :OI I ltl_Ua i0lI 2011 atrii 2015 Ucpartit) ctit Public %\,wkl `,trot, I ratfic ( untact PUNIC \\ ork, D;rr.tor with the Cite Council adopted RoA%\a\ Impro\Cnt:ut Policy. ,trCCt I-atinc,..tnd Pa\:Iti:nl \].ut.i_Cm:nt I i, ,.i l,., '/ _ • E • CAPITAL INTROVEMENT PLAN City of Hopkins, MN Project# 01-CIP-S102 Project Name Residential Street Improvements --Utilities Future 2011 rhru 2015 Department Public Works: Streets/Traffic Contact Public Works Director T) pe Improvement Useful Life Unassigned Category Trans: Streets Priority n,/a *rota) Project Cost: $3,330.000 Locations to be determined as they, are consistent with the street reconstruction program. Program to reconstruct deteriorated water main and sanitary sewer and to provide storm sewer improvements in conjunction with street improvement projects. iblic hearing: Year prior to planned construction ans and specifications: Year prior to planned construction d: Year of planned construction Consistent with the Storm Water Management Plan. Water and Sewer Utility Master Planand television inspection Justification In most cases where street reconstruction takes place, storm sewer facilities either need upgrading or need to be installed new. In some cases, water main and sanitary sewer need to be rehabilitated in conjunction with street reconstruction. The numbers assume the city funding 100% of major storm sewer, water main, and sanitan sewer re/construction. These costs are to be used in conjuncton with street reconstruction costs shown on 01-CIP-S 101. Prior Expenditures 2011 2012 2013 2014 2015 Total 1,900,000 Construction/Maintenance 275,000 275,000 290,000 290,000 300,000 1,430,000 Total TOW 275,000 275,000 290,000 290,000 300,000 1,430,000 Prior Funding Sources 2011 2012 2013 2014 2015 Total 1,900,000 SF - Sanitary Sewer Fund 100,000 100,000 100,000 100,000 100,000 500,000 Total SU - Storm Sewer Fund 100,000 100,000 110,000 110,000 110,000 530,000 WF - Water Fund 75,000 75,000 80,000 80,000 90,000 400,000 Total 275,000 275,000 290,000 290,000 300,000 1,430,000 Budget Impact/Other Public Hearing - year prior to planned construction Plans and specifications - year prior to planned construction 3id - \ ear of planned construction with the Storm Plan. Water and Sewer Utility Master Pa2e28 Nednesdcn% t1m,'6. 20/0 CAPITAL MPROVEMENT PLAN City of Hopkins, MN 2011 1!11'1! 2015 DcV:u-iill •lit Public %\ r,rk, titrcct, I ntllic ( untact Pubir,: \\ork, Ihr'ra r 0 0 • • CAPITAL RvIPROVEMENT PLAN 2011 rhru 2015 City of Hopkins, MN Project# 01-CIP-S103 Project Name Citywide Concrete Alleys Future 10: Lake Street NE alley (South side of Lake Street NE) (Murphy to Texas Avenue) Department Public Works: Streets/Traffic Contact Public Works Director Ty pe Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $1,139,000 11: Alley south of 6th street South and North of Nine Mile Creek, between 11th Avenue South and 10th Avenue South. 12: Alley south of 3rd Street North and Nrth of 2nd Street North, between 61h Avenue North and 5th Avenue North. Program to construct concrete alleys in aras designated as poor on the Alley Condition Survey. Hearing - y ear prior to project. specifications. bid. construction -year of project. tant %with the Ctiv Council adopted RoadN%ay Improvement Policw and Justification 'he city has had a policy of constructing concrete alleys for a number of years. This policy has proved to be sound by the concrete alleys` urability and low maintenance costs. Current policy has the city share at 20% of the cost in residential areas. The city u ill experience cost ivings due to lower maintenance costs. Prior Expenditures 2011 2012 2013 2014 2015 Total 1,020,000 Construction/Maintenance 58,000 61,000 119,000 Total Total 58,000 61,000 119,000 Prior Funding Sources 2011 2012 2013 2014 2015 Total 7020,000 PI - PIR/General Obligation So 11,600 13,000 24,600 Total SA - Special Assessment 46,400 48,000 94,400 Total 58,000 61,000 119,000 Approximately 1250 feet per year for four years Public Hearing - year prior to project Plans, specifications, bid construction - year of project .with and Page 30 If' dnes&n•. I&n- 26. 2010 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN 2011 il» 1i 2015 Dc partill cnl Public 1\ ork, 1u'ect I raific ( oniact Puhlj,: ork, I)irca,,r • 0 CAPITAL IMPROVEMENT PLAN A City of Hopkins, MN Project # 01-CIP-S104 Project lame County Road 3 Future 2011 rhru 2015 Department Public Works: Streetsfrraffic Contact Public Works Director Ty pe improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $2.300,000 County Road 3 from Shady Oak Road to Meadowbrook Road. Lighting, landscaping. street etc. improvements along Excelsior Boulevard from the east to west city limits. GO Bond payments to be financed by a combination of existing TIF revenue. Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds. and. as a last resort, general city revenue Segment 1: Construction - 19981 1999 Segment 2: Planning - 2004: bidding and construction (median upgrades only) - 2005 Segment 3: Planning and acquisition - 1999/2001. bidding/construction - 2002/2003/2004 Segment 4: Planning and acquisition - 2012/2013. bidding,'construction - 2014/2015 TIF funded work includes the following: A signalized intersection will be constructed at Monroe Avenue. A second intersection will also be built at Jackson Ave/St. Louis Street. There will also be a reconfiguration of Monroe Avenue and Milwaukee south of Excelsior Boulevard. This work is being completed in conjunction with the reconstruction of Excelsior Boulevard from Highway 169 to Blake Road. The intersection is being constructed to facilitate redevelopment of the SunerValu north annex site. Justification Deficiencies in terns of roadway condition, traffic/pedestrian movement, safety and aesthetics appear in all four segments of County Road 3: -Segment ( from Shady Oak Road to 1 nth Avenue S.: upgrade existing undivided roadway. upgrade 1 nth Avenue intersection to meet future needs. implement beautification program --completed in 1998 - Segment 2 from 1 Ith Avenue S. to Hlv% 169: median pavers construction - Segment 3 from highway 169 to Blake Road. upgrade existing narrow undivided roadway. resolve safety issues at railroad crossing, improve north -south access. account for future LRT access, address redevelopment needs, add integration for full access at Jackson Avenue. - Ceoment 4 from Blake Road to Meadowbrook Road: upgrade roadx%2\. implement beautification program. Prior L.�=J Total Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 2,300,000 2,300,000 Total 2,300,000 2,300,000 Prior Funding Sources 2011 2012 2013 2014 2015 Total 0 GU - Other Governmental Unit 1,600,000 1,600,000 Total MS - Municipal State Aid Stree 700,000 700,000 Total 2,300,000 2,300,000 GO bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds. additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue. Segment 1: Construction - 1998/1999 Segment 2: Planning - 2005: bidding and construction (median upgrades only) - 2006 Segment 3: Planning and acquisition - 199912000: bidding/construction - 2003/2004 Segment 4: Planning and acquisition - 2012/2013: bidding and construction - 2014/2015 ('(insistent with Hennenin Countv CIP and Cite Council action. Pace 32 11 ednes&n% 11m '6. '010 CAPITAL RvIPROVEMENT PLAN City of Hopkins, MN 2011 thrit 2015 De 1) a rt m c n I hihli, %\ )Th, 1,ii e,!t, I ra I is ( miNict Puhh,: \\ork, 0 CAPITAL INTROVEMENT PLAN A City of Hopkins, MN 0 • Project # 01-CIP-S106 Project Name County Road 61 (Shady Oak Road) Future 2011 thru 2015 Shady Oak Road from County Road 3 to T.H. 7. Mainstreet from 20th Avenue to Shad) Oak Road. Lighting, lanscaping. street. etc.. improvements from County Road 3 to T.H. 7 Reconstruction and amenities on Mainstreet from 20th Avenue to Shad} Oak Road. Reconstruction of West Park Road. 2nd Street N.. and 21 st Avenue N. (2nd Street -4th Street N.) also 01-CIP 0003 for the Storm SeNver Management associated with this project. Department Public Works: Streets/Traffic Contact Public Works Director T� pe improvement useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $27,225,430 Justification Deficiencies appear on Shady Oak Road in terns of roadway conditions, traffic/pedestrian movement safety, and aesthetics. upgrade an undivided roadway. resolve safety issues with number of drivewa} access points and intersection at Mainsheet. Lighting needs upgrading and provide beautification program. of Mainstreet for I block section needs to be done to conclude the upgrading of all of Mainstreet. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 6,596,549 20,628,881 27,225,430 Total 6,596,549 20,628,881 27,225,430 Funding Sources 2011 2012 2013 2014 2015 Total GU - Other Governmental Unit 2,010,000 20,178,881 22,188,881 MS - Municipal State Aid Stree 4,437,849 4,437,849 PI - PIR/General Obligation Bo 100,000 200,000 300,000 SA - Special Assessment 48,700 250,000 298,700 Total 6,596,549 20,628,881 27,225,430 2005/2013: Planning and acquisition 14/2015: Bidding and construction stent with Hennepin County CIP, city's desire to upgrade the roadway. and reconstruction program for all of Mainstreet. project totals $27.225.430. Hopkins share is $5.036.549 of which we have $1.3 million budgeted. The remaining $3.5 + million is right -of tcauisitions for which we currentlN have no funding. The project is not feasible under the current funding program. Paee 34 I1ed,res&n% t/cn- 26. 10/0 CAPITAL IlVIl'ROVEMENT PLAN City of Hopkins, MN 2011 , rr, 2015 UcpartntcnI I,uhlic 1\ or1,. Iu::t, I rani: ( ontaci Puhh: \fork, Ihrc:Ior • • CAPITAL IMI'ROVEMENT PLAN City of Hopkins, MN 2011 thru 2015 Project# I0-CIP- SI20 Project lame Highway 7 and 5th Ave North - Signal Replacement Future Department Public Works: Streets/Traffic Contact PW Director Tt pe Improvement Useful Life 25 years Categor} Trans: Streets Priority 3Important Expenditures 2011 2012 2013 2014 2015 Total Construction 445,000 445,000 Total 445,000 445,000 Funding Sources 2011 2012 2013 2014 2015 Total GU - Other Governmental Unit 300,000 300,000 PI - PIR/General Obligation Bo 145,000 145,000 Total 445,000 445,000 Pa2e36 Ifidnes&n•. Vur 26. 20/0 CAPITAL INTROVEMENT PLAN 2011 1 rii 2015 City of Hopkins, MN Project # 10-CIP-S119 Project Name Emergency Vehicle Preemption (EVP) Signal Upgrade Future D cpartment hthhc \\ ork, ti(I"eCl, I I3111c ( untact PIN I,: \\, rk, I>ii I.Npe Impicmrnl t ,cful I il'c 2 ` . ar, ( atc_or� I rang tilgn Si_nah Priorih ? \'crN Important Description I I utal Project ( u,[: 5111.000 Upgrade traffic signals on Excchtor B1\ J at the 11 _h a 101) t:[ull„ to mc] 11 e "I_nt r n�\ \ ,hirl f'rccny,tioll" I:al,,thilitir>. Justification Emergency Vehicle Preemption 11"\ 11) i. I i I C u1,_�raIIC that IHCrC;nC ,,Il n iuriII', III) IirC I irr rr,hon, , h\ dcicctirl,❑I,hrt,,t�hin, rmrr n� "vehicle and changing the traffic ,ipal lir thCir Lru,.in_ til the intruCCti n Expenditures 2011 2012 2013 2014 2015 Total Construction 40 Oa0 400D Total 40,000 40,000 Funding Sources 2011 2012 2013 2014 2015 Total PI - PIR/General Obligation Bo 40 OJC 40 O, O Total 40.000 40,000 is CAPITAL IN4PROVEMENT PLAN A City of Hopkins, MN Project # 01-CIP-F502 Project Name Light Rail Transit Stations (2) Future 2011 117ru 2015 Department Public Works: Transportation Contact Public Works Director T% pe Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $110,000 1) Intersection of Third Street South and Fifth Avenue South 2) Second Street Northeast Supplemental improvements to two Light Rail Transit (LRT) stations in the proposed HCRRA locations. Justification The HCRRA proposes to construct two stations along the Southwest Corridor. The proposed expenditures would he in addition to the funds expended by the HCRRA. The additional funds would be used to ensure the stations are high quality in appearance. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 150,000 150,000 Total 150,000 150,000 • Funding Sources 2011 2012 2013 2014 2015 Total TF - Tax Increment Financing 150,000 150,000 Total 150,000 150,000 on HCRRA plans. with plans for LRT stops in Hopkins by Hennepin County. 0 Page M Jt ednesday. 11ar 26. 