CR2012-089 (2013-2017 CIP Plani August 21, 2012 Council Report 2012-089 City of Hopkins 2013-2017 CAPITAL IMPROVEMENT PLAN Proposed Action Staff recommends adoption of the following motion: Move to adopt the 2013-2017 Capital Improvements Plan. Adoption of this motion will authorize staff to begin efforts to implement 2013 projects by including them in the 2013 budget process, and to begin the preliminary process for their implementation. Overview The Capital Improvements Plan is a planning document intended to help the City anticipate major capital items and to consider the financial impact of proceeding with those planned improvements. Discussions have been held with the Park Board and Planning Commission, as well as the City Council, in detailing proposed and necessary improvements. Staff is recommending adoption of the plan. Primary Issues to Consider • Does adoption of the CIP mean projects will be implemented? The CIP is a planning document, not an implementation action, and therefore, additional approvals will be necessary for projects to proceed. Appropriate notifications would also be made for those projects that have funding implications. • Are funds available for all projects? The plan outlines funding implications if all projects are implemented. Necessary funding changes have been anticipated as part of this plan, and are recommended therein Supporting Information • 2013-2017 CIP Power Point slides • 2013-2017 Capital Improvements Plan Christine M. Harkess, CPA, CGFM Finance Director Financial Impact: $ proiects included in budgets Budgeted: Y/N X N Source: Various Related Documents (CIP, ERP, etc.)- CIP Notes- • City of Hopktins CIP Background ■ The Capital Improvement Plan is a tool for long range capital planning and financial projections. ■ The plan is reviewed annually to ensure the overall objectives of City development, assessment of project needs and the City's fiscal capabilities. ■ Following are some highlights of the plan for 2013. 1 Funding Sources Taxes ■Special assessments ■Special fees ■Municipal state aid ■Utilities revenues -Other governmental units. The impact of specific capital projects are carefully considered prior to approval of the project. City Buildings Arts Center Carpeting — Theater and dressing rooms Seal floors in public restrooms & kitchen Activity Center Cafe on 14th oil Ems 2 ■ Parks ■ Play equipment in Oakes Park ■ Repair tennis courts in Central, Burnes and Oakes Parks ■ Burnes Park play courts — asphalt overlay & new color coating system ■ Skate Park Improvements Skate Park Improvements Pavilion ■ No projects for 2013 3 Street Improvements The city has a pavement management plan which provides information regarding scheduled street repairs and improvements Street Improvements • Municipal State Aid street improvements • Residential Street & Utility improvements • Total Estimated Cost - $6,410,000 El Street improvements - $3,800,000 El Utility improvements - $2,300,000 11 Other street/road improvements - $310,000 0 Utility Improvements ■ In most cases, where street reconstruction takes place, storm sewer facilities either need upgrading or replacement. ■ In some cases water main and sanitary sewer needs to be rehabilitated. ■ In 2013 we are anticipating $432,000 in miscellaneous utility improvements. Utility Improvements - other ■ Water Meter Replacement $ 95,000 ■ Storm Drainage System Maintenance $ 24,000 ■ Emergency Chlorine shut-off valves $ 33,000 ■ Cottageville Park storm water impry $250,000 ■ Emergency water connection w/Edina $ 20,000 r. Cottageville Park Alley with recent repairs 5 Conclusion 2013 Improvements Total $7,079,500 Funding ❑ Special Assessments $1,500,000 ❑ PIR/Bonding $2,495,000 ❑ Utility funds $2,732,000 ❑ Park Dedication funds $ 112,000 ❑ Capital Improvement fund $ 35,500 ❑ Private Sector funds $ 90,000 ❑Other Governmental Units $ 115,000 1.1 City of Hopkin CAPITAL IMPROVEMENT PLAN 2013-2017 30 F0 R AHEAD -r- City of Hopkins 1010 first Street South • Hopkins, MN 55343-7573 • Phone: 952-935-8474 • Fax• 952-935-1834 Web address: www.hopk*=.com DATE: August 2012 TO: Honorable Mayor and Members of the City Council FROM: Mike Morrison, City Manager SUBJECT: 2013-2017 CAPITAL IMPROVEMENT PLAN With this letter I respectfully submit the 2013-2017 Capital Improvement Plan. This five- year planning document represents the combined efforts of city staff, advisory commissions, citizens and the City Council. The Capital Improvement Plan is a five-year forecast of project needs in the City of Hopkins. It is intended to alert the Council and citizens to the major capital needs on the horizon. The first year of the plan becomes an adopted capital budget and relates almost completely to the operating budget that is approved on a yearly basis. The remaining four year represents an estimate of project needs and funding capabilities of the city. This year's plan does not include proposed equipment purchases. A document relating specifically to equipment replacement needs has been developed into a separate document. The Capital Improvement Plan is intended to serve as a planning tool and is therefore structured to present a meaningful, long-range perspective of the city's capital programming needs. At the same time, sufficient projected detail is provided to enable those who review the information to make informed decisions on the programming of projects over the next several years. Please use the information provided to formulate plans, projects and questions. The Capital Improvement Plan can serve the community best by provoking thoughts and actions. This document was developed by the Finance Department with assistance of all city departments. I want to especially thank all those involved in the development of the Capital Improvement Plan and especially Steve Stadler, Public Works Director, Kersten Elverum, Planning and Economic Development Director, Christine Harkess, Finance Director, and Debbie Sperling, Administrative Assistant for their hard work and dedication. Partnering with the Community to Enhance the Quality of Life + Inspire + Educate + Involve + Communicate 4 CAPITAL IMPROVEMENT PLAN 2013-2017 TABLE OF CONTENTS Pace City Manager's Message Table of Contents 2 Introduction Introduction and Purpose 4 Program Descriptions 5 Utilities Program 5 Transportation Program 6 Parks, Forestry, and Pavilion Program 9 General Public Buildings Program 8 Economic Development 11 Sources of Funding Sources of Funding 13 Funding Abreviations 16 Programs and Categories 17 Summary of Impacts on Major Funding Sources 19 Cash Flow Statements 33 Park Capital Improvement Fund 24 Capital Improvemetn Fund 25 Municipal State Aid Fund 26 Permanent Improvement Revolving Fund (PIR) 27 Water Utility Fund 28 Sewer Utility Fund 29 Storm Sewer Utiltiy Fund 30 Pavilion - Ice Arean Fund 31 Five -Year Project Summaries Projects by Year 33 Department Summary 35 Projects by Department 36 Funding Source Summary 39 Projects by Funding Source 40 Project Descriptions & Narratives Economic Development 44 General Public Buildings 49 Parks & Recreation 72 Streets 79 Utilities 96 2 Introduction INTRODUCTION AND PURPOSE The Capital Improvement Plan is a flexible plan based upon long-range physical planning and financial projections, which schedules the major public improvements that may be incurred by the City over the next five years. Flexibility of the Capital Improvement Plan is established through annual review, and revision if necessary. The annual review assures that the program will become a continuing part of the budgetary process and that it will be consistent with changing demands as well as changing patterns in cost and financial resources. Funds are appropriated only for the first year of the program, which is then included in the annual budget. The Capital Improvement Plan serves as a tool for implementing certain aspects of the City's comprehensive plan; therefore, the program describes the overall objectives of City development, the relationship between projects with respect to timing and need, and the City's fiscal capabilities. The Capital Improvement Plan can help assure: 1. A systematic approach to planning and initiating capital projects affording the opportunity to plan the location, timing, and financing of needed public improvements; 2. The development of a realistic program of capital spending within the City's projected fiscal capability to finance such projects, avoiding sharp change in the tax levy or bonded indebtedness; 3. The coordination of public and private improvement projects permitting adequate time for design and engineering to eliminate duplication of effort and expense; 4. The expenditure of public funds that is compatible with the City's adopted Comprehensive Plan; 5. That the public is kept informed of the proposed future projects and expenditures; 6. That private investors are aware of the City's long-range development program so that they may guide their development in a way that is compatible with the City's program; 7. Aid in achieving federal and/or state participation by providing the necessary planning and lead time necessary for a successful application in addition to meeting prerequisites needed for certain federal and state grants. a PROGRAM DESCRIPTIONS In order to effectively plan for and manage the projects contained in a Capital Improvement Plan, it is necessary to group similar activities into "Program Categories". The City of Hopkins' activities are divided into four program categories which are 1) Utilities, 2) Transportation, 3) Parks, Forestry and Pavilion, and 4) General Public Buildings. The City also includes an outline of proposed expenditures for unscheduled projects. Program categories are explained in the following sections. UTILITIES PROGRAM Program Description: The Utilities Program includes the municipal water, municipal sanitary sewer, storm sewer and refuse systems. Program Goal: Provide reliable, efficient, and safe utility service to all parts of the City with a minimum of adverse effects on the environment. Subprograms: Water, sanitary sewer, storm sewer, and refuse service. I. Municipal Water System Subprogram (WA) A. Subprogram Goal: The goal of the Municipal Water System subprogram is to provide water in sufficient quantities at sufficient pressure, with a high degree of reliability and safety to all parts of the City so as to satisfy the normal demands of the general public for water while at the same time providing sufficient reserves in case of fire emergency or power outages. B. Objectives: 1. Water quality shall meet the purity standards of the Minnesota Department of Health. 2. Any hydrant on the system shall, under maximum condition, deliver no less than 500 gallons per minute with a residual pressure of 20 pounds per square inch. 3. The system shall be looped to provide maximum reliability. 4. The supply and storage system shall be designed and maintained to have maximum reliability. 6i II. Municipal Sanitary Sewer Subprogram (SA) A. Subprogram Goal: The goal of the Municipal Sanitary Sewer subprogram is to promote a healthful environment by collecting all sewage from existing and projected development in a sanitary and economic manner. B. Objectives: 1. Provide sewer lines of adequate size and grade to collect and transmit all discharge sewage. 2. Prevent sewage from overflowing into the natural environment. 3. Prevent sewage back-ups. 4. Encourage or promote connection of all generators of sewage to the Municipal system. 5. Meet the effluent and infiltration standards of the Metropolitan Waste Control Commission. III. Storm Sewer Subprogram (SS) A. Subprogram Goal: Manage and control surface and ground waters in order to protect the man-made and natural environment in a safe and efficient manner. B. Objectives: 1. Prevent flooding. 2. Prevent damage to property due to erosion. 3. Meet water quality standards established by the controlling regulatory law or authority. TRANSPORTATION PROGRAM Program Description: This program includes streets, walkways, traffic signs and signals, vehicular parking facilities, and street lighting. Program Goal: Provide for the safe and efficient movement of people and goods throughout the city. 6 Subprograms: Streets, Walkways/Sidewalks, Signs/Signals, Parking Facilities, and Street Lights. I. Streets Subprogram (ST) A. Subprogram Goal: The goal of the Streets subprogram is to provide safe, convenient, economic public streets to best facilitate the movement of vehicular traffic. B. Objectives: Streets should be constructed with permanent surfaces, concrete curb and gutter, and with ancillary storm drainage, to standards established by the City. 2. Streets should be of a size and load capacity consistent with their functional classifications. 3. Timely major repair to preserve the basic capital investment in streets. II. Walkways/Sidewalks Subprogram (WS) A. Subprogram Goal: To provide a safe and convenient pedestrian system with incidental recreational benefits. III. Signs/Signals Subprogram (SI) A. Subprogram Goal: The goal of the Signs/Signals subprogram is to provide an efficient and orderly system of street and traffic signing so as to promote safe, convenient travel throughout the City. B. Objectives: Signs and signals should be installed in conformity with the Minnesota Manual on Uniform Traffic Control Devices. 2. Periodic surveys and studies should be made to document the effectiveness of City signing patterns. IV. Parking Facilities Subprogram (PA) A. Subprogram Goal: To provide such supporting facilities as will promote maximum use of public parking spaces by employers, employees, customers, and visitors. B. Objectives: 1. Provide parking facilities for present and anticipated needs of the City of Hopkins. V. Street Lights Subprogram (SL) A. Subprogram Goal: To provide a system of street lighting within the City that will promote safe and convenient vehicular and pedestrian travel on City Streets. B. Objectives: 1. To provide lighting at each street intersection within the City. 2. To provide mid -block street lighting in conformance with the City's street lighting policy, in order to provide equitable, cost efficient lighting. 3. To continually update the system so as to provide energy and cost efficient lighting. PARKS, FORESTRY AND PAVILION PROGRAM Program Description: This program includes community parks, neighborhood parks, open spaces, recreational structures and facilities. Program Goal: The goal of the Park and Recreation Program is to provide facilities for safe, stimulating, and comprehensive leisure time activities of Hopkins citizens. Subprograms: Neighborhood Facilities, Community Facilities I. Neighborhood Facilities Subprogram (NF) A. Subprogram Goals: To acquire ownership or use rights of park sites located to provide convenient walking access to all Hopkins citizens and to develop such sites to provide optimum recreational serviceability consistent with the preservation and enhancement of pleasing aesthetic qualities. B. Objectives: 1. Acquire property or use rights on those neighborhoods that do not have convenient walking access to neighborhood park facilities. 2. Develop neighborhood park facilities to meet the needs of various user groups. 8 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Preserve and enhance the aesthetic qualities of neighborhood parks. II. Community Facilities Subproaram (CF) A. Subprogram Goals: The goal of the Community Facilities subprogram is to develop, or acquire ownership or use rights of sites which serve the entire City and to provide facilities that serve community -wide needs. B. Objectives: 1. Acquire sites that have valuable and unique natural characteristics to preserve irreplaceable community resources. 2. Preserve by acquisition, gift, or other arrangement properties that have valuable historic -cultural qualities. 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Construct or acquire structures and facilities necessary to meet the changing needs of the community. GENERAL PUBLIC BUILDINGS PROGRAM Program Description: The General Public Buildings Program includes all municipal buildings except those provided for in the Utility and Park Facilities Program. Program Goal: Provide buildings that are adequate and convenient for the efficient accommodation of City functions. Subprograms: Administrative Offices, Maintenance Facilities, Fire Facilities, Community Center. I. Administrative Offices Subprogram (AO) A. Subprogram Goal: The goal of the Administrative Offices subprogram is to provide facilities for the efficient and safe conduct of legislative and administrative functions of the City. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of the City services. II. Maintenance Facilities Subprogram (MF) A. Subprogram Goal: The goal of the Maintenance Facilities subprogram is to provide facilities for the efficient and safe conduct of City maintenance functions. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of City services. III. Fire Facilities Subprogram (FF) A. Subprogram Goal: To provide a fire station, or stations, for storage of Fire Department equipment and for the training and meetings of volunteer fire fighters to provide prompt and efficient protection to life and property. B. Objectives: 1. Provide a maximum four -minute daytime and three-minute nighttime response to all points within the City. 2. Meet objective 1 through the use of volunteers. IV. Community Center Subprogram (CC) A. Subprogram Goal: To provide a community facility, or facilities, which meet the social, recreational, and cultural needs of all citizens, particularly senior citizens. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repairs. we, 2. Construct or acquire structures and facilities necessary to meet the changing needs of the City. 3. Upgrade facilities as necessary to provide for efficient, safe, and effective provision of City services. ECONOMIC DEVELOPMENT PROGRAM Program Description: This program includes redevelopment projects that have been identified through adopted plans and goals of the City of Hopkins. Program Goal: To facilitate the redevelopment of key sites in order to achieve the state objectives of the project. Objectives: 1. Elimination of blight or blighting conditions 2. Creation of jobs 3. Increase property value(s) 4. Catalyst of additional redevelopment 5. Environmental clean-up Increase transit -oriented development around LRT stations m Sources of Funding 12 SOURCES OF FUNDING In order to fund the anticipated Capital Improvements, the City must draw upon a variety of sources. Many of these sources have a specific or "dedicated" purpose (i.e., the water utility fund will finance water main installation but not a street overlay). Therefore, it is important to identify the uses and limitations of the various revenue sources. CURRENT REVENUES - GENERAL FUND (CR) This represents funding from current year revenue collections in the General Fund that support operations and capital outlay expenditures. Revenue sources include property tax levies, state aid payments, and various permit and license fees. This source of funding is generally used only for operations and small capital purchases. GENERAL FUND RESERVES (GR) Reserves of the general fund are the funds remaining after subtracting cash flow and emergency amounts from the City's cash balance, sometimes referred to as "fund balance". The use of General Fund Reserves is not recommended for Capital Improvements without significant staff and Council review. COMMUNICATION (formerly Cable TV) FUND (CT) This funding source consists of franchise fees received from the local Cable TV company, in excess of the amounts earmarked for the access programming and commission budgets. Expenditures are limited to cable -related facilities, or must have a cable related purpose. ECONOMIC DEVELOPMENT FUND (ED) This funding source was established by the Housing and Redevelopment Authority (HRA) and the City of Hopkins, to provide funding for the purpose of promoting development and redevelopment within the City. The Economic Development fund is a revolving fund administered by the HRA, intended to provide an ongoing funding source used to reduce or extend the long term debt involved with development and redevelopment activities. The HRA reviews all proposed uses of this fund on an individual basis. GRANT-IN-AID (GA) This is aid received from either the Federal or State government. In many cases, grants are made on matching basis, which means the City shares a portion of the costs of the project being funded. 13 MUNICIPAL STATE AID STREETS (MS) This funding source represents funds received from the State of Minnesota to support construction and maintenance of State Aid classified municipal streets. State law defines the types and limits of State Aid Streets expenditures. PERMANENT IMPROVEMENT REVOLVING/GENERAL OBLIGATION BONDS (PI) Improvements with a life of several years may be financed from the proceeds of a General Obligation Bond Issue. Law limits the total debt that can be incurred under this method of financing. With some exception, General Obligation Bonds are generally subject to a referendum process. Examples of projects, which may not require a referendum, are those financed through the use of special assessments where at least 20 percent of the project cost is assessed to the benefiting property owners. The remaining portion not assessed can be financed through general obligation bonds repaid by a tax levy. PRIVATE SECTOR FUNDING (PF) This funding source consists primarily of payments made by developers for the purchase of land, the installation of water, sewer, or streets or other related expenditures. It can also refer to donations made to the City by individuals or groups. OTHER GOVERNMENTAL UNITS (GU) These are funds received from Hennepin County, adjacent communities, etc. for projects that also benefit a jurisdiction other than the City of Hopkins. REVENUE BONDS (RB) These are bonds issued for improvements made for specific revenue producing facility or operation. The debt incurred is repaid from the revenue generated by the facility. If the revenue generated is insufficient, then the difference becomes an annual obligation of the taxpayers and becomes an additional tax levy. These are generally not subject to referendum. REAL ESTATE SALES FUND (RE) This funding source consists primarily of funds built up from the sale of City owned property. To date, the fund has been used for building improvements. Because the sale of both general City property and park/recreation property are accumulated into this fund, earmarking a portion for recreational purposes may be justified. 14 SPECIAL ASSESSMENT (SA) A number of projects may be realistically financed using Special Assessment to pay the ultimate cost. Almost any project can potentially be financed using the assessment process. In each case it is necessary to make a determination that the assessed property will benefit by the amount of the assessment. The cost of street reconstruction is shared by the property owner and the City. Special assessments to individual properties are capped per city policy. Concurrent improvement costs to the utility systems are assumed by the respective utility funds. TAX INCREMENT FINANCING (TF) This funding source results from the tax value of new development that is "incrementally" greater than the existing tax value. Typically, bonds are sold based on the assumption that the higher tax receipts will retire the bonds. However, the use of TIF funds through a "pay as you go" method has become more common. This type of funding can be used for public improvements within a redevelopment district to support the goals of redevelopment, specifically the elimination of blighted conditions. Approval of the Hopkins HRA should be anticipated prior to the commitment of these funds. State law strictly regulates the use of these funds. WATER FUNDS (WF) Water funds consist of revenue generated from the sale of water. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. SANITARY SEWER FUNDS (SF) Sanitary sewer funds consist of revenue generated from charges made for sewage disposal. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. STORM SEWER UTILITY REVENUES (SU) Storm sewer funds consist of revenue generated by charging storm water drainage fee to parcels of land for the availability and use of municipal storm sewer facilities. Expenditures from this funding source are related to drainage facilities. PAVILION FUND (PA) Pavilion Funds consist of revenues generated from rental fees collected from users of the Pavilion. These funds are utilized to pay for operating, and capital expenditures. 15 Funding Sources Communication (formerly Cable TV) Fund CT Current Revenues — General Fund CR General Fund Reserves GR Economic Development Fund ED Grant -In -Aid GA Housing and Redevelopment Authority HRA Municipal State -Aid Streets MS Other Government Units GU Park Dedication Fund PDF Pavilion Fund PA Permanent Improvement Revolving/General Obligation Bonds PI Private Sector Funds PF Real Estate Sales Fund RE Revenue Bonds RB Sanitary Sewer Fund SF Special Assessment SA Storm Sewer Fund SU Tax Increment Financing TF Water Fund WF 16 Programs and Categories Utilities Program Municipal Water System Category Municipal Sanitary Sewer Category Storm Sewer Category Transportation Program Streets Category Walkways/Sidewalks Category Signs/Signals Category Parking Facilities Category Street Lights Category Parks, Forestry and Pavilion Program Neighborhood Facilities Category Community Facilities Category General Public Buildings Program Administrative Offices Category Maintenance Facilities Category Fire Facilities Category Community Center Category Arts Center Category Economic Development Program 17 Summary of Impacts on Major Funding Sources 18 SUMMARY OF PROJECT IMPACTS ON MAJOR FUNDING SOURCES CURRENT REVENUES/GENERAL FUND RESERVES Expenditures for 2012 are budgeted at an increase of 2.5% over the 2011 budget. The 2012 budget was compiled as a maintenance budget following the State's change to Market Value Exclusion (MVE) from Market Value Homestead Credit and the uncertainty as to how that would impact values and the taxes placed on various properties. To keep the budget balanced we eliminated capital outlay from the General Fund, salaries were held at 2011 rates and implemented small cuts across all departments. The 2013 budget has begun with all departments again working towards a maintenance budget. The tax levy is the major source of revenues (82%) for the General Fund and therefore would need to increase if general fund operating and capital expenditures increase in 2013. Annually the legislature debates the future of tax levy limits which were reinstated for 2009 and again eliminated for . Unassigned fund balance in the General Fund totals $4,266,048 at the end of 2011 and is projected to remain at that level for 2012. The State Auditor's Office recommends no less than five month of operating expenditures in reserves. For 2012 five months of expenditures would total $4,398,552. At January 1, 2012 the fund balance was at 40.4% of budgeted expenditures. PERMANENT IMPROVEMENT REVOLVING FUND, (P.I.R.) - G.O. DEBT Funding from bonds is used to reimburse the P.I.R. fund for public improvement projects, which have been previously expended. The debt is funded by special assessment collections and city tax levies over a ten to fifteen year period. Bonds totaling $3,355,000 will be sold in 2012 to fund the 2011 and 2012 street improvement projects. The next bond sale is scheduled for 2013 and will be for the 2013 project that was originally scheduled for two years but was moved to 2013 to minimize the disruption of the neighborhood, get positive construction bids and a favorable bond rate. Those bonds are expected to total $4.2 million. The P.I.R. fund has completed substantial projects over the last three years totaling almost $5 million. This pace is expected to continue with scheduled projects for 2013 totaling $3,995,000 and future projects in the years 2014-2017 totaling over $8.97 million. Projects scheduled for 2013 include the Presidential Avenue S, and 1St S and 2 St S between Monroe and Harrison Streets along with W Park Rd. (see project 01-CIP-5101 for details), Mainstreet signal upgrades, Blake Road streetscape and replacement of the asphalt walk on Excelsior Blvd. The funding is provided for these projects by special assessments, $1,500,000 and PIR/Bonding, $2,495,000 for a total project estimated at $3,995,000. In the years 2014-2017 as mentioned above, the city has an aggressive residential street improvement schedule planned, in addition to major improvements to County Road 61 — Shady Oak Road, all of which will require bonding. 19 MUNICIPAL STATE AID FUND Funding for municipal state aid road projects comes from state MSA funding and is drawn down as projects are done. State funding is not sufficient for current planned projects as a significant draw was made on existing funds for the Co Rd 3 — Phase I project. This draw totaled $3,243,793 of which $2,907,829 has been paid from available allotments and $335,964 will come from future allotments as they become available in the years 2013 and forward. In addition in the queue is a request for $950,956 for the Minnetonka Mills Rd project and $894,020 for the 5°i St South project. These funds will be released once the Co Rd 3 funds are fully drawn down. This will push back receipt of funds for other eligible MSA funded projects; however those project requests will be placed in the queue for future allotment payments. Currently there is one MSA project scheduled for 2014-2015 and one for 2016. In 2014-2015 the County Road 61, Shady Oak Road project that involves the cities of Hopkins and Minnetonka, Hennepin County and the State will be done. The project is in the planning stages and has a tentative scheduled construction start date of 2014. The project is estimated at $20.4 million of which $2.8 is Hopkins share of the project of which $1.3 million is budgeted. The remaining $1.5 million is right-of-way acquisition costs for which we currently have no funding. We continue to work with Hennepin County and the City of Minnetonka to develop funding for this project. CAPITAL IMPROVEMENT FUND Funding for these improvements comes from a general tax levy that was implemented in 2005 at $25,000. With the exception of 2010 when the levy was eliminated due budget constraints as a result of the governors MVHC unallotment. we have been able to steadily increase this levy and it is budgeted at $125,000 for 2013. Projects scheduled in 2013 total $35,500 and are for flooring projects at the Arts Center. PARK IMPROVEMENT FUND The source of funding for this fund is development fees charged to developers for park development. Future funds are dependent on future development and redevelopment in the city. Projects scheduled for 2013 total $1 12,000 and include play equipment in Oakes Park, Burns Park tennis and play court maintenance and Skate Park improvement. While past redevelopment projects generated $384,000 in Park Dedication Fees those funds will shortly be exhausted if additional resources are not identified. Additional development projects in the planning stages are anticipated to bring in additional funds within the next year. The Park Board spent considerable time soliciting resident input on city parks and developed a long-range plan for the city's park system. 'This plan is the basis for future park improvements. WATER FUND Implementing the rates as proposed in the Utility Master Plan (UMP) along with a bond sale in 2012 provide the funding needed for projects scheduled over the next several years. 