CR 11-063 (2012-2016 Capital Improvement Plan)0 June 29, 2011 Proposed Action Council Report 2011-063 2012-2016 CAPITAL IMPROVEMENT PLAN Staff recommends adoption of the following motion: Move to adopt the 2012-2016 Capital Improvements Plan. Adoption of this motion will authorize staff to begin efforts to implement 2012 projects by including them in the 2012 budget process, and to begin the preliminary process for their implementation. Overview The Capital Improvements Plan is a planning document intended to help the City anticipate major capital items and to consider the financial impact of proceeding with those planned improvements. Discussions have been held with the Park Board and Planning Commission, as well as the City Council, in detailing proposed and necessary improvements. Staff is recommending adoption of the plan. Primary Issues to Consider Does adoption of the CIP mean projects will be implemented? The CIP is a planning document, not an implementation action, and therefore, additional approvals will be necessary for projects to proceed. Appropriate notifications would also be made for those projects that have funding implications. • Are funds available for all projects? The plan outlines funding implications if all projects are implemented. Necessary funding changes have been anticipated as part of this plan, and are recommended therein Supporting Information • 2012-2016 Capital Improvements Plan Christine M. Harkess, CPA, CGFM Finance Director Financial Impact: $ projects included in budgets Budgeted: Y/N X N Source: Various Related Documents (CIP, ERP, etc.): CIP Notes: 2012-2016 CAPITAL IMPROVEMENT PLAN - cl Y or \ I J� HOPKINS % • City of q-lopkins loloFirst street south • Hopkins, %N 55343-757.3 • Phone: 952.935.8474 • Fax 952-935-1834 Web address: www.hopkknsmn.com DATE: July 2011 TO: Honorable Mayor and Members of the City Council FROM: Jim Genellie, Acting/Assistant City Manager SUBJECT: 2012-2016 CAPITAL IMPROVEMENT PLAN With this letter I respectfully submit the 2012-2016 Capital Improvement Plan. This five- year planning document represents the combined efforts of city staff, advisory commissions, citizens and the City Council. The Capital Improvement Plan is a five-year forecast of project needs in the City of Hopkins. It is intended to alert the Council and citizens to the major capital needs on the horizon. The first year of the plan becomes an adopted capital budget and relates almost completely to the operating budget that is approved on a yearly basis. The remaining four year represents an estimate of project needs and funding capabilities of the city. This year's plan does not include proposed equipment purchases. A document relating specifically to equipment replacement needs has been developed into a separate document. The Capital Improvement Plan is intended to serve as a planning tool and is therefore structured to present a meaningful, long-range perspective of the city's capital programming needs. At the same time, sufficient projected detail is provided to enable those who review the information to make informed decisions on the programming of projects over the next several years. Please use the information provided to formulate plans, projects and questions. The Capital Improvement Plan can serve the community best by provoking thoughts and actions. This document was developed by the Finance Department with assistance of all city departments. I want to especially thank all those involved in the development of the Capital Improvement Plan and especially Steve Stadler, Public Works Director, Kersten Elverum, Planning and Economic Development Director, Christine Harkess, Finance Director, and Debbie Sperling, Administrative Assistant for their hard work and dedication. Partnering with the Community to Enhance the Quality of Life • Inspire • Educate 0 Involve • Communicate • CAPITAL IMPROVEMENT PLAN 2012-2016 TABLE OF CONTENTS to Page City Manager's Message Table of Contents Introduction Introduction and Purpose Program Descriptions Utilities Program Transportation Program Parks, Forestry, and Pavilion Program General Public Buildings Program Economic Development Sources of Funding Sources of Funding Funding Abreviations Programs and Categories Summary of Impacts on Major Funding Sources Cash Flow Statements Park Capital Improvement Fund Capital Improvemetn Fund Municipal State Aid Fund Permanent Improvement Revolving Fund (PIR) Water Utility Fund Sewer Utility Fund Storm Sewer Utiltiy Fund Pavilion - Ice Arean Fund Communications (CableTV) Fund Five -Year Project Summaries Projects by Year Department Summary Projects by Department Funding Source Summary Projects by Funding Source Project Descriptions & Narratives Economic Development General Public Buildings Parks & Recreation Streets Utilities N FA 4 5 5 6 9 10 11 13 16 17 19 24 0 25 26 27 28 29 30 31 32 34 36 37 40 41 44 48 67 77 95 0 Introduction • INTRODUCTION AND PURPOSE The Capital Improvement Plan is a flexible plan based upon long-range physical planning and financial projections, which schedules the major public improvements that may be incurred by the City over the next five years. Flexibility of the Capital Improvement Plan is established through annual review, and revision if necessary. The annual review assures that the program will become a continuing part of the budgetary process and that it will be consistent with changing demands as well as changing patterns in cost and financial resources. Funds are appropriated only for the first year of the program, which is then included in the annual budget. The Capital Improvement Plan serves as a tool for implementing certain aspects of the City's comprehensive plan; therefore, the program describes the overall objectives of City development, the relationship between projects with respect to timing and need, and the City's fiscal capabilities. The Capital Improvement Plan can help assure: 1. A systematic approach to planning and initiating capital projects affording the opportunity to plan the location, timing, and financing of needed public improvements; 2. The development of a realistic program of capital spending within the City's projected fiscal capability to finance such projects, avoiding sharp change in the tax levy or bonded indebtedness; 0 3. The coordination of public and private improvement projects permitting adequate time for design and engineering to eliminate duplication of effort and expense; 4. The expenditure of public funds that is compatible with the City's adopted Comprehensive Plan; 5. That the public is kept informed of the proposed future projects and expenditures; 6. That private investors are aware of the City's long-range development program so that they may guide their development in a way that is compatible with the City's program; 7. Aid in achieving federal and/or state participation by providing the necessary planning and lead time necessary for a successful application in addition to meeting prerequisites needed for certain federal and state grants. 11 a] 0 PROGRAM DESCRIPTIONS • In order to effectively plan for and manage the projects contained in a Capital Improvement Plan, it is necessary to group similar activities into "Program Categories". The City of Hopkins' activities are divided into four program categories which are 1) Utilities, 2) Transportation, 3) Parks, Forestry and Pavilion, and 4) General Public Buildings. The City also includes an outline of proposed expenditures for unscheduled projects. Program categories are explained in the following sections. UTILITIES PROGRAM Program Description: The Utilities Program includes the municipal water, municipal sanitary sewer, storm sewer and refuse systems. Program Goal: Provide reliable, efficient, and safe utility service to all parts of the City with a minimum of adverse effects on the environment. Subprograms: Water, sanitary sewer, storm sewer, and refuse service. I. Municipal Water System Subprogram (WA) A. Subprogram Goal: The goal of the Municipal Water System subprogram is to provide water in sufficient quantities at sufficient pressure, with a high degree of reliability and safety to all parts of the City so as to satisfy the normal demands of the general public for water while at the same time providing sufficient reserves in case of fire emergency or power outages. B. Objectives: 1. Water quality shall meet the purity standards of the Minnesota Department of Health. 2. Any hydrant on the system shall, under maximum condition, deliver no less than 500 gallons per minute with a residual pressure of 20 pounds per square inch. 3. The system shall be looped to provide maximum reliability. 4. The supply and storage system shall be designed and maintained to have maximum reliability. 5 II. Municipal Sanitary Sewer Subprogram (SA) 0 A. Subprogram Goal: The goal of the Municipal Sanitary Sewer subprogram is to promote a healthful environment by collecting all sewage from existing and projected development in a sanitary and economic manner. B. Objectives: 1. Provide sewer lines of adequate size and grade to collect and transmit all discharge sewage. 2. Prevent sewage from overflowing into the natural environment. 3. Prevent sewage back-ups. 4. Encourage or promote connection of all generators of sewage to the Municipal system. 5. Meet the effluent and infiltration standards of the Metropolitan Waste Control Commission. III. Storm Sewer Subprogram (SS) A. Subprogram Goal: Manage and control surface and ground waters in order to protect the man-made and natural environment in a safe and efficient manner. B. Objectives: 1. Prevent flooding. 2. Prevent damage to property due to erosion. 3. Meet water quality standards established by the controlling regulatory law or authority. TRANSPORTATION PROGRAM Program Description: This program includes streets, walkways, traffic signs and signals, vehicular parking facilities, and street lighting. Program Goal: Provide for the safe and efficient movement of people and goods throughout the city. I* I Subprograms: Streets, Walkways/Sidewalks, Signs/Signals, Parking Facilities, and Street Lights. I. Streets Subprogram (ST) A. Subprogram Goal: The goal of the Streets subprogram is to provide safe, convenient, economic public streets to best facilitate the movement of vehicular traffic. B. Objectives: Streets should be constructed with permanent surfaces, concrete curb and gutter, and with ancillary storm drainage, to standards established by the City. 2. Streets should be of a size and load capacity consistent with their functional classifications. 3. Timely major repair to preserve the basic capital investment in streets. II. Walkways/Sidewalks Subprogram (WS) A. Subprogram Goal: To provide a safe and convenient pedestrian system with incidental recreational benefits. III. Signs/Signals Subprogram (SI) A. Subprogram Goal: The goal of the Signs/Signals subprogram is to provide an efficient and orderly system of street and traffic signing so as to promote safe, convenient travel throughout the City. B. Objectives: Signs and signals should be installed in conformity with the Minnesota Manual on Uniform Traffic Control Devices. 2. Periodic surveys and studies should be made to document the effectiveness of City signing patterns. IV. Parking Facilities Subprogram (PA) A. Subprogram Goal: To provide such supporting facilities as will promote maximum use of public parking spaces by employers, employees, customers, and visitors. B. Objectives: 0 1. Provide parking facilities for present and anticipated needs of the City of Hopkins. V. Street Lights Subprogram (SL) A. Subprogram Goal: To provide a system of street lighting within the City that will promote safe and convenient vehicular and pedestrian travel on City Streets. B. Objectives: 1. To provide lighting at each street intersection within the City. 2. To provide mid -block street lighting in conformance with the City's street lighting policy, in order to provide equitable, cost efficient lighting. 3. To continually update the system so as to provide energy and cost efficient lighting. PARKS, FORESTRY AND PAVILION PROGRAM 0 Program Description: This program includes community parks, neighborhood parks, open spaces, recreational structures and facilities. Program Goal: The goal of the Park and Recreation Program is to provide facilities for safe, stimulating, and comprehensive leisure time activities of Hopkins citizens. Subprograms: Neighborhood Facilities, Community Facilities I. Neighborhood Facilities Subprogram (NF) A. Subprogram Goals: To acquire ownership or use rights of park sites located to provide convenient walking access to all Hopkins citizens and to develop such sites to provide optimum recreational serviceability consistent with the preservation and enhancement of pleasing aesthetic qualities. B. Objectives: 1. Acquire property or use rights on those neighborhoods that do not have convenient walking access to neighborhood park facilities. 2. Develop neighborhood park facilities to meet the needs of various user groups. 0 I 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Preserve and enhance the aesthetic qualities of neighborhood parks. II. Community Facilities Subprogram (CF) A. Subprogram Goals: The goal of the Community Facilities subprogram is to develop, or acquire ownership or use rights of sites which serve the entire City and to provide facilities that serve community -wide needs. B. Objectives: Acquire sites that have valuable and unique natural characteristics to preserve irreplaceable community resources. 2. Preserve by acquisition, gift, or other arrangement properties that have valuable historic -cultural qualities. 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Construct or acquire structures and facilities necessary to meet the changing needs of the community. GENERAL PUBLIC BUILDINGS PROGRAM Program Description: The General Public Buildings Program includes all municipal buildings except those provided for in the Utility and Park Facilities Program. Program Goal: Provide buildings that are adequate and convenient for the efficient accommodation of City functions. Subprograms: Administrative Offices Maintenance Facilities, Fire Facilities, Community Center. I. Administrative Offices Subprogram (AO) A. Subprogram Goal: The goal of the Administrative Offices subprogram is to . provide facilities for the efficient and safe conduct of legislative and administrative functions of the City. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of the City services. II. Maintenance Facilities Subprogram (MF) A. Subprogram Goal: The goal of the Maintenance Facilities subprogram is to provide facilities for the efficient and safe conduct of City maintenance functions. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of City services. III. Fire Facilities Subprogram (FF) A. Subprogram Goal: To provide a fire station, or stations, for storage of Fire Department equipment and for the training and meetings of volunteer fire fighters to provide prompt and efficient protection to life and property. B. Objectives: 1. Provide a maximum four -minute daytime and three-minute nighttime response to all points within the City. 2. Meet objective 1 through the use of volunteers. IV. Community Center Subprogram (CC) A. Subprogram Goal: To provide a community facility, or facilities, which meet the social, recreational, and cultural needs of all citizens, particularly senior citizens. B. Objectives: 0 1. Maintain current facilities in a state of good repair so as to maximize cost • effectiveness and avoid costly repairs. m 2. Construct or acquire structures and facilities necessary to meet the changing needs of the City. 3. Upgrade facilities as necessary to provide for efficient, safe, and effective provision of City services. ECONOMIC DEVELOPMENT PROGRAM Program Description: This program includes redevelopment projects that have been identified through adopted plans and goals of the City of Hopkins. Program Goal: To facilitate the redevelopment of key sites in order to achieve the state objectives of the project. Objectives: 1. Elimination of blight or blighting conditions 2. Creation of jobs 9 3. Increase property value(s) • 4. Catalyst of additional redevelopment 5. Environmental clean-up Increase transit -oriented development around LRT stations M 0 Sources of Funding M 0 SOURCES OF FUNDING In order to fund the anticipated Capital Improvements, the City must draw upon a variety of sources. Many of these sources have a specific or "dedicated" purpose (i.e., the water utility fund will finance water main installation but not a street overlay). Therefore, it is important to identify the uses and limitations of the various revenue sources. CURRENT REVENUES - GENERAL FUND (CR) This represents funding from current year revenue collections in the General Fund that support operations and capital outlay expenditures. Revenue sources include property tax levies, state aid payments, and various permit and license fees. This source of funding is generally used only for operations and small capital purchases. GENERAL FUND RESERVES (GR) Reserves of the general fund are the funds remaining after subtracting cash flow and emergency amounts from the City's cash balance, sometimes referred to as "fund balance". The use of General Fund Reserves is not recommended for Capital Improvements without significant staff and Council review. COMMUNICATION (formerly Cable TV) FUND (CT) This funding source consists of franchise fees received from the local Cable TV company, in excess of the amounts earmarked for the access programming and commission budgets. Expenditures are limited to cable -related facilities, or must have a cable related purpose. ECONOMIC DEVELOPMENT FUND (ED) This funding source was established by the Housing and Redevelopment Authority (HRA) and the City of Hopkins, to provide funding for the purpose of promoting development and redevelopment within the City. The Economic Development fund is a revolving fund administered by the HRA, intended to provide an ongoing funding source used to reduce or extend the long term debt involved with development and redevelopment activities. The HRA reviews all proposed uses of this fund on an individual basis. GRANT-IN-AID (GA) This is aid received from either the Federal or State government. In many cases, grants are made on matching basis, which means the City shares a portion of the costs of the project being funded. 13 MUNICIPAL STATE AID STREETS (MS) This funding source represents funds received from the State of Minnesota to support construction and maintenance of State Aid classified municipal streets. State law defines the types and limits of State Aid Streets expenditures. PERMANENT IMPROVEMENT REVOLVING/GENERAL OBLIGATION BONDS (PI) Improvements with a life of several years may be financed from the proceeds of a General Obligation Bond Issue. Law limits the total debt that can be incurred under this method of financing. With some exception, General Obligation Bonds are generally subject to a referendum process. Examples of projects, which may not require a referendum, are those financed through the use of special assessments where at least 20 percent of the project cost is assessed to the benefiting property owners. The remaining portion not assessed can be financed through general obligation bonds repaid by a tax levy. PRIVATE SECTOR FUNDING (PF) This funding source consists primarily of payments made by developers for the purchase of land, the installation of water, sewer, or streets or other related expenditures. It can also refer to donations made to the City by individuals or groups. OTHER GOVERNMENTAL UNITS (GU) These are funds received from Hennepin County, adjacent communities, etc. for projects that also benefit a jurisdiction other than the City of Hopkins. REVENUE BONDS (RB) These are bonds issued for improvements made for specific revenue producing facility or operation. The debt incurred is repaid from the revenue generated by the facility. If the revenue generated is insufficient, then the difference becomes an annual obligation of the taxpayers and becomes an additional tax levy. These are generally not subject to referendum. REAL ESTATE SALES FUND (RE) • This funding source consists primarily of funds built up from the sale of City owned property. To date, the fund has been used for building improvements. Because the sale of both general City property and park/recreation property are accumulated into this fund, earmarking a portion for recreational purposes may be justified. 0 14 SPECIAL ASSESSMENT (SA) A number of projects may be realistically financed using Special Assessment to pay the ultimate cost. Almost any project can potentially be financed using the assessment process. In each case it is necessary to make a determination that the assessed property will benefit by the amount of the assessment. The cost of street reconstruction is shared by the property owner and the City. Special assessments to individual properties are capped per city policy. Concurrent improvement costs to the utility systems are assumed by the respective utility funds. TAX INCREMENT FINANCING (TF) This funding source results from the tax value of new development that is "incrementally" greater than the existing tax value. Typically, bonds are sold based on the assumption that the higher tax receipts will retire the bonds. However, the use of TIF funds through a "pay as you go" method has become more common. This type of funding can be used for public improvements within a redevelopment district to support the goals of redevelopment, specifically the elimination of blighted conditions. Approval of the Hopkins HRA should be anticipated prior to the commitment of these funds. State law strictly regulates the use of these funds. 0 WATER FUNDS (WF) Water funds consist of revenue generated from the sale of water. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. SANITARY SEWER FUNDS (SF) Sanitary sewer funds consist of revenue generated from charges made for sewage disposal. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. STORM SEWER UTILITY REVENUES (SU) Storm sewer funds consist of revenue generated by charging storm water drainage fee to parcels of land for the availability and use of municipal storm sewer facilities. Expenditures from this funding source are related to drainage facilities. PAVILION FUND (PA) Pavilion Funds consist of revenues generated from rental fees collected from users of the Pavilion. These funds are utilized to pay for operating, and capital expenditures. 15 Funding Sources 0 Communication (formerly Cable TV) Fund CT Current Revenues — General Fund CR General Fund Reserves GR Economic Development Fund ED Grant -In -Aid GA Housing and Redevelopment Authority HRA Municipal State -Aid Streets MS Other Government Units GU Park Dedication Fund PDF Pavilion Fund PA Permanent Improvement Revolving/General Obligation Bonds PI Private Sector Funds PF Real Estate Sales Fund RE Revenue Bonds RB Sanitary Sewer Fund SF Special Assessment SA Storm Sewer Fund SU Tax Increment Financing TF Water Fund WF It. 0 Programs and Categories Utilities Program Municipal Water System Category Municipal Sanitary Sewer Category Storm Sewer Category Transportation Program Streets Category Walkways/Sidewalks Category Signs/Signals Category Parking Facilities Category 0 Street Lights Category Parks, Forestry and Pavilion Program Neighborhood Facilities Category Community Facilities Category General Public Buildings Program Administrative Offices Category Maintenance Facilities Category Fire Facilities Category Community Center Category Arts Center Category 0 Economic Development Program 17 Summary of Impacts on Major Funding Sources • • 0 SUMMARY OF PROJECT IMPACTS ON MAJOR FUNDING SOURCES CURRENT REVENUES/GENERAL FUND RESERVES Expenditures for 2011 are budgeted at an increase of 2.25% over the 2010 budget. The 2011 budget was compiled as a maintenance budget following a second year of state budget cuts to the Market Value Homestead program (MVHC) that reduced the budget by approximately $245,000. To keep the budget balanced we eliminated capital outlay from the General Fund, provided for small increases in wages for most employees and implemented small cuts across all departments. The 2012 budget has begun with all departments again working towards a maintenance budget as the MVHC will again be unallotted by the state. The tax levy is the major source of revenues (82%) for the General Fund and therefore would need to increase if general fund operating and capital expenditures increase in 2012. Annually the legislature debates the future of tax levy limits which was reinstated for 2009 and thus far remain in place through 2012. Reserves in the General Fund total $4,253,260 at the end of 2010 and are projected to remain at that level for 2011. The State Auditor's Office recommends no less than five month of operating expenditures. For 2011 five months of expenditures would total $4,291,386. At January 1, 2011 the fund balance was at 41.2% of budgeted expenditures. PERMANENT IMPROVEMENT REVOLVING FUND P.I.R. - G.O. DEBT Funding from bonds is used to reimburse the P.I.R. fund for public improvement projects, which have been previously expended. The debt is funded by special assessment collections and city tax levies over a ten to fifteen year period. The next bond sale is scheduled for 2012 and will replenish funds used for 2010 and 2011 projects. The current outstanding debt is from 2002, 200713, 2010A and 2010B Refunding ; however the 2002 debt was refunded with the 2010B issue and will be called in 2011. The P.I.R. fund has completed substantial projects over the last three years totaling over $4 million. This pace is expected to slow somewhat into the future with scheduled projects for 2012 totaling $1,995,000 and future projects in the years 2013-2016 totaling over $7.6 million. Projects scheduled for 2012 include central Hopkins reclamation project among several neighborhoods (see project 01-CIP-S101 for details), citywide concrete alley replacement, 2nd Ave S berm replacement and planning, design of the railroad quiet zone. The funding is provided for these projects by special assessments, $900,000 and PIR/Bonding, $1,095,000 for a total project estimated at $1,995,000. In the years 2012-2016 as mentioned above, the city has an aggressive residential street improvement schedule planned, in addition to major improvements to County Road 61 — Shady Oak Road, all of which will require bonding in 2012, 2014 and 2016 to fund these projects. 19 • MUNICIPAL STATE AID FUND Funding for municipal state aid road projects comes from state MSA funding and is drawn down as projects are done. State funding is not sufficient for current planned projects as a significant draw was made on existing funds for the Co Rd 3 — Phase I project. This draw totaled $3,243,793 of which $2,496,585 has been paid from available allotments and $747,208 will come from future allotments as they become available in the years 2012 and forward. In addition in the queue is a request for $950,956 for the Minnetonka Mills Rd project. These funds will be released once the Co Rd 3 funds are fully drawn down. We have yet to request MSA funds for the 5th Ave S project but once the project has been finaled this project will also be in the queue for state reimbursement. This will push back receipt of funds for other eligible MSA funded projects; however those project requests will be placed in the queue for future allotment payments. Currently there is one MSA project scheduled for 2012 and one for 2014. In 2012 plans are to upgrade signals at Mainstreet & I I 1 Ave and in 2014-2015 the County Road 61, Shady Oak Road project that involves the cities of Hopkins and Minnetonka, Hennepin County and the State will be done. The project is in the planning stages and has a tentative scheduled construction start date of 2014. Hopkins share of the project currently estimated at $5 million of which $1.3 million is budgeted. The remaining $3.7 million is right-of-way acquisition costs for which we currently have no funding. We continue to work with Hennepin County and the City of Minnetonka to develop funding • for this project. CAPITAL IMPROVEMENT FUND Funding for these improvements comes from a general tax levy that was implemented in 2005 at $25,000. In 2010 due budget constraints as a result of the governor's MVHC unallotment used the 2010 levy amount to help balance the 2010 budget, however the levy was reinstated for 2011 at $100,000 and is budget at $125,000 for 2012. Projects scheduled in 2012 total $380,050 include carpet replacement in the Stages Theater offices at the Arts Center, HVAC upgrade at the Activity Center and replacement of the air conditioning system in the City Hall server room. PARK IMPROVEMENT FUND The source of funding for this fund is development fees charged to developers for park development. Future funds are dependent on future development and redevelopment in the city. Projects scheduled for 2012 total $163,000 and include Valley Park play equipment, re -roofing of three park buildings in various parks, Cottageville Park play equipment, miscellaneous park improvements and Skate Park improvements along with the final payment to Minnetonka on the Shady Oak Beach play area renovations. In 2007 the redevelopment of the North Annex property by Opus has generated over $330,000 in park dedication fees and the Marketplace II condominium project has 20 generated $54,000 in developer park dedication fees. Additional development projects in the planning stages are anticipated to bring in additional funds within the next 2-3 years. The Park Board spent considerable time soliciting resident input on city parks and developed a long-range plan for the city's park system. This plan is the basis for future park improvements. WATER FUND Implementing the rates as proposed in the utility master plan along with a bond sale in 2009 provided the funding needed for projects scheduled over the next several years. Projects planned for 2012 include $75,000 in water main improvements done in conjunction with street improvements, $95,000 for meter replacements and $20,000 for an emergency connection to the City of Edina. The public works facility improvement project annual transfer of $45,000 has been transferred to the Storm Sewer Utility fund for the years 2012-2023. As established by the Utility Master Plan completed in 2007 annual incremental increases are planned for the next 17 years. Water rates will increase in 2012, however we are in the process of updating the utility master plan and specific rates are not known at the time of the CIP printing, however will be in line with the current plan. 0 SANITARY SEWER FUND Implementing the rates as proposed in the utility master plan along with transfers from the storm sewer fund and bond sales in 2009 and 2011 will provide the funding needed for projects scheduled over the next 10 years. Projects planned for 2012 include $100,000 in sewer main improvements done in conjunction with street improvement projects and $15,000 in Lift Station maintenance. In addition to the scheduled capital expenditures, the Metropolitan Waste Control Commission is projecting annual increases in its disposal charges to local governments. The public works facility improvement project annual transfer of $50,000 has been transferred to the Storm Sewer Utility fund for the years 2012-2023. As established by the Utility Master Plan completed in 2007 annual incremental increases are planned for the next 17 years. Sewer rates will increase in 2012, however we are in the process of updating the utility master plan and specific rates are not known at the time of the CIP printing, however will be in line with the current plan. STORM SEWER FUND The storm sewer utility issued bonds in 2003 to help cover infrastructure costs that were incurred prior to 2003. The current revenues and working capital balance will cover the projected operating and capital costs over the next several years. 