2010 CAPITAL HOPROVENIENT PLAN 2011 th ,t 2015 7�T Ik•p:urhnent I'uhli� 1i,,rh, Iran,p,,nau,,n City ofr ,� Hopkins, �'l1V (0111:10 Nuhli,� \ Diri:,t,v Project # 01-CIP-F503 I N pc hrprrn mein l Cul I ifc t 11 nicd Project Name Eighth Avenue LRT Corridor < atc_ur\ I ran, �ucct, Future I'riurit� n a Description I wal hr„ic t (,).c s-uu.ono Eighth Avenue from County Road ; to I ir.t tiurct \onh Relocation of utilities and recxmsuvC(inn Of ,trCCI tri ❑CC,lnunn&JtC li�,ht r,r:l u;ut,it line f- m ( offlM ItOJd ” ti, V;iin,ur,t. 0111,trurtitln Of pedestrian way. Justification Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance '00100 701 Total 700.000 700.000 Funding Sources 2011 2012 2013 2014 2015 Total SF - Sanitary Sewer Fund 350 03" 35.0 X0 SU - Storm Sewer Fund 100 J11 100 700 WF - Water Fund 250 01,`, 250) 0 Total 700.000 700,000 Budget Impact/Other Dependent on HCRRA plans. Consistent with recommendations imidc in I Ilakk r i_ , • • • • • CAPITAL UMPROVEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project # 10-CIP-F504 Project Name Seal Parking Ramp Concrete Decks Future Description lean and seal concrete parking decks "ith penetrating sealer. Department Public Works: Transportation Contact Public Works Director T) pe Improvement Useful Life Category Trans: Parking Facilities Priority n/a Total Project Cost: $28,000 Justification Sealing of post -tension steal reinforced concrete decks is required every (7) seven Nears to extend structure life by protecting against moisture and chloride penetration. Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 28,000 28,000 Total 28,000 28,000 Funding Sources 2011 2012 2013 2014 2015 Total PKG - Parking Fund 28,000 28,000 Total 28,000 28,000 Pane 40 If ednesdcn% lkcm 26. 2010 CAPITAL HAPROVEMENT PLAN 2011 ihrii 2015 City of Hopkins, MN Project # 01-CIP-0002 Project Name Storm Drainage System Maintenance - AlleN Repairs Future 2009-2013: Concrete alley" repair Justification I Annual aIle) pavement concrete dah rq)air, arc n::d:d Dcp:u'tIncnl 11111Ml: \\ ork, lulu r ( ontact PuMi: \\ ork, D ::tov 1.% pe Improx:mrnt l'Jul 1 ife 1 na„tenrJ ( atc_on 1 Ulitir, \lune q,al S,tnit.tn ti Priuriit n a ural {'rnjcct ( u.t: 'w126.111111 Prior Expenditures 2011 2012 2013 2014 2015 Total 32,000 Construction/Maintenance 1 0J01 8 000 19 000 20 000 20 DJC 94 000 Total Total 17,000 18.000 19,000 20.000 20,000 94.000 Prior Funding Sources 32,000 SU - Storm Sewer Fund Total 2011 2012 2013 2011 2015 Total 17 0JO 8 OOJ 9 Ob0 2C 000 20 005 Q4 000 Total 17.000 18.000 19.000 20.000 20,000 94,000 with the Storm Water NLm.t_imik:w flat. • • 0 0 CAPITAL IMPROVEMENT PLAN 2011 ihru 2015 Department Public Works: Utilities City OlrHopkins, NN Contact Public Works Director T� pe Improvement Project # 01-CIP-UO03 Cseful Life Unassigned Project Name Storm Water Management Projects Category Utilities: Storm Sewer Future Priority n/a "Total Project Cost: $200,000 14: Provide outlet pipe to Shady Oak Pond into CSAR 61 storm drainage piping in conjunction with Shady Oak Road reconstruction Justification ihady Oak Pond has no outlet and floods streets and residential property if not pumped. -onsistent with City Council approved action plan of October 21. 1997. the City's Storm Management Plan. and Shady Oak Road reconstruction Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 Funding Sources 2011 2012 2013 2014 2015 Total SU - Storm Sewer Fund 200,000 200,000 Total 200,000 200,000 Budget hnpact/Other with City Council approved Action Plan of October 21. 1997. the City's Storm Management Plan, and Shady Oak Road reconstruction i Pace 42 11 ednesdm% 11tH 26. 2010 CAPITAL IMPROVEMENT PLAN 2011 fi„ ;t 2015 �,(�� Dcpnr Artcnt Public \1,ul u'L. l iUc, City ofHopkim, 1V11V ( (1ntact PuMi,: \fork, I)irc,:trr lProjecl # 08-CIP-U00p Project Name Meter Replacement Future I .N pr Imps cmrnt t �cful I ifc (:ric'Cor� 1 trlrtirS unicit,il ',anitan ti Vriorih n a Prior Expenditures 2011 2012 2013 2014 2015 Total 7-1-90-00-01 Construction/Maintenance 95 000 95 000 95 1)00 285,300 Total Total 95,000 95.000 95,000 285,000 Prior Funding Sources 190000 WF --Water Fund Total �-m 2011 2012 2013 2014 2015 Total 95 000 95 000 95 000 Total 95.000 95.000 95.000 285 000 285,000 CAPITAL IMPROVEMENT PLAN 2011 thru 2015 • City of Hopkins, MN Project # 08-CIP-U001 Project Name Lift Station # 4 Future LS No. 4 Justification Lift station No. 4 "as identified for rehab in the 2007 comprehensive utility plan Regular major maintenance identified in the 2007 comprehensive utility plan. Department Public Works: Utilities Contact Public Works Director Tt pe Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $160,000 Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 160,000 160,000 Total 160,000 160,000 • Funding Sources 2011 2012 2013 2014 2015 Total SF - Sanitary Sewer Fund 160,000 160,000 Total 160,000 160,000 Page 44 H'adnesdcn•. 110, 26. 2010 CAPITAL RvEPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-UO08 Project Name Emergence Chlorine Shut Off Vali es 2011 iln'u 2015 UepariTucnI Public %\ ork. I tilde, ( ontacl I aoljlie� t)ni,:tur pc 1111pr crmrnt t cful I il'c ( aLcalon I tilitirs Nlunt,ihal tianttar Future Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 33 C0) 33 J30 Total 33.000 33,000 Funding Sources 2011 2012 2013 2014 22015 Total WF - Water Fund 33 000 33 D00 Total Budget Impact/Other 33,000 33.000 7 0 1 01 r • CAPITAL INTROVEMENT PLAN 2011 rhru 2015 City of Hopkins, MN Project # 08-CIP-UO09 Project Name Sanitary Sewer Lift Station Maintenance Future LS Major Maintenance Justification Regular major maintenance identified in the 2007 comprehensive utility plan. Department Public Works: Utilities Contact Facilities Director Tpe Improvement Useful Life Categoo Utilities: Municipal Sanitary S Priorit-, n/a Total Project Cost: $15,000 Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 15,000 15,000 Total 15,000 15,000 Funding Sources 2011 2012 2013 2014 2015 Total SF - Sanitary Sewer Fund 15,000 15,000 Total 15,000 15,000 Budget Impact/Other Paae 46 IWnes&n•. Win- 26, 2010 CAPITAL RvfPROVEMENT PLAN 2011 ,irr'u 2015 I) cp:u Inu nt Puhlic \ ori t ,tlitir, City of Hopkins, 1V11V (untatct I aolrtic, Ihrcct„r IP oject# 08-CIP-UU10 oject Xame St. Louis Park Emergency Connection Future Description St. Louis Park emergency connection. Justification items identified in 2007 comprnccmkc unlit lion t') hn'\ i.ic .nl'C ;u, i r.liuhlc ,,ttcr 1 .\ lu ImhroN cmem I 'cful I ifc ( I ulitrc> �luniciral ti,untan S I'riurit� n a ural1'rujcct (u.t: 5211.000 Expenditures 2011 2012 2013 2014 2015 Total Construction/Maintenance 2' 1 X90 211 3K Total 211.000 211.000 0 1 Funding Sources 2011 2012 2013 2014 2015 Total WF - Water Fund 2' 1 XQ 211 DO Total 211.000 211.000 CAPITAL IlSAPROVEMENT PLAN 2011 thru 2015 IS City of Hopkins, MN 0 • Project # 08-CIP-R001 Project \ame Skate Park Future equipment enhancments to Overpass Skate Park Justification Department Recreation Contact Facilities Director T% pe Improvement Useful Life 15 years Categor) PW - Parks Priority n/a Total Project Cost: $28,000 Per our agreement with 3rd Lair, who manages the Skate Park, we need to put $7.000 of enhancements into the Skate Park for the years 2006-20 The agreement for 2009-2011 requires annual enhancements of $7.000. Per the Overpass Skate Park Operators Agreement, the city annually puts an amount specified in the agreement of enhancements into the park to change/improve the park each year to keep the park attractive and challenging to users. Prior Expenditures 2011 2012 2013 2014 2015 Total 21,000 Construction/Maintenance 7,000 7,000 Total Total 7,000 7'000 Prior Funding Sources 2011 2012 2013 2014 2015 Total 21,000 PDF- Park Dedication Fund 7,000 7 Total Total 7,000 7,000 Budget Impact/Other =otmerly budgeted in Skate Park Enterprise Fund. which was eliminated 12/31/2005. it is now budgeted in the Park Dedication Fund. Pate 49 I1 idnesdaY. t1m 26. 2010 CAPITAL H PROVEMENT PLAN 2011 ihrii 2015 City of Hopkins, MN Project # 10-CIP-RO02 Project Name Depot Recreation Arca Future Dc pa rttile nI kr.rcaUun ( ontacl P\\ I)IRCL,i I , pe In l)r„\ en,rnt I ,crul I ire '_� \car, ( :recon I'\\ - Park„ PrioriIN ? \cr\ Inlh\uiant Description I 1411:0 Prniett ( mI: S500.1100 this project includes the addition I1'an,nrld\\nr murillk court and .Ul)l),vt huiILIini-i('n propert\ \\c,t of - the I)CPot I"acilit\. Ihc,C amenities are proposed to he utili/Cd a. l,,u-t Ot' I )CI)01 \ ('ill 11 Cn_.I_enlent ,Inti\ itis, and a, hart ,\I the cr,mmunit', ICC Ica_"Uc, ,111d I,Ia\ _r„UnLl )rograms. The multipurpose rink COLIN \\ ill iIIClu,1e ,ill u.i)h,llt ,urltice ,111,1 h(1CkC`, ,1a.hcr htalr,1. Ik,r ,L,Itill_ and I)r,',,nlh.tll u.0 in the \\inter: and Nuipmentto accommodate baskcthall. inIinc .katin_. \ollc\h,lll and occcr A,'Cs in thr,luin ,umnlcr.ln,1 Iall nl,nnh.. lhc.ul)l,urt (malar\ \\ill nclude equipment for a bike maintcn,alcc .old rcl,air ,itc ,l)\nl.\,red h\ t!lr Uclh't..0 \\c1I nultipurposearea to be used as a \\;irmin_ huU.c in the \\ inter. Grant of$150-Uuu \\ill he Urrlicd for. Justification rhe Depot site has needed outdoor a menitic, fi,r it, t❑r ct ,Iu lienee ,incC its li,undinL,. \ \ r,ir-11,4111,1 ,hl,rt, ",Inch„r" ,n the I)ch,,t ,itc tIl 'omplement arts and music and entrCl1IC11Uri;Il hu>inc„ 1AI"Cricnc1: I:v \0LIth \\ ill pro\ Idc additional renii-Orcetllcrllerlt \,f positi\e hchu\ i„r.. As nore people come to the Depot t1,r }outh aCti\ itie. a. \NCII 11> _cnruc dL1,1\h\,ur c.11 ,tlrlll_ ,l\ IiI11C ,..uh a cI'arilit% COUId hr tl'ed 'Ill da\ and into the tvening hours. Proximity to the rail corridor \\ill aca,rd hi_h \ i.ihilit\ and ,\nlholiic arii\r li\ in_ ,old ronununit\ connection. in ❑ \\aI ,Iblc. like -able community. Rec league hnu,ulh;tll Or h\\chc\ COtIld ,h,irc ice \\ it[) licetinlcs. 1 t\ral hu,inc» cnll,l„\ cc ec,uld uli.c ,id\.Intauc tll he facilty over lunch times. La.\ Ir.11l aCCe„ IIIAC, the I)Cpot ,ind e;l,\ lith I01- kids \\ ho \\Ullld Como there to pl,l\. I he I)Crol h.r, I)CCIl \\,UhIII_ ox%ard more bike -oriented prgrams opert to the \\ hole ronunurlit\ I c._ 13i c �cre,un \un,1a\.1 ,old ha, ,onr: connection. alread\ \\ ith local hal c etailer/advocates at FreeA%heel h\ h\„ull_ I hik,: c\luiI)IICI t \endiII . In,Ichine \\n ,itc. l)rdir,ltrd ,hare \\gold _i\r uc,\ l,\,.,ihilitic.s to illi. a.l\crt if the "Depot on the Move" Initiati\ C. Expenditures 2011 2012 2013 2014 2015 Total Construction 500 000 500 000 Total 500.000 500.000 Funding Sources 2011 2012 2013 2014 2015 Total GU -Other Governmental Unit 500 000 500 000 Total Budget hnpact/Other 500.000 500.000 • U • CITY OF HOPKINS FINANCE DEPARTMENT LJ 0 MEMORANDUM Date: June 8. 2010 To: Mayor & City Council From: Christine I larkess. Finance Director Subject: 2011-2015 Equiprnent Replacement Plan (ERP) Overviews The City of Hopkins is beginning the process of establishing the 2011-2015 equipment replacement plan. F,very year the city council reviews with the city manager and staff, the equipment planned for replacement for the next five years. The goal is to ensure the city's priorities and objectives are being met and the funding sources are reasonable and available. Departments were once again asked to assess the equipment planned for replacement, evaluate the estimated cost and life expectancy of the equipment with the intent to prolong equipment life expectancy when practical and to refurbishing equipment instead of replacing it. Through a combination of several equipment changes and a better estimate of costs, departments were successful in accomplishing this goal. Included in the ERP draft is an explanation of the changes that are considered for implementation. ERP Goals • Maintain the integrity, reliability and safety of city equipment. • Provide funding for replacement of current equipment as needed. • Forecast funding needs and tax implications to assure strong long-term financial stability. Attached is a draft of the 2011-2015 equipment replacement plan. 1. Summary of Changes 2, ERP Cash Flow Analysis 3. 20 year ERP plan 4. ERP Projects by year 5. Fundine Source Summary 6. Projects by Funding Source 7. Department Summary 8. Projects by Department 9. Individual Project Sheets • ERP — SUMMARY OF CHANGES IN 2011-2015 PLAN General 1. Incorporated rate increases for years 2011-2015 ERP Fund 1. City Hall — no changes 2. Community Services a. One copier to be replaced in 2011 and the second copier due in 2011 was moved to 2013 3. Fire Dept a. 2012 — Extraction tool cost decreased from $26,500 to $22,300 b. 2013 — Thermal imaging cameras decreased from $18,000 to $11,500 c. 2014 — Automated defibrillator — increased from 2 to 4 for same replacement cost and moved from 2013 to 2014 d. Purchased a Summit trainer in 2010 instead of Stairmaster — replacement scheduled for 2015 4. Police — no changes 5. Public Works— Forestry a. 2011 — two items scheduled for 2011 were moved back to 2012 i. %z ton pickup • ii. 3/4 ton utility truck b. 2011 — tractor scheduled for 2012 eliminated as toolcat was purchased in 2010 and tractor due in 2014 was pushed back to 2016 c. Riding mower due in 2011 pushed back to 2013 6. Public Works— Streets/Traffic a. Tandem dump truck — move truck due in 2013 to 2011, refurb at a cost of $22,000 and extend life to 2018. Move 2015 purchase to 2013 b. Skid steer loader — move 2010 purchase to 2011 c. Sweeper due in 2013 for a cost of $164,500 has been reduced to $156,400 Arts Center Fund 1. Carpet Extractor added in 2012 - $3,000 Pavilion Fund 1. Ice Resurfacer—price change from $88,100 to $180,000 2. Ice Edger added in 2014 at a cost of $5,000 0 I1tJI'\1I\I RI -VI VI -NII -11 Ft \D (6112) 0 Rate Change 4 11 V U XI V H ki lit 1)(11 1 lit 11(.1 I lit W. I I lit D(J I lit DW I lit MJ I 2111p8 21"19 2110 21111 2012 21114 2015 Working Capital Begun Year -,-I Sfi 1 -, . - ,: I'd I'll I ,'ti --I II -,—] I;! ,,, S' .", Re%vutws from charges 28.12' ZS -.463 293.212 3112.0111) 314.1,Y) 329.'93 349.581 3-41.356 Transfer in General Fund Transfer In - Pavilion - Capital Lea,, Transfer In - Pat Ilion - Hocked Loan Federal State Grams II 1 1 Fire Truck lease Reimbursement -Radio System Interest earnings Otherre%enties isalcofassets) Total Rimennes 801.025 31111.928 3114.115 311 413.322 39.'812 390,1'2 411.819 E\pendituresi excludes Dept Fire Truck Financing P\Tnnl 12009-2, 1 Capital Oill - Equipment 1.119.011 184;.46- 282.1110 9-M.