20 Projects planned for 2013 include $1,1,000 in water main improvements done in conjunction with street improvements, $95,000 for meter replacements, $33,000 for emergency choline shut- off valves and $20,000 for an emergency connection to the City of Edina. The public works facility improvement project annual transfer of $45,000 has been transferred to the Storm Sewer Utility fund for the years 2012-2023. As established by the Utility Master Plan completed in 2007 and reviewed every two years thereafter, annual incremental increases are planned for the next 17 years. Water rates will increase in 2013 by approximately 3%, and will be in line with the current UMP. SANITARY SEWER FUND Implementing the rates as proposed in the Utility Master Plan (UMP) along with a bond sale in 2012 provide the funding needed for projects scheduled over the next several years. Projects planned for 2013 include $700,000 in sewer main improvements done in conjunction with street improvement projects and $15,000 in Lift Station maintenance. In addition to the scheduled capital expenditures, the Metropolitan Waste Control Commission is projecting annual increases in its disposal charges to local governments. The public works facility improvement project annual transfer of $50,000 has been transferred to the Storm Sewer Utility fund for the years 2012-2023. As established by the Utility Master Plan completed in 2007 and reviewed every two years thereafter, annual incremental increases are planned for the next 17 years. Water rates will increase in 2013 by approximately 4%, and will be in line with the current UMP. STORM SEWER FUND The storm sewer utility issued bonds in 2003 to help cover infrastructure costs that were incurred prior to 2003. Bonds will be sold in 2012 for the 2011 and 2012 project costs. These bonds issues along with current revenues should provide the needed funding for scheduled projects. Projects scheduled for 2013 include $500,000 in storm sewer improvements done in conjunction with street improvement projects, $19,000 in storm drainage system maintenance and $250,000 in storm water improvements in Cottageville Park. The public works facility improvement project will cost the storm sewer enterprise $25,000 a year for twenty years (2004-2023). In addition beginning in 2012 the Storm Sewer Utility fund will absorb the public works facility transfers for both the water fund ($45,000) and the sewer fund ($50,000) for a total increased cost of $95,000. The most recent rate increase pursuant to the 2007 Utility Master Plan was done in 2009. This rate increase is expected to support the storm sewer system well into the future and currently no additional rates increases are proposed. 21 PAVILION FUND The Pavilion Fund was added to the CIP in 2006 to provide for future improvements that will be needed as this facility ages. As an Enterprise Fund capital items are usually funded within the fund but due to several large capital improvements over the past few years this fund while meeting its operational needs does not currently have adequate financial resources to meet future capital needs. Some of the improvements recently completed were done at the request of major leaseholders of the facility and are being paid by those leaseholders through long-term lease arrangements. This facility built in 1990 is starting to need repairs and replacement to areas that are heavily used; there are no capital projects scheduled for 2013, however in 2014-2017 facility projects totaling $375,000 will be needed. As part of the 2013 budget process funding of these Pavilion capital needs will need to be addressed as well as future infrastructure needs which will continue to increase as the building ages and facility use remains in high demand. TAX INCREMENT FINANCING FUNDS Considering all tax increment districts, as a whole cash on hand, projected increments and loan repayments are sufficient to cover TIF project expenditures. The state has provided municipalities with a pooling tool to accommodate short-term deficiencies within the districts. The city will be allowed to pool the districts tax increment revenues to cover outstanding debt. Currently none of the city's districts are projected to have shortfalls. 22 Cash Flow Statements 23 24 PARK CAPITAL IMPROVEMENTS FUND (301) 07/19/2012 Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 Working Capital Beginning Year 232,629 112,195 170,317 42,020 (53,560) (54,095) (55,718) Revenues: Taxes (from matured Park Bonds 1,346 Interest 1,585 1,122 1,703 420 (536) (1,623) (1,672) Dedication fees 0 128,000 0 0 0 0 0 Hennepin County Grant 150,000 Met Council - easememt/grant 50,000 300,000 Grants - Private Foundations 30,000 Donations - general 0 1,000 1,000 1,000 Donations - benches Transfer in - close fund 412 2,581 Total Revenues 5,512 360,122 302,703 1,420 (536) (1,623) (1,672) Expenditures: C.I.P. Projects 118,946 295,000 105,000 90,000 0 0 Cottageville Property Acquisition 319,000 Skate Park commitment 7,000 7,000 7,000 7,000 Total Expenditures 125,946 302,000 431,000 97,000 0 0 0 Working Capital Year End 112,195 170,317 42,020 (53,560) (54,095) (55,718) (57,390) 24 25 07/19/2012 CAPITAL IMPROVEMENTS FUND (305) Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 Working Capital Beginning Year 221,836 272,471 18,784 108,377 92,919 243,384 108,601 Revenues: Miscellaneous Interest 1,822 1,362 94 542 465 1,217 543 Federal Stimulus Funds Transfers In from General Fund Tax Levy 96,141 125,000 125,000 125,000 150,000 150,000 150,000 Total Revenues 97,963 126,362 125,094 125,542 150,465 151,217 150,543 Expenditures: Pavilion Projects Expenses - Audit 1,125 C.I.P. Projects 46,203 380,050 35,500 141,000 0 286,000 543,510 Transfer to General Fund Total Expenditures 47,328 380,050 35,500 141,000 0 286,000 543,510 Working Capital Year End 272,471 18,784 108,377 92,919 243,384 108,601 (284,366) 25 Working Capital Beginning Bal Revenues: State MSA Funds, projects Interest Earnings Total Revenues Expenditures: CIP State Aid Projects Total Expenditures Working Capital Ending Balance includes cash, interest rcvbl, & A'P Cash Balance 12/31/20XX Cash Balance 7/19/2012 ESTIMATED Cash Balance 12/31/20XX 07/19/2012 MUNICIPAL STATE AID FUND (302) Project Total Due Paid Balance Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 950.955.56 5th Street South 1.165,881.73 1,303,108 1,666,333 2,094,240 2.480.182 819.984 438,184 (279.289) 421.691 411,244 365,000 365.000 365,000 365,000 365,000 12,167 16,663 20.942 24,802 8,200 17,527 (11,172) 433,858 427.907 385.942 389.802 373,200 382,527 353,828 70,633 0 0 2.050,000 755,000 1,100,000 0 70.633 0 0 2.050,000 755.000 1,100,000 0 1,666,333 2.094.240 2.480.182 819,984 438,184 (279,289) 74,540 1,662,371 2,075,689 2,090,278 2,476,221 816,023 434,222 (283,250) 70,578 (3) Project Total Due Paid Balance State Aid Funds due City Total From State To Date Due 7/19112 Excelsior Blvd 5,408.756.28 3,243.792.74 2,907,828.85 335,963.89 Minnetonka Blvd 1.231,889.51 950,955.56 950.955.56 5th Street South 1.165,881.73 894,019.71 894,019.71 Total 7.806.527.52 5.088.768.01 2.907.828.85 2,180,939.16 65.19% 26 Cash Flow Analysis P.I.R. FUND (501) 07/19/2012 Working Capital Beginning Year Revenues: Special Assessment Revenues (1) Interest Bond Proceeds Total Revenues Expenditures: C.I.P. Projects C.I.P. Projects - Special Assm Transfers for SA Debt collected thru Assm Debt Service Transfers - 2007B Debt Service Transfers - 2010A - Impry Debt Service Transfers - 2010B - Rfdg Debt Service Transfers - 2012 debt ($1.289M) Debt Service Transfers - 2013 debt ($1.125M) Total Expenditures Working Capital Year End (1) Includes current, delinquent and penalties Total Projects Scheduled (CIP & SA) Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 1,814,430 563,533 2,271,527 2,002,589 1,597,188 4,084,248 1,486,434 788,484 700,668 568,551 558,298 725,584 754,518 821,876 6,440 2,536 10,222 9,012 7,187 18,379 6,689 3,286,510 3,500,000 5,000,000 1,500,000 794,924 3,989,714 4,078,773 567,310 5,732,771 772,897 2,328,565 1,795,110 1,095,000 2,495,000 620,000 1,600,000 1,865,000 1,566,000 900,000 1,500,000 0 1,200,000 1,060,000 1,064,000 71,900 71,900 71,900 71,900 71,900 71,900 71,900 120,592 156,600 156,600 156,600 156,600 156,600 156,600 58,219 58,219 124,211 124,211 124,211 124,211 124,211 93,000 93,000 93,000 2,045,821 2,281,719 4,347,711 972,711 3,245,711 3,370,711 3,075,711 563,533 2,271,527 2,002,589 1,597,188 4,084,248 1,486,434 739,288 1,795,110 1,995,000 3,995,000 620,000 2,800,000 2,925,000 2,630,000 27 WATER FUND - WORKING CAPITAL PROJECTION Actual Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 07/19/2012 Projected 2017 518,919 Working Capital Beginning Year (268.206) (488,484) 252.992 265.385 400,298 824,120 Revenues: Other Exp - int on current bonds 36,913 Operating Revenues 1.265.930 1,262,050 1.300.600 1.339.150 1,377.850 1,416,550 Other 132,583 129,480 140,280 152,149 158,533 165,235 Interest (2.329) 0 0 0 0 0 Bond Issuance 16.793 760,519 1.200.000 15,375 1,200,000 _ Total Revenues 1,396,184 2,152,049 2,640,880 1,491,299 2,736,383 1,581,785 Expenditures: 1,461, 500 172,272 0 1,633,772 Operation Expense 986,607 969,448 1,002,998 1,037,781 1,073,846 1,111,244 1,150,027 Other Exp - int on current bonds 36,913 0 0 Other Exp - int on refunded bonds 14,825 11,475 7,587 2,700 Other Exp - int on 2009 bonds 26,300 25,350 24,225 22,850 21,350 19.725 Other Exp - int on 2012 bonds 5.664 16.793 16,365 15,893 15,375 Other Exp - int on 2013 bonds 65,000 62,500 59,750 Other Exp - int on 2015 bonds 65,000 62,500 Equipment Replacement Items 0 0 75.000 0 6,800 0 61.700 Capital Improvements 384,169 190,000 1,248,000 0 800,000 411,000 200,000 Principal Bond payment 200,000 Principal Bond payment - refunded 165,000 170.000 175.000 180,000 Principal Bond pymnt - 2009 debt 45.000 50.000 50,000 50,000 50,000 50,000 Principal Bond pymnt - 2012 debt 40.000 45,000 45,000 45,000 45,000 Principal Bond pymnt - 2013 debt 50,000 55,000 60,000 Principal Bond pymnt - 2015 debt 50.000 55,000 Capital Lease (PW Facility) (1) 0 0 0 0 0 0 0 Total Expenditures 1,607,689 1,410,573 2,628,487 1,356,386 2,312,561 1,886,987 1,779,077 Change in available funds (211.505) 741,476 12,393 134,914 423,822 (305,202) (145,305) Inventory change 194 Bond Premium/Discount Exp (8,967) Working Capital Ending Year (488,484) 252,992 265,385 400,298 824.120 518.919 373,614 (1) Capital Lease moved to Storm Sewer Rate History 2012 - 2017 financial data was taken from the Utility Master Plan done by City Engineer 1984 $0.85 1993 $1.05 Notes - 1997 $1.10 Income - 2008 and forward used utility master plan rates (fixture/no surcharge option) 2000 $1.20 2005 $1.40 Per Utility Master Plan (10107) 2008 $1.65 2009 $1.86 2010 $1.90 2011 $1.94 - not increased, left at $1.90 2012 $1.96 2013 $2.02 2014 $2.08 projected rate 2015 $2.14 increases 2016 $2.20 2017 $2.27 28 Working Capital Beginning Year Revenues: Operating Revenues Other Interest Bond Issuance Total Revenues Expenditures: Operation Expense MWCC Charges (3% inflation) Interest Expense - 2009 Debt Interest Expense - 2012 Debt Interest Expense - 2013 Debt Interest Expense - 2015 Debt Equipment Replacement Items Capital Improvements Principal Bond payment (2009) Principal Bond payment (2012) Principal Bond payment (2013) Principal Bond payment (2015) Capital Lease (PW Facility) (1) Total Expenditures Change in available funds Inventory change Bond Premium/Discount Exp Working Capital Ending Year (1) Capital Lease moved to Storm Sewer Rate History 1983 $1.50 1989 $1.75 1991 $2.00 1993 $2.50 1999 $2.25 Rate DECREASE 2006 $2.50 rate increase Per Utility Master Plan (10107) 2008$2.70 2009$3.10 2010$3.40 2011 $3.70 - act 3.60 2012$375 2013 $3.90 projected rate 2014$4.05 increases 2015$4.21 2016$4.38 2017$4.55 these are the correct rates per the UMP SEWER FUND - WORKING CAPITAL PROJECTION 570,253 1,436,144 07/19/2012 Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 79,006 98,771 398,662 619,769 763,261 943,574 778,988 1,823,054 2,137,500 2,223,000 2,308,500 2,399,700 2,496,600 2,593,500 15,895 23,000 20,000 20,000 20,000 20,000 20,000 421 2,469 997 1,549 1,908 2,359 1,947 170,520 700,000 500,000 1,839,369 2,333,489 2,943,997 7330,049 2,921,608 2,518,959 2,615,447 473,113 516,840 534,037 1,148,036 1,309,108 1,371,126 32,651 32,650 31,450 1,277 0 0 0 114,363 115,000 715,000 50,000 60,000 60,000 10,000 0 0 0 1,818,163 2,033,598 2,722,890 21,207 299,891 221,107 0 (1,442) 98,771 398,662 619,769 551,833 570,253 1,436,144 1,504, 307 30,100 28,450 3,780 3,685 21,000 19,800 35,700 6,800 0 500,000 60,000 60,000 10,000 10,000 38,000 38,000 0 0 2,186,557 2,741,295 143,492 180,313 589,319 1,575,771 26,575 3,580 18,700 15,000 33,600 280,000 65,000 10,000 38,000 28,000 0 2,683,545 (164,586) 763,261 943,574 778,988 2009 - 2017 financial data was taken from the Utility Master Plan done by City Engineer 29 609,053 1,650,698 24,463 3,465 17,500 14,100 26,400 120,000 65,000 10,000 38,000 28,000 0 2,606,679 8,768 787,757 0711912012 STORM SEWER FUND - WORKING CAPITAL PROJECTION 30 Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 Working Capital Beginning Year 1,103,820 402,095 655,958 659,418 658,844 504,785 664,341 Revenues: Operating Revenues 796,587 802,140 802,140 802,140 802,140 802,140 802,140 Other 6,830 5,000 5,000 5,000 5,000 5,000 5,000 Interest 2,109 1,005 1,640 1,649 1,647 1,262 1,661 Bond Issuance 321,840 500,000 Total Revenues 805,526 1,129,985 1,308,780 808,789 808,787 808,402 808,801 Expenditures: Operation Expense 178,068 181,299 184,925 188,623 192,396 196,244 200,169 Bond Interest - existing 30,150 Bond Interest - 2009 refunded bonds 10,475 8,075 5,312 1,875 Bond Interest - 2010 bonds 16,348 15,935 15,348 14,585 13,623 12,485 Bond Interest - 2012 bonds 2,385 7,080 6,890 6,680 6,450 Bond Interest - 2013 bonds 15.000 14,100 13,300 12,500 Capital Outlay (per ERP) 0 0 0 0 0 0 0 Capital Improvements 148,011 368,000 769,000 220,000 370,000 181,000 131,000 2003 Principal Bond payment 910,000 2009 Principal Bond payment 115,000 120,000 120,000 125,000 125,000 2010 Principal Bond payment 60,000 70,000 65,000 70,000 70,000 70,000 2012 Principal Bond payment 15,000 20,000 20,000 20,000 20,000 2013 Principal Bond payment 28,000 28,000 28,000 28,000 Capital Lease - PW Facility (1) 120,000 120,000 120,000 120,000 120,000 120,000 120,000 Total Expenditures 1,501,229 876,122 1,305,320 809,363 962,846 648,846 600,604 Change in available funds (695,703) 253,864 3,460 (574) (154,059) 159,556 208,197 Inventory change (660) Bond Premium/Discount Exp (net) (5,362) Working Capital Ending Year 402,095 655,958 659,418 658,844 504,785 664,341 872,538 (1) In 2011 this includes Water, Sewer & Storm Sewer transfers Rate History (oer month) 1989 $4.75 per quarter 1991 $6.00 per quarter 1992 $2.50 1993 $3.00 1998 $3.20 1999 $4.00 2006 $4.50 2009 $5.00 30 Note: The School District lease expires in November 2013. A new lease will be negotiated with the School District, however a projected amount for the new lease is unknown at this time. The current lease amount of $38,000 was left as a placeholder. 31 PAVILION - ICE ARENA - WORKING CAPITAL PROJECTIONS 07/19/2012 Actual Projected Projected Projected Projected Projected Projected 2011 2012 2013 2014 2015 2016 2017 Working Capital Beginning Year (55,254) (39,521) 128,515 (19,591) (101,480) (123,904) (203,201) Revenues: Operating Revenues 340,319 357,335 375,202 393,962 413,660 434,343 456,060 Leases 38,000 38,000 38,000 38,000 38,000 38,000 38,000 current lease expires in 2013 Other 7,430 9,600 10,000 10,000 10,000 10,000 10,000 Donations (bleacher heating) 10,000 Equipment Certificates 185,000 Interest 1,573 Total Revenues 387,322 599,935 423,202 441,962 461,660 482,343 504,060 Expenditures: Operation Expense 348,446 358,899 369,666 380,756 392,179 403,944 416,063 Capital Outlay - - 185,000 - - - - Capital Improvements - 53,000 - 120,000 69,000 135,000 51,000 Payment on Equip Certific 1,032 23,095 22,905 22,695 22,465 Payment on Interfund Loan 23,143 20,000 15,609 - - - Total Expenditures 371,589 431,899 571,307 523,851 484,084 561,639 489,528 Change in available funds 15,733 168,036 (148,105) (81,890) (22,424) (79,297) 14,532 Working Capital Ending Year (39,521) 128,515 (19,591) (101,480) (123,904) (203,201) (188,669) Note: The School District lease expires in November 2013. A new lease will be negotiated with the School District, however a projected amount for the new lease is unknown at this time. The current lease amount of $38,000 was left as a placeholder. 