21 Projects scheduled for 2012 include $100,000 in storm sewer improvements done in conjunction with street improvement projects, $18,000 in storm drainage system maintenance and $250,000 in storm water improvements in Cottageville Park. The public works facility improvement project will cost the storm sewer enterprise $25,000 a year for twenty years (2004-2023). In addition beginning in 2012 the Storm Sewer Utility fund will absorb the public works facility transfers for both the water fund ($45,000) and the sewer fund ($50,000) for a total increased cost of $95,000. The most recent rate increase pursuant to the 2007 Utility Master Plan was done in 2009. This rate increase is expected to support the storm sewer system well into the future and currently no additional rates increases are proposed. PAVILION FUND The Pavilion Fund was added to the CIP in 2006 to provide for future improvements that will be needed as this facility ages. As an Enterprise Fund capital items are usually funded within the fund but due to several large capital improvements over the past few years this fund while meeting its operational needs does not currently have adequate financial resources to meet future capital needs. Some of the improvements recently completed were done at the request of major leaseholders of the facility and are being paid by those leaseholders through long-term lease arrangements. This facility built in 1990 is starting to need repairs and replacement to areas that are heavily used; projects scheduled for 2012 include $38,000 for bleacher heating replacement and $15,000 for ice resurfacer water heating system replacement. As part of the 2012 budget process funding of these Pavilion capital needs will need to be addressed as well as future infrastructure needs which will continue to increase as the building ages and facility use remains in high demand. TAX INCREMENT FINANCING FUNDS Considering all tax increment districts, as a whole cash on hand, projected increments and loan repayments are sufficient to cover TIF project expenditures. The state has provided municipalities with a pooling tool to accommodate short-term deficiencies within the districts. The city will be allowed to pool the districts tax increment revenues to cover outstanding debt. Currently none of the city's districts are projected to have shortfalls. 0 22 • • Cash Flow Statements 23 0 24 PARK CAPITAL IMPROVEMENTS FUND (301) 06128/2011 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 Working Capital Beginning Year 246,523 232,628 160,955 80,564 15,370 (80,476) (81,281) Revenues: Interest 1,520 2,326 1,610 806 154 (805) (2,438) Dedication fees 0 0 80,000 0 0 0 0 Joint Rec refunds Donations - general 1,000 1,000 1,000 1,000 1,000 Donations - benches Total Revenues 2,520 3,326 82,610 1,806 1,154 (805) (2,438) Expenditures: C.I.P. Projects 16,414 75,000 156,000 60,000 90,000 0 0 Skate Park commitment 7,000 7,000 7,000 Total Expenditures 16,414 75,000 163,000 67,000 97,000 0 0 Working Capital Year End 232,628 160,955 80,564 15,370 (80,476) (81,281) (83,720) 0 24 06/2812011 CAPITAL IMPROVEMENTS FUND (305) r; • 25 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 Working Capital Beginning Year 235,882 221,836 308,105 56,136 181,697 272,514 400,239 Revenues: Miscellaneous 5,544 Interest 1,454 2,218 3,081 561 1,817 2,725 20,012 Federal Stimulus Funds 75,000 Transfers In from General Fund Tax Levy 0 100,000 125,000 125,000 125,000 125,000 125,000 Total Revenues 81,998 102,218 128,081 125,561 126,817 127,725 145,012 Expenditures: Pavilion Projects C.I.P. Projects 96,044 15,950 380,050 0 36,000 0 391,000 Transfer to General Fund Total Expenditures 96,044 15,950 380,050 0 36,000 0 391,000 Working Capital Year End 221,836 308,105 56,136 181,697 272,514 400,239 154,251 r; • 25 06/28/2011 (2) Excelsior Blvd Streetscape (3) A/R of $1,698,163 is due from MnDOT and will be sent as funds become available. This is not shown on the schedule. Total funds to be received total $4,194,748 2010 - 5th St from 11th Ave S to Corporate limits - reconstruction 2011 -none 2012 - Mainstreet Signal Upgrade 2014 - Cc Rd 61 Shady Oak Road 2015 - Cc Rd 61 Shady Oak Road 2016 - Cc Rd 3 - ($700,000), Sixth St S (11 th-12th Ave S) - ($400,000) • (3) Project MUNICIPAL STATE AID FUND (302) Paid Balance State Aid Funds due City Total Actual Projected Projected Projected Projected Projected Projected 747,207.89 2010 2011 2012 2013 2014 2015 2016 Total Working Capital Beginning Bal 811817 1,303,108 1.705,760 1,837,817 2,221,195 558,407 173,992 Revenues: State MSA Funds, projects 347,792 365,000 365,000 State MSA Funds, Cc Rd 3 (3) 365,134 389,621 365,000 365,000 17,208 Interest Earnings 10,925 13,031 17,058 18,378 22,212 5,584 6,960 Hennepin County - Blake Sidewalks 117,991 Hennepin County (2) Total Revenues 494,050 402,652 382,058 383,378 387,212 370,584 371,960 Expenditures: CIP State Aid Projects 4,759 0 250,000 0 2,050,000 755,000 1,100,000 Total Expenditures 4,759 0 250,000 0 2,050,000 755,000 1,100,000 Working Capital Ending Balance 1,303,108 1,705,760 1,837,817 2,221,195 558,407 173,992 (554,049) includes cash, interest rcvbl, 8 A/P Cash Balance 12/31120XX 1,301,616 Cash Balance 61912011 1,689,580 ESTIMATED Cash Balance 12/31/20XX 1,821,638 2,205,016 542,228 157,812 (570,229) (2) Excelsior Blvd Streetscape (3) A/R of $1,698,163 is due from MnDOT and will be sent as funds become available. This is not shown on the schedule. Total funds to be received total $4,194,748 2010 - 5th St from 11th Ave S to Corporate limits - reconstruction 2011 -none 2012 - Mainstreet Signal Upgrade 2014 - Cc Rd 61 Shady Oak Road 2015 - Cc Rd 61 Shady Oak Road 2016 - Cc Rd 3 - ($700,000), Sixth St S (11 th-12th Ave S) - ($400,000) • (3) Project Total Due Paid Balance State Aid Funds due City Total From State To Date Due 5131111 Excelsior Blvd 5.408.756.28 3.243,792.74 2.496,584.85 747,207.89 Minnetonka Blvd 1,231.889.51 950.955.56 950,955.56 5th Street South (not finaled) Total 6.640,645.79 4,194.748.30 2,496,584.85 1,698,163.45 63.17 is RM Cash Flow Analysis 0 Working Capital Beginning Year Revenues: Special Assessment Revenues (1) Refunds & Reimbursements Interest Transfers In Bond Proceeds Total Revenues Expenditures: C.I.P. Projects C.I.P. Projects - Special Assm Transfers for SA Debt collected thru Assm Debt Service Transfers - 1999D Debt Service Transfers - 2002B Debt Service Transfers - 2007B Debt Service Transfers - 2010A - Impry Debt Service Transfers - 2010B - Rfdg Debt Service Transfers - 2012 debt ($1M) Debt Service Transfers - 2014 debt ($1.5M) Total Expenditures Working Capital Year End 1) Includes current, delinquent and penalties ( s Total Projects Scheduled (CIP & SA) • P.I.R. FUND (501) 06/28/2011 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 (31,817) 1,814,430 234,777 1,347,939 (515,995) 1,452,283 95,818 455,681 718,900 593,825 618,500 544,100 643,500 687,900 70,623 1,241 8,165 1,056 6,066 (2,322) 6,535 431 631 2,652,802 2,800,000 3,000,000 1,700,000 3,180,978 727,065 3,394,881 624,566 3,541,778 650,035 2,388,331 1,204,612 1,091,600 1,095,000 1,225,000 708,000 750,000 1,150,000 964,407 900,000 950,000 552,000 850,000 900,000 58,219 71,900 71,900 71,900 71,900 71,900 71,900 71,900 120,592 156,600 156,600 156,600 156,600 156,600 58,219 58,219 85,000 85,000 85,000 85,000 93,000 93,000 1,334,731 2,306,718 2,281,719 2,488,500 1,573,500 2,006,500 2,456,500 1,814,430 234,777 1,347,939 (515,995) 1,452,283 95,818 27,650 1,204,612 2,056,007 1,995,000 2,175,000 1,260,000 1,600,000 2,050,000 27 WATER FUND - WORKING CAPITAL PROJECTION 06/28/2011 • 28 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 • Working Capital Beginning Year 1,113,716 (268,206) 404,223 464,497 363,376 514,036 638,202 Revenues: Operating Revenues 1,245,063 1,401.200 1,445,400 1,474,600 1,503,800 1,540,300 1,576,800 Other 98,090 110,264 30.000 30,000 30,000 30,000 30,000 Interest 0 0 8,708 8,169 5,696 6,199 8,361 Bond Issuance 500,000 Total Revenues 1,343,153 2,011,464 1,484,108 1.512,769 1,539,496 1,576,499 1,615,161 Expenditures: Operation Expense 908,810 906.310 937.709 970,265 1,004,024 1,039,033 1,075,341 Loss on disposal of asset 340 Other Exp - int on current bonds 59163 0 Other Exp - int on refunded bonds 18,075 14,825 11,475 7,587 2,700 Other Exp - int on 2009 bonds 27,150 26,300 25,350 24,225 22,850 21,350 Other Exp - int on 2011 bonds 17,500 25,000 24,000 23,000 21,750 20.500 Equipment Replacement Items 0 0 134,800 0 21,000 0 Water System Maintenance Capital improvements 711,790 170,000 190,000 208,000 80,000 90,000 301,000 Capital Improvements - PW Bldg Principal Bond payment 1,000,000 Principal Bond payment - refunded 160,000 165,000 170,000 175,000 180,000 Principal Bond pymnt - 2009 debt 40,000 45.000 50,000 50.000 50,000 50,000 Principal Bond pymnt - 2011 debt 20.000 20,000 25,000 25,000 30,000 Capital Lease (PW Facility) (1) 45,000 Total Expenditures 2,725,103 1,339,035 1,423,834 1,613,890 1,388,836 1,452,333 1,498,191 Change in available funds (1,381,950) 672.429 60,274 (101,121) 150,660 124,166 116,970 Inventory change 219 Bond Premium/Discount Exp (191) Working Capital Ending Year (268,206) 404,223 464,497 363,376 514,036 638,202 755,172 (1) Capital Lease moved to Storm Sewer . Rate History 2012 - 2017 financial data was taken truni the Utility Master Plan done by City Engineer 1984 $0.85 1993 $1.05 Notes - 1997 $1.10 Income - 2008 and forward used utility master plan rates (fixture/no surcharge option) 2000 $1.20 2005 $1.40 Per Utility Master Plan (10107) 2008 $1.65 2009 $1.86 2010 $1.90 2011 $1.94 - -nt t increased 2012 $1.98 2013 $2.02 2014 $2.06 Projected rate 2015 $2.11 ncreases 2016 $2.16 2017 $2.21 • 28 • U Working Capital Beginning Year Revenues: Operating Revenues Other Interest Bond Issuance Total Revenues Expenditures: Operation Expense MWCC Charges (3% inflation) Interest Expense - 2009 Debt Interest Expense - 2011 Debt Equipment Replacement Items Capital Improvements Principal Bond payment (2009) Principal Bond payment (2011) Capital Lease (PW Facility) (1) Total Expenditures Change in available funds Inventory change Bond Premium/Discount Exp Working Capital Ending Year (1) Capital Lease moved to Storm Sewei Rate History 1983 $1.50 1989 $1.75 1991 $2.00 1993 $2.50 1999 $2.25 Rate DECREASE 2006 $2.50 rate increase Per Utility Master Plan (10107) 2008$2.70 2009$3.10 2010$3.40 2011 $3.70 - ac 3.60 2012$4.00 2013$4.30 projected rate 2014$4.60 increases 2015$4.90 2016$5.00 2017$5.25 SEWER FUND - WORKING CAPITAL PROJECTION 06/28/2011 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 410,089 79,006 844,693 811,230 863,860 944,841 1,111,850 1,795,043 2,109,000 2,280,000 2,451,000 2,622,000 2,793,000 2,850,000 17,542 23,000 23,000 20,000 20,000 20,000 20,000 2,256 23,967 22,270 27,596 33,415 32,767 36,885 800,000 1,814,841 2,955,967 2,325,270 2,498,596 2,675,415 2,845,767 2,906,885 513,550 1,149,287 36,376 0 397,360 50,000 2,146,573 (331,732) 680 (31) 79,006 693,479 715,749 738,762 1,288,051 1,365, 334 1,447,254 33,750 32,650 31,450 25,000 40,000 38,500 0 0 0 100,000 115,000 100,000 50,000 60,000 60,000 30,000 30,000 2,190,280 2,358,733 2,445,966 765,687 (33,463) 52,630 762,545 787,123 812,526 1,534,089 1,626,135 1,723,703 30,100 28,450 26,575 37,000 35,250 33,500 35,700 6,800 33,600 100,000 100,000 260,000 60,000 60,000 65,000 35,000 35,000 40,000 2,594,434 2,678,758 2,994,904 80,981 167,009 (88,019) 844,693 811,230 863,860 944,841 1,111,850 1,023,831 2009 - 2017 financial data was taken from the Utility Master Plan done by City Engineer Notes - Income - 2008 and forward used utility master plan rates (no fixture option) 29 06/28/2011 STORM SEWER FUND - WORKING CAPITAL PROJECTION 30 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 Working Capital Beginning Year 863,094 1,103,820 1,399,477 1.450,999 1,741,894 1,838,671 2,153,228 Revenues: Operating Revenues 796,644 802,140 802,140 802,140 802,140 802,140 802,140 Other 7,245 5,000 5,000 5,000 5,000 5,000 5,000 Interest 1,362 5,324 13,670 20,500 26,486 47,661 62,633 Bond Issuance 866,250 Total Revenues 1,671.501 812,464 820,810 827,640 833,626 854,801 869,773 Expenditures: Operation Expense 167,965 179,637 185,187 190,912 194,730 198,625 202,597 Bond Interest -existing bonds 53,794 32,345 30,626 28,758 26,808 24,744 22,534 Bond Interest- refunded bonds 12,825 10,475 8,075 5,312 1,875 Capital Outlay (per ERP) 0 0 0 0 0 0 0 Capital Improvements 189,951 117,000 368,000 129,000 330,000 130,000 131,000 1999 Principal Bond payment 715,000 2001 Principal Bond payment 225,000 2003 Principal Bond payment 55,000 55,000 55,000 60,000 60,000 65,000 65,000 Capital Lease - PW Facility (1) 25,000 120,000 120,000 120,000 120,000 120,000 120,000 Total Expenditures 1,431,710 516,807 769,288 536,745 736.850 540,244 541,131 Change in available funds 239,791 295,657 51,522 290,896 96,776 314,557 328.642 Inventory change 975 Bond Premium/Discount Exp (net) (40) Working Capital Ending Year 1,103,820 1,399,477 0 1,450,999 1,741,894 1,838,671 2,153,228 2,481,870 (1) In 2011 this includes Water, Sewer & Storm Sewer transfers Rate History (per month) 1989 $4.75 per quarter 2009 - 2017 financial data was taken from the Utility Master Plan done by City Engineer 1991 $6.00 per quarter 1992 $2.50 1993 $3.00 1998 $3.20 1999 $4.00 2006 $4.50 2009 $5.00 30 • • 31 PAVILION - ICE ARENA - WORKING CAPITAL PROJECTIONS 0612812011 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 Working Capital Beginning Year (67,341) (55,254) (30,881) (42,983) 361 (118,067) (152,278) Revenues: Operating Revenues 318,763 334,701 351,436 369,008 387,458 406,831 427,173 Leases 38,000 38,000 38,000 38,000 38,000 38,000 38,000 Other 6,828 12,000 12,000 13,000 13,000 13,000 14,000 Donations (bleacher heating) 10,000 Interest 2,055 Total Revenues 365,646 384,701 411,436 420,008 438,458 457,831 479,173 Expenditures: Operation Expense 330,416 340,328 350,538 361,054 371,886 383,043 394,534 Capital Outlay - - - - 185,000 - - Capital Improvements - - 53,000 - - 109,000 135,000 Payment on Interfund Loan 23,143 20,000 20,000 15,609 - - - Total Expenditures 353,559 360,328 423,538 376,663 556,886 492,043 529,534 Change in available funds 12,087 24,373 (12,102) 43,345 (118,428) (34,211) (50,361) Working Capital Ending Year (55,254) (30,881) (42,983) 361 (118,067) (152,278) (202,639) • • 31 COMMUNICATIONS (Cable TV) - WORKING CAPITAL PROJECTIONS 06/28/2011 0 • 32 Actual Projected Projected Projected Projected Projected Projected 2010 2011 2012 2013 2014 2015 2016 Working Capital Beginning Year 399,094 401,753 412,087 445,070 475,858 504,351 530,448 Revenues: Franchise Fees 200,739 200,000 200,000 200,000 200,000 200,000 200,000 Interest 2,945 4,018 4,121 4,451 4,759 5,044 15,913 Total Revenues 203,684 204,018 204,121 204,451 204,759 205,044 215,913 Expenditures: Expense 88,710 81,764 84,217 86,743 89,346 92,026 94,787 Transfer Out 86,920 86,920 86,920 86,920 86,920 86,920 86,920 Capital Outlay 25,395 25,000 Total Expenditures 201,025 193,684 171,137 173,663 176,266 178,946 181,707 Change in available funds 2,659 10,334 32,984 30,787 28,493 26,097 34,207 Working Capital Ending Year 401,753 412,087 445,070 475,858 504,351 530,448 564,655 • 32 r Five Year Project Summaries 33 City of Hopkins, MN CAPITAL IMPR0FEMEN T PLAN 2012 ,Ilya 2016 PROJECTS BY YEAR Project Name Department Project # Project Cost 2012 Activity Center HVAC Upgrade Activity Center 08-CIP-ACO20 1 355,000 Replace Office Carpet - HCA Stages Theatre Arts Center 08-CIP-AR006 n/a 15,050 City Hall Server Room Air Conditioning City Hall Administration 17-C/P-CH036 n/a 10,000 Block 64 Redevelopment Project Development 06-CIP-D404 n/a 5,500,000 Blake Corridor Redevelopment Development 