-IIII 631.-M11 3-511I 412.2011 'Fran sler to Pat thon (loan) Working Capital Ending Balance 1.031-05 1.161.011 1j,8-44 1.123.0111 15I.S96 S3.IIS2 (8.6-3) Cash balance 1, -9(,1'2,4.3' 1.135,32- 4NN. 14.7 A3,321 94.;15 2.-53 .4femo On Long Term Recenable 2007 llocktl% Booster Loan repI It Cash Balance - I I Rew\able 0 • • • X � z O. � F � O O � � •D C� m y e ti - o gg gq $ c �.• Yj X g X o O r O O o 0 J s � .� C s =� •" � � � L �, .Y $ �, t. � `� � _ 3 £i �1-' v 3--' � `� u ::> t -i •.�.+ u � 2 � CT$Si j � ,. 3F � $� � W = u = � u u e 4 •, rX ;n Y 'o ' O v i mill y aaf' y- y,� u � � v� a z� zs zCz'd� ccrtz°dz °d °d ccrtcma°dz P 8 I P = Q r v y b = - ag J W r - _ W r V1 J• l l _ _ _ _ Y _ _ _ / i � - _ 1 _ p� �+� � 0 10 le K / § ! % k ( $ ƒ f / $ \k I a! » \ K / § % ! $ # / $ � /\ Cl 91 01 71 7 7 C9 d oL c w Z - :: - - - - - - - - - - - - - - - - Cl 91 01 • • z Z Z ~ pqq� O C C Oyu. i 4L F L �.. z�L ccw���ga3byou uQ�e 5�z ue as u = t d �eeeeF u _ =oma pppLjuz<r :7J oC h r. N '� 8 po N i•c � � C p 8 � d: ? epp`I h � �6 C� pp Qo pp oQ W x— �• '$ %. p C N �I' N N Y Pro rvi 4' r i t 2 $ L J N 8 p C Lm i3 p 8 �j p Op O 8 C z Z Z ~ pqq� O C C Oyu. i 4L F L �.. z�L ccw���ga3byou uQ�e 5�z ue as u = t d �eeeeF u _ =oma pppLjuz<r :7J oC h Cite of Hopkins, NIN F_OUP.1fENT RF_PLACF_.IfENT PLAN 2011 2015 PROJECTS BY YEAR Project Name Department Project ±t Priorit.\ Project Cost 2011 Art Center Copy Machine Arts Cen-er 01 -ERP -1100 n a ' 2 100 Network Server City Fall Admrnistraton 01 -ERP -003 ma 81,100 Computers City F all Ad ninistravon 01 -ERP -006 n a 30 0;10 City Hall Main Copy Machine - Oce' Cop er Commurty SeR ices 01 -ERP -001 n ra 13 000 Engineering Printer/Scanner Ccmm,irry Services 01 -ERP -007 n 113 000 Document Management Scanner (3) CcmmunitySeRIces 01 -ERP -008 na 5500 Aerial Truck Fire 01 -ERP -106 n'a 54 217 Copy Machine Fre 01 -ERP -110 n a 10 300 Marked Patrol Vehicles (6) Police 01 -ERP -200 ma 57 200 Sergeant's Vehicle Police 01 -ERP -201 n a 33 600 Police Administrative Vehicles (2) Police 01 -ERP -204 n a 27 900 Copy Machine Pcllce 01-E.RP-209 n a 19 100 Network Server (3) Police 01 -ERP -211 n a 8 500 Tandem Dump Trucks (2) Public %Yorks Streets Tra"i, 01 -ERP -306 n a 22 000 Skid Loader (2) Publ,c 1Ycrks StreetsTraffc 01 -ERP -309 n a 36 003 oral for _III 1 358 417 2012 • Art Center Carpet Extractor ArtsCen*,er 01-E.RP-1101 n 3300 Network Server C'y Fall admin strat,nn 01 -ERP -003 n a 8 000 Computers City Fall td nimstraron 01 -ERP -006 n a 30 100 Engineering Printer/Scanner Ccmmurry Services 01 -ERP -007 n a 11000 Document Management Scanner (3) Ccmmur�ySen-ices 01 -ERP -008 n 3500 Quick Attack PumperlReswe (Rescue 8) Fire 01 -ERP -105 n a 234 000 AeriaITruck Fire 01 -ERP -106 n'a 54217 Extrication Tool (2) Fire 01 -ERP -109 n.a 22300 Workout Equipment - Treadnafi F re 01 -ERP -118 n -a 5 030 Workout Equipment - Dumb Bells Fire 01-EPP-122 n 5000 Marked Patrol Vehicles (6) Police 01 -ERP -200 n'a o9 200 Police Administrative Vehicles (2) Pol -e 01-EPP-204 n a 28 800 Network Server (3) Police 01-EPP-211 n 8500 Mobile Data Computers Police 01 -ERP -212 n a 62 700 Radios -Portable and Mobile Devices Police C1 -ERP -215 r 15000 1/2 Ton Pickup Truck Publ c'%Ycrks Parks Fc-estry 01 -ERP -800 n a 25 400 4x43/4TonTrucks (2) Public 'JJcrks ParksFores:ry 01 -ERP -801 n 67400 314 Ton Utility Truck Public'ddcrks Pa,ks Fores'ry 01 -ERP -802 n'a 32 200 Trucksters (3) Public `A-rks Pa,ks Fo-es:ry, 01-EPP-807 n a 19 300 Riding Mowers (3) Publ,c 1"dcrks Pa,ks Forestry 61 -ERP -808 n a ' 0 300 1 Ton Dump Truck (2) Public %dcrks Streets Tra"ic 01 -ERP -303 n a 34 700 1 Ton Traffic Boom Truck Public 'dcrks StreetsTraffc 01-EPP-304 n 75000 Front End Loaders (2) Public '%,crks Streets Traffic 01 -ERP -308 n a 172 )00 Roller Publ c',Yorks Streets Tra" c 01 -ERP -312 ma 45 930 focal for 20112 • 1 046217 Pa2c 2 7lrursdm•. Alar 27. 2010 Project Name Department Project # Priority Project Cost •2013 Activity Center Copy Machine Activity Center Of -ERP -030 n/a 15,000 Network Server City Hall Administration 01 -ERP -003 n/a 8,000 Computers City Hall Administration 01 -ERP -006 n/a 30,000 City Hall Small Copy Machine Community Services 01 -ERP -002 n/a 20,000 Engineering Printer/Scanner Community Services 01 -ERP -007 n/a 10,000 Document Management Scanner (3) Community Services 01 -ERP -008 n/a 6,500 Aerial Truck Fire 01 -ERP -106 n/a 54,217 Thermal Imaging Camera (2) Fire 01 -ERP -112 n/a 11,500 Marked Patrol Vehicles (6) Police 01 -ERP -200 n1a 71,200 Police Administrative Vehicles (2) Police 01 -ERP -204 n/a 29,600 Network Server (3) Police 01 -ERP -211 n1a 8,500 Tactical Ballistic Vests Police 01 -ERP -214 n/a 23,200 Radios - Portable and Mobile Devices Police 01 -ERP -215 n/a 15,000 Engineering Van Public Works: Engineering 01 -ERP -700 n/a 21,500 Riding Mowers (3) Public Works: Parks/Forestry 01 -ERP -808 n/a 22,800 Brush Chipper Public Works: Parks/Forestry 01 -ERP -813 n/a 25,700 4X4 314 Ton Truck with Plow Public Works: StreetslTraffic 01 -ERP -301 n/a 30,400 Tandem Dump Trucks (2) Public Works: Streetsirraffic 01 -ERP -306 n/a 142,400 Sweeper Public Works: Streetslrraffic 01 -ERP -311 n/a 156,400 Backhoe Loader Water 01 -ERP -502 n1a 134,800 Total for 2013 836,717 2014 Network Server City Hall Administration 01 -ERP -003 n/a 8,000 Computers City Hall Administration 01 -ERP -006 n/a 30,000 • Engineering Printer/Scanner Community Services 01 -ERP -007 n/a 10,000 Document Management Scanner (3) Community Services 01 -ERP -008 n/a 6,500 Aerial Truck Fire 01 -ERP -106 n1a 54,217 Automated External Defibrillator (2) Fire 01 -ERP -120 n/a 7,200 Copier HRA 01 -ERP -401 n/a 13,000 Ice Resurfacer Pavilion 01 -ERP -1000 n/a 180,000 Electric Ice Edger Pavilion 01 -ERP -1001 Na 5,000 Marked Patrol Vehicles (6) Police 01 -ERP -200 n/a 73,400 Utility, 4x4 (un it 212) Police 01 -ERP -203 n/a 47,700 Police Administrative Vehicles (2) Police 01 -ERP -204 n1a 30,500 Logging Recorder Police 01 -ERP -210 n1a 36,900 Network Server (3) Police 01 -ERP -211 n/a 8,500 Digital Squad Car Cameras Police 01 -ERP -213 rda 42,600 Radios - Portable and Mobile Devices Police 01 -ERP -215 n/a 15,000 Riding Mowers (3) Public Works: Parks/Forestry 01 -ERP -808 n/a 20,300 Asphalt Paver Public Works: Streets/Traffic 01 -ERP -314 Na 48,800 Refuse Truck (Rea r -L) Refuse 01 -ERP -901 n1a 101,600 44 314 Ton Truck Sewer 01 -ERP -550 n/a 35,700 Total for 2014 774,917 2015 Network Server City Hall Administration 01 -ERP -003 n/a 8,000 Telephone System City Hall Administration 01 -ERP -004 n/a 89,600 Computers City Hall Administration 01 -ERP -006 n/a 30,000 Engineering Printer/Scanner Community Services 01 -ERP -007 n1a 12,000 Document Management Scanner (3) Community Services 01 -ERP -008 n/a 6,500 • Duty Chief Vehicle (1) Asst Chiefs Vehicles (2) Fire 01 -ERP -103 n/a 37,000 Aerial Truck Fire 01 -ERP -106 n/a 54,217 Pa2c 2 7lrursdm•. Alar 27. 2010 Project Name Department Project -.�: Priorith Project Cost Workout Equipment -Ekptical Fire 01 -ERP -116 n'a 5 800 Workout Equipment- Summit Trainer Fire 01 -ERP -117 n a 5 800 • Workout Equipment- Weght lifting Fire 01 -ERP -119 n a 5 800 44 314 Ton Truck HP, A O1 -ERP -400 n'a 32 400 Marked Patrol Vehicles (6) Police 01 -ERP -200 in a 75 600 Sergeant's Vehicle Police 01 -ERP -201 n a 37 800 Police Administrative Vehicles (2) Police 01 -ERP -204 n'a 31 400 Police Services Liaison Vehicle Police 01 -ERP -206 n'a 22 000 Network Server (3) Police 01 -ERP -211 n a 8 500 Radios - Portable and Mobile Devices Police 01 -ERP -215 in a 15 000 4x4 314 Ton Pickup with Plow Public i`4crks Streets Traffic 01 -ERP -300 in a 33 600 Sgn Machine (Traffic) Publ c ,, crks StreetsTra is 01 -ERP -317 n a 13 400 Refuse Truck (RAP -R) (2) Refuse 01 -ERP -906 n a 204 800 Public Works Copy Machine 'Vater 01 -ERP -506 n a 14 200 I utaI for 2015 743 417 GRAND TOTAL 3755685 • 0 City of Hopkins, MN • EQUIPMENT REPLACEMENT PLAN 2011 thru 2015 r L J • FUNDING SOURCE SUMMARY Source 2011 2012 2013 2014 2015 Total AC - Arts Center Fund 12,100 3,300 15,400 BondstLease 54,217 54,217 54,217 54,217 54,217 271,085 Equipment Replacement Fund 292,100 988,700 647,700 385,400 424,200 2,738,100 HRA -Housing and Redevelopment Authority 13,000 32,400 45,400 PA - Pavilion Fund 185,000 185,000 RF - Refuse Fund 101,600 204,800 306,400 SF - Sanitary Sewer Fund 35,700 6,800 42,500 WF - Water Fund 134,800 21,000 155,800 GRAN D TOTAL 356,417 1,046,217 836,717 774,917 743,417 3,759,685 Pane I Thursdcn% tlur 37, _10/0 Cite of Hopkins, NIN F_OUPI fEA'T RFPLACF..1 fF_.\-T PLA • 2011 1J:ru 2015 PROJECTS Bl' FU DING SOURCE Source 1'rojecv� Priorit.N 2011 2012 2013 20141 2015 Total AC - Arts Center Fund Art Center Copy Machine 01 -ERP -1100 n a 12 103 12 100 Art Center Carpet Extractor 01-EPP-1101 n 33J0 3300 AC -Arts Center Fund '11ota1 12.100 3.300 15,400 Bonds/Lease Aerial Trude 01 -ERP -106 n a 54 217 54 217 54 217 54 217 54 217 271 085 Bonds/Lease 'I otai 54.217 54,217 54,217 54,217 54,217 271.085 jEcluipment Replacement Fund City Hall Main Copy Machine - Oce' Copier 01 -ERP -001 Ti a 13 J J 13 000 City Hall Small Copy Machine 01 -ERP -002 n a 20 Jap 20 000 Network Server 01-EPP-003 n a D30 3 pop 8 000 8 000 8 000 40 000 Telephone System 01 -ERP -004 n a 76 -100 '6 000 Computers 01-EPP-:006 n a 31 XU K ODO 30 3rO 30 000 30 000 150 000 • Engineering Printer/Scanner a -ERP-007 n a 13 "Cl 10 000 0 007 1J 000 12 000 52 000 Document Management Scanner (3) 01 -ERP -008 n a c 50J 3 533 6 500 5 5110 5 500 32 500 Activity Center Copy Machine 01 -ERP -030 n a 5 030 15 000 Duty Chief Vehicle (1) Asst. Chiefs Vehicles (2) 01-EP,P-103 ri a 37 DOO 37 000 Quick Attack Pumper/Rescue (Rescue 8) 01 -ERP -105 n a 234100 234 000 Extrimbon Tool (2) 01 -ERP -109 n a 22 3JJ 22 300 Copy Machine 01 -ERP -110 n a 10 300 10 300 Thermal Imaging Camera (2) 01 -ERP -112 n a 1 500 11 500 Workout Equipment - Elipticai 01 -ERP -116 n a 5 303 5 800 Workout Equipment- Summit Trainer 01 -ERP -117 n a 5 803 5 800 Workout Equpment-Treadmill 01 -ERP -118 r a 5 0DO 5 000 Workout Equipment - WeightLifting 01-EP,P-119 n 5300 5800 Automated External Defibrillator (2) 01 -ERP -120 n a 7 200 7200 Workout Equipment -Dumb Bells 01 -ERP -122 n 5ODO 5000 Marked Patrol Vehicles (6) 01 -ERP -200 n a 7 200 09 2JD 71 200 73 430 175 6 DO 356 600 Sergeants Vehicle 01 -ERP -201 n a 33 500 37 800 71 400 Utility 4x4(unit 212) 01 -ERP -203 n 47700 47700 Police Administrative Vehicles (2) 01 -ERP -204 n a 27 gJp 25 3Dp 29 030 30 500 31 400 143 200 Police Services Liaison Vehicle 01 -ERP -206 n a 22 KO 22 000 Copy Machine 01-EP,P-209 n 9100 19100 Logging Recorder 01 -ERP -210 n'a 36 930 36 900 Network Server (3) 01-EPP-211 n a 8 500 5 5D0 8 500 8 500 8 500 42 500 Mobile Data Computers 01 -ERP -212 n a 52 700 62 700 Digital Squad Car Cameras 01 -ERP -213 n a 42 KO 42 600 Tactical Ballistic Vests 01 -ERP -214 n a 23 200 23 200 Radios - Portable and Mobile Devices 01 -ERP -215 n a 15 OJp '5 OOp 15 000 15 030 60 000 44 314 Ton Pickup with Plow 01 -Epp -300 n a 33 900 33 600 • Source Project# Priority 2011 2012 2013 2014 2015 Total 314 Ton Truck with Plow 01-ERP-301 n/a 30,400 30,400 .4X4 1 Ton Dump Truck (2) 01-ERP-303 n/a 34,700 34,700 1 Ton Traffic Boom Truck 01-ERP-304 n1a 75,000 75,000 Tandem Dump Trucks (2) 01-ERP-306 n/a 22,000 142,400 164,400 Front End Loaders (2) 01-ERP-308 n/a 172,000 172,000 Skid Loader (2) 01-ERP-309 n/a 36,000 36,000 Sweeper 01-ERP-311 n/a 156,400 156,400 Roller 01-ERP-312 n/a 45,900 45.900 Asphalt Paver 01-ERP-314 n/a 48,800 48,800 Sign Machine (Traffic) 01-ERP-317 n1a 13,400 13,400 Engineering Van 01-ERP-700 n/a 21,500 21.500 112 Ton Pickup Trick 01-ERP-800 n/a 26,400 26,400 40 3/4Ton Trucks (2) 01-ERP-801 n/a 67,400 67,400 3/4 Ton Utility Truck 01-ERP-802 n/a 32,200 32,200 Trucksters (3) 01-ERP-807 n/a 19,800 19.800 Riding Mowers (3) 01-ERP-808 n1a 10,300 22,800 20,300 53,400 Brush Chipper 01-ERP-813 n/a 25,700 25.700 Equipment Replacement Fund Total 292,100 988,700 647,700 385,400 424,200 1,738,100 HRA - Housing and Redevelopment A 4x4 314 Ton Truck 01-ERP-400 n/a 32,400 32,400 Copier 01-ERP401 n/a 13,000 13.000 HRA - Housing and Redevelopment 13,000 32,400 45,400 Authority Total • PA - Pavilion Fund Ice Resurfacer 01-ERP-1000 n/a 180,000 180.000 Electric Ice Edger 01-ERP-1001 n/a 5,000 5,000 PA - Pavilion Fund Total 185,000 185,000 RF - Refuse Fund Refuse Truck (RAP-R) (2) 01-ERP-900 n1a 204,800 204,800 Refuse Truck (Rear-L) 01-ERP-901 n1a 101,600 101,600 RF - Refuse Fund Total 101,600 204,800 306,400 SF - Sanitary Sewer Fund Telephone System 01-ERP-004 n/a 6,800 6.800 44 3/4 Ton Truck 01-ERP-550 n/a 35,700 35.700 SF - Sanitary Sewer Fund Total 35,700 6,800 42,500 WF - Water Fund Telephone System Of-ERP-004 n/a 6,800 6,800 Backhoe loader 01-ERP-502 n/a 134,800 134,800 Pubic Works Copy Machine 01-ERP-506 n/a 14,200 14.200 WF- Water Fund Total 134,800 21,000 155,800 • pane 2 7hursdrn•, tfoy ?7. 