31 Five Year Project Summaries City of Hopkins, MN CAPITAL IMPRO VEMENT PLAN 2013 thru 2017 PROJECTS BY YEAR Project Name Department Project # Priority Project Cost 2013 Activity Center Cafe on 14th Activity Center 09-CIP--AC032 n/a 90,000 Carpet Replacement: Theater and Dressing Rooms Arts Center 12- C/P-AR01 2 22,000 Seal Floors in Public Restrooms and Kitchen Arts Center 12-C/P-AR003 1 11,000 Replace Miniblinds with Roller Blinds Arts Center 12-C/P-AR004 1 2,500 Block 64 Redevelopment Project Development 06-C/P-D404 n/a 5,500,000 8th Ave Streetscape and parking facility Development 12-C/P-D408 n/a 5,000,000 Play Equipment - Oakes Park Public Works: Parks 08-C/P-P016 n/a 60,000 Repair Tennis Courts and Burnes Park Play Court Public Works: Parks 12-C/P-PO37 n/a 45,000 Residential Street Improvements Public Works: Streets/Traffic 01-C/P-S101 n/a 3,800,000 Residential Street Improvements --Utilities Public Works: Streets/Traffic 01-C/P-5102 n/a 2,300,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-C/P-5121 3 50,000 Blake Road Streetscape Public Works: Streets/Traffic 11-C/P-5122 n/a 200,000 Replace Asphalt Walk - Excelsior Blvd. Public Works: Streets/Traffic 12-C/P-SO38 n/a 60,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 19,000 Meter Replacement Public Works: Utilities 08-C/P-0000 n/a 95,000 Emergency Chlorine Shut Off Valves Public Works: Utilities 08-C/P-0008 n/a 33,000 Sanitary Sewer Lift Station Maintenance Public Works: Utilities 08-C/P-0009 n/a 15,000 Storm Water Improvements - Cottageville Park Public Works: Utilities 11-C/P-S 123 n/a 250,000 Emergency Water Connection with Edina Public Works: Utilities 11-C/P-0011 2 20,000 Skate Park Recreation 08-CIP-RO01 n/a 7,000 Total for 2013 17,579,500 2014 Replace Carpet - Activity Center Rooms Activity Center 08-C/P-AC015 n/a 36,000 Replace Gynmasium Roof - Activity Center Activity Center 08-C/P-AC018 n/a 105,000 Redevelopment, East Excelsior Boulevard Development 01-C/P-D401 n/a 2,000,000 Pavilion Roof Replacement Pavilion 09-C/P-PO26 1 120,000 Play Equipment - Park Valley Public Works: Parks 08-C/P-PO10 n/a 45,000 Play Equipment - Hilltop Park Public Works: Parks 08-C/P-PO14 n/a 45,000 County Road 61 (Shady Oak Road) Public Works: Streets/Traffic 01-C/P-5106 n/a 8,200,000 Highway 7 and 5th Ave North - Signal Replacement Public Works: Streets/Traffic 10-C/P- 5120 3 445,000 Plan, Design and Implement Railroad Quiet Zone Public Works: Streets/Traffic 11-C/P-S120 n/a 225,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-C/P-5121 3 50,000 2014 Street Overlay Project Public Works: Streets/Traffic 12-C/P-039 n/a 200,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 01-C/P-0002 n/a 20,000 Storm Water Management Projects Public Works: Utilities 01-C/P-0003 n/a 200,000 Skate Park Recreation 08 -0P -R001 n/a 7,000 Total for 2014 11,698,000 20 Blake Corridor Redevelopment Development 09-C/P-D406 n/a 5,000,000 Pavilion Gas Fired Rooftop Furnace Pavilion 09-C/P-PO25 n/a 9,000 Pavilion Evaporator Condenser Replacement Pavilion 09-C/P-PO36 n/a 60,000 Tuesday, August 07, 2012 33 Project Name 1)cp.0 uuent Project # PrioritN Project Cost Residential Street Improvements Public Works: Streets/Traffic 07-C/P-5101 n/a 2,300,000 Residential Street Improvements --Utilities Public Works: Streets/Traffic 01-CIP-5102 n/a 1,650,000 County Road 61 (Shady Oak Road) Public Works: Streets/Traffic 07-CIP-S106 n/a 12,250,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-CIP-5121 3 50,000 Light Rail Transit Stations (2) Public Works: Transportation 07-CIP-5502 n/a 150,000 Eighth Avenue LRT Corridor Public Works: Transportation 01-CIP-S503 n/a 200,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 07-CIP-0002 n/a 20,000 Depot Recreation Area Recreation 10-CIP-RO02 2 500,000 Total for 2015 22,189,000 2016 Activity Center - Raspberry Room Roof Replacement Activity Center 08-CIP-ACO24 n/a 80,000 City Hall Lobby Upgrade City Hall Administration 09-CIP-CH030 n/a 110,000 Replace Carpet and Apparatus Floor Finish - FD Fire 08-CIP-FDO79 n/a 56,000 Pavilion Overhead Door Improvement Pavilion 07-C/P-P374 n/a 40,000 Pavilion Indoor Turf Replacement Pavilion 10-CIP-P319 n/a 95,000 Replace Carpet - Police Station Police 08-CIP-PD016 n/a 40,000 Residential Street Improvements Public Works: Streets/Traffic 01-CIP-5101 n/a 2,500,000 Residential Street Improvements—Utilities Public Works: Streets/Traffic 01-C/P-5102 n/a 430,000 Citywide Concrete Alleys Public Works: Streets/Traffic 07-CIP-5103 n/a 75,000 County Road 3 Public Works: Streets/Traffic 01-CIP-5104 n/a 2,300,000 Sixth Street South (11th to 12th Avenue South) Public Works: Streets/Traffic 07-CIP-5504 n/a 500,000 Parking Lots - Lot 200 Public Works: Streets/Traffic 06-CIP-S 178 n/a 250,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-CIP-SI21 3 50,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 07-CIP-0002 n/a 21,000 Lift Station # 4 Public Works: Utilities 08-C/P-0001 n/a 160,000 St. Louis Park Emergency Connection Public Works: Utilities 08-C/P-0070 n/a 211,000 Total for 2016 6,918,000 2017 Activity Center - Lower Roof Replacement Activity Center 09-CIP-AC037 n/a 80,000 Replace 25 Ton Rooftop HVAC Unit - HCA Arts Center 08CIP-AR073 n/a 100,000 Replace theatre seats and backs Arts Center 12-CIP-AR002 1 138,510 Replace Information Desk and Kiosk Arts Center 12-CIP-AR005 1 5,000 Replace 15 Rooftop HVAC units - HCA Arts Center 72-C/P-AR036 n/a 220,000 Pavilion skate Tile Replacement/Lobby Improvement Pavilion 07-CIP-P373 n/a 45,000 Pavilion - Desiccant Repl of Dehumidification Syst Pavilion 70-CIP-P320 n/a 6,000 Residential Street Improvements Public Works: Streets/Traffic 07-CIP-5101 n/a 2,500,000 Residential Street Improvements --Utilities Public Works: Streets/Traffic 07-CIP-S702 n/a 430,000 Citywide Concrete Alleys Public Works: Streets7Traffic 01-CIP-5103 n/a 80,000 Mainstreet Traffic Signal Upgrades Public Works: Streets/Traffic 11-CIP-S727 3 50,000 Storm Drainage System Maintenance - Alley Repairs Public Works: Utilities 07-CIP-0002 n/a 21,000 Total for 2017 3,675,510 GRAND TOTAL 62.060,010 lucvda.v. 0-, '011 34 Department Activity Center Arts Center City Hall Administration Development Fire Pavilion Police Public Works: Parks Public Works: Streets/Traffic Public Works: Transportation Public Works: Utilities Recreation City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2013 thru 2017 DEPARTMENT SUMMARY 2013 2014 2015 2016 2017 Total 90,000 141,000 80,000 80,000 391,000 35,500 463,510 499,010 110,000 110,000 10,500,000 2,000,000 5,000,000 17,500,000 56,000 56,000 120,000 69,000 135,000 51,000 375,000 40,000 40,000 105,000 90,000 195,000 6,410,000 9,120,000 16,250,000 6,105,000 3,060,000 40,945,000 350,000 350,000 432,000 220,000 20,000 392,000 21,000 1,085,000 7,000 7,000 500,000 514,000 TOTA1, 17,579,500 11,698,000 22,189,000 6,918,000 3,675,510 67,060,010 35 1 icsclay..hwuyi 07, 2012 City of Hopkins, MN C'API "1'AL IMPR01 'EMENT PLAN 2013 till -t, 2017 PROJECTS BY DEPARTMENT Department Project# Priority- 2013 2014 2015 2016 2017 Total Activitv Center Replace Carpet - Activity Center Rooms 08-CIP-AC015 n/a 36,000 36,000 Replace Gynmasium Roof - Activity Center 08-CIP-AC078 n/a 105.000 105,000 Activity Center- Raspberry Room Roof Replacement 08-CIP-ACO24 n/a 80,000 80,000 Activity Center - Lower Roof Replacement 09-CIP-AC037 n/a 80,000 80,000 Activity Center Cafe on 14th 09-CIP-AC032 n/a 90,000 90,000 Activity Center Total 90,000 141,000 80,000 80,000 391,000 Arts Center Replace 25 Ton Rooftop HVAC Unit- HCA 08CIP-AR013 n/a 100,000 100,000 Carpet Replacement: Theater and Dressing Rooms 12- CIP-ARO7 2 22,000 22,000 Replace theatre seats and backs 72-C/P-AR002 1 138,510 138,510 Seal Floors in Public Restrooms and Kitchen 72-CIP-AR003 1 11,000 11,000 Replace Miniblinds with Roller Blinds 12-C/P-AR004 1 2,500 2,500 Replace Information Desk and Kiosk 72 CIP-AR005 1 5,000 5,000 Replace 15 Rooftop HVAC units - HCA 72-CIP-AR036 n/a 220,000 220,000 Arts Center Total 35,500 463,510 499,010 City Hall Administration City Hall Lobby Upgrade 09-CIP-01030 n/a 110.000 110,000 City Hall Administration Total 110,000 110,000 Development Redevelopment, East Excelsior Boulevard 01-CIP-D407 n/a 2.000.000 2000,000 Block 64 Redevelopment Project 06-CIP-D404 n/a 5.500.000 5,500,000 Blake Corridor Redevelopment 09-CIP-D406 n/a 5,000,000 5,000,000 8th Ave Streetscape and parking facility 72-CIP-0408 n/a 5.000.000 5,000,000 Development Total 10,500,000 2,000,000 5,000,000 17,500,000 Fire � Replace Carpet and Apparatus Floor Finish - FD 08-CIP-FDO19 n/a 56,000 56,000 Fire Total 56,000 56,000 [Pavilion Pavilion skate Tile ReplacemenULobby Improvement 07-CIP-P313 n/a 45,000 45,000 Pavilion Overhead Door Improvement 07-CIP-P374 n/a 40.000 40,000 Pavilion Gas Fired Rooftop Furnace 09-CIP-PO25 n/a 9,000 9,000 Pavilion Roof Replacement 09-CIP-PO26 1 120.000 720,000 Pavilion Evaporator Condenser Replacement 09-CIP-PO36 n/a 60,000 60,000 Pavilion Indoor Turf Replacement 70-CIP-P319 n/a 95,000 95,000 Pavilion - Desiccant Repl of Dehumidification Syst 70 CIP-P320 n/a 6,000 6.000 36 li/csdae...la,,��c� 11'. ?III_' Department Project# Priority 2013 2014 2015 2016 2017 Total Pavilion Total 120,000 69,000 135,000 51,000 375,000 jPolice Replace Carpet - Police Station 08-C/P-PD016 n/a 40,000 40,000 Police Total 40,000 40,000 Public Works: Parks Play Equipment - Park Valley 08-C/P-Polo n/a 45,000 45,000 Play Equipment - Hilltop Park 08-C/P-PO14 n/a 45,000 45,000 Play Equipment - Oakes Park 08-C/P-P076 n/a 60,000 60,000 Repair Tennis Courts and Burnes Park Play Court 72-C/P-PO37 n/a 45,000 45,000 Public Works: Parks Total 105,000 90,000 195,000 - - -i Public Works: Streets/Traffic Residential Street Improvements 01-C/P-5701 n/a 3,800,000 2,300,000 2,500,000 2,500,000 11,100,000 Residential Street Improvements --Utilities 01-C/P-S102 n/a 2,300,000 1,650,000 430,000 430,000 4,810,000 Citywide Concrete Alleys 07-C/P-5703 n/a 75,000 80,000 755,000 County Road 3 01-ClP-S104 n/a 2,300,000 2,300,000 County Road 61 (Shady Oak Road) 07-C1P-5106 n/a 8,200,000 12,250,000 20,450,000 Sixth Street South (11th to 12th Avenue South) 07-C1P-5504 n/a 500,000 500,000 Parking Lots - Lot 200 06-C1P-S 118 n/a 250,000 250,000 Highway 7 and 5th Ave North - Signal Replacement 10-C/P- 5120 3 445,000 445,000 Plan, Design and Implement Railroad Quiet Zone 11-C/P-5120 n/a 225,000 225,000 Mainstreet Traffic Signal Upgrades 77-C/P-S721 3 50,000 50,000 50,000 50,000 50,000 250,000 Blake Road Streetscape 71-C/P-5122 n/a 200,000 200,000 2014 Street Overlay Project 72-C/P-039 n/a 200,000 200,000 Replace Asphalt Walk - Excelsior Blvd. 72-C/P-5038 n/a 60,000 60,000 Public Works: Streets/Traffic Total 6,410,000 9,120,000 16,250,000 6,105,000 3,060,000 40,945,000 (Public Works: Transportation Light Rail Transit Stations (2) 07-C/P-5502 n/a 150,000 150,000 Eighth Avenue LRT Corridor 01-ClP-5503 n/a 200,000 200,000 Public Works: Transportation Total 350,000 350,000 Fp­ublic Works: Utilities Storm Drainage System Maintenance - Alley Repairs 07-C/P-0002 n/a 19,000 20,000 20,000 21,000 21,000 101,000 Storm Water Management Projects 01-CIP-0003 n/a 200,000 200,000 Meter Replacement 08-C/P-0000 n/a 95,000 95,000 Lift Station # 4 08-CIP-0001 n/a 160,000 160,000 Emergency Chlorine Shut Off Valves 08-C/P-0008 n/a 33,000 33,000 Sanitary Sewer Lift Station Maintenance 08-CIP-0009 n/a 15,000 75,000 St. Louis Park Emergency Connection 08-CIP-0010 n/a 211,000 277,000 Storm Water Improvements - Cottageville Park 11-C1P-S 723 n/a 250,000 250,000 Emergency Water Connection with Edina 11-C/P-0011 2 20,000 20,000 Public Works: Utilities Total 432,000 220,000 20,000 392,000 21,000 1,085,000 Recreation Skate Park 08-CIP-ROOI n/a 7,000 7,000 14,000 Depot Recreation Area 70-CIP-RO02 2 500,000 500,000 Recreation Total 7,000 7,000 500,000 514,000 37 Tuesdav, August 07, 2012 Department GRAND TOTAL Project# Priority 2013 2014 2015 2016 2017 Total 17,579,500 11,698,000 22,189,000 6,918,000 3,675,510 62,060,010 38 hi,xday.-higucl ll'_ 2012 City of Hopkins, MN CAPITAL IMPROVEMENT PLAN 2013 li,ru 2017 FUNDING SOURCE SUMMARY Source 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 35,500 141,000 286,000 543,510 7,006,010 ED - Economic Development Fund 7,000,000 7,000,000 GU- Other Governmental Units 115,000 6,450,000 11,645,000 1,600,000 79,810,000 MS - Municipal State Aid Streets 2,050,000 755,000 1,100,000 3,905,000 PA - Pavilion Fund 120,000 69,000 135,000 51,000 375,000 PDF- Park Dedication Fund 112,000 97,000 209,000 PF - Private Sector Funds 90,000 90,000 PI - PIR/General Obligation Bonds 2,495,000 620,000 1,600,000 1,865,000 1,566,000 8,746,000 SA - Special Assessment 1,500,000 1,200,000 1,060,000 1,064,000 4,824,000 SF - Sanitary Sewer Fund 715,000 500,000 280,000 120,000 1,615,000 SU -Storm Sewer Fund 769,000 220,000 370,000 181,000 131,000 7,677,000 TF - Tax Increment Financing 3,500,000 2,000,000 5,250,000 10,750,000 WF - Water Fund 1,248,000 800,000 411,000 200,000 2,659,000 GRAND TOTAL 17,579,500 11,698,000 22,189,000 6,918,000 3,675,510 62,660,010 Tursdav, .-lugus! 07, 2012 39 City of Hopkins, MN CAPUAL 1.11PROFEMENT PLAN 2013 IIIR, 2017 PROJECTS BY FUNDING SOURCE Source 1'rojcct# I'riorit' 2013 2014 2015 2016 2017 Total CI - Capital Improvement Fund 1 Replace Carpet - Activity Center Rooms 08-CIP AC075 n/a 36,000 36,000 Replace Gynmasium Roof -Activity Center 08-C/P-AC018 n/a 105,000 105,000 Activity Center- Raspberry Room Roof Replacement 08-CIP-ACO24 n/a 80,000 80,000 Replace 25 Ton Rooftop HVAC Unit - HCA 08CIP-AR073 n/a 100,000 100,000 Replace Carpet and Apparatus Floor Finish - FD 08-CIP-FDO19 n/a 56,000 56,000 Replace Carpet - Police Station 08-CIP-PD016 n/a 40,000 40,000 Activity Center - Lower Roof Replacement 09-CIP-AC037 n/a 80,000 80,000 City Hall Lobby Upgrade 09-CIP-CH030 n/a 110,000 110,000 Carpet Replacement: Theater and Dressing Rooms 12- CIP-AR07 2 22.000 22,000 Replace theatre seats and backs 12-CIP-AR002 1 138,510 138,510 Seal Floors in Public Restrooms and Kitchen 12-CIP-AR003 1 11,000 11,000 Replace Miniblinds with Roller Blinds 12-CIP-AR004 1 2,500 2,500 Replace Information Desk and Kiosk 12-CIP-AR005 1 5,000 5,000 Replace 15 Rooftop HVAC units - HCA 12-CIP-AR036 n/a 220,000 220,000 Cl - Capital Improvement Fund Total 35,500 141,000 286,000 543,510 1,006,010 ED - Economic Development Fund Block 64 Redevelopment Project 06-CIP-D404 n/a 2,000,000 2,000,000 8th Ave Streetscape and parking facility 12-CIP-D408 n/a 5,000,000 5,000,000 ED - Economic Development Fund Total 7,000,000 7,0001000 GU - Other Governmental Units County Road 3 01-CIP-5104 n/a 1,600,000 1,600,000 County Road 61 (Shady Oak Road) 01-CIP-5106 n/a 6,150,000 11,045,000 17,195,000 Eighth Avenue LRT Corridor 01-CIP-5503 n/a 100,000 100,000 Highway 7 and 5th Ave North - Signal Replacement 10-CIP- 5120 3 300,000 300,000 Depot Recreation Area 10-CIP-RO02 2 500,000 500,000 Blake Road Streetscape 11-CIP-5122 n/a 100,000 100,000 Replace Asphalt Walk - Excelsior Blvd. 12-CIP 5038 n/a 15,000 75,000 GU - Other Governmental Units Total 115,000 6,450,000 11,645,000 1,600,000 19,810,000 MS - Municipal State Aid Streets County Road 3 01-CIP-5104 n/a 700,000 700,000 County Road 61 (Shady Oak Road) 01-CIP-5106 n/a 2.050,000 755,000 2,805,000 Sixth Street South (11th to 12th Avenue South) 01-CIP-5504 n/a 400,000 400,000 MS - Municipal State Aid Streets Total 2,050,000 755,000 1,100,000 3,905,000 PA - Pavilion Fund 40 I'm sdat-lu,Luct U-1.'012 Source Project# Priority 2013 2014 2015 2016 2017 Total Pavilion skate Tile Replacement/Lobby Improvement 07-C/P-P313 n/a Pavilion Overhead Door Improvement 07-C/P-P314 n/a Pavilion Gas Fired Rooftop Furnace 09-C/P-PO25 n/a Pavilion Roof Replacement 09-C/P-PO26 1 Pavilion Evaporator Condenser Replacement 09-C/P-PO36 n/a Pavilion Indoor Turf Replacement 10-C/P-P319 n/a Pavilion - Desiccant Repl of Dehumidification Syst 70-C/P-P320 n/a PA - Pavilion Fund Total 120,000 69,000 135,000 51,000 375,000 PDF- Park Dedication Fwd 45,000 45,000 Play Equipment - Park Valley 08-C/P-Polo n/a Play Equipment - Hilltop Park 08-C/P-P014 n/a Play Equipment - Oakes Park 08-C/P-POI6 n/a Skate Park 08-CIP-RO01 n/a Repair Tennis Courts and Burnes Park Play Court 12-C/P-PO37 n/a PDF- Park Dedication Fund Total 11-C/P-S 720 90,000 IPF - Private Sector Funds 1 90,000 Activity Center Cafe on 14th 09-CIP-AC032 n/a PF - Private Sector Funds Total PI - PIR/General Obligation Bonds Residential Street Improvements 45,000 45,000 2,300,000 40,000 40,000 6,650,000 9,000 9,000 n/a 120,000 120,000 15,000 16,000 60,000 60,000 07-CIP-5106 95,000 95,000 Lift Station # 4 6,000 6,000 Sixth Street South (11th to 12th Avenue South) 120,000 69,000 135,000 51,000 375,000 SF - Sanitary Sewer Fund Total 45,000 45,000 100,000 45,000 45,000 60,000 60,000 7,000 7,000 14,000 45,000 3 45,000 112,000 97,000 209,000 90,000 11-C/P-S 720 90,000 90,000 225,000 90,000 Residential Street Improvements 07-CIP-S101 n/a 2,300,000 07-CIP-5703 1,350,000 1,500,000 1,500,000 6,650,000 Citywide Concrete Alleys 01-C/P-5703 n/a 15,000 16,000 31,000 County Road 61 (Shady Oak Road) 07-CIP-5106 n/a n/a Lift Station # 4 200,000 200,000 Sixth Street South (11th to 12th Avenue South) 07-CIP-5504 n/a SF - Sanitary Sewer Fund Total 700,000 100,000 100,000 Parking Lots - Lot 200 06-CIP-S 178 n/a 160,000 200,000 200,000 Highway 7 and 5th Ave North - Signal Replacement 10-C/P- 5720 3 145,000 715,000 145,000 Plan, Design and Implement Railroad Quiet Zone 11-C/P-S 720 n/a 225,000 225,000 Mainstreet Traffic Signal Upgrades 11-C/P-S 121 3 50,000 50,000 50,000 50,000 50,000 250,000 Blake Road Streetscape 11-CIP-5122 n/a 100,000 100,000 2014 Street Overlay Project 12-C/P-039 n/a 200,000 200,000 Replace Asphalt Walk - Excelsior Blvd. 72-CIP-5038 n/a 45,000 45,000 PI - PIR/General Obligation Bonds Total SA - Special Assessment Residential Street Improvements 07-CIP-5707 n/a Citywide Concrete Alleys 07-CIP-5703 n/a County Road 61 (Shady Oak Road) 07-CIP-5106 n/a SA - Special Assessment Total �SF - Sanitary Sewer Fund 64,000 124,000 Residential Street Improvements --Utilities 01-CIP-5102 n/a Lift Station # 4 08-CIP-0001 n/a Sanitary Sewer Lift Station Maintenance 08-CIP-0009 n/a SF - Sanitary Sewer Fund Total 700,000 500,000 2,495,000 620,000 1,600,000 1,865,000 1,566,000 8,146,000 1,500,000 950,000 1,000,000 1,000,000 4,450,000 60,000 64,000 124,000 250,000 250,000 1,500,000 1,200,000 1,060,000 1,064,000 4,824,000 700,000 500,000 120,000 120,000 1,440,000 160,000 760,000 15,000 75,000 715,000 500,000 280,000 120,000 1,615,000 Es 1'ucsdaY. August 07. 