09-CIP-D406 n/a 5,000,000 Pavilion Arena Bleacher Heating Replacement Pavilion 08-C/P-P008 n/a 38,000 Ice Resufacer Water Heating System Replacement Pavilion 09-CIP-P316 n/a 15,000 Shady Oak Beach Community Play Area Public Works: Parks 07-C/P-P279 n/a 21,000 Play Equipment - Valley Park Public Works: Parks 08-C/P-PO75 n/a 65,000 Miscellaneous Park Improvements Public Works: Parks 10-C/P-PO77 n/a 10,000 Park Building Re -Roofing Public Works: Parks 11-C/P-PO 18 n/a 15,000 Play Equipment - Cottageville Park Public Works: Parks 77-CIP-PO79 n/a 45,000 Residential Street Improvements Public Works: Streets/Traffic 07-C/P-5707 n/a 1,800,000 Residential Street Improvements -Utilities Public Works: Streets/Traffic 01-C/P-5102 n/a 275,000 Citywide Concrete Alleys Public Works: Streets7Traffic 07-CIP-5103 n/a 135,000 Plan, Design and Implement Railroad Quiet Zone Public Works: Streets/Traffic 11-CIP-S 720 n/a 30,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 77-CIP-5721 3 250,000 • Storm Water Improvements - Cottageville Park Public Works: Streets/Traffic 11-CIP-S723 n/a 250,000 2nd Avenue S Berm Rehab Public Works: Streets/Traffic 77-CIP-S 724 n/a 30,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 07-CIP-0002 n/a 18,000 Meter Replacement Public Works: Utilities 08-CIP-0000 n/a 95,000 Sanitary Sewer Lift Station Maintenance Public Works: Utilities 08-CIP-0009 n/a 15,000 Emergency Water Connection with Edina Public Works: Utilities 71-CIP-0017 2 20,000 Total for 2012 14,007,050 20�J Activity Center Caf6 on 14th Activity Center 09-CIP-AC032 n/a 90,000 Redevelopment, East Excelsior Boulevard Development 01-CIP-D407 n/a 2,000,000 Play Equipment - Oakes Park Public Works: Parks 08-CIP-PO76 n/a 60,000 Residential Street Improvements Public Works: Streets/Traffic 07-CIP-S707 n/a 1,800,000 Residential Street Improvements -Utilities Public Works: Streets/Traffic 01-CIP-5102 n/a 290,000 Plan, Design and Implement Railroad Quiet Zone Public Works Streets[Traffic 11-CIP-S 720 n/a 225,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 77-CIP-5721 3 50,000 Blake Road Streetscape Public Works: Streets/Traffic 11-CIP-S 722 n/a 200,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 07-CIP-0002 n/a 19,000 Meter Replacement Public Works: Utilities 08-CIP-0000 n/a 95,000 Emergency Chlorine Shut Off Valves Public Works: Utilities 08-CIP-0008 n/a 33,000 Total for 2013 4,862,000 2014 Replace Carpet - Activity Center Rooms Activity Center 08-CIP-AC075 n/a 36,000 • Play Equipment - Park Valley Public Works: Parks 08-CIP-POIO n/a 45,000 Play Equipment - Hilltop Park Public Works: Parks 08-CIP-PO74 n/a 45,000 i c(7nesdav, Jum 9. 2011 34 Project Name Department Project # Priority Project Cost Residential Street Improvements Public Works: Streets/Traffic 01-C/P-5101 n/a 1,000,000 Street Improvements --Utilities Public Works: Streets/Traffic 01-C/P-5102 n/a 290,000 •Residential Citywide Concrete Alleys Public Works: Streets/Traffic 01-C/P-5103 n/a 65,000 County Road 61 (Shady Oak Road) Public Works: Streets/Traffic 01-C/P-5106 n/a 8,200,000 Highway 7 and 5th Ave North - Signal Replacement Public Works: Streets/Traffic 10-C/P- 5120 3 445,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-C/P-S121 3 50,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 20,000 Storm Water Management Projects Public Works: Utilities 01-C/P-0003 n/a 200,000 06-C/P-S118 Total for 2014 250,000 Public Works: Streets/Traffic 10,396,000 2015 50,000 Public Works: Utilities 01-C/P-0002 n/a Pavilion Mez. Roof Replacement (North Section) Pavilion 07-C/P-P315 n/a 40,000 Pavilion Gas Fired Rooftop Furnace Pavilion 09-C/P-PO25 n/a 9,000 Pavilion Evaporator Condenser Replacement Pavilion 09-C/P-PO36 n/a 60,000 Residential Street Improvements Public Works: Streets/Traffic 01-C/P-5701 n/a 1,100,000 Residential Street Improvements—Utilities Public Works: Streets/Traffic 01-C/P-5102 n/a 300,000 County Road 61 (Shady Oak Road) Public Works: Streets/Traffic 01-C/P-5106 n/a 12,250,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-C/P-S121 3 50,000 Light Rail Transit Stations (2) Public Works: Transportation 01-C/P-5502 n/a 150,000 Eighth Avenue LRT Corridor Public Works: Transportation 01-C/P-5503 n/a 200,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 20,000 Depot Recreation Area Recreation 10-CIP-RO02 2 500,000 Total for 2015 14,679,000 2016 Replace Gynmasium Roof - Activity Center • Activity Center - Raspberry Room Roof Replacement City Hall Lobby Upgrade Replace Carpet and Apparatus Floor Finish - FD Pavilion Overhead Door Improvement Pavilion Indoor Turf Replacement Replace Carpet - Police Station Residential Street Improvements Residential Street Improvements --Utilities County Road 3 Sixth Street South (11th to 12th Avenue South) Parking Lots - Lot 200 Mainstreet Traffic Signal Upgrades Storm Drainage System Maintenance - Alley Repairs Lift Station # 4 St. Louis Park Emergency Connection GRAND TOTAL • Activity Center 08-CIP-AC018 n/a 105,000 Activity Center 08-CIP-ACO24 n/a 80,000 City Hall Administration 09-C/P-CH030 n/a 110,000 Fire 08-CIP-FDO19 n/a 56,000 Pavilion 07-C/P-P314 n/a 40,000 Pavilion 10-C/P-P319 n/a 95,000 Police 08-C/P-PDO16 n/a 40,000 Public Works: Streets/Traffic 01-C/P-5101 n/a 1,900,000 Public Works: Streets/Traffic 01-C/P-5102 n/a 300,000 Public Works: Streets/Traffic 01-C/P-5104 n/a 2,300,000 Public Works: Streets/Traffic 01-C/P-5504 n/a 500,000 Public Works: Streets/Traffic 06-C/P-S118 n/a 250,000 Public Works: Streets/Traffic 11-C/P-5121 3 50,000 Public Works: Utilities 01-C/P-0002 n/a 21,000 Public Works: Utilities 08-C/P-UOO1 n/a 160,000 Public Works: Utilities 08-C/P-UO10 n/a 211,000 Total for 2016 6,218,000 35 50,162,050 Wednesday, June 29, 2011 City of Hopkins, MN CAP17AL IMPRO FEMENT PLAN 2012 ti-„ 2016 DEPARTMENT SUMMARY Department 2012 2013 2014 2015 2016 Total Activity Center 355,000 90,000 36,000 185,000 666,000 Arts Center 15,050 15,050 City Hall Administration 10,000 110,000 720,000 Development 10,500,000 2,000,000 72,500,000 Fire 56,000 56,000 Pavilion 53,000 109,000 135,000 297,000 Police 40,000 40,000 Public Works: Parks 156,000 60,000 90,000 306,000 Public Works: StreetslTraffic 2,520,000 2,565,000 10,050,000 13,700,000 5,300,000 34,735,000 Public Works: Transportation 350,000 350,000 Public Works: Utilities 398,000 147,000 220,000 20,000 392,000 1,777,000 Recreation 500,000 500,000 TOTA1_ 14,007,050 4,862,000 10,396,000 14,679,000 6,218,000 50,162,050 36 Wc(hicsday. June 29. 2011 101 • 0 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2012 thru 2016 PROJECTS BY DEPARTMENT Department Project# Priority 2012 2013 2014 2015 2016 Total Activity Center J Replace Carpet - Activity Center Rooms 08-C/P-AC075 n/a 36,000 36,000 Replace Gynmasium Roof -Activity Center 08-CIP-AC078 n/a 105,000 705,000 Activity Center HVAC Upgrade 08-CIP-ACO20 1 355,000 355,000 Activity Center - Raspberry Room Roof Replacement 08-C/P-ACO24 n/a 80,000 80,000 Activity Center Cafe on 14th 09-CIP-AC032 n/a 90,000 90,000 Activity Center Total 355,000 90,000 36,000 185,000 666,000 Arts Center i Replace Office Carpet - HCA Stages Theatre 08-C/P-AR006 n/a 15,050 75,050 Arts Center Total 15,050 15,050 City Hall Administration City Hall Lobby Upgrade 09-CIP-CH030 n/a 110,000 110,000 City Hall Server Room Air Conditioning 11-C/P-CH036 n/a 10,000 10,000 City Hall Administration Total 10,000 110,000 120,000 Development J Redevelopment, East Excelsior Boulevard 01-CIP-D407 n/a 2,000,000 2,000,000 Block 64 Redevelopment Project 06-C/P-0404 n/a 5,500,000 5,500,000 Blake Corridor Redevelopment 09-C/P-D406 n/a 5,000,000 5,000,000 Development Total 10,500,000 2,000,000 12,500,000 Fire -` Replace Carpet and Apparatus Floor Finish - FD 08-CIP-FD019 n/a 56,000 56,000 Fire Total 56,000 56,000 Pavilion Pavilion Overhead Door Improvement 07-CIP-P374 n/a 40,000 40,000 Pavilion Mez. Roof Replacement (North Section) 07-CIP-P315 n/a 40,000 40,000 Pavilion Arena Bleacher Heating Replacement 08-CIP-P008 n/a 38,000 38,000 Pavilion Gas Fired Rooftop Furnace 09-CIP-PO25 n/a 9,000 9,000 Pavilion Evaporator Condenser Replacement 09-C/P-PO36 n/a 60,000 60,000 Ice Resufacer Water Heating System Replacement 09-CIP-P376 n/a 15,000 75,000 Pavilion Indoor Turf Replacement 10-CIP-P379 n/a 95,000 95,000 Pavilion Total 53,000 109,000 135,000 297,000 Police i Replace Carpet - Police Station 08-CIP-PD016 n/a 40,000 40,000 37 H ediw«Iur../unr 29. 2011 Department Project# PrioritN 2012 2013 2014 2015 2016 Total Police Total 40-onoi 40,000 Public Works: Parks Shady Oak Beach Community Play Area 07-CIP-P219 n/a 21,000 27,000 Play Equipment - Park Valley 08-C/P-PO70 n/a 45,000 45,000 Play Equipment - Hilltop Park 08-CIP-P014 n/a 45,000 45,000 Play Equipment- Valley Park 08-CIP-P015 n/a 65,000 65,000 Play Equipment - Oakes Park 08-C/P-P016 n/a 60,000 60,000 Miscellaneous Park Improvements 70-CIP-PO77 n/a 10,000 70,000 Park Building Re -Roofing 11-CIP-P018 n/a 15,000 15,000 Play Equipment - Cottageville Park 11-C/P P079 n/a 45,000 45,000 Public Works: Parks Total 156,000 60,000 90,000 306,000 Public Works: Streets/Traffic Residential Street Improvements 01-CIP-5701 n/a 1,800,000 1,800,000 1,000,000 1,100,000 1,900,000 7,600,000 Residential Street Improvements -Utilities 01-C/P-5102 n/a 275,000 290,000 290,000 300,000 300,000 7,455,000 Citywide Concrete Alleys 07-C/P-5103 n/a 135,000 65,000 200,000 County Road 3 07-CIP-S704 n/a 2,300,000 2,300,000 County Road 61 (Shady Oak Road) 07-CIP 5106 n/a 8,200,000 12,250,000 20,450,000 Sixth Street South (11th to 12th Avenue South) 07-CIP-5504 n/a 500,000 500,000 Parking Lots - Lot 200 06-CIP-5718 n/a 250,000 250,000 Highway 7 and 5th Ave North - Signal Replacement 10-CIP- 5720 3 445,000 445,000 Plan, Design and Implement Railroad Quiet Zone 77-C/P-5120 n/a 30,000 225,000 255,000 Mainstreet Traffic Signal Upgrades 11-CIP-5121 3 250,000 50,000 50,000 50,000 50,000 450,000 Blake Road Streetscape 11-CIP-S 722 n/a 200,000 200,000 2nd Avenue S Berm Rehab 77-CIP-SI24 n/a 30,000 30,000 Public Works: Streets/Traffic Total 2,520,000 2,565,000 10,050,000 13,700,000 5,300,000 34,135,000 Public Works: Transportation Light Rail Transit Stations (2) 01-CIP-5502 n/a 150,000 150,000 Eighth Avenue LRT Corridor 01-CIP-5503 n/a 200,000 200,000 Public Works: Transportation Total 350,000 350,000 Public Works: Utilities Storm Drainage System Maintenance - Alley Repairs 01-C/P-0002 n/a 18,000 19,000 20,000 20,000 21,000 98,000 Storm Water Management Projects 01-CIP-0003 n/a 200,000 200,000 Meter Replacement 08-CIP-0000 n/a 95,000 95,000 790,000 Lift Station # 4 08-CIP-0001 n/a 160,000 760,000 Emergency Chlorine Shut Off Valves 08-C/P-0008 n/a 33,000 33,000 Sanitary Sewer Lift Station Maintenance 08-CIP-0009 n/a 15,000 75,000 St. Louis Park Emergency Connection 08-CIP-0010 n/a 211,000 277,000 Storm Water Improvements - Cottageville Park 77-CIP 5123 n/a 250,000 250,000 Emergency Water Connection with Edina 77-CIP-0017 2 20,000 20,000 Public Works: Utilities Total 398,000 147,000 220,000 20,000 392,000 1,177.000 Recreation Depot Recreation Area 70-CIP-RO02 2 500,000 500,000 Recreation Total 500,000 500,000 38 11 cdncedat..lnnr 29, 2011 Department GRAND TOTAL U • Project# Priority- 2012 2013 2014 2015 2016 Total 14,007,050 4,862,000 10,396,000 14,679,000 6,218,000 50,162,050 39 Wednesday, June 29, 2011 City of Hopkins, MN Source CAPITAL IMPROFF.11ENT PLAN 2012 1I„ -L 2016 FUNDING SOURCE SUMMARY 2012 2013 2014 2015 2016 Total CI- Capital Improvement Fund 380,050 36,000 391,000 807,050 ED - Economic Development Fund 2,000,000 100,000 2,700,000 GU- Other Governmental Units 100,000 6,450,000 11,645,000 1,600,000 19,795,000 MS - Municipal State Aid Streets 250,000 2,050,000 755,000 1,100,000 -4,755,000 PA - Pavilion Fund 53,000 109,000 135,000 297,000 PDF- Park Dedication Fund 156,000 60,000 90,000 306,000 PF - Private Sector Funds 90,000 90,000 PI - PIR/General Obligation Bonds 1,095,000 1,225,000 708,000 750,000 1,250,000 5,028,000 SA - Special Assessment 900,000 950,000 552,000 850,000 900,000 4,752,000 SF - Sanitary Sewer Fund 115,000 100,000 100,000 100,000 260,000 675,000 SU -Storm Sewer Fund 368,000 129,000 330,000 130,000 181,000 7,738,000 TF- Tax Increment Financing 8,500,000 2,000,000 250,000 70,750,000 WF - Water Fund 190,000 208,000 80,000 90,000 301,000 869,000 GRAND "1'0"1'A1, 14,007,050 4,862,000 10,396,000 14,679,000 6,218,000 50,162,050 11 rdneeday. Jaar° 29. 201 / 40 • Source City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2012 thm 2016 PROJECTS BY FUNDING SOURCE Project# Priority 2012 2013 2014 2015 2016 Total Cl - Capital Im rovement Fund Replace Carpet - Activity Center Rooms 08-C/P-AC015 Replace Gynmasium Roof - Activity Center 08-CIP-AC018 Activity Center HVAC Upgrade 08-CIP-ACO20 Activity Center - Raspberry Room Roof Replacement 08-C/P-ACO24 Replace Office Carpet - HCA Stages Theatre 08-C/P-AR006 Replace Carpet and Apparatus Floor Finish - FD 08-CIP-FDO19 Replace Carpet - Police Station 08-CIP-PDO16 City Hall Lobby Upgrade 09-CIP-CH030 City Hall Server Room Air Conditioning 11-C/P-CH036 Cl - Capital Improvement Fund Total 80,000 80,000 ED - Economic Development Fund Sixth Street South (11th to 12th Avenue South) 01-CIP-5504 Block 64 Redevelopment Project 06-CIP-D404 ED - Economic Development Fund Total n/a GU - Other Governmental Units County Road 3 01-CIP-5104 County Road 61 (Shady Oak Road) 01-CIP-5106 Eighth Avenue LRT Corridor 01-CIP-S503 Highway 7 and 5th Ave North - Signal Replacement 10-C/P- S120 Depot Recreation Area 10-CIP-RO02 Blake Road Streetscape 11-CIP-5122 GU - Other Governmental Units Total 110,000 n/a 10,000 MS - Municipal State Aid Streets County Road 3 01-CIP-5104 County Road 61 (Shady Oak Road) 07-CIP-5106 Sixth Street South (11th to 12th Avenue South) 01-CIP-5504 Mainstreet Traffic Signal Upgrades 11-CIP-S121 MS - Municipal State Aid Streets Total n/a PA - Pavilion Fund Pavilion Overhead Door Improvement 07-C/P-P314 Pavilion Mez. Roof Replacement (North Section) 07-C/P-P315 Pavilion Arena Bleacher Heating Replacement 08-CIP-P008 Pavilion Gas Fired Rooftop Furnace 09-CIP-PO25 Pavilion Evaporator Condenser Replacement 09-CIP-PO36 n/a 36,000 36,000 n/a 105,000 105,000 1 355,000 355,000 n/a 80,000 80,000 n/a 15,050 15,050 n/a 56,000 56,000 n/a 40,000 40,000 n/a 110,000 110,000 n/a 10,000 10 m 380,050 36,000 391,000 807,050 n/a 100,000 100,000 n/a 2,000,000 2,000,000 2,000,000 100,000 2,100,000 n/a 1,600,000 1,600,000 n/a 6,150,000 11,045,000 17,195, 000 n/a 100,000 100,000 3 300,000 300,000 2 500,000 500,000 n/a 100,000 100,000 100,000 6,450,000 11,645,000 1,600,000 19,795,000 n/a 700,000 700,000 n/a 2,050,000 755,000 2,805,000 n/a 400,000 400,000 3 250,000 250,000 250,000 2,050,000 755,000 1,100,000 4,155,000 n/a 40,000 40,000 n/a 40,000 40,000 n/a 38,000 38,000 n/a 9,000 9,000 n/a 60,000 60,000 Wednesday, June 29, 2011 41 Source Project# Priorih 2012 2013 2014 2015 2016 Total Ice Resufacer Water Heating System Replacement 09-C/P-P376 n/a 15,000 75,000 Pavilion Indoor Turf Replacement 70-CIP-P379 n/a 95,000 95,000.0 PA - Pavilion Fund Total 53,000 109,000 135,000 297,000 PDF- Park Dedication Fund Shady Oak Beach Community Play Area 01-C/P-P279 n/a 21,000 21,000 Play Equipment - Park Valley 08-C/P-PO70 n/a 45,000 45,000 Play Equipment- Hilltop Park 08-C/P-PO74 n/a 45,000 45,000 Play Equipment - Valley Park 08-C/P-PO75 n/a 65,000 65,000 Play Equipment - Oakes Park 08-C/P-PO76 n/a 60,000 60,000 Miscellaneous Park Improvements 70-C/P-P071 n/a 10,000 10,000 Park Building Re-Roofing 77-C/P-PO78 n/a 15,000 15,000 Play Equipment- Cottageville Park 77-C/P-PO79 n/a 45,000 45,000 PDF- Park Dedication Fund Total 156,000 60,000 90,000 306,000 PF - Private Sector Funds Activity Center Cafe on 14th 09-ClP-AC032 n/a 90,000 90,000 PF - Private Sector Funds Total 90,000 90,000 PI - PIR/General Obligation Bonds Residential Street Improvements 07-C/P-5701 n/a 1,000,000 850,000 500,000 500,000 1,000,000 3,850,000 Citywide