2010 Source Project Priority 2011 2012 2013 2014 2015 Total GRAND TOTAL 358.417 1.046,217 836,717 774.917 743.417 3,759,685 • • • City of Hopkins, MN EQUIPMENT REPLACEMENT PLAN 2011 thru 2015 PROJECTS BY DEPARTMENT Department Project# Priority 2011 2012 2013 2014 2015 Total lActivity Center Activity Center Copy Machine 01-ERP-030 n/a 15,000 15,000 Activity Center Total 15,000 15,000 Arts Center Art Center Copy Machine 01-ERP-1100 nla 12,100 12,100 Ad Center Carpet Extractor 01-ERP-1101 nla 3,300 3,300 Arts Center Total 12,100 3,300 15,400 ICity Hall Administration Network Server 01-ERP-003 n/a 8,000 8,000 8,000 8,000 8,000 40,000 Telephone System Of-ERP-004 n/a 89,600 89,600 Computers 01-ERP-006 n/a 30,000 30,000 30,000 30,000 30,000 150,000 City Hall Administration Total 36,000 38,000 36,000 38,000 127,600 279,600 Communi Services City Hall Main Copy Machine - Cce' Copier 01-ERP-001 n/a 13,000 13.000 City Hall Small Copy Machine 01-ERP-002 n/a 20,000 20,000 Engineering Printer/Scanner Of-ERP-007 n/a 10,000 10,000 10,000 10,000 12,000 52,000 Document Management Scanner (3) Of-ERP-008 n/a 6,500 6,500 6,500 6,500 6,500 32,500 Community Services Total 29,500 16,500 36,500 16,500 16,500 117,500 Fire Duty Chief Vehicle (1) Asst. Chiefs Vehicles (2) 01-ERP-103 n/a 37,000 37.000 Quick Attack Pumper/Rescue (Rescue 8) 01-ERP-105 nla 234,000 234,000 Aerial Truck 01-ERP-106 n/a 54,217 54,217 54,217 54,217 54,217 271,085 Extrication Tool (2) 01-ERP-109 n/a 22,300 22,300 Copy Machine 01-ERP-110 nla 10,300 10.300 Thermal Imaging Camera (2) 01-ERP-112 n/a 11,500 11,500 Workout Equipment-Eliptical 01-ERP-116 n/a 5,800 5,800 Workout Equipment - SummitTrainer Of-ERP-117 n/a 5,800 5:800 Workout Equipment-Treadmill 01-ERP-118 n/a 5,000 5.000 Workout Equipment - Weightlifting 01-ERP-119 n/a 5,800 5,800 Automated External Defibrillator (2) 01-ERP-120 n/a 7,200 7,200 Workout Equipment -Dumb Bells 01-ERP-122 nla 5,000 5.000 Fire Total 64,517 320,517 65,717 61,417 108,617 620,785 • HRA 44 314 Ton Truck 01-ERP-400 n/a 32,400 32.400 Copier 01-ERP-401 n/a 13,000 13.000 Pate 1 71wrsdur. 11ur 27. 2010 Cite of Hopkins, NIN F_OL-IP.1fEAT RF_PL,ACF_.IfEAT PLAN 2011 tl n; 2015 DEPARTMENT SUMMARY Department 2011 2012 2013 2013 20151 Total Activity Center 15 000 15 000 Arts Center 12 100 3 300 15 400 City Hall Administration 38 000 35 000 38 000 3B 000 127 600 279 600 Community Services 29 500 16 500 36 500 16 500 18 500 117 500 Fire 64 517 320 517 65 717 61 417 108 617 620 755 HRA 13 000 32 400 45 400 Pavilion 185 000 185 000 Police 156 300 184 200 147 500 254 500 190 300 932 900 Pubic Works: Engineering 21 500 21 500 Pubic Works: Parks/Forestry 156 100 48 500 20 300 224 900 Pubic Works: StreetslTraffic 58 000 327 300 329 200 43 800 47 000 81,0600 Refuse 101 600 204 800 306 400 Sewer 35 700 35. 7 00 Water 134 300 14 200 149 000 TOT.%L 358,417 1,046,217 836,717 774,917 743,417 3,759,685 • • Department Project# Priority 2011 2012 2013 2014 2015 Total • HRA Total 13,000 32,400 44400 Pavilion Ice Resurfacer Of-ERP-1000 n/a 180,000 180,000 Electric Ice Edger 01-ERP-1001 nla 5,000 5,000 Pavilion Total 185,000 1 BA000 Police Marked Patrol Vehicles (6) 01-ERP-200 n/a 67,200 69,200 71,200 73,400 75,600 356,600 Sergeants Vehicle 01-ERP-201 nia 33,600 37,800 71,400 Utility 4x4(unit 212) 01-ERP-203 n/a 47,700 47,700 Police Administrative Vehicles (2) 01-ERP-204 n/a 27,900 28,800 29,600 30,500 31,400 148,200 Police Services Liaison Vehicle 01-ERP-206 n/a 22,000 22,000 Copy Machine 01-ERP-209 n1a 19,100 19,100 Logging Recorder 01-ERP-210 nia 36,900 36,900 Network Server (3) 01-ERP-211 n/a 8,500 8,500 8,500 8,500 8,500 42,500 Mobile Data Computers 01-ERP-212 n/a 62,700 62,700 Digital Squad Car Cameras 01-ERP-213 n/a 42,600 42,600 Tactical Ballistic Vests 01-ERP-214 nia 23,200 23,200 Radios - Portable and Mobile Devices 01-ERP-215 n/a 15,000 15,000 15,000 15,000 60,000 Police Total 156,300 184,200 147,500 254,600 190,300 93Z900 Public Works: Engineering • Engineering Van Of-ERP-700 n/a 21,500 21,500 Public Works: Engineering Total 21,500 21,500 Public Works: Parks/Forestry 112 Ton Pickup Truck 01-ERP-800 n/a 26,400 26.400 44 314Ton Trucks (2) 01-ERP-801 n/a 67,400 67,400 314 Ton Utility Trude Of-ERP-802 n/a 32,200 32.200 Trucksters (3) 01-ERP-807 n/a 19,800 19,800 Riding Mowers (3) 01-ERP-808 nia 10,300 22,800 20,300 53,400 Brush Chipper 01-ERP-813 n/a 25,700 25,700 Public Works: Parks/Forestry Total 156,100 48,500 20,300 224,900 Public Works: Streets/Traffic 44 3/4 Ton Pickup with Plow 01-ERP-300 n/a 33,600 33,600 4X4 3/4 Ton Truck with Plow 01-ERP-301 n/a 30,400 30,400 1 Ton Dump Truck (2) 01-ERP-303 nia 34,700 34,700 1 Ton Traffic Boom Truck 01-ERP-304 n/a 75,000 75.000 Tandem Dump Trucks (2) 01-ERP-306 n/a 22,000 142,400 164,400 Front End Loaders (2) 01-ERP-308 n/a 172,000 172,000 Skid Loader (2) 01-ERP-309 n/a 36,000 36,000 Sweeper 01-ERP-311 n/a 156,400 156,400 Roller 01-ERP-312 n/a 45,900 45.900 Asphalt Paver 01-ERP-314 n/a 48,800 48,800 Sign Machine (Traffic) 01-ERP-317 n/a 13,400 13,400 • Public Works: Streets/Traffic Total 58,000 327,600 329,200 48,800 47,000 810,600 Paae 2 7hursdar. 97u3 '7. 2010 Department Project Priority 2011 2012 2013 2014 2015 Total I Refuse • Refuse Truck (RAP -R) (2) 01-ERp900 n a 204 500 204 800 Refuse Truck (Rear -L) 01 -ERP -901 n 10 000 101600 Refuse Total Sewer 4x4 3l4 Ton Truck 01 -ERG -550 n a Sewer Total Water Backhoe Loader 01-ERo-502 n a Pubic Works Copy Machine 01 -ERP -506 n a Water Total GRAND TOTAL 101,600 204,800 306,400 35 700 35 700 35,700 35,700 134 900 14 200 134 800 14 200 134,800 14,200 149.000 358.417 1,046.217 836.717 774.917 743,417 3,759.685 � ' / .; � ' L �� L I, e, 1 1- f ,, 01 01 EQUIPMENT REPLACEMENT PLAN 2011 rhru 2015 • City of Hopkins, MN Project # 01 -ERP -030 Project Name Activity Center Copy Machine Future machine used by staff for daily operations of the Hopkins Activity Center. urrent equipment: Ricoh 2228C Copy flyers. letters, forms, informational items. etc. Department Activit} Center Contact Facilities Director "f) pe Equipment t'seful Life Unassigned Category Equipment Priority n/a Total Project Cost: $56,000 Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 15,000 15,000 41,000 Total 15,000 15,000 Total • Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 15,000 15,000 41,000 Total 15,000 15,000 Total Budget Impact/Other Variance from 20 year plan -'.done Estimate salvage/resale value on replaced item: $ is Paee 1 TIwrv&n,. Var'?. 20/0 EQUIPMENT REPLACEMENT PLAN 2011 o7ril 2015 City of Hopkins, MN Project# 01 -ERP -1100 Project Name Art Center Cop) Machine Future Dcpa1-1tile [it \IISleillel ( ollwo I aC11111e, I)n'r tur .% pe I yuglment I'Jul I ife ' Near. ! atc_,.I-N I yulpmCnt Priurih n a Description Inial Pn,icct ( u.t: ',53.8110 Cop} machine capable ofprinting in chlor a. ,\CII a, perl ,rming iIIC llmcti,m ,1 CnI;Ir_in 1uplC�in_. CnlLtin_. marlin_ COpiCS an 1%CII un scanning. faking and acting as a IIctn �„ k rriIIIcI- urrent equipment: Aficio A1035 Justification The Art Center staff does alargc%OIumC,dCur�in�prinun;li,rc\cmpnir,lin,.r'�CL�htinnin,lt1:ri.il..nu,ilia..11'\.•Il11I'Czularl,t'tiCC dliplicatioll of reports. signs. records. etc. A III ulti-IunCti,at.tl nct\xuri.cd k:opicr \�III a!1„'\% IIIc CCntcr to Cliniinalc .I priiitCr cop icr 11t\ machine acid a color printer. The printer/copier/fax machine \wikr , \cr\ .Io\\I\ .h .I nci�\(,rLC,I ut:.ClliuC acid the oilot rrilncl i, u.iu-" a lot of ICI'LlCcincnt. party dtic to its heavN work load. The multi-ILncti,mal n:t\\ork crpi,r ,\ ill aa%c the CcntCr icp.Iir dollar . \\ ill he ilial— CiliCicIII un in_ >tall tnnC. an i i, ir„rC appropriate for the level of usage ilmn urine Ill L1 rIC 111,1CIllllC>. Prior Expenditures 2011 2012 2013 2014 2015 Total F.,turc 8.500 Equipment 121-10 121033200 12,100 Total Total 12100 12,100 1 Prior Funding Sources 2011 2012 2013 2014 2015 Total t -111, 1 r 87500 AC - Arts Center Fund 12 1 DO 12 100F-7,32700 Total Total 12,100 12,100 from 20 year plan - salvage;rcsale value on replica! item Is {i,; i!'•„ ' ' ,I '-'h,it • • EQUIPMENT REPLACEMENT PLAN • City of Hopkins, MN 0 Project # 01 -ERP -1101 Project Name Art Center Carpet Extractor Future 2011 drru 2015 Department Arts Center Contact Facilities Director 7'} pe Equipment Useful Life 10 years Category Equipment Priority n,ra Total Project Cost: $7,700 carpet extractor is used at the Xns Center and occassionally in other city facilities. The equipment is used to clean carpets on a regular basis ,een annual contractual cleanings. to remove spots and stains. and to pick up spills. Justification The current equipment is over 12 years old and ver) corroded from the dirt, water and cleaning chemicals. With regular touch up cleaning and removal of stains in the Arts Center carpet with this extractor, the need to pa} contractual cleaners to deep clean the carpet is reduced to once or twice annually. Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 3,300 3,3004,400 Total 3,300 3,300 Total Funding Sources 2011 2012 2013 2014 2015 Total Future AC - Arts Center Fund 3,300 3,300 4,400 Total 3,300 3.300 Total from 20 year plan - New item. sal age'resale value on replace item: S • Pace 3 T hursdm% I lrn 27. 2010 EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN Project # 01 -ERP -003 Project \ame Network Sen'cr Future 2011 thrit 2015 Ucpttrhnent L its I lall N.lnIII ntr:ni,ut ( otiuct I nrtnCC I)u'Ccnor 11 network server is the hub of the ncr,wv6. \c\\ Crnrnhutcn arC 1a�tcr .ind 111017C rClial�IC. 11 pe I '1uq,ntcnt t �eful I ife I Near ( atcenr-) I .Iui}nrtent Prior'iI� it a 1 oral Pn jcci ( n.0 5225.111111 Justification Networking allows user to share injorntal4m that i.'lorcd in a in l Iocrttion- the nct\wrk ,,r cr. I hi, i, nt v,� Cllicicnt hcc,,u,c the inti01-nt;ttio does not have to be stored on mangy ditlircrnt C:ompmoi �. It alar makc� I„r hCttCr LICCUraC hCrau>C .t, the ill litnuuti,m ChLutL'Ca Or i, u[),iatcd. C\k r user is \+orking with the same data. Prior Expenditures 65.-0001 Equipment Total 2011 2012 2013 2014 2()15 8 000 80K 8 000 8 000 8 000 Total 8,000 8.000 8.000 8.000 8,000 *I Total 1',tt,rr 40 JDO 2 000 40,000 [ t) • Prior Funding Sources 2011 2012 2013 2014 2015 Total t :;:i' L r— _7757,00-01 Equipment Replacement Fund 8 CJD 8 011 811-00 8 DDC 8 000 40 DDO 2D 000 , Total Total 8,000 8.000 8,000 8.000 8.000 40,000 [ . from 20 year plan - nonc salvage/resale Value on I-C111aCCd itCm: S- I - *I • �J EQUIPMENT REPLACEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project # 01 -ERP -004 Project Name Telephone System Future Department City Hall Administration Contact IT Director T) pe Equipment Useful Life 8 years Category Equipment Priority n1a Total Project Cost: $239,200 Includes the PBX. the voice mail systems, and all telephone instruments. Currently there are over 200 extensions served by this system. Also includes software for the PBX and voice mail systems. Justification Making receiving and routing telephone call-, storing voice mail messages. and providing telephone based information services (snow line, etc.) Prior Expenditures 2011 2012 2013 2014 2015 Total Future 601000 Equipment 89,600 89,600 1 89,600 Total Total 89,600 89,600 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 7-6-0,-00-01 Equipment Replacement Fund 76,000 76,000 89,600 Total SF - Sanitary Sewer Fund 6,800 6,800 Total WF - Water Fund 6,800 6,800 Total 89,600 89,600 ariance from 20 year plan - Upgrade to controller in 2009 delays complete replacement to 2015. stimate salvagz'resale value on replaced item: S Pate 5 Thursday. 11r)• 2 7, 2010 EQUEPMENT REPLACEMENT PLAN 2011 rhrzr 2015 City of Hopkins, MN Project # 01 -ERP -006 Project Name Computers Future Wiml-1111cnt II\ 11811 \(11111I11,11xiJll ( ontact I inane I)IR' 1Vr I I 1 N pc I qulpment t .