2012 Source ProjeCIP Priurit% 2013 2014 2015 2016 2017 Total SU - Storm Sewer Fund 500,000 Residential Street Improvements -Utilities 07-CIP-5102 Storm Drainage System Maintenance - Alley Repairs 01-CIP-0002 Stone Water Management Projects 07-CIP-0003 Parking Lots - Lot 200 06-CIP-S I78 Stone Water Improvements - Cottageville Park 11-CIP-S 723 SU - Storm Sewer Fund Total 707,000 TF - Tax Increment Financing � Redevelopment, East Excelsior Boulevard 07-CIP-D407 Light Rail Transit Stations (2) 07-CIP-S502 Eighth Avenue LRT Corridor 01-CIP-5503 Block 64 Redevelopment Project 06-CIP-D404 Blake Corridor Redevelopment 09-CIP-D406 TF - Tax Increment Financing Total 50,000 WF - Water Fund 250,000 Residential Street Improvements -Utilities 01-CIP-5102 Meter Replacement 08-CIP-0000 Emergency Chlorine Shut Off Valves 08-CIP-0008 St. Louis Park Emergency Connection 08-CIP-0010 Emergency Water Connection with Edina 11-CIP-0017 WF- Water Fund Total 1,671,000 GRAND TOTAL n/a 500,000 350,000 110,000 110,000 7,070,000 n/a 19,000 20.000 20,000 21,000 21,000 707,000 n/a 200,000 200,000 n/a 50,000 50,000 n/a 250,000 250,000 769,000 220,000 370,000 181,000 131,000 1,671,000 n/a 2,000,000 2,000,000 n/a 150,000 750,000 n/a 100,000 700,000 n/a 3,500.000 3,500,000 n/a 5,000,000 5,000,000 3,500,000 2,000,000 5,250,000 10,750,000 n/a 1,100,000 800,000 200,000 200,000 2,300,000 n/a 95.000 95,000 n/a 33.000 33,000 n/a 211,000 217,000 2 20.000 20,000 1,248,000 800,000 411,000 200,000 2,659,000 17,579,500 11,698,000 22,189,000 6,918,000 3,675,510 62,060,010 42 /iax,/,n. iu,11,1 U _'0/' Project Descriptions And Narratives 43 Economic Development CAPITAL IMPROVEMENT PLAN 2013 darn 2017 City of Hopkins, MN Project # 01-CIP-D401 Project Name Redevelopment, East Excelsior Boulevard Future Department Development Contact ED Director Type Improvement Useful Life Unassigned Category Economic Development Priority n/a Description Total Project Cost: $2,000,000 forth side of Excelsior Boulevard from Highway 169 to approximately Blake Road. tedevelopment of older commercial area. Based on the adopted redevelopment plan, it would involve commercial, and residential uses. Identified n the East End Redevelopment Study. Justification :xcelsior Boulevard was upgraded in this area, providing for additional property on the north side of the roadway. The buildings in this area are rider and no longer the highest and best use for this property. The funding amount is an estimate and will vary depending on the scope and timing rf the project. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 2,000,000 2,000,000 Total 2,000,000 2,000,000 Funding Sources 2013 2014 2015 2016 2017 Total TF - Tax Increment Financing 2,000,000 2,000,000 Budget Impact/Other Total 2,000,000 2,000,000 45 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 Mrit 2017 City of Hopkins, MN Project # 06-CIP-D404 Project Name Block 64 Redevelopment Project Future Department Development C onlact ED Director Tc pe Improvement I whit Life ( atcgor� Economic Development Priority n,a Description loud Project Cost: $5,500,000 Redevelopment of block between 5th and 6th Avenues. north of MainsUret. South of I st Street North. There currently is no proposed schedule for construction. Justification Will redevelop older commercial and residential areas. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 5,500,000 5,500,000 Total 5,500,000 5,500,000 Funding Sources 2013 2014 2015 2016 2017 Total ED - Economic Development F 2,000,000 2,000,000 TF - Tax Increment Financing 3,500,000 3,500,000 Total 5,500,000 5,500,000 Budget Impact/Other 46 III( dw. a-. '0/ , CAPITAL IMPROVEMENT PLAN 2013 ih, a 2017 City of Hopkins, MN Project # 09-CIP-D406 Project Name Blake Corridor Redevelopment Future Redevelopment of properties along the Blake Road Corridor including the Cottageville Park area. Department Development Contact ED Director Type Improvement Useful Life Category Economic Development Priority n/a Total Project Cost: $5,000,000 Justification 2emoval of blighted and/or obsolete structures, improve access to transit and improve livability of the area. Expenditures 2013 2014 2015 2016 2017 Total Land Acquisition/Demolition 5,000,000 5,000,000 Total 5,000,000 5,000,000 Funding Sources 2013 2014 2015 2016 2017 Total TF - Tax Increment Financing 5,000,000 5,000,000 Budget Impact/Other Total 5,000,000 5,000,000 47 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 ihru 2017 City of Hopkins, MN Project # 12-CIP-D408 Project Name 8th Ave Streetscape and parking facilitN Future Department Development Contact ED Director 1'.N pe Improvement l schil Lite 5,000,000 2013 2014 Category Economic Development Priority n'a Description Total Project ('os(: $5,000,000 Sidewalks, landscaping, Public Art, Bike Lancs. Street furniture. and other pedestrian and bike improvements. Parking Ramp Construction, north of Mainstreet between Sth and 9th Avc South Justification Che City of Hopkins has planned for Sth Avcnuc to be the gateway to the dovv ntown from Excelsior Blvd to the Hopkins SW LRT Station. For this o be accomplished, 8th Ave must be transformed into a pedestrian and bike friendly two -block stretch. Che proposed parking ramp will be used to support transit -oriented development. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 5,000,000 5,000,000 Total Funding Sources 5,000,000 2013 2014 5,000,000 2015 2016 2017 Total ED - Economic Development F 5,000,000 5,000,000 Total 5,000,000 5,000,000 Budget Impact/Other LCA TOD Grant, various grant development Accounts. Bonds 48 General Public Buildings 49 CAPITAL IMPROVEMENT PLAN 2013 ,n,„ 2017 City of Hopkins, MN Project # 08-CIP-AC015 Project Name Replace Carpet - Activity Center Rooms Future Description teplace Carpeting in Activity Center Raspberry Roosts, TV, Game Room; hallways. Justification Carpet is 18 years old, worn and requires replacement. Deparunent Activity center Contact Facilities Director ,1.\ pe Improvement I ~cilli Life Cate ore Buildings: Activity Center Prioritc nra Total Project Cost: $36,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 36,000 36,000 Total 36,000 36,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 36,000 36,000 Budget Impact/Other Total 36,000 36,000 50 htcc lur. ,Im-gtq u' 'Ul_' CAPITAL IMPROVEMENT PLAN 2013 rhru 2017 City of Hopkins, MN Project # 08-CIP-AC018 Project Name Replace Gynmasium Roof - Activity Center Future Department Activity Center Contact Public Works Director Type Improvement Useful Life 25 years Category Buildings: Activity Center Priority n/a Description Total Project Cost: $105,000 Existing roof was installed in 1989 and is at the end of its projected useful life. Portion is cost share with Raspberry Ridge Condo Assn. Justification goof was installed in 1989 and is at the end of its 25 year useful life. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 105,000 105,000 Total 105,000 105,000 Funding Sources 2013 2014 2015 2016 2017 Total CI - Capital Improvement Fund 105,000 105,000 Budget Impact/Other Total 105,000 105,000 51 Tuesday, August 07, 20/2 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08-CIP-ACO24 Project Name Activity Center - Raspberry Room Roof Replacement Future Department Activity Center Contact PW Director .N pe Improvement I wful Life Category Buildings: Activity Center Priorih n a Description Total Project Cost: $80,000 Built up asphalt rooting system covering Raspberry Rooms, Craft Room and Hallways at the Activity Crntcr Justification Existing roof was replaced in 1992, Expected life is 25 years. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 80,000 80,000 Total 80,000 80,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 80,000 80,000 Total 80,000 80,000 Budget Impact/Other nspection, repair and upkeep of rooting systems prevent deterioration of interior building structure and damage to interior components of building. 52 CAPITAL IMPROVEMENT PLAN 2013 rhru 2017 City of Hopkins, MN Project # 09-CIP-AC031 Project Name Activity Center - Lower Roof Replacement Future Built up Roof on Activity Center Raspberry Rooms and Hallway. Justification Existing roof was installed in 1992, estimated replacement due in 2017. Department Activity Center Contact PW Director Type Improvement Useful Life 25 years Category Buildings: Activity Center Priority n/a Total Project Cost: $80,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 80,000 80,000 Total 80,000 80,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 80,000 80,000 Total 80,000 80,000 Budget Impact/Other 53 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 the a 2017 City of Hopkins, MN Project # 09-CIP-AC032 Project Name Activity Center Cafe on 14th Future Description Department Activity Center Contact PW Director T.1 pe Improvement I sctul Lite C:uegorr Buildings: Activity Center Priority n Total Project Cost: $90,000 General - The Activity Center Cafe on 14th project is a project aimed at a growing trend among senior centers to reach out to younger audiences such as the baby boom generation. This protect gill tranform the Acti\ity Center from a traditional senior community center into a restaurant, gathering place, learning center, and health club - that happens to haye customers who may range in age from 50-90 (but still open to all ages). The original model of a Caf6 community facility ryas dcyeloped in Chicago and has been successfully implintented in other cities. The capital improvement portion of this new project inyok cs utili/ing the existing kitchen in a cafe fashion that would serve food in the morning until after lunch to people seated in what is currently the lounac area. Detailed - The project involves opening up a portion of the wall between the kitchen and lounge area and building a wall along what is now the serving line area of the kitchen. This new wall will close off the kitchen on the gym side and create a hallway for entrance and exit from the gym's West doors. The kitchen needs to be redesigned from it's previous school cafateria layout to a smaller "cafe" kitchen area with the appropriate equipment to serve breakfasts and sandwich salad soup based lunches. The lounge area carpet will be replaced with tile. a computer & table will be added for internet access in the lounge. Sources: Sources have yet to be identified but possible partners in the project could include: The Hopkins Historical Society, Hopkins listriet. a new non-profit "Friends of the Actiyity Center" orizani/ation. Justification It is well documented that baby boomers are not utili/ing traditional senior centers as readily as seniors hare in the past. People do not visit senior centers because it's for people of their age, they go there for the goods and services they need. The goal of the Cafe is to attract the younger older adult - younger in outlook, attitude and \cars - those who would benefit but seldom use "senior" se\ices. to increase partnership, risibility and service reach, to improve the quality of lite for our older adults, and to increase satisfaction of scryices. The eafd concept would satisfy scycral City strategic goals such us building on the small tovv n feel of Hopkins through developing new methods that are more responsive to citizens and customers. If partnering with the Historical Society the project \\ ill enhance the sense of place. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 90,000 90,000 Total 90,000 90,000 Funding Sources 2013 2014 2015 2016 2017 Total PF - Private Sector Funds 90,000 90,000 Total 90,000 90,000 Budget Impact/Other The operational goal of the cafe would be to break cycn as a trod service_ but the Qtfe would dray customers to the Activity Center to participate in the activitites many programs and activities offered by the Center thus increasing program and membership revenues. 54 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08CIP-AR013 Project Name Replace 25 Ton Rooftop HVAC Unit - HCA Future Description teplace existing 25 ton rooftop HVAC unit Justification Tanned replacement at 20 years estimated useful life. Department Arts Center Contact Public Works Director Type Improvement Useful Life Category Buildings: Arts Center Priority n/a Total Project Cost: $100,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 100,000 100,000 Total 100,000 100,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 100,000 100,000 Total 100,000 100,000 Budget Impact/Other 55 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 the it 2017 City of Hopkins, MN Project # 12- CIP-ARO1 Project Name Carpet Replacement: Theater and Dressing Rooms Future Deparuuent Arts Center Contact Arts Center Director T.% pe In,pro.ement I refill life 10 Years CaIeg",N Buildings: Arts Center Priorit. 2 Vey Important Description Total Project Cost: $51,500 Remove carpet and carpet base in the thcartcr walk\cay s. main dressing rooms, theater sound locks, JC studio dressing rooms, AN storage room Justification This carpet will be 16 years old in 2013 and %v ill have exceeded its useful life. Expenditures 2013 2014 2015 2016 2017 Total Future Construction/Maintenance 22,000 22,000 29,500 Total 22,000 22,000 Total Funding Sources 2013 2014 2015 2016 2017 Total Future Cl - Capital Improvement Fund 22,000 22,000F---2-9—,5700 Total 22,000 22,000 Total project in 2023 at $29, 500 (Est) 611 Future 0 Total 7iu�sd�n..111glrcl1)7, 2012 CAPITAL IMPROVEMENT PLAN 2013 Mm 2017 City of Hopkins, MN Project # 12-CIP-AR002 Project Name Replace theatre seats and backs Future Department Arts Center Contact Arts Center Director Type Improvement Useful Life 20 years Category Buildings: Arts Center Priority 1 Urgent Description I Total Project Cost: $138,510 temove and replace theater seats and backs. (Keeping existing stanchions) 3ased on quote from Cosney (they recently did Eisenhower seating) with Classic Quattro seat, 33" low back, waterfall back and seat tailoring. >herpa Shire -Grade G fabric (similar to existing), plush foam seat, 2" back foam, lexan seat numbers, demo and removal of existing seats and racks includes attic stock. !011 pricing $116,000 with 3% inflation compounded over 5 years $138,510 Justification Seats will be 20 years old in 2017 and will have exceeded useful life. Stanchions should still be usable. Quote includes replacement of all seats and backs. is not due until 2017 but wanted to get as much info as possible now to allow for time to plan. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 138,510 138,510 Total 138,510 138,510 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 138,510 138,510 Total 138,510 138,510 Budget Impact/Other �ould consider replacing main floor one year and balcony another year if required by cash flow. need tow weeks in theater to make exchange. Work on stage at same time okay will install team. )pportunity to potentially do a "seat sponsor" funding program similar to what was done before ect in 57 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 thin 2017 City of Hopkins, MN Project # 12-CIP-AR003 Project Name Seal Floors in Public Restrooms and Kitchen Future Department Arts Center Contact Arts Center Director 1) PC Improvement t w1til Life 7 years Categorc Buildings: Ails Center Priorih I Urgent Description Total Project Cost: $11,000 Have grout and tile cleaned in the restrooms and kitchen, color grout a neutral shade, and then seal the entire floor. Justification The current grout is white but over time, even with regular cleaning and diligent mopping, portions of it turn grey. AVre have done deep cleaning which turns it white temporarily but then it gets patchy again. This makes the restroom floors look dirty, even when they are not. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 11,000 11,000 Total 11,000 11,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 11,000 11,000 Total 11,000 11,000 Budget Impact/Other tepeat in 7 years, at approximately `h 13,500 58 hiccdu.r. 117. ?Ul? CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 12-CIP-AR004 Project Name Replace Miniblinds with Roller Blinds Future Department Arts Center Contact Arts Center Director Type Improvement Useful Life 10 years Category Buildings: Arts Center Priority 1 Urgent Description I Total Project Cost: $2,500 Replace existing miniblinds in the community room, class room, and conference room with roller blinds. Justification Existing miniblinds are hazardous due to the long cords which are left when the blinds are pulled up. Replacing that with a roller chain set up will be safer. This proposal does not include automatic up and down, they would still be adjusted manually. Expenditures Construction/Maintenance Total 2013 2014 2015 2016 2017 2,500 2,500 Total 2,500 2,500 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 2,500 2,500 Total 2,500 2,500 Budget Impact/Other 59 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 /n, ,t 2017 City of Hopkins, MN Project # 12-CIP-AR005 Project Name Replace Information Desk and Kiosk Future informational Kiosk and desk with more functional information Center. Department Arts Center (oulacl Arts Center Dircetor Type Improvement Useful Life 15 years (*atc;;or.% Buildings: Arts Center Priorily I Urgent Total Project Cost: $5,000 Justification �utrent informational kiosk and information desk arc not ideal for assisting Visitors with way finding and disseminatin- infonnation. Guests trriving are frequently confused and hayc a hard time finding location of meetings. Etc. Also, we would like to be able to display larger concert 3osters, the rental brochure, membership brochures and more. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 5,000 5,000 Total 5,000 5,000 Funding Sources 2013 2014 2015 2016 2017 Total CI - Capital Improvement Fund 5,000 5,000 Total 5,000 5,000 Budget Impact/Other M hn sdgr. li/ us n Vt/' CAPITAL IMPROVEMENT PLAN 2013 /hru 2017 Department Arts Center City Of Hopkins, MN Contact Bldg/Equip Supt Project # 12-CIP-AR036 Type Improvement Useful Life 20 years Project Name Replace 15 RooftopHVAC units - HCA Category Buildings: Arts Center Future Priority n/a Description Total Project Cost: $220,000 Rooftop heating and AC units were installed in 1997. Useful life is 20 years. 15 total units from 25 tons to 5 ton. Justification Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 220,000 220,000 Total Funding Sources 2013 220,000 2014 2015 2016 2017 220,000 Total Cl - Capital Improvement Fund 220,000 220,000 Total Budget Impact/Other 220,000 220,000 Tuesday, August 07, 20/2 61 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 09-CH'-CH030 Project Name City Hall Lobby Upgrade Future Department City Hall Administration Contact Public Works Director 'Type Improvement I ,cful Life 20 years Catcgor� Bldg: City Hall Priorit.N it'a Description Dotal Project Cost: $110,000 -ity Hall Lobby Upgrade was proposed as part of the 2007 City Hall upgradeCarpet proicct. This part was not completed exceeding estimates. Justification Existing lobby is dated, ceiling tiles ha\c yellowed and wallpaper has numerous stain, from 19 years of service. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 110,000 110,000 Total 110,000 110,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 110,000 110,000 Total 110,000 110,000 Budget Impact/Other 1, Ttndat..07. 2011 CAPITAL IMPROVEMENT PLAN 2013 ihru 2017 City of Hopkins, MN Project # 08-CIP-FDO19 Project Name Replace Carpet and Apparatus Floor Finish - FD Future Description teplace carpet and apparatus floor finish systems. Department Fire Contact Fire Chief Type Improvement Useful Life 10 years Category Buildings: Fire Facilities Priority n/a Total Project Cost: $56,000 Justification ?lanned replacement at end of estimated 10 year useful life. Classroom and 2nd and 3rd Floor entryway and louge replacement, due to excessive ise of classroom and lounge. ?D spoke with Steve Stadler and he was ok with moving it up to 10 years from 15 years. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 56,000 56,000 Total Funding Sources 2013 56,000 2014 2015 2016 2017 56,000 Total Cl - Capital Improvement Fund 56,000 56,000 Total 56,000 56,000 Budget Impact/Other )riginal plan replacement was 15 years. Due to excessive use of classroom and lounge the life was moved to 10 years. Tuesday, August 07, 2012 63 CAPITAL IMPROVEMENT PLAN 2013 1hri, 2017 City of Hopkins, MN Project # 07-CIP-P313 Project Name Pavilion skate Tile Replacement/Lobby Improvement Future Department Pavilion ('ontact PW Director I y pe hnprovenlent I seful Life 10 years Category Parks Fores-'Pay.: Comm Facil. Priorih n/a Description Twat Project Cost: $97,000 Replacement of existing skate tile and adding skate tile and ceramic tile to the lobby. Replacement of existing tile in team rooms, arena, warming room , and referees room: 5,500 square feet. Install skate tile to a portion of lobby so skaters can access drinking fountains; 500 square feet. Install ceramic tile in the entryway and a portion of the lobby: 500 square feet. Floor has a 10 Year Life - Put in CIP again for 2017 for evalutaion. May only need to do the high traffice areas. Justification �urrent skate tile is 16 years old and is the original tile; the wear layer of the tile is \aorn through in the high traffic areas. Original tile was not slued, which increases maintenance and can create gaps in scams. This can allow skates to touch the concrete underneath the tile. Lobby skate and ceramic tile would add to the building aesthetics. When done in 2007 this pro.icct cost $41,339.30. Prior Expenditures 2013 2014 2015 2016 2017 Total 52,000 Construction/Maintenance 45,000 45,000 Total Total 45,000 45,000 Prior Funding Sources 52,000 PA - Pavilion Fund Total Total 2013 2014 2015 2016 2017 Total 45,000 45,000 45,000 45,000 ew the glued down will save on maintenance. be safer. and improv c faciIit\ appearance and marketability. /11rSdn. 11iernl0- VI/' 64 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 07-CIP-P314 Project Name Pavilion Overhead Door Improvement Future Department Pavilion Contact Public Works Director Type Improvement Useful Life 30 years Category Bldgs: Pavillion Priority n/a Description I Total Project Cost: $40,000 Remove and lock -in four of the six overhead doors on the west side of the Pavilion with a portion to have windows or glass block to allow light to come through. Install automatic openers on the remaining four overhead doors in the arena. ESTIMATED PROJECT SCHEDULE: 2015 Justification Currently the overhead doors are seldom utilized and the removal and installation of glass blocks or windows will decrease the need to use arena lighting and add to arena aesthetics. Saving on repairs and maintenance of the removed doors. Pavilion user groups have asked for this project. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 40,000 40,000 Total 40,000 40,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 40,000 40,000 Total 40,000 40,000 savings on utilities and greater satisfaction from user groups with arena aesthetics. Tuesday, August 07, 2012 65 CAPITAL IMPROVEMENT PLAN 2013 /lint 2017 City of Hopkins, MN Department Pavilion (ontact Public Works Director Project# 09-CIP-PO25 1'.N pe Imprmement I scful Life 20 _years Project Name Pavilion Gas Fired RooftopFurnace ('atcl;orc Bldg.: Pasillion Future Priorih mu Total Project Cost: $9,000 Remove and replace existing gas tired rooftop furnace used for heating the tcarn rooms. ESTIMATED PROJECT SCHEDULE: Spring Suruncr 2015 Justification 'urrent unit was installed during ani ,truction of the facility in 1990. Planned replacement for cnd of cstimatcd useful life. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 9,000 9,000 Total 9,000 9,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 9,000 9,000 Total 9,000 9,000 Budget Impact/Other Savings on utilities due to increase in efticicncy of ne%� units. 66 7iu 001. Irr,•u r 0-, '01 , CAPITAL IMPROVEMENT PLAN 2013 rhru 2017 City of Hopkins, MN Project # 09-CIP-PO26 Project Name Pavilion Roof Replacement Future Department Pavilion Contact Public Works Director Type Improvement Useful Life 25 years Category Bldgs: Pavillion Priority 1 Urgent Total Project Cost: $120,000 Removal and replacement of existing ballast and membrane for both the north and south roof sections. Justification tepairs made in 2005 extended the life of the roof but it is now 25 years old and has surpassed manufacturers recommendation for replacements. Fhe current roof has leaks and given the current condition of the membrane more failures are expected. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 120,000 120,000 Total 120,000 120,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 120,000 120,000 Total 120,000 120,000 Budget Impact/Other Roof leaks can potentially be harmful to the steel roof deck and may cause damage to equipment and interior of Pavilion, impacting operations and adding cost to roof replacement. Tuesday, August 07, 2012 67 CAPITAL IMPROVEMENT PLAN 2013 ihni 2017 City of Hopkins, MN Project # 09-CIP-PO36 Project Name Pavilion Evaporator Condenser Replacement Future Remove and replace existing condenser with a new condenser, sump tank. pump and fun motors. ESTIMATED PROJECT SCHEDULE: 2015 Department Pa\'Ihon Contact Public Works Director T) pe Improvcnxnt Useful Lite 15-25 years Cawgory Bldgs: Pavillion Priorith n a Total Project ('ost: $60,000 Justification Existing condenser has extensive scaling and has experienced a loss in cfticiency causing higher head pressures and putting greater strain on compressors. Expenditures Construction/Maintenance 2013 2014 2015 60,000 2016 2017 Total 60,000 Total 60,000 60,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 60,000 60,000 Total 60,000 60,000 Budget Impact/Other liven the age, scaling, and corrosion of the existing condenser a frcon leak could potentially develop causing greater expense and need for repair. Tta�c�lu.r.. 11("'1w0-,_'01 ' 68 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 10-CIP-P319 Project Name Pavilion Indoor Turf Replacement Future Description 'urchase new turf for the Pavilion's arena Department Pavilion Contact Facilities Director Type Improvement Useful Life 15 years Category Bldgs: Pavillion Priority n/a Total Project Cost: $95,000 Justification Fhe current turf was purchased in 1998 and has a useful life of 15 years (2013), the turf is showing signs of wear and has been patched in a few treas. Replacement will be needed by 2016. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 95,000 95,000 Total 95,000 95,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 95,000 95,000 Total 95,000 95,000 Budget Impact/Other Possible resale of the existing turf may offset some of the cost of a new turf system. Tuesday, August 07, 2012 69 CAPITAL IMPROVEMENT PLAN 2013 iluo 2017 City of Hopkins, MN Project # 10-CIP-P320 Project Name Pavilion - Desiccant Repl of Dehumidification Syst Future and replace the desiccant medium used in the Pavilion's (fell umiditication system. Deparlinew Pavilion ("ontact Facilities Director 1 ype Improvement I scful Life 10 years ( alegor� Bldgs: Pavillion Priority n%a 1"otal Project Cost: $6,000 Justification Che current desiccant has never been replaced and has surpassed its useful lite. New desiccant will make the system run more efficient and ;ffectively saving on natural gas and electricity. Also provide dryer air which can have a positive effect on ice quality and indirectly cause more ;fficient operation of the refrigeration equipment. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 6,000 6,000 Total 6,000 6,000 Funding Sources 2013 2014 2015 2016 2017 Total PA - Pavilion Fund 6.000 6,000 Total 6,000 6,000 Budget Impact/Other 70 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08-CIP-PDO16 Project Name Replace Carpet - Police Station Future Description teplace Police Station Carpeting Department Police Contact Police Chief Type Improvement Useful Life 7 years Category Buildings: Police Department Priority n/a Total Project Cost: $40,000 Justification Planned replacement at end of estimated 10 year useful life. This is a 24hour/day work center that required the shorter carpet replacement cycle. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 40,000 40,000 Total 40,000 40,000 Funding Sources 2013 2014 2015 2016 2017 Total Cl - Capital Improvement Fund 40,000 40,000 Total 40,000 40,000 Budget Impact/Other May have to look at other flooring option for dispatch. (ie combination of carpet and tile due to wear under desk areas. Previously in at a 7 year life - moved back to 10 year life 71 Tuesday, August 07, 2012 Parks and Recreation 72 CAPITAL IMPROVEMENT PLAN 2013 tnrtt 2017 City of Hopkins, MN Project # 08-CIP-PO10 Project Name Play Equipment - Park Valley Future Description teplace park play equipment 4 ----------- 45,000.00 Justification Upgrade of park play equipment after 20 - 25 years of use. Department Public Works: Parks Contact PW Director Type Improvement Useful Life Category Parks/Fores/Pay.: Comm Facil. Priority n/a Total Project Cost: $45,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 45,000 45,000 Total 45,000 45,000 Funding Sources 2013 2014 2015 2016 2017 Total PDF- Park Dedication Fund 45,000 45,000 Total 45,000 45,000 Budget Impact/Other 73 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 din, 2017 City of Hopkins, MN Project # 08-CIP-P014 Project Name Play Equipment - Hilltop Park Future Description teplace park play equipment. Justification Jpgrade of park play equipment after 20-25 vcars Deparunent Public Works: Parks Contact Facilities Director t N pe Improvement Useful Life Cate„ ori Parks'Fores'Pay.: Comm. Facil. Priorit. nia Total Project Cost: $45,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 45,000 45,000 Total 45,000 45,000 Funding Sources 2013 2014 2015 2016 2017 Total PDF- Park Dedication Fund 45,000 45,000 Budget Impact/Other Total 45,000 45,000 74 lit, NJur. n-, 'nl' CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Project # 08-CIP-PO16 Project Name Play Equipment - Oakes Park Future Description teplace park play equipment. Justification Jpgrade of park play equipment after 20-25 years of use. 2013 thru 2017 Department Public Works: Parks Contact Facilities Director Type Improvement Useful Life Category Parks/Fores/Pay.: Comm. Facil. Priority n/a Total Project Cost: $60,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 60,000 60,000 Total Funding Sources 60,000 2013 2014 60,000 2015 2016 2017 Total PDF- Park Dedication Fund 60,000 60,000 Total 60,000 60,000 Budget Impact/Other Tuesday, August 07, 2012 75 CAPITAL IMPROVEMENT PLAN 2013 dirit 2017 City of Hopkins, MN Project # 12-CIP-PO37 Project Name Repair Tennis Courts and Burnes Park Play Court Future Department Public Works: Parks Contact Public Works Director TN pe Unassigned t Willi Lite Category PW - Parks Priorih nia Description Total Project Cost: $45,000 Surface repairs, crack repairs to tennis courts at Cental Park, Burncs Park and Oakes Park. Asphalt overlay and new color coating system for Burnes Park play court. Justification tepairs needed to protect investment in courts asphalt pavement, prolong: life and improve play conditions. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 45,000 45,000 Total 45,000 45,000 Funding Sources 2013 2014 2015 2016 2017 Total PDF- Park Dedication Fund 45,000 45,000 Total 45,000 45,000 Budget Impact/Other 76 r;�, ;_1 11" ,„ CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08-CIP-RO01 Project Name Skate Park Future Description Annual equipment enhancmcnts to Overpass Skate Park Justification Department Recreation Contact Facilities Director Type Improvement Useful Life 15 years Category PW - Parks Priority n/a Total Project Cost: $49,000 Per our agreement with 3rd Lair, who manages the Skate Park, we need to put $7,000 of enhancements into the Skate Park for the years 2006-2008. The agreement for 2009-2011 requires annual enhancements of $7,000. The agreement for 2012-2014 is currently being renewed for $7,000 each year. Per the Overpass Skate Park Operators Agreement, the city annually puts an amount specified in the agreement of enhancements into the park to chan a/im rove the park each year to keep the park attractive and challenging to users. Prior Expenditures 2013 2014 2015 2016 2017 Total 35,000 Construction/Maintenance 7,000 7,000 14,000 Total Total 7,000 7,000 14,000 Prior Funding Sources 35,000 PDF- Park Dedication Fund Total Total 2013 2014 2015 2016 2017 Total 7,000 7,000 14,000 7,000 7,000 14,000 Impact/Other budgeted in Skate Park Enterprise Fund, which was eliminated 12/31/2005. It is now budgeted in the Park Dedication Fund. Tuesday, August 07, 20/2 77 CAPITAL IMPROVEMENT PLAN 2013 ih u 2017 City of Hopkins, MN Project # 10-CIP-RO02 Project Name Depot Recreation Area Future Deparlinew Recreation Contact PW Director T% pe Improvanent Useful Life 25 years Category PW - Parks Priorit.N 2 Very Important Total Project Cost: $500,000 This project includes the addition of an outdoor multipurpose rink court and support building on property west of the Depot facility. These amenities are proposed to be utilized as part of Depot youth engagement activities and as part of the community rcc leagues and playground programs. The multipurpose rink court will include an asphalt surface and hockey dasher boards for skating and broomball use in the winter: and equipment to accommodate basketball, inline skating, volleyball and soccer uses in the spring, summer and tall months. The support facility will include equipment for a bike maintenance and repair site sponsored by the Depot, as well as restrooms. storage areas and a general multipurposearea to be used as a warming house in the winter. of $150,1100 will be applied for. Justification The Depot site has needed outdoor amenities for its target audience since its founding. A year-round sports "anchor" at the Depot site to complement arts and music and cntreprcnurial business experience for youth will provide additional rcnitorrcemement of positive behaviors. As more people come to the Depot for youth activities as well as general use during daytinic hours, such a facility could be used all day and into the evening hours. Proximity to the rail corridor will accord high risibility and symboli/c active living and community connections in a walkable, bike -able community. Rec league broomball or hockey could share icc \yith free skating times. Local business employees could take advantage of the facilty over lunch times. Easy trail access makes the Depot and easy ride for kids who would come there to play. The Depot has been working toward more bike -oriented prgrams open to the \�hole community (c.g. Bike Scream Sundays) and has some connections already with local bike retailer/advocates at Freewheel by hosting a bike equipment vending machine on site. Dedicated space \yould gig c nes\ possibilities to this aspect of the "Depot on the Move" Initiative. Expenditures 2013 2014 2015 2016 2017 'Total Construction 500,000 500,000 Total Funding Sources 2013 500,000 2014 2015 2016 500,000 2017 Total GU - Other Governmental Unit Total 500,000 500,000 500,000 500,000 Budget Impact/Other 78 111rsrlu}t .lug,r(q 07. 012 Streets, Traffic & Transportation w = w J o } } 4 -- } z Z d a V) (J) V) -- w O O O O _ I--) U U U n Q M V l.0 fl - 0 _ O O O 00 CL a N N N N N U NIIvd SIa0'I'.LS 'Oa rDOaHMO0V 3w Y a � •Da � 3Na�i nH 3-03WOH 7l3nOd a 0 '3AV SVx31 \ �IIH 37dtlW Y o H7tlla31Nl o � � � � `e�" w o •Da Doon�eo O u 0 •ane AHdanw N Y o 0 a m '0a o A3 Hse i z z z o u a¢ r a u J •J 3 a J f U m J z .... LL 0 {{JJuz _O�r NQ»j W elm z Z W R N w NN m m m O Z W W w W Y &m• Zo a z z z z a z uows�¢zz�a�oxJ W a a m W ¢ ¢ u u a m ¢ V Nf'r�N�y V mPmN� V N SI11O'I '.LS NNO.LHNNIW �; '3nV 37831d � '3AV rNOd 'N -3AV a3JA1� \ •3" 83�A1 V' O d � lP _ N 'N '3neJN0 ddVH 'S '3nV N V• NOSIdaVH J — N3df18 NVn w 'S 'ane N36he Nen 6 B _ 'N '3AV _ NOSN7tlP 'S '3AV NOSN7eNr •�nV 30aNOw O— U'��OSIOV.• 1 s'S '3ntl 3 3OS /�\\ �� 'S ane NOSIOtlw O + CK , ObN Ny LJ �� .2 �' V\ a V a o 0 \ p Az 'S '3nv NOSa3dd3r' N �\ i S 3AVo SWtlOV e i b�6 C _ S 'ane" NOlONIHSVM I)b � 13nV cc,^\ VNIUR Ogex \� �i 5 S 3nV 11 J w 12O IS I U` „i �¢O ��� i W dO \ 31�D' ONZ 31618 z � / � � d❑ A3��en 'rdbd '3 15e3 3nD >)Vn �� �i a�� ❑� _ � ibE 133Ms / d0 � N370 ne0 II I!� d0 A3��bn Habd 'M 31IDDSN S 'ane J�— H1aDN L7 3n00 3llw 3 it 'any H1S H19 ' b' 'S'3ne Hlc '^ NIN L —r 1 N I S 'ane H II Maui -3n � Hl- 15.� 'Da fJ l____ N N N L= o �NVw35130��1�^ 3ntl HlC •S '3AV H It •S 'ane HtC F �� �P a �•3ny HI- 's •3nbHis. '$ '3n� Hie ,}E 2 _ _ H16 5 '3nb H16J i° S '3nVH16 F0� c 24 L _ •S '3At, v? N •3nV ~ J H101 N U= 'S '3nb f H10—I� 'ane HtII H11I ' z S 3nV ¢ 0 0 5 3nb = W O Z O R0. jL cl__ 5 3n b�nl H12f0H y = 1 11HD• �iL �,- -- NW '3nV N N I NE —J�HI£I w '3nb Hl£I ��i SAe HIPI l _ S '3nb ne tat 3�V, z H1SI S '�n- .> 7 _���-b H1C1 0 I Hlsl S ane H191 L 11 ..— S I� �CHiel I s's�b� Hieb I I �� d- �— AA CAPITAL IMPROVEMENT PLAN 2013 ihru 2017 City of Hopkins, MN Project # 01-CIP-S101 Project Name Residential Street Improvements Future Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Description Total Project Cost: $17,290,000 Program to improve streets needing repair or reconstruction as indicated by street condition survey, or as part of an area street improvement. 2013: Presidential Avenues South and 1st Street and 2nd Street South, between Monroe and Harrison, West Park Road 2016 - 2017: Park Valley and Peaceful Valley Reclamation Project - East and West Park Valley Road; 9th Avenue South between Westbrooke Way and 7th Street South; 6th Street South between 10th Avenue and 6th Ave South; 7th Street South between 10th Avenue and East Park Valley Road; 5th Ave South between 5th Street South and 7th Street South 2015: Texas Avenue from Lake Street to Cambridge Street; Oxford Street from Blake Road to Texas Ace; Cambridge Street from Blake Road to Texas Ave; Murphy Street from Lake Street to Oxford Street; Lake Street from Blake Road to Texas Ave. Justification street improvements determined through Pavement Management Program. Prior 6,190,000 Total Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 3,800,000 2,300,000 2,500,000 2,500,000 11,100,000 Total 3,800,000 2,300,000 2,500,000 2,500,000 11,100,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 6,190,000 PI - PIR/General Obligation Bo 2,300,000 1,350,000 1,500,000 1,500,000 6,650,000 Total SA - Special Assessment 1,500,000 950,000 1,000,000 1,000,000 4,450,000 Total 3,800,000 2,300,000 2,500,000 2,500,000 11,100,000 Budget Consistent with the City Council adopted Roadway Improvement Policy, street ratings, and Pavement Management Program. Tuesday, August 07, 2012 81 CAPITAL IMPROVEMENT PLAN 2013 Ilivit 2017 City of Hopkins, MN Project # 01-CIP-S102 Project Name Residential Street Inip roventents--Utilities Future Department Public Works: Streets Traffic Contact Public Works Director T. pe Improvement I scful Life Unassigned ( alegorc Trans: Streets Priority n a Total Project Cost: $7,260,000 s to be determined as they are consistent \s ith the St-CCt trcomrruCtion program. to reconstruct deteriorated water main and sanitar\ r\\ Cr and to provide storm sewer improvements in conjunction with street nent projects. Public hearing: Year prior to planned construction Plans and specifications: Year prior to planned construction Bid: Year of planned construction Consistent with the Storm Water Mana-cmcnt Plan, Water and Sewer l;tiIit\ Master Plan, and television in Justification In most cases where street reconstruction takes place. storm sewer facilities either need upgrading or need to be installed nc�v. In some cases, water main and sanitary sewer need to be rehabilitated in conjunction \%ith street reconstruction. The numbers assume the city funding 100% of major storm sewer, water main, and sanitary sewer rc construction. These costs are to be used in conjunction with street reconstruction costs shown on 01-CIP-5101. Prior Expenditures 2013 2014 2015 2016 2017 Total 2,450,000 Construction/Maintenance 2,300,000 1,650,000 430,000 430,000 4,810,000 Total Total 2,300,000 1,650,000 430,000 430,000 4,810,000 Prior Funding Sources 2,450,000 SF - Sanitary Sewer Fun Total SU - Storm Sewer Fund WF - Water Fund Fund 2013 .2014 2015 2016 2017 Total 700,000 500.000 120,000 120,000 1,440,000 500,000 350.000 110,000 110,000 1,070,000 1,100,000 800,000 200,000 200,000 2,300,000 Total 2,300,000 1,650,000 430,000 430,000 4,810,000 Budget Impact/Other Public Hearing - year prior to planned construction Plans and specifications - year prior to planned construction Bid - year of planned construction with the Storm Water Man'.wcment Plan. Watcr and Sc\\ er l tility Mauer Plan. and television insocctions. 82 CAPITAL IMPROVEMENT PLAN 2013 rhru 2017 City of Hopkins, MN Project # 01-CIP-S103 Project Name Citywide Concrete Alleys Future Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Description I Total Project Cost: $1,368,000 2017: Alley south of 6th Street South and North of Nine Mile Creek, between 11 th Avenue South and 10th Avenue South. 2012: Alley south of 3rd Street North and North of 2nd Street North, between 6th Avenue North and 5th Avenue North. Alley South of Mainstreet between 8th and 9th Ave South Program to construct concrete alleys in areas designated as poor on the Alley Condition Survey. Public Hearing - year prior to project. Plans, specifications, bid, construction - year of project. Consistant with the Ctiy Council adopted Roadway Improvement Policy and Alley ratings. Justification The city has had a policy of constructing concrete alleys for a number of years. This policy has proved to be sound by the concrete alleys' durability and low maintenance costs. Current policy has the city share at 20% of the cost in residential areas. The city will experience cost savings due to lower maintenance costs. Prior Expenditures 2013 2014 2015 2016 2017 Total 1,213,000 Construction/Maintenance 75,000 80,000 155,000 Total Total 75,000 80,000 155,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 1,213,000 PI - PIR/General Obligation Bo 15,000 16,000 31,000 Total SA - Special Assessment 60,000 64,000 124,000 Total 75,000 80,000 155,000 Budget Impact/Other with the City Council adopted Roadway Improvement Policy and Alley ratings. Tuesday, August 07, 20/2 83 CAPITAL IMPROVEMENT PLAN 2013 don 2017 City of Hopkins, MN Project # 01-CIP-5104 Project Name County Road 3 Future Dcpartuent Public Works: Streets%Traffic ( ontacl Public Works Director Tcpe Improvement I sclul Life Unassigned ('alcgor� Trans: Streets Priority n Total Project ('ost: $2,300,000 County Road 3 from Shady Oak Road to Mcado%abrook Road. Lighting, landscaping, street, etc. improvements along Excelsior Boulevard from the cast to west city limits. GO Bond payments to be financed by a combination of existing TIF revenue. Municipal State Aid road funds. additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue Segment 1: Construction - 1998;1999 Segment 2: Planning - 2004; bidding and construction (median upgrades only) - 2005 Segment 3: Planning and acquisition - 1999-2001, biddin-construction - 2002 2003 2004 Segment 4: Planning and acquisition - 2012,2013, bidding'construction - 2014,2015 TIF funded work includes the following: A signalized intersection will be constructed at Monroe Avenue. A second intersection will also be built at Jackson Ave/St. Louis Street. There will also be a reconfiguration of Monroc AyCIIUC and Milwaukee south of Excelsior Boulevard. This work is being completed in conjunction \v ith the reconstruction of Excelsior Boulevard from Highway 169 to Blake Road. The intersection is being constructed to facilitate redevelopment of the SunerValu north annex site. Justification Deficiencies in terms of roadway condition. traffic pedestrian mo% anent. satcty and aesthetics appear in all four segments of County Road 3: - Segment I from Shady Oak Road to I Ith A�enuc S.: upgrade existing undi\ idcd road«°ay, upgrade 1 Ith Avenue intersection to meet future needs, implement beautification program --completed in 1998 - Segment 2 from I lth Avenue S. to Hwv 169: median pavers construction - Segment 3 from Highway 169 to Blake Road: upgrade existing narrow undivided roadway, resolve safety issues at railroad crossing, improve north -south access, account for future LRT access, address rede\clopment needs, add integration for full access at Jackson Avenue, - Segment 4 from Blake Road to Meadowbrook Road: unaradc road\\ a\ iniolcment beautification troeram. Prior Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 2,300,000 2,300,000 Total Total 2,300,000 2,300,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total �0 GU - Other Governmental Unit 1,600,000 1,600,000 Total MS - Municipal State Aid Stree 700,000 700,000 Total 2,300,000 2,300,000 Impact/Other GO bond payments to be financed h.\ .i combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds. and, as a last resort, general city revenue. Segment 1: Construction - 1998, 1999 Segment 2: Planning - 2005; bidding and construction (median upgrades on]\ - 2006 Segment 3: Planning and acquisition - 1999 201111: bidding construction - 2003 2004 Segment 4: Planning and acquisition - 201221113: bidding, and construction - 2014 2015 Consistent with Hennepin Count CI and Cite Council action. 111evda.r. ,Iu,Lur� a-. '0/' 84 CAPITAL IMPROVEMENT PLAN 2013 rhru 2017 City of Hopkins, MN Project # 01-CIP-S106 Project Name County Road 61 (Shady Oak Road) Future Description >hady Oak Road from County Road 3 to T.H. 7, Mainstreet from 20th Avenue to Shady Oak Road. .fighting, landscaping, street, etc., improvements from County Road 3 to T.H. 7 teconstruction and amenities on Mainstreet from 20th Avenue to Shady Oak Road. teconstruction of West Park Road, 2nd Street N., and 21 st Avenue N. (2nd Street -4th Street N.) also 01-CIP U003 for the Storm Sewer Manaeement associated with this Justification Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $20,450,000 icies appear on Shady Oak Road in terms of roadway conditions, traffic/pedestrian movement, safety, and aesthetics. Upgrade an A roadway, resolve safety issues with number of driveway access points and intersection at Mainstreet. Lighting needs upgrading and beautification program. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 8,200,000 12,250,000 20,450,000 Total 8,200,000 12,250,000 20,450,000 Funding Sources 2013 2014 2015 2016 2017 Total GU - Other Governmental Unit 6,150,000 11,045,000 17,195,000 MS - Municipal State Aid Stree 2,050,000 755,000 2,805,000 PI - PIR/General Obligation Bo 200,000 200,000 SA - Special Assessment 250,000 250,000 Total 8,200,000 12,250,000 20,450,000 12-2014: Planning and acquisition 14/2015: Bidding and construction with Hennepin County CIP, city's desire to upgrade the roadway, and reconstruction program for all of Mainstreet. its project totals $20,450,000. Hopkins share of the county project is $2,805,000 of which we have $1.3 million budgeted. The remaining $1.5 million is right-of-way acquisitions for which we currently have no funding. The project is not feasible under the current funding program. GU riding includes $7.28 million Federal Grant. Tuesday, August 07, 2012 85 CAPITAL IMPROVEMENT PLAN 2013 th, it 2017 City of Hopkins, MN EProject # 01-CIP-5504 Project Name Sixth Street South (11th to 12th Avenue South) Future Sixth Street South from l lth Avenue South to 12th A%cnuc South. Extension of roadway and box culvert crossing at Nine Mile Creek. Department Public Works: Streets%Traffic Contact Public Works Director T) pe Improvement I seful Life Unassigned C'ategor) Trans: Sweets Prioritc n I otal Project ( ost: 5500,(100 Justification chis project will offer a second access to the industrial arca (tire access). Will direct some of the existing industrial traffic north, away from the esidential intersection at Seventh Street and I 1 th Avenue. Will connect a current dead-end alley, west of 1 I th Avenue. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 500,000 500,000 Total 500,000 500,000 Funding Sources 2013 2014 2015 2016 2017 Total MS - Municipal State Aid Stree 400,000 400,000 PI - PIR/General Obligation Bo 100,000 100,000 Total 500,000 500,000 Currently on MSA plans. 86 �ursdur. ltr"'rr'r 11-. '01 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 06-CIP-5118 Project Name Parking Lots - Lot 200 Future Description !010: Municipal Parking Lot 200, south of Mainstreet between 8th and 9th Avenues. tehabilitate parking lot pavement Justification ?avement has deteriorated to the point where cracksealing and sealcoating are not effective. Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Category Trans: Parking Facilities Priority n/a Total Project Cost: $250,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 250,000 250,000 Total 250,000 250,000 Funding Sources 2013 2014 2015 2016 2017 Total PI - PIR/General Obligation Bo 200,000 200,000 SU - Storm Sewer Fund 50,000 50,000 Budget Impact/Other Total 250,000 250,000 87 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 tn)"„ 2017 City of Hopkins, MN Project # 10-CIP- S120 Project Name Highway 7 and 5th Ave North-- Signal Replacement Future Description traffic signal replacement at the intersection of Highway 7 and 5th Arc North. Justification VIN DOT has mandated the replacement of this signal. Department Public Works: StreetsTraffic ( ontact PW Director 'I".Npe Improvement I'seful Life 25 years ("ategor� Trans: Streets Prioritc 3lmportant Total Project ('os(: $445,000 Expenditures 2013 2014 2015 2016 2017 Total Construction 445,000 445,000 Total 445,000 445,000 Funding Sources 2013 2014 2015 2016 2017 Total GU - Other Governmental Unit 300,000 300,000 PI - PIR/General Obligation Bo 145,000 145,000 Total 445,000 445,000 Budget Impact/Other 88 /it, �dur. ti1."'not 0-, 2011 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 11-CIP-S120 Project Name Plan, Design and Implement Railroad Quiet Zone Future Department Public Works: Streets/Traffic Contact Facilities Director Type Improvement Useful Life 30 years Category Trans: Streets Priority n/a Description I Total Project Cost: $255,000 Modify existing railroad grade crossings to satisfy Federal Railroad Administration (FRA) requirements to create a Whistle -Free Quiet Zone for the CP Railroad corridor. Phase I: Plan and coordinate requirements with FRA and SWLRT project office. Design necessary supplemental safety measures (SSM). Phase I1: Construct SSM's and implement Quiet Zone. Justification Train horns sound in early morning hours and are disruptive to nearby residential areas. Prior Expenditures 2013 2014 2015 2016 2017 Total 30,000 1 Construction/Maintenance 225,000 225,000 Total Total 225,000 225,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 30,000 PI - PIR/General Obligation Bo 225,000 225,000 Total Total 225,000 225,000 Tuesday, August 07, 20/2 89 CAPITAL IMPROVEMENT PLAN 2013 gni i, 2017 City of Hopkins, MN Project # 11-CIP-S121 Project Name Mainstreet Traffic Signal Upgrades Future Department Public Works: Streets Traffic Contact Facilities Director 'UN Improvement I setiil Life 30 years ('atego r) Trans: Streets Priorit,N 3Important Description I Total Project Cost: $500,000 These projects upgrade the Mai nstrcct traffic signals vv it It LED lighting, countdown timers, controllers, and audible signals for the visually impaired. The equipment currently in place was installed years ago and is in need of replacement. 2017: 11th Ave and Mainstreet 2013: 5th and 8th Ave and Mainstrcct 2014: 9th and 10th Ave and Mainstreet 2015: 17th Avenue and Mainstrcct and 5th Ave and Minnetonka Mills 2016: 12th and 7th Ave and Mainstreet 2017: 14th and Mainstreet, 11 th A� c S and 5th Ave S Justification Prior Expenditures 2013 2014 2015 2016 2017 Total F-2-50,0001 Construction/Maintenance 50.000 50,000 50,000 50,000 50,000 250,000 Total Total 50,000 50,000 50,000 50,000 50,000 250,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 250,000 PI - PIR/General Obligation Bo 50,000 50,000 50,000 50,000 50,000 250,000 Total Total 50,000 50,000 50,000 50,000 50,000 250,000 Budget Impact/Other 90 hwa dat,..lugiol07.20/2 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 11-CIP-S122 Project Name Blake Road Streetscape Future Department Public Works: Streets/Traffic Contact Facilities Director Type Improvement Useful Life 50 years Category Trans: Streets Priority n/a Description Total Project Cost: $200,000 This project continues the upgrade of Blake Road with lighting and Streetscape enhancements. Much of the funding for this work comes from Hennepin County Grants. Justification Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 Funding Sources 2013 2014 2015 2016 2017 Total GU - Other Governmental Unit 100,000 100,000 PI - PIR/General Obligation Bo 100,000 100,000 Total 200,000 200,000 Budget Impact/Other 91 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN Protect # 12-CIP-039 Project Name 2014 Street Overlay Project 2013 alt t 2017 Department Public Works: Surrtt'Traf-fie Contact PW Director "vpe Improvement I seful Lite Category Trans: Streets Future Priorih n -a Description l"otal Project Cost: $200,000 2014 - 3,000 LF of Mill and Overlay in the Oakridge South neighborhood Justification Maintain streets that are in need of work but do not need to be reconstructed. Expenditures 2013 2014 2015 2016 2017 Total Construction 200,000 200,000 Total Funding Sources 2013 200,000 2014 2015 200,000 2016 2017 Total PI - PIR/General Obligation Bo 200,000 200,000 Total Budget Impact/Other 200,000 200,000 Jew item added in 2012 for 2014 /11"Ml01..1 w,m1 U'. 201' 92 CAPITAL IMPROVEMENT PLAN 2013 dire, 2017 City of Hopkins, MN E-i ect # 12-CIP-SO38 ect Name Replace Asphalt Walk - Excelsior Blvd. Future Department Public Works: Streets/Traffic Contact Public Works Director Type Improvement Useful Life Category Trans: Walkways/Sidewalks Priority n/a Description Total Project Cost: $60,000 Zecontruct the existing asphalt walk agbong the north side os Excelsior Blvd East of Blake Rd to Powell Rd. Justification Che existing walk is deteriorated beyond overlay and sections of the walk have excessive cross slope. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 60,000 60,000 Total 60,000 60,000 Funding Sources 2013 2014 2015 2016 2017 Total GU - Other Governmental Unit 15,000 15,000 PI - PIR/General Obligation Bo 45,000 45,000 Total 60,000 60,000 Budget Impact/Other 93 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 thi i 2017 City of Hopkins, MN Project # 01-CIP-S502 Project Name Light Rail Transit Stations (2) Future Department Public Works: Transportation Contact Public Works Director 7}pe Improvement t ,eful Life Unassigned Category Trans: Streets Priorih n a Total Project Cost: $1511,000 1) Intersection of Third Street South and Fifth Av enue South 2) Second Street Northeast Supplemental improvements to two Light Rail Transit (LRT) stations in the proposed HCRRA locations. Justification The HCRRA proposes to construct two stations along, the Southwest Corridor. The proposed expenditures would be in addition to the funds expended by the HCRRA. The additional funds would be used to ensure the stations arc high quality in appearance. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 150,000 150,000 Total 150,000 150,000 Funding Sources 2013 2014 2015 2016 2017 Total TF - Tax Increment Financing 150,000 150,000 Total Budget Impact/Other Dependent on HCRRA plans. Consistent with plans for LRT stops in Hopkins by Hennepin County. 94 150,000 150,000 lug sd�n. _ht,ucr n", 'lll' CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 01-CIP-S503 Project Name Eighth Avenue LRT Corridor Future Description ?ighth Avenue from County Road 3 to Mainstreet )esign and installtion of pedestrian improvements and streetscape improvements Justification Department Public Works: Transportation Contact Public Works Director Type Improvement Useful Life Unassigned Category Trans: Streets Priority n/a Total Project Cost: $200,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 Funding Sources 2013 2014 2015 2016 2017 Total GU - Other Governmental Unit 100,000 100,000 TF - Tax Increment Financing 100,000 100,000 Total 200,000 200,000 Budget Impact/Other )ependent on Metropolitan Council SWLRT plans 95 Tuesday, August 07, 20/2 Utilities CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 01-CIP-UO02 Project Name Storm Drainage System Maintenance - Alley Repairs Future Description 2009-2013: Concrete alley repairs Justification Annual alley pavement concrete slab repairs are needed. Department Public Works: Utilities Contact Public Works Director Type Improvement Useful Life Unassigned Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $168,000 Prior Expenditures 2013 2014 2015 2016 2017 Total 677000 Construction/Maintenance 19,000 20,000 20,000 21,000 21,000 101,000 Total Total 19,000 20,000 20,000 21,000 21,000 101,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 67,000 SU - Storm Sewer Fund 19,000 20,000 20,000 21,000 21,000 101,000 Total Total 19,000 20,000 20,000 21,000 21,000 101,000 Budget Impact/Other with the Storm Water Management Plan. 97 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 il, tl 2017 City of Hopkins, MN Project # 01-CIP-UO03 Project Name Storm Water Management Projects Future Department Public Works: Utilities Contact Public Works Director I N pe Improvement l with Life Unassigned t :11e,1.101'\ Utilities: StOl-In SCIA'el' Priority n it Total Project Cost: $200,000 14: Provide outlet pipe to Shady Oak Pond into CSAH 61 storm drainage piping in conjunction \s ith Shady Oak Road reconstruction Justification Shady Oak Pond has no outlet and floods streets and residential property if not pumped. Consistent with City Council approved action plan of October 21, 1997. the City's Storm Management Plan. and Shady Oak Road reconstruction Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 200,000 200,000 Total 200,000 200,000 Funding Sources 2013 2014 2015 2016 2017 Total SU - Storm Sewer Fund 200,000 200,000 Total 200,000 200,000 Budget Impact/Other Consistent with City Council approved Action Plan of Octobcr 21. 1997, the City's Storm Management Plan. and Shady Oak Road reconstruction timetable. 111"SS al..Im"n't 0-. '01 , 98 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08-CIP-U000 Project Name Meter Replacement Future Description Meter Replacement Justification Items identified in 2007 comprehensive utility plan to provide safe and reliable water. Department Public Works: Utilities Contact Public Works Director Type Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $475,000 Prior Expenditures 2013 2014 2015 2016 2017 Total 380,000 Construction/Maintenance 95,000 95,000 Total Total 95,000 95,000 Prior Funding Sources 2013 2014 2015 2016 2017 Total 380,000 WF - Water Fund 95,000 95,000 Total Total 95,000 95,000 Tuesday, August 07, 20/2 99 CAPITAL IMPROVEMENT PLAN 2013 inti, 2017 City of Hopkins, MN Project # 08-CIP-U001 Project Name Lift Station # 4 Future Description tehabilitate LS No. 4 Justification Lift station No. 4 was identified for rehab in the 2007 comprehciisk c utiIity plan Regular major maintenance identified in the 2007 comprehensi\c utiliq plan. Deparonent Public Works: Utilities Contact Public Works Director T% pe Itnprovetnent I srful Life Catcgor� Utilities: Municipal Sanitary S Priorit. n a Intal Pro icct Cost: $160,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 160,000 160,000 Total 160,000 160,000 Funding Sources 2013 2014 2015 2016 2017 Total SF - Sanitary Sewer Fund 160,000 160,000 Total 160,000 160,000 Budget Impact/Other m lii, dat U-. _M CAPITAL IMPROVEMENT PLAN 2013 /hru 2017 City of Hopkins, MN Project # 08-CIP-UO08 Project Name Emergency Chlorine Shut Off Valves Future Description Emergency Chlorine Shut Off Valves Justification Items identified in 2007 Expenditures utility plan to provide safe and reliable water. Department Public Works: Utilities Contact Facilities Director Type Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $33,000 2013 2014 2015 2016 2017 Total Construction/Maintenance 33,000 33,000 Total 33,000 33,000 Funding Sources 2013 2014 2015 2016 2017 Total WF - Water Fund 33,000 33,000 Budget Impact/Other Total 33,000 33,000 101 Tuesday, August 07, 2012 CAPITAL IMPROVEMENT PLAN 2013 do o 2017 City of Hopkins, MN F ect # 08-CIP-UO09 ect Name Sanitary Sewer Lift Station Maintenance Future Description tegular LS Major Maintenance Justification Zegular major maintenance identiticd in the 2007 comprehcnsk e utility plan. Expenditures 2013 2014 Department Public Works: Utilities Contact Facilities Director lope Improvement I wful Lire (atcgorc Utilities: Municipal Sanitary S Priorit. tva Total Project Cost. $15,000 2015 2016 2017 Total Construction/Maintenance 15,000 15,000 Total 15,000 15,000 Funding Sources 2013 2014 2015 2016 2017 Total SF - Sanitary Sewer Fund 15,000 15,000 Budget Impact/Other Total 15,000 15,000 111M lit, �dat. lit,,vml 0-, 012 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 City of Hopkins, MN Project # 08-CIP-UO10 Project Name St. Louis Park Emergency Connection Future Description it. Louis Park emergency connection. Justification tems identified in 2007 comprehensive utility plan to provide safe and reliable water. Department Public Works: Utilities Contact Facilities Director Type Improvement Useful Life Category Utilities: Municipal Sanitary S Priority n/a Total Project Cost: $211,000 Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 211,000 211,000 Total 211,000 211,000 Funding Sources 2013 2014 2015 2016 2017 Total WF - Water Fund 211,000 211,000 Total Budget Impact/Other 103 211,000 211,000 Tuesday, August 07, 20/2 CAPITAL IMPROVEMENT PLAN 2013 th a 2017 City of Hopkins, MN Project # 11-CIP-S123 Project Name Storm Water Improvements - Cottage-ville Park Future Department Public Works: Utilities ( ontact Tape Improvement t sclul life Cate„orc Utilities: Storm Sewer Priorit. n a ription notal Project Cost: $250,000 improvements provide water quality improvements fore Minnchaha ('reek as outlined in the cooperative agreement with the Minnchaha Watershed District for the renovation of the Blake Roa(I Lake Street Cottaa,,e\ i I I Park area. Justification Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 250.000 250,000 Total 250,000 250,000 Funding Sources 2013 2014 2015 2016 2017 Total SU - Storm Sewer Fund 250.000 250,000 Total 250,000 250,000 Budget Impact/Other 104 7L��sdur. -lulu<t U'. _'0/2 CAPITAL IMPROVEMENT PLAN 2013 thru 2017 Department Public Works: Utilities City of Hopkins, MN Contact Facilities Director Project # 11-CIP-U011 Type Improvement Useful Life 50 years Project Name Emergency Water Connection with Edina g y Category Utilities: Municipal Water Syst Future Priority 2 Very Important Description Total Project Cost: $20,000 This project connects the Hopkins and Edina water systems to provide mutual aid in the case of an emergency. The project include the construction of an 8" waterline and valve across 2nd Street South in the South Presidential Neighborhood. Expenditures 2013 2014 2015 2016 2017 Total Construction/Maintenance 20,000 20,000 Total Funding Sources 20,000 2013 2014 20,000 2015 2016 2017 Total WF - Water Fund 20,000 20,000 Total 20,000 20,000 Budget Impact/Other 104 Tuesday, August 07, 2012