Concrete Alleys 07-C1P-S703 n/a 35,000 13,000 48,000 County Road 61 (Shady Oak Road) 07-ClP 5106 n/a 200,000 200,000 Parking Lots - Lot 200 06-C1P-5178 n/a 200,000 200,000 Highway 7 and 5th Ave North - Signal Replacement 70-C/P- 5720 3 145,000 145,000 Plan, Design and Implement Railroad Quiet Zone 77-C/P-S 720 n/a 30,000 225,000 255,000 Mainstreet Traffic Signal Upgrades 11-C1P-S 727 3 50,000 50,000 50,000 50,000 200,000 Blake Road Streetscape 71-CIP-5122 n/a 100,000 100,000 2nd Avenue S Berm Rehab 77-C1P-5724 n/a 30,000 30,000 PI - PIR/General Obligation Bonds Total 1,095,000 1,225,000 708,000 750,000 1,250,000 5,028,000 SA - Special Assessment Residential Street Improvements 07-C/P-S107 n/a 800,000 950,000 500,000 600,000 900,000 3,750,000 Citywide Concrete Alleys 07-C/P-S103 n/a 100,000 52,000 752,000 County Road 61 (Shady Oak Road) 07-CIP-5106 n/a 250,000 250,000 SA - Special Assessment Total 900,000 950,000 552,000 850,000 900,000 4,152,000 SF - Sanitary Sewer Fund Residential Street Improvements-Utilities 07-CIP-5702 n/a 100,000 100,000 100,000 100,000 100,000 500,000 Lift Station # 4 08-C/P-0007 n/a 160,000 760,000 Sanitary Sewer Lift Station Maintenance 08-CIP-0009 n/a 15,000 75,000 SF - Sanitary Sewer Fund Total 115,000 100,000 100,000 100,000 260,000 675,000 SU - Storm Sewer Fund Residential Street Improvements-Utilities 01-C/P-S702 n/a 100,000 110,000 110,000 110,000 110,000 540,000 Storm Drainage System Maintenance - Alley Repairs 07-CIP-0002 n/a 18,000 19,000 20,000 20,000 21,000 98,000 11 irh�, �<1ur. Juir, N. ?Ul1 42 Source Project# Priority 2012 2013 2014 2015 2016 Total Storm Water Management Projects 01-CIP-0003 n/a 200,000 200,000 *Parking Lots - Lot 200 06-C1P-5718 n/a 50,000 50,000 Storm Water Improvements - Cottageville Park 11-C1P-5723 n/a 250,000 250,000 SU - Storm Sewer Fund Total 368,000 129,000 330,000 130,000 181,000 1,138,000 �TF - Tax Increment Financing � Redevelopment, East Excelsior Boulevard 07-C/P-D407 n/a 2,000,000 2,000,000 Light Rail Transit Stations (2) 01-C/P-5502 n/a 150,000 150,000 Eighth Avenue LRT Corridor 07-C1P-5503 n/a 100,000 100,000 Block 64 Redevelopment Project 06-C/P-D404 n/a 3,500,000 3,500,000 Blake Corridor Redevelopment 09-C/P-D406 n/a 5,000,000 5,000,000 TF - Tax Increment Financing Total 8,500,000 2,000,000 250,000 10,750,000 WF - Water Fund Residential Street Improvements --Utilities 01-C/P-S102 n/a 75,000 80,000 80,000 90,000 90,000 415,000 Meter Replacement 08-C/P-0000 n/a 95,000 95,000 790,000 Emergency Chlorine Shut Off Valves 08-C/P-0008 n/a 33,000 33,000 St. Louis Park Emergency Connection 08-CIP-0010 n/a 211,000 211,000 Emergency Water Connection with Edina 17-CIP-0077 2 20,000 20,000 WF - Water Fund Total 190,000 208,000 80,000 90,000 301,000 869,000 GRAND TOTAL 14,007,050 4,862,000 10,396,000 14,679,000 6,218,000 50,162,050 0 43 11'cdncsdm. Junt, ?y. 20/l • Economic Development • 44 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 01-CIP-D401 Project Name Redevelopment, East Excelsior Boulevard Future 2012 thru 2016 Department Development Contact ED Director Type Improvement Useful Life Unassigned Category Economic Development Priority n/a iption Total Project Cost: $2,000,000 side of Excelsior Boulevard from Highway 169 to approximately Blake Road. ment of older commercial area. Based on the adopted redevelopment plan, it would involve commercial, and uses. Identified in the East End Redevelopment Study. Justification Excelsior Boulevard was upgraded in this area, providing for additional property on the north side of the roadway. The buildings in this area are older and no longer the highest and best use for this property. The funding amount is an estimate and will vary depending on the scope and timing of the project. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 2,000,000 2,000,000 Ll Funding Sources Total 2,000,000 2,000,000 2012 2013 2014 2015 2016 Total TF - Tax Increment Financing 2,000,000 2,000,000 Budget Impact/Other • Total 2,000,000 2,000,000 45 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 dirt, 2016 City of Hopkins, MN Project # 06-CIP-D404 Project Name Block 64 Redevelopment Project Future Department Development Contact ED Director Type Improvement Useful Life Calegor� Economic Development Prioritc Na Description I Total Project Cost: $5,500,000 Redevelopment of block between 5th and 6th Avenues, north of Mainstreet, south of 1 st Street North. The current schedule is for construction to start in late 2012. I Justification (Will redevelop older commercial and residential areas. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 5,500,000 5,500,000 Total 5,500,000 5,500,000 Funding Sources 2012 2013 2014 2015 2016 Total ED - Economic Development F 2,000,000 2,000,000 TF - Tax Increment Financing 3,500,000 3,500,000 Total 5,500,000 5,500,000 Budget Impact/Other 46 C7 r� U • Il cdmsdcm. Jm c 2�/. 2011 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 09-CIP-D406 Project Name Blake Corridor Redevelopment Future 2012 thru 2016 Department Development Contact ED Director Type Improvement Useful Life Category Economic Development Priority n/a Description Total Project Cost: $5,000,000 Zedevelopment of properties along the Blake Road Corridor including the Cottageville Park area. Justification Removal of blighted and/or obsolete structures, improve access to transit and improve livability of the area. Expenditures 2012 2013 2014 2015 2016 Total Land Acquisition/Demolition 5,000,000 5,000,000 Total 5,000,000 5,000,000 Funding Sources 2012 2013 2014 2015 2016 Total TF - Tax Increment Financing 5,000,000 5,000,000 Budget Impact/Other is Total 5,000,000 5,000,000 47 Wednesday, June 29, 2011 General Public Buildings 48, • 0 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-AC015 Project Name Replace Carpet - Activity Center Rooms Future 2012 thru 2016 Department Activity Center Contact Facilities Director Type Improvement Useful Life Category Buildings: Activity Center Priority n/a Description Total Project Cost: $36,000 teplace Carpeting in Activity Center Raspberry Rooms, TV/Game Room; hallways. Justification Carpet is 18 years old, worn and requires replacement. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 36,000 36,000 Total 36,E 36,000 Funding Sources 2012 2013 2014 2015 2016 Total Cl - Capital Improvement Fund 36,000 36,000 Budget Impact/Other • TOW 36,000 36,000 49 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 di r, 2016 City of Hopkins, MN Project # 08-CIP-AC018 Project Name Replace Gynmasium Roof - Activity Center Future Description Zeplace existing roofing over gymnasium. I Justification Roof was installed in 1989 and is at the end of its 25 year useful life. Department Activity Center Contact Type Public Works Director 105,000 Improvement Useful Life 25 years Categorc Buildings: Activity Center Priority nia Dotal Project Cost: $105,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 105,000 105,000 Total Funding Sources 2012 105,000 2013 2014 2015 2016 105,000 Total CI - Capital Improvement Fund 105,000 105,000 Total 105,000 105,000 Budget Impact/Other 50 0 • 11("Im sdnr..lunr 9, 2011 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-ACO20 Project Name Activity Center HVAC Upgrade Future 2012 thru 2016 Department Activity Center Contact PW Director Type Improvement Useful Life 20-25 years Category Buildings: Activity Center Priority 1 Urgent Total Project Cost: $355,000 ice existing low pressure steam Boiler with two low pressure Hot Water Boilers. Replace existing AC Rooftop AC for Gymnasium with Gas Heat and AC. Replace existing AC fan oils with Heat and AC fan coils with new enser Units. Replace existing AC unit in Historical Society with Rooftop HVAC unit. Replace existing Steam up unit for Kitchen with Gas fired makeup unit. ;et includes a reduced size makeup unit) cost includes 25,000 Engineering cost and 10% contingency. 2012: Engineering: 25,000 2012: Construction: 300,000 2012: Contingency: 30,000 Justification Existing Low presuujre Steam Boiler is 30 years old (198 1) the supply piping for this Boiler are 60 years old. The supply piping is located in tunnel around the perimiter of the Building. Life of existing steam pipe is a concern. Cost of replacing pipe in a confined space would be costly. Existing Rooftop units for Gymnasium are 24 years old and need replacement. Upgraded system will allow better control of HVAC systems and reduce Energy costs. Existing Kitchen would be modified to meet current regulations. Engineering studv comnleted earlv in 2011 and used to justify costs and needs. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 355,000 355,000 Total 355,000 355,000 Funding Sources 2012 2013 2014 2015 2016 Total Cl - Capital Improvement Fund 355,000 355,000 Total 355,000 355,000 Budget Impact/Other of Major failure of 60 year od steam supply lines is a major concern. Repairs would only be temporary and costly. n Boiler is only source of Heart for Building. Existing Equipment has exceeded its expected life. Wednesday, June 29, 2011 51 CAPITAL IMPROVEMENT PLAN 2012 Ilirit 2016 Department Activity center City of Hopkins, MN Contact PW Director Project # 08-CIP-ACO24 Tc pe Improvement Oseful life Project Name Activity Center - Raspberry Room Roof Replacement Categor�Buildings: Activity Center Future Prioritc n/a Description Total Project Cost: $80,000 Built up asphalt roofing system covering Raspberry Rooms, Craft Room and Hallways at the Activity Center Justification Existing roof was replaced in 1992, Expected life is 25 years. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 80,000 80,000 Total 80,000 80,000 Funding Sources 2012 2013 2014 2015 2016 Total CI - Capital Improvement Fund 80,000 80,000 Total 80,000 80,000 Budget Impact/Other .nspection, repair and upkeep of roofing systems prevent deterioration of interior building structure and damage to nterior components of building. Wcdncsdat', Amc 29. 21111 52 * I *I • CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Activity Center City of Hopkins, MN Contact PW Director Project # 09-CIP-AC032 Type Improvement Useful Life Project Name ActivityCenter Cafe on 14th Category Buildings: Activity Center Future Priority n/a Description Total Project Cost: $90,000 General - The Activity Center Cafe on 14th project is a project aimed at a growing trend among senior centers to reach out to younger audiences such as the baby boom generation. This project will tranform the Activity Center from a traditional senior/community center into a restaurant, gathering place, learning center, and health club - that happens to have customers who may range in age from 50-90 (but still open to all ages). The original model of a Cafe community facility was developed in Chicago and has been successfully implimented in other cities. The capital improvement portion of this new project involves utilizing the existing kitchen in a cafe fashion that would serve food in the morning until after lunch to people seated in what is currently the lounge area. • Detailed - The project involves opening up a portion of the wall between the kitchen and lounge area and building a wall along what is now the serving line area of the kitchen. This new wall will close off the kitchen on the gym side and create a hallway for entrance and exit from the gym's West doors. The kitchen needs to be redesigned from it's previous school cafateria layout to a smaller "cafe" kitchen area with the appropriate equipment to serve breakfasts and sandwich/salad/soup based lunches. The lounge area carpet will be replaced with tile, a computer & table will be added for internet access in the lounge. Sources: Sources have yet to be identified but possible partners in the project could include: The Hopkins .1 Societv. Hopkins School District, a new non-profit "Friends of the Activity Center" organization. Justification It is well documented that baby boomers are not utilizing traditional senior centers as readily as seniors have in the past. People do not visit senior centers because it's for people of their age, they go there for the goods and services they need. The goal of the Cafe is to attract the younger older adult - younger in outlook, attitude and years - those who would benefit but seldom use "senior" sevices, to increase partnership, visibility and service reach, to improve the quality of life for our older adults, and to increase satisfaction of services. The caf6 concept would satisfy several City strategic goals such as building on the small town feel of Hopkins through developing new methods that are more responsive to citizens and customers. If partnering with the Historical Society the nroiect will enhance the sense of place. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 90,000 90,000 Total 90,000 90,000 53 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Funding Sources 2012 2013 PF - Private Sector Funds Total 2012 Ihru 2016 2014 2015 Department Activity Center Contact PW Director 2016 Total 90,000 90,000 90,000 90,000 The operational goal of the cafe would be to break even as a food service, but the Cafe would draw customers to the Activity Center to participate in the activitites many programs and activities offered by the Center thus increasing program and membership revenues. 1Jcdncsdur.Juni° 29 011 54 • • • CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-AR006 Project Name Replace Office Carpet - HCA Stages Theatre Future 2012 thru 2016 Department Arts Center Contact Arts Center Director Type Improvement Useful Life 10 years Category Buildings: Arts Center Priority n/a Total Project Cost: $35,275 ove and replace carpet and carpet base in Stages Theatre offices, ticket office and Facility Manager's office, and room and Arts Director office. 260 sq yards x $48/yard = $12,480 Justification Carpet is 13 years old as of 2010. Carpet will have exceeded its useful life. Carpet has separated from backing which has caused it to wrinkle and it can no longer be cleaned in these areas. Added Arts Director office (Susan's) guests do come in. It is visible to public - same vintage as facility office. Expenditures 2012 2013 2014 2015 2016 Total Future Construction/Maintenance 15,050 15,050 20,225 Total 15,050 15,050 Total Funding Sources 2012 2013 2014 2015 2016 Total Future CI - Capital Improvement Fund 15,050 15,050 20,225 Total 15,050 15,050 Total Budget Impact/Other Vote: Repeat project in 2021 at $20,225 • 55 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 thin 2016 Department City Hall Administration City of Hopkins, 1V11V Contact Public Works Director Project # 09-CIP-CH030 T.% pe Improvement Project name City Hall Lobby Upgrade Useful Life 20 years Category Bldg: City Hall Future PrioritN n%a Description Total Project Cost: $110,000 Dity Hall Lobby Upgrade was proposed as part of the 2007 City Hall upgrade/Carpet project. This part was not ;ompleted exceeding estimates. Justification Existing lobby is dated, ceiling tiles have yellowed and wallpaper has numerous stains from 19 years of service. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 110,000 110,000 Total 110,000 110,000 Funding Sources 2012 2013 2014 2015 2016 Total CI - Capital Improvement Fund 110,000 110,000 Total 110,000 110,000 Budget hnpact/Other 111,41n,'c</ur. ,lull, N 0/ / • • CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department City Hall Administration City of Hopkins, MN Contact Bldg/Equip Supt Project # 11-CIP-CH036 Type Improvement Useful Life 15 years Project Name City Hall Server Room Air Conditioning Category Bldg: City Hall Future Priority n/a Description I Total Project Cost: $10,000 Replace current portable AC units with 4 ton AC fan coil unit in City hall server room. Demolition of portion of block wall between existing server room and phone equipment room. I Justification Existing units are not designed for this type of application, New unit could utilize outside air for cooling in cooler months. Proposed unit would allow shutting down lower level air handler during unoccupied times. Project would include demolition of a portion of deviding wall between server room and telephone room to improve area for better contol of cooling. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 10,000 10,000 Total 10,000 10,000 Funding Sources 2012 2013 2014 2015 2016 Total Cl - Capital Improvement Fund 10,000 10,000 Total 10,000 10,000 Budget Impact/Other Police have informed Bldg Maint that they are adding a new 911 server to this area in 2012. This server adds an additional 25,000 BTU's of heat to this room. Without this upgrade this added load will not be possible to cool with existing Equipment. 0 57 Wednesday, June 19, 1011 CAPITAL IMPROVEMENT PLAN 2012 1111 -it 2016 City of Hopkins, MN Project # 08-CIP-FDO19 Project Name Replace Carpet and Apparatus Floor Finish - FD Future carpet and apparatus floor finish systems. Department Fire Contact '1. Fire Chief pe Improvement Useful Life 10 years CaIegorc Buildings: Fire Facilities Priority nia Total Project Cost: $56,000 Justification Planned replacement at end of estimated 10 year useful life. Classroom and 2nd and 3rd Floor entryway and louge replacement, due to excessive use of classroom and lounge. FD spoke with Steve Stadler and he was A with moving it up to 10 years from 15 years. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 56,000 56,000 Total 56,000 56,000 Funding Sources 2012 2013 2014 2015 2016 Total Cl - Capital Improvement Fund 56,000 56,000 Total 56,000 56,000 Budget Impact/Other Original plan replacement was 15 years. Due to excessive use of classroom and lounge the life was moved to 10 years. It'rrinrsrlur../u1rr 'y. '011 58 is C, CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Pavilion City of Hopkins, MN Contact Public Works Director Project # 07-CIP-P314 Type Improvement Useful Life 30 years Project Name Pavilion Overhead Door Improvement Category Bldgs: Pavillion Future Priority n/a Description Total Project Cost: $40,000 Remove and lock -in four of the six overhead doors on the west side of the Pavilion with a portion to have windows or glass block to allow light to come through. Install automatic openers on the remaining four overhead doors in the arena. ESTIMATED PROJECT SCHEDULE: 2015 Justification Zurrently the overhead doors are seldom utilized and the removal and installation of glass blocks or windows will Jecrease the need to use arena lighting and add to arena aesthetics. Saving on repairs and maintenance of the removed doors. Pavilion user groups have asked for this project. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 40,000 40,000 is Total 40,000 40,000 • Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 40,000 40,000 Total 40,000 40,000 Budget Impact/Other ?otential savings on utilities and greater satisfaction from user groups with arena aesthetics. 59 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 t/„ i, 2016 City of Hopkins, MN Project # 07-CIP-P315 Project Name Pavilion Mez. Roof Replacement (North Section) Future Depart nient Pavilion Contact Public Works Director Tope Improvement l serol Lire Category Bldgs: Pavillion Priority n'a Description 'Iota] Project Cost: $40,000 Zemoval and replacement of existing membrane material and re -using the existing ballast. Justification Existing roof membrane has exceeded its useful life and is experiencing seam failure around penetrations and joints along with pulling away from the outside curb. Leaks have been repaired on several occasions. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 40,000 40,000 Total 40,000 40,000 Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 40,000 40,000 Total 40,000 40,000 Budget Impact/Other Roof leaks can potentially be harmful to the steel roof deck and may cause damage to equipment and interior of Pavilion. 11'rdn(sdur. Jim, 29, 011 ME L` CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Pavilion City of Hopkins, MN Contact Public Works Director • • Project # 08-CIP-P008 Type Improvement Useful Life 15 years Project Name Pavilion Arena Bleacher HeatingReplacement P Category Bldgs: Pavillion Future Priority n/a Description Total Project Cost: $38,000 Zeplace the arena's current bleacher infrared heating system with a new efficient system. Justification The current system is 18 years old and no longer produces adequate heat due to deterioration of the major components. [replacement is warranted rather than repair due to the age of the system and the type of repairs needed. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 38,000 38,000 Total 38,000 38,000 Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 38,000 38,000 Total 38,000 38,000 Budget lmpact/Other Potential savings on utilities and greater satisfaction from user groups. Inadequate bleacher heat is the major complaint amonlr Pavilion users. 61 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Pavilion City of Hopkins, 1V11V Contact Public Works Director 3ject # 09-CIP-PO25 T> pe Improvement 3ject Name Pavilion Gas Fired Rooftop Furnace Lseful Lite 20 years ('atcgor� Bldgs: Pavillion Future Priority n'a ascription Total Project Cost: $9,000 move and replace existing gas fired rooftop furnace used for heating the team rooms. TIMATED PROJECT SCHEDULE: Spring/Summer 2015 Justification Current unit was installed during construction of the facility in 1990. Planned replacement for end of estimated useful life. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 9,000 9,000 Total 9,000 9,000 *I Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 9,000 9,000 Total 9,000 9,000 Budget Impact/Other Savings on utilities due to increase in efficiency of new units. 0 ifc dncr�lur. Jany 29. 2011 62 CAPITAL IMPROVEMENT PLAN 2012 Ihru 2016 Department Pavilion City of Hopkins, MN Contact Public Works Director Project # 09-CIP-PO36 Type Improvement Useful Life 15-25 years Project Name Pavilion Evaporator Condenser Replacement p p Category Bldgs: Pavillion Future Priority n/a Description Total Project Cost: $60,000 0 • Remove and replace existing condenser with a new condenser, sump tank, pump and fan motors. ESTIMATED PROJECT SCHEDULE: 2015 Justification Existing condenser has extensive scaling and has experienced a loss in efficiency causing higher head pressures and putting greater strain on compressors. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 60,000 60,000 Total Funding Sources 60,000 60,000 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 60,000 60,000 Total 60,000 60,000 Budget Impact/Other Given the age, scaling, and corrosion of the existing condenser a freon leak could potentially develop causing greater expense and need for repair. 63 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 diri< 2016 Department Pavilion City of Hopkins, 1V11V t'ontact Public Works Director Project # 09-CIP-P316 Tcpe Improvement Project Name Ice Resufacer Water Heating System Replacement lseful Life 20 years Categor� Bldgs: Pavillion Future Priorio n/a Description Total Project Cost: $15,000 Remove the three existing water heaters used to heat the ice resurfacing water and replace with new water heating system. Justification One of three heaters used is unusable and the other two water heaters have corrosion and major scaling issues. All three water heaters were part of the facility construction in 1990. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 15,000 15,000 Total 15,000 15,000 Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 15,000 15,000 Total 15,000 15,000 Budget hnpact/Other iavings on utilities due to increase in efficiency of new system. It'r(lncclod. Am(, 11). 1011 64 • • CAPITAL IMPROVEMENT PLAN City of Hopkins, MN • • Project # 10-CIP-P319 Project Name Pavilion Indoor Turf Replacement Future Description 'urchase new turf for the Pavilion's arena 2012 thru 2016 Department Pavilion Contact Facilities Director Type Improvement Useful Life 15 years Category Bldgs: Pavillion Priority n/a Total Project Cost: $95,000 Justification The current turf was purchased in 1998 and has a useful life of 15 years (2013), the turf is showing signs of wear and las been patched in a few areas. Replacement will be needed by 2016. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 95,000 95,000 Total 95,000 95,000 Funding Sources 2012 2013 2014 2015 2016 Total PA - Pavilion Fund 95,000 95,000 Total 95,000 95,000 Budget Impact/Other ?ossible resale of the existing turf may offset some of the cost of a new turf system. 65 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 11„ a 2016 City of Hopkins, MN Project # 08-CIP-PDO16 Project Name Replace Carpet - Police Station Future Description Replace Police Station Carpeting Department Police Contact Police Chief [-.% pe Improvement useful Life 7 years Category Buildings: Police Depatrtment Priorit. n,a I otal Projcct Cost: $40,000 Justification Planned replacement at end of estimated 10 year useful life. This is a 24hour/day work center that required the shorter carpet replacement cycle. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 40,000 40,000 Total 40,000 40,000 Funding Sources 2012 2013 2014 2015 2016 Total Cl - Capital Improvement Fund 40,000 40,000 Total 40,000 40,000 Budget Impact/Other May have to look at other flooring option for dispatch. (ie combination of carpet and tile due to wear under desk areas. Previously in at a 7 year life - moved back to 10 year life It chic day..luar 29. 2011 W 0 • • 0 Parks and Recreation 67 CAPITAL IMPROVEMENT PLAN 2012 11in, 2016 City of Hopkins, MN Project # 07-CIP-P219 Project Name Shady Oak Beach Community Play Area Future Description Department Public Works: Parks Contact Public Works Director lope Improvement Fsef ll Life Category Parks/Fores/Pay.: Comm. Facil. Priorit, n/a Total Project Cost: $330,000 ent of the Shady Oak Beach water play area with a community play area designed to be a destination for residents of Minnetonka and Hopkins. Justification The existing water play equipment at the site was installed when the beach was renovated in 1998 to encourage use of the site when weather conditions were not conducive to swimming. The system is in need of replacement due to health and safety requirements as well as aging equipment. Staff is recommending that the water play area be replaced with a community playground area designed to be a destination attraction for families with children 12 years of age and under. Use of this equipment on a seasonal basis would extend beyond the beach operating season and be available for use ,during the fall months as well. Prior Expenditures 2012 2013 2014 2015 2016 Total 7-30-9,0-0-01 construction/Maintenance 21,000 21,000 Total Total 21,000 21,000 Prior Funding Sources 309,000 PDF- Park Dedication Fund Total Total 2012 2013 2014 2015 2016 Total 21,000 21,000 21,000 21,000 Budget Impact/Other Completion of this project will enhance beach attendance during the normal beach operating season as well as post - season use. It is anticipated that season pass sales will increase due to the addition of a high quality community paly cation of the existing water play area and underground confined space that houses the operational equipment will in reduced annual operating expenditures of approxinamtely $5,000. Wcdnesdar. Junc 29. 201 68 • • CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Parks City of Hopkins, MN Contact PW Director Project # 08-CIP-PO10 Type Improvement Useful Life Project Name Play Equipment - Park Valley Category Parks/Fores/Pay.: Comm Facil. Future Priority n/a Description Total Project Cost: $45,000 Replace park play equipment 2014 ----------- 45,000.00 Justification Upgrade of park play equipment after 20 - 25 years of use. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 45,000 45,000 Total 45,000 45,000 0 Funding Sources 2012 2013 2014 2015 2016 Total PDF- Park Dedication Fund 45,000 45,000 Total 45,000 45,000 Budget Impact/Other • Wednesday, June 29, 2011 69 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-PO14 Project Name Play Equipment - Hilltop Park Future Description Zeplace park play equipment. Justification Upgrade of park play equipment after 20-25 years 2012 d t, 2016 Department Public Works: Parks Contact Facilities Director I\pc 1111Provement IV Useful Life Category Parks, Fores�Pay.: Comm. Facil. Priorit. n/a Total Project Cost: $45,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 45,000 45,000 Total 45,000 45,000 i Funding Sources 2012 2013 2014 2015 2016 Total PDF- Park Dedication Fund 45,000 45,000 Total 45,000 45,000 Budget Impact/Other 70 I1 (da,2%. 2011 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-PO15 Project Name Play Equipment - Valley Park Future Description Replace park play equipment. I Justification Upgrade of park play equipment after 20-25 years of use. 2012 thru 2016 Department Public Works: Parks Contact Facilities Director Type Improvement Useful Life Category Parks/Fores/Pay.: Comm. Facil. Priority n/a Total Project Cost: $65,000- Budget Impact/Other • Wednesday, June 29, 2011 71 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 65,000 65,000 Total 65,000 65,000 • Funding Sources 2012 2013 2014 2015 2016 Total PDF- Park Dedication Fund 65,000 65,000 Total 65,000 65,000 Budget Impact/Other • Wednesday, June 29, 2011 71 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN F ect # 08-CIP-P016 ect Name Play Equipment - Oakes Park Future Description Zeplace park play equipment. I Justification Upgrade of park play equipment after 20-25 years of use. 2012 d7 u 2016 Department Public Works: Parks Contact Facilities Director r)pe Improvement Useful Life Categorc Parks/Fores/Pay.: Comm. Facil. Prioritc wa Total Project Cost: $60,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 60,000 60,000 Total Funding Sources PDF- Park Dedication Fund Total Budget Impact/Other 60,000 60,000 2012 2013 2014 2015 2016 Total 60,000 60,000 60,000 60,000 H'ethicw&nv../unc 21). 20l l 72 *I •I CAPITAL IMPROVEMENT PLAN City of Hopkins, MN f ect # 10-CIP-P017 ect Name Miscellaneous Park Improvements Future 2012 thru 2016 Department Public Works: Parks Contact PW Director Type Improvement Useful Life Category Parks/Forestry Priority n/a Description Total Project Cost: $20,000 Improvements to various neighborhood and community parks to maintain safe and enjoyable play areas, shelters and i ustification Parks are periodically in need of play equipment container area repairs, play equipment repairs, shrub and tree replacements, picnic shelter repairs, etc. In order to keep the parks safe and enjoyable for residents. Prior Expenditures 2012 2013 2014 2015 2016 Total 7-1-0,0-0-01 Construction/Maintenance 10,000 10,000 Total Total 10,000 10,000 • Prior Funding Sources 7,000 PDF- Park Dedication Fund Total Total Budget Impact/Other L' 2012 2013 2014 2015 2016 Total 10,000 10,000 73 10,000 10,000 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 thn(2016 City of Hopkins, MN EProject # 11-CIP-PO18 Project Name Park Building Re -Roofing Future Description Remove old roofing, repair roof deck as needed and install new roofing. - Maetzold Field Storage Building - Harley Hopkins Warming House - Central Park Warming House Justification Existing roofing is beyond useful life and leaking. Department Public Works: Parks Contact Facilities Director T\pe Improvement Useful Life 20 years C'atcgor� PW - Parks Priority n/a Total Project Cost: $15,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 15,000 15,000 Total 15,000 15,000 • Funding Sources 2012 2013 2014 2015 2016 Total PDF- Park Dedication Fund 15,000 15,000 Total 15,000 15,000 11 cdncgdar. Atac 29. 2011 74 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 11-CIP-P019 Project Name Play Equipment - Cottageville Park Future Description Replace park play equipment. 