(ful I ife _ -� \eal, e atc_or) I yuipment Priurit\ n a ItioII I I utal Prnjcct (l .t: S9(IIL111111 computer purchases anJ uP_rade, liar the entire ('it\ ,Ltfl. e ,( r(iinc.Iill L her�011,11 0,111hutrr hLII-CI e, fimm ill Ji\ iJLKI1 dCJ1-Lu-tlnrnt, to (,ne I Justification Tools enabling staff to perform Johrc,hon,thll111c, e111cicill \ .111d cllccli\CI\. Prior Expenditures 2011 2012 2013 2014 2015 Total F,I'ttIt 300,000 Equipment 30 ODD 30 000 30 CJO 30 KO 3J 010 150 J00 F 450 0O0 Total Total 30.000 30.000 30.000 30.000 30,000 150,000 1 ,;,,I Prior Funding Sources 2011 2012 2013 2014 2015 Total F ,:; u l e 300.000 1 Equipment Replacement Fund 30 JJC 3J OOO 30 OJ0 30 000 30 0;0 150 000 450 000 Total Total 30.000 30.000 30,000 30.000 30,000 150,000 1,.t.,j Variance from 20 % ear plan - none Estimate sahage;resale %alue on replaced item: S -I I- • 0 EQUIPMENT REPLACEMENT PLAN IS City of Hopkins, MN Project # 01 -ERP -001 Project Name City Hall Main Copy Machine - Oce' Copier Future Copy machine to service needs of all departments located at City Hall. 1. Variety of copying tasks. 2. High volume product copier. equipment is leased. This copier may not make it to 2011. 2011 thru 2015 Department Community Services Contact City Clerk T% pe Equipment Useful Life 5 years Category Equipment Priority n/a "total Project Cost: $160,000 Justification Daily use to make copies of correspondence and forms. Periodically produce documents. i.e., budgets. financial reports. council reports and updates, city code revisions, various department reports, and hearing and information notices. Machine gill duplex. sort collate and staple copies. Prior Expenditures 2011 2012 2013 2014 2015 Total Future F-794—.20-01 Equipment 13,000 13,000 r 52,800 Total Toffi1 Total 13,000 13,000 Total • Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 94,200 Equipment Replacement Fund 13,000 13,000 52,800 Total Toffi1 13,000 13,000 Total Variance from 20 year plan -lease reneNved for 36 months. Plan to purchase new copier in 2011. Cost reduced by $1.000 due to pricing Estimate salvage/resale value on replaced item: 5-0- • Pa2e 7 7hur5ckm 1/cn-?7. 1010 EQUIPMENT REPLACEMENT PLAN 2011 liwa 2015 City of Hopkins, MN Project # 01 -ERP -002 Project Name City Hall Small CoPy Machine Future Coy} machine to service needs of all JCp,uunCnt> locCitCJ at c it\ 11,111. 1. Variety of copying tasks. 2. High volume product copier. This is a Ricoh color copier. Dcluu-1tile III L mununm I'11,:., ( ontact �_ its t_ Irrl, .\ pc I .IHipmCnl l ,cful I ifc �car> < atccur� I iuipmrnt Pri,rrih it a Iola[ Project ( u,t: \144.500 Current equipment: 2006 Ricoh Justification Dail) use to make copies of corresponJCnCC .tnd fin'm,. 1'C1_iOdiiulk pnOJuCC J,u'unICnt,. i.0 . huJ t.. lin ,nri.,l r h rt,. COUIlCil lvp ,rte ,111d updates. city code revisions, variou, JCp.u'unrnt l port,. and hC•u'i[I_- .u]d irtt0unt.,ti,m n„Iice,_ \IarhinC ill JupIC\. ,rnt. C,)IIatC .,nJ ,tuplC C,y'iC,. Prior Expenditures 2011 2012 2013 2014 2()15 Total Fulutc 43,200 Equipment _ _ _ 2r' w0 20 00081 300 Total Total 20.000 20,000 Prior Funding Sources 2011 2012 2013 2014 2-()15 Total F,tHrC 43,200 Equipment Replacement Fund 20 _00 20 D03 1 300 Total Total 20,000 20.000 Budget Impact/Other Variance from 20 year plan - Cost rcJucCJ ti(,. Inll Jue t11 Jul IC 1111-' rCJuiti,vt,. \]r C huCl. to 1n 1 Estimate salvage/resale value on rCpl,iccd itrrrt: ti'. tal • is 0 • • EQUIPMENT REPLACEMENT PLAN 2011 flint, 2015 City of Hopkins, MN Project# 01 -ERP -007 Project Name Engineering Printer/Scanner Future Department Community Services Contact Citi Clerk 'f3 pe Equipment Useful Life 5 years Category Equipment Priority n/a Total Project Cost: $312,560 rinter/scanner - large format copier use in Engineering to copy blueprints. plans and large documents. is leased. Justification JLarge document copier/scanner for use in Engineering. Also scans documents f'or permanent storage. Prior Expenditures 2011 2012 2013 2014 2015 Total Future 44,560 Equipment 10,000 10,000 10,000 10,D00 12,000 52,000 216,000 Total Total Total 10,000 10,000 10,000 10,000 12,000 52,000 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 44,560 Equipment Replacement Fund 10,000 10,000 10,000 10,000 12,000 52,000216,000 Total Total 10,000 10,000 10,000 10,000 12,000 52,000 Total Variance from 20 year plan - None Estimate salvage/resale value on replaced item: $-0- Pa2e 9 7hursiko-. lkn• '7. 2010 EQUIPMENT REPLACEMENT PLAN 2011 ihr,r 2015 City of Hopkins, MN Project # 01 -ERP -008 Project Name Document Management Scanner (3) Future Uchart0lcnI I,JIiiIiItill iI\ 1,elliee, (uutaci k- m (- Irrh .% fu• I µupmrnt t ,rful I ifc +car, ( at Cu,(ri") I gtnPIII Cl Il PI-iurih n a rtptton I IUtaI I'n,ictt ( u,i: S149.5OfI document( 11**x17") scanner I 0 JOCumCrtt Ill an,t_Cmcnt 'lnd reICI ntioII a, ++ell a, ecncral admiIIi,trati+e u,e. Three scanners each replaced eN cI\ three \,:ar. One replaced in 2009. 2012. 2015...... Here ++e did not replace rnC in 2(IU9: unit ++.: ICpaireJ to the ]I1 ' One replaced in 2010. 2013.2016...... . One replaced in 2011. 2014. 2017.. One additional small scanner \Nati adJcd to the ,Carnnin_ ,tation in _'O(J9. I hi, ,CXIIIer I)re+i++u,l\ ++a, Ll end h\ the In,pCction, ,CCI.ctar\. I hi, scanner does not handle 1 I" x I - paper ,o C,:n not do Al docuutcnt,. will he evaluated each \ear 1�,r icplaecmcnt. II ,canners :uc ++orkin= prn} Crl their lily %+ ill he :\Icn,k•d. We have been getting up to three I icc I ru,t +ulurttCCr, to ++oi k on ,C:uutin_ ind the ,mall ,Canner (1111+ h,uldle, doeunlent, up t.. S 1•• \1 e would like to replace this scanner ++ith a larcC dOCument ,canner to Il ll+ utiliic our +olun;eer>. I Prior Expenditures 2011 2012 2013 2014 2015 Total 19,500 Equipment 5 503 5 503 5 500 5 5HD 5 5)0 32 5,3 97 500 Total Total 6,500 6.500 6.500 6.500 6,500 32,500 I ,, if Prior Funding Sources 2011 2012 2013 2014 2015 Total I ., e F -7-9.5-D-0-1 Equipment Replacement Fund 5 530 5 530 0 500 3 50'10 5 530 32 500 F-----777500 Total Total 6.500 6.500 6,500 6.500 6.500 32,500 I..,.;i Budget ImpwVOther Variance fmin 20 \ear plan - item >Che 1u ICJ liar 2f)()Ll ++ ;, lot I Cplaecdi t nit ++a, ICpuiI.Cd to C\tenL1 its life I Inc a t-liti+,n,tl ,canner ++,is Aid Cd to the replacement shed ule in 2010. Estimate salvage. resale value on replaced iteut: `+ un-; l lou r �i EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN • 2011 thru 2015 Department Community Services Contact City Clerk Pace I1 lhursdm% 11m• 2. 2010 EQUIPMENT REPLACEMENT PLAN 2011 !hru 2015 City of Hopkins, MN Project is 01 -ERP -103 Project\ame Duty Chief Vehicle (1) Asst. Chief's Vehicles (2) Future Department I ire (untact I ire l h irf I \ pc I luil,ment t .ernl 1 ifc I � ,rat, ( atc2nn \ rhiclr Priuril\ n a Description I I utal Prnicct ( u.0 IQ54.200 A marked passenger vehicle for a>c h\ the llut\ ( hicl' anJ .\llisunt l hicl> in ur.ut,I,orun_ required cyuil,tnent_ rclemnec tnatrri.tl> .uIJ I,cr onncl .or emergency response. and routine I irc Wpurtntcm vehicles: 2010 Chevrolet I .thor 10)icf) 2006 Dodge DuraIIILO i.\>a. C hien) Chevrolet Impala t.\ >t. ( hicf) to be rchluceJ ith -,u 1 4� til \ Justification Used by the Fire Chief and Asst. Chicl*, \\hen rc,pondin_ to lirc�, anJ nthcr emcr encic.. l >ed I-tr ollicial hu�inc.. in ;utJ nut of the cit\ .tnJ lite fire fighter travel on official Fire Ucl,.uvnent hW inc,.. Eventually 3 SUV's -replaced c\ en � ate %\ ill) I � \c,tr dile. \r\\ - chic'. c\rlc do"n to \.,t. ( hict' 1 Prior Expenditures 64,500 Vehicles Total 2011 2012 2013 2014 2015 37 '3K Total 37.000 Total I ,L 37 )yU = 37,000 i , ! • Prior Funding Sources 2011 2012 2013 2014 2015 Total 1 , 64,500 Equipment Replacement Fund 37 p� 37 7J� 52 700 Total Total 37.000 37.000 1 I ariance from 20 year plan- Add 2 �chicic..utd ch.utec lil'c to I ,timate salvage/resale value on rcplaced item: ti Imus l is EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN 0 • 2011 thru 2015 Department Fire Contact Fire Chief Nee 13 7'hursc&rr. Ahn, 2. 2070 EQUIPMENT REPLACEMENT PLAN 2011 ihr,r 2015 City of Hopkins, MN Project # 01 -ERP -105 Project Name Quick Attack Pumper/Rescue (Rescue 8) Future ick attack pumper/rescue. Departlnenl I Ire ( 11111:11'1 I I(L' � Illcl 1 N pc I Iulpment l .crul 1 if � \ear> ( atc,on \ chicle, Priurih n :� otA Project ( mt: S598.600 Justification Would replace Rescue 8 (lite re-sc'uc) ;md u,c .1, ,1 utility \ chicle. 1 hi, truck cotlI'l he u,c d lur 1,1\ time and Ilishtti!nc Itle(IIC:11, ❑nLl 1111.111 lire, This x% ill reduce having all personnel re,'Foll l t ,m,111 lire>. It '\ ill ul„O Ict u�, 11101) cmc cncinc in ,I I'2 but �!i11 Lecp I -t I r,uimL. Expenditures 2011 Equipment 2012 2013 234 030 2014 2015 Total 234 000 Futnrr F 364 300 Total 234.000 234,000 1 , . ; ,1 Funding Sources 2011 2012 2013 2014 2015 Tota l I :; ry l c Equipment Replacement Fund 234 030 234 300 F-7-64-7070 Total 234 000 234,000 1 ,1 _ ,1 Budget Impact/Mer Variance from 20 Near plan - Ne%% itch. Estimate salvage./resale value on rc1iLlccd item 0 0 • LJ • EQUIPMENT REPLACEMENT PLAN '2011 awu 2015 City of Hopkins, MN Project # 01 -ERP -106 Project Name Aerial Truck Future Department Fire Contact Fire Chief f� pe Equipment Useful Life 20 years Category Vehicles Priori" n.�a Description I Total Project Cost: $2,559-597 ane hundred foot aerial ladder truck with a 1500 GPM fire pump and a full compliment of ground ladders. Lease payments due 2009-2018 on 2008 purchase of Pierce Aerial Truck. Payments due semi-annually each April 23 and October 23. 'urrent vehicle: 2008 Pierce Arrow XT Aerial [.adder Justification -, Jehicle was purchased in 2008 at a total cost of $870.427.08 including mounted equipment. Vehicle was paid using $445.427.08 in ERP cash and i 10 -year capital lease ol'$425.000. At the end ofthe lease term payments (P&1) will total $542.170. Total costs of aerial including cash )ayments equals $987.597. Prior Expenditures 2011 2012 2013 2014 2015 Total Future 553,861 Equipment 54,217 54,217 54,217 54,217 54,217 271,085 11,734,651 Total Total 54,217 54,217 54,217 54,217 54,217 271,085 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 553,861 Bonds/Lease 54,217 54,217 54,217 54,217 54,217 271,085 1,734,651 Total Total 54,217 54,217 54,217 54,217 54,217 271,085 Total Variance from 20 year plan - .Lease payments on financing added to the plan. Estimate salvage/resale value on replaced item: $ Paee 15 7huis&n•. ifm- 27. 2010 EQUIPMENT REPLACEMENT PLAN 2011 16 -it 2015 City of Hopkins, MN Project # 01 -ERP -109 Project Name Extrication Tool (2) Future Description I HNdraulic rescue and extrication tokol %%ith hr: ad r. cuttcr> and h\ draultc ram Dc partIII ctu I ire ( ontact I ire C hirf I ) pe I iIL111111101t l �cful I ifc I n �car'� ( atc�'un I yuipment Priuril� n :1 total 1'n jcct ( n.t: S136,900 Justification 411 vehicle and industrial rescue �ituatit'll , \01 CII MIM rcyuirc I)aticnt di�Cm,rn�-lcnit: nt ot- n(r,,hmc II I hi' t0k)I \l iI he Aldo2d to the I)urCh:r.r to II] quick attack pumper. The tool „ill he c,ticd J(M n for a >m,tllcr t(101. hL).>ihk rVduCin1- t:(`o.t. Prior Expenditures 20,300 Equipment Total 2011 2012 2013 2014 2015 Total I ci!lc 22 300 22 3-0F----74-7377 Total 22.300 22.300 1: Prior Funding Sources 20111 2012 2013 2014 2015 Total I !1;11j I C 20,300 Equipment Replacement Fund 22 30)22 300 G4 300 Total Total 22.300 22,300 I ;.,I Budget Impact/Other Variance from 20 year plan - mo x e hac 1. I n m 2 t t I � to -11) 11). Estimate salvage;resale value on rcillaccd itcnr ti 1.000 Purchased: 2007 C 0 • 0 • EQUIPMENT REPLACEMENT PLAN 2011 11tru 2015 City of Hopkins, MN Project # 01 -ERP -110 Project Name Copy Machine Future Department Fire Contact Fire Chief 7') pe Equipment Useful Life 8 years Category Equipment Priority n/a Prior Expenditures 2011 2012 2013 2014 2015 Total Future 7-7-40-01 Equipment 10,300 10,300 29,700 Total Total 10,300 10,300 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 7-7-40-01 Equipment Replacement Fund 10,300 10,300F-72-97700 Total Total 10,300 10,300 Total Budget Impact/Other Variance from 20 Near plan - none Estimate salvage/resale value on replaced item: $500 Paae 17 Thursday. ttcn• _'7. 2010 EQUIPMENT REPLACEMENT PLAN 2011 11u„ 2015 City of Hopkins, MN Project # 01 -ERP -112 Project lame Thermal Imaginc, Camera (2) Future Dcparoncnt I irc' ( unlacl I nye ( h1ct I N pe I .µuhnlent L still I He I cal" :Ite201-` I Ill P11h:111 Priurit� n a Description I I ural Prnjcct (u.t: S-2.200 Used by our fire companies to locat: N ictinu truPPrd in ,t anu r 1111rJ huilJin=. It hclPS u. da:rrnin: %herr l r: ,mJ brat nlu h: hidJrn J] 1 in_ for faster extinguishment. purchased 2005 & 2007 Justification Current camera is ten years old anJ Ila, hcrn thnw-h nl.lm brit III -r1 and nerd. til IN: rcPlaced. C urrcnt r.uncra �\a. Purrh:l,rd N1 ill) d011,1t1iN1 Prior Expenditures 15 000 Equipment Total 2011 2012 2013 2014 2015 Total 1- „tv 11 500 11 KO45 700 Total 11,500 11.500 i 1l Prior Funding Sources 2011 2012 2013 2014 2015 Total t .