1986-25u
CITY OF HOPKINS
Hennepin County, Minnesota
RESOLUTION NO. 86- 25
RESOLUTION DECLARING COSTS TO BE ASSESSED AND
ORDERING PREPARATION OF PROPOSED ASSESSMENTS
WHEREAS, certain improvements, all as more fully described in Exhibit
'A' hereto attached and hereby made a part hereof have been previously
ordered and completed:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
HOPKINS, MINNESOTA, as follows:
1. That the cost of each such improvement to be specially assessed is
hereby declared to be the cost or the amount to be assessed, whichever is
greater, which appears in said Exhibit 'A'.
2. That the City Clerk, with the assistance of the City Engineer, shall
forthwith calculate the proper amount to be specially assessed for each such
improvement against every assessed piece or parcel of land within the various
districts or locations affected without regard to cash valuation, as provided
by law, and he shall file a copy of such proposed assessments in his office
for public inspection.
3. The Clerk shall, upon the completion of such proposed assessments,
notify the Council thereof.
Passed and adopted by the Council of the City of Hopkins, Minnesota,
this 20th day of May, 1986.
J. SCOTT RENNE,
City Clerk
JERRE MILLER,
City Attorney
ELLEN LAVIN-; -- �---____—._..__.
Mayor
e
E X H IB IT 'A'
1. Project 82-10: Street construction including curb and gutter on
Smetana Road (11th Street South) from 11th Avenue .South to the
west city limits, estimated cost being $252,504.83
2. Project 82-11: Storm sewer construction on Smetana Road (11th
Street South) from 11th Avenue South to the west city limits,
estimated cost being $18,721.98
3. Project 82-12: Street lighting on Smetana Road (11th. Street South)
from 11th Avenue South to the west city limits, extimated cost being
$15,479.78
® 4. Project 82-13: Bridge construction on Smetana Road by the installa-
tion,
nstallation, landscaping and lighting of a secondary road - pedestrian under-
pass bridge, estimated cost be $54,329.51
Smetana Drive Costs:
Total Cost $ 591,468.64
Hopkins Share 296,553.13
Project 82-10 Street Construction $ 219,569.42
+ 15% 32,935.41
252,504.83
82-11 Storm Sewer
16,279.98
+ 15%
2,442.00
18,721.98
82-12 Street Lighting
13,460.68
+ 15%
2,019.10
X15,479.78
82-13 Bridge
47,243.05
+ 15%
7,086.46
54,329.51
TOTAL