2012 thru 2016 Department Public Works: Parks Contact Facilities Director Type Improvement Useful Life Category PW - Parks Priority n/a Total Project Cost: $45,000 Justification In accordance with new park master plan, replace existing 23 year old play equipment. Budget Impact/Other • Wednesday, June 29, 2011 75 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 45,000 45,000 Total • Funding Sources 45,000 2012 2013 45,000 2014 2015 2016 Total PDF- Park Dedication Fund 45,000 45,000 Total 45,000 45,000 Budget Impact/Other • Wednesday, June 29, 2011 75 CAPITAL IMPROVEMENT PLAN 2012 din, 2016 City of Hopkins, MN Project # 10-CIP-RO02 Project Name Depot Recreation Area Future Description Department Recreation Contact PW Director Tcpe Improvement Useful Lite 25 years Category PW - Parks Prioritc 2 Very Important Total Project Cost: $500,000 This project includes the addition of an outdoor multipurpose rink/court and support building on property west of the Depot facility. These amenities are proposed to be utilized as part of Depot youth engagement activities and as part of the community rec leagues and playground programs. The multipurpose rink/court will include an asphalt surface and hockey dasher boards for skating and broomball use in the winter; and equipment to accommodate basketball, inline skating, volleyball and soccer uses in the spring, summer and fall months. The support facility will include equipment for a bike maintenance and repair site sponsored by the Depot, as well as restrooms, storage areas and a general multipurposearea to be used as a warming house in the winter. Grant of $150,000 will be avolied for. Justification The Depot site has needed outdoor amenities for its target audience since its founding. A year-round sports "anchor" at the Depot site to complement arts and music and entreprenurial business experience for youth will provide additional reniforcemement of positive behaviors. As more people come to the Depot for youth activities as well as general use during daytime hours, such a facility could be used all day and into the evening hours. Proximity to the rail corridor will accord high visibility and symbolize active living and community connections in a walkable, bike -able community. Rec league broomball or hockey could share ice with free skating times. Local business employees could take advantage of the facilty over lunch times. Easy trail access makes the Depot and easy ride for kids who would come there to play. The Depot has been working toward more bike -oriented prgrams open to the whole community (e.g. Bike Scream Sundays) and has some connections already with local bike retailer/advocates at Freewheel by hosting a bike equipment vending machine on site. Dedicated space would give new possibilities to this aspect of the "Depot on the Move" Initiative. Expenditures 2012 2013 2014 2015 2016 Total Construction 500,000 500,000 Total 500,000 500,000 Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 500,000 500,000 Total Budget Impact/Other W. 000 500,000 It calaccdar. Jtna • Streets, Traffic & Transportation 77 w w _ z Z z _ w n O "w a izi i w z ¢ J C5 u a¢ r a u yy1 Q J m Q U W Z Z J W m u z w w W a 0– W z O J Y N¢>>> �mmm0 Y z z ¢ IA w"– m M. Z wwwx o¢ zzzzQz U IJ " Z¢ m z Z z Q Q Q 0 2� W W u Q Q m J j>>> F" 0 ¢ ¢ u a Q ¢ V N1.10 Nl0n mP �N�N stn®'t 'ls ?INO.LRNNIW -iIiL-L JRA O •" a 3lbAltl Z ¢ Qu VePN S Qy ) m >O V J 6 m �.�'JD• 7N I b0 ¢ oola N3aao Qo'z z 1J 0 QO' bA W x H� Eby z i o AbAy� x o bl AVAalsi r SSOaJ O SNINdOH N J O w } } CL c c U) C — O O O U v U F- O O 00 CL N N N N U XUVd SIM'] US 8 S ys d 'oa rooaenoae3w � �� m � 'Oa � 3Na0H1neH J F— '3ne SVX 31 L� p ❑ HO1163INl z x �Q� o •Ga GooMreo 0 0 •ane AHdanw 'u' '0a s AIIOH u G 11\ o u � O .� 'Oa 0o A3lHSV O aoo I N ` O �j o ' Oa 3NtlnB _ S 'Oa WrV 1B U. w ' S y l l a � \ ne af3 Al N 'N 'ane NOI 88VH J \3n b 'e� V'l AV ne 3OaNOw f�g3ne NOSIOew �I zlf'ny 'ane Alod 'ane a3�A1 � \ 'S '3ne • NOS IadeH JN 'S '3ne N3anB Nen s z 'S '3ntl �, NOSrJef s 'S '3ne N05I0ew p % 'S '3ne N058333Y £ 5 anew SWV0V \ \\\ 'S '3AV' NOlONIHS eM VNIUR \� �!,rt•� 'S '3ne ONZ V Q > ONZ J1ded '3 15tl3 3n0 ��__ILLS J oy 133n5/ a0 I N310 NVo i _ _ _ z 3N I I i 'd0 A3n� n 3-lIN 1001a>te0 t'Ir— 'S ]AV H19 e j�J; Z .3n1 H10 •3nb o New is=, '3v,e N HlL 'S '3nb H1C 3001a NVG l 2 �1 J�,� ��3nV Hlb'3nb' H�lbt!'L _J S ::N-3nV >J 3ne \� J w RD. o �� 3nV H121 S '3nV� H1ZIw 3nb Hlcl W '3nr N w: s - Ht[i W '3ne Htel 1�� NSI,= /;I �L. 3nV z r!1r c� •S '3nb H151 m ��:S '33 by �T '111;1 \;IQf—aJJIF— - I H. e 1 �Il_ e Haed n H18ON Hlnos V' I'S .]AV Il H15 3n0] 3�Iw 3NIN '3ne F u� r 'O S 'any Hlb F0 � c 'S '3ne H101_ I l •S .3nV o ❑ 'S '3ne x w o z o ¢ Y a V NINE S '3 5 ------------ Hlel S'3ntl lbl Z .S '3nV L H15I x 'S '3nb H", \\ S \\ CS� CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Streets/Traffic City of Hopkins, MN Contact Public Works Director Project # 01-CIP-S101 Type Improvement Useful Life Unassigned Project Name Residential Street Improvements Category Trans: Streets Future Priority n/a Description Total Project Cost: $11,990,000 Program to improve streets needing repair or reconstruction as indicated by street condition survey, or as part of an area street improvement. 12: Central Hopkins Reclamation Project - Minnetonka Mills Road between 11th and 7th Avenue; 11th Avenue ,rth between 1 st Street and 3rd Street; 9th Avenue North between 2nd Street and Mainstreet; 3rd Street North tween 8th and 11 th Avenues; 4th Street North between 10th and 11 th Avenue; 8th Ave North between 1 st and 2nd 13: Presidential Avenues South and 1 st Street and 2nd Street South, between Monroe and Harrison. 2014 - 2015: Park Valley and Peaceful Valley Reclamation Project - East and West Park Valley Road; 9th Avenue South between Westbrooke Way and 7th Street South; 6th Street South between 10th Avenue and 6th Ave South; 7th Street South between 10th Avenue and East Park Valley Road; 5th Ave South between 5th Street South and 7th Street South X16: Central Hopkins Street Reclamation Project - 20th Avenue North between Mainstreet and 3rd Street; 19th .venue North between Mainstreet and 1 st Street North; 18th Avenue North between Mainstreet and 4th Street; 16th .venue North between Mainstreet and 1 st Street North; 14th Avenue North between Mainstreet and 2nd Street North; ad Street North between 14th and 15th Avenue South. Future: Texas Avenue from Lake Street to Cambridge Street; Oxford Street from Blake Road to Texas Ace; Cambridge Street from Blake Road to Texas Ave; Murphy Street from Lake Street to Oxford Street; Lake Street from Blake Road to Texas Ave. Justification Ongoing street improvements determined through Pavement Management Program. Prior 4,390,000 Total LJ Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 1,800,000 1,800,000 1,000,000 1,100,000 1,900,000 7,600,000 Total 1,800,000 1,800,000 1,000,000 1,100,000 1,900,000 7,600,000 79 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 rhe n 2016 Department Public Works: streets Traffic City of Hoplems, 1Y11V Contact Public Works Director Prior Funding Sources 2012 2013 2014 2015 2016 Total • 590,000 PI - PIR/General Obligation Bo 1,000,000 850,000 500,000 500,000 1,000,000 3,850,000 Total SA - Special Assessment 800,000 950,000 500,000 600,000 900,000 3,750,000 Total 1,800,000 1,800,000 1,000,000 1,100,000 1,900,000 7,600,000 Budget hnpact/Other ?ublic hearing - year prior to planned construction Tans and specifications - year prior to planned construction aid and assessment - year of planned construction Consistent with the City Council adopted Roadway Improvement Policy, street ratings, and Pavement Management • • If cdnc�dav—hm, 21X 2011 80 CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Streets/Traffic City of Hopkins, M1V�TContact Public Works Director Project # 01-CIP-5102 Type Improvement Useful Life Unassigned Project Name Residential Street improvements --Utilities P Category Trans: Streets Future Priority n/a Description Total Project Cost: $3,630,000 rations to be determined as they are consistent with the street reconstruction program. gram to reconstruct deteriorated water main and sanitary sewer and to provide storm sewer improvements in [junction with street improvement projects. hearing: Year prior to planned construction and specifications: Year prior to planned construction Year of planned construction with the Storm Water Justification Water and Sewer Utility Master Plan, and television In most cases where street reconstruction takes place, storm sewer facilities either need upgrading or need to be installed new. In some cases, water main and sanitary sewer need to be rehabilitated in conjunction with street reconstruction. The numbers assume the city funding 100% of major storm sewer, water main, and sanitary sewer re/construction. These costs are to be used in conjunction with street reconstruction costs shown on 01-CIP-S101. AlftPrin Expenditures 2012 2013 2014 2015 2016 Total 2,175,0001 Construction/Maintenance 275,000 290,000 290,000 300,000 300,000 1,455,000 Total Total 275,000 290,000 290,000 300,000 300,000 1,455,000 Prior Funding Sources 2012 2013 2014 2015 2016 Total 7175,000 SF - Sanitary Sewer Fund 100,000 100,000 100,000 100,000 100,000 500,000 Total SU - Storm Sewer Fund 100,000 110,000 110,000 110,000 110,000 540,000 WF - Water Fund 75,000 80,000 80,000 90,000 90,000 415,000 Total 275,000 290,000 290,000 300,000 300,000 1,455,000 lic Hearing - year prior to planned construction [s and specifications - year prior to planned construction - year of planned construction Consistent with the Storm Water Management Plan, Water and Sewer Utility Master Plan, and television is Wednesday, June 29, 2011 81 CAPITAL IMPROVEMENT PLAN 2012 / 7rn 2016 City of Hopkins, MN Project # 01-CIP-5103 Project Name Citywide Concrete Alleys Future Department Public Works: Streets/Trafiic Contact Public Works Director T. pe Improvement Useful life Unassigned Category Trans: Streets Priority n/a Description Total Project Cost: $1,278,000 2014: Alley south of 6th Street South and North of Nine Mile Creek, between 11 th Avenue South and 10th Avenue South. 12: Alley south of 3rd Street North and North of 2nd Street North, between 6th Avenue North and 5th Avenue North. Alley South of Mainstreet between 8th and 9th Ave South Program to construct concrete alleys in areas designated as poor on the Alley Condition Survey. Public Hearing - year prior to project. Plans, specifications, bid, construction - year of project. Consistant with the Ctiy Council adopted Roadway Improvement Policy and Alley ratings. Justification The city has had a policy of constructing concrete alleys for a number of years. This policy has proved to be sound by the concrete alleys' durability and low maintenance costs. Current policy has the city share at 20% of the cost in residential areas. The city will experience cost savings due to lower maintenance costs. Prior Expenditures 2012 2013 2014 2015 2016 Total 1,078,000 Construction/Maintenance 135,000 65,000 200,000 Total Total 135,000 65,000 200,000 Prior Funding Sources 2012 1,078,000 PI - PIR/General Obligation Bo 35,000 Total SA - Special Assessment 100,000 2013 2014 2015 2016 Total 13,000 48,000 52,000 152,000 Total 135,000 65,000 200,000 Budget Impact/Other kpproximately 1250 feet per year for four years 3ublic Hearing - year prior to project Tans, specifications, bid construction - year of project Consistent with the City Council adopted Roadway Improvement Policy and Alley ratin;;s. 11'cdnrsdur. Junr 29, 20/ l 82 • CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Streets/Traffic City of Hopkins, MN Contact Public Works Director Project # 01-CIP-S104 Type Improvement Useful Life Unassigned Project Name County Road 3 Category Trans: Streets Future Priority n/a Description Total Project Cost: $2,300,000 Inty Road 3 from Shady Oak Road to Meadowbrook Road. hting, landscaping, street, etc. improvements along Excelsior Boulevard from the east to west city limits. Bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, itional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue ment 1: Construction - 1998/1999 2: Planning - 2004; bidding and construction (median upgrades only) - 2005 3: Planning and acquisition - 1999/2001, bidding/construction - 2002/2003/2004 4: Planning and acquisition - 2012/2013, bidding/construction - 2014/2015 funded work includes the following: A signalized intersection will be constructed at Monroe Avenue. A second intersection will also be built at Jackson Ave/St. Louis Street. There will also be a reconfiguration of Monroe Avenue and Milwaukee south of Excelsior Boulevard. This work is being completed in conjunction with the reconstruction of Excelsior Boulevard from Highway 169 to Blake Road. The intersection is being constructed to facilitate redevelopment of the SuperValu north annex site. Justification in terms of roadway condition, traffic/pedestrian movement, safety and aesthetics appear in all four segments of County Road 3: - Segment 1 from Shady Oak Road to 11th Avenue S.; upgrade existing undivided roadway, upgrade 11th Avenue intersection to meet future needs, implement beautification program --completed in 1998 - Segment 2 from 11th Avenue S. to Hwy 169; median pavers construction - Segment 3 from Highway 169 to Blake Road; upgrade existing narrow undivided roadway, resolve safety issues at railroad crossing, improve north -south access, account for future LRT access, address redevelopment needs, add integration for full access at Jackson Avenue. - Segment 4 from Blake Road to Meadowbrook Road; upgrade roadway, implement beautification program. Prior Expenditures �0 Construction/Maintenance Total Prior 0 Total 2012 2013 2014 2015 2016 Total 2,300,000 2,300,000 Total 2,300,000 2,300,000 Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 1,600,000 1,600,000 MS - Municipal State Aid Stree 700,000 700,000 Total 2,300,000 2,300,000 83 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 !nett 2016 City of Hopkins, MN Budget Impact/Other Department Public Works: Streets/Traffic Contact Public Works Director bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue. Segment 1: Construction - 1998/1999 Segment 2: Planning - 2005; bidding and construction (median upgrades only) - 2006 Segment 3: Planning and acquisition - 1999/2000; bidding/construction - 2003/2004 Segment 4: Planning and acquisition - 2012/2013; bidding and construction - 2014/2015 Consistent with Hennepin County CIP and Citv Council action. • • 11 cdiwsdnr. Amc 29. 2011 84 CAPITAL IMPROVEMENT PLAN 2012 rhru 2016 City of Hopkins, MN Project # 01-CIP-S106 Project Name County Road 61 (Shady Oak Road) Future Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $20,450,000 Shady Oak Road from County Road 3 to T.H. 7, Mainstreet from 20th Avenue to Shady Oak Road. Lighting, landscaping, street, etc., improvements from County Road 3 to T.H. 7 Reconstruction and amenities on Mainstreet from 20th Avenue to Shady Oak Road. Reconstruction of West Park Road, 2nd Street N., and 21 st Avenue N. (2nd Street -4th Street N.) See also 01-CIP U003 for the Storm Sewer Management associated with this project. Justification Deficiencies appear on Shady Oak Road in terms of roadway conditions, traffic/pedestrian movement, safety, and aesthetics. Upgrade an undivided roadway, resolve safety issues with number of driveway access points and intersection at Mainstreet. Lighting needs upgrading and provide beautification program. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 8,200,000 12,250,000 20,450,000 • Total 8,200,000 12,250,000 20,450,000 Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 6,150,000 11,045,000 17,195,000 MS - Municipal State Aid Stree 2,050,000 755,000 2,805,000 PI - PIR/General Obligation Bo 200,000 200,000 SA - Special Assessment 250,000 250,000 Total 8,200,000 12,250,000 20,450,000 Budget Impact/Other ?012-2014: Planning and acquisition 14/2015: Bidding and construction with Hennepin County CIP, city's desire to upgrade the roadway, and reconstruction program for all of Mainstreet. This project totals $20,450,000. Hopkins share of the county project is $2,805,000 of which we have $1.3 million budgeted. The remaining $1.5 + million is right-of-way acquisitions for which we currently have no funding. The Loiect is not feasible under the current funding Drogram. GU funding includes $7.28 million Federal Grant. Wednesday, June 29, 2011 85 CAPITAL IMPROVEMENT PLAN 2012 dint 2016 Department Public Works: SUa siTraff-ic City Of Hopkins, MN Contact Public Works Director Project # 01-CIP-5504 T.