• 15,000 Equipment Replacement Fund 11 50011 50 45 700 Total Total 11.500 11.500 j .I Variance from 20 year plan - deparunrnt O\'o u, 2 :,ullrr,l�. PIC%iOLI,I% rul: elle V,.1. inclt:dcd in the rchl.lrrm:nl Pl,m. I hi, a ill add to the replacement schedule the camera Purch.l�,rd lhlnl thr 111-r OCI)t hudL11-t in 'uu; Estimate salvaee resale value on rtP.11red it:nt: S-n- • • • • EQUIPMENT REPLACEMENT PLAN 2011 ihru 2015 City of Hopkins, MN Project # 01 -ERP -116 Project Name Workout Equipment - Eliptieal Future Department Fire Contact Fire Chief T,. pe Equipment Useful Life 6 vears Category Equipment Priority n/a Total Project Cost•. 520,300 Workout equipment used in Fire Department workout room. One eliptical machine replaced on a 6 year cycle, one every 3 pears. Justification This equipment is available to all City employees for health and wellness. Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 5,800 5,800F-71-45700 Total 5,800 5,800 Total Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 5,800 5,800 r 14,500 Total 5,800 5,800 Total Budget Impact/Other Variance from 20 year plan - had rico eliptical machines in the ERP. One was replaced along with the stairmaster with a summit trainer. The remaining eliptical is scheduled for replacement in 2015. Estimate salvage/resale value on replaced item: S Paae 19 7hursdcn% llrn• 2 7 '010 EQUIPMENT REPLACEMENT PLAN 2011 ,lx,r 2015 City of Hopkins, MN Project # 01 -ERP -117 Project \ame Workout Equipment - Summit Trainer Future orkout equipment used in Fire l)ci aruncnt %\ 01,k0ul 1.00111. ie summit trainer replaced on a c.Ir c\ c I c lCurrent equipment: 2010 Suniwit I raiim- Justification This equipment is available to all C il% clnhl cc. 1,01- hcalth an l l cllnc.,. Prior Expenditures 5,000 Equipment Total Total Ucpartntcnl I Irr (unt:u•t I Ire C hlc� � pc I �µullmcnt t .cful I ife ` lcaf ( atC'--0f-.N I i;UIP111 11 PriurilN n a I,rlal I'rnjcct (u.c \34.3110 2011 2012 2013 2014 2015 5 8K 5.800 Total 1 . .:I I k. 5 80 23 500 5.800 Prior Funding Sources 2011 2012 2013 2014 2()15 Total t :; 1 11 7000 Equipment Replacement Fund 5 8,0 5 305 F 23 500 Total Total 5.800 5,800 Variance from 20 Near plan - replace, tLiirn,.utcl. Estimate sal age,'resale value on rcplac, d ii, m: ti • �J EQUIPMENT REPLACEMENT PLAN • City of Hopkins, MN Project # 01 -ERP -118 Project Name Workout Equipment -Treadmill Future Description Workout equipment used in the Fire Department workout room. .)ne treadmill replaced on a 5 year cycle. Justification (This equipment is available to all City employees for health and wellness. 2011 thru 2015 Department Fire Contact Fire Chief T� pe Equipment Useful Life 5 gears Category Equipment Priorit-, n/a Total Project Cost: $25,300 Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 5,000 5,000 20,300 Total 5,000 5,000 Total • Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 5,000 5-000r--20-3700 Total 5,000 5,000 Total Variance from 20 year plan - move hack one year from 2011 to 2012. Estimate salvage/resale value on replaced item: $ • Nee 21 7hursJcrr, tho-27._'DID EQUIPMENT REPLACEMENT PLAN 2011 iirf,r 2015 City of Hopkins, MN Project # 01 -ERP -119 Project Name workout Equipment - Weight Lifting Future Smith machine - %+eight lifting machine. DcparinuCIII IlTL: ( nntact I n'e ( hlct I \ pr I �I 11111111 :Ill I crul Life %car, ( :Itf'('1') I yu111111cnt PriuriI n a ural I'rnlcct ( In(: 129.31111 Justification For use b) Police. Fire. Public \\ urh,. (it% .t:d to heel) in ,h,ll)c t1I h,rlwnl jl�h duties Auld ,1,1\ health ('111-rcnt ntichinc \\ ill he - \c.tr� I'ILI in 2012. Suggested replacement is c1 cry 5 C,11*,. Expenditures 2011 2012 2013 2014 2015 Total I „i u l r Equipment 5 8D0 5 85C23 500 Total 5.800 5.800 1 E Funding Sources 2011 2012 2013 2014 2015 Total I :u u t c Equipment Replacement Fund 5 DO 5 300 7723 500 Total 5.800 5,800 Variance from 20 .'earplan - mol c hag h fn+1n -'u I 1 it, 20 I Estimate salvage'resalevalue onrcplaccditcni.: S • • EQUIPMENT REPLACEMENT PLAN 2011 ihru 2015 City of Hopkins, MN Project # 01 -ERP -120 Project Name Automated External Defibrillator (2) Future rillator is used to help get someones heart restarted during a cardiac arrest. 2 - both are replaced at one time due to changing technology. nt equipment: 2010 - 4 AEDs ERP had 2 AEDs schedule for replacement at Justification With changes in technology, the AED's should be replaced every four years. Cost - $3.000 per unit Department Fire Contact Fire Chief T) pe Equipment Useful Life 3 years CategorN Equipment Priority n/a Total Project Cost: $49,100 Prior Expenditures 2011 2012 2013 2014 2015 Total Future 6300 Equipment 7,200 7,200 35,900 • Total Total 7,200 7,200 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 6,000 Equipment Replacement Fund 7,200 7,200 1 35,900 Total Total 7,200 7,200 Total Budget Impact/Other Variance from 20 year plan - adjustment from 3 years to 4 years. Estimate salvage; resale value on replaced item: $ C] Paw 23 Aurs&n% 116w 2. 2010 EQUIPMENTMN PLAN 2011 dint 2015 Di-partttt��itt i r� City ofPHopkins,kins, (4-mact I irc C hirf • 0 I / i • • 0 EQUIPMENT REPLACEMENT PLAN 2011 rhru 2015 City of Hopkins, MN Project # 01 -ERP -122 Project lame Workout Equipment - Dumb Bells Future Workout equipment used in Fire Department workout room. Department Fire Contact Fire Chief Ti pe Equipment Useful Life 10 vears Category Equipment Priority n/a Total Project Cost: $11,700 Justification Current dumb bells are 15 plus years old. The current dumb bells are older and some of the weight- contained lead based plaint This purchase would update our dumb bells to the current type fitness bells. Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 5,000 5,000 6,700 Total 5,000 5,000 Total Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 5,000 5,000 6,700 Total 5,000 5,000 Total Budget Impact/Other Variance from 20 year plan - stimate salvage/resale value on replaced item: $ Paye 25 7hurs&n'. t1rn'27.2010 EQUIPMENT REPLACEMENT PLAN 2011 viii -it 2015 City of Hopkins, MN Project # 01-ERP400 Projeel \ame 4x4 3/4 Ton Truck Dc11ar-tmcm IIK t,Otd I ife Sear, ( atc�on � 1hi11r, Future Pr-iorit, 0 a tion I ntal I'roicct ( o,C *96.300 N% heel drive 3/4 ton truck to he u.CJ h\ PUNK I I0u>in' m.tiutrnanrr ,t,,tl. InCILIJC, III O\\ III,i,X. -urrent vehicle: 2007 Chevrolet PiCl.uh Justification Housing ';uhcrint ndCIII ,111,1 1110„ I'li"\ in' ,,t ,,u l0LII I IR.k hr,hvrti , .m,un�i the Cit\ Prior Expenditures 22.800 Vehicles Total Total 2011 2012 2013 2014 2015 32 4D' 32.400 Total I 32 400 h 41 100 32,400 • Prior Funding Sources 2011 2012 2013 2011 2015 Total I , 22,800 HRA -Housing and Redevelop 32 406 32 400 F 41 100 Total Total 32.400 32,400 , Budget Impact/Other Variance from 20 year plan - none estimate sal age.'resale value on rchlaccd item til.sw • • EQUIPMENT REPLACEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project# 01 -ERP -401 Project Name Copier Future Department HRA Contact Finance Director T% pe Equipment Useful Life 8 years Category Equipment Priority n/a Total Project Cost: $50,400 copy machine to service the needs of the HRA. High volume product copier to do a variety of copying tasks. equipment: Imagistics Z1335 Justification Dail) use to make copies of correspondence. forms and rental documents. Periodically produce documents such as resident newsletters and marketing. Machine will duple\. sort. collate and staple copies. Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 13,000 13,000 37,400 Total 13,000 13,000 Total Funding Sources 2011 2012 2013 2014 2015 Total Future HRA - Housing and Redevelop 13,000 13,000r--37-4700 Total 13,000 13,000 Total Variance from 20 year plan -':dew item. Estimate salvage/resale value on replace item: $ - 0 - l'aee 27 Aursdin% May 2%. 2010 EQUIPMENT REPLACEMENT PLAN 2011 ruin 2015 City of Hopkins, MN Project #01 -ERP -1000 Project Name Ice Resurfacer Future resurfacer used b} the Pay ilion lur ire heel n1,,inten,uirr. 2003 Ohninia Ire Ite,urlaccr I)cpilrlfilet) I I' IN I11, 11 ( h111a1•1 DITe,:l Ul \ Ill' iILI lt,111C111 I, cful I ifc 12 \ear, ( alc_or% I yuirlllelll Priurir\ if a olal Project ( o.0 S,496.600 Justification Replace existing propane fueled iCe rc url',,crr \\ith ❑ elect is dri\en ice rc>tlrlarcr Uuc to chan_cl in the .tate. lt,Iluc�, I'1r indoor ,lir LIu,Ilit\ lilr ice arenas replacement with apropane iIIrIC\I r11\1\irl \\1111.1 \\,urunl thr l,urrh,.c ,111d init,IIkIti011 II-"Litc :g1l'1-O\e11 .lir yu,tliu mllnit\1rin12 cyuil,menl. Additional costs that would accompam the 11101litlrin_ ryui}1Inent ,\111111 he :JIIILI,l tc tine :uld rrr:Ilihr,uion ICC, �t,,tc It,,ttic' ,11..1 rcyuirc annual licensing and lover emission ,tandiidl I" hr HIC11 th,1l II r\1rC\Irll rl'ulll 11, > Ihl\ IC,ld 11 I,\I�IINC IaCllll\ CI\ tlrC> :hili 11", UI IC\ Clltlr. \\ Ith consideration of the above factors the I'a\ ili011 \\1uILI he c\emllt 1-1-1111 the IIC\\ ,t,nuc. if:l electric ice rr.urf:Ircr \\u, ulcd in I,lacc 1f i,rol,cnc icc resurfacer. Prior Expenditures 2011 2012 2013 2014 201-5 Total FtlIt! 'e 60,000 Equipment --- --- - — -- -- - --- 130 G0 180 0D0_ 250 500 Total Total 180.000 180,000 Prior Funding Sources 60,000 PA - Pavilion Fund Total Total 2011 2012 2013 2014 2015 Variance from 20 year plan - Value inrrr,ur\I to rCIlcrt arulal rcllluccrllrnt cOlt Estimate sal%age/resale value on replaced item: 520.000 130 DGO 180.000 Total I It tI rC 180 000 F 256 600 180,000 C, • 0 • • • EQUIPMENT REPLACEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project # 01 -ERP -1001 Project Name Electric Ice Edger Future Department Pavilion Contact Facilities Director T) pe Equipment Useful Life 10 years Category Equipment Priority n/a 'rota) Project Cost: $11,700 Electric ice edger used for ice maintenance of the Pavilion's ice sheet. An edger is used to shave the ice next to the boards to remove ice buildup that the ice resurface cannot reach. Justification For the Pavilion to he exempt from the changing stale statutes for air quality in ice arenas. the gas fueled edger must he replaced with an electric model. Expenditures 2011 2012 2013 2014 2015 Total Future Equipment 5,000 5,000r---6,7700 Total 5,000 5,000 Total Funding Sources 2011 2012 2013 2014 2015 Total Future PA - Pavilion Fund 5,000 5,000 6,700 Total 5,000 5,000 Total Vairanee from 20 year plan - New item. Estimate salvage/resale value on replaced item: S Paee 29 7hursdzn•. ilm- 17. '010 EQUIPMENT REPLACEMENT PLAN 2011 ih, r, 2015 City of Hopkins, MN Project # 01 -ERP -200 Project Name Marked Patrol Vehicles (6) Future Dc11artill •lit 11, )h, ( untact P,,h,:V l h,cl, .% pc I .lUipment t , ful I He 3 Ncar, ( atceur� \ chicle, I'riurih n a I ural Prnicct (,,.t: 52.3-4.300 patrol vehicles used bN hau„I „li;ccn:, to rc>hrnd to calIs. :it ,r.e trallic la," .Lit pert -01-111 eell,:n t Patna dutic,. consists of 6 patrol vehicle, - � marked. 1 unnnanccd. vehicles: (2) 20 10 Ford (7,mit \ ictonas. 1 I I ,009 I,grd ( rk,"\rn \ icturia. ( 21 _1oi)S I Ord ( r„\xn \ irtona,. t I 1 -'Iii), l ord ( r,mn \ ic:Ioria Justification Set up and marking of police \ ell icic, nota conihrm toy \Iinl—ota la%\ .,nd P( t` 1 ,t,, td.u.1, \ chicle, .•(ant,,in ,ccurc d;u.n .utd radio cquihment for routine and emergeneyoperation,. \ chide, COIIt,,ill ,ecurc ,e.ttiII f,r I)ri.nner u.un,h„rt. Equipment Replacement Fund 67 2J0 69 KJ 71 200 73 4G0 75 KC 356 601 1 4717 230 Total Prior Expenditures 2011 2012 2013 2014 2015 Total F,tt,tr� 570,500 Vehicles 37 2J0 65 20J i1 200 7`s 400 75 030 355 333 1447200 Total Total 67,200 69.200 71,200 73.400 75.600 356,600 Prior Funding Sources 2011 2012 2013 2014 2015 Total 4,,tttr, 570,500 Equipment Replacement Fund 67 2J0 69 KJ 71 200 73 4G0 75 KC 356 601 1 4717 230 Total Total 67.200 69.200 71.200 73.400 75.600 356.600 Budget Impact/C ther Variance from 20 Near plan - Original rchl.,cement ,rhedulr .,• m„dilirJ ,c cral car, ,, , durin_ the L(, \ rut,. Ill,: hn,ha.cd l)w-ct,a,c >chcdulc is to realign the replacement of x{und. m„r e c\ cnh . Estimate sal age resale value on replaced itcun: tilt n11 each • • L_J • EQUIPMENT REPLACEMENT PLAN 2011 thrtr 2015 City of Hopkins, MN Project # 01 -ERP -201 Project Mine Sergeant's Vehicle Future Department Police Contact Police Chief T` pe Equipment useful Life 4 years Categor} Vehicles Prioritv n/a Total Project Cost: $215,700 Marked patrol vehicle used by patrol officers to respond to calls, enforce traffic laws and perform general patrol duties. 4 year rotation. vehicle: 2007 Ford Crown Victoria Justification Set up and marking of police vehicles must conform to Minnesota lav and POS f standards. Vehicles contain secure data and radio equipment routine and emergency operations. Vehicles contain secure seating for prisoner transport. Expenditures 2011 2012 2013 2014 2015 Total Future Vehicles 33,600 37,800 71,400 144,300 Total 33,600 37,800 71,400 Total Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 33,600 37,800 71,400 144,300 Total 33,600 37,800 71,400 Total Budget Impact/Other Variance from 20 Near plan - move purchase of sergeant's squad back to 2011. Purchased new in 2007. ?stimate salvage/resale value on replaced item: $3.500 each Nee 31 7hursde,n% tfin• 7 '010 EQUIPMENT REPLACEMENT PLAN 2011 that 2015 City of Hopkins, MN Project a 01 -ERP -203 Project Name Utility 4x4 (unit 212 ) Future wheel drive uitlity vehicle. vehicle: 2008 Chevrolet I .thoc I)c1)artmcnt I'nli�:c ( ('ntact Rohcc C hrcf- I N pc I .{uiprneni l �cful 1 ifs 6 %car, < ate,—,or) \'chicle, 47 700 47 700 32500 Wal Pr icct ( n.0 S24".600 Vehicle is normally used by public ,:r icy ulliccr> ti,r a 'A I& \ :riun nl u,e, ,u h ;t, u,ut,}1ortin-' anintah :111d uL}ui} mCnt. I hC 1 \X6,:,:1 Liri\u vehicle is also used at times as a }itrirol N chicle. particul,trl\ in 111 � inlcr in c\tt-emc ,nrn\ c,nJitiwl,. Prior Expenditures 67,400 Vehicles Total 2011 2012 2013 2014 2013 Total 1 - - 47 700 47 700 ` '32 500 Total 47.700 47,700 i 1 Prior Funding Sources 2(11 1 2012 2013 2014 2013 Total I , 67,400 Equipment Replacement Fund 47 700 47 700 32500 Total Total 47,700 47,700 Variance from 20 }ear plan - can num,:rc} Ltc:mcnt puck on: , .u- to 2n(11) - nc\\ :I)Lillc, Estimate sal ageiresale value on rcpluccd item: Y;.ntrn • • 0 EQUIPMENT REPLACEMENT PLAN - City of Hopkins, MN Project # 01 -ERP -204 Project Name Police Administrative Vehicles (2) Future administrative and detective vehicles. Replace Chiefs vehicle - even numbered years Replace Captain's vehicle - odd numbered years 2011 r1tru 2015 Department Police Contact Police Chief T) pe Equipment Useful Life 2 years Category Vehicles Priority n/a Totai Project Cost: $962,900 Current vehicles: 2009 Chevrolet Impala. 2008 Ford "Taurus I Justification Unmarked vehicles. equipped with radios. siren and red grille lites used by chief and captain. Staff use is for two years. Vehicles are then mtated down to detectives and are kept for an additional 3-4 years. Vehicles are also used for surveillance by uniform and plain clothes officers. Prior Expenditures 2011 2012 2013 2014 2015 Total Future F-2-12,4001 Vehicles 27,900 28,800 29,600 30,500 31,400 148,200r-7-027700 Total Total 27,900 28,800 29,600 30,500 31,400 148,200 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 212,400 Equipment Replacement Fund 27,900 28,800 29,600 30,500 31,400 148,200 602,300 Total Total 27,900 28,800 29,600 30,500 31,400 148,200 Total ariance from 20 year plan - none stimate salvage'resale value on replaced item: $4.000 each Page 33 Thursdcm iknr 27. 2010 EQUIPMENT REPLACEMENT PLAN 2011 Thr t 2015 I,trr,rtr„tr,t P„I, r City of Hopkins, 1Vi1V Project # 01 -ERP -206 N pe I yuq mcnt l �cful I ifc I � scar, Project Name Police Services Liaison Vehicle ( ;,tceun � rhi�le, Future I'riurih 1 Description I Wal Pr­icct ( (,,t: S56.300 t vehicle was leased to Pulicc Dcharuncrtt. I ,cd h_\ Police `cry ice, I iai,nn I'k�r a un,h,ut to ,chop ,, nciL�hhurhoo i mectin trainin_ ,tnJ relations events. ` lCurrent vehicle: 2001 Chrxsler I' I ( rui,cr Justification 2001 PT Cruiser %%as leased to the Y, lice Uch,uuncnt lin ,t nt ntin;tl lcc ;ut i lctailinu ,,n 1 a hrrl, ter; ;rl,u ir,nutc i. I he C its I)urrh.t,cd the vehicle from the leasor in 2(N)5. Expenditures 2011 2012 2013 2014 2015 Total F tt! u rc Vehicles 22 Y _ 22 000 34 300 Total 22,000 22,000 Funding Sources '_(III 2012 2013 2014 201; Total F:,IoI-L Equipment Replacement Fund 22 KO 22 01034 300 Total 22.000 22.000 1.,t.,I Variance from 20 year plan - extcnJ,:J life I.r m 1 n to I c,u, Estimate salvage/resale value on rcl)I,,ccJ item. S 1.0( 10 7 EQUIPMENT REPLACEMENT PLAN . City of Hopkins, MN Project # 01 -ERP -209 Project Name Copy Machine Future 2011 rhru 2015 Department copy machine capable of producing double side copies and collating pages. Current equipment: 2006 Ricoh 2051 SP Justification It'sed to make duplicate copies of reports, letters, memos, etc., generated b) police personnel. Department Police Contact Police Chief T� pe Equipment Useful Life 5 years Categon Equipment Priorit- nia "total Project Cost: $127,200 Prior Expenditures 2011 2012 2013 2014 2015 Total Future 770-70-01 Equipment 19,100 19,100r---77—,4700 Total Total 19,100 19,100 Total • Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 30,700 Equipment Replacement Fund 19,10019,100 77,400 Total Total 19,100 19,100 Total Variance from 20 year plan - none Estimate salvage/resale value on replaced item: $1,000 • 1132e 3 5 7hursdar. I lm- ". 2010 EQUIPMENT REPLACEMENT PLAN 2011 1hrij 2015 Dch;trtrncnt P,rlt,� City of Hopkins, MN (ontact loh':c C l„Cf Project # 01 -ERP -210 1) lie I `lu'l"""'l � Project Name Logging Recorder t cful I ifc ' Nrar, ( atc_nn I IuiPmcnt Future Prurriit n a Description I Mal Pr, iecl ( ,,.t: .13x.100 The police logging recorder is a dc\ iCC \\ hich record, .ill t,]cphonC ;utd r.tdio tr.:n,mt .itm, l,roduCCd I-CCCi\ Cd I,\ the l'olirC lkpanmCnt. (Current equipment: 2005 Mercont loL_ in_ I-CCordCI' ,t,trnt I Justification Records all incoming/outgoing phone :,d I, Irons the di,p,ttCh C,:nICI- 0113 uIl t'.,ditr u,,n,mi„irn, from policc. Iirc ,utd interop r;,dio Equipment is necessary in case quC�,tion, ari>� a> to host Call for "CI iCC 01. Cnt, CI C h utdlyd or di,putChCd. Expenditures 2011 2012 2013 2014 2015 Tutal I1,: 1; It, Equipment 33 900 33 903 01 200 Total 36.900 36,900 I I Funding Sources 2011 2012 2013 2014 2015 Total t :I, t1 It! Equipment Replacement Fund 36 9'J 36 930 01 200 Total 36.900 36,900 from 20 \ ear plan - none salvage/resale %alue on rept CCd item: �-n- (b • 0 EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN Project # 01 -ERP -211 Project Name Network Server (3) Future 2011 ihru 2015 Department Police Contact Police Chief/IT Ty pe Equipment Useful Life 3 years Category Equipment Priority n/a Total Project Cost: $238,000 Computer servers store information and system programs. One sereno, $15.000 (to be purchased for digital squad car cameras storage and retrieval - see 01 -ERP -213) Justification Annual replacement cycle allows development of system storage program. Use of newer servers for heavy use programs while older servers used for data storage. Prior Expenditures 2011 2012 2013 2014 2015 Total Future 71000 Equipment 8,500 8,500 8,500 8,500 8,500 42,500 127,500 Total 8,500 Total 8,500 8,500 8,500 8,500 8,500 42,500 Total is Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 68,000 1 Equipment Replacement Fund 8,500 8,500 8,500 8,500 8,500 42,500 r 127,500 Total Total 8,500 8,500 8,500 8,500 8,500 42,500 Total Budget Impact/Other Variance from 20 year plan - Cost stabilized at $8.500 per year. ?stimate salvage/resale value on replaced item - $ • Page 37 7hursday. Ifin• ". 2010 EQUIPMENT REPLACEMENT PLAN 2011 tir; rt 2015 City of Hopkins, MN Project # 01 -ERP -212 Projec"amc Mobile Data Computers Future Dct,:u'uncrtt Pt�Ii�r < mltact Pt�lis C hied N pc I IL11111neIll l cful 1 ife 5,ean ( alvaor) I tluil,nlrnl I'riur'iI, n ;L 1 ntal Prnit•ct (rr.0 IQ9^.81111 Mobile data computers installed in I I .yu.l i cart uxd k, rccci, 0 c.11k Ir,,m Lii.TLIICh- 1IL1c1_\ inlurrllati�YI] 6-0111 X.n inLu iatah.l.es. ctuunuulic.itc ar to car. Justification limited life ol' 5 Nears - replacement Prior Expenditures 2011 2012 2013 2014 2013 Total I :••.,n 47,000 Equipment 32 710D 32 723 8 100 Total Total 62.700 62,700 I i Prior Funding Sources 2011 2012 2013 2014 201; Total I r-47,700-01 Equipment Replacement Fund 62 703 92 70, 33 100 Total Total 62.700 62.700 { { Budget Impact/Other Jariance from 20 -,ear plan - Incm.l�c ctUt 11"111 S5 4.5110 It' V,2.701) 1 �`. 4111 \ I I I Itr I,:ltcr I'i I�cil .l L11.11 o"t of \ I l)( docklll >t.lLlttll. stimate sal age:'resale value on rc1,l.lccd itcm: `-o- • • • EQUIPMENT REPLACEMENT PLAN Ah City of Hopkins, MN • • Project # 01 -ERP -213 Project Name Digital Squad Car Cameras Future 2011 rhru 2015 Department Police Contact Police Chief Ty pe Equipment Useful Life 5 years Category Equipment Priority n/a Total Project Cost: $213,000 Digital video camera system in each marked patrol car - used to document events in and out of the patrol car. Images downloaded to server for storaee and retrieval. Justification Police Dept. currenth has eight digital camera units installed and a dedicated server. 'I'he life expectancy of the cameras is about five years. Current cameras Nvere installed in September 2006. Cost: 8 cameras a` $5.000 per unit plus tax - $42.600 1 server ii, $15.000 (to be purchased from Police Netxvork Server (01 -ERP -211) annual allocation that carries fom-ard. Estimated cost $57,600. Cost could be lower if, at the time of replacement, a suitable product is available through a State or County equipment Prior Expenditures 2011 2012 2013 2014 2015 Total Future F-72-60-01 Equipment 42,600 42,600 1 127,800 Total Total 42,600 42,600 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 427600 Equipment Replacement Fund 42,600 42,600 127,800 Total Total 42,600 42,600 Total Budget Impact/Other Variance from 20 year plan - Purchase of squad cameras scheduled in 201 ]moved to 2009 due to continued equipment failure. Replacement schedule life is 5 years. Estimate salvage/resale value on replaced item: $ Pane 39 7'hursdca, lien- 2 7. 2010 EQUIPMENT REPLACEMENT PLAN 2011 ih,'11 2015 City of Hopkins, MN Project # 01 -ERP -214 Project Name Tactical Ballistic Vests Future ( untact R,lis C h,cf I ) he I uil\mcnt t cful I ife \cars l atc_ur) I yuipmrnt Priorit+ n a Intal 1'rnjcct ( u,C '13".51111 Tactical ballistic vests worn hl mcmhcr, of :he 1 lorkin, Police Ueparttrtent I lieh-rt,h I.ntr% aildlt I cam (I IL.1 I I. I he c \ c is +\li r ❑ hi her level ofprx)tection against weapon ,t,,,nilt th,ut the rc_ul❑r dut+ h.,lli,tie \e,1. Justification =ederal and State grant monies lime hecn ,1\,Iiluhle Ill,, h tr II'lIIi,tie \,:,I f'r r;,n, +;r the pa,1 ,c\ cmI xcar,. I he>e Lrmt, 0111\ hin a hn,lik+n )f the total cost of the vest, lea\im_ the Police l)cra tmeut to ha\ the h,tl,m;e I herr i> rn+, cu,u-untec 111,11 these r,utts ++ill he a+ailahle in the Iuttnc. 1'arrantN on the current vests expire, in 200- .ost: 9 vests x $2.133 = $19.197 I o&i\'> cW't). lhus 1101. include ,,u\ ,,l'hlic,Ihle Lt\e,. Prior Expenditures 2011 2012 2013 2014 2015 Total E:;(„rL 7_320,000 Equipment 23 20023 2305 54 300 Total Total 23.200 23.200 1 -,,1 Prior Funding Sources 2011 2012 2013 2014 2015 Total 1. ill7_1 2-0 0-0-01 Equipment Replacement Fund 23 211023 200 54 300 Total Total 23.200 23.200 j ; ,1 Budget Impact/Other Variance from 20 year plan - ne+� item. �,t;: re ul,a hullet hna,l*\ e-ts ltutdcd h+ I'C,Ier,tl 3stimate sahagz'resale value on rchl,,cc+l itcrnt: S • • • EQUIPMENT REPLACEMENT PLAN • City of Hopkins, MN Project # 01 -ERP -215 Project Name Radios -Portable and Mobile Devices Future 2011 thru 2015 Department Police Contact Police Chief Tc pe Equipment Useful Life Category Equipment Priority n/a Description Total Project Cost: $285,000 Portable and mobile radios used by the police. fire and public works departments to allow these departments to communicate on one frequence. Police and fire use their radios on a dail/regular basis. "The public works only uses theirs in the event ofan emergence. stimated Replacement Cost (based on 2009 cost) Portable - $2.300 Mobile - $3.000 Police Fire PW Total Portable 65 32 10 107 IMobile 17 8 0 25 Justification I_ Provides radios so that the police. lire and public works can communicate on a common radio frequent} during an emergence. _ Expenditures 2011 2012 2013 2014 2015 Total Future 0 Equipment 15,000 15,000 15,000 15,000 60,000 1 225,000 Total 15,000 15,000 15,000 15,000 60,000 Total Budget Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 15,000 15,000 15,000 15,000 60,0001 225,000 Total 15,000 15,000 15,000 15,000 60,000 Total from 20 year plan - added replacement cost at $1.000 per year fixed. starting in 2012. Do not expect all 132 radios to need replacing at time. mate salvage/resale value on replaced item: $ • Paye 41 7hursdcn% May ". 1010 EQUIPMENT R1V1E�1V P,�LTD�ACEMENT PLAN 2011 1hru 2015 ,p l City Ol Hopkins, (u111act P li c l hi t • • • ""') '- EQUIPMENT REPLACEMENT PLAN A City of Hopkins, MN L_J • Project # 01 -ERP -700 Project Name Engineering Van Future 2011 thru 2015 an used by Engineering Department for surrey equipment and on job site work. Current vehicle: 2000 Chevrolet Suburban Justification to and from job site, hauling of surveying and traffic counting equipment. Department Public Works: Engineering Contact Public Works Director "r) pe Equipment Useful Life 10 years Category Vehicles Priority n/a Total Project Cost: $66,400 Prior Expenditures 2011 2012 2013 2014 2015 Total Future 16,000 Vehicles 21,500 21,500 IT 28,900 Total Total 21,500 21,500 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 77000 Equipment Replacement Fund 21,500 21,500 28,900 Total Total 21,500 21,500 Total Variance from 20 year plan - increase amount from 14.300 to 16.000 to reflect actual cost. Purchase used Suburban from Hennepin Co. 2002 auction -price is $13.000 to $14.000 + $2.000 for equipment. Estimate salvage;resale value on replaced item: $2.500 Pace 43 77mrsday. tfrn• ". '010 EQUIPMENT REPLACEMENT PLAN 2011 ,h a 2015 City of Hopkins, MN Project # 01 -ERP -800 Project Name 1/2 Ton Pickup Truck Future Dcparlinc nl Puhh,: \\ ,art., I'atk. I rr;,tn ( unt:ut PUNIC \\urk, IhrceLor .