% Improvement l seful Life Unassigned Project Name ,Sixth Street South (11th to 12th Avenue South) Cate„ore Trans: Streets Future PrioritN n/a Description iixth Street South from 11th Avenue South to l2th Avenue South. Extension of roadway and box culvert crossing at Nine Mile Creek. Total Project Cost: $500,000 Justification This project will offer a second access to the industrial area (fire access). Will direct some of the existing industrial traffic north, away from the residential intersection at Seventh Street and 1 I th Avenue. Will connect a current dead-end alley, west of 11th Avenue. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 500,000 500,000 Total 500,000 500,000 Funding Sources 2012 2013 2014 2015 2016 Total ED - Economic Development F 100,000 100,000 MS - Municipal State Aid Stree 400,000 400,000 Total 500,000 500,000 Budget hnpact/Other Currently on MSA plans. 86 • • It ctinesday. Junr 29. 2011 CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Streets/Traffic City of Hopkins, MN Contact Public Works Director Project # 06-CIP-5118 Type Improvement Useful Life Project Name Parking Lots - Lot 200 Category Trans: Parking Facilities Future Priority n/a Description Total Project Cost: $250,000 2010: Municipal Parking Lot 200, south of Mainstreet between 8th and 9th Avenues. Rehabilitate parking lot pavement Justification Pavement has deteriorated to the point where cracksealing and sealcoating are not effective. Budget Impact/Other • 87 Wednesday, June 29, 2011 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 250,000 250,000 Total 250,000 250,000 Funding Sources 2012 2013 2014 2015 2016 Total PI - PIR/General Obligation Bo 200,000 200,000 SU - Storm Sewer Fund 50,000 50,000 Total 250,000 250,000 Budget Impact/Other • 87 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 Hint 2016 Department Public works: Streets Traffic City of Hopkins, MN contact PW Director Project # 10-CIP- S120 Type Improvement . Project Name Highway 7 and 5th Ave North - Signal Replacement lIseful Lite 25 years C'alcgor� Trans: Streets Future Prioritc 3Important Description Total Project Cost: $445,000 Traffic signal replacement at the intersection of Highway 7 and 5th Ave North. Justification IMN DOT has mandated the replacement of this signal. Expenditures 2012 2013 2014 2015 2016 Total Construction 445,000 445,000 Total 445,000 445,000 Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 300,000 300,000 PI - PIR/General Obligation Bo 145,000 145,000 Budget Impact/Other Total 445,000 445,000 88 It cdnevdai,..1wic 29, 20l 0 1 •I CAPITAL IMPROVEMENT PLAN 2012 thru 2016 City of Hopkins, MN Project # 11-CIP-S120 Project Name Plan, Design and Implement Railroad Quiet Zone Future Department Public Works: Streets/Traffic Contact Facilities Director Type Improvement Useful Life 30 years Category Trans: Streets Priority n/a Description Total Project Cost: $255,000 vlodify existing railroad grade crossings to satisfy Federal Railroad Administration (FRA) requirements to create a Whistle -Free Quiet Zone for the CP Railroad corridor. I: Plan and coordinate requirements with FRA and SWLRT project office. Design necessary supplemental safety res (SSM). Phase Il: Construct SSM's and implement Quiet Zone. Justification Train horns sound in early morning hours and are disruptive to nearby residential areas. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 30,000 225,000 255,000 0 Total 30,000 225,000 255,000 • Funding Sources 2012 2013 2014 2015 2016 Total PI - PIR/General Obligation Bo 30,000 225,000 255,000 Total 30,000 225,000 255,000 89 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 thrit 2016 City of Hopkins, MN Project # 11-CIP-S121 Project Name Mainstreet Traffic Signal Upgrades Future Deparuuen( Public Works: Streets/Traffic Contact Facilities Director T.% Total pe Improvement Lseful Life 30 years Categor) Trans: Streets Mork) 3 Important Description Total Project Cost: $500,000 These projects upgrade the Mainstreet traffic signals with LED lighting, countdown timers, controllers, and audible signals for the visually impaired. The equipment currently in place was installed _ years ago and is in need of 2012: 11 th Ave and Mainstreet 2013: 5th and 8th Ave and Mainstreet 2014: 9th and 10th Ave and Mainstreet 2015: 17th Avenue and Mainstreet and 5th Ave and Minnetonka Mills 2016: 12th and 7th Ave and Mainstreet 2017: 14th and Mainstreet, 11 th Ave S and 5th Ave S Justification Expenditures 2012 2013 2014 2015 2016 Total Future Construction/Maintenance 250,000 50,000 50,000 50,000 50,000 450,00050,000 Total 250,000 50,000 50,000 50,000 50,000 450,000 Total Funding Sources MS - Municipal State Aid Stree PI - PIR/General Obligation Bo Budget Impact/Other 2012 2013 250,000 50,000 2014 2015 50,000 50,000 2016 50,000 Total Future 250,000 50000 200,000 Total Total 250,000 50,000 50,000 50,000 50,000 450,000 It Cdncedav, Junc 29. 201 l CAPITAL IMPROVEMENT PLAN City of Hopkins, MN r1 U Project # 11-CIP-S122 Project Name Blake Road Streetscape Future 2012 thru 2016 Department Public Works: Streets/Traffic Contact Facilities Director Type Improvement Useful Life 50 years Category Trans: Streets Priority n/a Description Total Project Cost: $200,000 This project continues the upgrade of Blake Road with lighting and streetscape enhancements. Much of the funding for this work comes from Hennepin County Grants. Justification Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 100,000 100,000 PI - PIR/General Obligation Bo 100,000 100,000 Budget Impact/Other Pi Total 200,000 200,000 91 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 11i it 2016 City of Hopkins, MN Project # 11-CIP-S124 Project Name 2nd Avenue S Berm Rehab Future Description Remove dead and dying mature spruce trees Re -landscape right-of-way berm Department Public Works: Streets%Traffic Contact Public Works Director l vpe Improvement 40 l soul Life Category Trans: Streets Priority n/a Lotal Project Cost: $30,000 Justification This landscaped berm buffer is 30+ years old, the spruce trees are dying and the area needs landscaping. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 30,000 30,000 Total 30,000 30,000 0 Funding Sources 2012 2013 2014 2015 2016 Total PI - PIR/General Obligation Bo 30,000 30,000 Total 30,000 30,000 • It rdnrsdut. Juni° 29. 2011 92 CAPITAL IMPROVEMENT PLAN 2012 thru 2016 Department Public Works: Transportation City of Hopkins, MN Contact Public Works Director Project # 01-CIP-5502 Type Improvement Useful Life Unassigned Project Name Light Rail Transit Stations (2) Category Trans: Streets Future Priority n/a Description Total Project Cost: $150,000 1) Intersection of Third Street South and Fifth Avenue South 2) Second Street Northeast Supplemental improvements to two Light Rail Transit (LRT) stations in the proposed HCRRA locations. Justification The HCRRA proposes to construct two stations along the Southwest Corridor. The proposed expenditures would be in addition to the funds expended by the HCRRA. The additional funds would be used to ensure the stations are high quality in appearance. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 150,000 150,000 Total • Funding Sources 150,000 150,000 2012 2013 2014 2015 2016 Total TF - Tax Increment Financing 150,000 150,000 Total 150,000 150,000 Budget Impact/Other dependent on HCRRA plans. consistent with plans for LRT stops in Hopkins by Hennepin County. • Wednesday, June 29, 2011 93 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN jest # 01-CIP-S503 jest Name Eighth Avenue LRT Corridor Future 2012 thrit 2016 Department Public Works: Transportation Contact Public Works Director Avenue from County Road 3 to Mainstreet and installtion of pedestrian improvements and streetscape improvements Justification J . pe Improvement Useful Lite Unassigned Category Trans: Streets Priorit.N n/a Total Project Cost: $200,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 • Funding Sources 2012 2013 2014 2015 2016 Total GU - Other Governmental Unit 100,000 100,000 TF - Tax Increment Financing 100,000 100,000 Total 200,000 200,000 Budget Impact/Other Dependent on Metropolitan Council SWLRT plans * I 11'cdnccdur. Jun, 29. 2011 94 • Utilities Oil CAPITAL IMPROVEMENT PLAN City of Hopkins, MN 2012 ihrir 2016 Department Public Works: Utilities Contact Public Works Director Project # 01-CIP-UO02 Project Name Storm Drainage System Maintenance - Alley Repairs Future Description 2009-2013: Concrete alley repairs Justification (Annual alley pavement concrete slab repairs are needed. Prior Expenditures 49,000 Construction/Maintenance Total Total 18,000 19,000 20,000 20,000 21,000 98,000 T)pe Improvement Useful Life Unassigned Catekor� Utilities: Municipal Sanitary S Priorih n a Total Project Cost: $147,000 2012 2013 2014 2015 2016 Total 18,000 19,000 20,000 20,000 21,000 98,000 Prior Funding Sources 2012 2013 2014 2015 2016 Total 49,000 SU - Storm Sewer Fund 18,000 19,000 20,000 20,000 21,000 98,000 Total Total 18,000 19,000 20,000 20,000 21,000 98,000 Budget Impact/Other -onsistent with the Storm Water Management Plan. 96 0 1 0 1 ff c du +dor. Amc 21). 2011 CAPITAL IMPROVEMENT PLAN 2012 rhru 2016 Department Public Works: Utilities City of Hopkins, MN Contact Public Works Director Project # 01-CIP-UO03 Type Improvement Useful Life Unassigned Project Name Storm Water Management Projects Category Utilities: Storm Sewer Future Priority n/a Description Total Project Cost: $200,000 2014: Provide outlet pipe to Shady Oak Pond into CSAH 61 storm drainage piping in conjunction with Shady Oak Road Justification Shady Oak Pond has no outlet and floods streets and residential property if not pumped. Consistent with City Council approved action plan of October 21, 1997, the City's Storm Management Plan, and Shady Oak Road reconstruction timetable. I Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 200,000 200,000 Total • Funding Sources 2012 SU - Storm Sewer Fund 200,000 2013 2014 2015 200,000 200,000 2016 Total 200,000 Total 200,000 200,000 Budget Impact/Other Consistent with City Council approved Action Plan of October 21, 1997, the City's Storm Management Plan, and Shady Oak Road reconstruction timetable. • Wednesday, June 29, 2011 97 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-U000 Prosect name Meter Replacement Future Description Meter Replacement 2012 1hru 2016 Department Public Works: Utilities Contact Public Works Director Tape Improvement Useful Lite Category Utilities: Municipal Sanitary S Prioritc n/a Total Project Cost: $475,000 Justification Items identified in 2007 comprehensive utility plan to provide safe and reliable water. Prior Expenditures 2012 2013 2014 2015 2016 Total 285,000 Construction/Maintenance 95,000 95,000 Total Total 95,000 95,000 Prior Funding Sources 2012 2013 2014 285,000 WF - Water Fund 95,000 95,000 Total Total 95,000 95,000 Budget Impact/Other 98 190,000 190,000 2015 2016 Total 190,000 190,000 0 1 0 1 If'rdbi, cdai. Am,29. 1011 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-UO01 Project Name Lift Station # 4 Future Description Rehabilitate LS No. 4 2012 thru 2016 Department Public Works: Utilities Contact Public Works Director Type Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $160,000 Justification Lift station No. 4 was identified for rehab in the 2007 comprehensive utility plan Regular major maintenance identified in the 2007 comprehensive utility plan. Budget Impact/Other • Wednesday, June 29, 2011 99 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance Total • Funding Sources 2012 160,000 160,000 2013 2014 2015 2016 160,000 160,000 Total SF - Sanitary Sewer Fund 160,000 160,000 Total 160,000 160,000 Budget Impact/Other • Wednesday, June 29, 2011 99 CAPITAL IMPROVEMENT PLAN 2012 thri, 2016 City of Hopkins, MN oject # 08-CIP-UO08 oject Name Emergency Chlorine Shut Off Valves Future Description 3mer¢encv Chlorine Shut Off Valves Department Public Works: Utilities Contact Facilities Director I. pe Improvement l'scful Litc Catekor� Utilities: Municipal Sanitary S Priorit,N n,a Total Project Cost: $33,000 Justification Items identified in 2007 comprehensive utility plan to provide safe and reliable water. Expenditures Construction/Maintenance Total 2012 2013 33,000 33,000 2014 2015 2016 'Total 33,000 33,000 Funding Sources 2012 2013 2014 2015 2016 Total WF - Water Fund 33,000 33,000 Total 33,000 33,000 Budget Impact/Other • li c iln, vdw', Janc 29, 2011 • • CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Projcc(# 08-CIP-UO09 Project Name Sanitary Sewer Lift Station Maintenance Future Description regular LS Major Maintenance 2012 thru 2016 Department Public Works: Utilities Contact Facilities Director Justification Regular major maintenance identified in the 2007 comprehensive utility plan. Type Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $15,000 Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 15,000 15,000 Total 15,000 15,000 Funding Sources 2012 2013 2014 2015 2016 Total SF - Sanitary Sewer Fund 15,000 15,000 Total 15,000 15,000 101 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 tnt a 2016 City of Hopkins, MN Project # 08-CIP-UO10 Project Name St. Louis Park Emergency Connection Future Description St. Louis Park emergency connection. Department Public Works: Utilities Contact Facilities Director I ype Improvement t seful Life Cate„or. Utilities: Municipal Sanitary S Priority Na Total Project Cost: $211,000 Justification Items identified in 2007 comprehensive utility plan to provide safe and reliable water. Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 211,000 211,000 Total 211,000 211,000 Funding Sources 2012 2013 2014 2015 2016 Total WF - Water Fund 211,000 211,000 Total 211,000 211,000 Budget Impact/Other 102 • 11 crinwcdai. Jum, 21). 2011 • CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 11-CIP-S123 Project Name Storm Water Improvements - Cottageville Park Future 2012 thru 2016 Department Public Works: Utilities Contact Type Improvement Useful Life Category Utilities: Storm Sewer Priority n/a Description Total Project Cost: $250,000 These improvements provide water quality improvements fore Minnehaha Creek as outlined in the cooperative agreement with the Minnehaha Creek Watershed District for the renovation of the Blake Road/Lake Street/Cottaageville ?ark area. Justification Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 250,000 250,000 Total 250,000 250,000 C Funding Sources 2012 2013 2014 2015 2016 Total SU - Storm Sewer Fund 250,000 250,000 Total 250,000 250,000 Budget Impact/Other • 103 Wednesday, June 29, 2011 CAPITAL IMPROVEMENT PLAN 2012 Mri, 2016 Department Public Works: Utilities City Of Hopkins, MN Contact Facilities Director Project # l i-CIP-U01 )< Type Improvement Useful Life 50 years Project Name Emergency Water Connection with Edina Categorc Utilities: Municipal Water Syst Future Prioritc 2 Very Important Description Total Project Cost: $20,000 Chis project connects the Hopkins and Edina water systems to provide mutual aid in the case of an emergency. The )roject include the construction of an 8" waterline and valve across 2nd Street South in the South Presidential Justification Expenditures 2012 2013 2014 2015 2016 Total Construction/Maintenance 20,000 20,000 Total 20,000 20,000 Funding Sources 2012 2013 2014 2015 2016 Total WF - Water Fund 20,000 20,000 Total 20,000 20,000 Budget Impact/Other f[/m.] 0 Ilrc(nrcc/rn'. Jmt, 29. 20/ /