% pc I .lugvnrnt t «�nrl I irc ���,cttr. Equipment Replacement Fund 26 40) I'riur'ih n a Expenditures 2011 2012 2013 2014 201; Total F1.11:1 - Vehicles _ 26 4N 26 47F-7-54700 Total 26,400 26,400 1 t,, l Funding Sources 2011 2012 2013 2014 2015 Total F:,;�trt Equipment Replacement Fund 26 40) 2 4400 35.400 Total 26.400 26,400 I , from 20 %ear plan - mo% L! hick I r mt 2011 t,) n l' sahagz resale value on NJ)ILI ;J it m: ti ,r u • 0 CJ • EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN Project # 01 -ERP -801 Project Name 4x4 3/4Ton Trucks (2) Future 2011 thru 2015 Department Public Works: Parks/Forestry Contact Public Works Director T� pe Equipment Useful Life 8 years Category Vehicles Priority n/a Prior Expenditures 2011 2012 2013 2014 2015 Total Future 53,200 Vehicles 67,400 67,400 1 193,200 Total Total 67,400 67,400 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 53,200 Equipment Replacement Fund 67,400 67,400 1 193,200 Total Total 67,400 67,400 Total ariance from 20 N car plan - none +timate salvage/resale value on replaced item: $ Pa=e 45 Amrsdcn% Min- 27. 2010 EQUIPMENT REPLACEMENT PLAN 2011 : ir-tt 2015 '--r �7 Dcp:u-nnent Puhlic \l,,rl,� I';u4.ti I .,re>Ut City of Hopkins, �/11V ( onUct Puhlic \\ „rl„ Uir,.tor Project # 01 -ERP -802 I %Ile I .Jilllrrncnt t ,cful I He I I tear, Project lame 3/4 Ton Utility Truck aieeur� \'chicle, Future Prioritt n a Description 1 t,t:t1 Pri'juet c .,.r. "u.troo 3•14 ton truck with utiliri bod', u>ed I'Or uan,poilin_ toot, and cquihm.ni I' r iepair of t ariou, huildill_ 1. irri_,llinrl. ete. around 111e eil%. Current vehicle: 1998 Dodge Ram ; � I u I Justification Expenditures 2011 2012 2013 2014 2015 Total 1 t c Vehicles 32 20,' 32 200 49700 Total 32.200 32.200 • Funding Sources 21111 2012 2013 2014 2015 Total I u o I Equipment Replacement Fund 32 2',J 32 20" F 43 7 Total 32.200 32.200 1 ,! j from 2O3earplan -mo%a hark Iroin 21)11 to _21i1-1. Chun c Jif Ihmt III to I salvage,'resale value on replaced item: 5 � " �, I ", � _' - -: " ;; 0 1 EQUIPMENT .REPLACEMENT PLAN 2011 thru 2015 City of Hopkins, MN Project # 01 -ERP -807 Project \ame Trueksters (3) Future used by Parks Division of Public Works for bailfield and parks maintenance. 1996 Tom Workman, 2004 Toro Workman 3200. 2004 Toro Workman 2110 Justification IPark maintenance, bailfield grooming and weed spraying. Prior Expenditures 29,900 Equipment Total • • Total Department Public Works: Pad s/Forestry Contact Public Works Director Ti pe Equipment Useful Life 15 years Category Equipment Priority n/a Total Project Cost: $114,700 2011 2012 2013 2014 2015 19,800 19,800 Total Future 197800 1 65,000 19,800 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 29,900 Equipment Replacement Fund 19,800 19,80065,000 Total Total 19,800 19,800 Total Budget Impact/Other Variance from 20\ear plan -'alone Estimate sal agetresale value on replaced item: $1,400 each Pa2e47 Aursdar, I1m• 27.'010 EQUIPMENT REPLACEMENT PLAN 2011 ilirit 2015 1)cI)arintcnl Public \\,wk, Park, I o%n,ti,_ City of Hopkins, MN ( ontact PIN j,: \\ „rk, I)irccior Project # 01 -ERP -808 I \ I I `Iuil,mettt Project Name Riding Mowers (3) l ,clul 1 ifc X gran (atcuor) I 'µuprnent Future I'riurit\ n a Description I ul,l Prniccl Riding mowers used by Parks Di\ i.,on 01 PLANiC \1, r1 OIlC 1111M CI .il ll Ll Cid lur ,i&I \,Ilk >n„u rrmu ;tl burin ntrr month.,,. (Current equipment: 1996 Toro Gn,undm.1�1tCr ; I;. '(u -I 101-0 LCF, I urn.'u 16 IaCt,h.,vt ILolar\ \hm Cr I Justification Movving cit)parks and right of\\.n, .ind ,itiC ;ilk ,nog\ runio\\ tl. Prior Expenditures 7-4-900-01 Equipment Total 2011 2012 2(113 2014 2015 J 3GG 22 &00 20 3G0 Total 10.300 22.800 20.300 Total ,if i!rC 53 4JJ 53 300 53,400 Prior Funding Sources 2011 2012 2013 2014 2015 Total [-.I: a rt 47000 Equipment Replacement Fund J 3GJ 22 &JJ 2J 300-777 53 4J0 F 53 300 Total Total 10.300 22.800 20.300 53,400 1 : - 11 rdget Impact/Other -ianee from 20 Near plan - mo N C l n u n' 1 1 11,, ' i t 13. imate salvage/resale value on repLICCLi itCnr �huu Cath •I • 0 16 EQUIPMENT REPLACEMENT PLAN City of Hopkins, MN Project # 01 -ERP -813 Project Name Brush Chipper Future 2011 thru 2015 Department Public Works: Parks/Forestry Contact Public Works Director chipper used for Forestn and brush pick up operations of Public Works. 7) pe Equipment Useful Life 20 years Category Equipment Priority n/a Total Project Cost: $25,700 Current equipment: 1993 Brush Bandit Chipper 250 1 Justification Variance from 20 year plan - change to usable life to 20 years - move back from 2009 to 2013. Estimate salvagelresale value on replaced item: $ • Pace 49 77mrsdm% Afar ". 2010 Expenditures 2011 2012 2013 2014 2015 Total Equipment 25,700 25,700 Total Funding Sources 2011 25,700 2012 2013 2014 25,700 2015 Total Equipment Replacement Fund 25,700 25,700 Total 25,700 25,700 Variance from 20 year plan - change to usable life to 20 years - move back from 2009 to 2013. Estimate salvagelresale value on replaced item: $ • Pace 49 77mrsdm% Afar ". 2010 EQUIPMENT REPLACEMENT PLAN 2011 aim 2015 City of Hopkins, MN Project # 01 -ERP -300 Project Name 4x4 3/4 Ton Pickup Ni ith PloNi Future Dc 1)arrIII cnt Puhh,: \\,ui,, 1,trat, I ta11i� ( untact Pnhli,: \\„rl,, Di%ct,v I �% pc I .luilmtcnt I cful I ifc I i \car, ( atcCar� \ chi lc, Priurin n ;t Prior Expenditures 2011 2012 2013 2014 2015 Total I :.ts 25,000 1 Vehicles 33 6D, 33 303 45 2U0 Total Total 33.600 33.600 I I Prior Funding Sources 2011 2012 22013 2014 2015 Total I ,.,: t 7-25,-00-01 Equipment Replacement Fund 33 ; 33 5 .i �-= t� 5 200 Total Total 33.600 33,600 I Budget Impact/Other Variance from 20 Near plan - Incrca�,: c\hc1)1i1tun-1: tO FLAICCt actual COIL ( han_�c Irknrt 1 2 nm I"cl.uh t„ ; 1 t.m 1\ I I'icl.uii. :stimate sahageiresale value on Nil1,tccd itrm: �1.5nu • • 0 • • • EQUIPMENT REPLACEMENT PLAN 2011 lhru 2015 City of Hopkins, MN Project # 01 -ERP -301 Project Name .1X4 314 Ton Truck with Plow Future ton pickup used by Street Divison of Public Works for heavy loads and pulling trailers. vehicle: 2006 Ford F250 ng, pulling trailers. transportation to and from Department Public Works: Streets/Traffic Contact Public Works Director T% pe Equipment Useful Life 8 years Category Vehicles Priority n/a Total Project Cost: $141,700 Prior Expenditures 2011 2012 2013 2014 2015 Total Future 24,000 Vehicles 30,400 30,400 87,300 Total Total 30,400 30,400 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 24,000 Equipment Replacement Fund 30,400 30,400 87,300 Total Total 30,400 30,400 Total ariance from 20 ) ear plan - none ;timate salvage./resale value on replaced item: $1.500 Pace ; I lhursdtn% alai ", 2010 EQUIPMENT REPLACEMENT PLAN 2011 ihrii 2015 City of Hopkins, MN Project # 01 -ERP -303 Project Name 1 Ton Dump Truck (2) Future Truck is used in the Street Div i>iom o I'uhlic \\ orl.r. urrent vehicles: 1997 Ford F3;o S _nnn I ,,,,i 1 1;n ehicle used b} various department, tw ueet ani Il,u1, in,Jmenancc acid li:ht huuljnL. Ucparlmcm Public 1\ ork. St C;t, I riiliC ( ont:tct PuhllC \\ orh, I)ircct,,r �N pc I Iuipment I .eful I ife 12 \carr, ( alcaor) \'Chicle, I'riruit� n a utal I'rujcct ( ...t: S205,500 Prior Expenditures 2011 2012 2013 2014 2015 Total I ti: ur'r 677900 Vehicles _ 34 707 34 7J0 02 900 Total Total 34.700 34.700 Prior Funding Sources 2011 2012 2013 2014 2015 Total F.ttit i r 67,90D Equipment Replacement Fund 34 713 34 7JO 02 900 Total Total 34.700 34,700 1 ,.,1 Budget bnpact/Other Variance from 20 N ear plan - moN e h.tc 1. l nom low) t') n l u. Estimate sahage.'resale value on rel,luccd item: ti • • 0 EQUIPMENTfREPLACEMENT PLAN 2011. rhru 2015 Department Public Works: Streets"I'raiic •City OlCHopkins, MN Contact Public Works Director Project # 01 -ERP -304 1'y pe Equipment Useful Life 17 years Project Name 1 Ton Traffic Boom Truck Category Vehicles Future truck used in Street and Traffic Divisions of Public Works. Current vehicle: 1995 Chevrolet 1 Ton Boom Truck Justification Vehicle used by Traffic Department for signal and light pole maintenance. Priority n/a 'Fetal Project Cost: $199,000 Expenditures 2011 2012 2013 2014 2015 Total Future Vehicles Total 1 0 75,000 75,00011 24,000 75,000 75,000 Total Funding Sources 2011 2012 2013 2014 2015 Total Future Equipment Replacement Fund 75,000 75,000124,000 Total 75,000 75,000 Total Budget Impact/Other Variance from 20 year plan - None stimate sat%age 'resale value on replaced item: $8.000 • Pane 53 Thurs&n% flan- 27. 2010 EQUIPMENT REPLACEMENT PLAN 2011 that 2015 City of Hopkins, MN Project # 01 -ERP -306 Project Name Tandem Dump Trucks (2) Future 1)c ha rt incnI Puhl,c \\ ork> Strca, I r:llhc ( ontact Puhh,: \\,,rk, 1)irc.nor I .% lir I yugxnent t clul I ife I - \car. < atcenr, \'chide, Priorih n a total Project ( o.i: C5-6.1(it) Expenditures 2011 2012 2013 2014 2015 Total I a,ur, Vehicles _ 22 0J0 — - 142 400 164 400 1 411 700 Total 22.000 142.400 164,400 j j Funding Sources 2011 21112 2013 2014 2015 Total I.:,ur� Equipment Replacement Fund 22 0:10 142 400 1344,10 F 411 700 Total 22.000 142,400 164,400 j : , j Variance from 20 %ear plan - \Io\c'il1 t,,-'() I I - hu i t S_ .nail to rclurh )5 I ord I.ui�lrnt \\ ith nL�\\ .t\ Ic hug anJ d1,01) ,,ln i r .1nJ hrc ttin salt option - extend life to 2018. Moi c'll1 5 hLlrch.L c to 'll I" JLIc to c,1nditl,tn1 Of tf Lick. Estimate salvage.%resale value on rcl,l❑ccd item: ti -n - Ll • • • n EQUIPMENT REPLACEMENT PLAN 2011 ihi-it 2015 City of Hopkins, MN Project i# 01 -ERP -308 Project \ame Front End Loaders (2) Future Current equipment: 1991 Caterpillar 928E Loader & 2005 Prior Expenditures 140.000 Equipment Total liar 9386 Department Public Works: Streets/Traffic Contact Public Works Director T) pe Equipment Useful Life 15-18 vears Category Equipment Priority ata "rota) Project Cost: $848,600 2011 2012 2013 2014 2015 Total Future 172,000 172,00051 36,600 Total 172,000 172,000 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future —14-0—,0 0-0 Equipment Replacement Fund 172,000 172,000 536,600 Total Total 172,000 172,000 Total Budget Impact/Other Variance from 20 year plan - None H'stimate salyage.,resale value on replaced item: S Pate 55 Aitrsdin,. H0,27, 2010 EQUIPMENT REPLACEMENT PLAN 2011 hrit 2015 �,�1V T Uhm cartent I'uhlic 1l,rrl., SU'c,t, I rc atli 1V1 City of Hopkins, ( owact Public \\ork, I)irca r An Project # 01 -ERP -309 Project Name Skid Loader (2) 1 N pv I quihment I ,clul 1 rfe 12 \car, ( ntr M'.N I Iuihment Future Priorit% n a Expenditures 2011 2012 2013 2014 2015 Total I -!urc Equipment 36 013 35 D30 1---75-1-6070 Total 36.000 36,000 i I • Funding Sources 2011 2012 2013 2011 2015 Total I.,t.tt. Equipment Replacement Fund 35 210 36 333 7-771-757 Total 36.000 36,000 1 , , .,1 from 20 Near plan -mo\c h,ir,klrom -20111 to 2u1 I. sahagehesale value on repla, cd item: S :7 • • EQUIPMENT REPLACEMENT PLAN 2011 ihru 2015 City of Hopkins, MN Project # 01 -ERP -311 Project Name Sweeper Future sweeper used by Streets Division for sweeping streets and parking lots. 2001 Elvin Pelican SE Justification Street sweeping, event Prior 115,300 Total Expenditures spring sand removal. Department Public Worts: Streets/Traffic Contact Public Works Director T) pe Equipment Useful Life 12 years Category Equipment Priority n/a Total Project Cost: $494,700 2011 2012 2013 2014 2015 Total Future 156,400 156,400 1 223,0001 Total 156,400 156,400 Total Prior Funding Sources 2011 2012 2013 2014 2015 Total Future 115,300 Equipment Replacement Fund 156,400 156,400 223,000 Total Total 156,400 156,400 Total fmm 20 year plan - none salvage/resale value on replaced item: $12.000 Pace i7 Thursday. t/ay 27. 2010 EQUIPMENT REPLACEMENT PLAN 2011 2015 City of Hopkins, MN Protect # 01 -ERP -312 Project Name Roller Future Used bN Street Department for wphalt rr�urGtring. urrenteauinmenC 19891ni!ersoll R,md Roper Expenditures 2011 2012 2013 Equipment 45 90) Total 45.900 Wpartment Puhh,: %\ ork, Snca, I cllfic ( untact PUNIC \\ork, Ihreaor I IN pc I Iuipntcnt I cf ll I itc 2fi \ear, ( aic on I 'luipntcni I'riurih n a Mal I'rujcct ( u.t: 045,900 2014 2015 Total 45 KO 45,900 Funding Sources 21111 2012 2013 2014 2015 Total Equipment Replacement Fund 45 90D 45 90J Total 45.900 45,900 Budget Impact/Other Variance ITom 20 New plan - :Vonc 3stimate salvage/resale value on rchl.iccd item ti 01 0